CASTLEBERRY PARK EB5 PROJECT CASTLEBERRY PARK (BOLTON ATLANTA EB5 PROJECT) QUARTERLY REPORT (ISSUE 8) 1 Bolton Atlanta LP Castleberry Park Mixed-Use (Bolton Atlanta LP EB5 Project) Issue 8 2019.07

Upload: others

Post on 17-Feb-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Bolton Atlanta LP...(Bolton Atlanta LP Eb5 Project) ran well according to the plan. During this quarter, the construction process are as follow: 1. Hotel Section 7opped-out in April

CASTLEBERRY PARK EB5 PROJECT

CASTLEBERRY PARK (BOLTON ATLANTA EB5 PROJECT) QUARTERLY REPORT (ISSUE 8) 1

Bolton Atlanta LP

Castleberry Park Mixed-Use

(Bolton Atlanta LP EB5 Project)

Issue 8

2019.07

Page 2: Bolton Atlanta LP...(Bolton Atlanta LP Eb5 Project) ran well according to the plan. During this quarter, the construction process are as follow: 1. Hotel Section 7opped-out in April

CASTLEBERRY PARK -BOLTON ATLANTA EB5 PROJECT

CASTLEBERRY PARK (BOLTON ATLANTA EB5 PROJECT) QUARTERLY REPORT (ISSUE 6) 2

I. 2ND QUARTER OF 2019 PROGRESS

From April to June 2019, Atlanta Castleberry Park (Bolton Atlanta LP Eb5 Project) ran well according to the plan. During this quarter, the construction process are as follow:

1. Hotel Section Topped-out in AprilThe concrete pouring of the hotel was completed accordingly to the project

schedule.

Roof Concrete Pouring 2019.04 South Elevation 2019.04

Page 3: Bolton Atlanta LP...(Bolton Atlanta LP Eb5 Project) ran well according to the plan. During this quarter, the construction process are as follow: 1. Hotel Section 7opped-out in April

CASTLEBERRY PARK (BOLTON ATLANTA EB5 PROJECT) QUARTERLY REPORT (ISSUE 8) 3

2. Interior Framing and Ceiling Skimming finished for Level 1-10;HVAC,Electrical and Plumbing Rough-in ongoing

East Elevation 2019.04 "Hard Rock hotel's topping-out marks latest change in downtown landscape" Source: Curbed 2019.04

Level 10 Interior Framing 2019.05 Level 9 Ceiling Skimming 2019.05

Level 7 Electrical Line Rough-in 2019.05 Level 11 Plumbing 2019.06

CASTLEBERRY PARK -BOLTON ATLANTA EB5 PROJECT

Page 4: Bolton Atlanta LP...(Bolton Atlanta LP Eb5 Project) ran well according to the plan. During this quarter, the construction process are as follow: 1. Hotel Section 7opped-out in April

CASTLEBERRY PARK (BOLTON ATLANTA EB5 PROJECT) QUARTERLY REPORT (ISSUE 8) 4

3.Stair and Window Installation Almost Finished

East Elevation 2019.06 7Level 7 Pop-out Window Framing 2019.06

Level 7 Stair # 1 2019.06 Level 7 Window Installation 2019.05

4. Fire Sprinklers and Insulation Installation Ongoing

Level 2 Insulation Fire Sprinklers 2019.05 Level2 and Level3 Slab Insulation 2019.06

CASTLEBERRY PARK -BOLTON ATLANTA EB5 PROJECT

Page 5: Bolton Atlanta LP...(Bolton Atlanta LP Eb5 Project) ran well according to the plan. During this quarter, the construction process are as follow: 1. Hotel Section 7opped-out in April

CASTLEBERRY PARK (BOLTON ATLANTA EB5 PROJECT) QUARTERLY REPORT (ISSUE 8) 5

5. Started to Install the Curtain Walls and LED Board

Steel Erection for Curtain Walls 2019.06 North Elevation LED Board 2019.06

6. Model Room under Construction

Model Room Paint 2019.06 Model Room Tile 2019.06

Other Operation-related Progress:

• Residential Section: Subcontractor selection and contract negotiation is under final stage. The apartment management company was selected;

• Hotel Section: Subcontractor selection and contract negotiation is under final stage. The data provider and phone provider was selected and the contracts were signed.

CASTLEBERRY PARK -BOLTON ATLANTA EB5 PROJECT

Page 6: Bolton Atlanta LP...(Bolton Atlanta LP Eb5 Project) ran well according to the plan. During this quarter, the construction process are as follow: 1. Hotel Section 7opped-out in April

CASTLEBERRY PARK (BOLTON ATLANTA EB5 PROJECT) QUARTERLY REPORT (ISSUE 8) 6

0B

II. NEXT QUARTER PROGRESS LOOK AHEAD

1. The interior framing will be completed;2. Continue rough-in plumbing, electrical and HVAC. Continue to install the fire

sprinklers;3. Continue installing EIFS on West, East and North elevations.4. Start interior finishes.

CASTLEBERRY PARK -BOLTON ATLANTA EB5 PROJECT