Division 200 Specifications: Earthwork Overview of Major Revisions MICHELLE R. MANN, P.E. [email protected] (505) 490-1507 NMDOT GEOTECHNICAL ENGINEERING/EXPLORATION SECTION MANAGER

Upload: others

Post on 03-Jul-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Division 200 Specifications: Earthwork · 2. The Contractor has requested to begin Borrow operations and the Project Manager has concurred; and 3. Embankment areas that require borrow

Division 200

Specifications: EarthworkOverview of Major Revisions

MICHELLE R. MANN, P.E.

[email protected] (505) 490-1507

NMDOT GEOTECHNICAL ENGINEERING/EXPLORATION SECTION MANAGER

Page 2: Division 200 Specifications: Earthwork · 2. The Contractor has requested to begin Borrow operations and the Project Manager has concurred; and 3. Embankment areas that require borrow

Division 200 Specifications2014 Specification 2019 Specification Modifications

201: Clearing and Grubbing 201: Clearing and Grubbing Minor Revisions

203: Excavation and Borrow 203: Excavation and Borrow Major Revisions

- 203-A Unstable Subgrade Stabilization Newly added

206: Excavation and Backfill for

Culverts and Minor Structures

206: Excavation and Backfill for Culverts and

Minor StructuresMajor Revisions

207: Subgrade Preparation 207: Subgrade Preparation Minor Revisions

208: Linear Grading Deleted Due to overlap with Section

209

209: Blading and Reshaping 209: Blading and Reshaping Minor Revisions

210: Excavation and Backfill for Major

Structures

210: Excavation and Backfill for Major

StructuresMajor Revisions

213: Obliterating Old Road 213: Obliterating Old Road Minor Revisions

Page 3: Division 200 Specifications: Earthwork · 2. The Contractor has requested to begin Borrow operations and the Project Manager has concurred; and 3. Embankment areas that require borrow

Minor Revisions

Section 201 Clearing and Grubbing

Section 207 Subgrade Preparation

Updated Section 207.3 to remove Subexcavation.

The Contractor shall ensure the top two (2) feet of borrow Materials in the finished Subgrade is comprised of Material with the design R-value.

Section 213: Obliterating Old Road

Section 209 Blading and Reshaping

Due to overlap in requirements and frequency of use, applicable sections

of 208: Linear Grading were combined with section 209: Blading and

Reshaping

Page 4: Division 200 Specifications: Earthwork · 2. The Contractor has requested to begin Borrow operations and the Project Manager has concurred; and 3. Embankment areas that require borrow

203: Excavation, Borrow, and

Embankment Recall per Section 203.4.1 Rock

Excavation

Page 5: Division 200 Specifications: Earthwork · 2. The Contractor has requested to begin Borrow operations and the Project Manager has concurred; and 3. Embankment areas that require borrow

203: Excavation, Borrow, and

Embankment

2014 Specification

Ripping Test. Material that cannot be broken down by one pass with a single tooth ripper mounted on a crawler-type tractor in low gear with a minimum net flywheel power rating of 255 hp;

2019 Specification

Ripping Test. Material that cannot be broken down with two passes parallel to construction centerlinewith a single tooth ripper mounted on a crawler-type tractor in low gear with a minimum net flywheel power rating of 255 hp;

Page 6: Division 200 Specifications: Earthwork · 2. The Contractor has requested to begin Borrow operations and the Project Manager has concurred; and 3. Embankment areas that require borrow

203: Excavation, Borrow, and Embankment203.2.1.3 Borrow

Borrow shall consist of Contractor provided suitable Embankment Materials obtained from an

approved source outside the Right of Way, unless otherwise specified in the Contract.

The Contractor shall only utilize borrow when the following conditions are met, unless

approved otherwise by the Project Manager:

1. All unclassified excavation Material has be utilized in the Contractor’s current phase of

construction;

2. The Contractor has requested to begin Borrow operations and the Project Manager has

concurred; and

3. Embankment areas that require borrow have been bladed and cross sectioned by the

Contractor and provided to the Project Manager.

Borrow Material placed within two (2) Ft, vertically and laterally, of final Subgrade elevations

shall meet the design R-Value as shown in the Contract. Prior to borrow operations the Contractor

shall perform R-value testing in accordance with AASHTO T-190 at the best fit exudation pressure of

300 psi at each borrow source. This information shall be submitted to the Project Manager with the

request to begin borrow operations. During borrow placement, if the Project Manager observes

changes in soil properties, including gradation, plasticity limits, and/or additional soil

characteristics, then, at the Project Manager’s request, additional AASHTO T-190 tests may be

required, at the Contractors expense.

When Work conforming to Section 306, “Portland Cement or Lime Treated Subgrade” is

specified in the Contract, the Contractor shall perform sulfate testing in accordance with AASHTO

T290 at each borrow source. Sulfate content shall be determined and reported as parts per million

(ppm). Soils with sulfate contents equal to or greater than 2,000 ppm shall

not be used as borrow.

Page 7: Division 200 Specifications: Earthwork · 2. The Contractor has requested to begin Borrow operations and the Project Manager has concurred; and 3. Embankment areas that require borrow

203: Excavation, Borrow, and Embankment

2014 Specification

203.2.1.4 Subexcavation – Associated with R-Value

and Deleterious Material

203.2.1.5 Unstable Subgrade Stabilization

2019 Specification

203.2.1.4 Unstable Subgrade Stabilization – References

203-A: Unstable Subgrade Stabilization

203.2.1.5 Unsuitable Material – Includes types of

unsuitable material and differentiates between

unsuitable and unstable materials.

Page 8: Division 200 Specifications: Earthwork · 2. The Contractor has requested to begin Borrow operations and the Project Manager has concurred; and 3. Embankment areas that require borrow

203: Excavation, Borrow, and

EmbankmentConstruction Requirements

Page 9: Division 200 Specifications: Earthwork · 2. The Contractor has requested to begin Borrow operations and the Project Manager has concurred; and 3. Embankment areas that require borrow

203: Excavation, Borrow, and Embankment

Method of Measure

203.4.3 Unclassified Excavation and Borrow

For each phase identified in the Contract the Contractor is required to

measure the original ground surface of all cut, fill and borrow areas.

For embankment and borrow areas the Contract is required to measure the

final surface once the operations are complete.

Earthwork quantities are calculated as the neat volume from the original

ground surface (less the existing Roadway surfacing) between the limits shown

on the plans, and/or authorized changes by the Project Manager, and the

new ground surface.

The Department will not apply any shrinkage or swell factor due to payment

being made on the final cross sectioned volume.

The measurements are performed by means of a survey using electronic XML-

compatible format for each phase of the project at 50-foot intervals and a

report is generated that summarizes the basis for the final volumes.

Page 10: Division 200 Specifications: Earthwork · 2. The Contractor has requested to begin Borrow operations and the Project Manager has concurred; and 3. Embankment areas that require borrow

203: Excavation, Borrow, and

Embankment

203.5 Basis of Payment

2014 Specification

2019 Specification

Page 11: Division 200 Specifications: Earthwork · 2. The Contractor has requested to begin Borrow operations and the Project Manager has concurred; and 3. Embankment areas that require borrow

203: Excavation, Borrow, and

Embankment

203.5.1 Double Handling

Department will pay for excavated Materials that require more than

one handling as identified in the Contract.

Paid for as the bid item unit price for each handling approved by

the Project Manager.

Double handling does not include excavated and borrow materials

requested by the Contractor for their convenience.

For example, stockpiling excess unclassified excavation material that will

be used in a later phase

Double handling shall not be paid, for Material that is excavated

and placed in the same phase of the project.

Page 12: Division 200 Specifications: Earthwork · 2. The Contractor has requested to begin Borrow operations and the Project Manager has concurred; and 3. Embankment areas that require borrow

New 203A: Unstable Subgrade

Stabilization

Stabilization of unstable subgrade soils

encountered in non-borrow sections, such as

cuts or existing grades within and not

exceeding the top two (2) feet of finished

subgrade elevation…

Revised definition to clarify proof rolling.

Stabilization options may consist of mechanical

stabilization and/or reworking existing Materials.

Page 13: Division 200 Specifications: Earthwork · 2. The Contractor has requested to begin Borrow operations and the Project Manager has concurred; and 3. Embankment areas that require borrow

206: Excavation and Backfill for Culverts and

Minor Structures

206.2. Materials

Page 14: Division 200 Specifications: Earthwork · 2. The Contractor has requested to begin Borrow operations and the Project Manager has concurred; and 3. Embankment areas that require borrow

210: Excavation and Backfill for Major

Structures

Deleted 210.3.3 Contractor Certification of Backfill

Modified Method of Measure

Major Structure Excavation

Major Structure Backfill

Page 15: Division 200 Specifications: Earthwork · 2. The Contractor has requested to begin Borrow operations and the Project Manager has concurred; and 3. Embankment areas that require borrow

210: Excavation and Backfill for Major

Structures

210.4.2 Major Structure Excavation

Measurement is made for each phase of the project based on the neat

volume below the original ground surface and the final excavated ground

surface.

Contractor is required to survey and submit the original ground surface and

the final excavated ground surface in a volume summary report.

Project Manager can request cross section intervals that adequately

quantify the volumes.

Volumes that do not count toward structure excavation are included in

210.4.1 (7 items).

Page 16: Division 200 Specifications: Earthwork · 2. The Contractor has requested to begin Borrow operations and the Project Manager has concurred; and 3. Embankment areas that require borrow

210: Excavation and backfill for major

structures

210.4.2 Major Structure Backfill

Measurement is made for each phase of the project based on the cubic yard compacted in place.

Major structure backfill is calculated as the neat volume above existing or excavated ground surface and the final compacted ground surface.

Contractor is required to survey and submit the existing or excavated ground surface and the final compacted ground surface for each phase.

Project Manager can request cross section intervals that adequately quantify the volumes.

No measurement for payment will be made for additional backfill required due to slides, cave-ins, infilling, overexcavation or carelessness of the Contractor.

Page 17: Division 200 Specifications: Earthwork · 2. The Contractor has requested to begin Borrow operations and the Project Manager has concurred; and 3. Embankment areas that require borrow

Questions

My Contact information:

Michelle R. Mann, P.E., [email protected] 505.490.1507

For Questions regarding the Specifications contact your CLE.

Thank you to all core and ad-hoc committee members that assisted with this effort