doka h frame_staxo100

80
The Formwork Experts 06/2008 Ü GB 999800302 User information Method statement Doka load-bearing tower Staxo 100 98003-287-01

Upload: ajitpushpa

Post on 28-Sep-2015

46 views

Category:

Documents


3 download

DESCRIPTION

Good for heavy slabs and elevated slabs

TRANSCRIPT

  • The Formwork Experts

    06/2008

    GB999800302

    User information

    Method statement

    Doka load-bearing tower Staxo 100

    98003-287-01

  • 2 999800302 - 06/2008

    User information Doka load-bearing tower Staxo 100

    The Formwork Experts

    Introduction

    by Doka Industrie GmbH, A-3300 Amstetten

  • 3999800302 - 06/2008

    Contents Page

    User information Doka load-bearing tower Staxo 100 Introduction

    The Formwork Experts

    Introduction .................................................................................................. 2Elementary safety warnings ........................................................................ 4Eurocodes at Doka........................................................................................ 6

    System description ...................................................................................... 8System overview ........................................................................................10The Staxo 100 frame in detail....................................................................12Practical examples......................................................................................14Adapts to different ground plans, heights, floor shapes and loads .......16

    Assembly (overview)..................................................................................19

    Horizontal assembly...................................................................................20

    Assembling towers in the upright ............................................................ 25Assembling towers in the upright with mounted-ahead railings.......25Assembling towers in the upright: with mounted-ahead 1.20m frames......................................................30Assembling towers in the upright by forklift truck .................................. 34Examples of the system in action .............................................................36

    Repositioning..............................................................................................37Repositioning using wheel units ...............................................................38Lifting by crane ...........................................................................................40Lifting by forklift truck ................................................................................42

    Structural design (overview).....................................................................43

    Standard application: Load capacity up to 70 kN ...................................44

    Custom application: Load capacity up to 85 kN......................................56

    Custom application: Load capacity up to 97 kN......................................58

    General remarks ......................................................................................... 62Combining Staxo 100 with Staxo..............................................................62Anchoring on the structure........................................................................63Back-stays/shoring supports for the load-bearing towers ......................64Adapting to the building layout with single legs .....................................66Inclination adjustment................................................................................69Transporting, stacking and storing ...........................................................70

    Floor prop Eurex 60 550.............................................................................72

    Component overview.................................................................................74

  • The Formwork Experts4 999800302 - 06/2008

    Introduction User information Doka load-bearing tower Staxo 100

    Elementary safety warnings

    User target groups This User Information booklet (Method State-

    ment) is aimed at everyone who will be working with the Doka product or system it describes. It contains information on how to set up this sys-tem, and on correct, compliant utilisation of the system.

    All persons working with the product described herein must be familiar with the contents of this manual and with all the safety instructions it con-tains.

    Persons who are incapable of reading and under-standing this booklet, or who can do so only with difficulty, must be instructed and trained by the customer.

    The customer is to ensure that the information materials provided by Doka (e.g. User Informa-tion booklets, Instructions for Assembly and Use, Operating Instruction manuals, plans etc.) are available to all users, and that they have been made aware of them and have easy access to them at the usage location.

    Remarks on this document This User Information booklet can also be used

    as a generic method statement or incorporated with a site-specific method statement.

    Many of the illustrations in this booklet show the situation during formwork assembly and are therefore not always complete from the safety point of view.

    Further safety instructions, especially warnings, will be found in the individual sections of this document!

    Planning Provide safe workplaces for those using the

    formwork (e.g. for when it is being erected/dis-mantled, modified or repositioned etc). It must be possible to get to and from these workplaces via safe access routes!

    If you are considering any deviation from the details and instructions given in this booklet, or any application which goes beyond those described in the booklet, then revised static cal-culations must be produced for checking, as well as supplementary assembly instructions.

    Rules applying during all phases of the assignment: The customer must ensure that this product is

    erected and dismantled, reset and generally used for its intended purpose under the direction and supervision of suitably skilled persons with the authority to issue instructions.

    Doka products are ONLY to be used in accord-ance with the Doka User Information booklets or other technical documentation provided by Doka.

    The stability of all components and units must be ensured during all phases of the construction work!

    The functional/technical instructions, safety warnings and loading data must all be strictly observed and complied with. Failure to do so can cause accidents and severe (even life-threaten-ing) damage to health, as well as very great material damage.

    Fire-sources are not permitted anywhere near the formwork. Heating appliances are only allowed if properly and expertly used, and set up a safe distance away from the formwork.

    The work must take account of the weather con-ditions (e.g. risk of slippage). In extreme weather, steps must be taken in good time to safeguard the equipment, and the immediate vicinity of the equipment, and to protect employees.

    All connections must be checked regularly to ensure that they still fit properly and are function-ing correctly.It is very important to check all screw-type con-nections and wedge-clamped joins whenever the construction operations require (particularly after exceptional events such as storms), and to tighten them if necessary.

    Assembly The equipment/system must be inspected by the

    customer before use, to ensure that it is in suita-ble condition. Steps must be taken to rule out the use of any components that are damaged, deformed, or weakened due to wear, corrosion or rot.

    Combining our formwork systems with those of other manufacturers could be dangerous, risking damage to both health and property. If you intend to combine different systems, please con-tact Doka for advice first.

    The assembly work must be carried out by suita-bly qualified employees of the client's.

  • User information Doka load-bearing tower Staxo 100 Introduction

    5999800302 - 06/2008 The Formwork Experts

    Erecting the formwork Doka products and systems must be set up in

    such a way that all loads acting upon them are safely transferred!

    Pouring Do not exceed the permitted fresh-concrete pres-

    sures. Excessively high pouring rates lead to formwork overload, cause greater deflection and risk causing breakage.

    Striking the formwork Do not strike the formwork until the concrete has

    reached sufficient strength and the person in charge has given the order for the formwork to be struck!

    When striking the formwork, never use the crane to break concrete cohesion. Use suitable tools such as timber wedges, special pry-bars or sys-tem features such as Framax stripping corners.

    When striking the formwork, do not endanger the stability of any part of the structure, or of any scaffolding, platforms or formwork that is still in place!

    Transporting, stacking and storing Observe all regulations applying to the handling

    of formwork and scaffolding. In addition, the Doka slinging means must be used - this is a mandatory requirement.

    Remove any loose parts or fix them in place so that they cannot be dislodged or fall free!

    All components must be stored safely, following all the special Doka instructions given in the rele-vant sections of this User Information booklet!

    Regulations; industrial safety Always observe all industrial safety regulations

    and other safety rules applying to the application and utilisation of our products in the country and/or region in which you are operating.

    Instruction as required by EN 13374: If a person or object falls against, or into, the

    sideguard system and/or any of its accessories, the sideguard component affected may only con-tinue in use after it has been inspected and passed by an expert.

    Maintenance Only original Doka components may be used as

    spare parts.

    Symbols usedThe following symbols are used in this booklet:

    MiscellaneousWe reserve the right to make alterations in the inter-ests of technical progress.Unless otherwise stated, all dimensions are given in cm.

    Important noteFailure to observe this may lead to mal-function or damage.

    Caution / warning / dangerFailure to observe this may lead to mate-rial damage, and to injury to health which may range up to the severe or even life-threatening.

    InstructionThis symbol indicates that actions need to be taken by the user.

    Sight-checkIndicates that you need to do a sight-check to make sure that necessary actions have been carried out.

    TipPoints out useful practical tips.

    ReferenceRefers to other documents and materials.

  • The Formwork Experts6 999800302 - 06/2008

    Introduction User information Doka load-bearing tower Staxo 100

    Eurocodes at DokaIn Europe, a uniform series of Standards known as Eurocodes (EC) was developed for the construction field by the end of 2007. These are intended to pro-vide a uniform basis, valid throughout Europe, for product specifications, tenders and mathematical verification.The EC are the world's most highly developed Standards in the construction field.In the Doka Group, the EC are to be used as stand-ard from the end of 2008. They will thus supersede

    the DIN norms as the "Doka standard" for product design.The widely used "Permissible stress design" (com-paring the actual stresses with the permissible stresses) has been superseded by a new safety con-cept in the EC.The EC contrast the actions (loads) with the resist-ance (capacity). The previous safety factor in the permissible stresses is now divided into several partial factors. The safety level remains the same!

    Comparison of the safety concepts (example)

    Ed Design value of effect of actions(E ... effect; d ... design)Internal forces from action Fd(VEd, NEd, MEd)

    Rd Design value of the resistance(R ... resistance; d ... design)Design capacity of cross-section(VRd, NRd, MRd)

    Fd Design value of an action Steel: Rd =Rk Timber: Rd = kmod

    RkFd = F Fk M M(F ... force)

    Fk Characteristic value of an action"actual load"(k ... characteristic)e.g. dead weight, live load, concrete pres-sure, wind

    Rk Characteristic value of the resistancee.g. moment resistance to yield stress

    F Partial factor for actions(in terms of load; F ... force)e.g. for dead weight, live load, concrete pres-sure, windValues from EN 12812

    M Partial factor for a material property(in terms of material; M...material)e.g. for steel or timberValues from EN 12812

    kmod Modification factor (only for timber to take account of the moisture and the duration of load action)e.g. for Doka beam H20Values as given in EN 1995-1-1 and EN 13377

    Ed

    Rd

    Permissible stress design EC/DIN concept

    Factual Fpermissible Ed Rd

    A Load factor

    60 [kN]60

  • User information Doka load-bearing tower Staxo 100 Introduction

    7999800302 - 06/2008 The Formwork Experts

  • 8 999800302 - 06/2008

    User information Doka load-bearing tower Staxo 100

    The Formwork Experts

    System description

    System description

    Load-bearing tower Staxo 100 the extra-high-capacity, fast load-bear-ing tower made of steel, with inte-gral safety featuresStaxo 100 comes with all the field-proven advan-tages of Staxo meaning that it is robust, fast and versatile. On top of all this, Staxo 100 has been given an extensive package of built-in safety fea-tures, and its load capacity greatly increased.Sturdy galvanised steel frames, in three different heights, are the basis of this high-speed, high-per-formance load-bearing tower system.High load-bearing capacity, quick and easy assem-bly using integrated connectors, and great versatil-ity - these are the outstanding characteristics of Staxo.Wherever high loads occur, in either the building-construction or civil-engineering fields, this load-bearing tower is the ideal solution.

    The high-performance load-bearing tower

    high capacity of up to 97 kN per leg with lightweight components (frames up to

    h=1.20 m can be manhandled) ergonomical: easy-to-handle parts

    ... speeds up work

    the small number of system components makes for easier handling and means that no time is wasted searching for parts

    the connector components are captively inte-grated into the frames and so cannot be lost

    no tools are needed for assembling the towers

    ... provides optimum safety

    high stability, due to its 1.52 m wide frames slip-proof ladders integrated in the frames suspension points for chest harness

    ... is flexible

    the inter-frame spacing can be varied (from 0.60 m to 3.00 m), for optimum utilisation of the frames' load-bearing capacity. (From 1.00m, in 50 cm increments).

    different frame heights - 0.90 m, 1.20 m and 1.80 m - for rough height adjustment in 30 cm increments: 0.90, 1.20 and 1.80 m

    fine adjustment by means of screw-jack U-heads and feet

    can be used in conjunction with floor props and Dokaflex

    ... is economical

    The tower units are quick and easy to assemble:- either on their sides or in the upright- for tall towers, tower units can be pre-assem-

    bled on their sides, and then simply stacked by crane

    - clip-on assembly battens make it easy to erect and dismantle the tower and the superstruc-ture

    with special wheel units, complete tableforms can quickly be wheeled to their next location

    the Forklift shifting device TG makes the job of erecting, dismantling and transporting Doka load-bearing towers very much easier.

  • User information Doka load-bearing tower Staxo 100 System description

    9999800302 - 06/2008 The Formwork Experts

    Areas of useThe Load-bearing tower Staxo is ideal: as falsework for use in bridge-building, where

    high loads occur and where great stability is called for in that horizontal forces such as wind loads have to be safely transferred

    in the building construction field, e.g. for admin-istration buildings and multistorey car-park decks, where large-area tableform units reduce forming-times

    in the industrial and power-station construction field, as a load-bearing tower for all manner of applications

    Doka stair tower 250The Doka stair tower 250 consists of 1.20 m frames and a small number of lightweight aluminium stair-way elements.Quick to erect, the stair tower provides "high-level" safety and lets the site crew get quickly to their workplaces.

    Follow the directions in the "Doka stair tower 250" User Information!

  • The Formwork Experts10 999800302 - 06/2008

    System description User information Doka load-bearing tower Staxo 100

    System overview

    How to erect

    a ... Inter-frame spacing = 60* / 100 / 150 / 200 / 250 / 300 cmb ... Frame width = 152 cm* only for 1.20 and 0.90m frames

    The Staxo 100 system components

    Head units (A)

    Staxo 100 frames (B)

    A Head unit

    B Staxo 100 frame

    C Diagonal cross

    D Base unit

    E Assembly batten

    9800

    3-22

    8-01

    a

    b

    A

    CB

    E

    C

    D

    4-way screw-jack head

    Screw jack U-head

    Heavy duty screw jack 70 top + Split nut

    B

    U-head D

    Top height-adjustment spindles for load-bear-ing towers. For holding the superstructure and

    adjusting its height.

    Rotatable, but with no height

    adjustment.

    May be used with either one

    or two Doka H20 beams.

    For holding the primary beams (e.g. steel walings, steel gird-

    ers).

    For holding the primary beams (e.g. WS10 steel walings or double H20

    beams). The primary

    beams are fixed so that

    they cannot tip over.

    Staxo 100 frame 1.80m

    Staxo 100 frame 1.20m

    Staxo 100 frame 0.90m

    Hot-dip galvanised steel frames. Connectors for upward stack-ing of the frames are captively integrated into each frame.

  • User information Doka load-bearing tower Staxo 100 System description

    11999800302 - 06/2008 The Formwork Experts

    Diagonal crosses (C)

    Note: For horizontal bracing of the frames, always use Diagonal crosses 9.xxx.In levels in which assembly battens are mounted, horizontal bracing with diagonal crosses is no longer needed. This only applies, of course, if the assembly battens are left in place in this "storey" until the very end of the assignment (assembly, pouring etc.).

    Base units (D)

    Assembly battens (E)

    Slot-in bracing crosses made of tubular steel, for mounting between the frames.Identified by: Embossed marking (G) e.g.

    18.250- 18 = frame height 1.80 m- 250 = inter-frame spacing

    250 cm Notched, colour-coded clips

    (H) (see table)

    Designation Colour-coded clip Notches

    Diagonal cross 9.060 Black Diagonal cross 9.100 Green Diagonal cross 9.150 Red Diagonal cross 9.200 Blue Diagonal cross 9.250 Yellow Diagonal cross 9.300 Orange

    Diagonal cross 12.060 Black 1Diagonal cross 12.100 Green 1Diagonal cross 12.150 Red 1Diagonal cross 12.200 Blue 1Diagonal cross 12.250 Yellow 1Diagonal cross 12.300 Orange 1Diagonal cross 18.100 Green 3Diagonal cross 18.150 Red 3Diagonal cross 18.200 Blue 3Diagonal cross 18.250 Yellow 3Diagonal cross 18.300 Orange 3

    G

    H

    Screw jack footHeavy duty screw

    jack 70 + Split nut B

    Heavy duty screw jack 130 + Split nut B

    Bottom height-adjustment spindle for load-bearing towers.The Split nut B can be swung apart, mean-

    ing that it does not need to be turned through the full length of the threaded

    spindle.Specially for height mis-matches such as on steps. Other-

    wise identical to Heavy duty screw

    jack 70. For details, see the section

    headed "Structural design".

    Assembly batten Assembly batten with manhole

    Aluminium assembly battens with or without self-locking cover, for making safe platforms.

    Integral anti-liftout guardWidth 60 cm. Lengths from 100 to 300 cm, in 50 cm increments.

    Permitted service load: 1.5 kN/m2 (150 kg/m2)Load Class 2 to EN 12811-1:2003

  • The Formwork Experts12 999800302 - 06/2008

    System description User information Doka load-bearing tower Staxo 100

    The Staxo 100 frame in detail

    Features of the Staxo 100 framesThe Staxo 100 frames have the following character-istic features differentiating them from the previous Staxo frames.

    Integral interconnection system The crane-handling-safe link between the frames

    uses a captive locking spring plus built-in safety bolt. It can be locked or released in an instant - with no need for any tools.

    Mode of functioning for upward stacking

    Mode of functioning for fitting the base unitsConnection sleeve (A) unfixed = yellow locking spring (B) is pushed in.

    Mode of functioning for fitting the head unitsBlue locking spring (C) is pushed in.

    Important note:Only Staxo 100 frames meet the loading capacity data stated in this manual!

    Attachment point for safety harnesses only

    It is forbidden to attach the lift-ing chain here!

    A "Staxo 100" sticker

    B Stamped-in type designation: 18, 12 or 9

    C Arrow to make clear where "top and bottom" are

    D Attachment point for safety harness

    9800

    3-20

    6-01

    D

    C

    B

    A

    Connection sleeve (A) fixed = yellow locking spring (B) is

    pushed out.

    Frames linked in a crane-han-dling-safe manner = blue lock-ing spring (C) is pushed out.

    9716

    -211

    -01

    A

    B

    9716

    -236

    -01

    C

    9800

    3-22

    9-02

    F

    E

    98003-229-03

    G

  • User information Doka load-bearing tower Staxo 100 System description

    13999800302 - 06/2008 The Formwork Experts

    Safety catch tried-and-tested interconnection system (captive) secures the diagonal crosses two defined positions (closed open)

    Connecting the couplers

    a ... max. 16 cm (exception: where tubes are being connected for constructional design purposes)b ... Diameter 48 mmc ... Diameter 75 mm

    Profile form low weight, yet high load-bearing capacity sturdy

    Profile seal prevents connection sleeve falling out protects against damage sliding contact surface for nuts

    Vertical access system integral ladder extra "handles" to pick the frame up by

    Closed Open

    A Transition swivel coupler 48/76mm. This type of link is not in conformity with DIN 4421 (DIN EN 74). No loads may be introduced parallel to the Staxo tubes.

    B Swivel coupler 48mm or Normal coupler 48mm

    98003-223-01

    98003-222-01

    c

    a

    a

    b

    B

    A

    Warning!Never climb up or down the outside of the tower! You risk falling and/or causing the tower to tip over! Only ever climb up the inside of the

    tower. When doing this, make sure that the assembly battens are in the correct positions (as intermediate landings)!

    9800

    3-25

    5-01

    9800

    3-25

    7-01

    9800

    3-25

    7-01

  • The Formwork Experts14 999800302 - 06/2008

    System description User information Doka load-bearing tower Staxo 100

    Practical examplesTableforms and tower frames are both assembled from the same system components.

    Tableform units For repetitive use, the load-bearing tower can be

    assembled into complete table-forms.

    Combined with DokaflexFor floor-beams, load-bearing towers and beam-forming supports can be combined very effectively with Dokaflex 1-2-4.

    Edge floor-beam

    Tower framesWith a load-bearing capacity of up to 97 kN per leg, Staxo 100 is an extremely strong load-bearing tower system.It safely withstands horizontal forces such as wind loads.The wide frames make for high stability right from the word "go".Close inter-frame spacing is possible, for transfer-ring high loads.

    A Load-bearing tower

    B Dokaflex 1-2-4

    C Beam forming support 20

    D Handrail post T 1.80m, Handrail clamp S or Handrail post 1.50m

    E Lashing strap 5.00 m

    F Doka Express anchor 16x125mm and Doka coil 16mm

    98003-230-01

    A B

    D

    E

    C

    F

    The Spindle wrench makes it easier to turn the Split nut B - even when it is under higher loads.

    98003-231-01

  • User information Doka load-bearing tower Staxo 100 System description

    15999800302 - 06/2008 The Formwork Experts

    Shoring load-bearing structuresOn bridges, culverts and industrial structures, the load-bearing tower and Doka large-area formwork Top 50 together make an ideal combination.In this way, even complex structures can be formed using mostly standard parts - at lower cost.

    Falsework beneath arched bridge

    Typical cross-section - Falsework beneath super-structure formwork

    9716-222-01

    98003-232-01

  • The Formwork Experts16 999800302 - 06/2008

    System description User information Doka load-bearing tower Staxo 100

    Adapts to different ground plans, heights, floor shapes and loadsThe different sizes of diagonal brace for each height of frame enable the frames to be spaced close together or further apart, depending on the load.

    In this way, only as much material is used as is really needed.

    e.g. heavy loads frames spaced close together e.g. light loads frames spaced further apart

    Plan view Plan view

    e.g. adapting to irregular shaped layoutsby using single legs

    98003-309-01 98003-311-01

    98003-310-01 9716-263-01

    98003-268-01

    98003-269-01

  • User information Doka load-bearing tower Staxo 100

    17999800302 - 06/2008 The Formwork Experts

    Height adjustment The 3 different heights of frame (0.90 m, 1.20 m

    and 1.80 m) enable coarse adjustment to within 30 cm.

    Fine adjustment, down to the last millimetre, is done using the various head and base units.

    System dimensions

    on multi-section towersRegarding Table A ("Height ranges and materials schedule"), use the version of this table given in the chapter for the usage situation concerned.

    Table B: Head zone

    Values in cm Min. values with no formwork-striking play

    Table C: Base zone

    Values in cm Min. values with no formwork-striking play

    Important note:The structural design of the load-bearing tower may make it necessary to plan for shorter extension lengths. For details, see the section headed "Structural design".

    Screw jack U-head and 4-way screw-jack head Heavy duty screw jack 70 top U-head D

    Frames in the top "storey"1.80 / 1.20 / 0.90m 1.80m 1.20m 0.90m 1.80 / 1.20 / 0.90m

    LK max. 45.8 71.2 71.2 71.2 1.6LK min. 7.8 8.4 8.4 24.9 1.6

    Screw jack foot Heavy duty screw jack 70 + Split nut BHeavy duty screw jack 130

    + Split nut B

    Frames in the bottom "storey"1.80m 1.20m 0.90m 1.80m 1.20m 0.90m 1.80m 1.20m 0.90m

    LF max. 46.2 46.2 46.2 71.2 71.2 71.2 131.2 131.2 --LF min. 8.2 8.2 26.3 8.8 28.2 58.1 40.0 100.0 --

    9800

    3-21

    9-04

    L K

    9800

    3-23

    7-01

    L K

    9800

    3-23

    6-01

    L K

    9800

    3-21

    9-03 L F

    9800

    3-23

    6-02 L F

    9800

    3-23

    6-03

    L F

  • 18 999800302 - 06/2008

    User information Doka load-bearing tower Staxo 100

    The Formwork Experts

    on single-section towers

    Note: For towers consisting of one section only, the min. values LK and LF given in Tables B and C for the head and base units respectively will often not be reached.Reason: The lengths of the head and base units and the integrated connector (V) in the frame add up to a larger dimension than the height of the frame.These constraint points have already been allowed for in the operational height data given in Table A.

    Close-up: Cut-away view of frame tube

    a b cConnector 30.5 -- --Screw jack foot -- 69.2 --Heavy duty screw jack 70 -- 101.2 --Heavy duty screw jack 130 -- 173.0 --Screw jack U-head -- -- 68.84-way screw-jack head -- -- 68.8Heavy duty screw jack 70 top -- -- 100.9U-head D -- -- 10.0

    98003-238-01

    ac

    b

    V

  • User information Doka load-bearing tower Staxo 100

    19999800302 - 06/2008 The Formwork Experts

    Assembly (overview)

    AssemblyApproaches to assembling the Staxo load-bearing tower 100

    Horizontal assembly(standard set-up) Assembling in the upright

    using the Forklift shifting device TG by hand

    Railings mounted-ahead 1.20m frames and diagonals mounted-ahead

    98003-213-01 98003-211-01

    9800

    3-10

    1

    98003-293-01 98003-294-01

  • 20 999800302 - 06/2008

    User information Doka load-bearing tower Staxo 100

    The Formwork Experts

    Horizontal assembly

    Horizontal assemblyPreliminary remark: The terms "vertical" and "horizontal" (e.g. refer-

    ring to the diagonal crosses) are always used here with reference to their installation situation in the finished, upright tower.

    The job of erecting the load-bearing tower begins with the bottom (i.e. first) section.

    Arrow on frame must be pointing upwards.(= yellow locking spring at bottom)

    Erecting the first section Having regard to the instructions given above,

    place the tower frames on their sides on timber supports (min. 4cm high).

    Bracing the frames in the vertical Link the frames with diagonal crosses (F) .

    Plan-bracing the frames (in the horizontal)

    Slot diagonal crosses (K) onto the gravity latches of the horizontal frame tubes and secure them.

    Press the yellow locking springs (E) on the frame (D) inwards (to open) the connection sleeves can now be moved freely.

    Push in and secure the base units. See the sec-tion headed "Lifting by crane".

    General remarks: As soon as you have slotted a diagonal cross onto the latch-type peg, secure it with the safety catch.

    When erecting the tower, make sure that the climbing rungs are in the right position rela-tive to the tower.

    Seen from outside, the ladder must always be on the left-hand side.This makes it possible to use assembly bat-tens where needed (see "Assembling towers in the upright with mounted-ahead rail-ings").

    9800

    3-20

    6-01

    9800

    3-21

    6-02

    9800

    3-28

    6-01

    Basic rule:

    Horizontal diagonal crosses 9.xxx are needed: at intervals of every two storeys - beginning

    with the first storey.

    98003-216-01

    F

    F

    98003-215-01

    K

    E

    D

  • User information Doka load-bearing tower Staxo 100 Horizontal assembly

    21999800302 - 06/2008 The Formwork Experts

    Erecting further sections

    Note: Do not pre-assemble units any higher than 10 m.

    Lock the connection sleeves (H) on the frames that you are about to add, by pressing the yellow locking springs (E) towards the outside.

    Place these frames onto the finished section, and push the blue locking springs of the bottom frames outward (to join the frames).

    Fit and secure diagonal crosses (F) in the same way as in the first section.

    h ... max. 10 m

    Install assembly battens where needed Close the anti-liftout guard.

    98003-303-01

    E

    H

    98003-213-01

    F

    F

    F

    h

    98003-213-02

  • 22 999800302 - 06/2008

    User information Doka load-bearing tower Staxo 100

    The Formwork Experts

    Optionally: Railings on the top "storey"To meet very stringent safety requirements, mounted-ahead railings can be fitted in the top section.This is done in line with the instructions given in "Assembling towers in the upright with mounted-ahead railings".

    Mount the Staxo 100 side railing and secure it with a spring-locked connecting pin 16mm (N) to prevent accidental lift-out.

    Close-up 1

    Mount the Staxo 100 front railing and secure it with a Spring cotter 4mm (O) to prevent acciden-tal lift-out.

    Close-ups 2 and 3

    L Staxo 100 side railing

    M Staxo 100 front railing

    98003-312-01

    L

    L

    M

    M

    1

    2

    3

    9800

    3-31

    2-02

    N

    9800

    3-31

    2-03

    9800

    3-31

    2-04

    O

  • User information Doka load-bearing tower Staxo 100 Horizontal assembly

    23999800302 - 06/2008 The Formwork Experts

    Lifting into the upright by crane Check before attaching the crane suspension

    tackle:

    Lifting into the upright

    Attach the crane suspension tackle to the frames of the top section and lift the entire tower into the upright.

    DismantlingAfter the tower has been placed back on its side, it can be dismantled in reverse order.

    All the locking springs must be closed = pushed outwards (to link the frames).

    All safety catches must be closed. All base units must be secured.

    Max. extension length of the base units when the tower is being lifted into the upright: 35 cm!

    Important note: Erect the load-bearing tower in the verti-cal on ground that is statically capable of supporting the load.

    If the load-bearing tower is over 6 m high, back-stay it or combine it with other tow-ers.

    When the tower is standing in the upright, check once again to make sure that all the safety catches are closed.

    98003-214-01

    Detaching the crane suspension tackle near ground level:This method must not be used for placing the tower back on its side!

    Items needed: 3 x Scaffolding tube 48.3mm (G)

    - Minimum length: Inter-frame space + 1.00 m

    6 x normal or swivel couplers, 48mm (H) Attach the scaffolding tubes:

    - one between the bottom frames - two between the top frames

    Attach two chains or lifting straps to the bottom scaffolding tube.

    Lead the chains or lifting straps along the outside of the tower and between the top scaffolding tubes.

    a ... min. 0.5 mb ... max. 0.2 m

    After the tower has been lifted into the upright, the chains or lifting straps are detached by a crewman working from ground level.

    98003-218-01

    a

    GH

    b

  • The Formwork Experts24 999800302 - 06/2008

    Horizontal assembly User information Doka load-bearing tower Staxo 100

  • User information Doka load-bearing tower Staxo 100

    25999800302 - 06/2008 The Formwork Experts

    Assembling towers in the upright

    Assembling towers in the upright with mounted-ahead railings

    General remarks: Arrow on frame must be pointing upwards.

    (= yellow locking spring at bottom)

    As soon as you have slotted a diagonal cross onto the latch-type peg, secure it with the safety catch.

    Important note: Erect the load-bearing tower in the verti-cal on ground that is statically capable of supporting the load.

    If the load-bearing tower is over 6 m high, back-stay it or combine it with other tow-ers.

    9800

    3-20

    6-01

    9800

    3-23

    3-01

    When erecting the tower, make sure that the climbing rungs are in the right position rela-tive to the assembly battens.

    9800

    3-25

    6-01

  • The Formwork Experts26 999800302 - 06/2008

    Assembling towers in the upright User information Doka load-bearing tower Staxo 100

    e.g. with Heavy duty screw jack 70 and 4-way screw-jack head.

    Erecting the first section Place a Split nut B (A) on the Heavy duty screw

    jack 70 (B) , push the two halves together and secure it with the spring locking pin.

    Press the yellow locking springs (E) on the frame (D) inwards (to open) the connection sleeves can now be moved freely.

    Insert the Heavy duty screw jacks 70 into the frames.

    Link the frames with diagonal crosses (F) .

    Erecting the second section

    Fitting the mounted-ahead railings Mount Staxo 100 side railings (L) above the diag-

    onal crosses.

    Close-up of how to hang into place

    Mount Staxo 100 front railings (M) above the Staxo 100 frames.

    Close-up of how to hang into place

    Make sure that the spring locking pin (C) points downwards when it is secured.

    98003-234-01

    A

    B

    C

    B

    D

    E

    E

    98003-210-01

    F

    98003-251-01

    L L

    9800

    3-25

    1-02

    98003-250-01

    M

    M

    9800

    3-25

    0-03

    9800

    3-25

    0-02

  • User information Doka load-bearing tower Staxo 100 Assembling towers in the upright

    27999800302 - 06/2008 The Formwork Experts

    Mounting the assembly battens Place an assembly batten (G) on the finished sec-

    tion.

    Close the anti-liftout guard.

    Stacking the frames Climb up onto the assembly battens. Lock the connection sleeves on the frames that

    you are about to add, by pressing the yellow lock-ing springs (E) towards the outside.

    Place these frames onto the finished section, and push the blue locking springs of the bottom frames outward (to join the frames).

    Bracing the frames in the vertical Fit and secure diagonal crosses (F) in the same

    way as in the first section.

    98003-209-01

    G

    98003-209-02

    Connection sleeve (A) fixed = yellow locking spring (E) is

    pushed out.

    Frames linked in a crane-han-dling-safe manner = blue lock-ing spring (C) is pushed out.

    98003-272-01

    9800

    3-22

    9-01

    A

    E

    9800

    3-22

    9-04

    C

    98003-207-01

  • The Formwork Experts28 999800302 - 06/2008

    Assembling towers in the upright User information Doka load-bearing tower Staxo 100

    Erecting the third section

    Raising the mounted-ahead railings1) Push the Staxo 100 front railings down into the

    stand-by position.2) Move the Staxo 100 side railings up one section

    ("storey").3) Move the Staxo 100 front railings up again.

    Mount the assembly battens. Climb up onto the assembly battens. Fix on the frames in the same way as on the 2nd

    section. Fit and secure diagonal crosses (F) in the same

    way as on the 2nd section.

    Horizontal bracing

    Slot diagonal crosses (K) onto the gravity latches of the horizontal frame tubes and secure them.

    Erecting further sections Add further frames in the same way as for the 3rd

    section, and brace them in the vertical with diag-onal crosses.

    98003-208-01

    1

    3

    2

    2

    98003-211-01

    F

    To meet very stringent safety requirements, the mounted-ahead railings can be left in place on all levels ("storeys") with assembly battens.

    Important note:If no assembly battens are used, or if these are removed before the end of the assign-ment, the following rule applies.

    Basic rule:

    Horizontal diagonal crosses 9.xxx are needed: at intervals of every two storeys - beginning

    with the first storey.

    98003-285-01

    K

  • User information Doka load-bearing tower Staxo 100 Assembling towers in the upright

    29999800302 - 06/2008 The Formwork Experts

    Head zone

    Fitting the head unit Press the blue locking springs (I) of the top

    frames towards the inside (to open them). Insert the head unit (J) .

    Always place the primary beams (single or double formwork beams) centrally.

    On the Screw-jack U-head, too, it is also possible to twist the head so as to hold single beams centrally.

    DismantlingTo dismantle, perform the above steps in reverse order.

    Warning! Where the primary beams cantilever out

    a long way, protect them against being lifted out or tipped over (e.g. by nailing board-plates over the beam joins, or by fastening them to the head unit).

    Important note: When lifting and repositioning the entire tower unit (or pre-assembled sub-units) by crane: Follow the instructions in the section headed "Lifting by crane"!

    9800

    3-21

    2-02

    I

    J

    9716-215-01

  • The Formwork Experts30 999800302 - 06/2008

    Assembling towers in the upright User information Doka load-bearing tower Staxo 100

    Assembling towers in the upright: with mounted-ahead 1.20m frames

    General remarks: Arrow on frame must be pointing upwards.

    (= yellow locking spring at bottom)

    As soon as you have slotted a diagonal cross onto the latch-type peg, secure it with the safety catch.

    e.g. with Heavy duty screw jack 70 and 4-way screw-jack head.

    Erecting the first section Place a Split nut B (A) on the Heavy duty screw

    jack 70 (B) , push the two halves together and secure it with the spring locking pin.

    Press the yellow locking springs (E) on the frame (D) inwards (to open) the connection sleeves can now be moved freely.

    Insert the Heavy duty screw jacks 70 into the frames.

    Link the frames with diagonal crosses (F) .

    Important note: Erect the load-bearing tower in the verti-cal on ground that is statically capable of supporting the load.

    If the load-bearing tower is over 6 m high, back-stay it or combine it with other tow-ers.

    9800

    3-20

    5-01

    9800

    3-23

    3-01

    Make sure that the spring locking pin (C) points downwards when it is secured.

    98003-265-01

    A

    B

    C

    B

    D

    E

    E

    98003-263-01

    F

  • User information Doka load-bearing tower Staxo 100 Assembling towers in the upright

    31999800302 - 06/2008 The Formwork Experts

    Mounting the assembly battens Place the assembly batten (G) onto the bottom

    level.

    Close the anti-liftout guard.

    Erecting the second section

    Stacking the frames Lock the connection sleeves on the frames that

    you are about to add, by pressing the yellow lock-ing springs (E) towards the outside.

    Place these frames onto the finished section, and push the blue locking springs of the bottom frames outward (to join the frames).

    Push the diagonal crosses (F) onto the bottom latch-type pegs and secure them with the safety catches.

    Bracing the frames in the vertical Move the assembly battens (G) up to the next

    level. Push the diagonal crosses (F) onto the top latch-

    type pegs and secure them with the safety catches.

    98003-273-01

    G

    98003-209-02

    Connection sleeve (A) fixed = yellow locking spring (E) is

    pushed out.

    Frames linked in a crane-han-dling-safe manner = blue lock-ing spring (C) is pushed out.

    98003-262-01

    9800

    3-22

    9-01

    A

    E

    9800

    3-22

    9-04

    C

    98003-274-01

    F

    G

  • The Formwork Experts32 999800302 - 06/2008

    Assembling towers in the upright User information Doka load-bearing tower Staxo 100

    Erecting the third section

    Stacking the frames Add 1.20 m frames in the same way as for the

    2nd section. Push the diagonal crosses (F) onto the bottom

    latch-type pegs and secure them with the safety catches.

    Mounting the assembly battens and bracing the frames in the vertical Place an assembly batten (G) on the finished sec-

    tion. Push the diagonal crosses (F) onto the top latch-

    type pegs and secure them with the safety catches.

    Horizontal bracing

    Slot diagonal crosses (K) onto the gravity latches of the horizontal frame tubes and secure them.

    98003-264-01

    F

    98003-261-01

    G

    Important note:If no assembly battens are used, or if these are removed before the end of the assign-ment, the following rule applies.

    Basic rule:

    Horizontal diagonal crosses 9.xxx are needed: at intervals of every two storeys - beginning

    with the first storey.

    98003-285-01

    K

  • User information Doka load-bearing tower Staxo 100 Assembling towers in the upright

    33999800302 - 06/2008 The Formwork Experts

    Erecting further sections Add further frames in the same way as for the 3rd

    section, and brace them in the vertical with diag-onal crosses.

    Head zone

    Fitting the head unit Press the blue locking springs (I) of the top

    frames towards the inside (to open them). Insert the head unit (J) .

    Always place the primary beams (single or double formwork beams) centrally.

    On the Screw-jack U-head, too, it is also possible to twist the head so as to hold single beams centrally.

    DismantlingTo dismantle, perform the above steps in reverse order.

    Arrange the assembly battens on alternate sides from one "storey" to the next.In the same way as in the first "storey", 2 assembly battens are used in the final "sto-rey", one of them with manhole. Make sure that the manhole is in the right position here.

    98003-259-01

    G

    G

    Warning! Where the primary beams cantilever out

    a long way, protect them against being lifted out or tipped over (e.g. by nailing board-plates over the beam joins, or by fastening them to the head unit).

    Important note: When lifting and repositioning the entire tower unit (or pre-assembled sub-units) by crane: Follow the instructions in the section headed "Lifting by crane"!

    9800

    3-21

    2-02

    I

    J

    9716-215-01

  • The Formwork Experts34 999800302 - 06/2008

    Assembling towers in the upright User information Doka load-bearing tower Staxo 100

    Assembling towers in the upright by forklift truck

    Forklift shifting device TGThe Forklift shifting device TG may only be used for erecting, dismantling and transporting Doka load-bearing towers Staxo and d2.

    Items needed:

    Max. heights of load-bearing towers

    Requirements for fork-lift trucks or telescop-ing stacker trucks

    Min. load carrying capacity: 4000 kg Driver protection roof Centre-to-centre distance of the fork prongs:

    850 mm

    Permitted types of fork extension:- box-style fork extensions 1)- telescopic fork prongs

    Min. fork length:Distance between the frames of the load-bearing tower + 400 mm

    Max. fork width: 195 mm Max. fork height: 71 mm

    Follow the directions in the Operating Instructions!

    Item Designation Q'ty (A) Forklift shifting device TG 1 (B) Multi-purpose walings WS10 Top50 2.00m 2 (C) Connecting pins 10cm 4 (D) Spring cotters 6mm 4 (E) Scaffolding tubes 48.3mm 1.00m 2 (F) Screw-on couplers 48mm 50 4 (G) Scaffolding tube 48.3mm 2.00m 1 (H) Swivel couplers 48mm 2

    Operating cord, site-provided (optional) 1

    Warning! While load-bearing towers are being

    erected or dismantled, lifted or lowered: It is forbidden to walk or stand beneath sus-pended loads.

    Max. load: when using box-style fork extensions: 1000 kg when using telescopic fork prongs: 600 kg

    9280

    7-20

    1-01

    F

    A

    B

    G

    C D

    E

    H

    with superstructure without superstructure

    When being travelled When being lifteda max. 7.20 m max. 9.00 mb max. 9.00 m max. 12.60 mc max. 5.40 m max. 9.00 md max. 3.60 m max. 3.60 m

    Warning! It is not permitted to use non-enclosed

    (open) fork extensions.

    A Box-style fork extension

    B Open fork extension

    1) observe the following manufacturer data: load carrying capacity of the fork extension required length of the fork prongs

    Tr745-200-05

    a

    c

    c

    b

    d

    d

    92807-207-01

    A

    92807-208-01B

  • User information Doka load-bearing tower Staxo 100 Assembling towers in the upright

    35999800302 - 06/2008 The Formwork Experts

    Travelling the towerframe units

    Assembling the towerframe units

    Build each section at ground level. Use a forklift truck to stack the towerframe sto-

    reys into a single towerframe unit.

    DismantlingTo dismantle, perform the above steps in reverse order.

    Important points to remember when wheel-ing load-bearing towers: As well as the fork-lift driver, a specially

    trained watchman must also be on hand during all lifting, assembly and travelling operations:

    max. inclination of trackway: 2%. The floor must be stable, firm and suffi-

    ciently smooth (e.g. concrete).

    For details of how to assemble and join together the individual sections ("tower-frame storeys"), see "Assembling towers in the upright"!

    Important note:Always only dismantle the bottom "storey" of the towerframe unit.

    Tr745-200-05

  • 36 999800302 - 06/2008

    User information Doka load-bearing tower Staxo 100

    The Formwork Experts

    Examples of the system in action

  • User information Doka load-bearing tower Staxo 100

    37999800302 - 06/2008 The Formwork Experts

    Repositioning

    RepositioningDifferent ways of repositioning

    Using traveller units: By crane By forklift truck ortelescoping stacker truck

    Transport winches Shifting carriage TG

    98003-299-01 98003-300-0198003-298-01 98003-296-01

  • The Formwork Experts38 999800302 - 06/2008

    Repositioning User information Doka load-bearing tower Staxo 100

    Repositioning using wheel unitsCompletely assembled tableforms can be wheeled to their next location, quickly and easily, using wheel units.The following different types of wheel unit are available for this. The crane is only needed when the tower has to be lifted up to the next storey.

    All types of wheel unit can perform the following functions: Lifting Wheeling Lining-and-levelling Lowering

    Example with Winch 70:

    Wheel-unit variants: Shifting carriage TG Modular system (with winches)

    Modular system (with winches)Optimum adaptability to on-site requirements.There is a choice of 2 types of winch and 2 types of wheel.

    Clamp the winch to the frame of the load-bearing tower, using the "Frame for Staxo/d2 winch".

    Secure the foot-pieces to prevent them dropping out. See the section headed "Lifting by crane".

    Equipment needed for one shifting unit

    Important note:On standard superstructures, the max. width-to-height ratio of the table+tower is 1:3 (W:H). A statical check must be per-formed on custom constructions.

    9716-259-01

    Max. load:1000 kg per Winch 70(lifting height 70 cm) with solid-tyre wheel1500 kg per Winch 125(lifting height 125 cm) with Heavy-duty wheel 15 kN

    The floor must be stable, firm and suffi-ciently smooth (e.g. concrete).Follow the directions in the Operating Instructions!

    Item Designation N of itemsA Winch 70 or 125 4B Frame for Staxo/d2 winch 4C Solid-tyre wheel or Heavy-duty wheel 15kN 4D Double wheeled transporter 4

    98003-226-01

    A

    C

    D

    B

  • User information Doka load-bearing tower Staxo 100 Repositioning

    39999800302 - 06/2008 The Formwork Experts

    Accessory for transporting the winches when empty:The Double-wheeled transporter (A) is bolted into the connecting sockets on the wheel flange and makes it easier to wheel the (empty) wheel units.

    Shifting carriage TGThis is an easy-to-operate, manual hydraulic lifting carriage for shifting light to medium-weight table-form units. As well as making the tableforms easier to move around, it also makes it easier to erect and strike the formwork.

    Hydraulic, for near-effortless lifting. Tables can be "inched" down slowly with handle-

    control. 3 guide-rolls, for maximum manoeuvrability. With an overall width of only 82 cm, the carriage

    can pass easily through any doorway when empty.

    Push the Shifting carriage TG (A) up against the front and rear faces of the tableform - the slot-in lifting profile (B) reaches under the bottom crossbar of the frame.

    Secure the foot-pieces to prevent them dropping out. See the section headed "Lifting by crane".

    Equipment needed for one shifting unit

    9716-220-01

    A

    Max. load per Shifting carriage TG 1000 kg

    The floor must be stable, firm and suffi-ciently smooth (e.g. concrete). Max. gradient of floor: 5 %. Max. configuration that can be trans-

    ported using 2 Shifting carriages TG: Tables with 3 cross-frames per section and a max. height of 5.0 m.

    Follow the directions in the Operating Instructions!

    Item Designation N of itemsA Shifting carriage TG 2

    98003-225-01

    A

    B

  • The Formwork Experts40 999800302 - 06/2008

    Repositioning User information Doka load-bearing tower Staxo 100

    Lifting by crane

    Where the tableforms are to be repositioned in the vertical, i.e. crane-lifted, they must be fitted with a Lifting rod 15.0 and Retaining plate 15.0 , which make it easy to attach the transfer cables.

    Mounting instructions Mount the Lifting rod 15.0 (A) and Retaining

    plate 15.0 (B) .

    Preparations

    Connect superstructure components together e.g. connect the primary and secondary beams to

    rafter plates, and nail on the form-ply.

    Connect the superstructure to the head units e.g. with Locking rod 15.0 (D) , Clamping plate (E)

    and Wing nut 15.0 (F) .

    Secure the head units so that they cannot be lifted out Slot the fixing-handle (G) into the cross-bar of

    the frame.

    Secure the base units to prevent them drop-ping out: On Screw jack foot (H) and Heavy duty screw jack 70 or 130 using Split nut B Slot the fixing-handle (I) into the cross-bar of the

    frame.

    Important note:The max. height of towerframe unit that can be lifted in one piece is 20 m!

    Max. load:1000 kg per Lifting rod 15.0 - where the load is applied centrally

    Use a 20 mm diam. bit to drill the hole through the form-ply. It can later be filled with a Universal plug R20/25.

    Follow the directions in the Operating Instructions!

    Warning!Danger from loose and unsecured parts. Observe the following points before lift-

    ing!

    9720-276-01

    5.1 5.1

    A

    B

    On Screw jack U-head On 4-way screw-jack head

    Only possible with Clamping plate a = 28 cm (2002 models

    onward)

    9716

    -285

    -01G

    9716-239-01

    H

    I

  • User information Doka load-bearing tower Staxo 100 Repositioning

    41999800302 - 06/2008 The Formwork Experts

    Link the frames in a crane-handling-safe man-ner Close the yellow (K) and blue (L) locking springs,

    by pressing them towards the outside.

    Lifting operation Attach the crane sling to the Lifting rods 15.0 and

    lift the tableform to its next location.Spread-angle max. 30.

    Shifting the table in skeleton construction Take the load off the table by turning the

    threaded spindles. Clamp on the wheel-units. Push in and secure the base units.

    Using the wheel-units, lower the table, and wheel it out as far as the stop (M) .

    Remove the front wheel-units. Screw the Lifting rod 15.0 into the previously

    mounted Retaining plate 15.0. Attach the crane sling to the Lifting rod 15.0, then

    raise the crane until the front legs are just off the floor.

    Push the table outwards until only the innermost legs are still over the floor.

    Mount more lifting rods and attach crane slings. Use a pulley-type adjuster (N) to shorten the rear

    cables until the table is suspended in the horizon-tal.

    Manoeuvre the table all the way out with the crane, then lift it to the next storey.

    While the tableform is being lifted, there must NOT be any loose parts, tools or other items on the tableform!

    9800

    3-22

    9-04

    L

    K

    9716-229-01

    9716-230-01

    9716-231-01

    M

    9716-232-01

    N

  • The Formwork Experts42 999800302 - 06/2008

    Repositioning User information Doka load-bearing tower Staxo 100

    Lifting by forklift truck

    Forklift shifting device TGFor product information on the Forklift shifting device TG and the requirements in respect of the forklift truck, see "Assembling towers in the upright by forklift truck".

    Max. heights of load-bearing towers

    Travelling the towerframe units

    Follow the directions in the Operating Instructions!

    with superstructure without superstructure

    When being travelled When being lifteda max. 7.20 m max. 9.00 mb max. 9.00 m max. 12.60 mc max. 5.40 m max. 9.00 md max. 3.60 m max. 3.60 m

    Important points to remember when wheel-ing load-bearing towers: As well as the fork-lift driver, a specially

    trained watchman must also be on hand during all lifting, assembly and travelling operations:

    max. inclination of trackway: 2%. The floor must be stable, firm and suffi-

    ciently smooth (e.g. concrete).

    Tr745-200-05

    a

    c

    c

    b

    d

    d

  • User information Doka load-bearing tower Staxo 100

    43999800302 - 06/2008 The Formwork Experts

    Structural design (overview)

    Structural design

    Structural-design configurations

    Load-bearing tower Staxo 100

    Standard application Custom applications

    max. 70 kN per leg max. 85 kN per leg max. 97 kN per leg

    Types of frame that can be used1.80 m1.20 m0.90 m

    1.20 m0.90 m

    1.20 m0.90 m

    Top and bottom "storeys" MUST be with 0.90m frames

    Load-bearing tower held at

    top

    Free-standing load-bearing

    towerLoad-bearing tower held at top Load-bearing tower held at top

    Max. extension lengths of the Head units LK

    45 cm 30 cm 30 cm 25 cm**70 cm* 45 cm* 45 cm* 40 cm*

    Max. extension lengths of the Base units LF

    70 cm 30 cm 30 cm 25 cm**130 cm* 45 cm* 45 cm* 40 cm*

    9800

    3-24

    0-01

    9800

    3-25

    3-01

    9800

    3-25

    4-01

    Important note:For the extension lengths marked with an *, suitable bracing of the head and base units is required.For the extension lengths marked **, the integrated connection sleeve must be removed from the frame.

  • 44 999800302 - 06/2008

    User information Doka load-bearing tower Staxo 100

    The Formwork Experts

    Standard application: Load capacity up to 70 kN

    Standard application: Load capacity up to 70 kN per leg

    Height ranges and materials sched-uleChoose the right diagonal crosses for the distance between the frames.

    1.80m, 1.20m and 0.90m frames are possible here.

    The minimum values "hmin." given inTable A are only applicable if the biggest possible frame is always used in the base section.

    The lowering distance of 6 cm is already allowed for in Table A!

    LK and LF are in accordance with the dimensioning diagrams. In some cases, the structural design will permit greater extension lengths see Page 15 "System dimensions", Tables B and C.

    98003-219-01

    h

    hFh

    L KL F L F

  • User information Doka load-bearing tower Staxo 100 Standard application: Load capacity up to 70 kN

    45999800302 - 06/2008 The Formwork Experts

    Table A

    The schedule of materials does not include assembly battens.

    The assembly battens have to be planned separately for each set-up configuration. Provided they are located in the same level, they replace the Diagonal crosses 9.xxx needed for horizontal bracing. This reduction in the number of diagonal crosses needed must be allowed for in the schedule of materials.

    Fixe

    d h

    eig

    ht

    of

    fram

    e F h

    [m

    ]Variant 1

    LK = max. 30 cmLF = max. 30 cm

    Variant 2LK = max. 45 cmLF = max. 70 cm

    Variant 3LK = max. 45 cmLF = max. 130 cm

    Basic items

    4-w

    ay s

    crew

    -jac

    k h

    ead

    , Scr

    ew ja

    ck U

    -hea

    d

    or

    Hea

    vy d

    uty

    scr

    ew ja

    ck 7

    0 to

    p

    Scr

    ew ja

    ck f

    oo

    t

    4-w

    ay s

    crew

    -jac

    k h

    ead

    , Scr

    ew ja

    ck U

    -hea

    d

    or

    Hea

    vy d

    uty

    scr

    ew ja

    ck 7

    0 to

    p

    Scr

    ew ja

    ck f

    oo

    t o

    rH

    eavy

    du

    ty s

    crew

    jack

    70

    + S

    plit

    nu

    t B

    4-w

    ay s

    crew

    -jac

    k h

    ead

    , Scr

    ew ja

    ck U

    -hea

    d

    or

    Hea

    vy d

    uty

    scr

    ew ja

    ck 7

    0 to

    p

    Hea

    vy d

    uty

    scr

    ew ja

    ck 1

    30 +

    Sp

    lit n

    ut

    B

    Sta

    xo 1

    00 f

    ram

    e 0.

    90m

    Sta

    xo 1

    00 f

    ram

    e 1.

    20m

    Sta

    xo 1

    00 f

    ram

    e 1.

    80m

    Dia

    go

    nal

    cro

    ss 9

    .xxx

    Dia

    go

    nal

    cro

    ss 1

    2.xx

    x

    Dia

    go

    nal

    cro

    ss 1

    8.xx

    x

    h [m] min. - max.

    h [m] min. - max.

    h [m] min. - max.

    1.20 1.75 - 1.80 4 4 2.06 - 2.35 4 4 2.78 - 2.95 4 4 - 2 - 1 2 -1.80 2.02 - 2.40 4 4 2.06 - 2.95 4 4 2.78 - 3.55 4 4 - - 2 1 - 21.80 2.20 - 2.40 4 4 2.52 - 2.95 4 4 --- 4 4 4 - - 5 - -2.10 2.32 - 2.70 4 4 2.52 - 3.25 4 4 3.24 - 3.85 4 4 2 2 - 3 2 -2.40 2.62 - 3.00 4 4 2.82 - 3.55 4 4 3.54 - 4.15 4 4 - 4 - 1 4 -2.70 2.92 - 3.30 4 4 2.92 - 3.85 4 4 3.24 - 4.45 4 4 2 - 2 3 - 23.00 3.22 - 3.60 4 4 3.22 - 4.15 4 4 3.54 - 4.75 4 4 - 2 2 1 2 23.30 3.52 - 3.90 4 4 3.52 - 4.45 4 4 4.44 - 5.05 4 4 2 4 - 4 4 -3.60 3.82 - 4.20 4 4 3.82 - 4.75 4 4 4.14 - 5.35 4 4 - - 4 1 - 43.90 4.12 - 4.50 4 4 4.12 - 5.05 4 4 4.44 - 5.65 4 4 2 2 2 4 2 24.20 4.42 - 4.80 4 4 4.42 - 5.35 4 4 4.74 - 5.95 4 4 - 4 2 2 4 24.50 4.72 - 5.10 4 4 4.72 - 5.65 4 4 5.04 - 6.25 4 4 2 - 4 4 - 44.80 5.02 - 5.40 4 4 5.02 - 5.95 4 4 5.34 - 6.55 4 4 - 2 4 2 2 45.10 5.32 - 5.70 4 4 5.32 -6.25 4 4 5.64 - 6.85 4 4 2 4 2 4 4 25.40 5.62 - 6.00 4 4 5.62 - 6.55 4 4 5.94 - 7.15 4 4 - - 6 2 - 65.70 5.92 - 6.30 4 4 5.92 - 6.85 4 4 6.24 - 7.45 4 4 2 2 4 4 2 46.00 6.22 - 6.60 4 4 6.22 - 7.15 4 4 6.54 - 7.75 4 4 - 4 4 2 4 46.30 6.52 - 6.90 4 4 6.52 - 7.45 4 4 6.84 - 8.05 4 4 2 - 6 4 - 66.60 6.82 - 7.20 4 4 6.82 - 7.75 4 4 7.14 - 8.35 4 4 - 2 6 2 2 66.90 7.12 - 7.50 4 4 7.12 - 8.05 4 4 7.44 - 8.65 4 4 2 4 4 5 4 47.20 7.42 - 7.80 4 4 7.42 - 8.35 4 4 7.74 - 8.95 4 4 - - 8 2 - 87.50 7.72 - 8.10 4 4 7.72 - 8.65 4 4 8.04 - 9.25 4 4 2 2 6 5 2 67.80 8.02 - 8.40 4 4 8.02 - 8.95 4 4 8.34 - 9.55 4 4 - 4 6 3 4 68.10 8.32 - 8.70 4 4 8.32 - 9.12 4 4 8.64 - 9.85 4 4 2 - 8 5 - 88.40 8.62 - 9.00 4 4 8.62 - 9.55 4 4 8.94 - 10.15 4 4 - 2 8 3 2 88.70 8.92 - 9.30 4 4 8.92 - 9.85 4 4 9.24 - 10.45 4 4 2 4 6 5 4 69.00 9.22 - 9.60 4 4 9.22 - 10.15 4 4 9.54 - 10.75 4 4 - - 10 3 - 109.30 9.52 - 9.90 4 4 9.52 - 10.45 4 4 9.84 - 11.05 4 4 2 2 8 5 2 8

    9800

    3-11

    3

    9800

    3-11

    3

    9800

    3-11

    3

  • The Formwork Experts46 999800302 - 06/2008

    Standard application: Load capacity up to 70 kN User information Doka load-bearing tower Staxo 100

    Selection diagram

    Inclination adjustment

    Inclination is adjusted with a wooden wedge = no effect on the restraint situation.- e.g. with Wedge for screw jack U-head or

    Staxo wedge support Inclination is adjusted with a centering strip =

    Screw jack U-head not restrained.- e.g. with Hexagon screw M20x230

    Staxo 100 load-bearing tower

    Held at top Free-standing

    Head units restrained in both planes

    Head units restrained in one plane only

    Head units restrained in both planes

    Head units restrained in one plane only

    e 50 cm e 50 cmInter-frame space 1.5 - 3.0 m

    Diagrams 2 and 3Inter-frame space 1.5 - 3.0 m

    Diagrams 4 and 5Inter-frame space 1.5 - 3.0 m

    Diagrams 14 and 15Inter-frame space 1.5 - 3.0 m

    Diagrams 16 and 17Inter-frame space 0.6 - 1.0 m

    Diagrams 6 and 7Inter-frame space 0.6 - 1.0 m

    Diagrams 8 and 9Inter-frame space 1.0 m

    Diagrams 18 and 19Inter-frame space 1.0 m

    Diagrams 20 and 21Statical proof must be provided for both the bracing-strut plane and

    the frame plane.

    98003-304-01 98003-305-01

    9716-314-01

    e

    9716-314-02 9716

    -314

    -05

    9716-314-01

    e

    9716-314-02 9716

    -314

    -05

    Important note:Separate proof must be provided, by a suit-ably skilled person, regarding the founda-tion. Particular attention must be paid here to the ground-bearing pressure!

  • User information Doka load-bearing tower Staxo 100 Standard application: Load capacity up to 70 kN

    47999800302 - 06/2008 The Formwork Experts

    Load-bearing tower held at topBasic points regarding the statical proof:1. On the basis of the extension lengths of the

    screw-jacks in the base zone (LF1 and LF2), ascer-tain the relevant range A or B in Diagram 1.See the legend to Diagram 1 for details of the resulting limitations in the head zone.Range B is divided into 2 sub-ranges:- B1 ... No need to brace the spindles- B2 ... Spindles must be braced with a scaffold-

    ing tube (Z) .2. Use the result obtained (Range A or B) to ascer-

    tain the permitted vertical load and height of the load-bearing tower from the following Diagrams 2 to 9.

    Diagram 1: Finding the applicable Range

    a ... Max. eccentricity of junction or coupling: 10 cm

    Practical example: Height adjustment to steps (mixture of Range B1 and B2)

    Bracing-strut plane:e.g. LF1 = 25 cm, LF2 = 75 cm: B1 (no need for bracing with scaf-folding tubes)Frame plane 1: (on the right in the illustration)e.g. LF1 = 75 cm, LF2 = 75 cm: B2 (bracing with scaffolding tubes required)Frame plane 2: (on the left in the illustration)e.g. LF1 = 25 cm, LF2 = 25 cm: A (no need for bracing with scaffold-ing tubes)

    Practical example: All spindles extended by more than 70 cm (all planes in Range B2)

    Ext

    ensi

    on

    len

    gth

    of

    Scr

    ew ja

    ck f

    oo

    t o

    r H

    eavy

    du

    ty s

    crew

    jack

    1 L

    F1 [

    cm]

    Extension length of Screw jack foot or Heavy duty screw jack 2 LF2 [cm]

    A Extension length of Screw jack U-head LK max. 30 cm

    B Extension length of Screw jack U-head LK max. 45 cm

    Bracing-strut plane Frame plane

    V Screw jack U-head, 4-way screw-jack head, Heavy duty screw jack 70 top or U-head D

    W Staxo 100 frames 1.80/1.20/0.90m

    X Screw jack foot or Heavy duty screw jack

    Z Scaffolding tube 48.3mm with Swivel couplers 48mm (only required in Range B2 as shown in Diagram 1)

    130703000

    30

    70

    130

    9800

    3-11

    2

    B1

    B2

    A

    W

    X

    V

    Z

    X

    98003-243-01

    L KL F

    2

    L F2 L

    F1a

    a

    L F1

    L K

    D Swivel coupler 48mm

    E Diagonal cross

    F Split nut B

    W Staxo frame

    X Heavy duty screw jack 130

    Z Scaffolding tube 48.3mm

    When using "Heavy duty screw jacks 70 top" extended by more than 30 or 45 cm, always brace these with scaffolding tubes!To do this, the scaffolding tube must be fas-tened to the cross-bar of the Staxo frame.This still applies even if the "Heavy duty screw jacks 70 top" are not joined to Multi-purpose walings or Doka beams.

    V Heavy duty screw jack 70 top

    Y Bracing is only necessary if the screw-jack heads are not connected with one another by way of the formwork base.

    9800

    3-22

    8-02

    W

    X

    D

    Z

    E

    F

    9800

    3-24

    8-01

    W

    X

    D

    Z

    E

    F

    9800

    3-28

    8-01

    V

    Y

    D

    Z

    Z

    D

    F

    Y

  • The Formwork Experts48 999800302 - 06/2008

    Standard application: Load capacity up to 70 kN User information Doka load-bearing tower Staxo 100

    Load-bearing tower held at top

    Inter-frame space 1.5 - 3.0 mNumber of frame planes 2

    Head units restrained in both planes

    e 50 cm

    To ascertain the relevant range A or B, see Diagram 1.

    The relevant wind loads are to be taken from the applicable local Standards.

    Bracing-strut plane Frame planea ... 1.5 - 3.0 mh ... see diagrams

    V Screw jack U-head, 4-way screw-jack head, Heavy duty screw jack 70 top or U-head DW Staxo 100 frames 1.80/1.20/0.90mX Screw jack foot or Heavy duty screw jackZ Scaffolding tube 48.3mm with Swivel couplers 48mm (only required in Range B2 as shown in Diagram 1)

    The following diagrams do not apply to load-bearing towers that are only one Staxo 100 frame high.

    98003-244-01a

    h

    FV FV FV FV

    L KL F

    W

    X

    V

    Z

    X

    9716-314-01

    e

    Per

    mit

    ted

    ver

    tica

    l lo

    ad F

    v p

    er le

    g [

    kN]

    Diagram 2 (Range A from Diagram 1)

    Per

    mit

    ted

    ver

    tica

    l lo

    ad F

    v p

    er le

    g [

    kN]

    Diagram 3 (Ranges B1 and B2 from Diagram 1)

    Height of load-bearing tower h [m] Height of load-bearing tower h [m]

    A Impact pressure qk=0 kN/m2 (v=0 m/s = 0 km/h)

    B Impact pressure qk=0.2 kN/m2 (v=17.9 m/s = 64.4 km/h)

    C Impact pressure qk=0.8 kN/m2 (v=35.8 m/s = 129 km/h)

    9800

    3-10

    2

    100

    90

    80

    70

    60

    50

    40

    30

    20

    10

    00 5 10 15 20

    70.069.668.2

    66.265.7

    64.0

    66.265.462.9

    66.2

    65.061.0

    65.8

    63.8

    65.4

    62.4

    4.20

    m

    6.00

    m

    9.60

    m

    13.2

    0 m

    16.8

    0 m

    20.4

    0 m

    ABC

    9800

    3-10

    3

    100

    90

    80

    70

    60

    50

    40

    30

    20

    10

    00 5 10 15 20

    55.2

    53.8

    49.4

    55.2

    53.8

    49.4

    53.3

    50.8

    43.2

    50.7

    47.2

    49.3

    44.6

    48.1

    42.4

    4.75

    m

    6.55

    m

    10.1

    5 m

    13.7

    5 m

    17.3

    5 m

    20.9

    5 m

    ABC

  • User information Doka load-bearing tower Staxo 100 Standard application: Load capacity up to 70 kN

    49999800302 - 06/2008 The Formwork Experts

    Load-bearing tower held at top

    Inter-frame space 1.5 - 3.0 mNumber of frame planes 2

    Head units restrained in one plane only

    To ascertain the relevant range A or B, see Diagram 1.

    The relevant wind loads are to be taken from the applicable local Standards.

    Bracing-strut plane Frame planea ... 1.5 - 3.0 mh ... see diagrams

    V Screw jack U-head, 4-way screw-jack head, Heavy duty screw jack 70 top or U-head DW Staxo 100 frames 1.80/1.20/0.90mX Screw jack foot or Heavy duty screw jackZ Scaffolding tube 48.3mm with Swivel couplers 48mm (only required in Range B2 as shown in Diagram 1)

    The following diagrams do not apply to load-bearing towers that are only one Staxo 100 frame 1.80m high.

    98003-244-01ah

    FV FV FV FV

    L KL F

    W

    X

    V

    Z

    X

    9716-314-02 9716

    -314

    -05

    Per

    mit

    ted

    ver

    tica

    l lo

    ad F

    v p

    er le

    g [

    kN]

    Diagram 4 (Range A from Diagram 1)

    Per

    mit

    ted

    ver

    tica

    l lo

    ad F

    v p

    er le

    g [

    kN]

    Diagram 5 (Ranges B1 and B2 from Diagram 1)

    Height of load-bearing tower h [m] Height of load-bearing tower h [m]

    A Impact pressure qk=0 kN/m2 (v=0 m/s = 0 km/h)

    B Impact pressure qk=0.2 kN/m2 (v=17.9 m/s = 64.4 km/h)

    C Impact pressure qk=0.8 kN/m2 (v=35.8 m/s = 129 km/h)

    9800

    3-10

    4

    100

    90

    80

    70

    60

    50

    40

    30

    20

    10

    00 5 10 15 20

    67.266.463.9 57.356.6

    54.6

    56.455.4 55.8

    54.4

    50.2

    55.3

    53.5

    55.0

    52.752.3

    4.20

    m

    6.00

    m

    9.60

    m

    13.2

    0 m

    16.8

    0 m

    20.4

    0 m

    ABC

    9800

    3-10

    5

    100

    90

    80

    70

    60

    50

    40

    30

    20

    10

    00 5 10 15 20

    45.2

    43.940.3

    45.2

    43.940.3

    45.2

    43.6

    37.6

    45.2

    42.6

    33.8

    45.2

    41.2

    45.0

    39.8

    4.75

    m

    6.55

    m

    10.1

    5 m

    13.7

    5 m

    17.3

    5 m

    20.9

    5 m

    AB

    C

  • The Formwork Experts50 999800302 - 06/2008

    Standard application: Load capacity up to 70 kN User information Doka load-bearing tower Staxo 100

    Load-bearing tower held at top

    Inter-frame space 1.0 mNumber of frame planes 2

    Head units restrained in both planes

    e 50 cm

    To ascertain the relevant range A or B, see Diagram 1.

    The relevant wind loads are to be taken from the applicable local Standards.

    Bracing-strut plane Frame plane

    a ... 1.0 mh ... see diagrams

    V Screw jack U-head, 4-way screw-jack head, Heavy duty screw jack 70 top or U-head DW Staxo 100 frames 1.80/1.20/0.90mX Screw jack foot or Heavy duty screw jackZ Scaffolding tube 48.3mm with Swivel couplers 48mm (only required in Range B2 as shown in Diagram 1)

    The following diagrams do not apply to load-bearing towers that are only one Staxo 100 frame 1.80m high.

    98003-245-01a

    h

    FV FV FV FV

    L KL F

    W

    X

    V

    ZX

    9716-314-01

    e

    Per

    mit

    ted

    ver

    tica

    l lo

    ad F

    v p

    er le

    g [

    kN]

    Diagram 6 (Range A from Diagram 1)

    Per

    mit

    ted

    ver

    tica

    l lo

    ad F

    v p

    er le

    g [

    kN]

    Diagram 7 (Ranges B1 and B2 from Diagram 1)

    Height of load-bearing tower h [m] Height of load-bearing tower h [m]

    A Impact pressure qk=0 kN/m2 (v=0 m/s = 0 km/h)

    B Impact pressure qk=0.2 kN/m2 (v=17.9 m/s = 64.4 km/h)

    C Impact pressure qk=0.8 kN/m2 (v=35.8 m/s = 129 km/h)

    9800

    3-10

    6

    100

    90

    80

    70

    60

    50

    40

    30

    20

    10

    00 5 10 15 20

    70.370.068.9

    66.065.4

    63.6

    66.0

    65.062.0

    65.7

    63.7

    57.9

    64.9

    61.3

    63.7

    56.8

    4.20

    m

    6.00

    m

    9.60

    m

    13.2

    0 m

    16.8

    0 m

    20.4

    0 m

    AB

    C

    9800

    3-10

    7

    100

    90

    80

    70

    60

    50

    40

    30

    20

    10

    00 5 10 15 20

    52.3

    50.5

    44.9

    52.3

    50.549.2

    46.1

    36.8

    46.5

    42.1

    44.3

    38.7

    42.344.9

    4.75

    m

    6.55

    m

    10.1

    5 m

    13.7

    5 m

    17.3

    5 m

    20.9

    5 m

    A

    BC

  • User information Doka load-bearing tower Staxo 100 Standard application: Load capacity up to 70 kN

    51999800302 - 06/2008 The Formwork Experts

    Load-bearing tower held at top

    Inter-frame space 1.0 mNumber of frame planes 2

    Head units restrained in one plane only

    To ascertain the relevant range A or B, see Diagram 1.

    The relevant wind loads are to be taken from the applicable local Standards.

    Bracing-strut plane Frame plane

    a ... 1.0 mh ... see diagrams

    V Screw jack U-head, 4-way screw-jack head, Heavy duty screw jack 70 top or U-head DW Staxo 100 frames 1.80/1.20/0.90mX Screw jack foot or Heavy duty screw jackZ Scaffolding tube 48.3mm with Swivel couplers 48mm (only required in Range B2 as shown in Diagram 1)

    The following diagrams do not apply to load-bearing towers that are only one Staxo 100 frame 1.80m high.

    98003-245-01ah

    FV FV FV FV

    L KL F

    W

    X

    V

    ZX

    9716-314-02 9716

    -314

    -05

    Per

    mit

    ted

    ver

    tica

    l lo

    ad F

    v p

    er le

    g [

    kN]

    Diagram 8 (Range A from Diagram 1)

    Per

    mit

    ted

    ver

    tica

    l lo

    ad F

    v p

    er le

    g [

    kN]

    Diagram 9 (Ranges B1 and B2 from Diagram 1)

    Height of load-bearing tower h [m] Height of load-bearing tower h [m]

    A Impact pressure qk=0 kN/m2 (v=0 m/s = 0 km/h)

    B Impact pressure qk=0.2 kN/m2 (v=17.9 m/s = 64.4 km/h)

    C Impact pressure qk=0.8 kN/m2 (v=35.8 m/s = 129 km/h)

    9800

    3-10

    8

    100

    90

    80

    70

    60

    50

    40

    30

    20

    10

    00 5 10 15 20

    63.262.359.6

    55.955.2

    53.0

    54.8

    53.649.9

    54.0

    52.1

    46.1

    53.6

    50.8

    53.2

    47.9

    4.20

    m

    6.00

    m

    9.60

    m

    13.2

    0 m

    16.8

    0 m

    20.4

    0 m

    AB

    C98

    003-

    109

    100

    90

    80

    70

    60

    50

    40

    30

    20

    10

    00 5 10 15 20

    43.6

    42.1

    37.7

    43.6

    42.1

    37.7

    43.2

    40.6

    32.7

    42.3

    38.5

    41.2

    36.0

    39.9

    4.75

    m

    6.55

    m

    10.1

    5 m

    13.7

    5 m

    17.3

    5 m

    20.9

    5 m

    AB

    C

  • The Formwork Experts52 999800302 - 06/2008

    Standard application: Load capacity up to 70 kN User information Doka load-bearing tower Staxo 100

    Free-standing load-bearing tower

    Inter-frame space 1.5 - 3.0 mNumber of frame planes 2

    Head units restrained

    Bracing-strut plane Frame planeLK max. ... 30 cm (with scaffolding-tube bracing: 45 cm)LF max. ... 30 cm (with scaffolding-tube bracing: 45 cm)For bracing-solutions, see Page 47a ... 1.5 - 3.0 mh ... max. 6.0 m

    A Screw jack U-head, 4-way screw-jack head, Heavy duty screw jack 70 top or U-head DB Staxo 100 frames 1.80/1.20/0.90mC Screw jack foot or Heavy duty screw jack

    Statical proof must be provided for both the bracing-strut plane and the frame plane.For the dimensioning calculation, it is the smaller of the two results that is relevant.98003-290-01a

    h

    FVFH FH FH FH

    FV FV FV

    L KL F

    B

    C

    A

    in bracing-strut plane in frame plane

    Per

    mit

    ted

    ver

    tica

    l lo

    ad F

    v p

    er le

    g [

    kN]

    Diagram 14

    Per

    mit

    ted

    ver

    tica

    l lo

    ad F

    v p

    er le

    g [

    kN]

    Diagram 15

    Permitted horizontal load FH per leg [kN] Permitted horizontal load FH per leg [kN]The diagrams apply in cases where the superstructure is constructed with multipurpose walings and Doka beams H20 with maximum

    beam centres 'e' of 50 cm. The values derived from the diagram "in frame plane" are not dependent upon the spacing of the frame planes.

    A Impact pressure qk=0 kN/m2 (v=0 m/s = 0 km/h)

    B Impact pressure qk=0.2 kN/m2 (v=17.9 m/s = 64.4 km/h)

    C Impact pressure qk=0.8 kN/m2 (v=35.8 m/s = 129 km/h)

    D Min. imposed load against slippage = 0.3 where qk = 0.8 kN/m2 (v=35.8 m/s = 129 km/h)

    E Min. imposed load against slippage = 0.3 where qk = 0.0 kN/m2

    (v=0 m/s = 0 km/h)

    98003-306-02 98003-306-02

    9800

    3-11

    4-01

    0.0 0.5 1.0 1.5 2.0

    100

    90

    80

    70

    60

    50

    40

    30

    20

    10

    0

    1.35

    1.70

    66.2

    3.3

    63.5

    56.5

    17.0

    61.759.3

    49.1

    50.050.1

    35.0

    57.7

    36.5

    55.6

    30.0

    8.5

    29.5

    AB

    C

    D

    E

    9800

    3-11

    5-01

    0.0 0.5 1.0 1.5 2.0

    100

    90

    80

    70

    60

    50

    40

    30

    20

    10

    0

    1.35

    1.702.0

    9.3

    60.4

    40.3

    15.5

    60.4

    34.0

    53.8

    64.5

    66.2

    7.5

    16.3

    AB

    C

    DE

  • User information Doka load-bearing tower Staxo 100 Standard application: Load capacity up to 70 kN

    53999800302 - 06/2008 The Formwork Experts

    Free-standing load-bearing tower

    Inter-frame space 1.5 - 3.0 mNumber of frame planes 2

    Head units not restrained

    Bracing-strut plane Frame planeLK max. ... 30 cm (with scaffolding-tube bracing: 45 cm)LF max. ... 30 cm (with scaffolding-tube bracing: 45 cm)For bracing-solutions, see Page 47a ... 1.5 - 3.0 mh ... max. 6.0 m

    A Screw jack U-head, 4-way screw-jack head, Heavy duty screw jack 70 top or U-head DB Staxo 100 frames 1.80/1.20/0.90mC Screw jack foot or Heavy duty screw jack

    Statical proof must be provided for both the bracing-strut plane and the frame plane.For the dimensioning calculation, it is the smaller of the two results that is relevant.98003-290-01a

    h

    FVFH FH FH FH

    FV FV FV

    L KL F

    B

    C

    A

    in bracing-strut plane in frame plane

    Per

    mit

    ted

    ver

    tica

    l lo

    ad F

    v p

    er le

    g [

    kN]

    Diagram 16

    Per

    mit

    ted

    ver

    tica

    l lo

    ad F

    v p

    er le

    g [

    kN]

    Diagram 17

    Permitted horizontal load FH per leg [kN] Permitted horizontal load FH per leg [kN]The values derived from the diagram "in frame plane" are not dependent upon the spacing of the frame planes.

    A Impact pressure qk=0 kN/m2 (v=0 m/s = 0 km/h)

    B Impact pressure qk=0.2 kN/m2 (v=17.9 m/s = 64.4 km/h)

    C Impact pressure qk=0.8 kN/m2 (v=35.8 m/s = 129 km/h)

    D Min. imposed load against slippage = 0.3 where qk = 0.8 kN/m2 (v=35.8 m/s = 129 km/h)

    E Min. imposed load against slippage = 0.3 where qk = 0.0 kN/m2

    (v=0 m/s = 0 km/h)

    98003-306-01 98003-306-01

    9800

    3-11

    6-01

    0.0 0.5 1.0 1.5 2.0

    100

    90

    80

    70

    60

    50

    40

    30

    20

    10

    0

    1.70

    56.9

    3.3

    17.0

    48.2

    37.035.0

    43.7

    8.5

    23.2

    D

    A CB

    E

    9800

    3-11

    7-01

    0.0 0.5 1.0 1.5 2.0

    100

    90

    80

    70

    60

    50

    40

    30

    20

    10

    0

    1.70

    1.20

    57.3

    2.0

    54.2

    9.3

    52.0

    34.0

    15.5

    7.5

    13.7

    A C

    D

    B

    E

  • The Formwork Experts54 999800302 - 06/2008

    Standard application: Load capacity up to 70 kN User information Doka load-bearing tower Staxo 100

    Free-standing load-bearing tower

    Inter-frame space 1.0 mNumber of frame planes 3

    Head units restrained

    Bracing-strut plane Frame planeLK max. ... 30 cm (with scaffolding-tube bracing: 45 cm)LF max. ... 30 cm (with scaffolding-tube bracing: 45 cm)For bracing-solutions, see Page 47FVR ... Vertical load on edge lega ... 1.0 mh ... max. 6.0 mA Screw jack U-head, 4-way screw-jack head, Heavy duty screw jack 70 top or U-head DB Staxo 100 frames 1.80/1.20/0.90mC Screw jack foot or Heavy duty screw jack

    Statical proof must be provided for both the bracing-strut plane and the frame plane.For the dimensioning calculation, it is the smaller of the two results that is relevant.

    9800-291-01a a

    h

    FVR FVR

    F *1.25VRFV FV

    L KL F

    B

    C

    A

    FH FH FH FH FH

    in bracing-strut plane in frame plane

    Per

    mit

    ted

    ver

    tica

    l lo

    ad F

    v p

    er le

    g [

    kN]

    Diagram 18

    Per

    mit

    ted

    ver

    tica

    l lo

    ad F

    v p

    er le

    g [

    kN]

    Diagram 19

    Permitted horizontal load FH per leg [kN] Permitted horizontal load FH per leg [kN]The diagrams apply in cases where the superstructure is constructed with multipurpose walings and Doka beams H20 with maximum

    beam centres 'e' of 50 cm. The values derived from the diagram "in frame plane" are not dependent upon the spacing of the frame planes.

    A Impact pressure qk=0 kN/m2 (v=0 m/s = 0 km/h)

    B Impact pressure qk=0.2 kN/m2 (v=17.9 m/s = 64.4 km/h)

    C Impact pressure qk=0.8 kN/m2 (v=35.8 m/s = 129 km/h)

    D Min. imposed load against slippage = 0.3 where qk = 0.8 kN/m2 (v=35.8 m/s = 129 km/h)

    E Min. imposed load against slippage = 0.3 where qk = 0.0 kN/m2

    (v=0 m/s = 0 km/h)

    98003-306-02 98003-306-02

    9800

    3-11

    8-01

    0.0 0.5 1.0 1.5 2.0

    100

    90

    80

    70

    60

    50

    40

    30

    20

    10

    0

    1.80

    1.70

    47.2

    56.456.0

    54.8

    2.6

    52.4

    48.7

    12.0

    51.549.1

    19.6

    41.5

    27.031.3

    41.3

    42.0

    10.0

    22.0

    AB

    C

    DE

    9800

    3-11

    9-01

    0.0 0.5 1.0 1.5 2.0

    100

    90

    80

    70

    60

    50

    40

    30

    20

    10

    0

    1.35

    1.702.0

    9.3

    60.4

    40.3

    15.5

    60.4

    34.0

    53.8

    64.5

    66.2

    7.5

    16.3

    AB

    C

    DE

  • User information Doka load-bearing tower Staxo 100 Standard application: Load capacity up to 70 kN

    55999800302 - 06/2008 The Formwork Experts

    Free-standing load-bearing tower

    Inter-frame space 1.0 mNumber of frame planes 3

    Head units not restrained

    Bracing-strut plane Frame planeLK max. ... 30 cm (with scaffolding-tube bracing: 45 cm)LF max. ... 30 cm (with scaffolding-tube bracing: 45 cm)For bracing-solutions, see Page 47FVR ... Vertical load on edge lega ... 1.0 mh ... max. 6.0 mA Screw jack U-head, 4-way screw-jack head, Heavy duty screw jack 70 top or U-head DB Staxo 100 frames 1.80/1.20/0.90mC Screw jack foot or Heavy duty screw jack

    Statical proof must be provided for both the bracing-strut plane and the frame plane.For the dimensioning calculation, it is the smaller of the two results that is relevant.

    9800-291-01a ah

    FVR FVR

    F *1.25VRFV FV

    L KL F

    B

    C

    A

    FH FH FH FH FH

    in bracing-strut plane in frame plane

    Per

    mit

    ted

    ver

    tica

    l lo

    ad F

    v p

    er le

    g [

    kN]

    Diagram 20

    Per

    mit

    ted

    ver

    tica

    l lo

    ad F

    v p

    er le

    g [

    kN]

    Diagram 21

    Permitted horizontal load FH per leg [kN] Permitted horizontal load FH per leg [kN]The values derived from the diagram "in frame plane" are not dependent upon the spacing of the frame planes.

    A Impact pressure qk=0 kN/m2 (v=0 m/s = 0 km/h)

    B Impact pressure qk=0.2 kN/m2 (v=17.9 m/s = 64.4 km/h)

    C Impact pressure qk=0.8 kN/m2 (v=35.8 m/s = 129 km/h)

    D Min. imposed load against slippage = 0.3 where qk = 0.8 kN/m2 (v=35.8 m/s = 129 km/h)

    E Min. imposed load against slippage = 0.3 where qk = 0.0 kN/m2

    (v=0 m/s = 0 km/h)

    98003-306-01 98003-306-01

    9800

    3-12

    0-01

    0.0 0.5 1.0 1.5 2.0

    100

    90

    80

    70

    60

    50

    40

    30

    20

    10

    0

    1.70

    34.4

    46.4

    2.6

    12.0

    38.6

    32.8

    27.019.6

    10.0

    18.4D

    A CB

    E

    9800

    3-12

    1-01

    0.0 0.5 1.0 1.5 2.0

    100

    90

    80

    70

    60

    50

    40

    30

    20

    10

    0

    1.70

    1.20

    57.3

    2.0

    54.2

    9.3

    52.0

    34.0

    15.5

    7.5

    13.7

    A C

    D

    B

    E

  • 56 999800302 - 06/2008

    User information Doka load-bearing tower Staxo 100

    The Formwork Experts

    Custom application: Load capacity up to 85 kN

    Custom application: Load capacity up to 85 kN per leg

    Height ranges and materials sched-uleChoose the right diagonal crosses for the distance between the frames.

    1.20m and 0.90m frames are possible here.

    Table A

    The schedule of materials does not include assembly battens.

    The assembly battens have to be planned separately for each set-up configuration. Provided they are located in the same level, they replace the Diagonal crosses 9.xxx needed for horizontal bracing. This reduction in the number of diagonal crosses needed must be allowed for in the schedule of materials.

    The minimum values "hmin." given inTable A are only applicable if the biggest possible frame is always used in the base section.

    The lowering distance of 6 cm is already allowed for in Table A!

    LK and LF are in accordance with the dimensioning diagrams