dia aim - a new, accountable organization · pdf file1 j. somer shindler the new dia aim...

15
1 J. Somer Shindler The New DIA AIM Development DIA Day October 7, 2014

Upload: dodang

Post on 06-Mar-2018

214 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: DIA AIM - A NEW, ACCOUNTABLE ORGANIZATION · PDF file1 J. Somer Shindler The New DIA AIM Development DIA Day October 7, 2014

1

J. Somer Shindler The New DIA AIM Development DIA Day October 7, 2014

Page 2: DIA AIM - A NEW, ACCOUNTABLE ORGANIZATION · PDF file1 J. Somer Shindler The New DIA AIM Development DIA Day October 7, 2014

2

– Renewed Culture that Focuses on Accountability,

Consistency, Transparency and Building Relationships

– Focus on streamlined process and continuous improvement

– Total Project Delivery - 3 Sections – Technical Programs – Mark Nagel – Infrastructure and Quality Assurance (Civil

Projects) – New Director – Glenn Frieler

– Facility Services (Building Projects) – New Director – David Mashburn

DIA AIM - A NEW, ACCOUNTABLE ORGANIZATION

Page 3: DIA AIM - A NEW, ACCOUNTABLE ORGANIZATION · PDF file1 J. Somer Shindler The New DIA AIM Development DIA Day October 7, 2014

3

DIA AIM - A NEW, ACCOUNTABLE ORGANIZATION

Page 4: DIA AIM - A NEW, ACCOUNTABLE ORGANIZATION · PDF file1 J. Somer Shindler The New DIA AIM Development DIA Day October 7, 2014

BEST PRACTICES

Partners in Leadership

Page 5: DIA AIM - A NEW, ACCOUNTABLE ORGANIZATION · PDF file1 J. Somer Shindler The New DIA AIM Development DIA Day October 7, 2014

A NEW, LEANER WAY OF DOING BUSINESS

With the development of the Project Management Guidelines (PMG), available on at www.flydenver.com , process maps illustrate a more efficient understanding on necessary steps for successful DIA project management.

Future Guideline Updates: Design Standard Manuals (DSM) January 2015 Tenant Development Guidelines (TDG) January 2015

Page 6: DIA AIM - A NEW, ACCOUNTABLE ORGANIZATION · PDF file1 J. Somer Shindler The New DIA AIM Development DIA Day October 7, 2014

PMG Guidelines

– Governing Entities and Document References: – State and Federal requirements provide a firm foundation as a baseline of

minimum objective criteria to build by. – TSA, FAA, EPA, USFW, etc – CDPHE, SHPO, CDOT, etc – Federal Codes - 49 CFR, Parts 23 & 26

– CCD Ordinances – Ordinance 760

– CCD Building Codes – Contract and General Contract Conditions (The Yellow Book) Title 17,

Inspection and Defects – DEN Design Standard Manual and Construction Specifications

– 24 hour/7 days a week Critical Infrastructure

– Meet the Operational and Financial Needs of our Airline Partners and Traveling Public – DEN Airside/Terminal/Landside Operations – Keep Airline Costs Low

6

Page 7: DIA AIM - A NEW, ACCOUNTABLE ORGANIZATION · PDF file1 J. Somer Shindler The New DIA AIM Development DIA Day October 7, 2014

7

PROCESS MAP – Ex. Bidding Projects

Appendix A – in the PMG Consists of 38 Process maps. This map shows page 1 of the process to hire Contractors through bids for specific projects at the airport.

Page 8: DIA AIM - A NEW, ACCOUNTABLE ORGANIZATION · PDF file1 J. Somer Shindler The New DIA AIM Development DIA Day October 7, 2014

8

PROCESS MAP – Ex. Bidding Projects

Appendix A – in the PMG Consists of 38 Process maps. This map shows page 2 of the process to hire Contractors through bids for specific projects at the airport.

Page 9: DIA AIM - A NEW, ACCOUNTABLE ORGANIZATION · PDF file1 J. Somer Shindler The New DIA AIM Development DIA Day October 7, 2014

9

AIM - Business Education Courses

Page 10: DIA AIM - A NEW, ACCOUNTABLE ORGANIZATION · PDF file1 J. Somer Shindler The New DIA AIM Development DIA Day October 7, 2014

Business Opportunities http://business.flydenver.com/

–Registration

Page

10

Future Opportunities Page

Page 11: DIA AIM - A NEW, ACCOUNTABLE ORGANIZATION · PDF file1 J. Somer Shindler The New DIA AIM Development DIA Day October 7, 2014

AIM Development – Project Delivery

11

– Project Delivery Methods – Collaboration with our Business Partners,

Project Understanding and Scope Definition, and Risks Determine the best Delivery Method for the Project

– New and Old Methods for DIA:

– Design Build: Lump Sum, GMAX – Hard Bid – On Calls – Hard Bid/Negotiated – CMR/CMGC – Stipends

Page 12: DIA AIM - A NEW, ACCOUNTABLE ORGANIZATION · PDF file1 J. Somer Shindler The New DIA AIM Development DIA Day October 7, 2014

AIM Development

12

Capital Improvement Program 2014-19 (Infrastructure Program)

– Airfield Pavement Annual Rehabilitation (annual program)

– Rehab 17L-35R Pavement – Gate Pavement Replacement and Drainage Improvement

Program – CMGC w/ Negotiated Fee

– Airfield Drainage Improvements (annual program) – Terminal Taxiway and Apron Slab Rehab (annual program) – Pena Blvd Erosion Control (annual program) – Roadway Pavement Rehabilitation (annual program) – Parking Lot Improvements

Page 13: DIA AIM - A NEW, ACCOUNTABLE ORGANIZATION · PDF file1 J. Somer Shindler The New DIA AIM Development DIA Day October 7, 2014

AIM Development

13

Capital Improvement Program 2014-19 (Facility Services Program)

– Storm and Sewer Repairs – Piping Repairs – Soil Heaving Foundation Repairs – HVAC Controls Upgrade – Boiler Replacement – Cooling Tower Lining Repair Program – Conveyance Replacement Program – Jetbridge Replacement Program – Concourse B PC Air Replacement

– Baggage System Security Upgrades

Page 14: DIA AIM - A NEW, ACCOUNTABLE ORGANIZATION · PDF file1 J. Somer Shindler The New DIA AIM Development DIA Day October 7, 2014

14

Questions?

Page 15: DIA AIM - A NEW, ACCOUNTABLE ORGANIZATION · PDF file1 J. Somer Shindler The New DIA AIM Development DIA Day October 7, 2014

15

J. Somer Shindler The New DIA AIM Development DIA Day October 7, 2014