Done: (1/2)
Preliminary civil engineering drawing and Functional specification approved by CERN on 18/03/2014 (EDMS 1365362 and 1350076)
Civil engineering Tender Design phase started on 2/04/2014 by ARCADIS
Submission of the « Permis de construire » on 19/05/2014
Market survey issued to the firms on 11/06/2014 → Two work packages (WP1-Civil engineering & WP2-Steel structure and cladding)
02 October 20141
Extension of Building 887 - Neutrino Platform General MeetingsN.Lopez – M.Manfredi
Done: (2/2)
Tender documents ready and EDMS approval procedure launched on 10/07/2014 → 9 firms qualified for WP1, 7 firms for WP2 and 4 firms for WP 1+2
Specification Committee meeting held on 29/07/2014
Tender documents sent to the firms on 18/08/2014
Construction Design phase started on 18/08/2014 by ARCADIS
Bidders Conference held on 4/09/2014
Extension of Building 887 - Neutrino Platform General MeetingsN.Lopez – M.Manfredi
CENF – Civil Engineering Extension B887
02 October 20142
Next steps:
Bids expected on 2/10/2014
Preparatory works to start on October 2014 (abattage, déviation de réseaux, etc)
Construction Design expected on November 2014
Adjudication foreseen on December 2014 FC
Contract signature
Start of the works expected on January 2015 (if possible, anticipate Excavation works as early as possible)
Extension of Building 887 - Neutrino Platform General MeetingsN.Lopez – M.Manfredi
CENF – Civil Engineering Extension B887
TODAY // Commercial Opening soon
02 October 20143
Remarks: All material requiring CERN approval or distribution process is on EDMS (CERN-0000097536 v.0) Public documents available are the Preliminary Civil Engineering drawing (n°1365362) and Functional
specification (n°1350076)
Tender drawings and documents are «Released» but still with restricted access. Construction drawings will be «Under Approval» once received. As agreed, all the users request (i.e. general or specific information, coordination plan, etc..) concerning
the integration studies has to pass via Ilias Efthymiopoulos and his group.
Extension of Building 887 - Neutrino Platform General MeetingsN.Lopez – M.Manfredi
CENF – Civil Engineering Extension B887
02 October 20144