disallowance under the nec
DESCRIPTION
Presentation ─── September 2013. Disallowance Under the NEC. ICES Seminar. Section One. NEC and Disallowed Costs Overview. Contract Overview. The NEC is now in its 3 rd edition as has been with us for over 20 years - PowerPoint PPT PresentationTRANSCRIPT
![Page 1: Disallowance Under the NEC](https://reader035.vdocuments.us/reader035/viewer/2022062323/568164c0550346895dd6d10b/html5/thumbnails/1.jpg)
Click to edit Master title style
Disallowance Under the NECICES Seminar
———— Pioneering ———— Bahrain ———— Construction ———— Public sector ———— Energy ———— Real estate ———— London ———— Tax ———— IT ———— Dubai ———— Manchester ———— Infrastructure ———— Diverse ———— Regeneration ———— Spirited ————
Connecting ———— Knowledge ———— Pragmatic ———— Malaysia ———— Exeter ———— Thought leadership ———— Housing ———— Agile ———— Creative ———— Connecting ———— Private equity ———— Funding ———— Housing ———— Islamic finance ———— Charities ————
— Local government ———— Manchester ———— Environment ———— Focused ———— Islamic finance ———— Projects ———— Abu Dhabi ———— Corporate finance ———— Passionate ———— Team work ———— Technology ———— Development ———— Oman ———— Innovative
—— Employment ———— Regulation ———— Procurement ———— Expertise ———— Specialist ———— Planning ———— Investment ———— Committed ———— Delivery ———— IT ———— Governance ———— Experience ———— Pensions ———— Focused ———— Care ————
——— IP ———— Corporate ———— Infrastructure ———— Cairo ———— Development ———— Private wealth ———— Oman ———— Governance ———— Birmingham ———— Corporate finance ———— Connecting ———— Pragmatic ———— Charities ———— Dispute resolution ———— Tax ————
—— Dynamic ———— Pensions ———— Dispute resolution ———— Insight ———— Banking and finance ———— Arbitration ———— Diverse ———— Regeneration ———— Care ———— Communication ———— Public sector ———— Specialist ———— Projects ———— Talented ————
Presentation ─── September 2013
![Page 2: Disallowance Under the NEC](https://reader035.vdocuments.us/reader035/viewer/2022062323/568164c0550346895dd6d10b/html5/thumbnails/2.jpg)
Section OneNEC and Disallowed Costs Overview
———— Pioneering ———— Bahrain ———— Construction ———— Public sector ———— Energy ———— Real estate ———— London ———— Tax ———— IT ———— Dubai ———— Manchester ———— Infrastructure ———— Diverse ———— Regeneration ———— Spirited ————
Connecting ———— Knowledge ———— Pragmatic ———— Malaysia ———— Exeter ———— Thought leadership ———— Housing ———— Agile ———— Creative ———— Connecting ———— Private equity ———— Funding ———— Housing ———— Islamic finance ———— Charities ————
— Local government ———— Manchester ———— Environment ———— Focused ———— Islamic finance ———— Projects ———— Abu Dhabi ———— Corporate finance ———— Passionate ———— Team work ———— Technology ———— Development ———— Oman ———— Innovative
—— Employment ———— Regulation ———— Procurement ———— Expertise ———— Specialist ———— Planning ———— Investment ———— Committed ———— Delivery ———— IT ———— Governance ———— Experience ———— Pensions ———— Focused ———— Care ————
——— IP ———— Corporate ———— Infrastructure ———— Cairo ———— Development ———— Private wealth ———— Oman ———— Governance ———— Birmingham ———— Corporate finance ———— Connecting ———— Pragmatic ———— Charities ———— Dispute resolution ———— Tax ————
—— Dynamic ———— Pensions ———— Dispute resolution ———— Insight ———— Banking and finance ———— Arbitration ———— Diverse ———— Regeneration ———— Care ———— Communication ———— Public sector ———— Specialist ———— Projects ———— Talented ————
![Page 3: Disallowance Under the NEC](https://reader035.vdocuments.us/reader035/viewer/2022062323/568164c0550346895dd6d10b/html5/thumbnails/3.jpg)
Contract Overview
● The NEC is now in its 3rd edition as has been with us for over 20 years
● There is considerable debate over how it works and how it will be interpreted by the Courts as there remain very few cases on it
● This is a highly sophisticated form of contract with complex ideas and methodologies
● As with most standard forms you see a wide variety of amendments
![Page 4: Disallowance Under the NEC](https://reader035.vdocuments.us/reader035/viewer/2022062323/568164c0550346895dd6d10b/html5/thumbnails/4.jpg)
Contract Overview
● Just looking at the main form ECC● You can have disallowance in the subcontract and
even the professional services contract but that is less common• Why?
● Disallowance is only relevant to those Main Options based on cost recovery (C, D and E)
![Page 5: Disallowance Under the NEC](https://reader035.vdocuments.us/reader035/viewer/2022062323/568164c0550346895dd6d10b/html5/thumbnails/5.jpg)
Basic Principles of Disallowance
● Disallowance is intended as a means of ensuring that there is no overpayment for sums which are not properly due
● It forms part of the calculation of the Amount Due which therefore becomes part of the payment notice
● As part of the calculation of the Amount Due it is for the Project Manager to ascertain
● It is not part of a payless notice● Disallowance should be specific identifiable sums
for specific identifiable reasons
![Page 6: Disallowance Under the NEC](https://reader035.vdocuments.us/reader035/viewer/2022062323/568164c0550346895dd6d10b/html5/thumbnails/6.jpg)
Disallowance in Context
● The “cash” options contracts are intended to be low risk for the contractor
● They are intended to give keener prices and more transparency on costs
● However, disallowance used incorrectly can cause significant cash flow problems for a contractor
● A low risk contract can very quickly become high risk because there is no margin or supply network for a contractor to hide behind
![Page 7: Disallowance Under the NEC](https://reader035.vdocuments.us/reader035/viewer/2022062323/568164c0550346895dd6d10b/html5/thumbnails/7.jpg)
Section TwoContractual Framework for Disallowance
———— Pioneering ———— Bahrain ———— Construction ———— Public sector ———— Energy ———— Real estate ———— London ———— Tax ———— IT ———— Dubai ———— Manchester ———— Infrastructure ———— Diverse ———— Regeneration ———— Spirited ————
Connecting ———— Knowledge ———— Pragmatic ———— Malaysia ———— Exeter ———— Thought leadership ———— Housing ———— Agile ———— Creative ———— Connecting ———— Private equity ———— Funding ———— Housing ———— Islamic finance ———— Charities ————
— Local government ———— Manchester ———— Environment ———— Focused ———— Islamic finance ———— Projects ———— Abu Dhabi ———— Corporate finance ———— Passionate ———— Team work ———— Technology ———— Development ———— Oman ———— Innovative —— Employment ———— Regulation ———— Procurement ———— Expertise ———— Specialist ———— Planning ———— Investment ———— Committed ———— Delivery ———— IT ———— Governance ———— Experience ———— Pensions ———— Focused ———— Care ————
——— IP ———— Corporate ———— Infrastructure ———— Cairo ———— Development ———— Private wealth ———— Oman ———— Governance ———— Birmingham ———— Corporate finance ———— Connecting ———— Pragmatic ———— Charities ———— Dispute resolution ———— Tax ————
—— Dynamic ———— Pensions ———— Dispute resolution ———— Insight ———— Banking and finance ———— Arbitration ———— Diverse ———— Regeneration ———— Care ———— Communication ———— Public sector ———— Specialist ———— Projects ———— Talented ————
![Page 8: Disallowance Under the NEC](https://reader035.vdocuments.us/reader035/viewer/2022062323/568164c0550346895dd6d10b/html5/thumbnails/8.jpg)
● Definition of Disallowed Costs● Costs which the Project Manager decides
• A changed decision is a Compensation Event (60.1(8))
● There are 8 basic reasons for disallowance, some used much more frequently than others
● Grouped today into five categories• Accounts and records• Sums which shouldn’t have been paid • Correcting defects• Failure to follow procedure or give early warning• Things not used to provide the works
Clause 11.2(25)
![Page 9: Disallowance Under the NEC](https://reader035.vdocuments.us/reader035/viewer/2022062323/568164c0550346895dd6d10b/html5/thumbnails/9.jpg)
● “is not justified by the Contractor’s accounts and records”
● There should be a statement from the Employer somewhere on what accounts and records are expected, probably in Works Information
● Very rarely set out explicitly and in detail● Should be agreed at an operational level as early as
possible to make interim payments functional
Accounts and Records
![Page 10: Disallowance Under the NEC](https://reader035.vdocuments.us/reader035/viewer/2022062323/568164c0550346895dd6d10b/html5/thumbnails/10.jpg)
● “should not have been paid to a Subcontractor or supplier in accordance with his contract”
● This would include any designer and is intended to prevent gratuitous payments
● Care needed when finalising and settling an account to make sure the settlement is in accordance with the contract
● If delay damages could have been levied then a disallowance may arise if they were not taken
● A Project Manager should not need to re-assess the subcontract payments but he could
● This can cause problems where the Project Manager does not have access to the terms of the Subcontract
Sums which should not have been paid
![Page 11: Disallowance Under the NEC](https://reader035.vdocuments.us/reader035/viewer/2022062323/568164c0550346895dd6d10b/html5/thumbnails/11.jpg)
● “correcting Defects after Completion” and “correcting Defects caused by the Contractor not complying with a constraint on how he is to Provide the Works stated in the Works Information”
● Intended to encourage early identification and correction of defects
● It is the “cost of” that is relevant so there has to be a cost actually incurred, an assessment of possible cost is not appropriate to the disallowance although it can be under 45.1 in assessing the defect
● This clause is often amended as Employers do not like the idea of paying for the correction of any defective work which shifts the risk balance
Correcting Defects
![Page 12: Disallowance Under the NEC](https://reader035.vdocuments.us/reader035/viewer/2022062323/568164c0550346895dd6d10b/html5/thumbnails/12.jpg)
● “was incurred because the Contractor did not follow an acceptance or procurement procedure stated in the Works Information or give an early warning which the contract required him to give”
● The first part of this test is wide and would include all interim and final testing and commissioning
● There is cross over with the defect provisions● Works Information would include any from the
Contractor and process it may have given at tender● The second part focuses on early warnings and needs
to be read in conjunction with 16.1 for when early warning should be given and 61.5 which allows compensation events to be valued at a lower level
Early Warning and Procedure Failures
![Page 13: Disallowance Under the NEC](https://reader035.vdocuments.us/reader035/viewer/2022062323/568164c0550346895dd6d10b/html5/thumbnails/13.jpg)
Not Used to Provide the Works
● “Plant and Materials not used to Provide the Works…resources not used to Provide the Works”
● Plant and Materials are permanent not temporary items
● Provide the Works is very broadly defined• To do all the work necessary to complete the works
in accordance with this contract and all incidental work, services and actions which this contract requires
● There is an allowance for wastage and reasonable utilisation, in the Project Manager’s assessment
![Page 14: Disallowance Under the NEC](https://reader035.vdocuments.us/reader035/viewer/2022062323/568164c0550346895dd6d10b/html5/thumbnails/14.jpg)
Section ThreePractical Issues in Disallowed Costs
———— Pioneering ———— Bahrain ———— Construction ———— Public sector ———— Energy ———— Real estate ———— London ———— Tax ———— IT ———— Dubai ———— Manchester ———— Infrastructure ———— Diverse ———— Regeneration ———— Spirited ————
Connecting ———— Knowledge ———— Pragmatic ———— Malaysia ———— Exeter ———— Thought leadership ———— Housing ———— Agile ———— Creative ———— Connecting ———— Private equity ———— Funding ———— Housing ———— Islamic finance ———— Charities ————
— Local government ———— Manchester ———— Environment ———— Focused ———— Islamic finance ———— Projects ———— Abu Dhabi ———— Corporate finance ———— Passionate ———— Team work ———— Technology ———— Development ———— Oman ———— Innovative —— Employment ———— Regulation ———— Procurement ———— Expertise ———— Specialist ———— Planning ———— Investment ———— Committed ———— Delivery ———— IT ———— Governance ———— Experience ———— Pensions ———— Focused ———— Care ————
——— IP ———— Corporate ———— Infrastructure ———— Cairo ———— Development ———— Private wealth ———— Oman ———— Governance ———— Birmingham ———— Corporate finance ———— Connecting ———— Pragmatic ———— Charities ———— Dispute resolution ———— Tax ————
—— Dynamic ———— Pensions ———— Dispute resolution ———— Insight ———— Banking and finance ———— Arbitration ———— Diverse ———— Regeneration ———— Care ———— Communication ———— Public sector ———— Specialist ———— Projects ———— Talented ————
![Page 15: Disallowance Under the NEC](https://reader035.vdocuments.us/reader035/viewer/2022062323/568164c0550346895dd6d10b/html5/thumbnails/15.jpg)
Disallowed Cost [DC]Practical Management
• DC Review at Tender• Managing DC at Contract Commencement• Managing DC during the Contract• Common Issues• Cost risk under the Contract
![Page 16: Disallowance Under the NEC](https://reader035.vdocuments.us/reader035/viewer/2022062323/568164c0550346895dd6d10b/html5/thumbnails/16.jpg)
DC Review at Tender
• Contractor Paid PWDD• PWDD = Defined Cost + Fee• Defined Cost = Actual Cost - DC• DC allowance in the Fee• DC allowance % in Fee?
![Page 17: Disallowance Under the NEC](https://reader035.vdocuments.us/reader035/viewer/2022062323/568164c0550346895dd6d10b/html5/thumbnails/17.jpg)
Managing DCAt Contract Commencement
Agreed Protocol• DC Register – Unique Reference• PM Notice• PM Particulars• PM / C Review Meeting• Actions• Agree / Disagree• Allowable Cost / DC
![Page 18: Disallowance Under the NEC](https://reader035.vdocuments.us/reader035/viewer/2022062323/568164c0550346895dd6d10b/html5/thumbnails/18.jpg)
Managing DCDuring the Contract
Risk Register • Driven by Early Warnings• Add 3 columns with a tick mark (pencil)
• CE• DC• P/G
![Page 19: Disallowance Under the NEC](https://reader035.vdocuments.us/reader035/viewer/2022062323/568164c0550346895dd6d10b/html5/thumbnails/19.jpg)
Managing DCDuring the Contact
Accounts & Records• Orders & Invoices Matching• Labour & Plant Allocation Sheets• Material Delivery Notes• Plant on / off Hire Notes• Major Material Reconciliations• Staff Timesheets & Expenses
![Page 20: Disallowance Under the NEC](https://reader035.vdocuments.us/reader035/viewer/2022062323/568164c0550346895dd6d10b/html5/thumbnails/20.jpg)
Managing DCDuring the Contract
Subcontractors• 3 Quotes?• Subcontract Order• CEs – The Works & Domestic Issues• DCs – Back to Back Provisions• Agreement if different Option
![Page 21: Disallowance Under the NEC](https://reader035.vdocuments.us/reader035/viewer/2022062323/568164c0550346895dd6d10b/html5/thumbnails/21.jpg)
Managing DCDuring the Contract
Defects• Raising and closing out NCRs (Before
Completion)• Where Defects are DC – Timely and
Proper Agreed Resource based records to be signed off by PM.
![Page 22: Disallowance Under the NEC](https://reader035.vdocuments.us/reader035/viewer/2022062323/568164c0550346895dd6d10b/html5/thumbnails/22.jpg)
Common IssuesTimely DCs
When should DC be crystallised?• When the cost is incurred?• Anytime before the final assessment of
the Contractor’s Share?• Assessed monthly by PM?• Assessed Quarterly by external audit
team?
![Page 23: Disallowance Under the NEC](https://reader035.vdocuments.us/reader035/viewer/2022062323/568164c0550346895dd6d10b/html5/thumbnails/23.jpg)
Common IssuesTimely DCs
If the DC is levied several months after incurred – what are the implications?• Subcontractor account settled• Cost could have been reduced• Has the Contractor’s position be
prejudiced by the late DC?
![Page 24: Disallowance Under the NEC](https://reader035.vdocuments.us/reader035/viewer/2022062323/568164c0550346895dd6d10b/html5/thumbnails/24.jpg)
Common IssuesTimely DCs
If DC is levied several months after incurred – what does the contract say?• Can it be an allowable cost one month
and then DC a later month?• Clause 50.5 allows the PM to correct
any wrongly assessed amount due in a later payment certificate.
![Page 25: Disallowance Under the NEC](https://reader035.vdocuments.us/reader035/viewer/2022062323/568164c0550346895dd6d10b/html5/thumbnails/25.jpg)
Common IssuesTimely DCs
What is the Contractor’s Remedy?• The Party alleging the certificate is
wrong bears the burden of proof.• Clause 51.3 allows interest to be paid
on the correcting amount.• Persuade or adjudicate• Tribunal
![Page 26: Disallowance Under the NEC](https://reader035.vdocuments.us/reader035/viewer/2022062323/568164c0550346895dd6d10b/html5/thumbnails/26.jpg)
Common IssuesDC and Pain Gain Relationship
• Standard contract states P/G impacted on certificate at completion.
• That could expose Employer to recover a debt.
• Amended contracts impact P/G when PWDD exceeds the Prices
![Page 27: Disallowance Under the NEC](https://reader035.vdocuments.us/reader035/viewer/2022062323/568164c0550346895dd6d10b/html5/thumbnails/27.jpg)
Common IssuesDC and Pain Gain Relationship
• Experience / history has shown that interim assessments of DC higher when P/G assessed at completion to offset debt risk.
• Impact on certificate is significantly different – with 50:50 P/G its 50p in the £1 but with DC £1 for £1.
![Page 28: Disallowance Under the NEC](https://reader035.vdocuments.us/reader035/viewer/2022062323/568164c0550346895dd6d10b/html5/thumbnails/28.jpg)
Common IssuesSpecific v General
• PM must identify specific items of cost and identify how they fall within the definition of Disallowed Cost.
• PM cannot take a view as to the overall level of Defined Cost or take a view as to the economy or efficiency that should have been achieved.
![Page 29: Disallowance Under the NEC](https://reader035.vdocuments.us/reader035/viewer/2022062323/568164c0550346895dd6d10b/html5/thumbnails/29.jpg)
Common IssuesDC or Pain/Gain Risk Share
• Matters of efficiency and economy are the subject of the pain/gain risk share.
• Procurement losses are the subject of the pain/gain risk share.
• Misunderstanding between lump sum fixed price contracts and pain/gain risk sharing contracts.
![Page 30: Disallowance Under the NEC](https://reader035.vdocuments.us/reader035/viewer/2022062323/568164c0550346895dd6d10b/html5/thumbnails/30.jpg)
Cost risk under the Contract
Contractor is paid Defined Cost regardless of the level of Defined Cost.Exception is Disallowed Cost
• These are specific items of cost defined in the Contract• They are not related to the level of Defined Cost• The PM decides disallowed cost in interim payments
Pain/Gain (Contractor’s Share) is a separate and distinct mechanism which is related to the level of PWDD (Defined Cost + Fee) compared to the Target (Prices).
• The risk is shared• It is a calculation after Completion (Standard)
![Page 31: Disallowance Under the NEC](https://reader035.vdocuments.us/reader035/viewer/2022062323/568164c0550346895dd6d10b/html5/thumbnails/31.jpg)
Section FourQuestions
———— Pioneering ———— Bahrain ———— Construction ———— Public sector ———— Energy ———— Real estate ———— London ———— Tax ———— IT ———— Dubai ———— Manchester ———— Infrastructure ———— Diverse ———— Regeneration ———— Spirited ————
Connecting ———— Knowledge ———— Pragmatic ———— Malaysia ———— Exeter ———— Thought leadership ———— Housing ———— Agile ———— Creative ———— Connecting ———— Private equity ———— Funding ———— Housing ———— Islamic finance ———— Charities ————
— Local government ———— Manchester ———— Environment ———— Focused ———— Islamic finance ———— Projects ———— Abu Dhabi ———— Corporate finance ———— Passionate ———— Team work ———— Technology ———— Development ———— Oman ———— Innovative —— Employment ———— Regulation ———— Procurement ———— Expertise ———— Specialist ———— Planning ———— Investment ———— Committed ———— Delivery ———— IT ———— Governance ———— Experience ———— Pensions ———— Focused ———— Care ————
——— IP ———— Corporate ———— Infrastructure ———— Cairo ———— Development ———— Private wealth ———— Oman ———— Governance ———— Birmingham ———— Corporate finance ———— Connecting ———— Pragmatic ———— Charities ———— Dispute resolution ———— Tax ————
—— Dynamic ———— Pensions ———— Dispute resolution ———— Insight ———— Banking and finance ———— Arbitration ———— Diverse ———— Regeneration ———— Care ———— Communication ———— Public sector ———— Specialist ———— Projects ———— Talented ————
![Page 32: Disallowance Under the NEC](https://reader035.vdocuments.us/reader035/viewer/2022062323/568164c0550346895dd6d10b/html5/thumbnails/32.jpg)
Contact
Trowers & Hamlins LLP has taken all reasonable precautions to ensure that information contained in this document is accurate, but stresses that the content is not intended to be legally comprehensive. Trowers & Hamlins LLP recommends that no action be taken on matters covered in this document without taking full legal advice.
© Copyright Trowers & Hamlins LLP – October 2012 – All Rights Reserved. This document remains the property of Trowers & Hamlins LLP. No part of this document may be reproduced in any format without the express written consent of Trowers & Hamlins LLP.
Rob HornePartnerd +44 (0) 207 423 8616e [email protected]
David GibsonCEOd +44 (0) 207 182 4062e [email protected]