![Page 1: DOE/NETL CO Capture R&D Program NETL CO2...Pathway Sorbent Pathway Membrane Pathway This is for New Plants and assumes comparison to SCPC plant with carbon capture ($60/tonne) Overall](https://reader034.vdocuments.us/reader034/viewer/2022050719/5e43deaea28ea513480e11b7/html5/thumbnails/1.jpg)
National Energy Technology Laboratory
Michael Matuszewski
Carbon Capture Technology Manager
2014 NETL CO2 Capture Technology Meeting
July 29th – August 1st, 2014
DOE/NETL CO2 Capture R&D Program
2014 NETL CO2 Capture Technology Meeting, Pittsburgh, PA
![Page 2: DOE/NETL CO Capture R&D Program NETL CO2...Pathway Sorbent Pathway Membrane Pathway This is for New Plants and assumes comparison to SCPC plant with carbon capture ($60/tonne) Overall](https://reader034.vdocuments.us/reader034/viewer/2022050719/5e43deaea28ea513480e11b7/html5/thumbnails/2.jpg)
Thank You
2
![Page 3: DOE/NETL CO Capture R&D Program NETL CO2...Pathway Sorbent Pathway Membrane Pathway This is for New Plants and assumes comparison to SCPC plant with carbon capture ($60/tonne) Overall](https://reader034.vdocuments.us/reader034/viewer/2022050719/5e43deaea28ea513480e11b7/html5/thumbnails/3.jpg)
R&D Areas: CO2 Capture
3
$12MM $80MM
![Page 4: DOE/NETL CO Capture R&D Program NETL CO2...Pathway Sorbent Pathway Membrane Pathway This is for New Plants and assumes comparison to SCPC plant with carbon capture ($60/tonne) Overall](https://reader034.vdocuments.us/reader034/viewer/2022050719/5e43deaea28ea513480e11b7/html5/thumbnails/4.jpg)
Carbon Capture Program Budget
4
0
10
20
30
40
50
60
70
80
90
FY 12 FY 13 FY 14
An
nu
al F
un
din
g [$
MM
]
Post-Combustion
Pre-Combustion
$69MM $66MM
$92MM
![Page 5: DOE/NETL CO Capture R&D Program NETL CO2...Pathway Sorbent Pathway Membrane Pathway This is for New Plants and assumes comparison to SCPC plant with carbon capture ($60/tonne) Overall](https://reader034.vdocuments.us/reader034/viewer/2022050719/5e43deaea28ea513480e11b7/html5/thumbnails/5.jpg)
Growth of the NETL Carbon Capture Program
5
![Page 6: DOE/NETL CO Capture R&D Program NETL CO2...Pathway Sorbent Pathway Membrane Pathway This is for New Plants and assumes comparison to SCPC plant with carbon capture ($60/tonne) Overall](https://reader034.vdocuments.us/reader034/viewer/2022050719/5e43deaea28ea513480e11b7/html5/thumbnails/6.jpg)
Program Area Key Technology Number of R&D Projects Total
TRL 1 TRL 2 TRL 3-4 TRL 5-6 TRL 7
Post-Combustion Capture
Solvents 3 9 5 - 17
Sorbents 3 9 2 - 14
Membranes 4 5 1 - 10
Hybrid/Novel 5 3 1 1 10
Pre-Combustion Capture
Solvents 2 1 - 3
Sorbents 2 1 1 - 4
Membranes 2 5 - - 7
Hybrid/Novel 3 - - - 3
Compression Compression - - 2 - 2
TRL Totals 24 33 12 1 70
Capture Program: Active Portfolio Distribution
Need for fresh, transformational ideas “Wave” of bench scale projects approaching graduation (1/2 of portfolio) Up to 12 candidate ≤1MW pilots progressing toward large pilot (25-50MW)
6
![Page 7: DOE/NETL CO Capture R&D Program NETL CO2...Pathway Sorbent Pathway Membrane Pathway This is for New Plants and assumes comparison to SCPC plant with carbon capture ($60/tonne) Overall](https://reader034.vdocuments.us/reader034/viewer/2022050719/5e43deaea28ea513480e11b7/html5/thumbnails/7.jpg)
Laboratory/Bench-Scale - Simulated operating conditions
-Short duration tests (hours/days)
- Proof-of-concept and parametric testing
- High risk -0.2 to 1,000 scf per minute
up to 0.5 MWe –> TRL: 2-4
Capture Technology Progress Performance Improvement & Scale Up Drive Costs Down
Then (>$100/Tonne)
Now (~$60/Tonne)
1 MW Solvent Pilot
(Neumann)
5 MW Oxy-combustion Pilot
(Alstom)
25 MW Solvent Heat Integration (Southern Company)
Pilot-Scale Slipstream - Real operating conditions
- Longer duration tests (weeks/months)
- Lower risk - 5,000 to 100,000 scf per minute
1.0 to 25 MWe –> TRL: 5-7
Demonstration-Scale - Variable operating conditions
- Extended duration (typically years)
- Demonstrate integrated full-scale; Minimal risk
commercial application - CO2 Utilization/Storage
Project(s) – 50 to 500 MWe –> TRL: 7+
Future (<$40/Tonne)
7
![Page 8: DOE/NETL CO Capture R&D Program NETL CO2...Pathway Sorbent Pathway Membrane Pathway This is for New Plants and assumes comparison to SCPC plant with carbon capture ($60/tonne) Overall](https://reader034.vdocuments.us/reader034/viewer/2022050719/5e43deaea28ea513480e11b7/html5/thumbnails/8.jpg)
U.S. CO2 Capture Pilots/Demos through 2017
8
![Page 9: DOE/NETL CO Capture R&D Program NETL CO2...Pathway Sorbent Pathway Membrane Pathway This is for New Plants and assumes comparison to SCPC plant with carbon capture ($60/tonne) Overall](https://reader034.vdocuments.us/reader034/viewer/2022050719/5e43deaea28ea513480e11b7/html5/thumbnails/9.jpg)
0%
5%
10%
15%
20%
25%
30%
35%
40%
Po
we
r G
en
era
tio
n P
en
alty
[%
of
Pla
nt
Ou
tpu
t]
Performance Improvements in Capture R&D Improvements Drive Down CO2 Captured Cost
2005 2012 2020
$100+/Tonne (FOAK)
~ $60/Tonne (NOAK)
< $40/Tonne (NOAK)
Energy Penalty Reductions Enable Cost Reductions
Relative to Supercritical PC Plant w/o Capture (39.3%
HHV efficiency)
9 9
![Page 10: DOE/NETL CO Capture R&D Program NETL CO2...Pathway Sorbent Pathway Membrane Pathway This is for New Plants and assumes comparison to SCPC plant with carbon capture ($60/tonne) Overall](https://reader034.vdocuments.us/reader034/viewer/2022050719/5e43deaea28ea513480e11b7/html5/thumbnails/10.jpg)
Tracking DOE Goals
Crosscutting Research
Carbon Capture
$40/tonne
A-USC Materials
($/tonne)
Post-Combustion
Capture ($/tonne)
Advanced Compression
($/tonne)
Milestone A (metric: pilot start-up, # of
test hours, etc.
Milestone B Milestone C
Supporting projects
Solvent Pathway
Sorbent Pathway
Membrane Pathway
This is for New Plants and assumes comparison to SCPC plant with
carbon capture ($60/tonne)
Overall Goal: $60/tonne to $40/tonne ($20/tonne
reduction ) through R&D which will be completed by
2020 (i.e, through large-pilot-scale and ready for demo in
2020-2025 timeframe)
Post-Combustion Pathway
Oxycombustion Pathway
IGCC Pathway
Check marks indicate info or data that we
have available, or boxes that are part of
the chart’s flow pattern.
Example: Post-Combustion Pathway, 2nd Generation
Technology
10
![Page 11: DOE/NETL CO Capture R&D Program NETL CO2...Pathway Sorbent Pathway Membrane Pathway This is for New Plants and assumes comparison to SCPC plant with carbon capture ($60/tonne) Overall](https://reader034.vdocuments.us/reader034/viewer/2022050719/5e43deaea28ea513480e11b7/html5/thumbnails/11.jpg)
![Page 12: DOE/NETL CO Capture R&D Program NETL CO2...Pathway Sorbent Pathway Membrane Pathway This is for New Plants and assumes comparison to SCPC plant with carbon capture ($60/tonne) Overall](https://reader034.vdocuments.us/reader034/viewer/2022050719/5e43deaea28ea513480e11b7/html5/thumbnails/12.jpg)
![Page 13: DOE/NETL CO Capture R&D Program NETL CO2...Pathway Sorbent Pathway Membrane Pathway This is for New Plants and assumes comparison to SCPC plant with carbon capture ($60/tonne) Overall](https://reader034.vdocuments.us/reader034/viewer/2022050719/5e43deaea28ea513480e11b7/html5/thumbnails/13.jpg)
![Page 14: DOE/NETL CO Capture R&D Program NETL CO2...Pathway Sorbent Pathway Membrane Pathway This is for New Plants and assumes comparison to SCPC plant with carbon capture ($60/tonne) Overall](https://reader034.vdocuments.us/reader034/viewer/2022050719/5e43deaea28ea513480e11b7/html5/thumbnails/14.jpg)
![Page 15: DOE/NETL CO Capture R&D Program NETL CO2...Pathway Sorbent Pathway Membrane Pathway This is for New Plants and assumes comparison to SCPC plant with carbon capture ($60/tonne) Overall](https://reader034.vdocuments.us/reader034/viewer/2022050719/5e43deaea28ea513480e11b7/html5/thumbnails/15.jpg)
Recent Accomplishments
![Page 16: DOE/NETL CO Capture R&D Program NETL CO2...Pathway Sorbent Pathway Membrane Pathway This is for New Plants and assumes comparison to SCPC plant with carbon capture ($60/tonne) Overall](https://reader034.vdocuments.us/reader034/viewer/2022050719/5e43deaea28ea513480e11b7/html5/thumbnails/16.jpg)
Title: “Development of Post-Combustion and Pre-Combustion Carbon Dioxide Capture Technologies for New and Existing Power Plants”
• Fill in the R&D technology gaps identified since the last FOA – Hybrid Approaches (3 bench-scale projects selected)
– Enabling Technologies (2 projects selected)
• Continuation of ARPA-E projects – 4 projects selected – funding for these projects could not have been extended
under ARPA-E
• Continuation of “best-in-class” FE R&D projects in the existing Capture Program and through the SBIR program – 2 bench-scale projects selected
• Scale-up of the most promising laboratory/bench-scale projects to pilot-scale (0.5 to 5 MWe) – 8 existing bench-scale projects were advanced to pilot-scale. . .highest priority
of the FOA
• A total of 18 projects were awarded
2013 FOA Results
15
![Page 17: DOE/NETL CO Capture R&D Program NETL CO2...Pathway Sorbent Pathway Membrane Pathway This is for New Plants and assumes comparison to SCPC plant with carbon capture ($60/tonne) Overall](https://reader034.vdocuments.us/reader034/viewer/2022050719/5e43deaea28ea513480e11b7/html5/thumbnails/17.jpg)
National Carbon Capture Center Awarded
Pilot Solvent Test Unit
Post Combustion
PC4 Facility – 4.3MWe Real PC flue gas Bench through pilot scale ~25,000 hours of testing 15 Technologies tested “Tech-Flexible”
Pre Combustion
6.3MWe Trig gasifier Air- or O2 fired syngas Bench through pilot scale ~20,000 hours of testing 13 gasifier runs “Tech-Flexible”
– World Class Carbon Capture Technology Test Facility –
TRIG Gasifier
5 year $150MM
$100MM Capture Funding
Independent Test Facility
Supports Capture & Gasification
16
![Page 18: DOE/NETL CO Capture R&D Program NETL CO2...Pathway Sorbent Pathway Membrane Pathway This is for New Plants and assumes comparison to SCPC plant with carbon capture ($60/tonne) Overall](https://reader034.vdocuments.us/reader034/viewer/2022050719/5e43deaea28ea513480e11b7/html5/thumbnails/18.jpg)
• Expanding borders of capture technology
• Broadened Horizons to New Approaches – Electrochemical
– Advanced/Non-Aqueous Solvents
– Direct CO2 Phase Change
– Nano-Engineered Materials for CO2 Capture
– Process Intensification
• Hybrid systems – working together!
2013 SBIR Encouraging Transformational Research
17
![Page 19: DOE/NETL CO Capture R&D Program NETL CO2...Pathway Sorbent Pathway Membrane Pathway This is for New Plants and assumes comparison to SCPC plant with carbon capture ($60/tonne) Overall](https://reader034.vdocuments.us/reader034/viewer/2022050719/5e43deaea28ea513480e11b7/html5/thumbnails/19.jpg)
“If I have seen further than others, it is by standing upon the shoulders of giants.” – Isaac Newton
18
![Page 20: DOE/NETL CO Capture R&D Program NETL CO2...Pathway Sorbent Pathway Membrane Pathway This is for New Plants and assumes comparison to SCPC plant with carbon capture ($60/tonne) Overall](https://reader034.vdocuments.us/reader034/viewer/2022050719/5e43deaea28ea513480e11b7/html5/thumbnails/20.jpg)
For More Information About the NETL Carbon Capture Program
Annual CO2 Capture Meeting
Michael S. Matuszewski
Technology Manager
Carbon Capture Program
National Energy Technology Laboratory
U. S. Department of Energy
(Tel) 412-386-5830
• Office of Fossil Energy website:
www.fe.doe.gov
Reference Shelf
• NETL Website:
– www.netl.doe.gov
• Capture Program Website:
– www.netl.doe.gov/technologies/
coalpower/ewr/co2/index.html
19