Summary
Contents
Key Activities
Scope Development
Schedule
Progress Photos
1
2
3
4
5
EXTERIOR DESIGN BUILD TEAM I JE DUNN I TREANOR ARCHITECTS I ADG
JULY 2016
OKLAHOMA STATE CAPITOL RESTORATION
Exterior Rehabilitation
EXTERIOR DESIGN
BUILD TEAM I
JE DUNN I TRE
ANORHL ARCHITE
CTS I ADG
OKLAHOMA STATE CAPITOL RESTORATION
Exterior Rehabilitation
ContentsSummary
Safety
Progress Photos
Attachments
1
2
3 Roofi ng Update
15
03
9D
B
MO
NT
HLY
CO
NS
TR
UC
TIO
N P
RO
GR
ES
S R
EP
OR
T
4
5
January 2020 January 2020
-
15
03
9D
B
MO
NT
HLY
CO
NS
TR
UC
TIO
N P
RO
GR
ES
S R
EP
OR
T
4 E SHERIDAN AVE SUITE 200 I OKLAHOMA CITY, OK 73104
CLICK HERE
Exterior RehabilitationJE DUNN I TREANORHL ARCHITECTS I ADG
January 2020
Summary:
During the month of January on the Oklahoma State Capitol Exterior Restoration
Project, the interior tunnel work continued. The drywall for the tunnel and the fram-
ing and sheetrock for the vestibule area were completed in January. The fi nal tunnel
fi nishes began in mid-January with the fl oor prep for tile installation and painting.
Flooring, millwork, and lay-in ceilings will all start in February. The tunnel is still
tracking a March completion; however, the tunnel will remain closed until the new
Visitor’s Center is complete this summer.
The roofi ng replacement has progressed on all remaining wings. The copper sky-
lights and ridge cap on the South Wing were completed in January. The copper
standing seam panels on the East Wing low roof and East Monitor roof are complete.
Gutters, snow-guards, and the ridge cap will fi nish out the East Wing in early Febru-
ary. The West Wing’s substrate demo, repairs, and new substrate were all completed
on the low roof and West Wing monitor this month. The West Wing copper fl at-lock
panels installation started in January. The low roof copper standing seam panels will
start in early February. The new copper roofi ng completion is still tracking for March
completion, weather permitting.
RETURN TO TABLE OF CONTENTS
-
15
03
9D
B
MO
NT
HLY
CO
NS
TR
UC
TIO
N P
RO
GR
ES
S R
EP
OR
TCLICK HERE
KeyActivities:
- South wing standing seam panel installation is complete
- South wing skylight copper installation is icomplete
- West wing low roof repairs are complete
- West wing monitor work is icomplete
- Interior tunnel drywall is complete
- Interior tunnel fl oor prep is in progress
- Interior tunnel tile installation is in progress
- Interior tunnel paint is in progress
- Interior tunnel VCT abatement is complete
JE DUNN I TREANORHL ARCHITECTS I ADG
Exterior RehabilitationAugust 2019January 2020
RETURN TO TABLE OF CONTENTS
4 E SHERIDAN AVE SUITE 200 I OKLAHOMA CITY, OK 73104
complete
complete
-
15
03
9D
B
MO
NT
HLY
CO
NS
TR
UC
TIO
N P
RO
GR
ES
S R
EP
OR
TCLICK HERE
Safety:The safety of our workforce and the general public during the course of
construction is the most important task that we must deliver. To that end, every
craftsmen involved with the project receives a detailed project orientation, and prior
to performing any task, the teams develop detailed task specifi c work plans. These
work plans are often called Job Site Analysis (JSA) and assist project teams with ana-
lyzing diff erent hazards associated with each work activity prior to
beginning work.
JE DUNN I TREANORHL ARCHITECTS I ADG
Safety Data and Metrics
Orientations Performed through
01.31.20903
First Aid Incidents for the month of
January0
Recordable Incidents for the month
of January0
Trade Partner Incidents for the
month of January0
Total Man-Hours for the month of
January (hrs)3,088
Total Project Man-Hours (hrs.) 228,492
Exterior RehabilitationJanuary 2020
RETURN TO TABLE OF CONTENTS
4 E SHERIDAN AVE SUITE 200 I OKLAHOMA CITY, OK 73104
-
15
03
9D
B
MO
NT
HLY
CO
NS
TR
UC
TIO
N P
RO
GR
ES
S R
EP
OR
TCLICK HERE
JE DUNN I TREANORHL ARCHITECTS I ADG
Safety Spotlight
In January on the Oklahoma Capitol Exterior Restoration project, the safety
focus has been on working in and around occupied spaces. With the new leg-
islative session starting in February, the building and surrounding areas will be
full of people. The safety of those around us is paramount. Extra precautions
are taken by the use of signage, debris netting, keeping construction entranc-
es closed and gates locked.
Exterior RehabilitationJanuary 2020
RETURN TO TABLE OF CONTENTS
4 E SHERIDAN AVE SUITE 200 I OKLAHOMA CITY, OK 73104
d.
-
15
03
9D
B
MO
NT
HLY
CO
NS
TR
UC
TIO
N P
RO
GR
ES
S R
EP
OR
TCLICK HERE
Roofi ng Update
JE DUNN I TREANORHL ARCHITECTS I ADG
Exterior RehabilitationJanuary 2020
RETURN TO TABLE OF CONTENTS
4 E SHERIDAN AVE SUITE 200 I OKLAHOMA CITY, OK 73104
Topping Out Ceremony
Copper Progress
-
15
03
9D
B
MO
NT
HLY
CO
NS
TR
UC
TIO
N P
RO
GR
ES
S R
EP
OR
TCLICK HERE
JE DUNN I TREANORHL ARCHITECTS I ADG
Progress Photos & Field Reports
The photos and fi eld reports attached in the subsequent pages represent progress photos
taken during the month of January for the Oklahoma State Capitol Exterior Restoration
project.
Exterior RehabilitationJanuary 2020
RETURN TO TABLE OF CONTENTS
4 E SHERIDAN AVE SUITE 200 I OKLAHOMA CITY, OK 73104
-
P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field
Reports\ADG\OSCR FR 158 - 2019_12-17.docx
Page 1 of 5
FIELD OBSERVATION REPORT REPORT NO: 158 DATE: 12/17/2019
TIME: 2:30 – 3:15 PM DAY OF WEEK: Tuesday
OWNER: OMES TEMP. RANGE: Mid 40s
PROJECT: Oklahoma Capitol Restoration - Exterior Rehabilitation
CAP PROJECT NO: 15039DB
JE DUNN PROJECT NO: 15025800
ADG PROJECT NO: 15-007
TREANORHL PROJECT NO: HP 15.007.00B
ZFI PROJECT NO: 15071-01
ALVINE PROJECT NO: 2014-4286
SRB PROJECT NO: 114801
WEATHER: Clear Overcast Rain Snow Cold
Warm Hot Foggy Windy Ice Other _________
SITE CONDITIONS: Clear Dusty Muddy Other ______________________
PERSONS CONTACTED: Lindsey Ross, Mark Maska - JE Dunn
WORK OBSERVED:
Roof work progressing on south slope of east wing (Foxtrot).
Roof work progressing on east slope of south wing (Golf).
Roof work progressing on west slope of south wing (India).
ITEMS DISCUSSED:
Electrical rough-in passed inspection per Mark.
ACTION REQUIRED:
None
ITEMS TO VERIFY:
None
REMARKS:
Tunnel was locked up and workers had left at time of site visit.
OBSERVED BY: Peter Breninger (ADG)
-
P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field
Reports\ADG\OSCR FR 158 - 2019_12-17.docx
Page 2 of 5
COPIES TO: Bobby Snyder (JE Dunn), Brandon Marriott (JE Dunn), Lindsey Ross (JE Dunn), Mark
Maska (JE Dunn), Rick Fleming (JE Dunn), JC Witcher (ADG), Robert Meek (ADG), Amelia
Hudspeth (TreanorHL), Julia Manglitz (TreanorHL), Vance Kelley (TreanorHL), Mike
Thompson (ZFI), Andy Wiese (Alvine), Ed Kongs (Alvine), Sam Haberman (Alvine), Steve
Alvine (Alvine), Gary Noland (Smith Roberts Baldischwiler)
Roof progress on south slope of east wing (Foxtrot)
-
P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field
Reports\ADG\OSCR FR 158 - 2019_12-17.docx
Page 3 of 5
Copper panel forming in progress on south slope of east wing (Foxtrot)
Copper panel installation in progress on south slope of east wing (Foxtrot)
-
P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field
Reports\ADG\OSCR FR 158 - 2019_12-17.docx
Page 4 of 5
Copper panel installation in progress on south slope of east wing (Foxtrot)
Roof progress on east slope of south wing (Golf)
-
P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field
Reports\ADG\OSCR FR 158 - 2019_12-17.docx
Page 5 of 5
Roof work progress on west slope of south wing (India)
-
P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field
Reports\ADG\OSCR FR 159 - 2020_01-07.docx
Page 1 of 10
FIELD OBSERVATION REPORT REPORT NO: 159 DATE: 1/7/2020
TIME: 10:00 – 10:30 AM DAY OF WEEK: Tuesday
OWNER: OMES TEMP. RANGE: Lower 30s
PROJECT: Oklahoma Capitol Restoration - Exterior Rehabilitation
CAP PROJECT NO: 15039DB
JE DUNN PROJECT NO: 15025800
ADG PROJECT NO: 15-007
TREANORHL PROJECT NO: HP 15.007.00B
ZFI PROJECT NO: 15071-01
ALVINE PROJECT NO: 2014-4286
SRB PROJECT NO: 114801
WEATHER: Clear Overcast Rain Snow Cold
Warm Hot Foggy Windy Ice Other _________
SITE CONDITIONS: Clear Dusty Muddy Other ______________________
PERSONS CONTACTED: Brandon Marriott, Lindsey Ross, Mark Maska, Rick Fleming - JE Dunn
WORK OBSERVED:
Roof work progressing on north slope of east wing (Delta).
Roof work progressing on south slope of east wing (Foxtrot).
Roof work progressing on east slope of south wing (Golf).
Roof work progressing on west slope of south wing (India).
Roof work progressing on south slope of west wing (Juliette).
Roof work progressing on north slope of west wing (Lima).
Gypsum board installation progressing in tunnel.
Light fixture installation progressing in tunnel.
ITEMS DISCUSSED:
None
ACTION REQUIRED:
None
ITEMS TO VERIFY:
None
-
P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field
Reports\ADG\OSCR FR 159 - 2020_01-07.docx
Page 2 of 10
REMARKS:
The OAC Meeting occurred prior to the site visit in the jobsite trailers.
The Interior/Exterior Coordination Meeting occurred prior to the site visit in the jobsite trailers.
OBSERVED BY: Peter Breninger (ADG)
COPIES TO: Bobby Snyder (JE Dunn), Brandon Marriott (JE Dunn), Lindsey Ross (JE Dunn), Mark
Maska (JE Dunn), Rick Fleming (JE Dunn), Curtis Freeman (ADG), JC Witcher (ADG),
Robert Meek (ADG), Amelia Hudspeth (TreanorHL), Julia Manglitz (TreanorHL), Vance
Kelley (TreanorHL), Mike Thompson (ZFI), Ed Kongs (Alvine), Sam Haberman (Alvine),
Steve Alvine (Alvine), Gary Noland (Smith Roberts Baldischwiler)
Roof progress on north slope of east wing (Delta)
-
P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field
Reports\ADG\OSCR FR 159 - 2020_01-07.docx
Page 3 of 10
Ridge cap work in progress at monitor roof on east wing
Copper panel installation progress on south slope of east wing (Foxtrot)
-
P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field
Reports\ADG\OSCR FR 159 - 2020_01-07.docx
Page 4 of 10
Copper installation in progress at side wall of monitor on south slope of east wing (Foxtrot)
Roof progress on east slope of south wing (Golf)
-
P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field
Reports\ADG\OSCR FR 159 - 2020_01-07.docx
Page 5 of 10
Copper panel forming in progress at skylight on east slope of south wing (Golf)
Roof progress on west slope of south wing (India)
-
P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field
Reports\ADG\OSCR FR 159 - 2020_01-07.docx
Page 6 of 10
Copper panel installation in progress on west slope of south wing (India)
Copper panel flashing installation in progress at skylight on west slope of south wing (India)
-
P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field
Reports\ADG\OSCR FR 159 - 2020_01-07.docx
Page 7 of 10
Sleeper removal in progress on south slope of west wing (Juliette)
Fill repair in progress on south slope of west wing (Juliette)
-
P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field
Reports\ADG\OSCR FR 159 - 2020_01-07.docx
Page 8 of 10
Framing progress at side wall of monitor roof on south slope of west wing (Juliette)
Roof progress on north slope of west wing (Lima)
-
P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field
Reports\ADG\OSCR FR 159 - 2020_01-07.docx
Page 9 of 10
Plywood installation in progress at monitor wall on north slope of west wing (Lima)
Gypsum board installation progress at east end of tunnel
-
P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field
Reports\ADG\OSCR FR 159 - 2020_01-07.docx
Page 10 of 10
Light fixture installation in wall in tunnel
-
P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field
Reports\ADG\OSCR FR 160 - 2020_01-14.docx
Page 1 of 9
FIELD OBSERVATION REPORT REPORT NO: 160 DATE: 1/14/2020
TIME: 9:15 – 10:00 AM DAY OF WEEK: Tuesday
OWNER: OMES TEMP. RANGE: Lower 50s
PROJECT: Oklahoma Capitol Restoration - Exterior Rehabilitation
CAP PROJECT NO: 15039DB
JE DUNN PROJECT NO: 15025800
ADG PROJECT NO: 15-007
TREANORHL PROJECT NO: HP 15.007.00B
ZFI PROJECT NO: 15071-01
ALVINE PROJECT NO: 2014-4286
SRB PROJECT NO: 114801
WEATHER: Clear Overcast Rain Snow Cold
Warm Hot Foggy Windy Ice Other _________
SITE CONDITIONS: Clear Dusty Muddy Other ______________________
PERSONS CONTACTED: Lindsey Ross, Mark Maska, Rick Fleming - JE Dunn
WORK OBSERVED:
Roof work progressing on north slope of east wing (Delta).
Roof work progressing on south monitor slope of east wing (Foxtrot).
Roof work progressing on east slope of south wing (Golf).
Roof work progressing on west slope of south wing (India).
Roof work progressing on monitor south slope of west wing (Juliette).
Roof work progressing on monitor north slope of west wing (Lima).
Gypsum board installation along with control joint progressing in tunnel.
Light fixture installation progressing in tunnel.
ITEMS DISCUSSED:
None
ACTION REQUIRED:
None
ITEMS TO VERIFY:
None
-
P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field
Reports\ADG\OSCR FR 160 - 2020_01-14.docx
Page 2 of 9
REMARKS:
None
OBSERVED BY: Curtis Freeman (ADG)
COPIES TO: Bobby Snyder (JE Dunn), Brandon Marriott (JE Dunn), Lindsey Ross (JE Dunn), Mark
Maska (JE Dunn), Rick Fleming (JE Dunn), Peter Breninger (ADG), JC Witcher (ADG),
Robert Meek (ADG), Amelia Hudspeth (TreanorHL), Julia Manglitz (TreanorHL), Vance
Kelley (TreanorHL), Mike Thompson (ZFI), Ed Kongs (Alvine), Sam Haberman (Alvine),
Steve Alvine (Alvine), Gary Noland (Smith Roberts Baldischwiler)
Roof progress on north slope of east wing (Delta)
-
P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field
Reports\ADG\OSCR FR 160 - 2020_01-14.docx
Page 3 of 9
Copper panel installation progress on north slope of east wing (Delta)
Roof progress on south slope of east wing (Foxtrot)
-
P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field
Reports\ADG\OSCR FR 160 - 2020_01-14.docx
Page 4 of 9
Copper installation in progress at side wall of monitor on south slope of east wing (Foxtrot)
Roof progress on east slope of south wing (Golf)
-
P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field
Reports\ADG\OSCR FR 160 - 2020_01-14.docx
Page 5 of 9
Roof progress on west slope of south wing (India)
Copper flashing installation in progress on west slope of south wing (India)
-
P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field
Reports\ADG\OSCR FR 160 - 2020_01-14.docx
Page 6 of 9
Roof progress on south slope of west wing (Juliette)
Steel angle installation in progress at monitor roof on south slope of west wing (Juliette)
-
P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field
Reports\ADG\OSCR FR 160 - 2020_01-14.docx
Page 7 of 9
Roof progress on north slope of west wing (Lima)
Demolition in progress at monitor roof on north slope of west wing (Lima)
-
P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field
Reports\ADG\OSCR FR 160 - 2020_01-14.docx
Page 8 of 9
Gypsum board installation progress at east end of tunnel
Light fixture and control joint installation in wall in tunnel
-
P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field
Reports\ADG\OSCR FR 160 - 2020_01-14.docx
Page 9 of 9
Gypsum board installation progress at west end of tunnel
-
P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field
Reports\ADG\OSCR FR 161 - 2020_01-21.docx
Page 1 of 10
FIELD OBSERVATION REPORT REPORT NO: 161 DATE: 1/21/2020
TIME: 9:30 – 10:15 AM DAY OF WEEK: Tuesday
OWNER: OMES TEMP. RANGE: Lower 30s
PROJECT: Oklahoma Capitol Restoration - Exterior Rehabilitation
CAP PROJECT NO: 15039DB
JE DUNN PROJECT NO: 15025800
ADG PROJECT NO: 15-007
TREANORHL PROJECT NO: HP 15.007.00B
ZFI PROJECT NO: 15071-01
ALVINE PROJECT NO: 2014-4286
SRB PROJECT NO: 114801
WEATHER: Clear Overcast Rain Snow Cold
Warm Hot Foggy Windy Ice Other _________
SITE CONDITIONS: Clear Dusty Muddy Other ______________________
PERSONS CONTACTED: Brandon Marriott, Lindsey Ross, Mark Maska, Rick Fleming - JE Dunn
WORK OBSERVED:
Roof work progressing on north slope of east wing (Delta).
Roof work progressing on south slope of east wing (Foxtrot).
Roof work progressing on east slope of south wing (Golf).
Roof work progressing on west slope of south wing (India).
Roof work progressing on south slope of west wing (Juliette).
Roof work progressing on north slope of west wing (Lima).
Gypsum board installation progressing in tunnel.
ITEMS DISCUSSED:
Levelling of tunnel floor was discussed with flooring trade partner. ADG to provide follow up
response regarding meeting and the information discussed.
ACTION REQUIRED:
None
ITEMS TO VERIFY:
None
-
P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field
Reports\ADG\OSCR FR 161 - 2020_01-21.docx
Page 2 of 10
REMARKS:
OAC Meeting occurred prior to the site visit in the jobsite trailers.
OBSERVED BY: Peter Breninger (ADG)
COPIES TO: Bobby Snyder (JE Dunn), Brandon Marriott (JE Dunn), Lindsey Ross (JE Dunn), Mark
Maska (JE Dunn), Rick Fleming (JE Dunn), Curtis Freeman (ADG), JC Witcher (ADG),
Robert Meek (ADG), Amelia Hudspeth (TreanorHL), Julia Manglitz (TreanorHL), Vance
Kelley (TreanorHL), Mike Thompson (ZFI), Ed Kongs (Alvine), Sam Haberman (Alvine),
Steve Alvine (Alvine), Gary Noland (Smith Roberts Baldischwiler)
Roof progress on north slope of east wing (Delta)
-
P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field
Reports\ADG\OSCR FR 161 - 2020_01-21.docx
Page 3 of 10
Copper panel installation in progress at side wall of monitor on north slope of east wing (Delta)
Copper panel layout in progress on north slope of east wing (Delta)
-
P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field
Reports\ADG\OSCR FR 161 - 2020_01-21.docx
Page 4 of 10
Roof progress on south slope of east wing (Foxtrot)
Roof progress on east slope of south wing (Golf)
-
P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field
Reports\ADG\OSCR FR 161 - 2020_01-21.docx
Page 5 of 10
Roof progress on west slope of south wing (India)
Roof progress on south slope of west wing (Juliette)
-
P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field
Reports\ADG\OSCR FR 161 - 2020_01-21.docx
Page 6 of 10
Deck repairs in progress on south slope of west wing (Juliette)
Flashing installation in progress at flat lock copper on south slope of west wing (Juliette)
-
P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field
Reports\ADG\OSCR FR 161 - 2020_01-21.docx
Page 7 of 10
Roof progress on north slope of west wing (Lima)
Underlayment installation progress at flat lock copper on north slope of west wing (Lima)
-
P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field
Reports\ADG\OSCR FR 161 - 2020_01-21.docx
Page 8 of 10
Framing installation progress at side wall of monitor roof on north slope of west wing (Lima)
Abatement progress at top landing of stair at east end of tunnel
-
P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field
Reports\ADG\OSCR FR 161 - 2020_01-21.docx
Page 9 of 10
Existing State fiber lines conduit leak/drip at east end of tunnel
Primer progress at east end of tunnel
-
P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field
Reports\ADG\OSCR FR 161 - 2020_01-21.docx
Page 10 of 10
Primer progress at west end of tunnel
-
N:\HP15.007.00B Oklahoma State Capitol Exterior Rehabili\6_CA\Site Visits\TA\TA.163_2019-12-19\OSCR FR TA.163 - 2019_12_19.docx
Page 1 of 7
FIELD OBSERVATION REPORT REPORT NO: 163 DATE: 12/19/2019 TIME: 11:30 am – 2:00 pm DAY OF WEEK: Thursday OWNER: OMES TEMP. RANGE: Lo 50s – Mid 50s PROJECT: Oklahoma Capitol Restoration - Exterior Rehabilitation CAP PROJECT NO: 15039DB JE DUNN PROJECT NO: 15025800 ADG PROJECT NO: 15-007 TREANOR PROJECT NO: HP 15.007.00B ZFI PROJECT NO: 15071-01 ALVINE PROJECT NO: 2014-4286 SRB PROJECT NO: 114801 WEATHER: Clear Overcast Rain Snow Cold Warm Hot Foggy Windy Ice Other SITE CONDITIONS: Clear Dusty Muddy Other _________________ PERSONS CONTACTED:
Mark Maska (JE Dunn) Michael Conway, Shannon Cheek (Baker Roofing) Chris Brackin (Brackin Estimating & Consulting) Jason Cady (Mass Architects) Steven Naggatz, Joshua Freedland (WJE)
WORK OBSERVED:
East wing – Reviewed progress on mockups S, T, and W. See review comments posted to the Box site on 1/20/20. Mockup T is reviewed as noted and provided no alterations are made remains accepted. Mockup W/U has items outstanding. Mockup S was in progress, but not complete. Alterations to the height of the ridge proposed by Brackin were discussed and accepted for integration into the next iteration.
Substrate replacement on the skylight is in progress and nearly complete. Roofing on south main slope has progressed to the west end of the monitor.
South wing – Installation of skylight cladding and crickets is in progress, five of eight lower skylights on are complete. Portions of the upper skylights are missing finishing side wall trim and ridges are outstanding. Main ridge remains incomplete. Construction of mockup M on the west slope has resulted in a standing seam much closer to the end of the flat flock than originally planned.
West wing – Substrate repairs are in progress, including repairs to the slab/pediment stone connection. Replacement of monitor decking is not complete, temporary protection is in place. Workers have been assigned to substrate repairs.
-
N:\HP15.007.00B Oklahoma State Capitol Exterior Rehabili\6_CA\Site Visits\TA\TA.163_2019-12-19\OSCR FR TA.163 - 2019_12_19.docx
Page 2 of 7
ITEMS DISCUSSED:
Construction schedule for Christmas and New Years holidays. Discussed the need for ridges and all edges that have not been completed to be protected and well-sealed before Baker Roofing leaves for the holidays.
South wing mockup M area: seam layout did not end up as predicted. Discussed the need to evaluate how many standing seams need to be rolled over and location/width of the divertor for the gutter with running water. Area needs to be completed on both sides. Hose tests may help, but observations made during a rain will likely be necessary.
ACTION REQUIRED:
Corrective actions noted during 11-1-2019 site visit have not occurred.
Complete Mockup S and Mockup U/W for review. ITEMS TO VERIFY:
REMARKS:
OBSERVED BY: Julia Manglitz, Associate Principal (TreanorHL) COPIES TO: David Mihm (OMES), Doug Kellogg (OMES), Mike Jones (OMES), Trait Thompson
(OMES), Duane Mass (MAI), Jason Cady (MAI), Matthew Radcliffe (MAI), Richard Fleming (JE Dunn), Mark Maska (JE Dunn), Bobby Snyder (JE Dunn), Brandon Marriott (JE Dunn), Lindsey Ross (JE Dunn), JC Witcher (ADG), Robert Meek (ADG), Julia Manglitz (TreanorHL), Todd Renyer (TreanorHL), Vance Kelley (TreanorHL), Mike Thompson (ZFI), Steve Ford (ZFI), Andy Wiese (Alvine), Ed Kongs (Alvine), Sam Haberman (Alvine), Steve Alvine (Alvine), Gary Noland (Smith Roberts Baldischwiler)
-
N:\HP15.007.00B Oklahoma State Capitol Exterior Rehabili\6_CA\Site Visits\TA\TA.163_2019-12-19\OSCR FR TA.163 - 2019_12_19.docx
Page 3 of 7
East Wing, south slope. Mockup S and T at downslope corner of monitor.
East Wing, south slope. Mockup S at downslope corner of monitor.
-
N:\HP15.007.00B Oklahoma State Capitol Exterior Rehabili\6_CA\Site Visits\TA\TA.163_2019-12-19\OSCR FR TA.163 - 2019_12_19.docx
Page 4 of 7
East wing monitor. Mockup S at ridge, incomplete but in progress.
East wing monitor. Mockup S at ridge with ridge and sub-ridge removed. Isolation of vented ridge area is
necessary.
-
N:\HP15.007.00B Oklahoma State Capitol Exterior Rehabili\6_CA\Site Visits\TA\TA.163_2019-12-19\OSCR FR TA.163 - 2019_12_19.docx
Page 5 of 7
Overview of east wing, south slope.
South wing, east slope. Ridge and edge trim outstanding on two of three upper skylights. Third upper
skylight copper work is outstanding.
-
N:\HP15.007.00B Oklahoma State Capitol Exterior Rehabili\6_CA\Site Visits\TA\TA.163_2019-12-19\OSCR FR TA.163 - 2019_12_19.docx
Page 6 of 7
South wing, west slope. Work in progress on northern-most lower skylight.
South wing, view looking north along the incomplete ridge.
-
N:\HP15.007.00B Oklahoma State Capitol Exterior Rehabili\6_CA\Site Visits\TA\TA.163_2019-12-19\OSCR FR TA.163 - 2019_12_19.docx
Page 7 of 7
West wing, south slope. Substrate repairs in progress.
-
C:\Users\jmanglitz\Desktop\OSCR FR TA.164 - 2020_01_20.docx Page 1 of 6
FIELD OBSERVATION REPORT REPORT NO: 164 DATE: 01/20/2020 TIME: Noon – 2:30 pm DAY OF WEEK: Monday OWNER: OMES TEMP. RANGE: Lo 40s – Hi 40s PROJECT: Oklahoma Capitol Restoration - Exterior Rehabilitation CAP PROJECT NO: 15039DB JE DUNN PROJECT NO: 15025800 ADG PROJECT NO: 15-007 TREANOR PROJECT NO: HP 15.007.00B ZFI PROJECT NO: 15071-01 ALVINE PROJECT NO: 2014-4286 SRB PROJECT NO: 114801 WEATHER: Clear Overcast Rain Snow Cold Warm Hot Foggy Windy Ice Other SITE CONDITIONS: Clear Dusty Muddy Other _________________ PERSONS CONTACTED:
Mark Maska, Rick Fleming, Brandon Marriott (JE Dunn) Michael Conway, Vince Latona, Shannon Cheek (Baker Roofing) Chris Brackin (Brackin Estimating & Consulting) Jarek Sienkiewicz (Mark 1) Jason Cady (Mass Architects)
WORK OBSERVED:
East wing – Reviewed progress on mockups S and W. See review comments posted to the Box site on 1/20/20. Mockup S is not complete down to the main roof ridge. Mockup W is approved with the note that the expansion joint ends should not sag between the supports, end caps and downspouts will be done as for the gutters on the back of the tall parapet (these items were not installed at the monitor during review).
Counterflashing at the pediment valleys has not been completed and lead t-cap requires adjustment in various locations.
Cladding is being applied to monitor sidewalls. Roofing panels for monitor roof are staged and ready to start installation.
South wing – Installation of ridge caps at the main slope and on the upper skylights is in progress.
West wing – Substrate repairs are in progress, replacement of decking at the monitor is nearly complete.
-
C:\Users\jmanglitz\Desktop\OSCR FR TA.164 - 2020_01_20.docx Page 2 of 6
ITEMS DISCUSSED:
Punch list for the east wing (both slopes) and the east slopes above the low roof on the north and south wings. Per JE Dunn and Baker 1/30 will be the date. Goal is to have all items complete including snow guards on the east wing. North and south complete except for snow guards. This will need to include all work at the low roofs as well. Removal of railings, and patching associated with removal will not be complete.
Installation of counter flashing at pediment valley ends, masons need to set threaded rods. Detail is the same as is used on the north and south wings.
Mark 1 on site to provide anchors and patches for reconfiguration of lighting protection down leads.
Area of spalled stone on the Kilo-Juliette corner of the drum base, west wing. The spall is adjacent to a reglet and requires repair to provide secure sheet metal attachment. Concept for repair drawn and emailed to JE Dunn on 1/20/20.
ACTION REQUIRED:
Confirm that all previous punchlist items (ADG or TreanorHL) are complete for sheet metal work on Delta and Foxtrot low roofs. (JED, Baker)
Transmit photos and descriptions for the remainder of mockup S for review and comment. (Baker)
ITEMS TO VERIFY:
REMARKS:
OBSERVED BY: Julia Manglitz, Associate Principal (TreanorHL) COPIES TO: David Mihm (OMES), Doug Kellogg (OMES), Mike Jones (OMES), Trait Thompson
(OMES), Duane Mass (MAI), Jason Cady (MAI), Matthew Radcliffe (MAI), Richard Fleming (JE Dunn), Mark Maska (JE Dunn), Bobby Snyder (JE Dunn), Brandon Marriott (JE Dunn), Lindsey Ross (JE Dunn), JC Witcher (ADG), Robert Meek (ADG), Julia Manglitz (TreanorHL), Todd Renyer (TreanorHL), Vance Kelley (TreanorHL), Mike Thompson (ZFI), Steve Ford (ZFI), Andy Wiese (Alvine), Ed Kongs (Alvine), Sam Haberman (Alvine), Steve Alvine (Alvine), Gary Noland (Smith Roberts Baldischwiler)
-
C:\Users\jmanglitz\Desktop\OSCR FR TA.164 - 2020_01_20.docx Page 3 of 6
Mockup S - Monitor ridge detail with stainless steel sub-ridge and copper ridge cover removed.
Mockup S - End of ridge with copper cap in place
-
C:\Users\jmanglitz\Desktop\OSCR FR TA.164 - 2020_01_20.docx Page 4 of 6
Mockup W – expansion joint
Mockup W – expansion joint. Ensure that gutter low point does not occur at expansion joint.
-
C:\Users\jmanglitz\Desktop\OSCR FR TA.164 - 2020_01_20.docx Page 5 of 6
East wing – north slope progress.
East wing – south slope progress
-
C:\Users\jmanglitz\Desktop\OSCR FR TA.164 - 2020_01_20.docx Page 6 of 6
West wing – substrate repairs to wood decking in progress.
West wing – spalled stone at reglet on the drum base.
-
ZFI Engineering Co.
8411 S. Walker Ave.
OKC, OK 73139
Ph: 405.634.3393
Fx: 405.634.6414
www.zfiengr.com
ENGINEER’SFIELDREPORT Project: Oklahoma State Capitol Exterior Renovation Project#: 15071-01 Date/Time: November 1, 2019 Temperature: Mid 50’s Weather: Sunny, Gusty
WorkinProgress: Installation of miscellaneous steel framing and CretePlank on
the East Wing monitor roof. Installation of monitor wall light gauge steel framing.
ReasonforVisit: Review of East Wing monitor wall framing configurations especially
at louvers Personnel: Brandon Marriott – JE Dunn (General Contractor) Mike Thompson – ZFI Engineering (Structural EOR) Mark Maska - JE Dunn (General Contractor) Mike Thompson (MDT) of ZFI was on-site to observe monitor wall framing operations and was on-site when an anchor issue was discovered on the East Wing monitor East wall. Observations:
1. The north side of the East Monitor was walked in order to observe several of the monitor wall framing configurations.
2. Several of the louver locations were framed differently than as intended on the construction documents. The adjacent photo is consistent with the design intent where the top and bottom horizontal stud members are continuous through the louver width.
Horiz Stud Continuous Through Louver Opening
-
Engineer’s Field Report Oklahoma State Capitol Exterior Renovation ZFI Project # 15071-01 November 1, 2019 Page 2 of 4
3. In one or two locations, the top and bottom stud framing was ‘broken’ and not
continuous across the bay width. This is not consistent with the design intent. See the photo below for and example of the non-continuous line of studs. Based on conversations with Brandon Marriott of JE Dunn, the non-continuous framing would be re-worked with the final louver opening sizes and framed continuously.
Horiz Stud Not Continuous Through Louver Opening
Horiz Stud Continuous Through Louver Opening
-
Engineer’s Field Report Oklahoma State Capitol Exterior Renovation ZFI Project # 15071-01 November 1, 2019 Page 3 of 4
4. The jamb framing at the end of the bays was also reviewed and found to be in
general conformance with the construction drawings. An example of this framing is shown below. NotethatZFIconductedastructuralobservation,notspecialinspections,toevaluategeneralconformancewithcontractdocuments. Structuralobservationsarethevisualobservationofthestructuralsystemforgeneralconformancetotheapprovedconstructiondocuments.Structuralobservationsdonotwaivetheresponsibilityofthegeneralcontractortoperforminternalqualityassuranceandqualitycontrolnordotheywaiveorproporttomeetthespecialinspectionsrequirements.
Horiz Stud Not Continuous Through Louver Opening
Example of Jamb Construction @ Ends of Bays
-
Engineer’s Field Report Oklahoma State Capitol Exterior Renovation ZFI Project # 15071-01 November 1, 2019 Page 4 of 4
5. ZFI and JE Dunn observed an unforeseen condition at the east endwall of the East Wing monitor. The specified fasteners for the plywood substrate were unable to find purchase in the nominally 1½”-2” thick, brittle, cementitious wall material on Hy-Rib lathe and were spinning out or stripping out with little-to-no load. Note that the back of this wall framing was not directly observable due to the presence of spray-applied fireproofing foam. It was determined after discussions on-site to pursue the use of toggled bolts (similar to those used in drywall construction) to fasten the sheathing to this end wall. These bolts and the installation method would be forwarded via RFI for the SEOR to review. (SeeRFI0011)
ReportedBy: Mike Thompson, PE ZFI Engineering Co.
-END-
Stripped‐out Fastener Holes
Attempts to perform shallower drilling for fasteners still resulted in stripping out of fasteners.
-
ZFI Engineering Co.
8411 S. Walker Ave.
OKC, OK 73139
Ph: 405.634.3393
Fx: 405.634.6414
www.zfiengr.com
ENGINEER’SFIELDREPORT Project: Oklahoma State Capitol Exterior Renovation Project#: 15071-01 Date/Time: December 4, 2019 Temperature: High 50’s Weather: Sunny, Calm
WorkinProgress: Roofing demolition on west roof, West Wing gap repair.
ReasonforVisit: Review of crack in West Wing, north slope near end of monitor, review West Wing gap repair progress
Personnel: Brandon Marriott – JE Dunn (General Contractor) Mike Thompson – ZFI Engineering (Structural EOR) Mark Maska - JE Dunn (General Contractor) Mike Thompson (MDT) of ZFI was on-site to observe an unforeseen condition of a crack in the structural concrete roof slab at the northwest corner of the West Wing roof near the west end of the north side of the monitor. Observations:
1. A crack was observed in the Hy-Rib concrete roof slab in the immediate vicinity of the northwest corner of the West Wing roof monitor.
Crack in Hy‐Rib Roof Slab
-
Engineer’s Field Report Oklahoma State Capitol Exterior Renovation ZFI Project # 15071-01 December 4, 2019 Page 2 of 6
The crack appeared to originate at the point where the Hy-Rib deck meets the monitor steel framing up from the steel roof truss below at the northwest corner of the West Wing roof monitor. The crack propagated north. The crack was located below a small strip of cementitious fill between two beveled wood sleepers that were in close proximity (see adjacent photo and on the previous page). The original construction suggests this may have been a pour joint or construction joint in the roof slab.
The crack measured approximately ¼” to 3/8” along its length. The crack was through the entire depth of the Hy-Rib slab and the metal lathe of the Hy-Rib system was visible from above in many locations. The crack appeared to follow a seam in the lathe system.
Crack Follows Seam in Hy‐Rib Lathe Below
-
Engineer’s Field Report Oklahoma State Capitol Exterior Renovation ZFI Project # 15071-01 December 4, 2019 Page 3 of 6
The crack was also visible from the attic below, confirming it occurred through the entire depth of the slab and reflected through the plaster on the soffit of the slab. It followed the line of the steel truss all the way to the north edge of the roof.
The crack appeared to be quite old (see photo below) and may have occurred relatively soon after original construction.
Crack Visible from Attic Below
Crack Follows Steel Roof Truss
-
Engineer’s Field Report Oklahoma State Capitol Exterior Renovation ZFI Project # 15071-01 December 4, 2019 Page 4 of 6
Given the location, there are several possibilities as to its origin: a. A failed seam in the Hy-Rib lathe that allowed shrinkage-related movement
to manifest along the seam, b. A poorly bonded construction joint that propagated a crack due to
shrinkage-related movement, c. Expected shrinkage-related movement may have been exceeded due to the
differing aspect ratios for the portion of the roof due north of the monitor (red portion in below) and the portion of the roof west of the monitor (green portion below),
d. Shrinkage-related stress was concentrated at the re-entrant corner in the roof slab created by the presence of the monitor framing, or
e. Some combination of these reasons.
It is our opinion that this is not a seismic-related crack and as it runs parallel to the north-south framing direction of the roof slab (recall that roof purlins run east-west between north-south running roof trusses), it does not pose a significant gravity load-carrying issue. As mentioned above, the crack appears to be quite old and given the ragged edges does not appear to be a ‘working’ crack that experiences cyclical loading or opening and closing of any kind. ZFI directed JEDunn to cut out the existing concrete along the length of the crack to 4”-to-5” minimum width and down the Hy-Rib lathe. The lathe should be maintained and new repair concrete per Type 1 concrete repair on sheet SS003 would be utilized to patch the slab back to its original profile along the entire length of the crack.
Crack Location at Assumed Const. Joint
-
Engineer’s Field Report Oklahoma State Capitol Exterior Renovation ZFI Project # 15071-01 December 4, 2019 Page 5 of 6
2. At the same location on the south slope of the West Wing, a similar crack was observed from the attic below. This crack appeared to ‘jump’ from one Hy-Rib lathe seam west to the next before continuing south along the roof slope. The existing roof demolition has not reached this location at the time of ZFI’s visit; however, if a similar condition is encountered once the skyward facing side of the deck was uncovered, ZFI directed JEDunn to perform the same repair as outlined previously. It is unclear if the crack compromises the slab’s load-carrying ability at this location of if the cracking is confined to the plaster soffit material.
-
Engineer’s Field Report Oklahoma State Capitol Exterior Renovation ZFI Project # 15071-01 December 4, 2019 Page 6 of 6
3. The repair at the gap between the west end of the West Wing roof slab and the west pediment stone was underway. The north slope had been completed and the south slope was in progress. See the October1,2019Engineer’sFieldReport for additional information.
ReportedBy: Mike Thompson, PE
ZFI Engineering Co.
-END-
North Slope Repair Complete
South Slope Repair On‐going
-
15
03
9D
B
MO
NT
HLY
CO
NS
TR
UC
TIO
N P
RO
GR
ES
S R
EP
OR
TCLICK HERE
JE DUNN I TREANORHL ARCHITECTS I ADG
Phasing & Schedule Attachments: The following documents are included in the subsequent pages:
- Site Phasing Plan
- Site Utilization Plan
- Schedules
Exterior RehabilitationJanuary 2020
RETURN TO TABLE OF CONTENTS
4 E SHERIDAN AVE SUITE 200 I OKLAHOMA CITY, OK 73104
-
JED
JED
-
Activity ID Activity Name RemDur
Start Finish
SiteSite 70 09-May-19 A 01-May-20
TunnelTunnel 44 22-Jan-20 A 26-Mar-20
Tunnel FinishesTunnel Finishes 44 22-Jan-20 A 26-Mar-20
CON-32890 Flooring Tile 30 22-Jan-20 A 06-Mar-20
CON-32840 Ceiling Grid 10 27-Jan-20 A 07-Feb-20
CON-33970 Field Measure Vestibule Panels 3 27-Jan-20 29-Jan-20
CON-32870 Millwork 20 19-Feb-20 17-Mar-20
CON-32860 Acoustical Panels Installation 15 27-Feb-20 18-Mar-20
CON-32850 Handrails 5 09-Mar-20 13-Mar-20
CON-32880 Rubber Stair Treads & Risers 5 09-Mar-20 13-Mar-20
CON-32930 Drop Tile 5 09-Mar-20 13-Mar-20
CON-32900 Carpet 3 18-Mar-20 20-Mar-20
CON-33930 Trim Out 1 23-Mar-20 23-Mar-20
CON-33940 Final Paint 1 24-Mar-20 24-Mar-20
CON-32910 Final Clean 2 25-Mar-20 26-Mar-20
CON-32940 Tunnel Finishes Complete 0 26-Mar-20
Site-Northeast Ret Wal l/LandscapeSite-Northeast Ret Wal l/Landscape 30 23-Mar-20 01-May-20
HardscapeHardscape 15 23-Mar-20 10-Apr-20
CON-33810 NE Wall-Form/Place New Retaining Wall & Mow Strip (after crane demob) 15 23-Mar-20* 10-Apr-20
LandscapeLandscape 15 13-Apr-20 01-May-20
CON-33820 NE Wall-Grading & Landscaping (after crane demob) 15 13-Apr-20* 01-May-20
Site-Southwest Ret Wall /LandscapeSite-Southwest Ret Wall /Landscape 0 09-May-19 A 27-Jan-20
LandscapeLandscape 0 09-May-19 A 27-Jan-20
CON-33210 SW Wall-Sump Pump Piping Daylighting (MCC Gravel Ramp Removal) 0 09-May-19 A 27-Jan-20
Closeout & WarrantyCloseout & Warranty 301 27-Jan-20 30-Mar-21
.. 50 27-Jan-20 03-Apr-20
.. 50 27-Jan-20 03-Apr-20
CON-10760 Base Job Demobillization 50 27-Jan-20 03-Apr-20
JED-0600 Substantial Completion 0 26-Mar-20
Warranty ReviewsWarranty Reviews 197 22-Jun-20 30-Mar-21
J J F F F F M M M M M A A A A M M M M M J J J J J J J J A A A A A S S S S
Flooring Tile
Ceiling Grid
Field Measure Vestibule Panels
Millwork
Acoustical Panels Installation
Handrails
Rubber Stair Treads & Risers
Drop Tile
Carpet
Trim Out
Final Paint
Final Clean
Tunnel Finishes Complete
NE Wall-Form/Place New Retaining Wall & Mow Strip (after crane demob)
NE Wall-Grading & Landscaping (after crane demob)
SW Wall-Sump Pump Piping Daylighting (MCC Gravel Ramp Removal)
Base Job Demobillization
Substantial Completion
Remaining Construction
Data Date: 27-Jan-20
Run Date: 24-Jan-20; 10:37
Oklahoma State Capitol Exterior Renovation
Page 1 of 1
-
Activity ID Activity Name RemDur
Start Finish Actual Start Actual Finish
OSCR-Roof ReplacementOSCR-Roof Replacement 51 06-Feb-19 A 06-Apr-20 06-Feb-19
SummarySummary 51 06-Feb-19 A 06-Apr-20 06-Feb-19
CON-2110 South Wing Duration 12 06-Feb-19 A 11-Feb-20 06-Feb-19
CON-2120 North Wing Duration 15 18-Feb-19 A 14-Feb-20 18-Feb-19
CON-2130 East Wing Duration 5 10-Apr-19 A 31-Jan-20 10-Apr-19
CON-2140 West Wing Duration 32 15-Jul-19 A 10-Mar-20 15-Jul-19
CON-4420 MCC Crane Use 5 03-Feb-20* 07-Feb-20
CON-2100 Demob Scaffolding/Mtl 5 16-Mar-20 20-Mar-20
CON-2090 Demob Crane 3 23-Mar-20 25-Mar-20
CON-2070 Planned Weather Contingency 8 26-Mar-20 06-Apr-20
CON-2080 Substantial Completion 0 06-Apr-20*
ConstructionConstruction 35 09-Dec-19 A 13-Mar-20 09-Dec-19
South Wing-IndiaSouth Wing-India 13 03-Feb-20 19-Feb-20
CON-1200 Install 4" Gutter-South Wing India 2 03-Feb-20* 04-Feb-20
CON-4440 Install Snow Guards 3 17-Feb-20* 19-Feb-20
South Wing-GolfSouth Wing-Golf 7 03-Feb-20 11-Feb-20
CON-1250 Install 4" Gutter-South Wing Golf 2 03-Feb-20* 04-Feb-20
CON-3880 Clean-Up-Demob-Punchlist-South Wing 5 05-Feb-20* 11-Feb-20
North Wing-CharlieNorth Wing-Charlie 11 05-Feb-20 19-Feb-20
CON-1040 Install 4" Gutter-North Wing Charlie 2 05-Feb-20* 06-Feb-20
CON-4460 Install Snow Guards 3 17-Feb-20* 19-Feb-20
North Wing AlphaNorth Wing Alpha 6 07-Feb-20 14-Feb-20
CON-1090 Install 4" Gutter-North Wing Alpha 2 07-Feb-20* 08-Feb-20
CON-3870 Clean-Up-Demob-Punchlist-North Wing 5 10-Feb-20* 14-Feb-20
East Wing-MonitorEast Wing-Monitor 8 20-Jan-20 A 05-Feb-20 20-Jan-20
Copper Panels/Wall CladdingCopper Panels/Wall Cladding 8 20-Jan-20 A 05-Feb-20 20-Jan-20
CON-1300 Install Copper Panels/Cladding-East Monitor East Cornice2 20-Jan-20 A 28-Jan-20 20-Jan-20
CON-4480 Install Snow Guards 3 29-Jan-20 31-Jan-20
CON-4470 Install Ridge Cap 6 29-Jan-20 05-Feb-20
CON-3860 Clean-Up-Demob-Punchlist-EW Monitor 3 03-Feb-20 05-Feb-20
West Wing Monitor-South SideWest Wing Monitor-South Side 35 27-Jan-20 13-Mar-20
Remove Sheathing/Install Crete-PlankRemove Sheathing/Install Crete-Plank 2 27-Jan-20 28-Jan-20
CON-4410 Felt/Densglass/Plywood 2 27-Jan-20 28-Jan-20
Copper Panels/Wall CladdingCopper Panels/Wall Cladding 15 22-Feb-20 13-Mar-20
CON-4200 Install Copper Panels-West Monitor-East Cornice/Sec 13 22-Feb-20 25-Feb-20
CON-4210 Install Copper Panels-West Monitor-Sec 2-5 2 26-Feb-20 27-Feb-20
CON-4220 Install Copper Panels-West Monitor-Sec 6-8 2 28-Feb-20 29-Feb-20
CON-1485 Install Copper Panels-West Monitor-West Cornice 2 02-Mar-20 03-Mar-20
CON-4510 Install Ridge Cap 3 04-Mar-20 06-Mar-20
CON-4500 Install Snow Guards 5 04-Mar-20 10-Mar-20
CON-3830 Clean-Up-Demob-Punchlist-WW Monitor 3 11-Mar-20 13-Mar-20
Small Skylight-WestSmall Skylight-West 24 29-Jan-20 02-Mar-20
CON-3310 Demo Small Skylights-West 2 29-Jan-20 30-Jan-20
CON-3320 Rebuild Small Skylights-West 3 31-Jan-20 04-Feb-20
CON-1550 Install Copper Small Skylight-West 3 28-Feb-20 02-Mar-20
West Low Roof-South SideWest Low Roof-South Side 25 19-Dec-19 A 28-Feb-20 19-Dec-19
CON-3240 Demo Sheathing/Repair Sleepers (if needed)-West Low South Side1 19-Dec-19 A 27-Jan-20 19-Dec-19
CON-4260 Install Flatlock Copper-West Low South Side 2 27-Jan-20 28-Jan-20
CON-3250 Install New Sheathing-West Low South Side 2 31-Jan-20 03-Feb-20
CON-4380 Install Copper Panels/Gutter-West Low South Side-Area A5 05-Feb-20 10-Feb-20
CON-1580 Install Copper Panels/Gutter-West Low South Side-Area B5 11-Feb-20 15-Feb-20
Feb Mar Apr May Jun
2020
South Wing Duration
North Wing Duration
East Wing Duration
West Wing Duration
MCC Crane Use
Demob Scaffolding/Mtl
Demob Crane
Planned Weather Contingency
Substantial Completion
Install 4" Gutter-South Wing India
Install Snow Guards
Install 4" Gutter-South Wing Golf
Clean-Up-Demob-Punchlist-South Wing
Install 4" Gutter-North Wing Charlie
Install Snow Guards
Install 4" Gutter-North Wing Alpha
Clean-Up-Demob-Punchlist-North Wing
Install Copper Panels/Cladding-East Monitor East Cornice
Install Snow Guards
Install Ridge Cap
Clean-Up-Demob-Punchlist-EW Monitor
Felt/Densglass/Plywood
Install Copper Panels-West Monitor-East Cornice/Sec 1
Install Copper Panels-West Monitor-Sec 2-5
Install Copper Panels-West Monitor-Sec 6-8
Install Copper Panels-West Monitor-West Cornice
Install Ridge Cap
Install Snow Guards
Clean-Up-Demob-Punchlist-WW Monitor
Demo Small Skylights-West
Rebuild Small Skylights-West
Install Copper Small Skylight-West
Demo Sheathing/Repair Sleepers (if needed)-West Low South Side
Install Flatlock Copper-West Low South Side
Install New Sheathing-West Low South Side
Install Copper Panels/Gutter-West Low South Side-Area A
Install Copper Panels/Gutter-West Low South Side-Area B
Remaining Construction
Data Date: 27-Jan-20
Run Date: 24-Jan-20; 10:17
OSCR-Roof Replacement
Page 1 of 2
-
Activity ID Activity Name RemDur
Start Finish Actual Start Actual Finish
CON-4520 Install Snow Guards 5 17-Feb-20 21-Feb-20
CON-3970 Install Roof Ladders-West Wing 10 17-Feb-20 28-Feb-20
West Low Roof-North SideWest Low Roof-North Side 29 09-Dec-19 A 05-Mar-20 09-Dec-19
CON-3280 Demo Sheathing/Repair Sleepers (if needed)-West Low North Side2 09-Dec-19 A 28-Jan-20 09-Dec-19
CON-4270 Install Flatlock Copper-West Low North Side 6 29-Jan-20 04-Feb-20
CON-3290 Install New Sheathing-West Low North Side 2 03-Feb-20 04-Feb-20
CON-4390 Install Copper Panels/Gutter-West Low North Side-Area A5 17-Feb-20 21-Feb-20
CON-1680 Install Copper Panels/Gutter-West Low North Side-Area B5 22-Feb-20 27-Feb-20
CON-4530 Install Snow Guards 5 28-Feb-20 05-Mar-20
Feb Mar Apr May Jun
2020
Install Snow Guards
Install Roof Ladders-West Wing
Demo Sheathing/Repair Sleepers (if needed)-West Low North Side
Install Flatlock Copper-West Low North Side
Install New Sheathing-West Low North Side
Install Copper Panels/Gutter-West Low North Side-Area A
Install Copper Panels/Gutter-West Low North Side-Area B
Install Snow Guards
Remaining Construction
Data Date: 27-Jan-20
Run Date: 24-Jan-20; 10:17
OSCR-Roof Replacement
Page 2 of 2