Download - Investor Presentation - September 2014
Aug-Sept 2012
Path to
Production
September 2014TSX-V : SGXPath to Production
Path to Production
Forward Looking Statements
1
Statements made in this presentation, other than those concerning historical information, should be
considered forward-looking statements which are subject to various risks and uncertainties. Such
forward-looking statements are made based on management’s belief as well as assumptions made by,
and information currently available to, management.
The Company’s actual results may differ materially from the results anticipated in such forward-looking
statements as a result of a variety of factors. Additional information concerning factors that could cause
actual results to materially differ from those in such forward-looking statements is contained in the
Company’s filings with the securities and regulatory authorities.
Note: All currencies are in Canadian dollars unless otherwise noted
Path to Production
2
Sage Gold plans are to develop production from their existing resources on the
Clavos and Lynx projects to generate cash flow.
CORPORATE STRUCTURE
CORPORATE VISION
Exchange Symbol: TSX.V – SGX
OTC – SGGDF (USA)
• Shares O/S: 9.0 million
• Shares F/D: 10.3 million
• Current price: $0.14
• 52 week high/low: $0.60/$0.14
• Market Cap: C$ 1.26 million
• Average Strike Price of Warrants/Options: $1.38
• Proceeds from Warrants/Options: $1.9 million
Path to Production
3
SAGE GOLD ADVANTAGE
Near term production
1. Clavos Au and Lynx Cu- Ag - Au project Potential to generate strong cash flow for the company
Sage has access to custom mills for both the Clavos and Lynx projects
Permits in place to re-open Clavos for dewatering and underground rehabilitation
2. Both Clavos and Lynx have 43-101 resources
3. Preliminary Economic Assessment on Clavos Project 71% Internal Rate of Return (pre-tax) and $23.2MM Net Present Value
4. Blue Sky Potential – Clavos and Lynx Projects Open at depth and on multiple directions along strike
Management will focus on continuing to increase resources
5. Excellent Infrastructure - Clavos Established infrastructure with $46 million spent on underground development
Note: The PEA does not indicate the economic viability of the mineral resource and is preliminary in nature, includes inferred resources that are considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorized as mineral reserves and that there is no certainty that the PEA will be realized. Mineral resources that are not mined reserves do not have demonstrated economic viability. A PEA is deemed to be reliable +/- 50% level.
Path to Production
4
TIMMINS GOLD CAMPS CLAVOS
PROJECT
Timmins, Ontario
Primero
Mill
Path to Production
5
CLAVOS PROJECT- HIGHLIGHTS
Located in the prolific Timmins Mining camp -produced in excess of 100 million ozs gold
Existing infrastructure - underground ramp and levels every 25 metres to the 300m level
Low initial Capex required for potential production … $14.1million
Option agreement to purchase St Andrew’s 40% interest in Clavos
Permits in place to re-open Clavos mine
Clavos is located in close proximity to several operating mills
Natural Gas pipeline - Clavos Property – Potential Fuel and Power savings – Study
Path to Production
6
CLAVOS
PROJECT
Timmins, Ontario
15
9
6
0
0 5 10 15 20
Commercial Production
Initial Tonnage Extractionand Production
Dewater and Rehab mine
Complete Financing
Months
NEAR TERM PRODUCTION PLANS
Path to Production
7
GOLD PRICE US$ / Oz (Au) $1400/Oz $1500/Oz $1600/Oz
Base Case
Gold Production Oz/Au 145,448 145,448 145,448
Revenue Cdn$ million 203.6 218.2 232.7
Initial Capital Expenditures (100%) Cdn$ million 14.1 14.1 14.1
Sustaining Capital Cdn$ million 21.1 21.1 21.1
Total Capital Cdn$ million 35.1 35.1 35 .1
Operating Expense Cdn$ t/Ore 142.5 142.5 142.5
Net Smelter Return Cdn$ t/Ore 6.1 6.5 7.0
Cash flow (undiscounted) Cdn$ million 19.9 34.0 48.1
Pre Tax
Net Present Value (NPV) 8% Cdn$ million 13.5 23.2 33.0
Internal Rate Of Return (IRR) % 48% 71% 94%
After Tax
Net Present Value (NPV) 8% Cdn$ million 5.6 12.6 19.5
Internal Rate Of Return (IRR) % 27% 47% 67%
Life of Mine Year 7 7 7
Payback Period Year 2.25 2.00 1.75 Note - assumes an exchange rate of 1:1 of Cdn to US Dollar;
-tax rates are based on a blended rate between Sage and SAS
-excludes any financing costs
-contingency on capital expenditures of 30%
-CAPEX figures represents 100% of financing
The PEA does not indicate the economic viability of the mineral resource and is preliminary in
nature, includes inferred resources that are considered too speculative geologically to have
the economic considerations applied to them that would enable them to be categorized as
mineral reserves and that there is no certainty that the PEA will be realized. Mineral resources
that are not mined reserves do not have demonstrated economic viability.
Clavos
PEA
Economic
Model
Path to Production
8
CLAVOS EXISTING UNDERGROUND
2,923m of primary access
710m of secondary access
3,208m of lateral level development
+200,000 m of surface & underground diamond drilling
10 levels with detail geological mapping & channel
sampling
Replacement value $40.0m
FootwallHanging WallSedimentContact
Hanging WallFootwallContactSediment
2.5 km
Ramp
Path to Production
9
Total Indicated 1,258,400 4.81 g/t 194,600
__________________________________________________________________________
Total Inferred 795,600 4.70 g/t 120,000
__________________________________________________________________________
Note: The 2012 resources are estimated at a cut-off grade of 2.75 g/t Au, high gold assays are cut to 60 g/t Au and an average long-term gold
price of US$1600 per ounce was used.
CLAVOS NI43-101 MINERAL RESOURCE Oct ‘12
Tonnes Grade Total OuncesCategory
Path to Production
10
CLAVOS PEA REPORT 2013
Forecasted production rate 600 tpd Life of Mine 7 years Forecasted Full production 3rd year, 4th Qtr. Internal dilution in resource block estimate External dilution:
- cut & fill methods 10% at 0 gms/t- long hole methods 40% at 0 gms/t
Tonnage recovery:- cut & fill methods 95%- long hole methods 90%
Note: The PEA does not indicate the economic viability of the mineral resource and is preliminary in nature, includes inferred resources that are considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorized as mineral reserves and that there is no certainty that the PEA will be realized. Mineral resources that are not mined reserves do not have demonstrated economic viability.
Path to Production
11
ONAMAN PROPERTY - LYNX PROJECT - ONTARIO
Lynx Cu Ag Au 9,096 acres
NE Mine Mill*
Leitch*
Nortoba*
* PREMIER GOLD OPTION
Path to Production
12
ONAMAN
Yellow = .5% Cu x 3 metres – Cut Off Red = 1% Cu x 3 metres
Lynx NI43-101 Resource
1.936 million tonnes, 1.44% Cu
39.6 g Ag/T, 0.58 g Au/T
Lynx NI43-101 Open Pit Resource 485,000
tonnes 2.1 % Cu, 45.3 g Ag/T, 0.70 g Au/T
at 1% Cu cut off
LYNX PROJECT
Beardmore, Ontario
Path to Production
13
LYNX PROJECT – Cu Ag Au
Located within the Onaman Property – Northern Ontario
VMS system – high grade Cu-Ag-Au 43-101 Resource
Numerous VMS targets on the Onaman Property – potential to host large VMS deposit
Open at depth and along strike – Existing compliant resource - only drilled to 250-300 metres
Open Pit component – potential to increase size to the north
Sage – Agreement with Premier Gold to purchase Northern Empire mine and mill – 75km from Lynx
Path to Production
14
Patrick J. MarsChairman and Director
Mr. Mars is an independent consultant specializing in mine financing and analysis with over 30 years of
experience in the investment industry. Mr. Mars has acted as Chairman, CEO, or Director for several public-
traded mining companies and is currently Director of Aura Minerals, Carpathian Gold, Selwyn Resources and
Yamana Gold.
Peter BojtosDirector
Mr. Bojtos is a professional engineer with extensive experience in mineral development and production. Since 1996
following a successful career as CEO of several companies, Mr. Bojtos serves on mining company boards as an
independent Director.
Gary RobertsonDirector
Mr. Robertson is a Certified Financial Planner. He has worked in the financial industry for the past twenty years, and
presently serves on the board of several private companies as well as on the board of six Canadian junior gold mining
companies.
Mr. Freeman has extensive experience in public markets, finance and compliance, this includes six years as Director of
Markets and Compliance at the OFEX Market (now ISDX). Mr. Freeman is Compliance Officer of Loeb Aron & Company
a London corporate finance firm, a Lay member of the Upper Tribunal (Tax & Chancery) and of the Probate Committee
of the ICAEW. Mr. Freeman is also a director of TSX-V quoted Cabo Drilling Inc., of AIM quoted Capital Lease Aviation
PLC and of Jenolan Ltd.
Sandy ChimDirector
Mr. Chim is an international business executive. He is the President and CEO of Century Iron Mines Corporation (TSX-
FER), a director of Augyva Mining Resources Inc. (TSX.V-AUV) and non executive director of Prosperity Minerals Holdings
Limited. Mr.Chim resides in Kowloon, SAR, Hong Kong, PRC.
C. Nigel LeesPresident, CEO and Director
.
Mr. Lees is a founder and past director of TVX Gold Inc., a significant gold producer in North and South America,
which merged into Kinross Gold, listed on the TSX and the New York Stock Exchange. Mr. Lees has over 30 years
experience in the Canadian investment industry and is currently a Director of several publicly traded mining companies
including Yamana Gold.
BOARD OF DIRECTORS
Peter FreemanDirector
Path to Production
15
MANAGEMENT and CONSULTANTSManagement
William D. LoveVP and Business Development
Robert RyanChief Financial Officer
Michael SkutezkyLegal Counsel
Consultants
Bob RitchieMining Engineer
Mr. Peter Hubacheck is a consulting geologist and President of W. A. Hubacheck Consultants Ltd. He has over
35 years of experience as a project geologist, exploration manager and Qualified Person for the purposes of NI
43-101, with experience in the exploration for gold, silver, base metals, uranium and diamonds in Canada and the
USA. He holds a Mining Technologist (1974) diploma from the Haileybury School of Mines and Technology,
Haileybury, Ontario and a B.A.Sc. (Geol. Eng. 1977) degree from the South Dakota School of Mines and
Technology, Rapid City, South Dakota.
Mr. Ritchie is a Professional Engineer with over 40 years of experience in mine management and development,
feasibility studies and mine construction. He has worked with several mining companies including Goldcorp,
Noranda Mines and St. Andrew Goldfields. He was responsible for the construction of the Stock (now Brigus
Gold) Mill. Mr. Ritchie is a graduate of the Michigan Technological University with a Bachelor of Science in
Geology Engineering. He is also a Qualified Person (QP) as defined by NI43-101.
Peter HubacheckP.Geo, QP
C. Nigel LeesPresident, CEO and Director
Mr. Lees is a founder and past director of TVX Gold Inc., a significant gold producer in North and South America,
which merged into Kinross Gold, listed on the TSX and the New York Stock Exchange. Mr. Lees has over 30 years
experience in the Canadian investment industry and is currently a Director of several publicly traded mining companies
including Yamana Gold.
Mr. Love is a geologist who has been involved in mineral exploration in Canada and was part of the world class Hemlo
discovery team. He was also an institutional equity salesperson in London, England, for a Canadian brokerage firm.
Mr. Love has spent the last fifteen years as a venture capitalist and a corporate finance specialist in a variety of
resource and technology companies.
Mr. Ryan brings over 25 years of experience in CFO and COO roles in private and public companies with an extensive
background in financing and M&A transactions. Mr. Ryan is a CPA, CA and holds an MBA from the University of
Toronto.
Mr. Skutezky was Assistant General Counsel of Royal Bank for 25 years focused on International Project financing
based in Montreal and Toronto, in addition to working in Eastern Europe with Canadian Law Firms. He has recently
formed his own professional corporation for the practice of law and is the principal of Rhodes Capital Corporation.
Path to Production
16
WHY INVEST IN SAGE GOLD
Clavos – one of the few permitted gold deposits in Ontario
Near Term Potential Production
Clavos Positive Preliminary Economic Assessment – Low Capex/ Fast Payback
Lynx – Compliant Resource / Large Deposit Potential/ Open Pit tonnage
Clavos/ Lynx - potential to Increase Tonnage through further in-fill and exploration
drilling
Production Financing – Joint Ventures being pursued
Low Market Capitalization
SMALL AND PROFITABLE IS BEAUTIFUL
Path to Production
17
CONTACT INFORMATION
Sage Gold Inc. 365 Bay Street, Suite 500
Toronto, ON M5H 2V1
Tel.: 416 204-3170
Fax: 416 260-2243
Karen Levy