Department of TransportAnnual Report

2014-2015

Department of Transport Annual Report 2014-15

Page 2: DOT Annual Report 2015 · Web viewThe Annual Report has been prepared in accordance with the provisions of the Financial Management Act 2006 and fulfils the Department of Transport’s

Our PurposeWe provide and enable safe, accessible and efficient movement for the economic and social prosperity of Western Australia.

Our VisionTo have the best integrated and intelligent transport services and solutions for the State.

Our ValuesClear DirectionWe set clear direction and have the courage to follow  through.

Fresh ThinkingWe welcome fresh thinking and better ways of working.

Excellent ServiceWe work together to deliver excellent service.

Great peopleWe make things happen through our great people.

Department of Transport Annual Report 2014-15

Page 3: DOT Annual Report 2015 · Web viewThe Annual Report has been prepared in accordance with the provisions of the Financial Management Act 2006 and fulfils the Department of Transport’s

Statement of compliance with the Financial Management Act 2006For the year ended 30 June 2015

To the MinisterHon. Dean Nalder MLAMinister for Transport

In accordance with Section 63 of the Financial Management Act 2006, I hereby submit for your information and presentation to Parliament the Annual Report of the Department of Transport for the financial year ended 30 June 2015.

The Annual Report has been prepared in accordance with the provisions of the Financial Management Act 2006 and fulfils the Department of Transport’s reporting obligations under the Public Sector Management Act 1994, the Disability Services Act 1993 and the Electoral Act 1907.

Reece WaldockDirector General – Transport

Department of Transport Annual Report 2014-15

Page 4: DOT Annual Report 2015 · Web viewThe Annual Report has been prepared in accordance with the provisions of the Financial Management Act 2006 and fulfils the Department of Transport’s

OVERVIEWDIRECTOR GENERAL’S FOREWORDAs Western Australia’s population continues to grow, so too does the importance of moving our people and goods in the safest, most accessible and efficient way. This not only protects and enhances our lifestyle but secures the economic future of the State and the Department of Transport (DoT) is committed to achieving both.

What is now more clear than ever is that we can’t do it alone. We must work with our portfolio partners, the Public Transport Authority and Main Roads WA, to better integrate and optimise our network, invest in infrastructure and plan and prioritise for the future.

When I reflect on what we have accomplished in 2014-15, I am proud to say we have made strong progress in each of these areas that will ultimately deliver a smarter transport system for our growing community.

DoT continued to lead the way in transport planning, commencing drafting of the Perth Transport Plan for 3.5 million People and Beyond. The plan complements the Western Australian Planning Commission’s Perth and Peel @ 3.5 million suite of strategic documents and will look at options for demand management, mass transit, roads, river crossings, cycling and future technologies.

This long-term vision for Perth’s transport network will be complemented by the Perth Central Area Transport Plan 2025, which outlines a 10-year strategy for the CBD and surrounding key destinations and activity centres.

I am pleased with the direction that these crucial cross-portfolio plans are taking and look forward to finalising them both in 2016.

In the meantime, a number of key infrastructure projects focused on connecting people and places continued across the portfolio in 2014-15, with the $221 million Butler Line extension completed in September 2014 and procurement for the $2 billion Forrestfield-Airport Link commenced. Further, $88.1 million from the Perth Parking Licensing Account was invested back into CBD transport initiatives aimed at improving traffic flow.

Improvements to cycling infrastructure around the State were completed through the ongoing expansion of the cycling network and a range of projects funded through the Perth and Regional Bicycle Network grants programs. DoT continued to oversee these and other initiatives throughout the year as part of the implementation of the Western Australian Bicycle Network (WABN) Plan 2014-2031.WA’s first State Aviation Strategy was released in February 2015 following extensive stakeholder and community input. The strategy, which DoT will now turn its attention to implementing, supports the economic and social development of WA through the provision of safe, affordable, efficient and effective aviation services and infrastructure.

As well as looking at the way we move people, DoT worked towards finalising the Perth Freight Transport Network Plan and continued to oversee the implementation of the Western Australian Regional Freight Transport Network Plan. These plans ensure our metropolitan and regional transport networks continue to perform effectively as our freight task increases and lead the way for investment in major projects including Gateway WA, NorthLink WA and Perth Freight Link. Together, the $3.7 billion trio will create a seamless transport freight link from Muchea to Fremantle, cementing Perth’s freight corridors as some of the most productive and efficient in Australia.

Department of Transport Annual Report 2014-15

Page 5: DOT Annual Report 2015 · Web viewThe Annual Report has been prepared in accordance with the provisions of the Financial Management Act 2006 and fulfils the Department of Transport’s

Another area where I believe DoT is setting the standard is in the planning and delivery of coastal infrastructure. This was highlighted in 2014-15 with the successful completion of the Augusta Boat Harbour and Port Geographe coastal reconfiguration in October 2014 and May 2015 respectively. The Augusta facility is truly world-class and as well as providing a welcome safe-haven for vessels, it opens up important commercial and tourism opportunities for the growing South West region.

Safety on and around our waterways is paramount and I am pleased to see WA’s boating community embracing this message that DoT works so hard to promote through its ongoing education and compliance activities.

As regulators of WA’s on-demand transport industry, balancing the needs and expectations of both passengers, drivers and operators is an ongoing challenge – one that I believe we responded to proactively throughout the year. Our trial of purpose built taxis continued with great success and we are on track to start transitioning taxi drivers to a state-wide occupational licensing framework designed to improve service standards and security for passengers in early 2016.

Most significantly, DoT finalised a Green Paper in June 2015 outlining concepts for industry reform. The Green Paper seeks to promote discussion around areas of policy reform that will best deliver a safe, more flexible, responsible and innovative customer service-focused on-demand transport industry.

Customer service is key in everything we do and I am pleased to see this positively reflected in our Driver and Vehicle Services (DVS) 2015 Customer Perception Survey. The results showed improvement across all service delivery channels including metropolitan DVS and vehicle examination centres, regional offices, our Customer Contact Centre and website.

Our Mirrabooka DVS Centre opened in September 2014 to meet growing demand in the north-eastern suburbs, while in regional WA our successful Remote Areas Licensing Program expanded to service the Mid West.

With demand for our full complement of transport services growing state-wide, DoT established three new regions – Northern, Southern and Central – led by Regional Directors to enhance strategic oversight of planning and service delivery across WA. This approach has already improved local decision-making and I am confident it will continue to improve operational and strategic transport outcomes in our regions in the future.

As we look to the future, we do so not only as a unified DoT committed to our customers and the community, but as a unified Transport portfolio. Together, we will continue to strive to deliver the best integrated and intelligent transport services for the State.

Reece WaldockDirector General – Transport

Department of Transport Annual Report 2014-15

Page 6: DOT Annual Report 2015 · Web viewThe Annual Report has been prepared in accordance with the provisions of the Financial Management Act 2006 and fulfils the Department of Transport’s

HIGHLIGHTSState-wide occupational licensing framework for taxi drivers a step closer with Taxi Drivers Licensing Act 2014 passed by State Government.

Green Paper outlining concepts for on-demand transport industry reform finalised.$36.5 million Augusta Boat Harbour completed in October 2014.

$28.1 million Port Geographe coastal reconfiguration completed.

Mirrabooka Driver and Vehicle Services Centre offered new standard in service for customers.

89% of customers rated their overall experience at a Driver and Vehicle Services Centre as excellent or good.

Success of Your Move Cockburn program recognised with Institute of Public Administration Australia WA Achievement Award.

$88.1 million invested back into CBD transport initiatives from the Perth Parking Licensing Account.

WA’s first State Aviation Strategy released.

Four new regionally-focused port authorities commenced operation.

Financial SummaryDoT provides services to a range of customers and stakeholders, aggregated into the following high-level service categories:

Transport system and services development, planning, operation and regulation;

Motor vehicle and driver licensing services; and

Strategic transport policy and integrated planning integrated transport planning.

Gross expenses in 2014-15 totalled $365.96 million and the net cost of services, which takes into account operating revenue, was $32.61 million. The following charts illustrate gross expenses by service and expense categories.

DoT generates income from operating activities primarily in the areas of driver and vehicle services, management of coastal facilities, marine safety, parking levies in the Perth CBD and regulation of the on-demand transport industry. In 2014-15, DoT also retained Motor Vehicle Recording and Motor Driver Licence Fees as controlled income, resulting in an increase over 2013-14 income.

DoT managed a diverse physical asset base totalling $472.72 million to deliver its services. The chart below shows the distribution by asset  class.

DoT’s equity at 30 June 2015 was $709.69 million.

DoT also administers functions where the revenue is taken directly to the Consolidated Fund or to other Government agencies. Total administered revenue from these functions totalled $1.94 billion in 2014-15, as illustrated below.

Department of Transport Annual Report 2014-15

Page 7: DOT Annual Report 2015 · Web viewThe Annual Report has been prepared in accordance with the provisions of the Financial Management Act 2006 and fulfils the Department of Transport’s

OPERATIONAL STRUCTUREThe Transport portfolioDoT is a key agency in the State Government’s Transport portfolio, integrating and enhancing coordination of the State’s transport operations, regulatory functions and planning and policy development processes.

Throughout 2014-15, Reece Waldock concurrently held the positions of Director General of the Department of Transport, Chief Executive Officer of the Public Transport Authority and Commissioner of Main Roads WA.

The structure of the Transport portfolio is outlined in the Organisational Chart on page 17.

The Department of TransportDoT delivers its services through two divisions – Policy, Planning and Investment; and Transport Services.

Policy, Planning and Investment provides strategic transport policy, integrated transport planning solutions and coordinated investment decisions in collaboration with key stakeholders, to assist in the development of a safe and sustainable transport system for the movement of people and freight.

Transport Services leads and manages the state-wide delivery of a number of specialist transport services, including driver and vehicle services, coastal infrastructure and marine and rail safety, while also regulating WA’s on-demand transport industry.

The core functions of each directorate that make up these divisions are outlined in the Organisational Chart on page 17.

Changes to the Department in 2014-15DoT renamed and restructured its former Transport Policy and Systems Directorate in 2014-15. The new Transport Strategy and Reform Directorate, which operates within DoT’s Policy, Planning and Investment Division, is focused on aviation policy and programs, congestion mitigation, freight efficiency and strategic transport analysis and reform. The Directorate’s renewed strategic direction allows DoT to better meet the evolving transport needs of its customers and stakeholders.

DoT also established a new Business Information Systems Directorate within its Transport Services Division. The Directorate, scheduled to officially commence operations in August 2015, recognises the important role IT plays in delivering services to our customers and will ensure a coordinated, strategic and customer-focused approach to this.

Enabling legislationDoT was established on 1 July 2009, under the Public Sector Management Act 1994.

Responsible MinisterHon. Dean Nalder MLA, Minister for Transport.

Department of Transport Annual Report 2014-15

Page 8: DOT Annual Report 2015 · Web viewThe Annual Report has been prepared in accordance with the provisions of the Financial Management Act 2006 and fulfils the Department of Transport’s

Organisational structureTransport portfolio organisational chart

Department of Transport organisational chart

Department of Transport Annual Report 2014-15

Page 9: DOT Annual Report 2015 · Web viewThe Annual Report has been prepared in accordance with the provisions of the Financial Management Act 2006 and fulfils the Department of Transport’s

Corporate ExecutiveReece Waldock Director General – Transport As the head of the Transport portfolio, Reece is responsible for setting the strategic direction of transport in the State, shaping the development of a number of major integrated transport plans and leading the implementation of some of WA’s most transformational capital projects.

With more than 35 years’ experience in strategic management, with particular expertise in organisational reform, his appointment as Director General – Transport in 2010 was the culmination of a 20-year journey within various State Government transport agencies including 14 years as a Chief Executive Officer. Prior to his public sector career, Reece held a number of senior management roles with BHP Pty Ltd.

Reece is also a Commissioner of the Western Australian Planning Commission, Lifeline WA board member and a Director of the Australian Urban Design Research Centre.

Graeme Doyle Managing Director – Policy, Planning and Investment Graeme was appointed as Managing Director – Policy, Planning and Investment in April 2015. He brings a wealth of knowledge to the role with 35  years of experience in the public sector and has been a valuable member of DoT’s Corporate Executive for almost five years in his previous capacity as Executive Director – Investment and Finance Coordination.

Graeme and his expert team provide policy advice, strategic transport solutions and coordinated investment decisions to State Government to assist in effective movement of people and goods. In doing so, Graeme ensures strong collaboration across the Transport portfolio for a unified approach to planning and delivering WA’s transport services, infrastructure and systems.

Nina Lyhne Managing Director – Transport ServicesNina joined DoT in January 2011 as the Managing Director – Transport Services. Nina holds a Bachelor of Arts degree in Psychology and has previously held the positions of WorkSafe Western Australia Commissioner and the Executive Director of the Office of Road Safety. Nina has worked in diverse roles across government agencies in sectors ranging from trade and commerce to community development and occupational safety and health.

In her key role with DoT, Nina is responsible for the delivery of a wide range of transport services including driver and vehicle services, coastal infrastructure, marine and rail safety and on-demand transport. She also oversees the provision of information technology, people and corporate services for DoT.

Kate Wang Director – Office of the Director General Kate joined DoT as Director – Office of the Director General in October 2014. In this strategically focused role, Kate leads the communications, Ministerial liaison and governance activities of the Department while ensuring strong coordination of these functions across the Transport portfolio.

Kate has more than 20 years of State Government experience, having worked in policy and project roles for a range of agencies and Ministerial offices across the portfolios of Commerce, Education and most recently Transport.

Department of Transport Annual Report 2014-15

Page 10: DOT Annual Report 2015 · Web viewThe Annual Report has been prepared in accordance with the provisions of the Financial Management Act 2006 and fulfils the Department of Transport’s

As Principal Policy Advisor to the Minister for Transport for some five years, she has a thorough understanding of the challenges and opportunities facing DoT and its portfolio partners. This background, together with a Masters of Business Administration in International Business, enables Kate to effectively lead the business and strategic planning for the DoT and the Transport portfolio and facilitate the progression of key priorities on behalf of the Director General.

Kate is an Alumna of Leadership Western Australia.

Fiona Knobel Executive Director – People and Organisational DevelopmentFiona joined DoT as the Executive Director – People and Organisational Development in July 2011. She has more than 20 years’ experience in a range of human resources, change management and organisational development roles in both the public and private sectors.

Her expertise in aligning the people, performance and culture of organisations with financial and non-financial business results is well supported by a Master of Business degree and a Graduate Diploma from the Australian Institute of Company Directors.

In her role with DoT, Fiona leads the people and organisational development strategies that enable DoT to achieve its vision, mission and desired culture.

Dennis O’Reilly Executive Director – Corporate ServicesA public servant for over 20 years, Dennis returned to DoT as the Executive Director – Corporate Services in February 2012, following more than six years leading MRWA’s customer service transformation. Prior to his time at MRWA, Dennis headed up DoT’s Regional Services Business Unit.

In his current role, Dennis builds internal partnerships to provide quality services in the areas of accommodation and buildings, procurement and fleet, strategic information and technology, information and records management, as well as legal and legislative services.

During his time with Corporate Services, Dennis has provided his team with a clear focus in respect to customer service, relationship-building, business improvement and innovation, and governance and accountability.

Dennis has overseen the implementation of a significant reform agenda over the last 12 months, resulting in Corporate Services’ partnering with business units to provide ‘best for business’ outcomes.

Kathryn Martin Acting Executive Director – Investment and Finance CoordinationKathryn was appointed Acting Executive Director – Investment and Finance Coordination in April 2014.

Kathryn has almost 20 years of experience as a transport economist, successfully undertaking the position of Director Portfolio Investment Coordination at DoT for the past five years and prior to this held a range of other senior investment and asset management planning roles at Main Roads WA and Austroads.

As Acting Executive Director, Kathryn leads the development of Transport portfolio investment programs and strategies to ensure the State’s transport solutions deliver the maximum benefit to the WA community. She is also responsible for the overall financial management of DoT including accounting functions, resource allocation, budget performance and risk management.

Department of Transport Annual Report 2014-15

Page 11: DOT Annual Report 2015 · Web viewThe Annual Report has been prepared in accordance with the provisions of the Financial Management Act 2006 and fulfils the Department of Transport’s

Ann King General Manager – Driver and Vehicle ServicesAnn joined DoT as General Manager – Driver and Vehicle Services in January 2015. In her dynamic, customer-focussed role, she is responsible for overseeing all aspects of driver and vehicle licensing in WA to ensure DoT achieves its outcomes of safe drivers, safe vehicles, secure identities and excellence in service.

Ann has experience in both the public and private sectors including expertise in registration and licensing services from her time at NSW Roads and Maritime Services. This experience, together with her extensive strategic policy and planning background and commitment to excellent service and new technologies, mean she is well-placed to lead the delivery of driver and vehicle services state-wide.

In doing this, she balances the needs of DoT’s customers and a strong focus on education and compliance, providing service outcomes that deliver value for money for the WA community.

Ann values her team and is committed to creating a positive culture through collaborative relationships.

Christian Thompson Executive Director – Business Information SystemsChristian commenced as Executive Director – Business Information Systems in April  2015. In this newly created role, Christian provides strategic direction for the development and support of information technology across DoT.

His expertise in leading high-performing, innovative technology teams ensures the smooth delivery of IT services both internally and externally, as DoT continues to improve its online service delivery to meet the growing needs of our customers.

Christian is qualified in geology and IT and has more than 30  years of experience in the latter. He has worked in various IT roles within the mining industry including General Manager of Shared Business Services for Rio Tinto and Chief Information Officer for iron ore junior Citic Pacific Mining.

Department of Transport Annual Report 2014-15

Page 12: DOT Annual Report 2015 · Web viewThe Annual Report has been prepared in accordance with the provisions of the Financial Management Act 2006 and fulfils the Department of Transport’s

Administered legislationOn behalf of the Minister for Transport, DoT administers the following Acts:

Air Navigation Act 1937

Civil Aviation (Carriers’ Liability) Act 1961

Damage by Aircraft Act 1964

Harbours and Jetties Act 1928

Jetties Act 1926

Lights (Navigation Protection) Act 1938

Marine and Harbours Act 1981

Marine Navigational Aids Act 1973

Maritime Fees and Charges (Taxing) Act 1999

Motor Vehicle Drivers Instructors Act 1963

Owner-Drivers (Contracts and Disputes) Act 2007

Perth Parking Management Act 1999

Perth Parking Management (Consequential Provisions) Act 1999

Perth Parking Management (Taxing) Act 1999

Pilots’ Limitation of Liability Act 1962

Pollution of Waters By Oil and Noxious Substances Act 1987

Port Authorities Act 1999

Rail Safety Act 2010

Railway Discontinuance Act 2006

Railway Discontinuance Act (No. 2) 2006

Railway (Butler to Brighton) Act 2010

Railway (Tilley to Karara) Act 2010

Road Traffic (Administration) Act 2008

Road Traffic (Authorisation to Drive) Act 2008

Road Traffic (Vehicles) Act 2012

Road Traffic (Vehicles) (Taxing) Act 2008

Sea-Carriage of Goods Act 1909

Shipping and Pilotage Act 1967

Taxi Act 1994

Trans-Continental Railway Act 1911

Transport Co-ordination Act 1966

Western Australian Marine Act 1982

Western Australian Marine (Sea Dumping) Act 1981

Wire and Wire Netting Act 1926

Western Australian Photo Card Act 2014

Department of Transport Annual Report 2014-15

Page 13: DOT Annual Report 2015 · Web viewThe Annual Report has been prepared in accordance with the provisions of the Financial Management Act 2006 and fulfils the Department of Transport’s

Other legislation affecting the functions and operation of DoT include:

State Records Act 2000

State Trading Concerns Act 1916

Criminal Code 1913

Electronic Transactions Act 2011

Evidence Act 1906

Financial Management Act 2006

Freedom of Information Act 1992

Limitation Act 2005

Public Sector Management Act 1994

Disability Services Act 1993

Equal Opportunity Act 1984

Industrial Relations Act 1979

Interpretation Act 1984

Library Board of Western Australia Act 1951

Minimum Conditions of Employment Act 1993

Native Title Act 1993 (Commonwealth)

Occupational Safety and Health Act 1984

Royal Commission (Custody of Records) Act 1992

State Supply Commission Act 1991

Taxi Driver Licensing Act 2014

Department of Transport Annual Report 2014-15

Page 14: DOT Annual Report 2015 · Web viewThe Annual Report has been prepared in accordance with the provisions of the Financial Management Act 2006 and fulfils the Department of Transport’s

PERFORMANCE MANAGEMENT FRAMEWORKOutcome-based management framework Under an outcome-based management framework, DoT contributes to two of the State Government’s strategic goals:

State Government strategic goals DoT outcomes DoT services

Results-based service delivery Greater focus on achieving results in key service delivery areas for the benefit of all Western Australians.

1. An accessible and safe transport system.

1. Transport system and services development, planning, operation and regulation.

2. Vehicles and road users that meet established vehicle standards and driver competencies to deliver safe vehicles and safe drivers.

2. Driver and vehicle services.

State building – major projects Building strategic infrastructure that will create jobs and underpin Western Australia’s long-term economic development.

3. Integrated transport systems that facilitate economic development.

3. Strategic transport policy and integrated planning.

Changes to outcome-based management framework There were no changes to the Outcome Based Management Framework in 2014-15.

Shared responsibilities with other agenciesSupporting a safe and efficient transport system in the Indian Ocean TerritoriesDoT supports the delivery of a safe, efficient, effective and equitable transport system in the Indian Ocean Territories (IOT) – consisting of Christmas Island and the Cocos (Keeling) Islands – through a Service Delivery Agreement with the Commonwealth Government.

The arrangement aims for the IOT to achieve consistency, as far as practicable, with WA’s transport system through DoT providing advice, services and support as requested by the Commonwealth Government.

In June 2015, DoT officers visited the IOT to meet with key stakeholders on various operational matters relating to the Service Delivery Agreement. These matters included providing advice and support to assist in the delivery of driver and vehicle services – particularly practical driving assessments, examining and gaining an overview of the port, stevedoring and shipping piloting operations, and other compliance services.

Throughout the year, DoT continued to meet regularly with Commonwealth Government officers to ensure an open dialogue and discuss any issues relating to management of the agreement. As a result, DoT received positive feedback from the Commonwealth Government on the level of advice and support provided.

DoT and the Commonwealth Government are currently negotiating to finalise a new Service

Department of Transport Annual Report 2014-15

Page 15: DOT Annual Report 2015 · Web viewThe Annual Report has been prepared in accordance with the provisions of the Financial Management Act 2006 and fulfils the Department of Transport’s

Delivery Agreement and this is anticipated to be in place in July 2015.

Moving people and freightDoT works closely with portfolio partners the PTA and MRWA, as well as local, State and Commonwealth government agencies and private sector organisations on a range of integrated transport policy, planning, regulation, investment coordination and service delivery projects aimed at the safe and sustainable movement of people and freight.

DoT also works closely with WA’s five port authorities, providing leadership in developing investment programs and strategies, supporting reforms and initiatives, and assisting ports to facilitate trade through the development of ports strategies.

The scope and status of these projects is detailed in the Report on Operations.

Providing a shared IT serviceIn 2014-15, DoT continued to host and operate a shared IT infrastructure service for the Department of Planning. This arrangement is managed through Service Level Agreements and continues to realise economies of scale and cost neutrality for the State Government.

Enhancing compliance coordination on WA’s waterwaysDoT’s Marine Safety Business Unit works in collaboration with the Western Australia Police, Swan River Trust, Rottnest Island Authority, the Department of Fisheries and the Department of Parks and Wildlife to increase education, compliance and enforcement of the Marine Act 1982 and associated legislation on WA’s waterways.

This collaborative approach enhances coordination and avoids duplication of patrol efforts throughout the year. This has resulted in a significant increase in patrols, ensuring improved compliance with the Marine Act 1982 and Navigable Waters Regulations 1958 by the recreational boating community.

The business unit also works in partnership with the Australian Maritime Safety Authority to deliver the National System for Domestic Commercial Vessels which establishes a safety framework for commercial vessels and seafarers.

As the appointed Hazard Management Agent under the State Emergency Management Regulations 1986 for Maritime Transport Emergencies and Marine Oil Pollution Emergencies, the business unit also works in collaboration with the Australian Maritime Safety Authority, Port Authorities, Department of Fire and Emergency Services, Department of Environment, Department of Parks and Wildlife, Swan River Trust, Rottnest Island Authority, Western Australia Police to ensure adequate prevention, preparation, response and recovery strategies are in place for these emergencies.

Promoting cycle safetyIn September 2014, DoT and the Office of Road Safety launched a community safety education campaign aimed at cyclists, pedestrians and motorists to assist in addressing growing community concern for cyclist safety.

The joint campaign was designed to complement other initiatives to improve safety for vulnerable road users, reduce barriers to cycling participation and better leverage existing infrastructure assets. It was developed in consultation with cycling and motorist groups and rolled out in two stages.

Stage 1 ran between September and November 2014 and focused on motorists and cyclists sharing the road to encourage safer behaviour. Through a combination of radio advertising as well as advertising on buses and bus shelters, the campaign reached one in three Perth residents.

Department of Transport Annual Report 2014-15

Page 16: DOT Annual Report 2015 · Web viewThe Annual Report has been prepared in accordance with the provisions of the Financial Management Act 2006 and fulfils the Department of Transport’s

Stage 2 commenced in March 2015 to coincide with DoT’s Bikeweek and encouraged cyclists and pedestrians to share paths safely. Advertising in newspapers as well as on buses and bus shelters was complemented by over 330 signs on the Principal Shared Path network and a range of fact sheets, educational videos and online promotions employed to spread the safety message.

The campaign, which officially concluded in June 2015, contributed towards the State Government’s goals to create a safer road environment and increase cycling participation.

Department of Transport Annual Report 2014-15

Page 17: DOT Annual Report 2015 · Web viewThe Annual Report has been prepared in accordance with the provisions of the Financial Management Act 2006 and fulfils the Department of Transport’s

AGENCY PERFORMANCEReport on operationsDoT’s role in achieving government goalsDoT supported the State Government’s goals of ‘results-based service delivery’ and ‘State building – major projects’ in 2014-15 by striving to achieve and exceed three outcomes:

1.an accessible and safe transport system;

2.vehicles and road users that meet established vehicle standards and driver competencies to deliver safe vehicles and safe drivers; and

3.integrated transport systems that facilitate economic development.

To achieve these outcomes, DoT delivered three corresponding services:

1.transport system and services development, planning, operation and regulation;

2.driver and vehicle services; and

3.strategic transport policy and integrated planning.

DoT’s success in delivering these services and, in turn, achieving desired outcomes and contributing to State Government goals are measured through key performance indicators.

This report on operations summarises DoT’s key performance indicators and details projects and programs that have significantly contributed to service delivery designed to meet the three outcomes.

Outcome one: An accessible and safe transport system

Key effectiveness indicators

2014-15 target

2014-15 actual

Reasons for significant variance

Percentage of standard metropolitan (non multi-purpose) taxi jobs which were not covered – peak

1% 1.70% In a period of softening demand for taxi services there has been an improvement in the number of taxi jobs which were not covered during peak period from 2.58% in 2013-14 to 1.70% in 2014-15.While performance against index has improved, the 2014-15 Budget Target was not met.

Percentage of standard metropolitan (non multi-purpose) taxi jobs which were not covered – off peak

0.5% 0.59% In a period of softening demand for taxi services there has been an improvement in the number of taxi jobs which were not covered during off-peak period from 0.88% in 2013-14 to 0.59% in 2014-15.While performance against index has improved, the 2014-15 Budget Target was not met.

Percentage by which the waiting time standard for metropolitan area taxis is met

91% 92%

No significant variance noted this year between target and actual.

Percentage of time 99.71% 99.40%

Department of Transport Annual Report 2014-15

Page 18: DOT Annual Report 2015 · Web viewThe Annual Report has been prepared in accordance with the provisions of the Financial Management Act 2006 and fulfils the Department of Transport’s

maritime infrastructure is fit for purpose when required

No significant variance noted this year between target and actual.

Percentage of regional airports receiving scheduled regular public transport (RPT) air services

100% 96%

No significant variance noted this year between target and actual.

Rate of reported incidents (accidents) on the water per 100 commercial vessels surveyed

5.58 5.44

No significant variance noted this year between target and actual.

Rate of reported incidents (accidents) on the water per 10,000 registered recreational vessels

9.5 10.96 The slowdown in the WA economy has reduced the anticipated number of recreational vessels being registered. There has also been an increase in the number of incidents reported due largely to the change in reporting requirements of marine insurance industry.The industry now only accepts claims made by clients only where the incident has been reported to DoT.

Number of serious rail accidents per million train kilometres

1.55 0.83 There has been a reduction in the number of incidents and an increase of ‘train kilometres’ travelled.The reduction in the rate of incidents indicates that the safety outcome is being met by rail transport operators.

Service one: Transport system and services development, planning, operation and regulation

Key effectiveness indicators

2014-15 target

2014-15 actual

Reasons for significant variance

Cost of regulation per taxi plate administered

$3,207.63 $3,478.72 Taxi plate release slowed in response to softening in demand for taxi services.The number of taxi plates regulated did not increase at the rate initially anticipated, resulting in an increased cost of regulation per taxi plate administered.

Average cost per day per maritime infrastructure asset managed

$70.24 $74.90 The total cost to manage maritime infrastructure assets exceeded the 2014-15 published budget by $4.27 million.Additional funds of $1.75 million were spent to address channel dredging and sand bypassing to maintain safety navigation in various locations

Department of Transport Annual Report 2014-15

Page 19: DOT Annual Report 2015 · Web viewThe Annual Report has been prepared in accordance with the provisions of the Financial Management Act 2006 and fulfils the Department of Transport’s

across the State.Depreciation expenses were over-budget by $2.25 million primarily due to DoT taking over the Two Rocks Marina facility.

Average survey cost per commercial vessel

$2,807.79 $3,383.72 The application of the National Law in July 2013 resulted in a change of definition in what constituted a survey vessel under the previous Western Australian Law.This variation meant that some vessels previously requiring survey are now survey exempt under the National Law and can now be surveyed anywhere in Australia regardless of the area of operation.In addition, a decrease in volumes can be attributed to a demobilisation of vessels involved in major resource construction projects in the North West and a continued reduction in the commercial fishing vessel fleet around the State.

Average cost per private recreational vessel registration

$100.11 $102.74

No significant variance noted this year between target and actual.

Cost to maintain marine pollution response preparedness per registered vessel

$19.65 $17.64 The actual cost is lower than the target due to vacancies not filled during periods in 2014-15.

Average cost per household contacted under the ‘TravelSmart’ scheme

$144.47 $126.63 An additional 259 households above forecast were recruited into the program by 30 June 2015.The program was delivered with reduced resources following a review of DoT’s Transport Strategy and Reform Directorate.

DoT plans, develops, operates and regulates a diverse range of transport systems and services to facilitate an accessible and safe transport system for all Western Australians.

In 2014-15, DoT focused on the following key areas:

regulating WA’s on-demand transport industry, which includes taxi and omnibus drivers and vehicles;

regulating WA’s intrastate air services;

planning and developing enhanced maritime infrastructure;

keeping people safe on and around WA’s waterways; and

encouraging people to change their travel behaviour to more active transport modes such as walking, cycling or public transport.

Following are some of the key initiatives and services delivered by DoT in 2014-15 to provide Western Australians with accessible and safe transport systems.

Department of Transport Annual Report 2014-15

Page 20: DOT Annual Report 2015 · Web viewThe Annual Report has been prepared in accordance with the provisions of the Financial Management Act 2006 and fulfils the Department of Transport’s

High-use taxi ranks upgradedDoT continued to work with CBD Taxi Rank Reference Group partners – the City of Perth, the Taxi Council of Western Australia and the Taxi Industry Forum of Western Australia – to implement the CBD Taxi Rank Strategy. The strategy is focused on developing visible, accessible and safe taxi ranks that meet short, medium and long-term transport needs in the Perth CBD.

Under the strategy, all eight medium-to-high use taxi ranks in the CBD were upgraded in 2014-15. Following a successful pilot program, multi-function poles that greatly enhance the visibility and usability of the ranks with night-time illuminations, street maps indicating the location of the rank and a flashing LED sign to assist passengers to hail a taxi were installed. Additional street lighting and CCTV cameras were also installed to enhance safety and security for both passengers and drivers.

In 2015-16, DoT will continue to work with the CBD Taxi Rank Reference Group to develop the technical guidelines for the design and location of future taxi ranks.

Taxi driver licensing legislation introducedThe Taxi Drivers Licensing Act 2014 (the Act) received Royal Assent in July 2014, providing a state-wide occupational licensing framework for taxi drivers in a single piece of legislation.

Designed to improve service standards and security for passengers, key features of the framework include a penalty point system for certain breaches of the regulations and the Code of Conduct, mandatory disqualification for serious offences, and new laws to cancel licences for serious or persistent breaches. The Act also provides more scope for additional driver training and a more secure system of taxi driver identification.

During 2014-15, DoT completed the design of the regulatory framework and administrative systems to support the implementation of the Act once the regulations are proclaimed. The simpler, more user-friendly systems will automate a range of administrative processes, saving significant time and reducing the opportunity for human error. Further, the DoTDirect suite of online tools will be enhanced to enable taxi drivers to administer their taxi driver licence online.

Successful trial of purpose-built taxisDoT’s four-year trial of purpose-built taxis (PBTs) continued in 2014-15, with 99 London Taxi Company TX4 taxis now participating.

The trial aims to improve the safety, standards and accessibility of Perth taxis. DoT is collecting feedback from passengers, drivers and operators in order to evaluate the advantages of the PBTs when compared to standard taxis.

To date, more than 700 passengers have been surveyed and over 90 per cent of respondents have indicated that they would prefer a PBT over a standard taxi.

Over the last 12 months, DoT worked closely with trial stakeholders to identify and implement improvements to the TX4 vehicles in order to better meet the needs of PBT operators and passengers.

A small-scale pilot is also under way to assess the TX4’s suitability to carry passengers in wheelchairs. The pilot, developed in consultation with the Disability Services Commission and the Insurance Commission of Western Australia, involves a small number of PBTs and passengers in wheelchairs who regularly use taxis. As part of the pilot, DoT appointed National Disability Services (NDS) to develop safe practice guidelines for participants and to develop and deliver training to PBT drivers.

Department of Transport Annual Report 2014-15

Page 21: DOT Annual Report 2015 · Web viewThe Annual Report has been prepared in accordance with the provisions of the Financial Management Act 2006 and fulfils the Department of Transport’s

It is anticipated that the pilot will conclude in August 2015. NDS will then prepare a report on the outcomes of the pilot and provide advice on the suitability and limitations of the TX4 as a wheelchair-accessible vehicle.

On-demand transport Green Paper finalisedChanging consumer expectations, emerging technologies, new market entrants and economic factors continue to place pressure on WA’s on-demand transport industry to evolve.

In early 2015, the State Government announced that a Green Paper outlining concepts for industry reform was being developed. The Green Paper, finalised by DoT in late June 2015, seeks to promote discussion around areas of policy reform that will best deliver a safe, more flexible, responsible and innovative customer service-focused on-demand transport industry.

It is anticipated that the Green Paper will be released for public comment in July 2015. DoT will then consider the submissions received before providing recommendations to the State Government. While this is an important first step in reforming on-demand transport services and laws in WA, any changes to the regulatory model will be incremental.

More flexible on-demand transport options deliveredDoT continued to work with the community and industry to deliver more flexible on-demand transport services in 2014-15.

In December 2014, a trial of a hybrid taxi–charter–omnibus service commenced in Jurien Bay where traditional taxi services have been found to be unviable. The trial allows operators to negotiate a pre-agreed fare with the passenger, rather than using a regulated fare structure. This enables cost-effective on-demand transport services for passengers.

Feedback from both operators and the Shire of Dandaragan has been positive and DoT will continue to monitor the trial’s success and evaluate whether similar services could be implemented in other population centres where traditional taxi services are unsustainable.

DoT also issued interim approval for two new taxi dispatch services, Ingogo and WA Cabs, to operate in the Perth Taxi Control Area. The interim approval will enable DoT to analyse their respective dispatch systems in order to inform a decision as to whether they meet the requirements for full registration as a taxi dispatch service.

Regulated regular public transport air routes review completedIn 2014-15, DoT completed its Review of Regulated Regular Public Transport (RPT) Air Routes in Western Australia. As part of the review, a position paper proposing the future approach for eight currently protected RPT air routes was released for public comment in July 2014. These routes connect Perth with the following regional locations:

1. Albany; 2. Carnarvon–Monkey Mia (Shark Bay); 3. Derby;4. Esperance;5. Laverton–Leonora;6. Learmonth (Exmouth); 7. Leinster–Wiluna; and8. Mount Magnet–Meekatharra.

Department of Transport Annual Report 2014-15

Page 22: DOT Annual Report 2015 · Web viewThe Annual Report has been prepared in accordance with the provisions of the Financial Management Act 2006 and fulfils the Department of Transport’s

The position paper also proposed amendments to DoT’s policy for charter air services on RPT routes. The policy is designed to ensure that charter air services do not impact on the viability of RPT air services in WA as a matter of public interest, while also seeking to accommodate the needs of mining companies.

A total of 43 submissions were received during the three-month public comment period. DoT used this feedback, together with the findings of extensive stakeholder and community consultation undertaken over the last two years, to prepare a final report outlining the future regulatory approach to be taken for consideration by State Government.

The final report took into consideration feedback collected through the submissions, regional workshops, biannual Aviation Community Consultation Group meetings for each route and one-on-one meetings with stakeholder organisations. In addition, it was informed by the statistics that provided a demand profile for each route with regard to the unique social and economic context of each community.

The final report has been released and DoT will now undertake a competitive tender process for the provision of RPT air services for all routes that will continue to be regulated beyond February 2016 when the existing agreements expire.

Augusta Boat Harbour completed on scheduleWorks on the Royalties for Regions-funded $36.47  million Augusta Boat Harbour were completed on schedule in October 2014. The world-class facility, officially opened in November 2014, now provides a welcome safe-haven for vessels navigating the rugged coastline between Albany and Busselton, as well as important commercial and tourism opportunities for the growing South West region.

The harbour features a four-lane boat launching facility for easy and safe access to the water; a service wharf to allow larger commercial vessels to safely and efficiently transfer passengers and products; 40 boat pens for commercial and recreational vessels; and car and trailer parking for more than 200 vehicles.

Its award-winning breakwaters provide locals and visitors with a unique ocean walk and an excellent base for recreational fishing and diving. They can also enjoy the ambience of the harbour, purchase fresh seafood direct from local operators and picnic in the landscaped plaza area. This vibrant experience will be further enhanced in the future with four fully-serviced lots available for retai development.

Based on the positive feedback received from stakeholders, commercial operators, recreational boating users, residents and tourists, DoT is confident that the harbour will continue to be embraced by all.

Port Geographe coastal reconfiguration completed The $28.15 million project to reconfigure the coastal structures at Port Geographe was successfully completed and officially opened in May 2015.

The original coastal structures, built as part of a private development in the 1990s, caused serious seagrass wrack accumulation on the western side of the development and amplified coastal erosion on the adjacent eastern coast. Extensive community consultation and scientific research confirmed a complete reconfiguration was required to address environmental and health issues.

DoT managed and delivered the long-awaited project in three stages, with construction commencing in September 2013. With the main component of the project – the construction of the reconfigured breakwaters – completed in June 2014, works throughout 2014-15 included dredging, and beach works and landscaping to transform the foreshore into an attractive and inviting recreational space.

Department of Transport Annual Report 2014-15

Page 23: DOT Annual Report 2015 · Web viewThe Annual Report has been prepared in accordance with the provisions of the Financial Management Act 2006 and fulfils the Department of Transport’s

Sand and seagrass are now able to bypass the new coastal structures naturally. This has resulted in reduced seagrass accumulation, and beach erosion at Port Geographe is now at levels consistent with other coastal areas along Geographe Bay. In addition to delivering significant environmental benefits, amenity and access to beaches for local residents and the wider community has been improved. Further, the reconfiguration is expected to reduce ongoing annual coastal maintenance costs at the site.

Exmouth Boat Harbour upgrade commencedIn 2014-15, DoT secured $18.27 million in Royalties for Regions funding for Stage 2 of the Exmouth Boat Harbour upgrade.

Following extensive consultation with users, the preliminary design was completed in March 2015 and the detailed design is nearing completion.

As part of the project, the existing wharf will be extended and a heavy lift facility will be built to provide better access for loading and unloading vessels. To make way for the extension, existing trawler pens will be relocated. The upgrade will also include additional cyclone moorings, augmenting the 25 floating pens that were delivered in Stage 1.

This expanded infrastructure will support local businesses and industries supporting the fishing, charter and resource sectors. It will also deliver economic and community benefits for Exmouth and the Gascoyne region.

On-site works are expected to commence in late 2015 with relocation of the fuel farm and other services within the harbour. Following this, the main construction package will be delivered over 2015-16 and 2016-17, with the project anticipated to be completed in March 2017.

Fremantle Fishing Boat Harbour Jetty 2 replacement commencedDetailed design work to replace Jetty 2 at the Fremantle Fishing Boat Harbour with modern floating pontoon systems was completed in 2014-15.

The $3.9 million redevelopment project will deliver 56 boat pens (ranging from 15 to 20 m) and will provide a higher level of safety and improved level of service for boat harbour users.

Staged demolition of the existing jetty, which was built in the 1960s, commenced in June 2015 and construction of the new jetty is anticipated to be completed in April 2016.

Grants for the Recreational Boating Facilities Scheme administeredDoT administers the Recreational Boating Facilities Scheme (RBFS) on behalf of the State Government. The aim of the scheme is to improve recreational boating infrastructure by providing grants to eligible authorities around the State.

The RBFS is funded directly from recreational boat registration fees and was supplemented by Royalties for Regions funding during grant rounds 16 to 20. Since 1998, the RBFS has allocated almost $42 million for 395 projects located from Wyndham in the north to Esperance in the south.

Examples of projects completed in 2014-15 include:

remediation of the groyne at the Back Beach boat launching facility in Karratha;

construction of a new boat launching facility at Illyarrie Street in Leeman;

upgrades to the Dampier public boat ramp facility;

installation of two new floating jetties at Riverside Gardens and Tranby House in Bayswater;

upgrades to the Sykes Foreshore boat ramp facility in Bunbury; and

Department of Transport Annual Report 2014-15

Page 24: DOT Annual Report 2015 · Web viewThe Annual Report has been prepared in accordance with the provisions of the Financial Management Act 2006 and fulfils the Department of Transport’s

extension of the trailer parking area and provision of ablution facilities at the Windy Harbour boat ramp south of Northcliffe.

In April 2015, nearly $5.5 million worth of round 20  RBFS grants for 28 projects throughout WA were announced and will be undertaken over the next two years.

Coastal Adaptation and Protection grants program administered The Coastal Adaptation and Protection grants program, administered by DoT, is designed to preserve and enhance the Western Australian coastline by funding works that assist coastal managers to sustainably adapt to hazards.

Since 2005, approximately $10 million has been allocated to 142 projects from Port Hedland in the north to Esperance in the south.

Examples of projects completed in 2014-15 include:

refurbishment of rock groynes at Abbey foreshore in Busselton;

stabilisation of the foreshore at Locke Estate in Busselton;

beach monitoring, data collection and numerical modelling to develop long-term coastal management options for Quinns Beach in Quinns Rocks;

sand nourishment at Esperance Bay; and

Stage 2 City Beach groyne maintenance.

More than $1 million will be allocated to coastal protection projects across WA in the 2015-16 funding round.

New navigational aids installed at Esperance and Kalbarri In 2014-15, DoT installed navigational aids in Esperance and Kalbarri to improve water safety for all users.

In Esperance, new navigational aids were installed around Cook Rock, Wylie Head and at Town Beach boat ramp in October 2014. The aids, which assist in safe vessel movement, address community concerns raised during DoT’s aquatic use review of the area.

In February 2015, additional aids were installed at the mouth of the Murchison River in Kalbarri. As the site is recognised as one of the most challenging areas for boating in the State, DoT worked closely with local fishermen and the Volunteer Marine Rescue Group to determine the location for the markers, which now clearly indicate the preferred channel to transit the river mouth.

In addition to the new navigational aids, DoT also released updated boating guides for both Esperance and Kalbarri, highlighting the new markers and other important information for skippers. Both the aids and the boating guides were well-received by the community and DoT plans to replicate this success with the installation of additional markers and upgrades to existing markers at Rottnest Island and Garden Island in 2015-16.

200,000th Recreational Skipper’s Ticket issuedIn July 2014, DoT issued WA’s 200,000th Recreational Skipper’s Ticket (RST) – a nationally-recognised certificate of competency designed to ensure skippers possess the minimum knowledge and practical skills needed to safely operate a powerboat on the water.

DoT actively encourages the take-up of RSTs in WA through ongoing community education programs, including the ‘You’re the skipper, you’re responsible’ message. This message has been enthusiastically embraced by the boating community, resulting in a ratio of approximately two RST holders for every registered recreational vessel in the State. Throughout 2015-16, DoT will continue to promote the safe and sustainable use of the State’s waterways by encouraging more Western Australians to obtain an RST.

Department of Transport Annual Report 2014-15

Page 25: DOT Annual Report 2015 · Web viewThe Annual Report has been prepared in accordance with the provisions of the Financial Management Act 2006 and fulfils the Department of Transport’s

More accurate and up-to-date information for mariners providedDoT updates and distributes nautical charts and notices to mariners online to provide seafarers with safety and navigational information. In 2014-15, the website applications through which these charts and notices are made available were upgraded to enable data to be sourced directly from the tools that DoT’s cartographers and geospatial scientists use. The upgrade has delivered more accurate and up-to-date information to customers, while also improving efficiency and reducing system maintenance costs.

In 2015-16, DoT plans to make further improvements to the applications to make them more accessible and responsive for customers.

Regional service delivery improvedDoT delivers transport services and solutions to customers all over the State through its Regional Services Business Unit. To enhance strategic oversight of this service delivery, DoT established three new regions – Northern, Southern and Central – in December 2014.

The regions are led by Directors based in Karratha, Bunbury and Geraldton and supported by on-the-ground Operations Managers in each of the previous seven regions brought together under the new arrangement.

The change aims to improve local decision-making and operational and strategic transport outcomes in the regions. It also provides for an increased focus on service delivery and new opportunities to share resources and multi-skill staff to meet current and future demand across WA.

Success of the Your Move program continued The Your Move Cockburn program has assisted more than 25,000 residents in the City of Cockburn to swap car trips for more active travel modes such as walking, cycling or public transport and increase levels of physical activity.

The free 12-month program, which concluded in July 2014, was delivered by DoT and the Department of Sport and Recreation with support from the City of Cockburn. The program achieved positive results, with a five per cent reduction in car driver trips per participant, totalling 410,000 fewer trips. Participants also increased their daily physical activity by 10 minutes, with eight per cent moving from insufficient to sufficient levels of activity.

The success of this collaborative approach was recognised in June 2015 with an Institute of Public Administration Australia WA Achievement Award for Best Practice in Collaboration Across Government Agencies in the Same Jurisdiction.

Following the success in Cockburn, Your Move Wanneroo commenced in April 2015. The joint DoT and Department of Sport and Recreation program was off to a great start with the target of 10,250 households registering to participate ahead of schedule. In addition, eight schools signed up to DoT’s TravelSmart to Schools program and two workplaces will develop travel plans as part of Your Move Wanneroo.

Through the program, participants will receive a personalised information pack and ongoing phone coaching to encourage them to achieve their goals. Program partners – the City of Wanneroo and, RAC with assistance from HBF, PTA, North Metropolitan Public Health Service, Heart Foundation, Nature Play WA and Diabetes WA – will also provide additional support through infrastructure upgrades, bicycle education sessions and fitness classes.

To date, the City of Wanneroo has installed new bicycle facilities across 10 sites and the PTA has installed 45 new information stands at bus stops in the northern suburbs of the City to make it easier for people to get to their destination.

Department of Transport Annual Report 2014-15

Page 26: DOT Annual Report 2015 · Web viewThe Annual Report has been prepared in accordance with the provisions of the Financial Management Act 2006 and fulfils the Department of Transport’s

To support participants and keep them up-to-date on the latest program news and information, DoT launched a new Your Move website (yourmove.org.au). The site features a personalised ‘My Hub’ area where participants can log-in to track their progress and connect with others to help them stay motivated.

DoT will continue to work with its partner agencies to deliver the program until it concludes in December 2015. Following this, DoT will conduct follow-up surveys from April to June 2016 to measure the program’s success.

Employees encouraged to switch to active transport modesDoT continued to assist workplaces to reduce car trips and enable staff to use active, sustainable transport options more often. This was achieved through the delivery of its TravelSmart Workplaces program and the active travel component of the State Government’s Healthier Workplace WA program.

Throughout the year, DoT supported 34 organisations to identify or implement actions to encourage employees to use active travel alternatives. Seven workplace plans were drafted and participating workplaces implemented a range of actions including informing staff about travel options, improving end-of-trip facilities and offering incentives.

The efforts of these workplaces were recognised at DoT’s biennial TravelSmart Awards in October 2014. MBS Environmental, the City of Nedlands, the City of Joondalup and Edith Cowan University, as well as individuals from the City of Vincent and the City of Cockburn, were awarded for their outstanding achievements in engaging employees and embedding sustainable transport practices within the workplace.

In 2015-16, DoT will continue to engage with workplaces, particularly those in the Perth central area, through a range of activities including training and networking forums, workshops and online newsletters and videos.

Outcome two:Vehicles and road users that meet established vehicle standards and driver competencies to deliver safe vehicles and safe drivers

Key effectiveness indicators

2014-15 target

2014-15 actual

Reasons for significant variance

Percentage of vehicle examinations completed in accordance with the Australian Design Rules assessed by audit (Safe Vehicles).

100% 90% DoT has identified improvements in workflow practices associated with the electronic Vehicle Inspection System at Authorised Inspection Stations (AIS).From October 2014, DVS introduced a new online electronic solution whereby AIS providers return the original certificate of inspection forms directly to DVS on a monthly basis which has improved this index.It is anticipated performance will continue to improve once the new process has been in place for a full year.

Percentage of driver licences issued that comply with the Graduated Driver Training and Licensing System (GDTLS) assessed by audit.

100% 96%

Department of Transport Annual Report 2014-15

Page 27: DOT Annual Report 2015 · Web viewThe Annual Report has been prepared in accordance with the provisions of the Financial Management Act 2006 and fulfils the Department of Transport’s

No significant variance noted this year between target and actual.

Service two:Vehicles and road users that meet established vehicle standards and driver competencies to deliver safe vehicles and safe drivers

Key effectiveness indicators

2014-15 target

2014-15 actual

Reasons for significant variance

Average cost per vehicle and driver transaction

$17.58 $17.19

No significant variance noted this year between target and actual.

Average cost per vehicle inspection

$98.07 $111.01 The variance is primarily due to increased Authorised Inspection Station (AIS) commission payments as the proportion of inspections performed in the metropolitan area shifts from DoT to AIS faster than anticipated.DoT will continue to transition its business to accommodate this shift.

Average cost per driver assessment

$103.85 $107.59

No significant variance noted this year between target and actual.

Percentage of driver’s licence cards issued within 21 days of completed application

100% 100%

No significant variance noted this year between target and actual.

As the State’s population continued to grow at one of the fastest rates in the nation, so too did demand for driver and vehicle services. In 2014-15, DoT remained focused on improving the delivery of these services to better meet the changing needs and expectations of the Western Australian community.

The results of the Driver and Vehicle Services 2015 Customer Perception Survey showed improvement across all DoT service delivery channels since 2013, highlighting the success of the projects and programs delivered by DoT.

Following are details on key driver and vehicle services projects and programs completed or significantly progressed in 2014-15.

How we delivered driver and vehicle services in 2014-15:

1.2 million customers* assisted at our nine metropolitan DVS centres;

495,650 customers* assisted at our nine regional offices;

12,000 customers assisted in remote Western Australia;

1.8 million calls taken at our Customer Contact Centre with an 81 per cent answer rate;

4.1 million* online transactions conducted;

149,226 vehicle examinations conducted; and

Department of Transport Annual Report 2014-15

Page 28: DOT Annual Report 2015 · Web viewThe Annual Report has been prepared in accordance with the provisions of the Financial Management Act 2006 and fulfils the Department of Transport’s

134,485 practical driving assessments conducted.*Financial transactions only.

Improved service delivery highlighted by customer perception survey In 2013, DoT engaged an independent market research organisation to undertake a comprehensive customer perception survey to measure satisfaction with the accessibility, reliability and accuracy of driver and vehicle services.

These results were used to benchmark performance and informed a number of service delivery improvement strategies that have been completed or commenced over the last two years.

In May 2015, DoT repeated the survey to assess current customer satisfaction across its service delivery channels. The survey targeted 2,707 customers who had interacted with DoT in relation to driver and vehicle services matters within the last six months. Of these, 76 per cent were metropolitan and 24 per cent were regional customers.

The survey results showed improvement across all DoT service delivery channels, as detailed below.

DoT will use the findings of the survey to further inform service delivery improvement strategies. A survey will be conducted again in 2017 to measure the effectiveness of these and other strategies in providing excellent service to customers.

iQ helped customers find licensing information fast In March 2015, DoT launched a new licensing online search tool that helps customers quickly find the information they are looking for. The intuitive search tool, known as iQ, follows natural language, meaning customers can type any licensing question into the search box and it will return the most relevant results from across DoT’s range of information sources, including the Knowledge Management System.

As the Knowledge Management System is the principal source of licensing information, legislation and business rules for all DoT staff, customers can be assured that iQ is returning the most accurate, up-to-date information in response to their search. The most popular searches and results are recorded to further refine the results and deliver them to customers faster.

Since its launch, DoT customers have embraced iQ as a single access point for licensing information online, with more than 25,000 searches conducted. As its success continues to grow, DoT plans to look at ways to expand the search technology across its other business areas.

Online vehicle transfers introducedDoT continued to improve customer convenience and choice in 2014-15 by enabling customers to complete vehicle transfers online through DoTDirect. The introduction of this self-service channel not only allows customers to securely conduct simple transfers 24/7, with 500,000 vehicle transfers processed in person or over the phone each year, it also frees up DoT staff to assist customers with more complex transactions.

Since its launch in October 2014, take-up of online transfers has been steady and is expected to grow in 2015-16 as customer awareness increases and the service is expanded to include organisations and businesses in addition to individuals.

Updating addresses made quicker and easierMore than a quarter of a million change of address requests are received from customers each year and over 80 per cent of these requests are submitted via an online form.

To make this process quick and easy for customers, and better verify and safeguard their

Department of Transport Annual Report 2014-15

Page 29: DOT Annual Report 2015 · Web viewThe Annual Report has been prepared in accordance with the provisions of the Financial Management Act 2006 and fulfils the Department of Transport’s

information, DoT made significant improvements to the online form in 2014-15.

When the updated form launches in July 2015, customers will be able to access it through DoTDirect, making this the most secure and efficient way to change their address.

The form is easier to navigate and features address prompting and validation that allows users to correct any mismatches prior to submission. Improving the accuracy of the data submitted will reduce the number of errors currently forwarded to DoT’s Customer Contact Centre for follow-up and correction, saving time for both customers and staff.

Auxiliary number plates made available in WA firstIn May 2015, DoT made auxiliary plates available for purchase for the first time in Western Australia. Available to individuals through DoTDirect, the extra plate can be used on a vehicle when a bicycle or mobility device rack obstructs its rear number plate, ensuring a visible licence number is displayed.

The introduction of auxiliary plates supports law enforcement by improving vehicle identification and increases safe transport options for drivers carrying bicycles or mobility devices. As such, the move has been welcomed by WA Police, the Office of Road Safety and the wider community, particularly cycling and disability groups.

DoT plans to extend the availability of auxiliary plates to include organisations and businesses in addition to individuals in October 2015.

High call volumes supported by leading-edge technology DoT’s Customer Contact Centre receives close to 1.8 million calls for assistance with driver and vehicle licensing matters every year. To support these high call volumes, significant upgrades were made to the Customer Contact Centre’s technology when it relocated to new premises in Stirling in August 2014.

The new telephony platform and call referral system have assisted centre staff to better serve customers. A more robust system to support call centre coordination for emergency services in the event of a disaster has also resulted.

Together with other integrated systems, these new technologies also provide more accurate data on the 8,000 calls (on average) handled each day, which assists in business forecasting and rostering of staff to meet customer demand.

Further, the custom-designed information and communication technology system supports rapid response to any technical issues in DoT’s licensing databases.

This leading-edge technology, together with the state-of-the-art accommodation, meets not only the current but future needs of the high-performing Customer Contact Centre, enabling DoT to continue to provide excellent service.

New standard in service offered at Mirrabooka centreIn September 2014, DoT opened a new Driver and Vehicle Services (DVS) Centre in Mirrabooka to meet growing customer demand in the north-eastern suburbs. The conveniently-located centre is easily accessible by public transport and provides improved customer parking facilities compared to the previous Morley site.

The spacious interior offers customers a new standard in service, with a concierge, more counters and dedicated areas for learner drivers undertaking theory and hazard perception tests as well as practical driving assessments. The centre also offers free Wi-Fi internet access for the comfort and convenience of customers.

Department of Transport Annual Report 2014-15

Page 30: DOT Annual Report 2015 · Web viewThe Annual Report has been prepared in accordance with the provisions of the Financial Management Act 2006 and fulfils the Department of Transport’s

Australia Post partnership expanded to meet customer demand To assist in meeting existing and projected demand for driver and vehicle services, DoT expanded its partnership with Australia Post in 2014-15. Through the staged expansion, customers can now complete a range of licensing transactions at 32 metropolitan Australia Post Offices, with this number to increase to 33 upon completion in July  2015.

To support the delivery of these services, DoT and Australia Post worked collaboratively to design and implement improvements to the WebPOS system – an interface between DoT’s licensing database and Australia Post’s frontline computer systems. The improvements allow more complex transactions to be completed at select Australia Post Offices, providing customers with greater convenience and choice while easing demand at DoT’s DVS centres.

DoT is currently finalising a comprehensive audit tool to ensure that 100 per cent of all financial and non-financial transactions processed by Australia Post are audited. Monthly performance reports have also been streamlined to provide greater transparency and ensure agreed key performance indicators are met. These initiatives add greater rigour to DoT’s governance and compliance processes, which will remain a high priority as DoT continues to grow its partnership with Australia Post in 2015-16 by expanding the range of services offered.

Heavy vehicle training and assessment program rolled outFollowing the 2013 comprehensive trial of the Heavy Vehicle Driver Licence Training and Assessment Partner program in Bunbury, DoT successfully rolled out the new program across Western Australia in 2014-15.

Through a state-wide tender process, DoT appointed 12 registered training organisations (RTOs) to deliver training and conduct practical driving assessments (PDAs) for heavy vehicles in Perth, Bunbury, Busselton, Geraldton, Kalgoorlie and Kununurra.

The partner program, which officially commenced in November 2014 with extensive induction and training, delivers a range of benefits to customers and the wider community. While it was community safety concerns regarding the high volume of heavy vehicle PDAs being conducted in the Bunbury CBD that initially sparked the need for a long-term solution to keep heavy vehicle assessments out of the CBD, the program also offers customers greater convenience and choice in completing these assessments.

Customers have embraced this choice, with the majority of heavy rigid, heavy combination and multi-combination assessments in the above locations conducted by the RTOs. This has, in turn, allowed DoT to reallocate resources from heavy vehicle assessments to other licence classes, in particular C class assessments. Statistics from the first quarter of 2015 indicated that the number of C class PDAs conducted state-wide had increased by approximately 1,000 per month compared to the first quarter of 2014. These figures suggest DoT is on track to make an additional 12,000–15,000 C class and motorcycle PDAs available annually to meet customer demand.

To support the RTOs in managing, recording and validating the training and assessment of customers, DoT developed an automated eligibility, booking and accounting system known as the Licence Assessment Provider System (LAPS).

LAPS, which is integrated with DoT’s licensing database, provides DoT with an extensive reporting package that allows compliance officers to analyse all aspects of service delivery. This, together with regular on-site audit and compliance checks and dedicated support, allows DoT to ensure that the RTOs continue to deliver services to the highest standard.

Department of Transport Annual Report 2014-15

Page 31: DOT Annual Report 2015 · Web viewThe Annual Report has been prepared in accordance with the provisions of the Financial Management Act 2006 and fulfils the Department of Transport’s

‘Chain of Responsibility’ law introduced In 2014-15, the new regulations required in order for DoT to implement the ‘Chain of Responsibility’ law in Western Australia were drafted. The law, which came into effect on 27 April 2015, extends the responsibility for the safe transport of goods by road beyond the driver to everyone involved – from packers and loaders to those receiving goods, company directors, employers and associations.

Ahead of the launch of the new regulations, DoT and Main Roads WA conducted over 100 information sessions in metropolitan and regional locations to ensure stakeholders and industry members were informed of the upcoming changes to existing legislation and understood the potential impacts.

The changes are expected to improve road safety for all users, as well as reduce infrastructure damage and promote a level playing field for industry.

Outcome three:Integrated transport systems that facilitate economic development

Key effectiveness indicators

2014-15 target

2014-15 actual

Reasons for significant variance

Percentage of containerised freight transported via rail in relation to total metropolitan container movements to and from Fremantle port

14.5% 13.2% Rail growth was on target until the temporary closure of the Fremantle rail bridge in August 2014, following damage caused by a vessel.Rail containers were transported by road for three weeks while the bridge was closed, which significantly reduced rail’s market share.Other factors such as a reduction in containerised grain also contributed to the variance.

Service three:Strategic transport policy and integrated planning

Key effectiveness indicators

2014-15 target

2014-15 actual

Reasons for significant variance

Average cost per policy hour for strategic transport policy development

$94.30 $96.04

No significant variance noted this year between target and actual.

Average cost per planning hour for integrated transport planning development

$126.95 $129.18

No significant variance noted this year between target and actual.

Department of Transport Annual Report 2014-15

Page 32: DOT Annual Report 2015 · Web viewThe Annual Report has been prepared in accordance with the provisions of the Financial Management Act 2006 and fulfils the Department of Transport’s

As the lead agency in the Transport portfolio for policy, planning and investment, DoT develops strategic transport policies and integrated transport plans to keep people and freight moving throughout Western Australia – now and into the future.

During 2014-15, DoT progressed six transport plans of State significance to various stages, from development to implementation:

Perth Transport Plan for 3.5 million People and Beyond;

Central Area Transport Plan 2025;

Western Australian Bicycle Network Plan 2014-2031;

Western Australian State Aviation Strategy;

Perth Freight Transport Network Plan; and

Western Australian Regional Freight Transport Network Plan.

These plans inform Western Australia’s transport policy and infrastructure decisions over the next two decades and beyond to ensure metropolitan and regional networks meet expected demand and continue to help grow the State’s economy.

Drafting of Perth Transport Plan for 3.5 million People and Beyond commencedDoT commenced work on the Perth Transport Plan for 3.5 million People and Beyond in late 2014-15. The plan, which complements the Western Australian Planning Commission’s Perth and Peel @ 3.5 million suite of strategic documents, will consider what Perth will look like in the future and plan to accommodate its growing population by providing better access and more transport choices for the community.

Specifically, it will look at options for demand management, mass transit, roads, river crossings, cycling and future technologies.

The draft Public Transport Plan for Perth 2031 and the Moving People Network Plan will be used to inform and develop the overarching plan. To inform the mass transit component of the plan, the Transport portfolio is working collaboratively with the Planning and Transport Research Centre of WA to undertake a high-level research study that is expected to be completed in late 2015.

Work on the plan will continue throughout 2015-16, with the view for DoT to present it to State Government for consideration in mid-2016.

Central Area Transport Plan drafting commencedDoT continued work on the Central Area Transport Plan 2025 together with portfolio partners PTA and Main Roads WA as well as the Metropolitan Redevelopment Authority and the City of Perth.

The plan builds on the CBD Transport Plan to 2016 but has two distinct differences. Firstly, it will provide a longer term, 10-year vision for the transport network in the central metropolitan area. And secondly, it will also include key destinations and activity centres that surround the Perth CBD such as Subiaco, Leederville, Mount Lawley, the QEII/UWA precinct, future Perth Stadium and major development areas on the Burswood Peninsula.

To inform the plan, which will develop initiatives to aid the improvement of all transport modes in the central metropolitan area, the project team has engaged with a range of key stakeholders on major transport issues.

DoT anticipates that the plan will be finalised and submitted to State Government for consideration in 2015-16.

Department of Transport Annual Report 2014-15

Page 33: DOT Annual Report 2015 · Web viewThe Annual Report has been prepared in accordance with the provisions of the Financial Management Act 2006 and fulfils the Department of Transport’s

$88.1 million invested in transport initiatives DoT continued to administer the Perth Parking Licensing Account (PPLA) during 2014-15 to invest revenue from the Perth Parking Levy in transport initiatives in the Perth Parking Management Area. The aim of these initiatives is to deliver balanced transport outcomes for central Perth.

A total of $88.1 million was expended from the PPLA this financial year for the following projects and services across the Transport portfolio:

Provision of the Central Area Transit (CAT) service and the Free Transit Zone (FTZ)

Completion of forward works for the William Street transit mall

Detailed design of the Riverside Drive priority bus lanes

Construction of the Barrack Street on-road cycle lanes between Riverside Drive and St Georges Terrace to create a north–south cycle route through the central city

Commencement of the design of the Roe Street/Railway Street Principal Shared Path extension to improve east–west connectivity

Implementation of parallel walk phases at a further 11 intersections to provide a safer and more efficient pedestrian movement system

Upgrade of the traffic management system including the Incident Response Service and clearway towing to help ensure better flow of buses and traffic on city streets

Extension of the Mounts Bay Road merge taper (west of the Point Lewis Rotary) to improve traffic flow and bus efficiency

Contribution towards the construction of the Perth Busport.

Bicycle network plan implementation continued Ongoing funding will be provided for a range of these projects and services, including construction of bus lanes and bicycle lanes, traffic management and the CAT service and FTZ. A three-year CAT bus renewal program will also commence in 2015-16.

The Western Australian Bicycle Network (WABN) Plan 2014-2031 provides a blueprint for metropolitan and regional cycling facilities over the next two decades. Overseeing the plan, DoT and the WABN Implementation Reference Group, made significant progress on the following five key initiatives identified in the plan.

1. Cycling network expandedTo meet rising demand, the expansion of the cycling network continued. The focus remained on building Principal Shared Paths (PSPs) along freeways and railway lines, prioritising those within a 15 km radius of the Perth CBD, and included the following projects:

$700,000 new path from Scandrett Way to London Way along the Kwinana Freeway completed in July 2014

$3.5 million upgrade to the Thelma Street–Mill Point Road path along the Kwinana Freeway completed in September 2014

$3.3 million new path from Erindale Road to Balcatta Road along the Mitchell Freeway completed in December 2014

$3.4 million new path from Bassendean Station to Success Hill Station along the Midland Line completed in December 2014.

In addition to the completion of these projects, the construction of a new path from Loch Street Station to Shenton Park Station along the Fremantle Line was progressed at a cost of $2.6 million, with a further $3.1 million allocated to complete the path in  2015-16.

Department of Transport Annual Report 2014-15

Page 34: DOT Annual Report 2015 · Web viewThe Annual Report has been prepared in accordance with the provisions of the Financial Management Act 2006 and fulfils the Department of Transport’s

Significant design work was also completed for the following PSP links:

Glendalough Station to Hutton Street along the Mitchell Freeway

Grant Street Station to Cottesloe Station and on to Victoria Street along the Fremantle Line

Guildford Station to Morrison Road along the Midland Line.

DoT will continue to oversee the expansion and monitor use of the PSP network during 2015-16.

2. Cycling infrastructure improvedDoT administers the Perth Bicycle Network and Regional Bicycle Network grants programs. These grants support local government authorities to build cycling infrastructure and develop bicycle plans.

In 2014-15, 25 projects totalling 11.7 km of shared path and 2.8 km of on-road infrastructure were completed through $1.3 million in Perth Bicycle Network Grants. Through $1.3 million in Regional Bicycle Network Grants, 25 projects totalling 10.7 km of shared path infrastructure were completed.

In the 2015-16 grants programs, 33 local government authorities will share more than $2.7 million to create, design or upgrade 22.1 km of shared pedestrian and cycle paths and 1.4 km of on-road bicycle lanes.

To assist local government authorities to develop high-quality bicycle plans, which provide the strategic direction for these grant investments, DoT released new guidelines for developing a bicycle plan in June 2015.

3. Safe cycling and walking routes audit completedFollowing the successful pilot of the Connecting Stations program in 2013-14, an audit of safe cycling and walking routes within a 3 km and 1.5 km radius of Greenwood and Cockburn stations respectively was completed in 2014-15. Connecting Stations aims to encourage cycling for short trips to assist in reducing congestion and parking pressures while benefitting community health. The program will be further developed in 2015-16 based on the findings of the audit.

4. Perth CBD end-of-trip inventory completedIn 2014-15, DoT completed an end-of-trip inventory of the Perth CBD to ensure the facilities available can support growing demand from commuting cyclists. The inventory identified locations where shortfalls in bicycle parking exist and this information will assist in developing bicycle parking strategies for the future.

5. Cycle counting and monitoring strategy completedThe cycle counting and monitoring strategy for Perth was completed in 2014-15. The strategy outlines proposed improvements to assist in assessing the use of the PSP network and the reporting of information. This information will help to more accurately measure and plan for cycling growth over the next decade.

Innovative cycling solutions exploredIn March 2015, DoT and RAC hosted WA’s first Cycling Imagineering Workshop to explore innovative cycling solutions for the State.

The one-day workshop brought together a broad range of stakeholders including representatives from local and State governments, private sector transport and urban planners, academics and advocacy groups. It was an opportunity for all parties, including two Dutch cycling experts, to share knowledge, forge relationships and develop ways to make Western Australia a place where cycling is safe, connected and widely accepted.

Department of Transport Annual Report 2014-15

Page 35: DOT Annual Report 2015 · Web viewThe Annual Report has been prepared in accordance with the provisions of the Financial Management Act 2006 and fulfils the Department of Transport’s

As a result of the workshop, planning has already commenced to develop and implement demonstration low-speed bicycle boulevards. These boulevards slow the speed of motorised traffic to provide a safer environment for all road users, and also provide connections to schools, stations and hospitals.

As these and a number of other key actions arising from the workshop progress, DoT will seek input and feedback from the WABN Implementation Reference Group.

WA’s first aviation strategy releasedThe first Western Australian State Aviation Strategy was released in February 2015. The strategy was developed by DoT, with extensive stakeholder and community input, to support the economic and social development of WA through the provision of safe, affordable, efficient and effective aviation services and infrastructure.

The implementation of the strategy commenced immediately after its release and is overseen by an interagency steering committee led by DoT. Each of the 29 actions outlined in the strategy, under seven key priority areas, have been progressed to some degree to date.

In 2015-16, DoT will finalise implementation plans for each of these actions, which are a combination of one-off projects and ongoing responsibilities, and engage with key stakeholders who will play an important role in implementing the strategy in the short and long term.

Air services and safety boostedIn 2014-15, DoT continued to administer the Regional Airports Development Scheme (RADS). The scheme is designed to improve Western Australian air services and safety by providing financial assistance for infrastructure to eligible owners or leaseholders of regional airports that can be accessed by the public.

A total of 34 projects, with a combined grant value of $3.5 million in Royalties for Regions funding, were completed in 2014-15. Projects included the development of runways; improving airport terminals, facilities and grounds; and the completion of planning studies. A further four projects, with a combined grant value of $3 million in Royalties for Regions funding, will be progressed in 2015-16.

Perth freight plan neared completionDoT continued to develop the Perth Freight Transport Network Plan in 2014-15. The plan complements the Western Australian Regional Freight Transport Network Plan and together they form a long-term freight infrastructure, policy, planning and project blueprint for the development of the State’s freight roads, rail lines and port authorities to 2031 and beyond.

Through significant progress achieved in 2014-15, the plan now sets out the following five strategic priorities for the metropolitan freight network:

1. Port planning and development2. Freight rail demand and investment3. Intermodal terminal planning and development4. Major freight road development priorities5. Measures to better protect the freight network. Addressing these priorities will allow the network to cope with future demand and ensure the State’s businesses are able to trade freely and efficiently in the domestic and global marketplaces.

DoT will finalise the plan and submit it to State Government for consideration in 2015-16.

Department of Transport Annual Report 2014-15

Page 36: DOT Annual Report 2015 · Web viewThe Annual Report has been prepared in accordance with the provisions of the Financial Management Act 2006 and fulfils the Department of Transport’s

Regional freight plan implementation continuedThe Western Australian Regional Freight Transport Network Plan, released in May 2013, identifies the long-term strategic planning, policy and project priorities required to facilitate growth in, and ensure optimal network performance for, the State’s regional freight network to 2031.

DoT continued to lead the implementation of the plan throughout 2014-15. In early 2015, a report card highlighting the significant progress made towards the four key themes and 15 strategic directions set out in the plan was published on DoT’s website.

The report card indicates that almost half of the 109 priority activities, studies and projects identified have either secured funding, been commenced or had at least one stage completed – with five per cent of the projects having been completed in their entirety.

DoT has established a monitoring program to continue to track the implementation of the plan and progress reports will be produced every two to three years.

First stage of ports reforms completedThroughout 2014-15, DoT continued to facilitate the implementation of reforms arising from the Western Australian Ports Governance Review. The reforms will result in a better overall structure for the oversight and governance of WA’s ports and ensure the risks associated with the operations of ports and shipping are managed effectively.

The first stage of the reforms, the amalgamation of seven regional port authorities into four, was completed when the Mid West, Pilbara and Kimberley ports authorities commenced operations on 1 July 2014, followed by the Southern Ports Authority on 1 October 2014. The new ports authorities bring a regional focus to strategic port development planning, policy and priority setting, financial planning, budget allocation and decision-making.

DoT also made substantial progress in the drafting of the Ports Legislation Amendment Bill 2015 (the Bill). The Bill is designed to enable the second stage of the reforms to be carried out – the transfer of nine ports, comprising 13 port facilities, operating under the Shipping and Pilotage Act 1967 to the Port Authorities Act 1999.

Once complete, this will bring all Western Australian ports under a consistent regulatory regime. The nine ports operating under the Shipping and Pilotage Act 1967 will be progressively transferred to come under the Port Authorities Act 1999.In preparation for this, the ports authorities have been undertaking due diligence activities and meeting with the operators of the 13 port facilities to increase their understanding of the operations and ensure a seamless transition following the passage of legislation.

Preparation for ports divestment continuedIn August 2014, the State Government announced the first tranche of public asset sales that will include the sale of the port facilities in Kwinana and Port Hedland – the Kwinana Bulk Terminal and Utah Point Bulk Handling Facility. As part of the 2015-16 State Budget, additional asset sales were announced in May 2015, including the divestment of the assets and operations of the Port of Fremantle (which incorporates the Kwinana Bulk Terminal).

Throughout 2014-15, DoT provided significant input into the preparation for the divestment of the port assets.

DoT will continue to work in close consultation with key stakeholders including the Department of Treasury, Fremantle Port Authority and Pilbara Ports Authority, and the State Government’s external advisors to provide input into the due diligence and subsequent transaction processes required to progress the divestments.

Department of Transport Annual Report 2014-15

Page 37: DOT Annual Report 2015 · Web viewThe Annual Report has been prepared in accordance with the provisions of the Financial Management Act 2006 and fulfils the Department of Transport’s

Kewdale Intermodal Rail Supply Chain project completedBoth components of the State and Commonwealth-funded Kewdale Intermodal Rail Supply Chain project were completed as scheduled in 2014-15.

The $32 million extension of the North Quay Rail Terminal was completed by Fremantle Port Authority on behalf of DoT in August 2014. The rail terminal at the Inner Harbour has been extended from 400 m to 690 m, reducing turnaround times for trains delivering containers to and from the port and achieving a better interface with container terminals.

The $6 million Spearwood crossing loop project was completed by portfolio partner the PTA in July 2014. The project involved the replacement of 850 m of narrow-gauge track with dual-gauge track and the installation of new sleepers and turnouts. The passing loop allows freight trains to pass each other on the rail line that connects Fremantle Port with the Kewdale/Forrestfield area, enabling more freight train movements during the day and minimising service delays.

Both projects will help reduce the reliance on heavy road freight vehicles by using rail more efficiently to move goods around the Perth metropolitan area, particularly between inland hubs and Fremantle Port.

Implementation support for national transport reforms providedDuring 2014-15, DoT continued to support the implementation of the national transport systems for rail and commercial vessel safety initiated by the Council of Australian Governments.

National law for rail safetyThe National Rail Safety Regulator commenced operations in January 2013 and DoT is progressing legislation through State Parliament to establish the Office of the National Rail Safety Regulator in Western Australia.

In November 2014, the Rail Safety National Law (WA) Bill 2014 (the Bill) was passed by the Legislative Assembly. At the same time, it was introduced and had its second reading in the Legislative Council and was referred to the Standing Committee on Uniform Legislation and Statutes Review (the Committee) to consider the impact of the Bill upon the sovereignty and law-making powers of the Parliament of Western Australia and to report its findings back to the Legislative Council.

In December 2014, DoT briefed the Committee to assist with the inquiry. The Committee submitted a final report to the Legislative Council in March 2015. A response to the Committee’s recommendations has been prepared and further detailed consideration of the Bill by the Legislative Council is anticipated to take place during the Spring 2015  sittings.

It is anticipated that Western Australia will commence operations under the Office of the National Rail Safety Regulator in November 2015.

National law for commercial vessel safetyThe national law governing commercial vessel safety came into effect in July 2013. Throughout 2014-15, DoT continued drafting the Marine Safety (Domestic Commercial Vessel National Law Application) Bill 2014 to enact the national law in WA, while simultaneously preparing consequential amendments to the Western Australian Marine Act 1982 and other Acts and regulations to ensure the seamless regulation of vessels under the national law and those remaining under the State’s jurisdiction. DoT is continuing to deliver the national system functions in Western Australia as a formal Delegate of the National Regulator.

Department of Transport Annual Report 2014-15

Page 38: DOT Annual Report 2015 · Web viewThe Annual Report has been prepared in accordance with the provisions of the Financial Management Act 2006 and fulfils the Department of Transport’s

National heavy vehicle charges Australia uses a pay-as-you-go model for heavy vehicle charges which is based on a fixed annual registration and fuel-based road-user charges. Revenue recovered through these charges assists in providing better and safer roads.

In most states and territories, heavy vehicle charges are determined by the National Transport Commission (NTC). Each year, the NTC puts forward a new heavy vehicle charges determination or recommends an annual adjustment to ensure heavy vehicle charges keep pace with road spending programs.

In February 2014, the NTC proposed a new schedule of national heavy vehicle charges, which the Transport and Infrastructure Council agreed would be implemented on 1 July 2016.

In recent years, the State’s heavy vehicle charges have not been aligned with the national charges as determined by the NTC. As the determination incorporates an improved modeling process and a new schedule of charges, DoT has been working with the NTC to model the potential impacts of these charges in Western Australia. Should the new charges be considered appropriate for the State’s heavy vehicle fleet, freight task and road conditions, consideration will be given to transitioning to the new national schedule of charges over a number of years.

In the meantime, the State Government agreed to implement a 0.6 per cent annual registration fee increase for 2015-16 in line with other jurisdictions.

Department of Transport Annual Report 2014-15

Page 39: DOT Annual Report 2015 · Web viewThe Annual Report has been prepared in accordance with the provisions of the Financial Management Act 2006 and fulfils the Department of Transport’s

Actual results versus budget targetsThe following table provides a comparison of the financial targets and outcomes against criteria included in the Resource Agreement between the Chief Executive Officer, the Minister for Transport and the Treasurer.

2014-15 Actual results versus budget targets2014-15 Target $000

2014-15 Actual $000

Variation $000 Note*

Total cost of services 378,069 365,957 12,112 1

Net cost of services 66,986 32,607 34,379 2

Total equity 691,907 709,693 17,786 3

Net increase/(decrease) in cash held (36,622) (34,246) 2,376 4

Approved full time equivalent (FTE) 1,406 1,410 4 5

*NotesThese notes should be read in conjunction with the Explanatory Statement to the Financial Statements on page 109.

Note 1: Total cost of servicesThe total cost of services trailed estimates primarily due to lower than anticipated expenditure on various grants and subsidies.

Note 2: Net cost of servicesIn addition to lower expenditure on grants and subsidies, higher revenue primarily from the transfer to DoT of the responsibility of the Two Rocks Marina contributed to the lower net cost of service.

Note 3: Total equityTotal equity exceeded estimates reflecting the impact of the favourable operating result for 2014-15.

Note 4: Net increase/(decrease) in cash heldThe net decrease in cash held is close to budget.

Note 5: Approved FTEThe actual paid FTE closely reflects the budget, with the small variance primarily due to the retention of Rail Safety staff due to a delay in the transition to the National Rail Safety Regulator.

Department of Transport Annual Report 2014-15

Page 40: DOT Annual Report 2015 · Web viewThe Annual Report has been prepared in accordance with the provisions of the Financial Management Act 2006 and fulfils the Department of Transport’s

SIGNIFICANT ISSUES IMPACTING THE AGENCYEconomicThe rapid development of the Perth metropolitan area, the CBD and major activity centres requires a proactive approach to transport planning and delivery of new initiatives to manage traffic growth and ensure a balanced transport system.

To address this need, DoT is developing a suite of strategic transport plans for the medium and long term.

The Perth Transport Plan for 3.5 million People and Beyond will establish a blueprint for the development of, and investment in, the city’s transport network across all modes for a city of 3.5 million people. This is nominally expected by around 2050.

The transport plans for the medium term include the Central Area Transport Plan to 2025 which will underpin further investment in the infrastructure, policies and services in the CBD such as the CAT bus services. Detailed transport planning and modelling is also being undertaken for the Stirling City Centre, Murdoch, Cannington, Morley, Karrinyup and Bentley/Curtin to inform changes needed for the network and new travel demand management measures to meet the expansion plans for these centres, particularly where large shopping centre expansions are being proposed.

Cycling has increased well above the rate of population growth, with a 32 per cent increase in cyclists on the Principal Shared Path network since  2011. DoT, along with portfolio partners Main Roads WA and the Public Transport Authority, continue to invest in cycling infrastructure to meet this growing demand. In 2015-16, DoT will develop innovative options to create greater separation of cyclists and motorised traffic on roads to further improve safety and support the increased use of cycling as a transport mode.

Demand for new or improved coastal infrastructure facilities continues to grow in both metropolitan and regional locations. DoT has made significant progress in addressing this demand with the completion of the Augusta Boat Harbour and other new boating infrastructure around the State. The $18.27 million Royalties for Regions funded Exmouth Boat Harbour upgrade has commenced to further support the development of marine tourism and recreational activities and enhance business opportunities associated with the resources sector.

Ageing coastal infrastructure around the State continues to impact DoT, requiring ongoing maintenance and ultimately replacement. The $3.9 million replacement of Jetty 2 at the Fremantle Fishing Boat Harbour has commenced and DoT will also replace the 109 year old Denham Jetty with a new $2.2 million Royalties for Regions funded multi-purpose jetty in 2015-16.

Western Australia has seen a significant expansion in regional port facilities and shipping operations in the past decade. Port governance arrangements are being updated to ensure further developments are well planned and the risks associated with the operation of ports and shipping are appropriately managed.

The State Government released Western Australia’s first State Aviation Strategy in February 2015. The strategy provides a framework for future policy, planning and investment in the State’s aviation sector by Government and the private sector. Consistent with the strategy, the State will play a more active role in the aviation sector to ensure air services and airports support Western Australia’s economic and social development.

Department of Transport Annual Report 2014-15

Page 41: DOT Annual Report 2015 · Web viewThe Annual Report has been prepared in accordance with the provisions of the Financial Management Act 2006 and fulfils the Department of Transport’s

Social The Western Australian community continues to demand convenient access to Driver and Vehicle Services (DVS) information and transactions. DoT completed a number of initiatives to meet this growing expectation in 2014-15 including the opening of the new Mirrabooka DVS Centre, improving the efficiency of the Customer Contact Centre’s telephony system and introducing online vehicle transfers.

DoT also continued to provide customers with alternative service delivery options for vehicle inspections through its Authorised Inspection Stations network and a range of licensing transactions through its partnership with Australia Post. From July 2015, the governance and compliance programs in place to support these alternative service delivery options will be strengthened by the progressive implementation of audit and data intelligence systems.

Increasing calls for regulatory reform have highlighted the need for definitive changes in the on-demand transport industry. In June 2015, DoT finalised a Green Paper that seeks to promote discussion around areas of policy reform that will best deliver a safe, more flexible, responsible and innovative customer service-focused on-demand transport industry.

Environmental Seagrass accumulation and beach erosion at Port Geographe has been an issue for a number of years. The $28.15 million project to reconfigure the coastal structures at the site was completed in May 2015. Sand and seagrass are now able to bypass the new coastal structures naturally, resulting in reduced seagrass accumulation, and beach erosion at Port Geographe is now at levels consistent with other coastal areas along Geographe Bay. In addition to addressing these environmental issues, the successful project has improved amenity and access to beaches for local residents and the wider community.

Department of Transport Annual Report 2014-15

Page 42: DOT Annual Report 2015 · Web viewThe Annual Report has been prepared in accordance with the provisions of the Financial Management Act 2006 and fulfils the Department of Transport’s

DISCLOSURES AND LEGAL COMPLIANCECertification of financial statements For the year ended 30 June 2015The accompanying financial statements of the Department of Transport have been prepared in compliance with the provisions of the Financial Management Act 2006 from proper accounts and records to present fairly the financial transactions for the financial year ended 30 June 2015 and the financial position as at 30 June 2015.

At the date of signing we are not aware of any circumstances which would render the particulars included in the financial statements misleading or inaccurate.

Kathryn Martin Steve TroughtonChief Finance Officer Accountable Authority

2 September 2015 2 September 2015

CERTIFICATION OF KEY PERFORMANCE INDICATORSFor the year ended 30 June 2015I hereby certify that the key performance indicators are based on proper records, are relevant and appropriate for assisting users to assess Department of Transport’s performance, and fairly represent the performance of the Department of Transport for the financial year ended 30 June 2015.

Steve TroughtonAccountable Authority

2 September 2015

KEY PERFORMANCE INDICATORSFor the year ended 30 June 2015The transport function is integral to business and commerce and is important for social interaction and connecting communities. DoT’s focus is on strategic transport policy and planning, regulation, and the delivery of safe and sustainable transport services and programs. This includes the licensing of drivers, vehicles and vessels, developing and planning infrastructure, and setting and ensuring service and safety standards across the range of public and commercial transport systems in WA.

Together with its portfolio partners, DoT has the expertise to deliver the high quality and integrated transport policy, services and plans needed to connect a complex, inter-related economic and social network. DoT connects people with goods and services through an intricate system of roads, railways, airports, ports and waterways, and keeps people safe within those networks through an integrated approach to planning, licensing, education and compliance strategies.

The breadth and diversity of DoT’s functions and services mean that DoT contributes to two of the Government’s strategic goals outlined below.

Department of Transport Annual Report 2014-15

Page 43: DOT Annual Report 2015 · Web viewThe Annual Report has been prepared in accordance with the provisions of the Financial Management Act 2006 and fulfils the Department of Transport’s

Government strategic goals DoT outcomes DoT services

Results based service deliveryGreater focus on achieving results in key service delivery areas for the benefit of all Western Australians.

1. An accessible and safe transport system

1. Transport system and services development, planning, operation and regulation

2. Vehicles and road users that meet established vehicle standards and driver competencies to deliver safe vehicles and safe drivers

2. Driver and vehicle services

State building – major projectsBuilding strategic infrastructure that will create jobs and underpin Western Australia’s long-term economic development.

3. Integrated transport systems that facilitate economic development

3. Strategic transport policy and integrated planning

Outcome one:An accessible and safe transport systemDoT’s responsibility for the accessibility and safety of the transport system derives from the Transport Co-ordination Act 1966 (the Act). The Act confers on DoT the responsibility for coordinating and planning the transport system and enabling accessibility and safety considerations.

There are varying degrees of accessibility and safety across the agency for the different modes of transport. For example, the Marine Safety Business Unit provides regulation, education, training and compliance monitoring in regards to safety of marine vessels, whereas accessibility to marine related infrastructure and waterways is the responsibility of the Coastal Infrastructure Business Unit.

Rail safety is managed by the Office of Rail Safety which is charged with administering the Rail Safety Act 2010 in WA and nationally as part of a national approach to rail safety regulation. It does this by ensuring railway owners and operators comply with regulatory standards to construct, operate and maintain railways. Accessibility to railways is the responsibility of the owners and operators.

Accessibility to taxis is the responsibility of the Passenger Services Business Unit whereby they are responsible for ensuring an adequate taxi service is being provided to the public of WA. Safety in taxis in regards to vehicles and drivers is the responsibility of Driver and Vehicle Services in its role in administering road laws as defined in Road Traffic (Administration) Act 2008 and is covered under outcome two of the Department’s outcome structure – “Vehicles and road users that meet established vehicle standards and driver competencies to deliver safe vehicles and safe drivers”. Safety for taxi operators and passengers not related to use on the road is the responsibility of the WA Police in its community safety role.

Accessibility to regular public transport air services is the responsibility of DoT’s Transport Strategy and Reform Directorate which ensures an adequate air service is provided to key regional communities throughout the State. Aviation safety is controlled through the Commonwealth Government’s Civil Aviation Safety Authority. DoT ensures all aircraft that carry passengers for regular public transport or charter purposes within WA are licensed annually.

Department of Transport Annual Report 2014-15

Page 44: DOT Annual Report 2015 · Web viewThe Annual Report has been prepared in accordance with the provisions of the Financial Management Act 2006 and fulfils the Department of Transport’s

The effectiveness indicators below measure transport system accessibility and safety for DoT:

AccessibilityPercentage of standard metropolitan (non-multi-purpose) taxi jobs which were not covered

– peak;

Percentage of standard metropolitan (non-multi-purpose) taxi jobs which were not covered – off-peak;

Percentage by which the waiting time standard, for Metropolitan Area taxis is met;

Percentage of Time Maritime Infrastructure is Fit for Purpose when required; and

Percentage of Regional Airports Receiving Scheduled Regular Public Transport.

SafetyRate of Reported Incidents (Accidents) on the Water per 100 Commercial Vessels Surveyed;

Rate of Reported Incidents (Accidents) on the Water per 10,000 Registered Recreational Vessels; and

Rate of Serious Accidents per Million Train Kilometres.

Effectiveness key performance indicatorsPercentage of standard metropolitan (non multi-purpose) taxi jobs which were not covered – peakDoT is responsible for regulation of the Perth Metropolitan Taxi Industry via the administration of the Taxi Act 1994.

Following the 1999 National Competition Policy Review of the Perth Metropolitan Taxi Industry, the then Department for Planning and Infrastructure introduced performance standards for the industry. Performance standards have been in place since 1 July 2000 to ensure that the public receives acceptable levels of service. The taxi industry is required to meet these performance standards. An independent external consultant analyses taxi industry data, sourced from the Taxi Dispatch Service (TDS) providers, and reports on taxi demand and industry viability trends as well as the performance of the taxi industry against the industry standards on a monthly and quarterly basis.

This assessment gives DoT the ability to provide the Minister for Transport with evidence-based policy recommendations and therefore directly assists the regulatory function of the Department.

The key performance indicator of taxi jobs not covered – Peak (JNC – Peak) is the percentage of total jobs going unserviced in the peak period (Friday and Saturday nights from 5pm to 6am).

Until the 2012-13 financial year the peak and off-peak JNC was reported as a single KPI. The total number of jobs not covered in all hours was divided by the total number of phone orders advertised to taxi drivers. This did not allow evaluation of the sharp differences in service delivery in different times of the week. Since the 2012-13 financial year peak and off-peak periods have been reported separately.

Trends from this indicator assist with determining supply and demand requirements for the industry and provide rationale for determining whether there is a requirement to release additional taxi plates.

Department of Transport Annual Report 2014-15

Page 45: DOT Annual Report 2015 · Web viewThe Annual Report has been prepared in accordance with the provisions of the Financial Management Act 2006 and fulfils the Department of Transport’s

Industry performance is assessed by obtaining and analysing data from the two major TDS providers in the metropolitan area. Of these, both the number of customer telephone orders placed on and advertised through the taxi company dispatch system and the number of jobs not covered against these orders during peak periods are recorded.

2011-12 actual

2012-13 actual

2013-14 actual

2014-15 target

2014-15 actual

Reasons for significant variance

Percentage of standard metropolitan (non-multi-purpose) taxi jobs which were not covered – peak

4.53% 4.75% 2.58% 1.00% 1.70% In a period of softening demand for taxi services there has been an improvement in the number of taxi jobs which were not covered during peak period from 2.58% in 2013-14 to 1.70% in 2014-15.While performance against index has improved, the 2014-15 Budget Target was not met.

Percentage of standard metropolitan (non multi-purpose) taxi jobs which were not covered – off-peakDoT is responsible for regulation of the Perth Metropolitan Taxi Industry via the administration of the Taxi Act 1994.

Following the 1999 National Competition Policy Review of the Perth Metropolitan Taxi Industry, the then Department for Planning and Infrastructure introduced performance standards for the industry. Performance standards have been in place since 1 July 2000 to ensure that the public receives acceptable levels of service. The taxi industry is required to meet these performance standards. An independent external consultant analyses taxi industry data, sourced from the Taxi Dispatch Service (TDS) providers, and reports on taxi demand and industry viability trends as well as the performance of the taxi industry against the industry standards on a monthly and quarterly basis.

This assessment gives DoT the ability to provide the Minister for Transport with evidence-based policy recommendations and therefore directly assists the regulatory function of the Department.

The key performance indicator of taxi jobs not covered – Off-peak (JNC – off-peak) is the percentage of total jobs going unserviced in the off-peak period (all times with the exception of the peak period which is Friday and Saturday night, 5pm to 6am).

Until the 2012-13 financial year the peak and off-peak JNC was reported as a single KPI.

The total number of jobs not covered in all hours was divided by the total number of phone orders advertised to taxi drivers. This did not allow evaluation of the sharp differences in service delivery in different times of the week. Since the 2012-13 financial year peak and off-peak periods have been reported separately.

Trends from this indicator assist with determining supply and demand requirements for the industry and provide rationale for determining whether there is a requirement to release additional taxi plates.

Department of Transport Annual Report 2014-15

Page 46: DOT Annual Report 2015 · Web viewThe Annual Report has been prepared in accordance with the provisions of the Financial Management Act 2006 and fulfils the Department of Transport’s

Industry performance is assessed by obtaining and analysing data from the two major TDS providers in the metropolitan area. Of these, both the number of customer telephone orders placed on and advertised through the taxi company dispatch system and the number of jobs not covered against these orders during the off-peak period are recorded.

2011-12 actual

2012-13 actual

2013-14 actual

2014-15 target

2014-15 actual

Reasons for significant variance

Percentage of standard metropolitan (non-multi-purpose) taxi jobs which were not covered – off-peak

1.65% 1.67% 0.88% 0.50% 0.59% In a period of softening demand for taxi services there has been an improvement in the number of taxi jobs which were not covered during off-peak period from 0.88% in 2013-14 to 0.59% in 2014-15.While performance against index has improved, the 2014-15 Budget Target was not met.

Percentage by which the waiting time standard for metropolitan area taxis is metDoT is responsible for regulation of the Perth Metropolitan Taxi Industry via the administration of the Taxi Act 1994. Following the 1999 National Competition Policy Review of the Perth Metropolitan Taxi Industry, the then Department for Planning and Infrastructure introduced performance standards for the industry. Performance standards have been in place since 1 July 2000. The taxi industry is required to meet these performance standards.

An independent external consultant analyses taxi industry data, sourced from the TDS providers, and reports on taxi demand and industry viability trends as well as the performance of the taxi industry against the industry standards on a monthly and quarterly basis.

This assessment gives DoT the ability to provide the Minister for Transport with evidence-based policy recommendations and therefore directly assists the regulatory function of the Department.

In addition to JNC, taxi performance is measured by determining the average time a customer has to wait for a taxi following a booking, during both peak and off-peak times, and then comparing the result against the relevant performance standards. To calculate this measure the wait times for taxis requested as soon as possible (ASAP) have been measured during both peak and off-peak times and bookings that meet the performance standard determined and presented as a percentage against all ASAP bookings.

Trends from this indicator assists with determining supply versus demand requirements for the industry and provides rationale for determining whether there is a requirement to release additional taxi plates.

Industry performance is assessed by obtaining and analysing data from the two major TDS providers in the metropolitan area. Waiting time information is available from the TDS systems and measured as the difference between when the customer first requested the taxi and when the driver turned on their meter to start the job.

Department of Transport Annual Report 2014-15

Page 47: DOT Annual Report 2015 · Web viewThe Annual Report has been prepared in accordance with the provisions of the Financial Management Act 2006 and fulfils the Department of Transport’s

2011-12 actual

2012-13 actual

2013-14 actual

2014-15 target

2014-15 actual

Reasons for significant variance

Percentage by which the waiting time standard for metropolitan area taxis is met

91.5% 91.7% 92.3% 91% 92% No significant variance noted this year between target and actual.

Percentage of time maritime infrastructure is fit for purpose when requiredDoT is responsible for the planning, creation, enhancement and management of new and existing land and water based maritime facilities for small craft throughout WA.

DoT manages and maintains a variety of maritime infrastructure assets, including jetties, wharves, boat launching facilities, pens and moorings at approximately 50 discrete locations throughout the State, to service the fishing and commercial maritime industries and the recreational boating needs of Western Australians.

In addition to this, DoT maintains associated navigational aids which are strategically placed in water and onshore to ensure that the boating community can safely transit through waterways. It also maintains the navigable waters at its managed maritime facilities as well as at a small number of other locations, including two commercial ports, throughout the State by providing access via dredged channels.

The facilities and their purpose vary for each location and the associated management and maintenance plans vary accordingly.

A consistently high percentage of availability will confirm that maritime infrastructure is being appropriately maintained and is accessible to the boating industries and the public of WA.

2011-12 actual

2012-13 actual

2013-14 actual

2014-15 target

2014-15 actual

Reasons for significant variance

Percentage of time maritime infrastructure is fit for purpose when required

99.76% 99.53% 99.07% 99.71% 99.40% No significant variance noted this year between target and actual.

Percentage of regional airports receiving scheduled regular public transport (RPT) air servicesDoT provides advice on a range of aviation issues. It provides grants to support the development of airport infrastructure through the Regional Airports Development Scheme and regulates intrastate air services to ensure that key WA regional communities receive sustainable regular public transport (RPT) air services.

Under the Transport Co-ordination Act 1966, all aircraft that carry passengers for RPT or charter purposes within WA are required to be licensed annually. In addition, the Minister for Transport has powers to apply conditions to aircraft licences to determine where they may fly in WA. Where there are insufficient passenger numbers to support competition to a key regional centre, the WA Government protects the service by offering it through a public tender process, so that a limited number of airlines may service it.

The objective is that communities in WA with populations of more than 500 are located within a 250 kilometre radius of an airport accessible by a safe road which provides two or more weekly RPT air services or have access to other forms of public transport.

Department of Transport Annual Report 2014-15

Page 48: DOT Annual Report 2015 · Web viewThe Annual Report has been prepared in accordance with the provisions of the Financial Management Act 2006 and fulfils the Department of Transport’s

To ensure that charter operations do not undermine the RPT service, charter operators are limited by a condition on their aircraft licence to providing one return flight per client per week to an RPT airport in WA. Approval from the Minister for Transport is required to provide additional charter services over RPT air routes.

The licensing arrangements and deeds for the protected and subsidised services are monitored through monthly statistics and meetings with the airlines to ensure that the outcome of the regional centres having a sustainable RPT service is achieved.

A reduction in the percentage of key regional centres being serviced by RPT air services or other forms of public transport would indicate that services to remote communities are not being maintained.

2011-12 actual

2012-13 actual

2013-14 actual

2014-15 target

2014-15 actual

Reasons for significant variance

Percentage of regional airports receiving scheduled regular public transport (RPT) air services

100% 96% 96% 100% 96% No significant variance noted this year between target and actual.

Rate of reported incidents (accidents) on the water per 100 commercial vessels surveyedThe Commercial Vessel Safety Branch (CVS) is a delegate to the National System for Domestic Commercial Vessel Safety under the auspice of the Marine Safety (Domestic Commercial Vessel) National Law 2012. With the National Regulator CVS ensures all commercial vessels in WA are subject to survey to certify they meet minimum standards for construction and equipment safety before they are allowed to operate.

A commercial vessel must hold a current certificate to show that it meets national and international construction standards to continue to operate.

All accidents or incidents that result in serious injury or death, or cause damage to the vessel rendering it unseaworthy or unsafe must be reported. An incident (accident) is defined as any commercial vessel which is involved in a collision that sustains:

(a) casualty;(b) damage affecting her seaworthiness or efficiency, either in hull or in any part of the

boilers and machinery; or(c) causes the loss or damage to any other vessel, or where by reason of a casualty

happening to, or on board a commercial vessel, loss of life or serious injury to any person ensues.

It is a requirement under the National Law for people to report any accident or incident involving a domestic commercial vessel.

The information for this indicator is derived from DoT’s commercial vessel database and the marine incidents database, and is calculated by dividing the number of incidents by the number of commercial vessels holding current survey certificates (expressed as a rate per hundred vessels).

Department of Transport Annual Report 2014-15

Page 49: DOT Annual Report 2015 · Web viewThe Annual Report has been prepared in accordance with the provisions of the Financial Management Act 2006 and fulfils the Department of Transport’s

2011-12 actual

2012-13 actual

2013-14 actual

2014-15 target

2014-15 actual

Reasons for significant variance

Rate of reported incidents (accidents) on the water per 100 commercial vessels surveyed

4.97 4.82 6.54 5.58 5.44 No significant variance noted this year between target and actual.

Rate of reported incidents (accidents) on the water per 10,000 registered recreational vesselsWA’s temperate climate and unique marine environment entice an estimated 250,000 people to make recreational use of the State’s waterways each year.

DoT takes a lead role in ensuring the safety of the State’s mariners through:

setting standards for recreational vessels and registering only those that meet legislative requirements;

requiring recreational mariners to meet basic safety competencies through the Recreational Skipper’s Ticket (compulsory from 1 April 2008);

maintaining marine charts and signs to promote safe navigation and warn of hazards;

responding to oil spills and other pollutants;

maintaining navigational aids (navaids); and

educating and informing mariners on marine safety matters.

Under the Navigable Waters Regulations 1958, all vessels that have a motor or have the capacity to have a motor fitted, must be registered to operate on navigable waters in WA. In addition, it is a requirement under the WA Marine Act 1982 for people to report any accident or incident that results in serious injury or death, or the vessel being damaged enough to make it unseaworthy or unsafe.

The data for this indicator is taken from DoT’s recreational vessel registration database and the marine incidents database, and is calculated by dividing the number of incidents by the number of registered recreational vessels (expressed as a rate per ten thousand vessels).

A reduction in the rate of incidents per registered recreational vessel indicates that the safety outcome is being met in relation to recreational boating.

2011-12 actual

2012-13 actual

2013-14 actual

2014-15 target

2014-15 actual

Reasons for significant variance

Rate of reported incidents (accidents) on the water per 10,000 registered recreational vessels

10.69 9.48 10.56 9.50 10.96 The slowdown in the WA economy has reduced the anticipated number of recreational vessels being registered. There has also been an increase in the number of incidents reported due largely to the change in reporting requirements of marine insurance industry.

The industry now only

Department of Transport Annual Report 2014-15

Page 50: DOT Annual Report 2015 · Web viewThe Annual Report has been prepared in accordance with the provisions of the Financial Management Act 2006 and fulfils the Department of Transport’s

accepts claims made by clients only where the incident has been reported to DoT.

Number of serious rail accidents per million train kilometresThrough administration of the Rail Safety Act 2010 (the Act), DoT is responsible for promoting the safety of the rail transport system. In this regulatory scheme, where railway managers are accountable for rail safety, the Office of Rail Safety:

accredits rail transport operators to construct, operate and maintain railways where they have met requirements in the Act, including demonstrating the competence and capacity to manage risks to safety associated with railway operations and to implement their proposed safety management systems; and

monitors performance of accredited railways to ensure they are complying with the terms of their accreditation and their approved safety management system and to achieve continuous development and improvement in railway safety.

A ‘serious’ rail accident is one consistent with a Category A ‘notifiable occurrence’ as set out in the Rail Safety Regulations 2011. That is:

an accident or incident that causes the death, serious injury or significant property damage;

a running line derailment;

a running line collision between rolling stock;

a collision at a road or pedestrian level crossing between rolling stock and either a road vehicle or a person;

a fire or explosion on or in a rail infrastructure or rolling stock that affects the safety or railway operations or that endangers one or more people;

a suspected terrorist attack or threat of attack; or

any accident or incident that is likely to generate intense public interest or concern.

A train kilometre is a unit of measure representing the movement of a train over one kilometre. A reduction in the rate of occurrences would indicate that the safety outcome is being met on rail transport and gives users reasonable confidence that the rail system they use is safe.

The result is economic growth and development through the promotion of rail as a safe form of transport connecting commuters and goods to the desired destination for business or personal purposes. Social and economic growth benefits are also accrued through avoiding the high costs associated with rail accidents.

Department of Transport Annual Report 2014-15

Page 51: DOT Annual Report 2015 · Web viewThe Annual Report has been prepared in accordance with the provisions of the Financial Management Act 2006 and fulfils the Department of Transport’s

2011-12 Actual

2012-13 Actual

2013-14 Actual

2014-15 Target

2014-15 Actual

Reasons for significant variance

Number of serious rail accidents per million train kilometres

1.82 1.66 1.35 1.55 0.83 There has been a reduction in the number of incidents and an increase of ‘train kilometres’ travelled.The reduction in the rate of incidents indicates that the safety outcome is being met by rail transport operators.

Department of Transport Annual Report 2014-15

Page 52: DOT Annual Report 2015 · Web viewThe Annual Report has been prepared in accordance with the provisions of the Financial Management Act 2006 and fulfils the Department of Transport’s

Efficiency Key Performance IndicatorsService one: Transport system and services development, planning, operation and regulationTransport system and services development, planning, operation and regulation are designed to improve accessibility and safety of the transport system for all Western Australians.

This service contributes to the Government’s Framework for Strategic Management Goal – Results Based Service Delivery through:

integration between and within transport modes;

managing heavy vehicle freight movement to major industrial and intermodal sites;

increasing accessibility to a reasonable level of transport services for all individuals, businesses and communities;

encouraging sustainable choices through programs, such as TravelSmart and cycling promotions;

provision and management of infrastructure, including small craft facilities and marine navigation aids, to maintain safe and accessible transport operations;

setting competencies/standards and monitoring compliance for operators, vehicles and vessels in the on-demand transport and maritime industries;

developing policies, standards and guidelines for rail safety regulation, accrediting rail owners and rail operators in accordance with relevant standards, and ensuring rail owners and operators comply with the terms of their accreditation;

developing and implementing policies and strategies to facilitate safe navigation and safe use of the State’s waterways;

maintaining effective contingency response strategies and mechanisms to combat marine transport emergencies and marine environmental pollution incidents;

safe jetties through licensing;

marine and transport related data collection, analysis and dissemination; and

provision of cartographic information services.

The key efficiency performance indicators used to measure this performance are detailed below:

Cost of regulation per taxi plate administeredReasons for significant varianceTaxi plate release slowed in response to softening in demand for taxi services.

The number of taxi plates regulated did not increase at the rate initially anticipated, resulting in an increased cost of regulation per taxi plate administered.

Average cost per day per maritime infrastructure asset managedReasons for significant varianceThe total cost to manage maritime infrastructure assets exceeded the 2014-15 published budget by $4.27 million.

Additional funds of $1.75 million were spent to address channel dredging and sand bypassing to maintain safety navigation in various locations across the State.

Depreciation expenses were over-budget by $2.25 million primarily due to DoT taking over

Department of Transport Annual Report 2014-15

Page 53: DOT Annual Report 2015 · Web viewThe Annual Report has been prepared in accordance with the provisions of the Financial Management Act 2006 and fulfils the Department of Transport’s

the Two Rocks Marina facility.

Average survey cost per commercial vesselReasons for significant varianceNo significant variance noted this year between target and actual.

Average cost per recreational vessel registrationReasons for significant varianceNo significant variance noted this year between target and actual

Cost to maintain marine pollution response preparedness per registered vesselReasons for significant varianceThe application of the National Law in July 2013 resulted in a change of definition in what constituted a survey vessel under the previous Western Australian Law.

This variation meant that some vessels previously requiring survey are now survey exempt under the National Law and can now be surveyed anywhere in Australia regardless of the area of operation.

In addition, a decrease in volumes can be attributed to a demobilisation of vessels involved in major resource construction projects in the North West and a continued reduction in the commercial fishing vessel fleet around the State.

The actual cost is lower than the target due to vacancies not filled during periods in 2014-15.

Outcome two:Vehicles and road users that meet established vehicle standards and driver competencies to deliver safe vehicles and safe driversThe Road Traffic Act 1974 (until 26 April 2015) and thereafter the Road Traffic (Authorisation to Drive) Act 2008, Road Traffic (Vehicles) Act 2012 and Road Traffic (Administration) Act 2008 confers on DoT through Driver and Vehicle Services (DVS), the responsibility for licensing the State’s drivers and registering vehicles. Drivers must demonstrate that they are competent to drive a vehicle through complying with the requirements of Section 16 of the Road Traffic (Authorisation To Drive) Regulations 2014. Vehicles must be registered before they may lawfully be used on the road. Road Traffic (Vehicles) Regulations 2014 details the specific requirements for examination against the Australian Design Rules which allow a vehicle to be deemed roadworthy.

DoT measures its effectiveness in meeting this outcome through measuring:

The percentage of vehicle examinations completed in accordance with the Australian Design Rules assessed by audit; and

The percentage of driver licences issued that comply with the Graduated Driver Training and Licensing System assessed by audit.

Effectiveness Key Performance IndicatorsPercentage of vehicle examinations completed in accordance with the Australian Design Rules assessed by auditThe road laws as defined in the Road Traffic (Administration) Act 2008 confers on DoT responsibility for licensing the State’s vehicles. Vehicles must be licensed before they may lawfully be used on the road. Registration is conferred only where a vehicle is deemed roadworthy (passed examination).

Department of Transport Annual Report 2014-15

Page 54: DOT Annual Report 2015 · Web viewThe Annual Report has been prepared in accordance with the provisions of the Financial Management Act 2006 and fulfils the Department of Transport’s

This indicator measures the extent to which vehicle examinations are conducted according to processes designed to establish levels of roadworthiness pursuant to the provisions of the road laws as defined in the Road Traffic (Administration) Act 2008 and related regulations.

The Road Traffic (Vehicles) Regulations 2014 detail specific requirements for vehicles, including dimensions, braking, lighting and emissions – all of which must conform to the Australian Design Rules (as at the date of manufacture of the vehicle). DoT’s Vehicle Examiners and personnel at Authorised Inspection Stations (AIS) are registered motor vehicle mechanics and trained to examine vehicles in accordance with the Australian Design Rules.

The Motor Vehicle “Certificate of Inspection” form is used to record details of the vehicle examination.

2011-12 actual

2012-13 actual

2013-14 actual

2014-15 target

2014-15 Actual

Reasons for significant variance

Percentage of vehicle examinations completed in accordance with the Australian Design Rules assessed by audit (safe vehicles)

99.25% 87.75% 85% 100% 90% DoT has identified improvements in workflow practices associated with the electronic Vehicle Inspection System at Authorised Inspection Stations (AIS).From October 2014, DVS introduced a new online electronic solution whereby AIS providers return the original certificate of inspection forms directly to DVS on a monthly basis which has improved this index.It is anticipated performance will continue to improve once the new process has been in place for a full year.

Percentage of driver licences issued that comply with the Graduated Driver Training and Licensing system (GDTLS) assessed by auditThe road laws as defined in the Road Traffic (Administration) Act 2008 confers on Transport responsibility for licensing the State’s drivers. Section 16 of the Road Traffic (Authorisation to Drive) Regulations 2008 details the requirements prescribed under section 42 of the Act. Drivers must demonstrate that they are competent to drive a vehicle through passing theoretical and practical tests, completing the prescribed hours of supervised driving and passing a computerised hazard perception test.

This indicator measures the extent to which licensing of drivers is conducted according to processes designed to establish levels of competence pursuant to the provisions of the road laws as defined in the Road Traffic (Administration) Act 2008 and related regulations.

Department of Transport Annual Report 2014-15

Page 55: DOT Annual Report 2015 · Web viewThe Annual Report has been prepared in accordance with the provisions of the Financial Management Act 2006 and fulfils the Department of Transport’s

2011-12 actual

2012-13 actual

2013-14 actual

2014-15 target

2014-15 actual

Reasons for significant variance

Percentage of driver licences that comply with the Graduated Driver Training and Licensing system (GDTLS) assessed by audit

82.0% 87.5% 87% 100% 96% No significant variance noted this year between target and actual.

Efficiency Key Performance IndicatorsService two: Driver and vehicle servicesThe road laws as defined in the Road Traffic (Administration) Act 2008 confers on DoT responsibility for licensing the State’s drivers and registering vehicles. Drivers must demonstrate that they are competent to drive a vehicle through passing theoretical and practical tests, completing the prescribed hours of supervised driving and passing a computerised hazard perception test.

Vehicles must be registered before they may lawfully be used on the road. Registration is conferred only where a vehicle is roadworthy.

This service contributes to the Government’s Results Based Service Delivery of ‘Greater focus on achieving results in key service delivery areas for the benefit of all Western Australians’, through:

setting motor vehicle standards in accordance with national and State Government requirements, examining motor vehicles for compliance with those standards and registering and transferring compliant motor vehicles;

setting standards and requirements within government policies for the issue of a licence to drive on roads;

assessing driver competency, issuing and renewing driver licences in accordance with national and state government requirements and driver competency standards;

maintaining a database of registered vehicles and drivers, and managing vehicle identification numbers, to support the enforcement of road traffic and other relevant laws;

collecting revenue for vehicle and driver licensing on behalf of other government agencies; and

informing and educating road users about driver licensing, vehicle registration and related requirements.

The key efficiency performance indicators used to measure this performance are:

Average cost per vehicle and driver transactionReasons for significant varianceNo significant variance noted this year between target and actual.

Average cost per vehicle inspectionReasons for significant varianceThe variance is primarily due to increased Authorised Inspection Station (AIS) commission payments as the proportion of inspections performed in the metropolitan area shifts from DoT

Department of Transport Annual Report 2014-15

Page 56: DOT Annual Report 2015 · Web viewThe Annual Report has been prepared in accordance with the provisions of the Financial Management Act 2006 and fulfils the Department of Transport’s

to AIS faster than anticipated.

DoT will continue to transition its business to accommodate this shift.

Average cost per driver assessmentReasons for significant varianceNo significant variance noted this year between target and actual.

Percentage of drivers’ licence cards issued within 21 days of completed applicationReasons for significant varianceNo significant variance noted this year between target and actual.

Outcome three: Integrated transport systems that facilitate economic developmentThe transport function is integral to business and commerce and important for social interaction and connecting communities. Therefore a major focus of DoT is on strategic transport policy and planning across the range of public and commercial transport systems that service WA.

DoT, through its Policy, Planning and Investment Division, develops, integrates and regulates the State’s transport systems and infrastructure.

DoT determines, through its policy and planning role, the location of major transport routes and infrastructure, their suitability for a range of transport services and how each integrates into the broader transport system for boats, trains, planes and vehicles.

DoT measures its effectiveness in meeting this outcome through measuring:

Percentage of containerised freight transported via rail in relation to total metropolitan container movements to and from Fremantle port.

Percentage of containerised freight transported via rail in relation to total metropolitan container movements to and from Fremantle port.The Fremantle Inner Harbour is serviced by both road and rail. The rail container service plays an important role in reducing truck movements on port roads and thereby addressing road congestion, noise, accidents and emissions. The State Government has a long-term target of transporting 30 per cent of all Inner Harbour containers by rail.

The North Quay Rail Terminal (NQRT) operator has received financial support in the form of a subsidy from the State Government since 2006 to support the abovementioned objectives. The support has been in recognition of the strategic importance of rail and the difficulty for rail to compete with road transport over short distances. DoT manages the current five year $15.5 million subsidy allocation. The current arrangement will cease in June 2017.

The subsidy received by the NQRT operator is passed on to its customers through reduced prices. The price per container transported by rail includes the additional handling costs associated with rail and the cost to transport containers between NQRT and the stevedore yards or to other container parks located in the Inner Harbour. These NQRT related costs are not incurred when road transport services are used from the outset. The subsidy assists in reducing the difference between the road and rail transport costs associated with transporting a container, thereby making rail transport a more attractive option.

Department of Transport Annual Report 2014-15

Page 57: DOT Annual Report 2015 · Web viewThe Annual Report has been prepared in accordance with the provisions of the Financial Management Act 2006 and fulfils the Department of Transport’s

The total annual subsidy amount and rate per Twenty Foot Equivalent Unit (TEU) container gradually reduces over time. The intention is for funding assistance to reduce over time as rail volumes grow and rail establishes itself in the market.

The rail container service experiences short to medium term fluctuations in the number of containers transported due to general economic conditions, commercial decisions and seasonal factors. However, total container trade through the port, including rail volumes, are expected to continue to grow over the long-term.

2011-12 actual

2012-13 actual

2013-14 actual

2014-15 target

2014-15 actual

Reasons for significant variance

Percentage of containerised freight transported via rail in relation to total metropolitan container movements to and from Fremantle Port

13.4% 13.8% 13.6% 14.5% 13.2% Rail growth was on target until the temporary closure of the Fremantle rail bridge in August 2014, following damage caused by a vessel.Rail containers were transported by road for three weeks while the bridge was closed, which significantly reduced rail’s market share.Other factors such as a reduction in containerised grain also contributed to the variance.

Efficiency Key Performance IndicatorsService three: Strategic transport policy and integrated planningThis service contributes to the Government’s Framework for the Strategic Management goal ‘State building – major projects’ by providing leadership for strategic management, development and protection of economic transport nodes and networks through:

the provision of an integrated transport policy framework to guide Government and the private sector in decision making;

the provision and coordination of integrated state-wide transport policy including those of national significance and those involving multi-modal solutions;

ensuring the transport policy framework supports cost effective transport systems and services.

developing an agreed state-wide integrated transport strategy;

undertaking state wide capital investment planning, evaluation and prioritisation;

integrated planning for major transport system projects;

development of funding principles and pricing signals to ensure appropriate development and use of transport assets;

improving freight access to key terminals, improving freight flows and increasing competitiveness through reduced costs;

reducing the costs associated with road trauma by enhancing the accessibility and safety of public transport systems;

Department of Transport Annual Report 2014-15

Page 58: DOT Annual Report 2015 · Web viewThe Annual Report has been prepared in accordance with the provisions of the Financial Management Act 2006 and fulfils the Department of Transport’s

providing for the efficient distribution of goods and services to business and the community;

ensuring flexibility to meet the demands of a changing economy and market environments; and

enabling commuter access to industrial centres and to the services and goods they require.

The key efficiency performance indicators used to measure this performance are:

Average cost per policy hour for strategic transport policy developmentReasons for significant variance No significant variance noted this year between target and actual.

Average cost per planning hour for integrated transport planning developmentReasons for significant variance No significant variance noted this year between target and actual.

MINISTERIAL DIRECTIVESNo ministerial directives were received during the 2014-15 financial year.

OTHER FINANCIAL DISCLOSURESPricing policies of services providedDoT reviews fees and charges annually to reflect, where legally permissible, full cost recovery in the provision of services, pursuant to the departmental policy for costing and pricing.

The following gazettes contain variations to DoT’s fees and charges for the 2014-15 financial year:

Western Australian Government Gazette No. 71 dated 16 May 2014;

Western Australian Government Gazette No. 77 dated 30 May 2014;

Western Australian Government Gazette No. 85 dated 13 June 2014; and

Western Australian Government Gazette No. 95 dated 27 June 2014.

Major capital projectsMajor capital projects are those over $5 million.

Department of Transport Annual Report 2014-15

Page 59: DOT Annual Report 2015 · Web viewThe Annual Report has been prepared in accordance with the provisions of the Financial Management Act 2006 and fulfils the Department of Transport’s

Capital projects incompleteExmouth Boat Harbour

Expected year of completion: 2015-16

$’000

Project life spent up to 30 June 2015 1,000

Estimated cost to complete 17,275

Estimated total cost of project 18,275

EMPLOYMENT AND INDUSTRIAL RELATIONSFull-time equivalents (FTE) and headcount, as at 30 June 2015:

Status Headcount* FTE*

Permanent full-time 1,135 1,135.00

Permanent part-time 200 124.05

Temporary full-time 134 134.00

Temporary part-time 26 16.68

Senior Executive Service 19 19.00

Total 1,514 1,428.73

*Headcount and FTE numbers include paid employees and employees on unpaid leave.

During 2014-15, DoT continued to work in partnership with the Joint Consultative Committee and union delegates to discuss initiatives and address any issues.

FREEDOM OF INFORMATIONDoT’s Freedom of Information (FOI) Unit is the initial contact point for members of the public, applicants, third parties, the Office of the Information Commissioner and other public sector agencies for all FOI-related matters.

FOI statistics for 2014-15, compared with previous years, are listed below.

In accordance with the Freedom of Information Act 1992, DoT is required to respond to FOI access applications within 45 days of receipt, unless an extension is granted. The average time to process applications during 2014-15 was 12 days.

Department of Transport Annual Report 2014-15

Page 60: DOT Annual Report 2015 · Web viewThe Annual Report has been prepared in accordance with the provisions of the Financial Management Act 2006 and fulfils the Department of Transport’s

FOI application Number 2012-13 Number 2013-14 Number 2014-15

Total received (not including those transferred to another agency)

178 204 257

Internal reviews 2 10 19

External reviews 1 2 7

Transferred to another agency 5 15 7

CUSTOMER FEEDBACK DoT’s Complaints Handling Policy provides a flexible approach where complaints can be made in person, by phone, fax, online or in writing.

The implementation of this policy in line with the Australian Standard on Complaints Handling (AS ISO 10002-2006) is guided by DoT’s Complaints Handling Procedures.

Complaints are managed through DoT’s Customer Feedback System (CFS), which is administered within Objective – the department’s electronic document and record management system.

As well as complaints, the CFS records compliments, general feedback and requests for information. However, this feedback may also be handled directly by individual DoT directorates.

Customer feedback may relate to access to information, service standards and facilities (including fees, fines and costs) or the legislation, regulations and standards that DoT administers.

Feedback statistics recorded through the CFS for 2014-15, compared with previous years, are shown below.

The total feedback received by DoT in 2014-15 decreased by two per cent from 2013-14. DoT’s largest directorate, Driver and Vehicle Services, accounted for 90 per cent of the feedback received.

Feedback type Number received 2012-13

Number received 2013-14

Number received 2014-15

Complaints 1,426 2,060 2,225

Compliments, feedback and requests for information

1,407 1,700 1,468

Total 2,833 3,760 3,693

Department of Transport Annual Report 2014-15

Page 61: DOT Annual Report 2015 · Web viewThe Annual Report has been prepared in accordance with the provisions of the Financial Management Act 2006 and fulfils the Department of Transport’s

INVESTING IN OUR GREAT PEOPLEDeveloping our people managers In 2014-15, DoT continued to place a high priority on developing the people management competencies of its frontline leaders.

People Managers ProgramThrough the ongoing success of the People Managers Program, an additional 40 first-time and entry-level managers were equipped with practical skills to build and lead high-performing teams.

The 12-month program is specifically tailored to DoT’s operations so participants can apply their new skills and knowledge in their everyday roles. People managers take part in four hands-on workshops and undertake a range of assessment activities, with successful completion earning them a nationally-accredited Certificate IV in Frontline Management.

In February 2015, 20 managers graduated from the program, with the remaining 20 due to graduate in September 2015. The program has been well-received by both the managers and their teams and will continue to mid-2016 when it scheduled to be reviewed.

Leadership Development and Induction ProgramDoT developed and implemented a Leadership Development and Induction Program for new DVS Centre Team Leaders in 2014-15. The program is specifically tailored to the skills required to succeed as a leader in the dynamic centre environment and covers key competencies required to be an effective people manager as well as personal and leadership development.

The program assisted 16 newly appointed Team Leaders to excel in their unique and challenging roles in 2014-15 and will be used to induct similar intakes in the future.

Setting staff up for success through Performance Partnership ProgramDoT’s Performance Partnership Program (PPP) provides a framework for people managers and employees to have ongoing discussions about performance objectives, measures and training and development needs.

In 2014-15, DoT continued to implement and improve the PPP to ensure all staff have individual performance plans in place aligned to its strategic direction.

A tailored ‘PPP Express’ training program was rolled out to support managers in setting their teams up for success. The five, shorter, more interactive modules offered cover a range of topics including addressing performance issues. To date, 21 per cent of people managers have attended at least one module and this number is expected to grow as the training continues.

An upward feedback process was also successfully piloted and incorporated into the program. It gives employees the opportunity to provide their managers with constructive feedback based on how well they believe their performance is aligned to DoT’s core values. Managers then participate in a coaching session to explore the results and complete an action plan to assist in further aligning their behaviours to the values.

Overall, employee participation in the PPP improved throughout the year, with the number of staff with an individual performance plan in place increasing from 73 per cent in September 2014 to 93 per cent in February 2015. Further, program reporting indicates that 98 per cent

Department of Transport Annual Report 2014-15

Page 62: DOT Annual Report 2015 · Web viewThe Annual Report has been prepared in accordance with the provisions of the Financial Management Act 2006 and fulfils the Department of Transport’s

of DoT staff are meeting expectation.

In 2015-16, DoT will continue to improve the PPP by developing career coaching skills for managers and learning sessions for employees.

Building priority skills with scholarship program DoT’s scholarship program demonstrates its commitment to ongoing learning for staff by supporting employees to undertake relevant formal study.

The program provides valuable opportunities for employees to improve their skills and knowledge in fields that have been identified as being of high priority in enabling DoT to achieve its business objectives.

In 2014-15, the program targeted business-related study, with 11 scholarships awarded to recipients in the fields of transport economics, policy and engineering as well as project and asset management and business administration.

CREATING A WORKPLACE WHERE PEOPLE WANT TO BELONGMoving towards a more culturally diverse and aware workforceDoT continues to implement strategies outlined in the DoT Workforce and Diversity Plan 2012-2016 to move towards a more culturally diverse and aware workforce.

Key among these strategies is ongoing participation in the Public Sector Aboriginal Traineeship Program to increase Aboriginal representation within DoT. DoT aims to increase its participation levels in 2015-16, requesting five metropolitan and three regionally based trainee placements.

Other achievements contributing to the implementation of the plan in 2014-15 include:

conducting a review of the DoT diversity framework to enable a more effective approach to embracing and improving cultural diversity;

providing online training courses for new and existing staff aimed at increasing awareness and understanding of the needs of Aboriginal and Torres Islander peoples and other ethnic groups; and

embracing National Aborigines and Islanders Day Observance Committee (NAIDOC) Week celebrations.

In 2015-16, DoT will review the strategies outlined in the plan and identify new strategies to continue to enable a culturally diverse and aware workforce from 2016-2020.

Continuing our cultural development journey Throughout the year, DoT continued to embed its core values of Clear Direction, Fresh Thinking, Excellent Service and Great People across the agency through a number of cultural development activities.

The activities are aimed at bringing these values – which represent who we are, what we do and how we want to work – to life at DoT.

Department of Transport Annual Report 2014-15

Page 63: DOT Annual Report 2015 · Web viewThe Annual Report has been prepared in accordance with the provisions of the Financial Management Act 2006 and fulfils the Department of Transport’s

The Fresh Think Tank, DoT’s online innovation forum, is now home to almost 500 business improvement ideas submitted by employees all over the state. More than 70 of these ideas have been successfully implemented and are delivering benefits to DoT staff and customers.

In April 2015, a cross-organisation team focusing on Excellent Service came together to identify, share and promote examples of DoT staff living this value and develop tools and resources to benefit our internal and external customers.

This approach has proved successful in embedding the values of Clear Direction and Fresh Thinking in previous years and will continue in 2015-16 with Great People. DoT will also continue to ensure its policies, procedures, plans and people practices are aligned to the values.

Enhancing staff wellbeing DoT offered a range of health promotion initiatives to enhance the wellbeing of staff in 2014-15. The initiatives, delivered through DoT’s Wellness Program, included online and one-on-one health checks, flu vaccinations and access to a range of information and services through the annual Health Fair.

DoT also offered ALERT (Awareness Links and Enable Resilient Teams) sessions aimed at increasing awareness and understanding of mental health, depression, anxiety and suicide prevention.

Recognising exceptional employees DoT’s annual reward and recognition program, the Radar Awards, continued to acknowledge exceptional employees living DoT’s values and contributing to its strategic goals.

GOVERNANCE DISCLOSURESContracts with senior officersDuring 2014-15, other than normal contracts for employment of services, no senior officers or firms of which senior officers are members, or entities in which senior officers have substantial interests, had any interests in existing or proposed contracts with DoT.

OTHER LEGAL REQUIREMENTSAct of Grace paymentsDoT did not make any Act of Grace payments in 2014-15.

Advertising As required under section 175ZE of the Electoral Act 1907, the following statement relates to advertising expenditure, which includes creative development, media placement, market research, polling and direct mail.

Department of Transport Annual Report 2014-15

Page 64: DOT Annual Report 2015 · Web viewThe Annual Report has been prepared in accordance with the provisions of the Financial Management Act 2006 and fulfils the Department of Transport’s

Advertising agency 2014/15

Cooch Creative Pty Ltd $15,740

$15,740

Media advertising

Media advertising – non-campaign

Adcorp Australia Limited $102,900

Media advertising – campaign

Carat Australia Media Services Pty Ltd $47,440

$150,340

Market research $89,950

Polling Nil

Direct mail Nil

Total $256,030

Disability Access and Inclusion PlanDoT is committed to providing people with disabilities, their families and carers, the same opportunities to access our products and services as any other member of the community.

This commitment is demonstrated in the Disability Access and Inclusion Plan (DAIP) 2012-17, which identifies a number of key strategies to improve access and inclusion.

These strategies are applied to projects and services delivered across DoT and in 2014-15, universal access to the new Augusta Boat Harbour and Port Geographe coastal facilities was delivered.

Key accessibility features of the Augusta Boat Harbour, which opened in October 2014, include:

a universal access pontoon, including ramp access, to provide unassisted wheelchair access to vessels for boarding;

unassisted wheelchair access from bus parking bays to the floating pen system;

boat launching ramps with two floating jetties that meet assisted accessibility requirements; and

landscaped plaza area with accessible grade ramps and tactiles.

Department of Transport Annual Report 2014-15

Page 65: DOT Annual Report 2015 · Web viewThe Annual Report has been prepared in accordance with the provisions of the Financial Management Act 2006 and fulfils the Department of Transport’s

The new recreational spaces at Port Geographe, completed as the final component of the reconfiguration project in May 2015, provide improved access through:

accessible playground equipment including an Ability Play Whirl that can accommodate wheelchairs;

accessible boardwalk to the lagoon beach;

accessible concrete path grades and ramps with tactiles; and

a wheelchair-accessible pathway right to the end of the western breakwater.

As part of its four-year trial of purpose-built taxis (PBTs), DoT also commenced a small-scale pilot to access the London Taxi Company TX4 taxi’s suitability to carry passengers in wheelchairs.

The pilot, developed in consultation with the Disability Services Commission and the Insurance Commission of Western Australia, involves a small number of PBTs and passengers in wheelchairs who regularly use taxis. As part of the pilot, DoT appointed National Disability Services (NDS) to develop safe practice guidelines for participants and to develop and deliver training to PBT drivers.

It is anticipated that the pilot will conclude in August 2015. NDS will then prepare a report on the outcomes of the pilot and provide advice on the suitability and limitations of the TX4 as a wheelchair-accessible vehicle.

Reconciliation Action PlanDoT is committed to conducting business in ways which promote our relationships with all Aboriginal and Torres Strait Islander people.

This commitment is demonstrated in the Reconciliation Action Plan 2012-2016, which outlines strategies aimed at promoting awareness of the diversity, history, heritage and culture of Aboriginal and Torres Strait Islander people and increasing opportunities for participation.

In 2014-15, DoT continued to effectively engage with Aboriginal and Torres Strait Islander people through a variety of formal and informal mechanisms. Specifically, DoT:

engaged with the Department of Aboriginal Affairs on general reconciliation planning;

engaged with the CEO Aboriginal Corporation in relation to provision Regional Airports Development Scheme funding;

engaged with Aboriginal corporations and private industry to deliver licensing services through the Remote Areas Licensing program; and

participated in the National Indigenous Driver Licensing Working Group to assist in developing national solutions to issues faced by Aboriginal people seeking to obtain a driver’s licence.

DoT continued to provide marine safety training for Aboriginal students through its Marine Safety Education Boatshed throughout the year. Thirteen students from Clontarf Aboriginal College attended a Recreational Skipper’s Ticket course in the metropolitan area, gaining the knowledge and practical skills needed to safely operate a powerboat in WA. DoT also provided nine weeks of marine education training to young people in regional areas, including Aboriginal youths from remote communities.

In February 2015, DoT established a 12-month contract with stationery supplier Kulbardi Pty Ltd. Kulbardi is Australia’s largest Aboriginal business and contributes part of its profits back to Aboriginal communities.

Department of Transport Annual Report 2014-15

Page 66: DOT Annual Report 2015 · Web viewThe Annual Report has been prepared in accordance with the provisions of the Financial Management Act 2006 and fulfils the Department of Transport’s

In recognition of the State Government Aboriginal Economic Participation strategy and amendments to the State Supply Commissions policy, the Department of Finance granted DoT exemption from the mandatory use of current Common Use Agreement’s for the purchase of copy paper, envelopes, office stationery and kitchen supplies.

The contract leads the way in DoT’s investment in Aboriginal economic participation and DoT looks forward to fostering a working partnership with Kulbardi.

Compliance with Public Sector Standards and ethical codesDoT is committed to fostering a culture of ethical behaviour and ensuring the highest standards of probity and accountability in all interactions. As public servants, DoT’s employees are ultimately working for the people of Western Australia, who expect them to act with integrity and to look after their interests. This places DoT in a position of trust, requiring standards of ethical behaviour that reflect community expectations.

During 2014-15, DoT continued to review its human resource management policies and procedures to empower managers to effectively manage their people in line with DoT’s culture and values.

These reviews resulted in the following:

The Suspected Breaches of Discipline Policy and Procedure was updated to provide managers with clear direction on how to manage breaches of discipline.

The Grievance Resolution Policy and Procedure was updated to assist managers and employees to better understand and resolve these types of situations.

The Conflict of Interest Policy and Procedure and DoT Code of Conduct were updated to ensure DoT employees do not accept gifts, incentives or hospitality from external customers, contractors or members of the public.

New leave management, time and attendance and flexible working hours policies and procedures were developed to ensure managers and employees understand their responsibilities concerning the accrual and acquittal of leave. In 2015-16, DoT will commence work on a new time and attendance recording system to allow for more streamlined and effective management of leave bookings and approvals.

Additionally, a Management of Displaced Employees Policy and Procedure was developed to incorporate new State Government regulations concerning displaced employees. The new policy and procedure will ensure a greater responsibility is placed on managers to support and manage displaced officers to ensure a positive outcome is reached for both the employee and DoT.

DoT continued to make its Accountable and Ethical Decision Making online training program available to staff throughout 2014-15, with over 95 per cent of employees having completed the program. To ensure staff are consistently provided with up-to-date information around accountable and ethical decision making, DoT also developed an online refresher training program in 2014-15.

Compliance issuesTen breach of standard claims relating to the Employment Standard were received in 2014-15.

Four of the claims were considered and dismissed by the Public Sector Commissioner; three were withdrawn by the claimants; and one was considered by DoT and upheld. The remaining two claims remain ongoing.

In 2014-15, 12 cases of non-compliance with the Code of Ethics/Code of Conduct were reported, eight of which resulted in disciplinary investigations.

Department of Transport Annual Report 2014-15

Page 67: DOT Annual Report 2015 · Web viewThe Annual Report has been prepared in accordance with the provisions of the Financial Management Act 2006 and fulfils the Department of Transport’s

Better recordkeepingDoT is committed to best practice recordkeeping to ensure compliance with the State Records Act 2000 (the Act) as well as enable best for business outcomes for the agency. The following information is provided in accordance with the State Records Commission Standard 2, Principle 6.

Efficiency and effectiveness of DoT’s recordkeeping systemsDoT has systems in place to effectively manage records and is committed to electronic recordkeeping including the digitisation of hardcopy records where appropriate.

All DoT staff have access to Objective, the department’s electronic document and record management system, and use it to capture and manage records in line with departmental policies and procedures.

Recordkeeping training and induction programsThe Online Recordkeeping Awareness Training Course is mandatory for all DoT staff. The course covers individual employee’s obligations to comply with both DoT’s recordkeeping policies and the Act.

Assessment of the course is integrated into the online module and feedback provided by staff is monitored and reviewed. Course content is regularly assessed to ensure it reflects current operational and administrative practices and processes.

Around 1,500 DoT staff, including contractors, are enrolled in the online module and of these, 88 per cent have completed the course.

An Objective online training course is available for all new staff and as a resource for existing staff. Comprehensive face-to-face training is also provided to individuals and groups as required.

DoT’s employee induction program also includes information on recordkeeping and the use of Objective and addresses employees’ roles and responsibilities in creating, managing and maintaining government records.

Training effectivenessThe effectiveness of DoT’s recordkeeping and Objective training is evidenced by the increasing number of corporate documents stored and managed in Objective. DoT continues to consolidate Objective as the corporate repository through its focus on electronic recordkeeping.

GOVERNMENT POLICY REQUIREMENTSSubstantive equalityDoT is committed to providing services to WA’s diverse community in a fair and non-discriminatory manner. In order to achieve this, DoT recognises the cultural diversity of its customers and caters for this appropriately.

During the year, the elimination of barriers to equality in existing services, policies and practices continued to be a priority, with a focus on raising staff awareness of substantive equality, improving the way we communicate with Culturally and Linguistically Diverse (CaLD) customers and improving outcomes for people in remote Western Australia through the obtainment and retention of a driver’s licence.

In doing this, DoT worked closely with the Equal Opportunity Commission and the Office of Multicultural Interests. DoT also continued to engage with and participate in the CaLD

Department of Transport Annual Report 2014-15

Page 68: DOT Annual Report 2015 · Web viewThe Annual Report has been prepared in accordance with the provisions of the Financial Management Act 2006 and fulfils the Department of Transport’s

community through the CaLD Driver Licensing Reference Group and the Western Australian CaLD Across Government Network.

Raising staff awarenessDoT continued to raise awareness of substantive equality by offering online training to all staff through Diverse WA’s Cultural Competency Training program and making this compulsory for customer-facing employees. Information on substantive equality was also provided to new employees through DoT’s induction program.

Communicating with CaLD customersDoT’s Language Services Policy and Procedure ensures employees are aware of the strategies and available resources to effectively and appropriately communicate with CaLD and hearing impaired customers.

In 2014-15, DoT appointed ONCALL Interpreters and Translators to provide interpreting and translating services under a contact arrangement. ONCALL provided awareness training to key staff, including those based in DoT’s Driver and Vehicle Services (DVS) centres and Customer Contact Centre.

To assist these staff in identifying when to engage interpreting and translating services, DVS developed Language Services Policy Business Rules. The rules also provide clear direction on how to work with an interpreter or translator to ensure equal access to DoT services and have since been adopted and tailored for use by other business areas across DoT.

Improving outcomes for remote customersDoT’s Remote Areas Licensing program continued to provide licensing services to customers in remote locations across the State in 2014-15.

The program is a combination of strategic project and operational work which aims to:

reduce barriers faced by people in remote areas when seeking to enter the driver licensing system;

increase access to all driver and vehicle licensing services for people living in remote areas and provide equitable and sustainable delivery of service to all customers; and

increase education and awareness of driver and vehicle licence requirements in remote areas.

Mobile service delivery to remote areas was expanded to the Mid West region with a Remote Licensing team commencing operation out of DoT’s Geraldton office in December 2014.

Throughout the financial year, four regionally-based teams servicing Mid West, Goldfields, Gascoyne, Kimberley and Pilbara:

issued, re-issued, transferred or renewed a total of 279 driver’s licences;

conducted 428 practical driving assessments; and

delivered 433 learner’s permit theory tests (including verbal tests).

The teams also attended a number of community open days, organised by the Department of the Attorney General, as part of a multi-agency approach to driver licensing and Aboriginal justice issues.

Theory testing agreements were expanded, with a new provider appointed in Carnarvon. In 2014-15, 469 people successfully completed a theory test through one of DoT’s authorised providers. Program staff continue to work closely with these providers by delivering training, materials and ongoing support.

Department of Transport Annual Report 2014-15

Page 69: DOT Annual Report 2015 · Web viewThe Annual Report has been prepared in accordance with the provisions of the Financial Management Act 2006 and fulfils the Department of Transport’s

Audit and Risk Management CommitteeThe Audit and Risk Management Committee (ARMC) plays a key role in fulfilling the DoT’s corporate governance and monitoring responsibilities in relation to reporting, internal control structure, risk management systems, external audit and internal audit functions.

The committee is made up of the following members:

Director General – Transport (Chair of the committee);

Managing Director – Policy Planning and Investment;

Managing Director – Transport Services;

Director – Office of the Director General;

MRWA Executive Director – Finance and Commercial Services; and

KPMG (contracted internal auditor).

The committee also contains two ex-officio members:

Executive Director – Investment and Finance Coordination (Chief Finance Officer); and

Manager – Governance and Audit (Office of the Director General).

A representative from the Office of the Auditor General also attends meetings as an independent observer.

The committee met five times in 2014-15.

Internal AuditDoT’s internal audits are conducted by DoT’s contracted internal auditors, KPMG, in accordance with the Financial Management Act 2006 and Institute of Internal Auditors International Standards for the Professional Practice of Internal Auditing.

During 2014-15, internal audits were carried out on:

budget system management processes;

coastal infrastructure standardisation of fees and charges;

driver’s licence processing;

information technology systems development;

omnibus licensing and compliance process; and

vehicle inspections governance.

Recommendations derived from the internal audits are managed and monitored through DoT’s Audit Recommendation Management System. The  implementation status of these recommendations is reported to the ARMC on a quarterly basis.

Risk ManagementDoT’s comprehensive risk management process meets the requirements of Treasurer’s Instruction 825 and the Public Sector Commissioner’s Circular 2015/03: Risk Management and Business Continuity Planning, and is aligned to the international standard AS/NZS ISO 31000:2009 Risk Management – Principles and Guidelines.

DoT’s structured Risk Management approach is integrated into planning, management and operational processes and assists DoT to achieve its desired outcomes by providing a transparent process that identifies what is essential to success and demonstrates the decision making process regarding the acceptance of risks.

Department of Transport Annual Report 2014-15

Page 70: DOT Annual Report 2015 · Web viewThe Annual Report has been prepared in accordance with the provisions of the Financial Management Act 2006 and fulfils the Department of Transport’s

The ARMC provides oversight for risk management across DoT. Risks rated as high are reported on to Corporate Executive and the ARMC on a quarterly basis.

OCCUPATIONAL SAFETY, HEALTH AND INJURY MANAGEMENTIn accordance with the Public Sector Commissioner’s Circular 2009-11: Code of Practice: Occupational Safety and Health in the Western Australian Public Sector, DoT complies with the requirements of the Occupational Safety and Health Act 1984, the Workers’ Compensation and Injury Management Act 1981 and the Code of Practice: Occupational Safety and Health in the Western Australian Public Sector 2007.

Our commitment DoT recognises the value of its employees and is committed to preventing injury and illness by providing a safe and healthy work environment. The success of occupational health and safety (OHS) and injury management (IM) activities is reliant upon the active participation and cooperation of all staff. DoT’s OHS commitment is designed to raise awareness of safety and health obligations and to promote safer work practices.

This commitment is strongly supported at the executive level. DoT’s OHS Policy has been endorsed by the Director General and the Corporate OHS Management Committee was established on the Director General’s behalf. The committee is comprised of all Executive Directors, General Managers and DoT’s OHS Branch and is accountable for the management of OHS within DoT, responsible for identifying and implementing initiatives, and charged with making recommendations on policy and strategy to the Corporate Executive.

In the event that a workplace injury occurs, DoT has an established IM program which details the steps taken to assist injured employees to return to work as soon as medically appropriate. The procedure ensures that IM intervention occurs promptly and effectively, so that injured employees can remain at work or return to work at the earliest appropriate time. DoT’s IM procedure is compliant with the requirements of the Workers’ Compensation and Injury Management Act 1981 and the Workers’ Compensation Code of Practice (Injury Management) 2005.

Both DoT’s OHS and IM systems are available to staff on the intranet. OHS and IM information is widely communicated as part of training sessions designed for new employees and managers/supervisors.

OHS information is also communicated through various OHS sub-committees. Due to the variation in roles and functions of DoT’s business units, as well as the different physical locations, there are three sub-committees chaired by a relevant Executive Director or General Manager: the Marine House and Regional Services OHS Sub-committee; the Driver and Vehicles Services and Passenger Services OHS Sub-committee; and the 140 William Street OHS Sub-committee.

Key achievements A number of key OHS and IM achievements were made in 2014-15:

New Alcohol and Drug Policy and Procedure developed and endorsed. The policy and procedure outline a zero tolerance approach to alcohol and drugs in the workplace in line with DoT’s values.

Department of Transport Annual Report 2014-15

Page 71: DOT Annual Report 2015 · Web viewThe Annual Report has been prepared in accordance with the provisions of the Financial Management Act 2006 and fulfils the Department of Transport’s

Continued focus on training, with 88 per cent of managers trained in their OHS and IM responsibilities and 98 per cent of safety and health representatives completing a mandatory five-day training course tailored to DoT’s OHS policies, procedures and guidelines.

Ergonomic information sessions conducted at major DoT sites and sessions focusing on vehicle ergonomics conducted in all regional offices.

Quarterly coaching sessions provided to safety and health representatives.

OHS and IM training offered to employees based in regional offices via video conference.

Successful delivery of DoT’s Wellbeing program which included flu vaccinations, online and one-on-one health checks, Lunch and Learn information sessions and access to corporate gym membership and corporate health insurance discounts.

ALERT (Awareness Links and Enable Resilient Teams) sessions aimed at increasing awareness and understanding of mental health, depression, anxiety and suicide prevention included in DoT’s ongoing corporate training.

Successful ongoing implementation of the Management of Customer Aggression Policy and Guidelines and Managing Difficult Customer Interactions training sessions, which support employees in managing difficult and aggressive customers.

‘DoT’s traffic light approach to dealing with aggressive customers’ visual prompt developed for display at customer-facing work stations to assist employees in dealing with aggressive customers.

Successful staff relocations to new DoT premises in the Stirling precinct and Mirrabooka DVS Centre, which included the review of office layout, furniture, emergency procedures, risk assessments and first aid requirements.

Suspicious Packages and Hazchem Spill Kit and accompanying procedures and instructions distributed to all DoT locations where mail is opened.

Bomb Threat Checklist made available on DoT’s intranet to inform and educate employees and guide them in the event that a threat is received.

Consultation mechanismsAll DoT staff are committed to improved and effective consultation in the workplace. Consultation provides employees with an opportunity to participate fully in decisions which impact their work lives. The establishment of an appropriate forum for consultation has resulted in better decision-making, with shared decisions leading to more effective implementation.

DoT’s three OHS sub-committees, comprised of safety and health representatives and managers, are focused on the continuous improvement of OHS performance. The sub-committees meet quarterly to discuss matters relating to workplace issues that affect the health and welfare of employees. Both the agenda and meeting minutes for each of these meetings, as well as those of the Corporate OHS and Wellbeing Committee meetings, are displayed on dedicated OHS noticeboards across all DoT sites.

The safety and health representatives, in consultation with managers, are responsible for updating the noticeboards accordingly. The effectiveness of the various OHS sub-committee meetings is measured by attendance rates, which form part of the key performance indicators reported back to the Corporate Executive.

Department of Transport Annual Report 2014-15

Page 72: DOT Annual Report 2015 · Web viewThe Annual Report has been prepared in accordance with the provisions of the Financial Management Act 2006 and fulfils the Department of Transport’s

During the year, DoT discussed and resolved issues raised by employees, reviewed accident and incident forms to ensure that hazards were addressed to eliminate or reduce future issues, discussed injury trends and identified preventative measures that promote a safe working environment.

Compliance with the injury management requirements of the Workers’ Compensation and Injury Management Act 1981As at 30 June 2015, DoT had 31 open workers’ compensation claims. Only two of the claimants were certified unfit, with the remainder on Return to Work programs. All 19 of the time-loss claims throughout the year returned to work within 13  weeks of their injury.

DoT has a dedicated Workers’ Compensation and IM Consultant who manages both the workers’ compensation claims and non-work related IM issues. DoT has a strong focus on early intervention and return to work strategies. Managers and supervisors are trained in the importance of good injury management and return to work, promoting a supportive, productive and positive workplace.

OHS system assessment and resultsAn OHS Safety Management System audit of DoT’s safety documentation was conducted in July 2014 to assist DoT in developing a new Corporate OHS Safety Management System aligned to the Australian/New Zealand Standard for Safety Management Systems (AS/NZS 4810).

The audit was conducted by external consultant RiskLink using the WorkSafe Plan Audit Tool and identified positive findings as well as areas for improvement.

The following are the main positive findings:

There was strong evidence to show management’s support of safety, health and wellbeing within DoT.

Each DoT workplace has an OHS Safety Folder containing site-specific OHS documentation including policies, procedures, training matrixes and emergency plans.

DoT supports employees’ flexible working arrangements, including working part-time, purchasing leave and flexi-time. Working from home is also facilitated where possible. All staff working from home undergo a home-based ergonomic assessment.

The Working in Remote Areas Policy and Procedure was developed and endorsed by the Corporate OHS and Wellbeing Management Committee. This policy and procedure provides both managers and staff with the tools and advice needed to travel to WA locations.

Robust processes are in place for managing first aid. All first aid kits are regularly inspected and stocked accordingly, and all staff members providing first aid are adequately trained.

Workplace inspections are conducted bi-monthly, with all hazards identified and managed accordingly in consultation with staff.

All staff are provided with the necessary personal protective equipment to safely undertake their duties.

All managers and supervisors have completed the necessary OHS and IM for Managers training session.

All staff have received both manual tasks and ergonomics training.

Department of Transport Annual Report 2014-15

Page 73: DOT Annual Report 2015 · Web viewThe Annual Report has been prepared in accordance with the provisions of the Financial Management Act 2006 and fulfils the Department of Transport’s

The main areas identified for improvement were:

Develop a Corporate OHS Safety Management System to ensure consistency across all DoT business units.

Develop an OSH Risk Register including common public sector hazards as described in the Code of Practice: Occupational Safety and Health in the Western Australian Public Sector 2007 (bullying, violence/aggression, manual handling, working alone, organisational changes, inadequate physical working environment, inadequate workstations, inadequate work organisation).

Develop an Independent Contractor Management Policy and Procedure for managing contactors visiting DoT sites.

Develop and deliver OHS training for all DoT staff to complement the strong existing OHS induction session for new employees.

Consider including pre-employment as part of the Health Management Strategy.

Continue to align local site-specific OHS activities with the corporate requirements, utilising support from the OHS Branch.

Establish an OHS Training Matrix to record all OHS training undertaken employees.

Include OHS responsibilities in individual job descriptions.

These recommendations for improvement have been detailed in an Action Plan and many are currently being addressed. Most significantly, in  2014-15 DoT completed its new Corporate OHS Safety Management System and is in the process of rolling it out across the business.

Our performanceDoT’s OHS and IM performance in 2014-15 is demonstrated in the table below.

OHS and IM performance 2014-15Measure 2013-14(1) 2014-15 Target Result

Number of fatalities 0 0 0 (zero) Target achieved

Lost time injury (LTI) and/or disease incidence rate

1.578 1.330(2) 0 or 10% reduction

Target achieved

LTI and/or disease severity rate 4.545 5.263(3) 0 or 10% reduction

Target not achieved

Percentage of injured workers returned to work within 13 weeks

95.45% 100%(4) Actual percentage result

100% achieved

Percentage of injured workers returned to work within 26 weeks

95.45% 100%(5) Actual percentage result

100% achieved

Percentage of managers trained in occupational safety, health and injury management responsibilities

86% 88%(6) Greater than or equal to 80%

Target achieved

Department of Transport Annual Report 2014-15

Page 74: DOT Annual Report 2015 · Web viewThe Annual Report has been prepared in accordance with the provisions of the Financial Management Act 2006 and fulfils the Department of Transport’s

Notes:

(1) The results are sourced from DoT’s Annual Report 2013-14.

(2) There were 22 LTI claims lodged in 2013-14, while the number of full-time equivalents in 2013-14 was 1,394. However, there were 19 LTI claims in 2014-15, while the full-time equivalents in 2014-15 were 1,428.

(3) There was one workers’ compensation claim lodged in 2014-15 with greater than 60 days or more lost from work. There were a total of 19 LTI claims in 2014-2015.

(4) All 19 workers’ compensation claims with registered LTIs were returned back to work within 13 weeks.

(5) All 19 workers’ compensation claim with registered LTIs were returned to work within 26 weeks.

(6) The training for managers and supervisors relates to their occupational safety and health and injury management responsibilities. In 2014-15, DoT successfully trained 88 per cent of the managers.

Department of Transport Annual Report 2014-15