dition number 4 in-plant material supply – choice of principle

12
In-plant material supply – Choice of principle ROBIN HANSON Northern LEAD Outlook Edition number 4

Upload: others

Post on 04-Jun-2022

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: dition number 4 In-plant material supply – Choice of principle

In-plant material supply – Choice of principle

Robin Hanson

Northern LEAD Outlo

ok

Edition number 4

Page 2: dition number 4 In-plant material supply – Choice of principle
Page 3: dition number 4 In-plant material supply – Choice of principle

Introduction

When mass production’s benefits of scale are weighed against customers’ increasingly higher demands for individually customized products, the questions about in-plant material supply come into focus. In the manufacturing industries, where large production volumes are combined with broad variation in the completed products, one speaks of mass-customization, with the choice of material feeding principle being far from self-evident. The following can be seen as the two primary alternatives:

Kitting – Individual parts are packed in advance into a kit that matches assembly’s needs for a certain product.

Continuous supply – The parts needed at each assembly station are delivered part number by part number to the assembly station and the assembler takes parts as needed for the pertinent product in conjunction with each assembly step.

With both of the principles, there are several advantages and disadvantages, and there is no clear-cut recommendation for which solution is best. What is clear however, is that a wrong decision can entail negative consequences for the enterprise on the whole.

Limited knowledgeDespite both kitting and continuous supply being established principles that have been applied for quite some time, the choice of material supply principle is often associated with considerable

uncertainty. From the academic perspective as well, clear and adequate guidance has previously been lacking. Granted, there are research models that compare material supply principles with one another. These models however, are characterized by simplifications and a relatively small amount of performance indicators: well-defined aspects of production against which the effects of the decided-upon principle are measured and analyzed. Moreover, stringent demands are set for detailed input data, something which in practice is often difficult to obtain.

While earlier studies have tended to address the selection of material supply principle as an isolated question, Robin Hanson argues for a broadened perspective, where the choice of feeding principle is considered based on the overall consequences for performance.

Knowledge, context – and decision-making support The right choice of material feeding principle and in-plant material supply system requires both advanced understanding of the advantages and disadvantages that the respective solutions can entail, as well as a capacity to place the question in a general production context. Once these pieces are in place, a well-structured decision-making process is needed. This constitutes the core in Robin Hanson’s thesis – a combination of practical orientation and bridging of theoretical gaps that have previously existed in the field.

Page 4: dition number 4 In-plant material supply – Choice of principle

The thesis’ empirical foundation primarily consists of field studies from the Swedish automotive industry, where most of the studies exhibit a chiefly qualitative character. The qualitative approach entails that a comparatively large number of performance indicators could be included in the analysis, which in turn is a prerequisite for an in-depth understanding of the differences between the two principles. Because the assembly process in the automotive industry is presently characterized by major similarities, regardless of brand and country where assembly is conducted, the results are thus considered as valid for this industry on the whole. But not just there. The thesis’ theoretical base, together with the stated ambition of describing the studies’ context in great detail, makes large portions of the results also relevant to other types of assembly industries.

The material feeding principle is one of several factors that determine how well an assembly plant functions. The plant’s physical layout and conditions, stock levels and packaging are some examples of all the aspects that influence – and

are influenced by – the material supply principle. Against this background, it is therefore important that the enterprise’s character on the whole guides the choice of material supply principle.

More than just efficiencyThere is a tradition in industry of a pronounced efficiency focus in strategic and tactical decisions, which often leads to an overly narrow selection of performance indicators in the analysis phase. The result is insufficient input for decision-making, where apparent positive effects of a decision can have negative consequences in other parts of the enterprise that are omitted from the analysis.

In contrast to the traditional view of efficiency, Robin Hanson identifies relevant performance indicators, which together create the conditions for a balanced and more complete picture of the degree of yield in production. The performance indicators and their placement in the subsequent production context are illustrated in the figure above.

Context of the in-plant materials supply system

Product- and part-related factors Production-related factors Layout-related factors

Configuration of the in-plant materials supply system

Materials feeding principlesMaterials handling and transportation Packaging and unit loads Manufacturing planning and control Storage and inventory

Performance

Man-hour consumptionProduct quality and assembly support Inventory levels and space requirements FlexibilityControl and visibilityProduct throughput timeErgonomics

The performance indicators and their placement in the general production context.

Page 5: dition number 4 In-plant material supply – Choice of principle

described in the figure on the previous page. As regards to the effects of the chosen material supply principle, the empirical results are not clear-cut, a fact that in itself emphasizes the importance of always letting the decision-making process have its departure point in the plant’s larger production context.

2. Kitting: The preparation stage’s effects on performanceBecause many of the potential problems when applying kitting can be related to the actual preparation stage, a closer study of this is justified. There are countless solutions for when, where and how kit preparation should be conducted, solutions that in turn have shown to play a major part in the overall results of applying kitting as a material supply principle.

A deeper understanding

One of the basic prerequisites for being able to make correct decisions in the choice between kitting and continuous supply is advanced knowledge of both alternatives. Despite this, the research surrounding the effects of decisions on material supply principle has previously been limited The thesis’ three research questions focus on the most common knowledge gaps.

1. Kitting or continuous supply: Effects on assembly and material supplyThe analysis that should precede the choice of material feeding principle is complicated. Advantages, which initially seem unquestionable, often have their opposite poles in the form of negative side or attendant effects. As an example, kitting in comparison to continuous supply can reduce man hours at the assembly stations; assemblers do not need to search for individual parts nor go as far to fetch each part.

Countering these savings in time are negative consequences, such as expended time, space and costs for preparation of the kits and in-plant transports of kits between preparation locations and the assembly stations. And if the kits are imperfect due to incorrect preparation, the desired savings in time can instead be quickly turned into loss. Consequently, this type of risk must also be included in the calculation.

The list of similar “opposite pairs” can be long, between or within the performance indicators

Part size, packaging and storage space are examples of factors that determine the results of the selected material supply principle.

Page 6: dition number 4 In-plant material supply – Choice of principle

Kit preparation can, depending on the circumstances in the specific case, be carried out in the warehouse, at a specially adapted area located at a central location in the plant or decentralized, as close to the respective assembly stations as possible. Another alternative is for preparation to be conducted externally, outside the plant. Just to mention a few examples.

To ensure a satisfactory survey of the overall effects that the location of kit preparation entails, seven performance indicators are identified in the thesis:

1. Transport needs

2. Stock levels and space requirements

3. Capabilities for visual direct control

4. Flexibility

5. Efficiency at the preparation stage

6. Quality

7. Opportunities for continual improvements

The results from the thesis’ sub-studies show positive effects for several performance indicators when the assembly station and location where kits are prepared are close to one another. A decisive prerequisite however, is that the plant’s layout and surface area permit such a location, something that may be impossible in practice at many plants. One of the risks with a preparation area, which in its configuration or location is not suited

to the purpose, is that the working hours that kitting saves in the assembly phase are consumed by increased time spent during the preparation phase.

3. Continuous supply: Time expenditure in relation to packaging size and typeOne of the biggest – and most obvious – advantages with continuous supply compared to kitting is the fact that no time needs to be devoted to preparing kits. At the same time, the continuous supply principle places high demands on the in-plant material deliveries, not the least with regard to unit loads and the physical volume of packaging because the physical space at the assembly stations is limited. The objective is to supply each assembly station with an optimal flow of each part, with regard to delivery and amount, packaged and presented in a way that facilitates the assembler’s work.

Under the condition that the external suppliers’ material deliveries to the plant match the in-plant material supply as related to packaging size, continuous supply can be an advantageous way of contributing to reducing the total number of steps in the in-plant material supply process. If the incoming packagings’ size, due to for example, agreement stipulations or logistical limitations cannot be adjusted, repackaging can be necessary prior to further delivery to the respective assembly stations. The costs thus rise as a result of increased labor.

Page 7: dition number 4 In-plant material supply – Choice of principle

The studies in the thesis show that a conversion of the in-plant material deliveries, from larger packaging units such as Euro pallets to smaller units and more frequent deliveries to match the needs at the assembly stations, does not necessarily entail an increase in the number of working hours in in-plant material supply. Smaller packaging units can namely be loaded together in an entirely different way than Euro pallets, which are normally delivered within the plant one at a time.

Combination principlesRobin Hanson emphasizes that the choice between kitting and continuous supply is not limited to “either or”. A combined application of the two material supply principles entails

opportunities to, at least to a certain extent, take advantage of the respective strengths of both principles. A solution can be for example, to apply kitting mainly for parts that have many variants, which can provide significant savings of space at the assembly stations and also function as a relatively good form of support for the assemblers. By supplying other parts – where variants are few – with continuous supply, work with preparation of kits can be limited in scope.

Regardless of the decision, just as when choosing a more absolute supply principle, the analysis must be based on the plant’s specific conditions.

Build your own Volvo. In the international vehicle industry, mass production’s advantages of scale are combined with individually customized products. Source: volvocars.se.

Page 8: dition number 4 In-plant material supply – Choice of principle

The 6 steps of the configuration process

In configuring in-plant material supply, there are no given answers. Because the plant’s specific conditions are decisive, the solution that can be the most suitable in one case can be the worst in another. Necessary for making the right decisions, besides in-depth knowledge of the larger production context and of the two material supply principles, is a structured and carefully considered 6-step configuration process.

Preliminary IPMSS configuration

Final IPMSS configuration

Analyse existing IPMSS* and its context

Set objectives

Generate preliminary configuration of the IPMSS:

Propose materials feeding principle

Propose design of unit loads, materials handling, manufacturing planning and control, and storage and inventory

Evaluate preliminary IPMSS configuration

* IPMSS = In-Plant Materials Supply System

Page 9: dition number 4 In-plant material supply – Choice of principle

Analyze the conditions. Decisive for the departure point is the question of the status of in-plant material supply. In an existing plant for example, the choice of material supply principle must be based on the existing conditions. In a new plant, where the frameworks have not yet been set, the analysis can instead have a freer departure point, with focus on the performance indicators that the company chooses to most highly prioritize.

1

Formulate objectives for how the in-plant material supply system is to function and deliver, based on strategic prioritizations among the eight performance indicators.2

Develop a preliminary proposal for the in-plant material supply system, including the choice of in-plant material supply principle, size and type of packaging, strategy for stock management, and so forth.

3

4 Prepare the preliminary proposal and take it to the next phase.

5 Configure, evaluate and adjust the preliminary supply system, using the prioritized performance areas as guidance. As needed, complement with possible combinations of kitting and continuous supply.

6 Decide on the plant’s completed system for in-plant material supply.

Page 10: dition number 4 In-plant material supply – Choice of principle

Future researchThe fact that the principles for kitting and continuous supply can be combined is only addressed to a certain extent in Robin Hanson’s thesis. Because combined solutions are already a reality in many plants, further research into simultaneous application of two – or even more – material supply principles appears as relevant.

While kitting in many respects entails advantages, including reduced needs for space at assembly stations and simplified work processes for assemblers, the time expended in conjunction with kit preparation is a significant negative factor. Against this background, it would be motivated with research into automation of kit preparation, with the potential to subsequently eliminate costs in the form of working hours. The departure point of such a research initiative should be a combined focus partly on the purely technical aspects, partly on the conditions and needs at the assembly stations, and within in-plant material supply on the whole.

References and reading tipsHanson, R. (2012). In-plant materials supply: Supporting the choice between kitting and continuous supply. The Department of Technology Management and Economics, Chalmers University of Technology, Gothenburg, Sweden. Doctoral thesis.

Hanson, R. och Brolin, A. (2012). A comparison of kitting and continuous supply in in-plant materials supply. International Journal of Production Research, DOI: 10.1080/00207543.2012.657806.

Hanson, R. (2012). Valet mellan kitting och kontinuerlig försörjning. Verkstäderna, 108(7): 34-36.

Hanson, R. och Medbo, L. (2012). Kitting and time efficiency in manual assembly. International Journal of Production Research, 50(4): 1115-1125.

Hanson, R., Medbo, L. och Medbo, P. (2012). Assembly station design – a quantitative comparison of the effects of kitting and continuous supply. Journal of Manufacturing Technology Management, 23(3): 315-327.

Hanson, R. (2011). Effects of using minomi in in-plant materials supply. Journal of Manufacturing Technology Management, 22(1): 90-106.

Page 11: dition number 4 In-plant material supply – Choice of principle

Northern LEAD | Chalmers University of Technology | SE-412 96 Gothenburg, Sweden | www.northernlead.se

For further information: Robin Hanson | +46 76 001 58 16 | [email protected]

Northern LEAD OutlookNorthern LEAD Outlook is a series of summaries of scientific theses that have been produced

in Northern LEAD’s network. The series includes the following previous editions:

Edition number 1:

Materials supply and production outsourcing Anna Fredriksson

Logistics and Transportation, Chalmers

Edition number 2:

Urban freight transport sustainability

Sönke BehrendsLogistics and Transportation, Chalmers

Edition number 3:

Integrated logistics platform

Badi AlmotairiLogistics and Transportation, Chalmers

Edition number 4:

Plant material supply – Choice of principle

Robin HansonLogistics and Transportation, Chalmers

Page 12: dition number 4 In-plant material supply – Choice of principle

Northern LEAD is a competence centre for logistics, established by Chalmers University of Technology and Göteborg University, in collaboration with the Logistics and Transport Foundation, LTS. The centre’s core consists of some eighty researchers, research students and teachers who work in five different research groups. As a link between academia, industry and authorities, Northern LEAD strives to support and disseminate leading research on logistics and transport. Further information: www.northernlead.se.

Robin Hanson has recently taken a doctor’s degree in the field of in-plant material supply at the Chalmers University of Technology’s department for Logistics and Transport. He conducted the research on which he has based his doctoral thesis primarily as an industrial postgraduate student at Saab Automobile, where he was employed from 2007 to 2011.

Since January of 2012, he has mainly worked as a management consultant at Capacent, but also holds a part-time position as a researcher at Chalmers.

Plant material supply – Choice of principle The principle for material supply is one of several factors that determine how well an assembly plant functions. In the manufacturing industries, where large production volumes are combined with broad variation in the completed products, one speaks of mass-customization, with the choice of material supply principle being far from self-evident.

In his thesis, Robin Hanson argues for a broadened perspective, with the choice of supply principle being considered based on the effects of the assembly process on the whole.