earthwork record system. earthwork record system the earthwork record system keeps a graphical...
TRANSCRIPT
EARTHWORKRECORD SYSTEM
Earthwork Record System
• The Earthwork Record System keeps a graphical representation of density tests and record of density tests for the earthwork portion of a construction project.
• It is the best method we know of to document that earthwork construction meets the requirements of the contract.
• The Earthwork Record System (ERS) is composed of form 675-020-27 maintained by the Contractor (QC) and form 675-020-28 maintained by the Engineer(VT).
• Question. What is the most important thing you can do for the IA inspector?
• Answer. The number 1 most important message from Earthwork IA is to understand the logbook.
Earthwork Record system
What is the function of the logbook?
• Used as the basis for accepting completed roadway earthwork.
• It contains forms and directions for earthwork construction.
Earthwork Record System
Contractor’s Responsibilities
• Quality Control? – Plot roadway and drainage sheets– Assemble the QC ERS Form 675-020-27– Maintain the QC ERS throughout the project.– Take QC densities– Sample, split and test for proctors– Maintain resolution and verification samples– Sample for all QC lab tests– QC takes resolution density tests– Meet the requirements of the contract.
• Verification? – Verify Contractor’s Results– Review Earthwork Record System for
completeness and accuracy.– Provide the reference gauge for comparisons
on new gauges brought to the project– Sample for LBR– Verification density testing– Witness surface and depth checks
Department’s Responsibilities
• District Materials IA– Explain to project personnel what is needed to make
sure Earthwork documentation can be understood.– Provide the reference nuclear density gauge for
initial comparison– Review ERS to make sure any deficiencies are
resolved– Perform Quality Performance Reviews for
technicians (QPR’s)– Observe ongoing construction
Department’s Responsibilities
Parts of the Record System
675-020-27 CONTRACTOR QC EARTHWORK
DENSITY RECORD SYSTEM
• This is the Earthwork Record System maintained by the Contractor and consists of pages for: Earthwork Density Report Pavement Plot Summary of Proctors LOT Index and Special Conditions Stabilizing Mixing Depth Rock Base Thickness Random Number Generator
• Gauge comparison sheet – Documents initial gauge comparisons required by
120- 10.1.1– A note requires gauge calibration sheets to be
kept with the Density Log Books.– The initial gauge comparison compares QC and VT
gauges to the District IA gauge.– Any new gauges brought out to the project shall
be compared to the verification gauge.
Earthwork Record System
7-1
8-1
9-1
10-2
• Included in QC & VT Logbooks
Summary of Proctors
2-16
The Proctor is a laboratory test which establishes a density standard that a contractor must achieve a certain percent of, in the field for a given material.
What is the Proctor
2-17
Unit Weight - the weight of a material occupying a unit volume.
Wet Density - the weight of soil and water occupying a unit volume.
Dry Density - the weight of just the soil solids occupying a unit volume.
Moisture Content - the amount of water, in the soil occupying a unit volume, (generally expressed in Percent of Dry Weight).
To understand the proctor you need to know:
2-18
Compaction is achieved by inputting energy to expel the air and water in the soil’s voids.
The reduction of these voids creates the following changes in the material:
• Increase in unit weight• Decrease in compressibility• Decrease in Permeability
Air Water
Air Water
Energy
How proctor relates to compaction
2-19
Just Right
MAXIMUM DENSITY (B)@
OPTIMUM MOISTURECONTENT (A)
100%
98%
Target AreaB
A
DryDensity
(pcf)
% Moisture
This is the maximumachievable densityfor the compactive effort.
Dry Mud
THE LABORATORY PROCTOR
2-20
FM 1 T-180 (FM 5-521) Moisture Density Relations of Soils Using 10-lb. (4.54-kg) Rammer and 18-inch (457-mm) Drop 56 blows/ layer - 5 layers
AASHTO T 99 (FM 5-525) Moisture Density Relations of Soils Using 5.5-lb. (2.5-kg) Rammer and 12-inch (305-mm) Drop 25 blows/layer - 3 layers
MODIFIED PROCTOR
TWO TYPES OF PROCTORS
STANDARD PROCTOR
2-21
The plotted data, represents a curvilinear relationship known as the Compaction Curve or more commonly, the Proctor Curve.
THE PROCTOR CURVE
118.0 pcf@ 12.5%
Unit Weight of Soil, lbs/cuft
98% of max. density = ______pcf
Plots • Computer plotted and page numbered.
• Shall accurately illustrate the required testing (the first to the last lift placed).
• Changes or replots that reflect a change from the plan cross sections shall have a detailed note.
• Verification plots may be used at the option of the Project Administrator
Attach computer plotted graphs for the sections with:
• EmbankmentUse a different bar chart for each pavement layer compacted separately. For the sections with no Embankment, the Pavement Plot sheet may be used.
• DrainageAttach plots for all Drainage structures that require testing.
• MSE Wall ConstructionA shorter section roadway graph, less than 500 feet may be used to plot sections of MSE wall construction.
EXCAVATION OF UNSUITABLE MATERIALS
• All computer-plotted embankment graphs shall be corrected for excavation of unsuitable materials.
• The anticipated depth of excavation may be coded as an undercut depth, to provide a blank space for hand corrections.
• If the graph is re-plotted, make an appropriate note to identify deviation from the plans.
When there is no embankment
Coding the Density Log book
Roadway & Drainage Plots
Getting Started
Download the DLB Plot Program to your PC from the FDOT website.
http://www.dot.state.fl.us/ecso/downloads/software/
http://materials.dot.state.fl.us/smo/Geotechnical/Earthwork/operations.htm
Required for Coding Roadway
• Highest proposed pavement elevation• Lowest existing ground elevation• Code for unsuitable material• Locate Shoulder break points and draw the
1:2 control line• Code thickness of Asphalt, Base, & Subgrade• Code pads for Shoulder base, Shoulder
Subgrade, Sidewalk, etc.
Code Critical points for both Left and Right Roadways from each Cross Section
PROJECT NUMBER PAGE NO:
SURFACE THICKNESS .250 BASE THICKNESS 20 SUBGRADE THICKNESS 1.00 UNDERCUT 1.00
REMARKS:
LABEL
THICKNESS
PAD 1 PAD 2 PAD 3 PAD 4
STATION 1 STATION 2 STATION 3 STATION 4 STATION 5 STATION 6 STATION + + + + + +
PROPOSED
EXISTING
STATION + + + +
PROPOSED
EXISTING
STATION PROPOSED
EXISTING
STATION + + + + +
PROPOSED
EXISTING
RECORD NO.________________ HEADER NO._______________
21066935201 1
Ratliff Rd New Construction
20 5017.8014.50
021 0018.50
14.80
21 5018.7514.85
22 50 23 5019.5017.20
24 8019.8017.00
32 89
19.80
17.00
33 50
19.70
15.70
19.1017.30
34 + 00 35 00
38+5038+0037+0036+0035 + 00 21.33 21.14 20.7820.4120.05
20.3018.70 18.6616.9017.20
20.05 19.69
17.20 16.40
0.4
RTSB
.333
RSSG
.479
LSSG
.417
From Typical Sections
Elevation in Feet
Base Subgrade
Shoulder BaseShoulder Subgrade
Bar Graphs
Existing ground level Proposed grade
Stationing WH
x
x x
xx
x
WH
12-30-09
1-3-10
1-3-10
ROADWAY PLOT
EARTHWORK
Bar Graphs
Base Subgrade
Shoulder BaseShoulder Subgrade
Cut Fill
Existing ground level Proposed grade
Stationing
Elevation in Feet
Required for Coding Drainage
• Flow line• Top & bottom Structure elevation• Length & size of pipe• These values are manually read from the
plans. This information rarely given in one place.– May require cross referencing with plan/profile or
summary of drainage structures.
Some structure tops & bottoms must be scaled from cross sections.
We need to find the lengths of pipe.
PROJECT NO_______________________________________ PAGE
PIPEREMARKS
LENGTHFEET/METERS
TYPE SIZEINCH/MM
STRUCTURE ONE
NUMBER TOPFLOWLINE
BOTTOM
STRUCTURE TWO
PIPE BACKFILL CODE SHEET
BOTTOMFLOWLINE
TOPNUMBER
Sta 21+50 to 22+68 115’ RCP 18” S-1 16. 57 13.45 S-2 18.20 13.20
Sta 22+68 X-Drain 75’ RCP 18” S-3 18.00 13.05 S-2 18.20 13.20
22+78 to 22+68 27’ RCP 18” S-3A 18.00 12.99 S-3 18.00 13.05
Sta 22+78 Lt 10’ RCP 18” MES 12.95 S-3A 18.00 12.99
21066935201
33+50 to 33+50 55 RCP 18” S-4 18.75 16.00 14.75 S-4 18.65 15.90 14.65 22+68 to 33+65 305 RCP 18” S-3 18.00 13.05 S-6 17.50 13.80
33+65 to 33+65 44 RCP 18” S-6 17.50 13.80 S-5 18.04 13.90
33+65 to 33+95 30’ RCP 18” S-6 17.50 13.80 S-7 18.19 13.90
18+ 07 to 17+35 72’ RCP 18” S-7A 17.05 S-7A 17.58
21+35 to 21+80 25’ RCP 18” MES 14.25 S-8 17.50 14.50
24+00 to 24+00 9’ RCP 18” S-9 18.00 13.95 MES 13.93
24+00 to 24+43 44 RCP 18 S-9 18.00 13.95 S-11 16.81 14.05
24+43 to 24+43 48’ RCP 18” S-11 16.81 14.05 S-10 16.65 14.15
WH
Page 115
XX X
X
WH
X
Test Locations
Page 115
What about Lot numbering?• Number LOTs combined with page
number (Lot# - Corresponding Page #)
• Example Lot 11-27, means lot 11, and page 27
• Start a new set of numbers for each type of construction on each sheet. i.e Pipe Backfill, Embankment, Subgrade, Base, MSE Wall
REMEMBER
• The District Materials Officeis there to help
• Check with the Materials Office about:Preliminary PagesRequirements of Lot IndexCoding elevations from PlansUsing the DLB Plot ProgramOther Logbook questions
Earthwork Record System Common mistakes in the Density Log Book
1. Missing density tests (both QC & VT)2. Missing dispositions/pre determined
dispositions .3. Density tests are not taken at a randomly
selected location. Lots for verification are not selected randomly
4. The plotted graph elevations are not correct.5. Water Table is not noted with initial & date
Earthwork Record System Common mistakes in the Density Log Book
6. Embankment is placed over more than one untested lot.
7. Nuclear density gauges are not compared before usage
8. Test sections are not performed before thick lift compaction
9. Notes are not used to explain the logbook
Nuclear Density & Speedy Moisture test Procedures
Film
Key Earthwork Specs
Recent changes to Stabilizing
• 914 describes material properties for the material used for stabilizing. The approval process was removed from this section.
• An acceptance program for local material has been added to Section 160
Witness - Sections 160 & 200
• Thickness and surface checks are verified by witness & recording the QC measurements .
• Unless the Engineer requests, no holes are drilled for Verification
• Accurate measurements are important because payment for base is computed from QC measurements.
• Test Strip Requirements for 12 inch thick compacted lifts.• 125-8.1.6 – In the soil envelope - maximum allowed thickness of backfill is 6 inches.
Max. Lift Thickness
Requirements for max. 12 inch thick compacted Earthwork
Material Embankment 120-8.2
Pipe Backfill125-8.1
A-3 and A-2-4 soils with up to 15% fines
No Test strip required
Test strip required
A-1, Plastic materials, and A-2-4 Materials with greater than 15% fines
Test strip required Test strip required
Section 125-8.3• What is the Soil Envelope?
The Soil Envelope is the ______zone and the _______zone for the pipe.
Soil Envelope
• How many passing density tests are required before the contract allows Reduced Frequency Density Testing for;
• Embankment?_____
• Pipe backfill?______
• 125-9.1.1 - requires LOTS to be selected randomly when reduced frequency testing is performed
Reduced Frequency Testing
• Plastic and Metal pipe backfill requires 95% of Standard Proctor for density.
• Concrete pipe backfill requires 100% of Standard Proctor.
• Structure backfill requires 100% of Standard proctor regardless of the type of pipe joining the structures.
125 – Pipe Backfill
• What are the density testing requirements when a metal pipe is connected to a concrete structure?
____standard proctor for the metal pipe &
_____standard proctor for the structure.
Density Testing Pipe/Structure
• Acceptance Program - 120-10 & 125-9– Both QC and VT inspectors are required to select
test locations, including station, offset and Lifts using a random number generator approved by the Engineer.
– A Chart has been added to the Earthwork Record System forms to assist with generating Random Numbers.
Location for Sampling and Testing
QUESTIONS & ANSWERS
WHAT’S ?
END