CASTLEBERRY PARK EB5 PROJECT
CASTLEBERRY PARK (BOLTON ATLANTA EB5 PROJECT) QUARTERLY REPORT (ISSUE 8) 1
Bolton Atlanta LP
Castleberry Park Mixed-Use
(Bolton Atlanta LP EB5 Project)
Issue 8
2019.07
CASTLEBERRY PARK -BOLTON ATLANTA EB5 PROJECT
CASTLEBERRY PARK (BOLTON ATLANTA EB5 PROJECT) QUARTERLY REPORT (ISSUE 6) 2
I. 2ND QUARTER OF 2019 PROGRESS
From April to June 2019, Atlanta Castleberry Park (Bolton Atlanta LP Eb5 Project) ran well according to the plan. During this quarter, the construction process are as follow:
1. Hotel Section Topped-out in AprilThe concrete pouring of the hotel was completed accordingly to the project
schedule.
Roof Concrete Pouring 2019.04 South Elevation 2019.04
CASTLEBERRY PARK (BOLTON ATLANTA EB5 PROJECT) QUARTERLY REPORT (ISSUE 8) 3
2. Interior Framing and Ceiling Skimming finished for Level 1-10;HVAC,Electrical and Plumbing Rough-in ongoing
East Elevation 2019.04 "Hard Rock hotel's topping-out marks latest change in downtown landscape" Source: Curbed 2019.04
Level 10 Interior Framing 2019.05 Level 9 Ceiling Skimming 2019.05
Level 7 Electrical Line Rough-in 2019.05 Level 11 Plumbing 2019.06
CASTLEBERRY PARK -BOLTON ATLANTA EB5 PROJECT
CASTLEBERRY PARK (BOLTON ATLANTA EB5 PROJECT) QUARTERLY REPORT (ISSUE 8) 4
3.Stair and Window Installation Almost Finished
East Elevation 2019.06 7Level 7 Pop-out Window Framing 2019.06
Level 7 Stair # 1 2019.06 Level 7 Window Installation 2019.05
4. Fire Sprinklers and Insulation Installation Ongoing
Level 2 Insulation Fire Sprinklers 2019.05 Level2 and Level3 Slab Insulation 2019.06
CASTLEBERRY PARK -BOLTON ATLANTA EB5 PROJECT
CASTLEBERRY PARK (BOLTON ATLANTA EB5 PROJECT) QUARTERLY REPORT (ISSUE 8) 5
5. Started to Install the Curtain Walls and LED Board
Steel Erection for Curtain Walls 2019.06 North Elevation LED Board 2019.06
6. Model Room under Construction
Model Room Paint 2019.06 Model Room Tile 2019.06
Other Operation-related Progress:
• Residential Section: Subcontractor selection and contract negotiation is under final stage. The apartment management company was selected;
• Hotel Section: Subcontractor selection and contract negotiation is under final stage. The data provider and phone provider was selected and the contracts were signed.
CASTLEBERRY PARK -BOLTON ATLANTA EB5 PROJECT
CASTLEBERRY PARK (BOLTON ATLANTA EB5 PROJECT) QUARTERLY REPORT (ISSUE 8) 6
0B
II. NEXT QUARTER PROGRESS LOOK AHEAD
1. The interior framing will be completed;2. Continue rough-in plumbing, electrical and HVAC. Continue to install the fire
sprinklers;3. Continue installing EIFS on West, East and North elevations.4. Start interior finishes.
CASTLEBERRY PARK -BOLTON ATLANTA EB5 PROJECT