I-69 Major Moves 2020 Expansion Project –
Public Information Meeting
Tony Jones, PEProject Manager, INDOT
April 21, 2016
I-69 Major Moves 2020 Expansion Project
Meeting Agenda
Introduce Design-Build Team
Describe Project Delivery Strategy
Describe Project Construction Schedule
Discussion of Exit 210 Reconstruction
Discussion of Noise Barriers
Open Discussion
I-69 Major Moves 2020 Expansion Project
Project Team
Indiana Department of Transportation
Indiana Finance Authority
Parsons Corporation (front end design)
Milestone Contractors (construction)
United Consulting (back end design)
I-69 Major Moves 2020 Expansion Project
I-69 Major Moves 2020 Expansion Project
Project Delivery Strategy
Package 1:
Overlay and Partial Depth Patching of existing lanes.
Median outlet pipe installation and culvert lining.
Night-time lane restrictions.
I-69 Major Moves 2020 Expansion Project
Project Delivery Strategy
Package 2 (116th Street to north of Brooks School Road):
Added travel lane construction in median.
Use of barrier rail to separate construction and travel lanes.
Maintain two lanes in each direction at all times.
I-69 Major Moves 2020 Expansion Project
Project Delivery Strategy
Package 3:
Reconstruction of Campus Parkway / Southeastern Parkway at Exit 210.
Multi-phase maintenance of traffic.
Maintain through traffic at all times.
I-69 Major Moves 2020 Expansion Project
Project Delivery Strategy
Package 4 (north of Brooks School Road to north of SR 13):
Added travel lane construction in median.
Use of temporary barrier to separate construction from the travel lanes.
Maintain two lanes in each direction at all times.
I-69 Major Moves 2020 Expansion Project
Project Delivery Strategy
Package 5 (north of SR 13 to north of SR 38):
Added travel lane construction in median.
Use of temporary barrier to separate construction from the travel lanes.
Maintain two lanes in each direction at all times.
I-69 Major Moves 2020 Expansion Project
MOT Plan – I-69, Phase I (pkg 2, 4, 5)
I-69 Major Moves 2020 Expansion Project
MOT Plan – I-69, Phase II (pkg 2, 4 & 5)
I-69 Major Moves 2020 Expansion Project
MOT Plan – I-69, Phase III (pkg 2,4 & 5)
I-69 Major Moves 2020 Expansion Project
MOT Plan – I-69, Phase IV (pkg 2, 4 & 5)
I-69 Major Moves 2020 Expansion Project
MOT Plan – Exit 210, Phase 1 (pkg 3)
I-69 Major Moves 2020 Expansion Project
MOT Plan – Exit 210, Phase 2 (pkg 3)
I-69 Major Moves 2020 Expansion Project
MOT Plan – Exit 210, Phase 3 (pkg 3)
I-69 Major Moves 2020 Expansion Project
MOT Plan – Exit 210, Phase 4 (pkg 3)
I-69 Major Moves 2020 Expansion Project
MOT Plan – Exit 210, Phase 5 (pkg 3)
I-69 Major Moves 2020 Expansion Project
MOT Plan – Exit 210, Phase 6 (pkg 3)
I-69 Major Moves 2020 Expansion Project
MOT Plan – SR 13, Phase 1 (pkg 2)
I-69 Major Moves 2020 Expansion Project
MOT Plan – SR 13, Phase 2 (pkg 2)
I-69 Major Moves 2020 Expansion Project
Project Schedule
Overall Schedule:
Construction to begin in May, 2016
Construction to be complete in November, 2017
Final acceptance in October, 2018
Campus Parkway / Southeastern Parkway Construction limited to 360 days
I-69 Major Moves 2020 Expansion Project
Project Schedule
I-69 Construction:
Location106th to SR 37
SR 37 to North of Brooks School Road
North of Brooks
School Road to North of
SR 13
North of SR 13 to North of SR 38
Phase Ia/Ib 6/2017 5/2016 6/2016 7/2016
Phase II6/2017 -9/2017
5/2016 -9/2016
9/2016 -7/2017
7/2017 -9/2017
Phase IIIa/IIIb 9/2017 5/2017 6/2017 7/2017
Phase IV 10/2017 8/2017 9/2017 10/2017
I-69 Major Moves 2020 Expansion Project
Project Schedule
Exit 210 Construction:
Campus Parkway / Southeastern Parkway
Phase 1 7/5/2016
Phase 2 tbd
Phase 3 tbd
Phase 4 tbd
Phase 5 tbd
Phase 6
tbdComplete by 6/30/2017
I-69 Major Moves 2020 Expansion Project
Project Schedule
Exit 215 Construction:
Overhead Bridge Construction:
SR 13
Phase 1
2017 (tbd)Phase 2
Brooks School Road
5/2017 –8/2017
Madison County CR 650 W
5/2017 –8/2017
I-69 Major Moves 2020 Expansion Project
Detour – Brooks School Road Overpass
I-69 Major Moves 2020 Expansion Project
Detour – Madison Co. CR 650 W Overpass
I-69 Major Moves 2020 Expansion Project
Noise Barriers
Cumberland Crossing / Cumberland Woods
I-69 Major Moves 2020 Expansion Project
Noise Barriers
Whispering Woods
I-69 Major Moves 2020 Expansion Project
Noise Barriers
Brooks Chase
I-69 Major Moves 2020 Expansion Project
Noise Barriers
Roselake
I-69 Major Moves 2020 Expansion Project
Thank you for attending!