1. Member (PS) Central Electricity Authority Sewa Bhawan, R.K.Puram New Delhi-110 066
2. The Member Secretary Western Regional Power Committee MIDC area, Marol, Andheri East, Mumbai 400 093
3. 3.
Chief Engineer (PSP&A - I) Central Electricity Authority Sewa Bhawan, R.K.Puram New Delhi-110 066
4. 4.
Director (Operation) Maharashtra State Electricity Transmission Co. Ltd., 4th Floor, “Prakashganga”, Plot No. C-19, E-Block, Bandra – Kurla Complex, Bandra(East), Mumbai- 400051
5. 5.
Managing Director Gujarat Energy Transmission Corp. Ltd, Sardar Patel Vidyut Bhawan, Race Course, Vadodara -390 007
6. 6.
Chairman & Managing Director Madhya Pradesh Power Transmission Co. Ltd., Block No. 3, Shakti Bhawan, Rampur, Jabalpur-482 008
7. 7.
Managing Director Chhattisgarh State Power Transmission Co. Ltd., Dangania, Raipur- 492 013
8. 8.
The Chief Engineer Electricity Department The Government of Goa, Panaji
9. 9.
Executive Engineer Administration of Daman & Diu (U.T.) Department of Electricity Moti Daman - 396220
10. 10.
Executive Engineer Electricity Department UT of Dadra & Nagar Havelli, Post Naroli-396 235, Silvassa
11. 11.
Chief Executive Officer POSOCO B-9, Qutab Institutional Area, Katwaria Sarai, New Delhi-110 016
12. 12.
General Manager Western Regional Load Despatch Centre F-3, M.I.D.C. Area, Marol, Andheri East, Mumbai-400 093
13. Executive Director (Engg.) NTPC Ltd., Engg. Office Complex, Plot no. A-8A, Sector-24, Post Box. 13, Noida 201 301 (U.P)
14. 14.
Chief Engineer (Transmission) Nuclear Power Corporation of India Ltd., 12th Floor, North wing, Vikram Sarabhai Bhawan, Anushakti Nagar, Mumbai-400 094
15. Sh. Ashish Shukla Senior Manager Gamesa Renewable Pvt. Ltd. (Mathak, Gagodar, Latur, Ghat Pimpri, Tuljapur/Deosingh & Kod Wind Power Projects) Future IT Prk, B-Block, 8th Flr, No. 334, Rajiv Gandhi Salai, Shollinganallur, Chennai-119, Tamil Nadu [email protected] Mob. 07869913518
16. Sh. Lalit Birla AGM Orange Rajkot Wind Power Pvt. Ltd. & Orange Ashok North Wind Power Pvt. Ltd (Gagodar, Hajapar & Lohara Wind Projects) 301B, 3rd Floor, D21 Corporate Park, Sector-21 Dwarka, New Delhi – 110075 [email protected] Mob. 09650015982
17. Sh. Alok Gupta General Manager-P.E. Inox Wind Infrastructure Services Ltd. (Bhachau, Dayapar & Bhuj Wind Farms) Inox Towers, Plot No. 17, Sector 16A, Film City, Noida – 201301, Uttar Pradesh [email protected] Mob. 09717364276
18. Shri M.R. Krishna Rao Vice President Adani Green Energy Ltd. (Khavda Wind Farm) Achalraj, Opposite Mayor Bungalow, Law Garden, Ahmedabad – 380006, Gujarat [email protected] Mob. 09099005556
19. Sh . Naresh Panchal Senior GM & Head PE Suzlon Power Infrastructure Ltd. (Baranda & Fulra Wind Farms) Level 1, Left Wing, Tree Suzlon, One Earth, Opposite Magarpatta, Pune-411028, Maharashtra [email protected] Mob. 09850829701
20. Sh. Rakesh Rathore Asst. Vice President, Srijan Energy System Pvt. Ltd. 102, EL TARA Building, Orchard Avenue, Hiranandani, Powai, Mumbai, 400076 [email protected] Mob. 07738091123
21. Sh. Rakesh Garg AVP-Project Development Renew Power Ventures Pvt. Ltd. (Bhuvad Wind Farm) 10th Floor, DLF Square, Jacaranada Marg, Sector 25, DLF Phase-2, Gurgaon, Haryana [email protected] Mob. 09711486060
22. Sh. Pratik Poddar Head, Project Development Ostro Kutch Wind Pvt. Ltd. Unit No. G-0, Ground Floor, Mira Corporate Suites, 1&2, Ishwar Industrial Estate, Mathura Road, New Delhi-110065 [email protected] Mob. 09810200736
23. Sh. Dheeraj Jain AGM –Regulatory Affairs Regen Wind Farm (Vagarai) Pvt. Ltd. C/4, No. 22, Vaidya Rama Iyer Street, T Nagar, Chennai –600 017 [email protected] Mob. 09910778484
24. Sh. Rakesh Garg AVP-Project Development Renew Power Ventures Pvt. Ltd. (Pugalur Wind Park) 10th Floor, DLF Square, Jacaranada Marg, Sector 25, DLF Phase-2, Gurgaon, Haryana [email protected] Mob. 09711486060
25. Sh. V.K. Soni Head (Projects & New Initiatives) Gujarat Fluorochemicals Ltd. Inox Towers, Plot No. 17, Sector 16-A, Noida-201301, UP [email protected] Mob. 09891795111
26.
Agenda of 24th Meeting of WR constituents for Connectivity & LTA applications
Page 1 of 16
Agenda for 24th Meeting of WR Constituents regarding Connectivity
& Long-term Access applications in Western Region
----------------------------------------------------------------------------------------------------------------
1. Confirmation of the minutes of 23rd Meeting of WR Constituents regarding
Connectivity & Long-term Access applications in Western Region held on 01-
06-2016 at NRPC, New Delhi
No comments on the MoM have been received till date. Members may confirm the
minutes of the 23rd Meeting of WR Constituents regarding Connectivity & Long-term
Access applications in Western Region held on 01.06.2016.
2. Connectivity Applications from RE Generation Developers in Western Region.
Total sixteen nos. of connectivity applications of about 5000MW quantum of power
have been received by CTU till August, 2016 for ISTS connectivity at Bhachau, Bhuj
Pool , Parli, Solapur and Rajgarh Substations of POWERGRID from RE generation
projects. Here it is to inform that CERC in its order dated 05.01.2016 in Petition No:
420/MP/2014 has directed that wind developers should comply to the provision of
LVRT (Low Voltage Ride Through). Further, the wind developers shall provide
adequate reactive compensation so that under all dispatch scenarios Power Factor
of 0.98 shall be maintained.
Further, it may be mentioned that as per the Connectivity Regulations, the Grant of
Connectivity shall not entitle an applicant to inter-change any power with the grid
unless it obtains LTA, MTOA or STOA. Further, since MTOA & STOA are granted on
the margins available in the grid and firm transfer of power is granted only with the
LTA, therefore, the applicants are advised to apply for the LTA to ensure power
evacuation & transfer to its beneficiaries under LTA.
Details of the connectivity applications in WR received till August, 2016 are given
below.
Table: 1
Sl Name of Applicant (Organization)
Date of receipt of Application
Date from which connectivity required
Distance from Nearest PS (km)
Name of the Power Plant
S/s for which Connectivity Requested
Installed capacity of Plant (in MW)
Application No
Aplication Status
Generation Projects in vicinity of Bhachau, Gujarat
1
Gamesa Renewable Pvt.
Ltd. (GRPL-Mathak)
22-Jul-
2016
31-Mar-2017 30.00 Mathak
Wind Power Project
Bhachau S/s 100 1200000444 Under
Process
2 Orange Rajkot
Wind Power Pvt. Ltd. (ORWPPL-
25-Jul- 30-Jun-2018 55.00 Gagodar Bhachau S/s 100 1200000447 Under
Process
Agenda of 24th Meeting of WR constituents for Connectivity & LTA applications
Page 2 of 16
Gagodhar) 2016
3
Inox Wind Infrastructure Services Ltd.
(IWISL-Bhachau)
1-Aug-
2016
1-Jul-2017 45.00 Bhachau wind farm
Bhachau S/s 500 1200000457 Under
Process
4
Gamesha Renewables Pvt
Ltd. (GRPL-Gagodhar)
3-Aug-
2016
31-Mar-2018 60.00 Gagodhar Bhachau S/s 300 1200000459 Under
Process
Subtotal 1000
Generation Projects in vicinity of Bhuj PS, Gujarat
5
Inox Wind Infrastructure Services Ltd.
(IWISL-Dayapar)
1-Jun-
2016
30-Jul-2017 70.00 Dayapar wind farm
Bhuj PS 500 1200000390 Under
Process
6 Adani Green Energy Ltd.
(AGEL-Khavda)
2-Jun-
2016
31-Mar-2019 72.00 Khavda
Wind Farm Bhuj PS 500 1200000378
Under Process
7
Suzlon Power Infrastructure Ltd. (SPIL-Baranda)
6-Jul-
2016
31-Jan-2019 65.00 Baranda
Wind Farm Bhuj PS 250 1200000395
Under Process
8 Suzlon Power Infrastructure
Ltd. (SPIL-Fulra)
8-Jul-
2016
31-Jan-2019 25.00 Fulra Bhuj PS 250 1200000394 Under
Process
9
Orange Rajkot Wind Power Pvt. Ltd. (ORWPPL-
Hajapar)
25-Jul-
2016
31-Oct-2018 40.00 Hajapar Bhuj PS / Bhachau
100 1200000432 Under
Process
10
Inox Wind Infrastructure Services Ltd.
(IWISL-Kotda)
1-Aug-
2016
31-Dec-2018 42.00 Bhuj wind
farm (Kotda) Bhuj PS 500 1200000458
Under Process
Subtotal 2100
Generation Projects in vicinity of Parli, Maharashtra
11
Gamesa Renewable Pvt.
Ltd. (GRPL-Latur)
22-Jul-
2016
30-Sep-2018 40.00 Latur wind
power project
Parli (PG) S/s
400 1200000441 Under
Process
12
Gamesha Renewables Pvt Ltd. (GRPL-Ghat
Pimpri)
3-Aug-
2016
30-Sep-2018 45.00 Ghat Pimpri Parli (PG)
S/s 500 1200000460
Under Process
13
Gamesha Renewables Pvt Ltd. (GRPL-Ghat
Pimpri)
4-Aug-
2016
30-Sep-2018 45.00 Ghat Pimpri Parli (PG)
S/s 100 1200000465
Under Process
Subtotal 1000
Agenda of 24th Meeting of WR constituents for Connectivity & LTA applications
Page 3 of 16
Generation Projects in vicinity of Solapur, Maharashtra
14
Gamesa Renewable Pvt.
Ltd. (GRPL-Tuljapur)
22-Jul-
2016
30-Sep-2018 60.00
Tuljapur & Deosingh
Wind Power Project
Solapur 765/400kV
400 1200000440 Under
Process
15
Orange Ashok North Wind
Power Pvt. Ltd. (OANWPPL-
Lohara)
25-Jul-
2016
31-Mar-2020 43.00 Lohara Wind
Farm Solapur
765/400kV 200 1200000433
Under Process
Subtotal 600
Generation Project in vicinity of Rajgarh, Madhya Pradesh
16
Gamesa Renewable Pvt.
Ltd. (GRPL-Khod)
22-Jul-
2016
31-Mar-2017 40.00 Khod wind
power project
Rajgarh S/s 218 1200000445 Under
Process
Subtotal 218
Total 4918
2.1 Connectivity Applications received in the vicinity of Bhachau :
Three nos of applicants have already been granted connectivity at Bhachau
substation. Details of these connectivity applications are as given below:
Table: 2
Sl
Name of Applicant Name of the Power Plant
S/s at which Connectivity Requested
Distance from Connected S/s (km)
Installed capacity of Plant (in MW)
Application No Connectivity Status
1 Ostro Kutch Wind Pvt. Ltd. (OKWPL-Kutch)
Kutch, Gujarat Bhachau 5 300 1200000409 Granted
2 Renew Power Ventures Pvt. Ltd. (RPVPL-Bhuvad)
Bhuvad Wind Power
Bhachau 45 400 1200000326 Granted
3 Gujarat Floro Ltd (GFL-Maliya)
Maliya, Rajkot, Gujarat
Bhachau 45 300 - Granted
Total 1000
Agenda of 24th Meeting of WR constituents for Connectivity & LTA applications
Page 4 of 16
Figure 1: Connectivity to RE generations in the vicinity of Bhachau and Bhuj
As per details given in table 1, four nos. of new connectivity applications have been
received at Bhachau S/s. Due to the severe ROW issues in the vicinity of Bhachau
and space constraints in Bhachau S/s, it is not possible to provide the connectivity to
new applicants at existing Bhachau S/s.
Considering the above and high RE potential in vicinity of Bhachau, it is proposed to
develop a new 400/220kV pooling station in vicinity of Lakadia in Bhachau Taluka,
Kutch district, Gujarat (Lakadia PS). The substation shall act as a pooling station for
the 4 nos. of new RE generations as well as for future RE generations that come up
in the area.
Here, it is to mention that Gujarat Flurochemicals Ltd. (GFL) was granted
connectivity to Bhachau s/s way back in 2011 through 220kV line (twin conductor) for
their 300MW wind farm at Maliya, Rajkot, Gujarat. It is understood that the line,
which was agreed to be constructed by GFL has not yet been taken up by them.
Accordingly, looking into severe ROW issues in the vicinity of Bhachau and space
contraints at Bhachau S/s, it is proposed to revise the connectivity of GFL to Lakadia
PS.
Accordingly, following is proposed for connectivity:
Common Transmission System for Connectivity of renewable generations in
Bhachau area (viz GRPL-Mathak, ORWPPL-Gagodhar, IWISL-Bhachau, GRPL-
Gagodhar):
Agenda of 24th Meeting of WR constituents for Connectivity & LTA applications
Page 5 of 16
LILO of both circuits of EPGL – Bhachau 400kV D/c (Triple) line at Lakadia
PS
Establishment of 1x500MVA, 400/220kV Lakadia PS.
1x125MVAR, 420kV Bus Reactor at Lakadia PS.
Dedicated connectivity system for RE applicants proposed to be pooled at
Lakadia PS:
Table: 3
Sr.
No.
Name of Applicant Connectivity
Quantum
(MW)
Proposed Connectivity System* Implemeting
Agency
1.
Gamesha
Renewables Pvt
Ltd. (Gagodhar)
(GRPL-Gagodhar)
300 GRPL (Gagodhar) – Lakadia PS 220kV S/c line (High Capacity) alongwith associated line bays at both ends
GRPL / TBCB as per deliberations in the meeting
2. Gamesha
Renewable Pvt.
Ltd. (Mathak)
(GRPL-Mathak)
100 GRPL (Mathak) – Lakadia PS 220kV S/c line alongwith associated line bays at both ends
GRPL
3. Orange Rajkot
Wind Power Pvt.
Ltd. (ORWPL-
Gagodhar)
100 ORWPL(Gagodhar) – Lakadia PS
220kV S/c line alongwith associated
line bays at both ends
ORWPL
4. Inox Wind
Infrastructure
Services Ltd.
(IWISL-Bhachau)
500 IWISL (Bhachau) – Lakadia PS
220kV D/c line (High Capacity)
alongwith associated line bays at
both ends
IWISL / TBCB as per deliberations in the meeting
5. Gujarat Floro Ltd
(GFL-Maliya)
300 GFL(Maliya) – Lakadia PS 220kV S/c line (High Capacity) alongwith associatged line bays at both ends.
GFL / TBCB as
per
deliberations in
the meeting
Total 1300
*As per the Manual on Transmission Planning Criteria, the ‘N-1’ criteria may not be applied to the
immediate connectivity of wind / solar farms with the ISTS / Intra-STS grid i.e. the line connecting the
farm to the grid and the step-up transformers at the grid station. In case, wind farm developer
envisages expansion in generation capacity, the same may be informed so that connectivity system
may be appropriately modified.
Since connectivity required by the 4 nos. of applicants mentioned above is from
Mar’17 to June’18, efforts may be made to implement Dedicated connectivity
system as well as Common Transmission System for Connectivity of
renewable generations in Bhachau area at an early date.
Agenda of 24th Meeting of WR constituents for Connectivity & LTA applications
Page 6 of 16
2.2 Connectivity Applications received in the vicinity of Bhuj :
Six nos. of new connectivity applications have been received at Bhuj PS as per the
details given in table 1. In view of project capacity and proximity of generation to
Bhuj PS, following transmission system is proposed for connectivity:
Table: 4
Sr.
No.
Name of
Applicant
Connectivity
Quantum (MW)
Proposed Connectivity System Implemeting
Agency
1 Orange Rajkot
Wind Power Pvt.
Ltd. (ORWPL-
Hajapar)
100
ORWPL(Hajapar) – Bhuj PS 220kV
S/c line along with associated line
bays at both ends ORWPL
2. Suzlon Power
Infrastructure Ltd
(SPIL-Fulra) 250
SPIL (Fulra) – Bhuj PS 220kV S/c
line (high capacity) along with
associated line bays at both ends
SPIL/ TBCB as per deliberations in the meeting
3 Suzlon Power
Infrastructure Ltd
(SPIL-Baranda) 250
SPIL (Baranda) – Bhuj PS 220kV
S/c line (high capacity) along with
associated line bays at both ends
SPIL/ TBCB as per deliberations in the meeting
4. Adani Green
Energy Ltd.
(AGEL-Khavda) 500
AGEL (Khavda) – Bhuj PS 220kV
D/c line (high capacity) along with
associated line bays at both ends
AGEL / TBCB as per deliberations in the meeting
5 Inox Wind
Infrastructure
Services Ltd.
(IWISL-Kotda)
500
IWISL(Kotda) – Bhuj PS 220kV D/c
line (high capacity) along with
associated line bays at both ends
IWISL/ TBCB as per deliberations in the meeting
6 Inox Wind
Infrastructure
Services Ltd.
(IWISL-Dayapar)
500
IWISL(Dayapar) – Bhuj PS 220kV
D/c line (high capacity) along with
associated line bays at both ends
IWISL / TBCB as per deliberations in the meeting
Total 2100
Note:
1. As per the Manual on Transmission Planning Criteria, the ‘N-1’ criteria may not be applied to
the immediate connectivity of wind / solar farms with the ISTS / Intra-STS grid i.e. the line
connecting the farm to the grid and the step-up transformers at the grid station. In case, wind
farm developer envisages expansion in generation capacity, the same may be informed so
that connectivity system my be appropriately modified.
2. Connectivity of all six applicants with the grid shall be established with the commissioning of
above mentioned dedicated line and Bhuj PS (765/400/220kV) – Banaskantha PS (765kV) –
Sankhari (400kV) Corridor or Bhuj PS (765/400/220kV) – Banaskantha PS (765kV) –
Chittorgarh PS (765kV) – Chittorgarh (RVPN) (400kV) corridor.
Agenda of 24th Meeting of WR constituents for Connectivity & LTA applications
Page 7 of 16
2.3 Connectivity Applications received in the vicinity of Parli & Solapur :
Three nos. of new connectivity applications desired to be connected at Parli (PG) &
two nos of connectivity applications desired to be connected at Solapur (PG) have
been received. The details of the connectivity applications are mentioned in table 1.
From the GPS co-ordiantes of these RE generations, it is observed that they are
mainly located in the vicinicty of Latur area. Hence, considering the large quantum of
RE generation, it is proposed to develop a new 400/220kV substation near Latur.
The substation shall act as a pooling station for the 5 nos. of RE generations as well
as for future RE generations that come up in this area.
Accordingly, following transmission system is proposed for connectivity:
Common Transmission System for Connectivity of renewable generations
around Latur area (viz GRPL-Ghat Pimpri (100MW), GRPL-Ghat Pimpri
(500MW), GRPL-Latur, GRPL-Tuljapur-Desingh, OANWPPL-Lohara):
Establishment of 1x500MVA, 400/220kV Latur PS.
Latur PS – Solapur (PG) 400kV D/c (Quad) line
1x125MVAR, 420kV Bus Reactor at Latur PS.
Dedicated connectivity system for RE applicants proposed to be pooled at
Latur PS:
Table: 5
Sr.
No.
Name of
Applicant
Connectivity
Quantum
(MW)
Proposed Connectivity System* Implemeting
Agency
Connectivity Applications received in the vicinity of Parli:
1
Gamesha
Renewables Pvt.
Ltd. (GRPL-Ghat
Pimpri)
100
GRPL(Ghat Pimpri) – Latur PS
220kV S/c line along with
associated line bays at both ends
GRPL
2
Gamesha
Renewables Pvt.
Ltd. (GRPL-Ghat
Pimpri)
500
GRPL(Ghat Pimpri) – Latur PS
220kV D/c line (high capacity)
along with associated line bays at
both ends
GRPL / TBCB as per
deliberations in the meeting
3
Gamesha
Renewables Pvt.
Ltd. (GRPL-Latur) 400
GRPL (Latur) – Latur PS 220kV
D/c line along with associated line
bays at both ends
GRPL / TBCB as per
deliberations in the meeting
Sub-total 1000
Agenda of 24th Meeting of WR constituents for Connectivity & LTA applications
Page 8 of 16
Connectivity Applications received in the vicinity of Solapur:
4
Gamesha Renewable Pvt. Ltd. (GRPL-Tuljapur-Desingh)
400
GRPL (Tuljapur-Deosingh) – Latur PS 220kV D/c line along with associated line bays at both ends
GRPL / TBCB as per
deliberations in the meeting
5
Orange Ashok North Wind Power Pvt. Ltd. (OANWPPL-Lohara)
200
OANWPPL (Lohara) – Latur PS 220kV D/c line along with associated line bays at both ends
OANWPPL / TBCB as per deliberations
in the meeting
Sub-total 600
Total 1600
*As per the Manual on Transmission Planning Criteria, the ‘N-1’ criteria may not be applied to the
immediate connectivity of wind / solar farms with the ISTS / Intra-STS grid i.e. the line connecting the
farm to the grid and the step-up transformers at the grid station. In case, wind farm developer
envisages expansion in generation capacity, the same may be informed so that connectivity system
my be appropriately modified.
Since connectivity required by the applicants mentioned above is from Sep’18 to
Oct’18, efforts may be made to implement Dedicated Connectivity System as well
as Common Transmission System for Connectivity of renewable generations
around Latur area at an early date.
Figure 2: Connectivity to RE generations in the vicinity of Parli and Solapur
Agenda of 24th Meeting of WR constituents for Connectivity & LTA applications
Page 9 of 16
2.4 Connectivity Applications received in the vicinity of Rajgarh :
The following new connectivity application has been received at Rajgarh S/s as per
details given in table 1. In view of project capacity & proximity of generation,
following transmission system is proposed for connectivity:
Table: 6
Sr.
No
.
Name of Applicant Connectivity
Quantum (MW)
Proposed Connectivity
System*
Implemeting
Agency
1 Gamesha
Renewables Pvt.
Ltd. (GRPL-Khod)
218
GRPL (Khod) – Rajgarh(PG)
220kV S/c line along with
associated line bays at both
ends
GRPL
*As per the Manual on Transmission Planning Criteria, the ‘N-1’ criteria may not be applied to the
immediate connectivity of wind / solar farms with the ISTS / Intra-STS grid i.e. the line connecting the
farm to the grid and the step-up transformers at the grid station. In case, wind farm developer
envisages expansion in generation capacity, the same may be informed so that connectivity system
my be appropriately modified.
The connectivity of GRPL(Khod) with the grid shall be established after the
commissioning of above connectivity system or 31-03-2017 whichever is later.
Figure 3: Connectivity to RE generations in the vicinity of Rajgarh
Agenda of 24th Meeting of WR constituents for Connectivity & LTA applications
Page 10 of 16
3 Revision in Grant of Connectivity & LTA to M/s Srijan Energy System Pvt Ltd.
(SESPL)
In the 23rd meeting of WR Constituents regarding Connectivity / Open Access
Applications held at NRPC, New Delhi on 01.06.2016, Connectivity (300MW) and
LTA (300MW) application of Srijan Energy System Pvt. Ltd. (SESPL) was discussed
and following system was agreed for connectivity & LTA (NR &SR):
Transmission System for Connectivity
SESPL switchyard – Bhuj PS 220kV D/c line along with line bays at both ends
(to be constructed by SESPL)
Installation of 2x500MVA, 400/220kV ICT at Bhuj PS (to be implemented by
POWERGRID under Green Energy Corridor)
Transmission System for LTA – WR (90 MW)
Existing & under construction transmission system shall be sufficient to enable
dispersal of power within WR
Transmission System for LTA – NR (150 MW)
Bhuj PS - Banaskantha PS 765kV D/c line
Banaskantha PS- Chittorgarh PS 765kV D/c line
Chittorgarh PS- Chittorgarh (RVPN) 400kV D/c (quad) line
Transmission System for LTA – SR (60 MW)
Wardha – Nizamabad 765kV D/c line along with Nizamabad – Dichpally
400kV D/c line (HTLS)
Nizamabad – Hyderabad (Maheshwaram) 765kV D/c line along with
associated 400kV transmission system
Subsequently, some more proposals have been received for interconnection of RE
generations at Bhuj PS. Accordinlgy, the scheme was reviewed comprehensively
and it is proposed to provide connectivity to SESPL at 220kV level at Bhuj PS.
Therefore, grant of Connectivity/LTA to SESPL is proposed with following
transmission system :
Transmission System for Connectivity:
SESPL switchyard – Bhuj PS 220kV D/c line along with line bays at both ends
(to be constructed by SESPL)@
@
Connectivity with the grid shall be established with the commissioning of above mentioned
dedicated line and Bhuj PS (765/400/220kV) – Banaskantha PS (765kV) – Sankhari (400kV)
Corridor or Bhuj PS (765/400/220kV) – Banaskantha PS (765kV) – Chittorgarh PS (765kV) –
Chittorgarh (RVPN) (400kV) corridor
Agenda of 24th Meeting of WR constituents for Connectivity & LTA applications
Page 11 of 16
Common Transmission System for LTA to WR, NR & SR
Installation of 2x500MVA, 400/220kV ICT at Bhuj PS
Transmission System for LTA to WR (90 MW)
Existing & under construction transmission system shall be sufficient to
enable dispersal of power within WR
Transmission System for LTA to NR (150 MW)
Bhuj PS- Banaskantha PS 765kV D/c line
Banaskantha PS- Chittorgarh PS 765kV D/c line
Chittorgarh PS- Chittorgarh (RVPN) 400kV D/c (quad) line
Transmission System for LTA to SR (60 MW)
Wardha – Nizamabad 765kV D/c line along with Nizamabad – Dichpally
400kV D/c line (HTLS)
Nizamabad – Hyderabad (Maheshwaram) 765kV D/c line along with associated
400kV transmission system
4 LTA Applications from RE developers in Western Region & Southern Region
Details of the three nos of applicants from generation projects in WR and from five
nos of applicants from generation projects in SR (seeking transfer of power from
Southern Region to Northern Region) who have applied for LTA are tabulated below:
Table: 7
Sl
Name of the Applicant
Location of Generating
Station
Installed Capacity
(MW) Connectiv
ity provided/proposed
at
Seeking LTA for (MW)
Type of
Fuel
Date of Receipt of App.
Date from which LTA required
Date upto which LTA required
Quantum allocated in the region
SR WR NR ER NER
LTA Applications in Western Region
1 Adani Green Energy Ltd (AGEL-Khavda)
WR (Khavda,
Kutch, Gujarat)
500 Bhuj PS 500 Wind 2-Jun-2016
31-Mar-2019
30-Mar-2044
- - 400 100 -
2
Renew Power Ventures Pvt. Ltd. (RPVPL-Bhuvad)
WR (Bhuvad,
Kutch, Gujarat)
400 Bhachau
S/s 400 Wind
30-Jun-2016
15-Dec-2017
14-Dec-2042
- 50 200 150 -
3 Ostro Kutch Wind Pvt. Ltd. (OKWPL-Kutch)
WR (Kutch, Gujarat)
300 Bhachau
S/s 300 Wind
8-Jul-2016
31-Mar-2018
30-Mar-2043
- - 300 - -
Subtotal 1200 - 50 900 250 -
Agenda of 24th Meeting of WR constituents for Connectivity & LTA applications
Page 12 of 16
LTA Applications in Southern Region
4 Regen Wind farm Pvt. Ltd. (RWFPL-Vagari)
SR (Tamil Nadu)
600 Pugalur
400/230kV S/s
40 Wind 30-May-
2016 01-May-
2017 30-Apr-
2042 - - 40 - -
5 Regen Wind farm Pvt. Ltd. (RWFPL-Vagari)
SR (Tamil Nadu)
600 Pugalur
400/230kV S/s
80 Wind 30-May-
2016 01-Apr-
2018 31-Mar-
2043 - - 80 - -
6 Regen Wind farm Pvt. Ltd. (RWFPL-Vagari)
SR (Tamil Nadu)
600 Pugalur
400/230kV S/s
80 Wind 30-May-
2016 01-June-
2018 31-May-
2043 - - 80 - -
7 Regen Wind farm Pvt. Ltd. (RWFPL-Vagari)
SR (Tamil Nadu)
600 Pugalur
400/230kV S/s
40 Wind 30-May-
2016 1-Sep-2017
31-Aug-2042
- - 40 - -
8
Renew Power Ventures Pvt. Ltd. (RPVPL-Karur)
SR (Karur, Tamil Nadu)
400 Pugalur
400/230kV S/s
400 Wind 30-
June-2016
31-03-2018
30-03-2043
50 - 250 100 -
Subtotal 640 50 - 490 100 -
Grand Total 50 50 1390 350 0
System studies were conducted considering the LTA applications mentioned in
Table:7 as well as the Connectivity applicants mentioned in table 1 and study results
are enclosed at Annexure-I.
4.1 Transmission system for LTA for Adani Green Energy Ltd. (Khavda Wind
Farm) (AGEL-Khavda)
Details of the application are given in Table: 7. The high capacity Green Energy
Corridor starting from Bhuj PS (WR) to Moga (NR) is under implementation by
POWERGRID for evacuation and dispersal of power from renewable generations
coming up in Gujarat (especially Kutch complex) and Rajasthan. The proposed
project is a wind generation in Kutch area of Gujarat. The applicant has requested
LTA quantam of 400 MW for NR and 100 MW for ER.
The proposed transmission system for connectivity for AGEL (Khavda)
project as mentioned in item no. 3.2 is as below:
AGEL (Khavda) – Bhuj PS 220kV D/c line (high capacity) along with
associated line bays at both ends (AGEL / TBCB as per deliberations in the
meeting)
Transmission system for LTA AGEL (Khavda) project:
It can be seen that total LTA quantum of 800MW (300MW form SESPL & 500MW
from AGEL) will be injected on Bhuj PS at 220kV level for which total of 3x500MVA,
Agenda of 24th Meeting of WR constituents for Connectivity & LTA applications
Page 13 of 16
400/220kV ICTs will be required. 2x500MVA, 400/220kV ICTs has already been
planned under LTA system of SESPL (proposed under item no. 3).
Accordingly, following Transmission System for LTA of AGEL (Khavda) for transfer
of power to ER (100MW) & NR (400MW) is proposed:
Transmission System for LTA to ER (100 MW)
Installation of 1x500MVA, 400/220kV (3rd) ICTs at Bhuj PS
Transmission System for LTA to NR (400 MW)
Installation of 1x500MVA, 400/220kV (3rd) ICTs at Bhuj PS
Bhuj PS- Banaskantha PS 765kV D/c line#
Banaskantha PS- Chittorgarh PS 765kV D/c line#
Chittorgarh PS- Chittorgarh (RVPN) 400kV D/c (quad) line#
#under implementation as part of Green Energy Corridors and expected to get commissioned by
July’18
4.2 Transmission system for LTA for Renew Power Ventures Pvt. Ltd. (Bhuvad
Wind Park, Gandhidham) (RPVPL-Bhuvad)
Details of the application are given in the table 7. The proposed project is a wind
generation in Kutch area of Gujarat. The applicant has requested LTA quantam of
200 MW for NR,150 MW for ER and 50 MW for WR.
In 23rd meeting of WR constituents held on 01.06.2016, following Transmission
System for Connectivity was agreed for RPVPL(Bhuvad) project:
RPVPL (Bhuvad) – Bhachau 220kV D/c line along with associated line bays at
both ends (to be constructed by RPVPL)*
*Line bays at Bhachau end to be implemented as GIS (on account of space constraints at
Bhachau S/s)
Transmission system for LTA RPVPL (Bhuvad) project:
Regarding power transfer under LTA within WR (50MW) and to ER (150MW), it may
be mentioned that existing and planned transmission infrastructure shall be
sufficient to enable dispersal of power within WR and from WR to ER.
LTA for transfer of power to beneficiaries in NR is proposed to be granted with the
commissioning of following transmission system.
Green Energy Corridor – ISTS (part system) (under implementation as part of Green
Energy Corridors and expected to get commissioned by July’18):
Bhuj PS – Banaskantha 765kV D/c line
Banaskantha PS – Chittorgarh 765kV D/c line
Chittorgarh – Chittorgarh (RVPN) 400kV D/c (quad) line
Agenda of 24th Meeting of WR constituents for Connectivity & LTA applications
Page 14 of 16
Transmission System Strengthening associated with Mundra UMPP (Part B) (under implementation by POWERGRID):
Mundra UMPP – Bhuj PS 400kV D/c (Triple) line
4.3 Transmission system for LTA for Ostro Kutch Wind Pvt. Ltd. (Kutch Wind
Park) (OKWPL-Kutch)
Details of the application are given in the table 7. The high capacity Green Energy
Corridor starting from Bhuj PS (WR) to Moga(NR) is under implementation by
POWERGRID for evacuation and dispersal of power from renewable generations
coming up in Gujarat (especially Kutch complex) and Rajasthan. The proposed
project is a wind generation in Kutch area of Gujarat. The applicant has requested
LTA quantam of 300 MW for NR.
In 23rd meeting of WR constituents held on 01.06.2016, following Transmission
System for Connectivity was agreed for OKWPL (Kutch) project:
OKWPL (Kutch) – Bhachau 220kV D/c line along with associated line bays at
both ends (to be constructed by OKWPL)*
*Line bays at Bhachau end to be implemented as GIS (on account of space constraints at
Bhachau S/s)
Transmission system for LTA:
LTA for transfer of power to beneficiaries in NR (300 MW) is proposed to be
granted with the commissioning of following transmission system:
Green Energy Corridor – ISTS (part system) (under implementation as part of Green
Energy Corridors and expected to get commissioned by July’18)
Bhuj PS – Banaskantha 765kV D/c line
Banaskantha PS – Chittorgarh 765kV D/c line
Chittorgarh – Chittorgarh (RVPN) 400kV D/c (quad) line
Transmission System Strengthening associated with Mundra UMPP (Part B) (under implementation by POWERGRID)
Mundra UMPP – Bhuj PS 400kV D/c (Triple) line
4.4 Transmission System for LTA for Regen Wind farm Pvt Ltd. (RWFPL-Vagari)
The details of the applications are given in Table: 7 (Sl.4 to 7). M/s Regen Wind Farm
Pvt Ltd. has applied for LTA for transfer of 240MW from Sourthern Region to Nothern
Region. The LTA applications were disucussed in 20th meeting of Southern Region
constituents regarding Connectivity / LTA applications of IPPs in SR held on
13.07.2016 at Gurgaon. In the meeting, following transmission system was agreed for
transfer of power to Northern Region:
Agenda of 24th Meeting of WR constituents for Connectivity & LTA applications
Page 15 of 16
WR- NR 765kV Inter-regional corridor
Jabalpur PS - Orai 765 kV D/C line
System studies indicate no problems in transfer of 240MW power to NR with the
commissioning of Jabalpur - Orai 765 kV corridor under implementation as “Inter-
Regional System Strengthening Scheme in WR and NR Part-B” and Champa –
Kurukshetra HVDC Phase II under implementation as “Transmission System
Strengthening in WR-NR Transmission Corridor For IPPs in Chhattisgarh”. Details of
both the schemes are as given below:
Inter-Regional System Strengthening Scheme in WR and NR Part-B
Jabalpur PS - Orai 765kV D/C line
Orai - Aligarh 765kV D/C line
Orai - Orai 400kV D/C (Quad) line
LILO of one ckt of Satna - Gwalior 765kV 2xS/C line at Orai
LILO of Agra - Meerut 765kV S/C at Aligarh
LILO of Kanpur - Jhatikara 765kV S/C at Aligarh
Transmission System Strengthening in WR-NR Transmission Corridor For
IPPs in Chhattisgarh
Up-gradation of ± 800kV, 3000MW HVDC bipole between Champa PS –
Kurukshetra (NR) to 6000MW
Kurukshetra (NR) – Jind 400kV D/c (Quad)
Hence, it is proposed to grant LTA to M/s Regen Wind farm Pvt Ltd. with the
transmission system mentioned above.
4.5 Transmission System for LTA for Renew Power Ventures Pvt. Ltd. (RPVPL-
Karur)
The details of the application are given in table 7.
M/s Renew Power Ventures Pvt. Ltd. has applied for LTA for transfer of 400MW with
the target beneficiaries as follows: SR- 50MW, NR-250MW & ER – 100MW.
System studies indicate no problems in transfer of power to NR with the
commissioning of Jabalpur - Orai 765 kV corridor under implementation as “Inter-
Regional System Strengthening Scheme in WR and NR -Part B” and Champa –
Kurukshetra HVDC Phase II under implementation as “Transmission System
Strengthening in WR-NR Transmission Corridor For IPPs in Chhattisgarh”. Details of
both the schemes are as given below:
Agenda of 24th Meeting of WR constituents for Connectivity & LTA applications
Page 16 of 16
Inter-Regional System Strengthening Scheme in WR and NR Part-B
Jabalpur PS - Orai 765kV D/C line
Orai - Aligarh 765kV D/C line
Orai - Orai 400kV D/C (Quad) line
LILO of one ckt of Satna - Gwalior 765kV 2xS/C line at Orai
LILO of Agra - Meerut 765kV S/C at Aligarh
LILO of Kanpur - Jhatikara 765kV S/C at Aligarh
Transmission System Strengthening in WR-NR Transmission Corridor For
IPPs in Chhattisgarh
Up-gradation of ± 800kV, 3000MW HVDC bipole between Champa PS –
Kurukshetra (NR) to 6000MW
Kurukshetra (NR) – Jind 400kV D/c (Quad)
Hence, it is proposed to grant LTA for transfer of power to NR to M/s Renew Power
Ventures Pvt. Ltd. (RPVPL-Karur) with the transmission system mentioned above.
Transmission system for transfer of power to ER and within SR shall be taken up for
discussion in the forthcoming meeting of SR Constituents regarding Connectivity &
Long-term Access Applications.
x----------x----------x