develop a schedule for an automobile factory using ms project
TRANSCRIPT
Develop a schedule for an Automobile Factory using MS Project.Constrain: All load carrying members should be steel. Duration 48 weeks.
Develop a schedule for a Row Housing Project using MS Project.Constrain: The water table is very high in that site. Minimum 5 houses, which has to be completed within 2 years.
Develop a schedule for dismantling a stadium which consists of Precast as well as RCC Structures, using MS Project.Constrain: Duration not exceeding 4 months.
Develop a schedule for a Bridge, which crosses the river of width 100m, using MS Project.Constrain: Maximum length of the span not to exceed 10m. Duration 80 weeks.
Develop a schedule for a Multi-storey building which is made of Prestressed slabs.Draw the WBS Structure, assign resources and find the Project duration & critical path using MS Project.
Develop a schedule for dismantling a Stadium which consists of Precast as well as RCC Structures, using MS Project.Constrain: Duration not exceeding 4 months.
Develop a schedule for substructure construction of depth 15m, using MS Project.Constrain: The soil is not strong enough to stand its own. Duration 10 weeks.
Develop a schedule for an Tunnel. Total length 200m, using MS Project.Constrain: Tunnel passes through Hard strata. Duration 45 weeks.
Develop a schedule for a Drainage canal of length 10km, using MS Project.Constrain: Duration is 80 weeks
Develop a schedule for Erection of 10 number of Transmission Towers of height 20m, using MS Project.Constrain: Tower to Tower distance -500m. Duration 53 weeks.
Develop a schedule for an Automobile Factory using Primavera.Constrain: All load carrying members should be steel. Duration 48 weeks.
Develop a schedule for a Row Housing Project using Primavera.Constrain: The water table is very high in that site. Minimum 5 houses, which has to be completed within 2 years.
Develop a schedule for dismantling a stadium which consists of Precast as well as RCC Structures, using Primavera.Constrain: Duration not exceeding 4 months.
Develop a schedule for a Bridge, which crosses the river of width 100m, using Primavera.Constrain: Maximum length of the span not to exceed 10m. Duration 80 weeks.
Develop a schedule for a flyover of total length of 100m in a busy traffic junction, using Primavera.Constrain: Maximum length of the span not to exceed 10m. Duration 50 weeks.
Develop a schedule for a Multi-storey building which is made of Prestressed slabs.Draw the WBS Structure, assign resources and find the Project duration & critical path using Primavera.
Develop a schedule for substructure construction of depth 15m, using Primavera.Constrain: The soil is not strong enough to stand its own. Duration 10 weeks.
Develop a schedule for an Tunnel. Total length 200m, using Primavera.Constrain: Tunnel passes through Hard strata. Duration 45 weeks.
Develop a schedule for a Drainage canal of length 10km, using Primavera.Constrain: Duration is 80 weeks
Develop a schedule for Erection of 10 number of Transmission Towers of height 20m, using PrimaveraConstrain: Tower to Tower distance -500m. Duration 53 weeks.