Community Update May 28, 2020
Douglas MacArthur Schematic Design
www.acps.k12.va.us 2
How to Use This Presentation Due to COVID-19 impacting much of our regular work flow, ACPS is posting this presentation for community review and feedback. We were, unfortunately, not able to record a video of this presentation due to captioning requirements and our timeline.
PLEASE DO: – Review the entire presentation at your own pace.
– Respond to the questions at the end of the slide deck by Wednesday, June 3rd at 5 pm, via the project e-mail: [email protected].
– Review past information from recent and past meetings at our project website.
– Share with your neighbors, Alexandria friends and children at home!
www.acps.k12.va.us 3
This Update includes:
• Recap of project information
• Evolution of the new MacArthur Elementary school design since concept selection
• Architect’s proposed material types and color palette recommendations for community feedback
www.acps.k12.va.us 4
Project Information
www.acps.k12.va.us www.acps.k12.va.us 5
Project Team Advisory Group The Advisory Group is composed of representatives from
surrounding Civic Associations, Alexandria City Council,
Alexandria School Board, Alexandria Planning Commission,
Campagna Center and parents and community members who
serve as At-Large members. This group meets regularly with
the Core Team to provide feedback and share perspectives
from their representative coalitions.
Core Team Meets Bi-Weekly
AG CT
ST
Cm
Core Team Paul Youmbi, ACPS (Project Manager)
Erika Gulick, ACPS (Director)
Tiffany Pache, ACPS (Communications Specialist)
Jack Browand, City of Alexandria, RPCA (Division
Chief)
Katherine Carraway, City of Alexandria, Planning &
Zoning (Urban Planner)
Megan Oleynik, City of Alexandria (Urban Planner)
Dana Wedeles, City of Alexandria, RPCA (Principal
Planner)
Dirk Geratz, City of Alexandria, Planning & Zoning
(Principal Planner)
Margaret Orlando, City of Alexandria, Recreation
Services (Division Chief)
DLR Group (Architecture)
Skanska (Construction Management)
Extended Core Team Dr. Gregory C. Hutchings, Jr., ACPS (Superintendent)
Mignon R. Anthony, ACPS (Chief Operating Officer)
Dr. Terri Mozingo, ACPS (Chief Academic Officer)
Helen Lloyd, ACPS (Director of Communications)
Advisory Group 7 Meetings To Date
School Team 5 Meetings To Date
School Team The School Team is composed of the school principal and other
school leaders; Early Childhood, Upper Elementary, Resource,
Specials and Resource teachers; school support staff. This
group meets regularly with the Core Team and is essential to
defining the school’s point of view in the design process.
Community 5 Meetings To Date
Community Public
www.acps.k12.va.us www.acps.k12.va.us 6
Concept (Oct ‘19 – Feb ‘20; 5 months)
Schematic Design (Mar ‘20 - May ‘20; 3 months)
Design Dev’t (June ‘20 – Aug ‘20; 3 months)
Construction Docs (Aug ‘20 – Jan ‘20; 6 months)
Schedule (as of May 2020)
Cm Cm Cm Cm
AG AG AG
ST ST
Cm
AG AG
ST
Cm
AG
ST
Cm
AG AG
ST ST
Cm
AG
ST
Periodic Updates
Periodic Updates
Move Planning
Occupy January 2023
Cm
AG
ST
Community Meeting
Advisory Group Meeting
School Team Meeting
School Board Meeting
Construction (25 months)
Note: due to COVID-19, engagement schedule has been changed in schematic design and design development phases.
www.acps.k12.va.us 7
Evolution of Design
www.acps.k12.va.us 8 View From the Back
Board approved concept for the new Douglas MacArthur – as of January 23, 2020 “Forest”. January 23, 2020
Site Plan Massing Diagrams
View From the Front
View From the Back
www.acps.k12.va.us 9
Forest Design Evolution – since concept selection
FOREST: Starting point for design – included condensed classroom wing at back
SOUTH WING CHANGE: Gym pushed back to allow for basketball court adjacent to gym. Main entry/ cafeteria more defined.
CLASSROOM WING CHANGE: Classrooms separated into two wings allowing a courtyard or “New Forest” in center of building for efficiency. All classrooms have view of existing or new forest.
ADDED LOOP CIRCULATION: Following discussion with School Team and observation at MacArthur, bridge and learning stair added to improve connectivity and allow for possible sensory loops. Direct access between courtyard and play areas maintained.
SHADE CANOPY: Canopy added at gym for shade and connection to roof at media center. Bridges combined to single structure on two levels.
LOOP CIRCULATION CHANGE: Bridges integrated into east wing connecting academic wings. Canopy eliminated and learning stair moved to courtyard façade.
www.acps.k12.va.us 10
Proposed Materials and Colors
www.acps.k12.va.us 11
Project Team – Hired Experts Architect: DLR Group
Sarah Woodhead, AIA, NCARB (Principal-in-Charge)
Erika Lehman, AIA, NCARB (Project Manager)
Jason Lembke, AIA (Design Leader)
Bob Widger, AIA (Senior Project Architect)
Rachel Mihaly (Project Designer)
Kwame Bailey (Community Liaison)
Construction Manager: Skanksa
Apryl Webb, LEED AP, AVS, MBA (Preconstruction Director)
Joe Kifus (Senior Project Manager)
MEP Engineers: CMTA
Structural Engineer: Fox Associates
Civil and Landscape Engineers: Kimley-Horn
Food Service Designer: Nyikos Associates
IT/AV/Security: Educational Systems Planning
Geotechnical/ Environmental: ECS Mid-Atlantic
Traffic Engineer: Wells Associates
www.acps.k12.va.us 12
Before You Dive In… The following 10 slides will walk you through three potential applications of three material palettes made up of specified façade materials and colors. The material palettes are in no particular order and no one is favored by the project team.
Please note that the following slides are representations of how the materials and colors may be placed and look. The actual look and placement of colors or materials may be different when it is built. Therefore, if you have an idea on how a palette could be improved, let us know!
www.acps.k12.va.us www.acps.k12.va.us 13
Material Palette A
Light Wood Veneer Neutral Brick Green Glazed Bricks Green “Patina” Perforated Panel Zinc Metal Panel
Inspiration
Palette A is inspired by natural tones of the summer season. Please note that façade images on the following slides are not final and components of different palettes can be changed or incorporated into any palette.
www.acps.k12.va.us www.acps.k12.va.us 14
Material Palette A
View from Intersection of Yale Drive and Janneys Lane
www.acps.k12.va.us www.acps.k12.va.us 15
Material Palette A
View from Playing Field
www.acps.k12.va.us www.acps.k12.va.us 16
Material Palette B
Medium Wood Veneer Grey Brick Red/Rust Blend Bricks Red/ Terra Cotta Panel Zinc Metal Panel
Inspiration
Palette B is inspired by natural tones of the fall season. Please note that façade images on the following slides are not final and components of different palettes can be changed or incorporated into any palette.
www.acps.k12.va.us www.acps.k12.va.us 17
Material Palette B
View from Intersection of Yale Drive and Janneys Lane
www.acps.k12.va.us www.acps.k12.va.us 18
Material Palette B
View from Playing Field
www.acps.k12.va.us www.acps.k12.va.us 19
Material Palette C
Dark Wood Veneer Grey Brick Blue Glazed Bricks Blue Metal Panel Aluminum Perforated Panel Architectural Concrete
Inspiration
Palette C is inspired by natural tones of the winter season. Please note that façade images on the following slides are not final and components of different palettes can be changed or incorporated into any palette.
www.acps.k12.va.us www.acps.k12.va.us 20
Material Palette C
View from Intersection of Yale Drive and Janneys Lane
www.acps.k12.va.us www.acps.k12.va.us 21
Material Palette C
View from Playing Field
www.acps.k12.va.us www.acps.k12.va.us 22
Material Palette Comparison
A
B
C
www.acps.k12.va.us
Superintendent School Board Cindy Anderson, Chair Veronica Nolan, Vice Chair
Meagan L. Alderton Ramee A. Gentry Jacinta Greene Margaret Lorber
Michelle Rief Christopher A. Suarez Heather Thornton
Dr. Gregory C. Hutchings, Jr.
23
Wait, We Have Questions For You!
1. What do you like about palette A?
2. What do you like about palette B?
3. What do you like about palette C?
4. If you have a preference, please rank the palettes.
Any additional comments are welcome. Please send responses to [email protected] by Wed., June 3, 2020 at 5 pm.