design basis imfa

Upload: durjoy-chakraborty

Post on 05-Feb-2018

225 views

Category:

Documents


5 download

TRANSCRIPT

  • 7/21/2019 Design Basis IMFA

    1/146

    OC No. Total Sheets

    DDC 067Document No. PP 067 M B01 0

    146

    DESIGN BASIS REPORT FOR

    MECHANICAL

  • 7/21/2019 Design Basis IMFA

    2/146

    POWER DIVISION THERMAX LIMITED

    Project Document Title Doc. No. Rev. Sheet

    2 x 60 MW THERMAL

    POWER PLANT, IMFA,

    ORISSA

    DESIGN BASIS REPORT

    MECHANICAL

    PP 067 M B01 0 1 2

    DESIGN BASIS REPORT MECHANICAL

    INDEX

    1. INTRODUCTION ...............................................................................................9

    2. UNITS OF MEASUREMENT & ABBREVIATIONS.........................................10

    2.1. UNITS OF MEASUREMENT .............................................................................10

    2.2. ABBREVIATIONS............................................................................................10

    3. CODES & STANDARDS.................................................................................11

    4. POWER PLANT CONFIGURATION...............................................................14

    4.1. PLANT CONFIGURATION ................................................................................14

    4.2. PLANT STARTUP,OPERATION AND CONTROL PHILOSOPHY ..............................16

    4 3 CUSTOMERS DESIGN INPUTS 16

  • 7/21/2019 Design Basis IMFA

    3/146

  • 7/21/2019 Design Basis IMFA

    4/146

    POWER DIVISION THERMAX LIMITED

    Project Document Title Doc. No. Rev. Sheet

    2 x 60 MW THERMAL

    POWER PLANT, IMFA,

    ORISSA

    DESIGN BASIS REPORT

    MECHANICAL

    PP 067 M B01 0 1 4

    7.3.4. Pressure Gradient ............................................................................................. 47

    7.3.5. Velocity Profile................................................................................................... 47

    7.3.6. Safety valve details ........................................................................................... 48

    7.3.6.1. Safety Valve Set Pressures .....................................................................................48

    7.3.6.2. Safety Valve Relieving Capacity ..............................................................................48

    7.3.7. Fuel, Limestone & Bed Material Consumption.................................................. 48

    7.4. BOILER MOUNTINGS AND FITTINGS ................................................................49

    7.4.1. Steam Drum ...................................................................................................... 49

    7.4.2. Furnace headers ............................................................................................... 49

    7.4.3. Drain Header..................................................................................................... 49

    7.4.4. Superheater....................................................................................................... 50

    7.4.5. Spray Water Line............................................................................................... 50

    7.4.6. Economiser ....................................................................................................... 50

    7.5. SOLID FUEL FIRING SYSTEM..........................................................................50

    7.5.1. Fuel Bunker....................................................................................................... 51

    7 5 2 Fuel Firing System 51

  • 7/21/2019 Design Basis IMFA

    5/146

    POWER DIVISION THERMAX LIMITED

    Project Document Title Doc. No. Rev. Sheet

    2 x 60 MW THERMAL

    POWER PLANT, IMFA,

    ORISSA

    DESIGN BASIS REPORT

    MECHANICAL

    PP 067 M B01 0 1 5

    7.13. ESP DESIGN BASIS .......................................................................................60

    7.14. CHIMNEYDESIGN BASIS.............................................................................61

    7.14.1. Calculation of Chimney Height....................................................................... 62

    7.14.2. Calculation of Chimney Diameter................................................................... 62

    7.14.3. Sketch of Chimney......................................................................................... 63

    8. STEAM, FEED WATER AND CONDENSATE SYSTEM ................................63

    8.1. STEAM SYSTEM............................................................................................63

    8.1.1. Control Philosophy............................................................................................ 66

    8.2. FEED WATER SYSTEM ..................................................................................66

    8.2.1. Deaerator .......................................................................................................... 668.2.2. Boiler Feed Pumps............................................................................................ 68

    8.2.3. HP Feed Water Heaters.................................................................................... 70

    8.2.4. Feed Water Control Station.............................................................................. 70

    8.2.5. Control Philosophy............................................................................................ 70

    8.3. CONDENSATE SYSTEM..................................................................................71

    8 3 1 S f C d 72

  • 7/21/2019 Design Basis IMFA

    6/146

    POWER DIVISION THERMAX LIMITED

    Project Document Title Doc. No. Rev. Sheet

    2 x 60 MW THERMAL

    POWER PLANT, IMFA,

    ORISSA

    DESIGN BASIS REPORT

    MECHANICAL

    PP 067 M B01 0 1 6

    9.2.1.2. System Sizing Calculation........................................................................................89

    9.2.2. Auxiliary Cooling Water System For Auxiliaries ................................................ 91

    9.2.2.1. System Description ..................................................................................................91

    9.2.2.2. System Sizing Calculation........................................................................................92

    9.2.3. Cooling Water Treatment Scheme.................................................................... 94

    10. FUEL OIL SYSTEM.........................................................................................94

    11. FUEL HANDLING SYSTEM............................................................................94

    11.1. SYSTEM SIZING ............................................................................................95

    11.2. SYSTEM DESCRIPTION ..................................................................................96

    12. LIME STONE HANDLING SYSTEM .............................................................101

    12.1. SYSTEM DESCRIPTION &SYSTEM SIZING .....................................................101

    13. ASH HANDLING SYSTEM............................................................................102

    13.1. SYSTEM DESCRIPTION ................................................................................102

  • 7/21/2019 Design Basis IMFA

    7/146

    POWER DIVISION THERMAX LIMITED

    Project Document Title Doc. No. Rev. Sheet

    2 x 60 MW THERMAL

    POWER PLANT, IMFA,

    ORISSA

    DESIGN BASIS REPORT

    MECHANICALPP 067 M B01 0 1 7

    16. VENTILATION SYSTEM ...............................................................................117

    16.1. SYSTEM DESCRIPTION ................................................................................117

    16.1.1. Ventilation System for Power House Building & associated Areas.............. 117

    16.1.2. Ventilation System for Auxiliary Buildings in Various Locations .................. 118

    16.2. SYSTEM SIZING ..........................................................................................120

    17. FIRE PROTECTION SYSTEM ......................................................................121

    17.1. SYSTEM DESCRIPTION ................................................................................121

    17.1.1. Fire Water System ....................................................................................... 122

    17.1.2. Hydrant System ........................................................................................... 122

    17.1.3. Spray Water System.................................................................................... 123

    17.1.4. Portable & Mobile Fire Extinguishers........................................................... 124

    17.1.5. Fire Detection & Alarm System.................................................................... 124

    18. CRANES AND HOISTS.................................................................................125

    19. ELEVATORS.................................................................................................127

  • 7/21/2019 Design Basis IMFA

    8/146

    POWER DIVISION THERMAX LIMITED

    Project Document Title Doc. No. Rev. Sheet

    2 x 60 MW THERMAL

    POWER PLANT, IMFA,

    ORISSA

    DESIGN BASIS REPORT

    MECHANICALPP 067 M B01 0 1 8

    21.12. EFFLUENT ...............................................................................................137

    21.13. SERVICE AND POTABLE WATER PIPE LINE...................................................138

    21.14. CONDENSER COOLING WATER PIPING ........................................................138

    21.15. AUXILIARY COOLING WATER PIPING ...........................................................138

    21.16. FIRE WATER PIPING .................................................................................13821.17. VALVES...................................................................................................138

    21.17.1. Insulation .................................................................................................. 139

    21.17.2. Pipe Supports and Hangers...................................................................... 139

    21.17.2.1. Constant Spring Hangers.......................................................................................139

    21.17.2.2. Variable Spring Hangers ........................................................................................140

    21.17.2.3. Rod Hangers ..........................................................................................................140

    21.17.2.4. Pipe Clamps and Shoe / Saddle supports .............................................................140

    21.17.2.5. Materials of Construction .......................................................................................140

    21.18. GENERAL GUIDELINES FOR PIPING............................................................140

    22. ANNEXURES ................................................................................................142

  • 7/21/2019 Design Basis IMFA

    9/146

    POWER DIVISION THERMAX LIMITED

    Project Document Title Doc. No. Rev. Sheet

    2 x 60 MW THERMAL

    POWER PLANT, IMFA,

    ORISSA

    DESIGN BASIS REPORT

    MECHANICALPP 067 M B01 0 1 9

    1. INTRODUCTION

    This document aims at establishing the criteria for basic and detail

    engineering, sizing and specifications of the Power Plant equipment, systems,

    components, and piping for the 2 x 60 MW Power Plant at Choudwar in Cuttack

    district, Odisha, being set up by M/s. Indian Metals & Ferro Alloys (IMFA) Limited.

    The basic design inputs like Fuel analysis, Water analysis, Site conditions,

    etc. have been spelt out in various sections of this document, which are as per

    IMFA inputs. Details developed in this document is generally in line with theagreed contract document.

    This document is to be read in conjunction with design basis report for

    Electrical Systems, Civil Works and Instrumentation systems. For an overall

    understanding of the plant and design of auxiliary equipments and system, certain

    d t il f j i t lik b il t t bi t h b i t d

  • 7/21/2019 Design Basis IMFA

    10/146

    POWER DIVISION THERMAX LIMITED

    Project Document Title Doc. No. Rev. Sheet

    2 x 60 MW THERMAL

    POWER PLANT, IMFA,

    ORISSA

    DESIGN BASIS REPORT

    MECHANICALPP 067 M B01 0 1 10

    2. UNITS OF MEASUREMENT & ABBREVIATIONS

    2.1. UNITS OF MEASUREMENT

    Deg.C Degree Celsius

    kg/cm2 (a) or Ata Kilograms per Square Centimetre (Absolute)

    kg/cm2 (g) Kilograms per Square Centimetre (Gauge)

    kV Kilo Volt

    kW Kilo Watt

    MLC Meters of Liquid Column

    MW Mega Watt

    MWC Meters of Water Column

  • 7/21/2019 Design Basis IMFA

    11/146

    POWER DIVISION THERMAX LIMITED

    Project Document Title Doc. No. Rev. Sheet

    2 x 60 MW THERMAL

    POWER PLANT, IMFA,

    ORISSA

    DESIGN BASIS REPORT

    MECHANICALPP 067 M B01 0 1 11

    LP Low Pressure

    MB Mixed Bed

    MCW Main Cooling Water System (for Condenser)

    MOC Material of Construction

    MSL Mean Sea Level

    PRDS Pressure Reducing & De-superheating Station

    PRV Pressure Reducing Valve

    Re Reynolds Number

    RL Reference Level

    RO Reverse Osmosis

    SAC Strong Acid Cation

  • 7/21/2019 Design Basis IMFA

    12/146

    POWER DIVISION THERMAX LIMITED

    Project Document Title Doc. No. Rev. Sheet

    2 x 60 MW THERMAL

    POWER PLANT, IMFA,

    ORISSA

    DESIGN BASIS REPORT

    MECHANICALPP 067 M B01 0 1 12

    Bureau of Indian Standards (BIS)

    International Electro-technical Commission (IEC)

    DIN Standards

    British Standards (BS)

    American Society of Mechanical Engineers (ASME)

    American Society of Testing and Materials (ASTM)

    American Welding Society (AWS)

    American Institute of Steel Construction (AISC)

    American Water Works Association (AWWA)

    American National Standard Institute (ANSI)

    Architecture Institute of Japan (AIJ)

  • 7/21/2019 Design Basis IMFA

    13/146

    POWER DIVISION THERMAX LIMITED

    Project Document Title Doc. No. Rev. Sheet

    2 x 60 MW THERMAL

    POWER PLANT, IMFA,

    ORISSA

    DESIGN BASIS REPORT

    MECHANICALPP 067 M B01 0 1 13

    Standards of Manufacturer Standardization Society (MSS)

    Indian Electricity Act

    Indian Electricity Rule

    Indian Factory Act & State Factory Act

    Instrument Society of America (ISA)

    Federal Occupational Safety and Health Organization (OSHA)

    Loss Prevention Association of India (LPA)

    Emission regulations of Central Pollution Control Board, India

    Central Board of Irrigation and Power (CBIP) publications, India

    Pollution Control Regulations of Dept. of Environment, Govt. of India

    Permissible limits for pollutants of Orissa Pollution Control Board

  • 7/21/2019 Design Basis IMFA

    14/146

    POWER DIVISION THERMAX LIMITED

    Project Document Title Doc. No. Rev. Sheet

    2 x 60 MW THERMAL

    POWER PLANT, IMFA,

    ORISSA

    DESIGN BASIS REPORT

    MECHANICALPP 067 M B01 0 1 14

    reliability.

    4. POWER PLANT CONFIGURATION

    4.1. PLANT CONFIGURATION

    The power plant consists of the following major Mechanical systems and

    equipment:

    Two (2) number Boilers: Circulating Fluidized Bed Combustion (CFBC)

    type, each generating 240 TPH at 101 kg/cm2 (a) pressure and 540 +

    5oC temperature at the Main Steam Stop Valve using fuel as per Coal

    Analysis mentioned elsewhere in this document. The boiler envisage de-

    sulphuring using lime stone as per lime stone analysis mentioned

    elsewhere in this document.

    Two (2) number Electro Static Precipitator (ESP), one each per

  • 7/21/2019 Design Basis IMFA

    15/146

    POWER DIVISION THERMAX LIMITED

    Project Document Title Doc. No. Rev. Sheet

    2 x 60 MW THERMAL

    POWER PLANT, IMFA,

    ORISSA

    DESIGN BASIS REPORT

    MECHANICALPP 067 M B01 0 1 15

    Regenerative feed heating system consists of two LP heater, one

    Deaerator, two HP heater.

    Turbine bypass system Capacity 60% of TMCR.

    Boiler feed water pumping system with 3 x 100 % Motor driven boiler

    feed water pumps. Out of these three pumps, one will be operating

    normally for each boiler unit while the third pump shall remain as a

    common standby and will come into operation automatically in case one

    of the working pump fails.

    One Main Cooling Tower for both units with 7 cells (6 working & 1

    standby) induced draft counter flow design and RCC / Pultruded FRP

    construction and main cooling water pumping system.

    One Auxiliary Cooling Tower for both units with 2 cells (1 working & 1

    standby) induced draft counter flow design and FRP / Pultruded FRP

  • 7/21/2019 Design Basis IMFA

    16/146

    POWER DIVISION THERMAX LIMITED

    Project Document Title Doc. No. Rev. Sheet

    2 x 60 MW THERMAL

    POWER PLANT, IMFA,

    ORISSA

    DESIGN BASIS REPORT

    MECHANICALPP 067 M B01 0 1 16

    CW treatment plant, potable and service water system and effluent

    system.

    Compressed air system consists of plant air compressors and Air

    drying plant for instrument air and service air compressors for service

    air.

    Ai r condit ioning &Venti lat ion system.

    Fire protection system for the power plant, transformer area, fuel oil

    area, switch yard area, coal handling area and ash handling area.

    Inter-connecting piping system

    EOT crane for TG building and miscellaneous hoists and monorails.

    Elevators for Boiler and Power House building.

  • 7/21/2019 Design Basis IMFA

    17/146

    POWER DIVISION THERMAX LIMITED

    Project Document Title Doc. No. Rev. Sheet

    2 x 60 MW THERMAL

    POWER PLANT, IMFA,

    ORISSA

    DESIGN BASIS REPORT

    MECHANICALPP 067 M B01 0 1 17

    Sr.No.

    Item Description

    1. Project Title 2 X 60 MW Thermal power project

    2. Location Choudwar, Distt. Cuttack, State ofOrissa.

    Longitude: 8554 E

    Latitude: 2031 N

    3. Nearest Town Choudwar: 0 KMs, Cuttack: 12 KMs

    4. Nearest City Cuttack 12 KMs.

    5. Nearest Port Paradeep

    6. Nearest Railway Station Charbatia 12 km away

  • 7/21/2019 Design Basis IMFA

    18/146

    POWER DIVISION THERMAX LIMITED

    Project Document Title Doc. No. Rev. Sheet

    2 x 60 MW THERMAL

    POWER PLANT, IMFA,

    ORISSA

    DESIGN BASIS REPORT

    MECHANICALPP 067 M B01 0 1 18

    Sr.No.

    Item Description

    g. Type of atmosphere Hot and Sultry

    h. Annual Mean WindVelocity

    6.4 Km/hr

    i. Maximum Wind velocity As per IS 875 Part III

    j. Basic wind speed As per IS 875 Part III

    k. Design Wind velocity As per IS code specific to the sitelocation Choudwar, Cuttack

    l. Wind Direction South to North.

    m. Seismic Data As per IS : 1893 (Latest Issue)

    4.3.2. COALANALYSIS

  • 7/21/2019 Design Basis IMFA

    19/146

    POWER DIVISION THERMAX LIMITED

    Project Document Title Doc. No. Rev. Sheet

    2 x 60 MW THERMAL

    POWER PLANT, IMFA,

    ORISSA

    DESIGN BASIS REPORT

    MECHANICALPP 067 M B01 0 1 19

    TOTAL 100.00 100.00 100.00

    GCV (Kcal/Kg) 3280.00 2010.00 2645.00

    PROXIMATE ANALYSIS

    Ash 42.00 60.00 51.00

    Volatile matter 21.00 14.00 17.50

    Moisture 15.00 13.00 14.00

    Fixed carbon 22.00 13.00 17.50

    Total 100.00 100.00 100.00

    COAL SIZE

    Feed Coal size at Grizzly of GroundHopper by Customer

    90 % below 100 mm.

  • 7/21/2019 Design Basis IMFA

    20/146

    POWER DIVISION THERMAX LIMITED

    Project Document Title Doc. No. Rev. Sheet

    2 x 60 MW THERMAL

    POWER PLANT, IMFA,

    ORISSA

    DESIGN BASIS REPORT

    MECHANICALPP 067 M B01 0 1 20

    Titanium as TiO2 1-2 2.32

    Total carbonates as CO3 - < 0.01

    Manganese oxide as

    Mn3O4/MnO0.02-0.04 0.12

    Zinc as ZnO - 0.02

    Loss on ignition - 2.11

    4.3.4. LIME STONEANALYSIS

    COMPONENT % BY WT. (RANGE)

    LIME STONE ANALYSIS

    CaCO3 90 94% for operability. Forguaranteed sulphur capture onperformance fuel to restrict chimneyheight to 44 m, CaCO3 content shall

  • 7/21/2019 Design Basis IMFA

    21/146

    POWER DIVISION THERMAX LIMITED

    Project Document Title Doc. No. Rev. Sheet

    2 x 60 MW THERMAL

    POWER PLANT, IMFA,

    ORISSA

    DESIGN BASIS REPORT

    MECHANICALPP 067 M B01 0 1 21

    TiO2 % 1.5 1.7

    MnO % Traces

    CaO % 0.5 0.6

    MgO % 0.2 0.25

    P2O5 % Less than 0.1

    Na2O % Less than 0.22

    K2O % Less than 0.45

    BED MATERIAL SIZE

    Size in Microns Unit % Passing

    < 500 % 100

  • 7/21/2019 Design Basis IMFA

    22/146

    POWER DIVISION THERMAX LIMITED

    Project Document Title Doc. No. Rev. Sheet

    2 x 60 MW THERMAL

    POWER PLANT, IMFA,

    ORISSA

    DESIGN BASIS REPORT

    MECHANICALPP 067 M B01 0 1 22

    8. Bi- Carbonates mg/l as CaCO3 52 60

    9. Total Anions mg/l 72 89

    10. Iron as Fe mg/l as CaCO3 0.8 1.0

    11. Silica (Reactive) mg/l as SiO2 8.0 10

    12. M- Alkalinity mg/l as CaCO3 52 60

    13. Turbidity NTU 184 200

    14. Total Suspended Solids mg/l 170 190

    15. Total Dissolved Solids mg/l 70 80

    16. pH value at 25oC 7.6 7.8

    17. Conductivity at 25oC S/cm 137 150

  • 7/21/2019 Design Basis IMFA

    23/146

    POWER DIVISION THERMAX LIMITED

    Project Document Title Doc. No. Rev. Sheet

    2 x 60 MW THERMAL

    POWER PLANT, IMFA,

    ORISSA

    DESIGN BASIS REPORT

    MECHANICALPP 067 M B01 0 1 23

    Convenience of fuel intake.

    Convenience of Installation.

    Minimum width of clear access around equipment shall be provided as 1

    m.

    Minimum clear height between two consecutive floors shall be determined

    considering maintenance, lifting and safety requirements. A clear head

    room of 2 m shall be maintained between floors and over head piping /

    cabling.

    All road crossing for pipe / cable rack shall be done with minimum 5.5 m

    head room from top of road to bottom of rack where only Truck movement

    is expected and 7.0 m where crane movement is expected. Minimum 8 m

    clearance shall be kept in case of railway track with overhead traction.

    Similarly top cover over any underground pipe / cable shall be minimum 1

  • 7/21/2019 Design Basis IMFA

    24/146

    POWER DIVISION THERMAX LIMITED

    Project Document Title Doc. No. Rev. Sheet

    2 x 60 MW THERMAL

    POWER PLANT, IMFA,

    ORISSA

    DESIGN BASIS REPORT

    MECHANICALPP 067 M B01 0 1 24

    c) Cooling tower

    d) Compressor room

    f) DG room

    5.1.1. POWER HOUSE

    The Power House will include:

    Steam Turbine Generator & auxiliaries which includes condenser, CEPs,

    LP & HP heaters, Deaerator, BFPs, steam jet ejectors, gland steam condenser etc.

    located in the Steam Turbine Hall.

    Power house building size shall be 87 m x 31.5 m devided into AB bay

    (20.5 m wide) & BC bay (11 m wide). AB bay shall have 3 floor elevations i.e.

    ground floor at 0 m, mezzanine floor at 4.5 m & operating floor at 10 m. BC bay

    shall have 4 floor elevations i.e. cable spreader floor at 0 m, swithgear floor at 4.0

  • 7/21/2019 Design Basis IMFA

    25/146

    POWER DIVISION THERMAX LIMITED

    Project Document Title Doc. No. Rev. Sheet

    2 x 60 MW THERMAL

    POWER PLANT, IMFA,

    ORISSA

    DESIGN BASIS REPORT

    MECHANICALPP 067 M B01 0 1 25

    5. The crane rails elevation of the turbine hall shall be selected based on

    turbine height and crane clearance required above turbine.

    6. The vertical can type Condensate Extraction Pump will be located adjacent

    to the Condenser on the ground floor.

    7. The Lube Oil System will be located at mezzanine floor (4.5 m) level on

    turbine side.

    8. The Deaerator will be mounted on the roof of the control building i.e. at

    Deaerator floor level (15 m). The Deaerator foundation design will take into

    consideration any possible vibration due to steam chugging.

    9. The boiler feed pumps shall be located within the power house at ground

    floor (0 m). Vertical HP & LP heaters are also located on ground floor.

    10. A mezzanine floor (4.5 m) would be provided to accommodate STG

    auxiliaries like Gland Steam Condenser & Steam Jet Air Ejector.

  • 7/21/2019 Design Basis IMFA

    26/146

    POWER DIVISION THERMAX LIMITED

    Project Document Title Doc. No. Rev. Sheet

    2 x 60 MW THERMAL

    POWER PLANT, IMFA,

    ORISSA

    DESIGN BASIS REPORT

    MECHANICALPP 067 M B01 0 1 26

    provided with necessary aviation lighting, lightning-protection, sampling ports with

    platforms etc.

    Adequate platform and staircase will be provided for boiler to access

    different floor levels and equipment / valves / instruments of boiler for operation

    and maintenance.

    Both the boiler will be suitably connected through galleries at three different

    levels.

    5.1.3. COOLING TOWERAREA

    Cooling tower area consists of Main Cooling Tower (MCT), Auxiliary

    Cooling Tower (ACT), Main & Auxiliary cooling water pump house, MCC & control

    room and chlorine dioxide generator room.

    The MCT shall be of RCC / Pultruded FRP construction & ACT shall be of

  • 7/21/2019 Design Basis IMFA

    27/146

    POWER DIVISION THERMAX LIMITED

    Project Document Title Doc. No. Rev. Sheet

    2 x 60 MW THERMAL

    POWER PLANT, IMFA,

    ORISSA

    DESIGN BASIS REPORT

    MECHANICALPP 067 M B01 0 1 27

    The inclination angle for coal conveyor will be 14 maximum. Central

    walkway of 1000 mm and side walkways of 800 mm with 2.7 m clear height will be

    provided along the belt conveyor gantry. A separate MCC cum control room for

    coal handling plant will be provided near the crusher house.

    5.3. WATER SYSTEM AREA

    5.3.1. RAW WATER RESERVOIR

    Raw Water Reservoir shall be developed in designated area for collection

    and storage of raw water. Reservoir shall be a cut and fill arrangement withsuitable embankment around this area upto a height required to build the 10,000

    m3 capacity of the reservoir. Reservoir shall have two (2) compartments so that

    one half can be emptied and maintained without disturbing the plant operation.

    Design and construction of the reservoir shall be done in such a fashion that no

    water can escape from the reservoir through seepage.

  • 7/21/2019 Design Basis IMFA

    28/146

    POWER DIVISION THERMAX LIMITED

    Project Document Title Doc. No. Rev. Sheet

    2 x 60 MW THERMAL

    POWER PLANT, IMFA,

    ORISSA

    DESIGN BASIS REPORT

    MECHANICALPP 067 M B01 0 1 28

    5.4. SWITCHYARD AREA

    The 132 kV switchyard & 33 kV switchyard are located on west end side of

    the plant so that HT line from the generator transformer can be conveniently

    interconnected.

    5.5. ASH SILO AREA

    Bed & Fly ash silos of RCC construction are provided eastern side of the

    plant near to the plant boundary & away form main plant area to avoid the dust

    nuisance while discharging to the open truck.

    5.6. MISCELLANEOUS

    The interconnection pipe work between plant utilities and power block

    equipment will be routed through pipe racks / sleepers and pipe trenches

    depending on the layout. The Main Cooling water and Auxiliary Cooling water

  • 7/21/2019 Design Basis IMFA

    29/146

    POWER DIVISION THERMAX LIMITED

    Project Document Title Doc. No. Rev. Sheet

    2 x 60 MW THERMAL

    POWER PLANT, IMFA,

    ORISSA

    DESIGN BASIS REPORT

    MECHANICALPP 067 M B01 0 1 29

    6.2. TURBINE

    The Steam Turbine will be of horizontal, single casing impulse-reaction with

    axial flow multistage construction. The Turbine will be designed with five bleeds,

    for the regenerative heating requirement in LP Heater, Deaerator and HP Heater.

    Steam Turbine Casings & Admiss ion Valves

    The turbine casing is horizontally split. The upper and lower casing halves

    are flanged and assembled by bolts. Steam flow through the turbine is in the axial

    direction. After leaving the body of the emergency stop valve, the live steam

    enters the valve chest with the control valves which forms an integral casting with

    the upper half of the outer casing. The valve chest is designed as a transverse

    tube with openings at both ends for assembly.

    The turbine casing is divided into an admission and an exhaust section.

    Depending on the initial steam conditions, the admission sections of comparable

  • 7/21/2019 Design Basis IMFA

    30/146

    POWER DIVISION THERMAX LIMITED

    Project Document Title Doc. No. Rev. Sheet

    2 x 60 MW THERMAL

    POWER PLANT, IMFA,

    ORISSA

    DESIGN BASIS REPORT

    MECHANICALPP 067 M B01 0 1 30

    The guide blades are manufactured from drawn bar material and have

    pronged roots. The guide blade tips are fitted with riveted shroud strips.

    Bearings

    By its brackets, the outer casing is supported on the two bearing pedestals

    independently from the bearing housings. The vertical position of the outer casing

    is determined by adjustable positioning elements located between the brackets

    and the supporting plane of the pedestals. The clearance left between the

    underside of the assembly-bolt head and the bracket allows for both axial and

    lateral expansion of the outer casing with respect to the pedestal. The central

    position is ensured by guideways in the bottom half of the casing. They leave the

    casing free to expand also in the vertical direction. The fixed reference position of

    the casing is at the rear end support brackets. The casing is thus free to yield to

    thermal expansion by moving forward on special slide elements between the front-

    end brackets and the front bearing pedestal. The turbine rotor is supported in the

  • 7/21/2019 Design Basis IMFA

    31/146

    POWER DIVISION THERMAX LIMITED

    Project Document Title Doc. No. Rev. Sheet

    2 x 60 MW THERMAL

    POWER PLANT, IMFA,

    ORISSA

    DESIGN BASIS REPORT

    MECHANICALPP 067 M B01 0 1 31

    multiple segments that would be pushed in the working position by the flat springs

    and by the steam pressure. The stator labyrinth rings segments can be pushed

    away from the rotor in case of accidental contact and the rubbing of rotating and

    stationary parts can be minimised. The shaft shall have in the gland sections

    caulked sheet fins that together with the stator collars form the small chambers of

    the labyrinth gland.

    During normal operation, the source of sealing steam is from the turbine

    itself. During start-up and low loads, an alternative source of sealing steam is

    provided from the main steam.The front outer gland shall be fed from a pressure-

    control valve, which shall receive the steam from the main steam line. The rear

    outer gland seals during the normal operation permanently face the vacuum inside

    of the turbine casing and must be therefore continuously fed by the steam. The

    feeding steam shall be taken from the front gland leakage. The leakage steam

    from outer labyrinths shall go to the Gland Steam Condenser (GSC). The gland

  • 7/21/2019 Design Basis IMFA

    32/146

    POWER DIVISION THERMAX LIMITED

    Project Document Title Doc. No. Rev. Sheet

    2 x 60 MW THERMAL

    POWER PLANT, IMFA,

    ORISSA

    DESIGN BASIS REPORT

    MECHANICALPP 067 M B01 0 1 32

    extraction steam lines before the QCNRV connection are connected to condenser.

    The downstream of QCNRV, the drains are connected to atmospheric flash tank

    and taken out. Vacuum drains are connected to a manifold in the flash tank whose

    top nozzle is connected to steam space of the Condenser and bottom nozzle

    connected to the hotwell. The high pressure drain is connected farthest from the

    condenser, where as the low pressure drains are connected closer to the

    condenser. The drain manifold connection will be above the maximum level in the

    condenser hotwell.

    6.5. TURBINE LUBE OIL SYSTEM

    6.5.1. OIL STORAGE TANKS

    Each turbine will have one (1) main oil tank designed considering the

    complete drain oil from lube oil system & control oil system. The capacity of the

    main oil tank is about 14 m3. The main oil tank will be provided with necessary

  • 7/21/2019 Design Basis IMFA

    33/146

    POWER DIVISION THERMAX LIMITED

    Project Document Title Doc. No. Rev. Sheet

    2 x 60 MW THERMAL

    POWER PLANT, IMFA,

    ORISSA

    DESIGN BASIS REPORT

    MECHANICALPP 067 M B01 0 1 33

    6.5.3. OIL PUMPS

    6.5.3.1. Main & Auxiliary Lube Oil Pump

    Total three (3) pumps of identical capacity i.e. 3 x 100 % have been

    provided, each one capable of meeting the total lube oil requirement. One of thesepumps is designated as Main Oil Pump (MOP) and other two as Auxiliary Oil

    Pump (AOP). All the three pumps are AC motor driven.

    6.5.3.2. Emergency Oil Pump

    The turbine will be provided with an emergency oil pump, mounted on top

    of oil tank, driven by an AC & DC motor. It will cater to the needs of bearings of

    turbine, gearbox and alternator in case of failure of AC motor driven auxiliary lube

    oil pump.

    6.5.3.3. Overhead Tank

  • 7/21/2019 Design Basis IMFA

    34/146

    POWER DIVISION THERMAX LIMITED

    Project Document Title Doc. No. Rev. Sheet

    2 x 60 MW THERMAL

    POWER PLANT, IMFA,

    ORISSA

    DESIGN BASIS REPORT

    MECHANICALPP 067 M B01 0 1 34

    escaping oil.

    6.5.6. LUBE OIL PURIFIER

    An oil purifier will be provided with necessary filters and heater, including

    the pump and motors of the purifier system. The purifier is an off-line equipmentmeant to clean the oil in the system by partial recirculation (operated for one shift

    per day). Desludging of the purifier shall be done manually periodically. The

    system will purify the re-circulating lubricating oil from entrained moisture &

    suspended solids. The purifier capacity will be 2000 LPM.

    6.6. JACKING OIL PUMP

    The turbine will have a 1 x 100 % AC motor driven and 1 x 100 % DC motor

    driven jacking oil pump for turbine and generator shaft lifting during starting,

    designed so as to lift the rotor from standstill condition.

  • 7/21/2019 Design Basis IMFA

    35/146

    POWER DIVISION THERMAX LIMITED

    Project Document Title Doc. No. Rev. Sheet

    2 x 60 MW THERMAL

    POWER PLANT, IMFA,

    ORISSA

    DESIGN BASIS REPORT

    MECHANICALPP 067 M B01 0 1 35

    516 Gr.70) construction. The condenser will be designed with 85% cleanliness

    factor. The hot well storage capacity will be minimum 3 minutes between normal

    and low level at MCR condition.

    6.9. MAIN TECHNICAL PARAMETERS OF STEAM TURBINE

    (A) At 100 % TMCR Condition

    Parameter Unit Value

    Power at generator terminal kW 60,000

    Main Steam Pressure at Turbine inlet Ata 98

    Main Steam Temperature at Turbine inlet OC 535

    Main Steam Flow at Turbine inlet TPH 224

    Main steam requirement for auxiliaries TPH 0.5

    Exhaust steam pressure Ata 0.1

  • 7/21/2019 Design Basis IMFA

    36/146

    POWER DIVISION THERMAX LIMITED

    Project Document Title Doc. No. Rev. Sheet

    2 x 60 MW THERMAL

    POWER PLANT, IMFA,

    ORISSA

    DESIGN BASIS REPORT

    MECHANICALPP 067 M B01 0 1 36

    Main Steam Pressure at Turbine inlet Ata 98

    Main Steam Temperature at Turbine inlet OC 535

    Main Steam Flow at Turbine inlet TPH 219

    Main steam requirement for auxiliaries TPH 0.5

    Exhaust steam pressure Ata 0.1

    Exhaust flow TPH 166.33

    (D) At Both HP Heaters out Condi tion

    Parameter Unit Value

    Power at generator terminal kW 60,000

    Main Steam Pressure at Turbine inlet Ata 98

    Main Steam Temperature at Turbine inlet OC 535

    Main Steam Flow at Turbine inlet TPH 210.6

  • 7/21/2019 Design Basis IMFA

    37/146

    POWER DIVISION THERMAX LIMITED

    Project Document Title Doc. No. Rev. Sheet

    2 x 60 MW THERMAL

    POWER PLANT, IMFA,

    ORISSA

    DESIGN BASIS REPORT

    MECHANICALPP 067 M B01 0 1 37

    (F) At 80 % TMCR Condition

    Parameter Unit Value

    Power at generator terminal kW 48,000

    Main Steam Pressure at Turbine inlet Ata 98

    Main Steam Temperature at Turbine inlet OC 535

    Main Steam Flow at Turbine inlet TPH 180.8

    Main steam requirement for auxiliaries TPH 0.5

    Exhaust steam pressure Ata 0.1

    Exhaust flow TPH 132

    (G) At 50 % TMCR Condi tion

    Parameter Unit Value

    Power at generator terminal kW 30,000

  • 7/21/2019 Design Basis IMFA

    38/146

    POWER DIVISION THERMAX LIMITED

    Project Document Title Doc. No. Rev. Sheet

    2 x 60 MW THERMAL

    POWER PLANT, IMFA,

    ORISSA

    DESIGN BASIS REPORT

    MECHANICALPP 067 M B01 0 1 38

    Sl.No.

    Parameters Unit Value

    1.0 Capacity

    1.1Maximum Continuous Rating [BMCR]

    at main steam stop valveTPH 240

    2.0 Pressure

    2.1Steam Pressure at main steam Stopvalve outlet

    Kg/cm2(a) 101

    3.0 Temperature

    3.1 Steam temperature at main steamStop valve outlet.

    C 540 5

    3.2Steam temp. control range for designperformance fuel

    % MCR 60% MCR -100% MCR

    3.3Feed water temperature at Deaeratoroutlet

    C 158

  • 7/21/2019 Design Basis IMFA

    39/146

    POWER DIVISION THERMAX LIMITED

    Project Document Title Doc. No. Rev. Sheet

    2 x 60 MW THERMAL

    POWER PLANT, IMFA,

    ORISSA

    DESIGN BASIS REPORT

    MECHANICALPP 067 M B01 0 1 39

    3. 100 % Washery rejects.

    The boiler is designed and manufactured as per Indian Boiler Regulations

    (IBR) codes. All the requirement of IBR will be taken care for safe operation of

    boiler. The pressure part materials will be as per IBR codes and standard. Piping

    design will be as per IBR / ASME B31.1 (latest addition). The calculations of all

    pressure parts will be submitted to the Chief Inspector of Boilers for their approval.

    Major boiler parts can be described as Pressure retaining parts (steam and

    water circuit), Bunker and fuel feeding equipments, Air-preheater and air ducting

    component, Flue gas system, Boiler supporting structure and platforms, Hoppersand fly ash system.

    The complete furnace section will be of fusion welded wall type arranged as

    a gas and pressure tight envelope. The circulation system will be complete with

    the necessary number of down comers, supply and riser tubes piping. Steam

  • 7/21/2019 Design Basis IMFA

    40/146

    POWER DIVISION THERMAX LIMITED

    Project Document Title Doc. No. Rev. Sheet

    2 x 60 MW THERMAL

    POWER PLANT, IMFA,

    ORISSA

    DESIGN BASIS REPORT

    MECHANICALPP 067 M B01 0 1 40

    pressure. The boiler is provided with necessary access platform, galleries and

    stair case to approach all equipments and pressure part. The boiler top is well

    enclosed by canopy with side sheeting / lovers up to drum level. The required

    structural supporting steelwork for the boiler, galleries, staircases and outer casing

    will be provided for the boiler, auxiliaries, ducting etc.

    The boiler has been provided with three storage bunkers for application of

    coal (as a main fuel), lime stone (an additive) and bed material.

    The fuel feeding system will consist of drag chain feeders and fuel feed

    lines. The fluidised bed is located at the bottom most part of the furnace.

    The boiler will be provided with two nos. (2 x 60% MCR) ID, SA and PA

    fans and the complete air and gas ducting with required dampers and expansion

    joints. All the fans will be provided with variable speed fluid coupling.

    The feed water system will consist of three (3) nos (3 x 100 %) motor

  • 7/21/2019 Design Basis IMFA

    41/146

    POWER DIVISION THERMAX LIMITED

    Project Document Title Doc. No. Rev. Sheet

    2 x 60 MW THERMAL

    POWER PLANT, IMFA,

    ORISSA

    DESIGN BASIS REPORT

    MECHANICALPP 067 M B01 0 1 41

    7.2.2. STEAM DRUM

    Steam drum will be of welded construction, completely radiographed to

    prove weld soundness, stress relieved and hydraulically tested. The boiler quality

    plate for the drums will be fabricated to the appropriate specification and

    constructed in accordance with the codes and regulations of Indian Boiler

    Regulations.

    Drum will be provided with suitable hemispherical dished ends and

    manholes, each with a swing type cover opening internally.

    The steam drum will be of fusion welded construction, with material

    specification conforming to SA 516 Gr. 70. The steam drum will have nozzles for

    saturated steam supply pipes to Primary super heater inlet headers, Feed water

    inlet piping from economiser, water level gauges, pressure gauges, continuous

    blow-down and intermittent blow down, chemical injection, sampling, air vent etc.

  • 7/21/2019 Design Basis IMFA

    42/146

    POWER DIVISION THERMAX LIMITED

    Project Document Title Doc. No. Rev. Sheet

    2 x 60 MW THERMAL

    POWER PLANT, IMFA,

    ORISSA

    DESIGN BASIS REPORT

    MECHANICALPP 067 M B01 0 1 42

    Beams are supported by bolts through water cooled roof.

    7.2.3.2. Divisional Wall

    Divisional wall is placed in the furnace. Divisional wall is of carbon steel

    construction and is a water cooled part of the boilers. This is located in the furnace

    and helps is achieving / maintaining the combustor temperature.

    7.2.3.3. Headers

    The headers will be of adequate size and design in accordance with Indian

    Boiler Regulations, and the material specification will conform to SA 106

    Gr. B / SA 335 Gr. P11 / SA 335 Gr. P22 depending on the fluid temperature. The

    necessary drain connections and hand-holes will be provided as required.

    The connections to the steam drum and the connections to the headers will

    be designed so as to form an integral circuit providing adequate natural circulation

    under all operating conditions

    POWER DIVISION THERMAX LIMITED

  • 7/21/2019 Design Basis IMFA

    43/146

    POWER DIVISION THERMAX LIMITED

    Project Document Title Doc. No. Rev. Sheet

    2 x 60 MW THERMAL

    POWER PLANT, IMFA,

    ORISSA

    DESIGN BASIS REPORT

    MECHANICALPP 067 M B01 0 1 43

    water line before the feed water control station.

    7.2.6. ECONOMISER

    The economiser will be made of bare carbon steel tubes conforming to SA

    210 Gr A1 seamless and of continuous inline type with inlet and outlet headers. Itwill be supported in a structural steel frame and enclosed within welded steel

    casing. Doors will be provided for observation and also access for maintenance.

    The economiser will be of non-steaming type. Temperature of economiser shall

    always below the saturated steam temperature.

    Necessary drains, vents, temperature, pressure gauges, etc. shall be

    furnished as per Indian Boiler Regulation requirement.

    7.3. BOILER PERFORMANCE DATA

    7.3.1. PRESSURE PART DETAILS

    POWER DIVISION THERMAX LIMITED

  • 7/21/2019 Design Basis IMFA

    44/146

    POWER DIVISION THERMAX LIMITED

    Project Document Title Doc. No. Rev. Sheet

    2 x 60 MW THERMAL

    POWER PLANT, IMFA,

    ORISSA

    DESIGN BASIS REPORT

    MECHANICALPP 067 M B01 0 1 44

    Tube OD mm 44.45

    Tube thickness mmAs per IBR calculation.

    Min. 4.06

    Tube material SA213 GR. T22 / SA213GR. T11 / SA210 GR. A1

    Header size NB 200 / 250

    Header thickness mmAs per IBR code

    calculation.

    Header material SA 106 GR.B / SA 335GR. P11

    Secondary Superheater

    Descript ion Unit Value

    POWER DIVISION THERMAX LIMITED

  • 7/21/2019 Design Basis IMFA

    45/146

    POWER DIVISION THERMAX LIMITED

    Project Document Title Doc. No. Rev. Sheet

    2 x 60 MW THERMAL

    POWER PLANT, IMFA,

    ORISSA

    DESIGN BASIS REPORT

    MECHANICALPP 067 M B01 0 1 45

    Tube material SA210 GR. A1

    Header size NB 200

    Header thickness mm As per IBR calculation.

    Header material SA 106 GR.B

    At temperator

    Descript ion Unit Value

    Header size NB 200 / 250

    Header thickness mm As per IBR calculation.

    Header material SA106 GR.B

    Risers

    POWER DIVISION THERMAX LIMITED

  • 7/21/2019 Design Basis IMFA

    46/146

    POWER DIVISION THERMAX LIMITED

    Project Document Title Doc. No. Rev. Sheet

    2 x 60 MW THERMAL

    POWER PLANT, IMFA,

    ORISSA

    DESIGN BASIS REPORT

    MECHANICALPP 067 M B01 0 1 46

    2 Economiser m2 3561

    3 Airpreheater ( PA + SA ) m2 10003

    4Furnace (water walls +enclosure walls + divisionalwalls etc.)

    m2 1441

    7.3.3. TEMPERATURE GRADIENT

    Sl. No. Description Unit Value

    1 Combustion air side

    1.1 Air pre heater In Deg. C 35

    1.2 Air pre heater out Deg. C 140-150

    2 Flue gas temperatures

    2.1 Super heater In Deg. C 800-820

    POWER DIVISION THERMAX LIMITED

  • 7/21/2019 Design Basis IMFA

    47/146

    POWER DIVISION THERMAX LIMITED

    Project Document Title Doc. No. Rev. Sheet

    2 x 60 MW THERMAL

    POWER PLANT, IMFA,

    ORISSA

    DESIGN BASIS REPORT

    MECHANICALPP 067 M B01 0 1 47

    3.8 Sec. Super heater Out Deg. C 535-555

    3.9 Spray water temperature Deg. C 220-230

    4 Feed water temperature

    4.1 Economizer In Deg. C 220-230

    4.2 Economizer out Deg. C 290-310

    7.3.4. PRESSURE GRADIENT

    Sl. No. Description Unit Value

    1 Steam / water side pressure drop

    1.1 Sec superheater Kg/cm2 4.6

    1.2 Pri superheater Kg/cm2 0.95

    POWER DIVISION THERMAX LIMITED

  • 7/21/2019 Design Basis IMFA

    48/146

    POWER DIVISION THERMAX LIMITED

    Project Document Title Doc. No. Rev. Sheet

    2 x 60 MW THERMAL

    POWER PLANT, IMFA,

    ORISSA

    DESIGN BASIS REPORT

    MECHANICALPP 067 M B01 0 1 48

    1.4 Airpreheater m/s 11-13

    2 Air

    2.1 Airpreheater m/s 10-12

    7.3.6. SAFETY VALVE DETAILS

    7.3.6.1. Safety Valve Set Pressures

    Sl. No. Description Unit Value

    1

    1stdrum safety valve set

    pressure Kg/cm2 (g) 119

    2 2nddrum safety valve setpressure

    Kg/cm2 (g) 120

    3Superheater safety valveset pressure

    Kg/cm2 (g) 108

    POWER DIVISION THERMAX LIMITED

  • 7/21/2019 Design Basis IMFA

    49/146

    POWER DIVISION THERMAX LIMITED

    Project Document Title Doc. No. Rev. Sheet

    2 x 60 MW THERMAL

    POWER PLANT, IMFA,

    ORISSA

    DESIGN BASIS REPORT

    MECHANICALPP 067 M B01 0 1 49

    1.2 ROM coal Kg/hr 51564

    1.3 Washery rejects Kg/hr 88746

    2 Limestone

    2.1 Performance fuel case Kg/hr 4030

    2.2 ROM coal Kg/hr 3430

    2.3 Washery rejects Kg/hr 4780

    3 Bed material Kg/hr Nil

    7.4. BOILER MOUNTINGS AND FITTINGS

    The Boiler will be provided with a complete set of mountings and fittings in

    accordance with the Indian Boiler Regulations, for the safe operation of the Boiler

    and the details of the mountings and fittings including:

    POWER DIVISION THERMAX LIMITED

  • 7/21/2019 Design Basis IMFA

    50/146

    POWER DIVISION THERMAX LIMITED

    Project Document Title Doc. No. Rev. Sheet

    2 x 60 MW THERMAL

    POWER PLANT, IMFA,

    ORISSA

    DESIGN BASIS REPORT

    MECHANICALPP 067 M B01 0 1 50

    7.4.4. SUPERHEATER

    -Safety valve (secondary outlet)

    -Motor operated main steam stop valve with integral by-pass valve

    -Steam outlet check valve

    -Start-up vent will be sized for 30% of BMCR capacity.

    -Pressure gauges with isolation valves and drain valves

    -Sampling valves

    -Drain valves

    -Air vent valves

    -Valves for pressure transmitters and flow transmitters

    -Main steam flow nozzle

    -Thermocouples

    7.4.5. SPRAY WATER LINE

    POWER DIVISION THERMAX LIMITED

  • 7/21/2019 Design Basis IMFA

    51/146

    Project Document Title Doc. No. Rev. Sheet

    2 x 60 MW THERMAL

    POWER PLANT, IMFA,

    ORISSA

    DESIGN BASIS REPORT

    MECHANICALPP 067 M B01 0 1 51

    100 % ROM Coal.

    100 % Washery rejects.

    7.5.1. FUEL BUNKER

    Each boiler will be provided with following bunker of mild steel construction.

    Fuel bunker 1600 m3

    Lime stone silo 120 m3

    Bed material silo 80 m3

    Fuel Bunker sizing basis

    Sl.No.

    Description Basis ofDesign

    Consumptionof Material perBoi ler, TPH

    BunkerCapacityRequired,m3

    BunkerVolumeProvided,m3

    a) Fuel bunker 50 % WasheryRejects + 50

    Consumption offuel at 100%

    64.42 TPHx 16 Hrs /

    1600 m3(Bunker

    POWER DIVISION THERMAX LIMITED

  • 7/21/2019 Design Basis IMFA

    52/146

    Project Document Title Doc. No. Rev. Sheet

    2 x 60 MW THERMAL

    POWER PLANT, IMFA,

    ORISSA

    DESIGN BASIS REPORT

    MECHANICALPP 067 M B01 0 1 52

    For each boiler there are separate bunkers. Fuel is fed into drag chain

    feeder. The drag chain feeder speed is controlled through VFD. The outlet of drag

    chain feeder is connected to the furnace.

    7.5.3. FLUIDIZED BED

    The fluidised bed will consist of compartments (sections). Each

    compartment will be provided with stainless steel fuel feeding nozzles and

    adequate number of stainless steel fluidizing air nozzles fitted on to the distributor

    plate.

    7.6. OIL FIRING SYSTEM

    Three (3) nos. of burners will be installed in the front side of the furnace

    panel. Burner will be used for start-up of the boiler. Burner support will be required

    till 20% of boiler loading. Each Burner will be 1500 litre capacity and combined

    POWER DIVISION THERMAX LIMITED

  • 7/21/2019 Design Basis IMFA

    53/146

    Project Document Title Doc. No. Rev. Sheet

    2 x 60 MW THERMAL

    POWER PLANT, IMFA,

    ORISSA

    DESIGN BASIS REPORT

    MECHANICALPP 067 M B01 0 1 53

    guard. The impeller is provided with tip liners and dynamically

    balanced. ID fan will be with inlet damper (multilouver) control. ID fan

    shall be with variable speed fluid coupling.

    Two (2) Secondary Air (SA) fan of 60% boiler MCR capacity supplying

    the necessary amount of combustion air for fluidised bed combustion of

    the different fuels with sufficient pressure to overcome the resistance of

    ducts, measuring devices, dampers, fluidising air nozzles, air heater

    and burners. The SA fan is centrifugal type with suitably sized impeller.

    The fan impeller shall be dynamically balanced and is complete with

    inspection door, foundation bolts and guard. The SA fan shall be

    provided with silencer to meet the noise level. The control shall be

    through Inlet Guide vane. SA fan shall be with variable speed fluid

    coupling.

    Two (2) Primary Air (PA) fan of 60% boiler MCR capacity boosting hot

    POWER DIVISION THERMAX LIMITED

  • 7/21/2019 Design Basis IMFA

    54/146

    Project Document Title Doc. No. Rev. Sheet

    2 x 60 MW THERMAL

    POWER PLANT, IMFA,

    ORISSA

    DESIGN BASIS REPORT

    MECHANICALPP 067 M B01 0 1 54

    d) Ambient temp. C 50 35 35 35

    e) Back end temp. C 160 140 140 140

    f) ID fan gas Qty kg/s 56.42 52.27 56.42 49.46

    g)Margin onCapacity

    % 20

    h) ID fan Capacity kg/s 67.7

    II) Head Details

    a) dP SH mmWC 15 12 15 12

    b) dP economiser mmWC 20 17 20 15

    c) dP APH mmWC 60 50 60 44

    d) dP ESP + MDC+ U Beam

    mmWC 140 117 140 101

    e)dP Ducts +Dampers

    mmWC 25 21 25 20

    f) Chi WC 10 8 10 8

    POWER DIVISION THERMAX LIMITED

  • 7/21/2019 Design Basis IMFA

    55/146

    Project Document Title Doc. No. Rev. Sheet

    2 x 60 MW THERMAL

    POWER PLANT, IMFA,

    ORISSA

    DESIGN BASIS REPORT

    MECHANICALPP 067 M B01 0 1 55

    h) SA fan Capacity kg/s 19.78

    II) Head Details

    a) dP Bed mmWC 430 430 388 421

    b) dP flowmeasuring +OFA + Duct andDamper +Silencer

    mmWC 560 533 560 522

    c) dP APH mmWC 50 47 50 47

    d) Total dP mmWC 1040 1010 1000 990

    e) Margin on head

    (only on variablehead)

    % 45

    f) SA fan Head mmWC 1375

    C) PA Fan ( 2 X 60 % MCR)

    POWER DIVISION THERMAX LIMITED

  • 7/21/2019 Design Basis IMFA

    56/146

    Project Document Title Doc. No. Rev. Sheet

    2 x 60 MW THERMAL

    POWER PLANT, IMFA,

    ORISSA

    DESIGN BASIS REPORT

    MECHANICALPP 067 M B01 0 1 56

    Silencer + Ductand Damper

    c) dP APH mmWC 60 54 60 53

    d) dP bubble cap mmWC 400 360 400 351

    e) Total dP mmWC 1585 1440 1460 1420

    f) Margin on head

    (only on variablehead)

    % 45

    g) SA fan Head mmWC 1920

    7.7.2. DUCTWORK AND DAMPERS

    Ducts will be sized considering a maximum velocity of 14 m/sec for air and

    12 m/sec upto Air Pre-heater & 16 m/sec after Air Pre-heater for flue gas

    applications. The ducts will be rectangular in cross section and will be of welded

    construction, properly stiffened and reinforced. All ducts handling air and flue gas

    will be fabricated with carbon steel plates of thickness not less than 5 mm for air

    POWER DIVISION THERMAX LIMITED

  • 7/21/2019 Design Basis IMFA

    57/146

    Project Document Title Doc. No. Rev. Sheet

    2 x 60 MW THERMAL

    POWER PLANT, IMFA,

    ORISSA

    DESIGN BASIS REPORT

    MECHANICALPP 067 M B01 0 1 57

    7.7.3. AIR PRE-HEATER

    A tubular air pre-heater is provided as the last stage of heat recovery unit.

    The shell and tube side fluid shall be combustion air and flue gas respectively.

    The air pre heater tubes shall be fitted into the tube sheets on both sides. Entire

    Air Pre-heater shall be supported in a structural steel frame and enclosed within

    welded steel casing. Air Pre-heater shall be provided with BS 6323 / 82 Part V ERW

    tubes.

    The clean air passes through tubes and those tubes are surrounded by hot

    flue gases which help to increase the temperature of air. This hot air is used in

    boiler to help combustion process.

    7.7.4. ASH RECYCLE SYSTEM

    Mechanical Dust Collector (MDC) is positioned in the exit of Economiser.

    Th h ll t d i th MDC ill b l d th h th

    POWER DIVISION THERMAX LIMITED

  • 7/21/2019 Design Basis IMFA

    58/146

    Project Document Title Doc. No. Rev. Sheet

    2 x 60 MW THERMAL

    POWER PLANT, IMFA,

    ORISSA

    DESIGN BASIS REPORT

    MECHANICALPP 067 M B01 0 1 58

    7.8. BOILER STRUCTURES AND AUXILIARIES

    7.8.1. STRUCTURAL STEEL

    The complete structural steel necessary to support/suspend the various

    components and equipment, ducts etc. will include all auxiliary columns, duct

    supporting columns, bracing, and all equipment structures etc. The structure is of

    fully welded construction. Only for erection purpose, erection bolts are provided.

    All structural steel will be designed for horizontal seismic forces as applicable

    under the latest Revision of IS 1893 and wind forces as per latest revision of IS

    875, whichever governs the design. All structural steel work will be designed as

    per IS 800 and material specification conforming to IS 2062. The structure will

    incorporate necessary lifting beams and hoist blocks required for maintenance of

    fans, pumps etc.

    7.8.2. PLATFORM,STAIRWAYS AND GRATING

    POWER DIVISION THERMAX LIMITED

    P j D Ti l D N R Sh

  • 7/21/2019 Design Basis IMFA

    59/146

    Project Document Title Doc. No. Rev. Sheet

    2 x 60 MW THERMAL

    POWER PLANT, IMFA,

    ORISSA

    DESIGN BASIS REPORT

    MECHANICALPP 067 M B01 0 1 59

    7.9.2. DESIGN TEMPERATURE DIFFERENTIAL -CRITERIA

    The thickness of wool mattress will be calculated such that insulation

    surface temperature shall remain within 65OC at an ambient temperature 35OC

    with 1 m/s wind velocity. Insulation will be provided for equipment and ducts

    where the temperature exceeds 60OC.

    7.9.3. EXTERNAL INSULATION

    The machine made mineral wool mattresses will be used as external

    insulating layer and will have a uniform density of 120 kg/m3. The mineral wool

    specifications and thermal conductivity figures will be as per IS: 8183.

    The wire netting to be provided on both sides of mattresses will be of GI /

    SS material.

    7.9.4. BINDING AND STITCHING WIRE

    POWER DIVISION THERMAX LIMITED

    P j t D t Titl D N R Sh t

  • 7/21/2019 Design Basis IMFA

    60/146

    Project Document Title Doc. No. Rev. Sheet

    2 x 60 MW THERMAL

    POWER PLANT, IMFA,

    ORISSA

    DESIGN BASIS REPORT

    MECHANICALPP 067 M B01 0 1 60

    etc.

    7.11. SAMPLING LINES

    The sampling lines and sample coolers will be provided for feed water,

    drum water, saturated steam and superheated steam. Sampling lines andnozzles will be of suitable material to take care of high chloride content in

    circulating water.

    7.12. BLOW DOWN TANKS

    One (1) continuous blow down (CBD) tank and one (1) intermittent blow

    down (IBD) tank of appropriate capacity, separate for each boiler, shall be

    provided to receive all the continuous and intermittent blow downs and all other

    drain discharges from the boilers. Necessary level control station for the

    continuous blow down tank along with other fittings shall be provided.

    POWER DIVISION THERMAX LIMITED

    Project Doc ment Title Doc No Re Sheet

  • 7/21/2019 Design Basis IMFA

    61/146

    Project Document Title Doc. No. Rev. Sheet

    2 x 60 MW THERMAL

    POWER PLANT, IMFA,

    ORISSA

    DESIGN BASIS REPORT

    MECHANICALPP 067 M B01 0 1 61

    1 Design flue gas flow m3/sec 124 134 117

    2 Flue gas temperature oC 140 140 140

    3 Gas Analysis (wet)

    CO2 % v./v. 13.31 12.62 13.70

    H2O % v./v. 14.07 16.16 12.87

    N2 % v./v. 69.54 68.20 70.32

    O2 % v./v. 3.06 3.00 3.1

    SO2 % v./v. 0.0064 0.0074 0.0056

    4Gas density (wetbasis)

    Kg/Nm3 1.2875 1.2732 1.2957

    5 Dust concentration atESP inlet (wet)

    gm/Nm3 70 70 70

    POWER DIVISION THERMAX LIMITED

    Project Document Title Doc No Rev Sheet

  • 7/21/2019 Design Basis IMFA

    62/146

    Project Document Title Doc. No. Rev. Sheet

    2 x 60 MW THERMAL

    POWER PLANT, IMFA,

    ORISSA

    DESIGN BASIS REPORT

    MECHANICALPP 067 M B01 0 1 62

    Stack emission shall be monitored to satisfy the requirements of Orissa Pollution

    Control Board.

    The design data for the chimney shall be as per the table below :

    7.14.1. CALCULATION OF CHIMNEY HEIGHT

    Sl. No. Particulars Units Value

    1 Coal Consumption per Boiler Kg/Hr 64420

    2 Sulphur Percentage % 0.34

    3 Total Sulphur from Fuel Kg/Hr 219.0

    4 Percentage Sulphur capture % 89.65 Sulphur at Stack Kg/Hr 22.7

    6 SO2 From Fuel Combustion Kg/Hr 45.5

    7 Stack height required m 44.0

    7.14.2. CALCULATION OF CHIMNEY DIAMETER

    POWER DIVISION THERMAX LIMITED

    Project Document Title Doc No Rev Sheet

  • 7/21/2019 Design Basis IMFA

    63/146

    Project Document Title Doc. No. Rev. Sheet

    2 x 60 MW THERMAL

    POWER PLANT, IMFA,

    ORISSA

    DESIGN BASIS REPORT

    MECHANICALPP 067 M B01 0 1 63

    7.14.3. SKETCH OF CHIMNEY

    POWER DIVISION THERMAX LIMITED

    Project Document Title Doc. No. Rev. Sheet

  • 7/21/2019 Design Basis IMFA

    64/146

    Project Document Title Doc. No. Rev. Sheet

    2 x 60 MW THERMAL

    POWER PLANT, IMFA,

    ORISSA

    DESIGN BASIS REPORT

    MECHANICALPP 067 M B01 0 1 64

    Following tapping point will be provided in main steam line

    a. For steam jet air ejector and turbine gland auxiliary PRDS.

    b. For turbine bypass system (sized for 60% TMCR flow).

    c. For deaerator pegging steam line.

    Suitable drain and vent connections shall be provided between

    isolation valves of each boiler in line with IBR requirements. These

    drain / vent isolation valves shall be manually operated.

    Each boiler superheater outlet would be provided with superheater

    safety valve and electromatic relief valve for over-pressure protection

    of boiler superheater. Start-up vent valveof 30% BMCR flow capacity

    is also provided.

    (B) Auxiliary steam system for steam jet air ejector & turb ine gland

    sealing steam system

    POWER DIVISION THERMAX LIMITED

    Project Document Title Doc. No. Rev. Sheet

  • 7/21/2019 Design Basis IMFA

    65/146

    Project Document Title Doc. No. Rev. Sheet

    2 x 60 MW THERMAL

    POWER PLANT, IMFA,

    ORISSA

    DESIGN BASIS REPORT

    MECHANICALPP 067 M B01 0 1 65

    (D) MP steam system for Deaerator

    From steam turbine, 3rd bleed with pressure around 6.6 kg/cm2 (a) will

    be taken for deaerator. This line will be provided with pneumatic

    operated quick closing non-return valve (QCNRV), normal non-return

    valve and motor operated valve. Pegging steam line from main steam

    will also be connected to this bleed line through a PRDS station for

    pegging of deaerator during start-up and low load.

    (E) LP steam system for LP heater

    Two (2) nos. low pressure bleeds with pressure at around 2.5 kg/cm2

    (a) & 0.735 kg/cm2 (a) will be taken for LP heaters. These lines will be

    provided with pneumatic operated quick closing non-return valve

    (QCNRV) and motor operated valve except low pressure line which will

    be provided with normal non-return valve.

    POWER DIVISION THERMAX LIMITED

    Project Document Title Doc. No. Rev. Sheet

  • 7/21/2019 Design Basis IMFA

    66/146

    j

    2 x 60 MW THERMAL

    POWER PLANT, IMFA,

    ORISSA

    DESIGN BASIS REPORT

    MECHANICALPP 067 M B01 0 1 66

    vents shall be provided with manually operated double isolation valves.

    8.1.1. CONTROL PHILOSOPHY

    Steam Temperature & pressure will be maintained by combustion control

    loop and attemperator in the respective boiler. The control range for temperature,

    as indicated earlier, is 60 100 % for the individual boilers for 100% coal firing. In

    the event of load throw-off, the main steam line pressure will tend to increase

    which will activate turbine bypass control valve and excess steam (maximum 60%

    of TMCR) will be bypassed to surface condenser. At the same time the

    combustion control loop of boiler will also activate and once the same is stabilised

    turbine bypass system will close.

    8.2. FEED WATER SYSTEM

    The feed water system will supply feed water to each boiler. It will also

    POWER DIVISION THERMAX LIMITED

    Project Document Title Doc. No. Rev. Sheet

  • 7/21/2019 Design Basis IMFA

    67/146

    j

    2 x 60 MW THERMAL

    POWER PLANT, IMFA,

    ORISSA

    DESIGN BASIS REPORT

    MECHANICALPP 067 M B01 0 1 67

    The deaerator-cum-storage tank unit will be complete with necessary

    internal trays, water sprays, water level control system, temperature control

    system, safety valve, water level indicator and alarm, access ladders and

    platforms.

    Chemical dosing would be performed inside the deaerator by means of

    sparger pipe inside the storage tank.

    Steam for heating will be supplied from the extraction of steam turbine.

    Provision will also be made for supply of steam from the main steam line through

    a system of pressure reducing valve and utilising flash steam from continuous

    blow-down tank. The oxygen content on the outlet water will be not more than

    0.007 ppm.

    Details of Deaerator & Feed water storage tank is as follows.

    POWER DIVISION THERMAX LIMITED

    Project Document Title Doc. No. Rev. Sheet

  • 7/21/2019 Design Basis IMFA

    68/146

    2 x 60 MW THERMAL

    POWER PLANT, IMFA,

    ORISSA

    DESIGN BASIS REPORT

    MECHANICALPP 067 M B01 0 1 68

    8.2.2. BOILER FEED PUMPS

    Boiler feed water pumping system with 3 x 100% motor driven boiler feed

    water pumps is provided. Out of these three pumps, one will be operating

    normally for each boiler unit while the third pump shall remain as a common

    standby and will come into operation automatically in case one of the working

    pump fails.

    Variable speed hydraulic coupling is provided to vary the speed of the feed

    pump smoothly and stably over the entire range to minimise the throttling losses in

    feed control valves.

    Three (3) nos. motor driven boiler feed pumps with all pipe works and

    valves will be supplied for the boilers. The pumps will be identical and

    interchangeable. The pump will be of multistage centrifugal type, complete with

    suction strainer, balance chamber and necessary suction and delivery valves,

    POWER DIVISION THERMAX LIMITED

    Project Document Title Doc. No. Rev. Sheet

  • 7/21/2019 Design Basis IMFA

    69/146

    2 x 60 MW THERMAL

    POWER PLANT, IMFA,

    ORISSA

    DESIGN BASIS REPORT

    MECHANICALPP 067 M B01 0 1 69

    margin will be provided on head calculated based on 2nd drum safety valve set

    pressure. With such margin, it shall be checked and ensured that even at 47.5 Hz

    frequency the boiler feed water pump is capable of delivering 100 % TMCR flow

    rate and required head during TMCR operation of unit. The BFP sizing basis is as

    follows.

    a) Pump Capacity Calculation

    Feed water flow at BMCR240 TPH

    As per boiler datasheet

    Feed water density at 158Ctemperature

    909.4 kg/m3 As per HBD

    MCR volume flow 263.9 m3/hr

    MCR volume flow with 3% make-up 271.8 m3/hr

    Margin 10% 27.2 m3/hr

    C l l d fl 299 3/h

    POWER DIVISION THERMAX LIMITED

    Project Document Title Doc. No. Rev. Sheet

  • 7/21/2019 Design Basis IMFA

    70/146

    2 x 60 MW THERMAL

    POWER PLANT, IMFA,

    ORISSA

    DESIGN BASIS REPORT

    MECHANICALPP 067 M B01 0 1 70

    Suction pressure (H) 7.8 kg/cm2 (a)As per HBD &prelim. equipmentlayout

    Required TDH in water column (G-H/ density)

    1375 mWC

    Required Rated Head (includingMargin 5%)

    1444 mWC

    Selected Rated Head 1495 mWC

    8.2.3. HPFEED WATER HEATERS

    Two (2) nos. HP heaters will be located on the down stream side of boilerfeed pumps and will be used for raising the boiler feed water temperature to

    230oC. The HP heater shall be mounted vertically in the turbine house. The

    heating steam for the HP heaters shall be supplied from the high pressure turbine

    bleeds. The normal condensate drain from the HP heater shall cascaded back to

    POWER DIVISION THERMAX LIMITED

    Project Document Title Doc. No. Rev. Sheet

  • 7/21/2019 Design Basis IMFA

    71/146

    2 x 60 MW THERMAL

    POWER PLANT, IMFA,

    ORISSA

    DESIGN BASIS REPORT

    MECHANICALPP 067 M B01 0 1 71

    % capacity pneumatically operated control valve is provided to control the feed

    water flow at low load. Full load control valve shall be operated through single

    element or three element control mode. Low load control valve shall be operated

    in single element mode. The upstream isolation valves for the control stations are

    motorised for automatic changeover.

    In order to avoid excessive throttling and power loss at feed control station,

    the differential pressure across feed control valves under steady state shall be

    maintained at a constant value by varying hydraulic coupling of boiler feed pump.

    HP heater shell side level is maintained by a control station leading the

    condensate to the earlier HP heater or deaerator. In case of deaerator high level

    or at low load & starting, this condensate will be diverted to the HP flash tank

    through another control station.

    In case of very high level in the shell, extraction steam line motorised valve

    POWER DIVISION THERMAX LIMITED

    Project Document Title Doc. No. Rev. Sheet

  • 7/21/2019 Design Basis IMFA

    72/146

    2 x 60 MW THERMAL

    POWER PLANT, IMFA,

    ORISSA

    DESIGN BASIS REPORT

    MECHANICALPP 067 M B01 0 1 72

    cooled surface condenser. Drain condensate from LP heaters, GSC and inter-

    after ejector condensers are taken to the flash pipe of the condenser.

    8.3.1. SURFACE CONDENSER

    The condenser shall condense all the steam at the steam turbine exhaust,

    and shall receive all the condensate from the steam jet ejector condensers, gland

    steam condenser and LP heaters. At an emergency condition of very high level in

    HP heater, the condensate drain will be diverted to condenser through HP flash

    tank instead of the deaerator. A flash pipe mounted near the condenser will

    receive all the drains. The vent and drain from the HP flash tank and flash pipe will

    be connected to the shell and hotwell of the condenser respectively.

    The condenser shall be designed as per Heat Exchanger Institute (HEI)

    standard for surface condensers.

    The condenser shall be of horizontal two-pass type and shall be so

    POWER DIVISION THERMAX LIMITED

    Project Document Title Doc. No. Rev. Sheet

  • 7/21/2019 Design Basis IMFA

    73/146

    2 x 60 MW THERMAL

    POWER PLANT, IMFA,

    ORISSA

    DESIGN BASIS REPORT

    MECHANICALPP 067 M B01 0 1 73

    maintenance. Condenser (tube side) shall be hydro-statically tested according to

    the Heat Exchange Institute Standards.

    Condenser water box shell shall be of carbon steel (SA 516 Gr. 70)

    material. Condenser tube sheet shall be of carbon steel (SA 516 Gr. 70) material.

    Suitable drain and vent connections complete with necessary valve shall be

    provided for all the water boxes to obtain a smooth flow path in the water boxes

    and even water distribution to the tubes and to avoid any unvented air pockets.

    The condenser shall be provided with a hotwell made of carbon steel (SA

    516 Gr. 70) having a total storage capacity of at least three (3) minutes of the totaldesign condensate flow (between normal and low level) at maximum steam load

    condition. The hotwell shall be provided with suitable access doors. Drain valves

    with blind flanges shall be provided on hotwell.

    A rupture disc designed as per manufacturers standard shall be provided

    POWER DIVISION THERMAX LIMITED

    Project Document Title Doc. No. Rev. Sheet

  • 7/21/2019 Design Basis IMFA

    74/146

    2 x 60 MW THERMAL

    POWER PLANT, IMFA,

    ORISSA

    DESIGN BASIS REPORT

    MECHANICALPP 067 M B01 0 1 74

    Cooling water temperature(inlet / outlet)

    33 C / 42 C

    Cleanliness factor 85 %

    Plugging margin 3 %

    Condenser heat load

    (corresponding to VWOoperation)

    87142367 Kcal/hr

    Surface area 4900 m2

    Hotwell capacity 3 minutes storage of the totaldesign condensate flow betweennormal level to low level atmaximum steam load condition

    Material of Construction :

    Shell Carbon steel (SA 516 Gr. 70)

    Tube sheet Carbon steel (SA 516 Gr. 70)

    Hot-well Carbon steel (SA 516 Gr. 70)

    T b St i l t l (SS 304)

    POWER DIVISION THERMAX LIMITED

    Project Document Title Doc. No. Rev. Sheet

  • 7/21/2019 Design Basis IMFA

    75/146

    2 x 60 MW THERMAL

    POWER PLANT, IMFA,

    ORISSA

    DESIGN BASIS REPORT

    MECHANICALPP 067 M B01 0 1 75

    condenser are provided. Each service air ejector is of two stages with an inter-

    condenser between the Ist and IInd stage and an after-condenser located after

    the IInd stage. The condensate from the inter-condenser and after-condenser is

    led to the main condenser through a loop seal and trap station respectively.

    Condensate from the CEP discharge passes through the tube side of the inter and

    after-condensers.

    The following are the brief details of the Ejectors: -

    No. of ejectors Service - Two (1 W + 1 S)

    Start up One (1)

    Design CalculationsStandard

    HEI

    Location Indoor

    Medium to be handledMixture of air, steam and non-condensable gases

    C li M di C d t

    POWER DIVISION THERMAX LIMITED

    Project Document Title Doc. No. Rev. Sheet

  • 7/21/2019 Design Basis IMFA

    76/146

    2 x 60 MW THERMAL

    POWER PLANT, IMFA,

    ORISSA

    DESIGN BASIS REPORT

    MECHANICALPP 067 M B01 0 1 76

    Condenser hotwell level is very low.

    Motor is overloaded.

    The standby pump will come on auto if:

    Running pump trips.

    Discharge header pressure drops below a predetermined value as sensed

    by a pressure switch.

    In order to prevent the operation of the CEP on shut off head and to ensure

    minimum flow through the inter/after ejector condenser and gland steam

    condenser, a minimum flow recirculation facility is provided for the CEP. This

    consists of a control valve and CEP discharge flow transmitter. The recirculation

    flow is routed back to the condenser hotwell.

    The condensate outlet from the CEP is routed to the deaerator after

    POWER DIVISION THERMAX LIMITED

    Project Document Title Doc. No. Rev. Sheet

    2 60 MW THERMAL

  • 7/21/2019 Design Basis IMFA

    77/146

    2 x 60 MW THERMAL

    POWER PLANT, IMFA,

    ORISSA

    DESIGN BASIS REPORT

    MECHANICALPP 067 M B01 0 1 77

    b) Pump Head Calculation

    Deaerator safety valve setpressure (A)

    8 kg/cm2 (a)As per deaeratordata sheet

    Pressure drop at deaeratorspray water nozzle (B)

    0.75 kg/cm2As per deaeratordata sheet

    Pressure drop in Piping (C) 0.4 kg/cm2As per prelim.piping layout

    Pressure drop across flownozzle (D)

    0.2 kg/cm2 Estimated

    Pressure drop in LP heaters (E) 1.6 kg/cm2 As per LP heaterdata sheet

    Pressure drop in ejectorcondenser (F)

    0.5 kg/cm2 As per ejector datasheet

    Pressure drop GSC (G) 0.5 kg/cm2 As per GSC data

    POWER DIVISION THERMAX LIMITED

    Project Document Title Doc. No. Rev. Sheet

    2 60 MW THERMAL

  • 7/21/2019 Design Basis IMFA

    78/146

    2 x 60 MW THERMAL

    POWER PLANT, IMFA,

    ORISSA

    DESIGN BASIS REPORT

    MECHANICALPP 067 M B01 0 1 78

    8.3.4. LPFEED WATER HEATERS

    The LP heaters will be located on the down stream side of condensate

    extraction pumps after gland steam condenser and will be used for raising the

    condensate water temperature to 123C. The LP heater shall be mounted

    vertically in the turbine house. The heating steam for the LP heater shall besupplied from the low pressure turbine bleeds. The normal condensate drain from

    the LP heater shall be cascaded back to earlier LP heater and then to the

    condenser. An emergency condensate drain of LP heater 1 is also provided

    directly to the condenser flash pipe. The condensate water side of the LP heater

    shall be designed to withstand the CEP shut-off pressure. The steam side of theLP heater shall be designed to suit the highest bleed steam pressure obtainable.

    The condensate water outlet from LP heater will be connected to the deaerator

    through level control station.

    POWER DIVISION THERMAX LIMITED

    Project Document Title Doc. No. Rev. Sheet

    2 x 60 MW THERMAL

  • 7/21/2019 Design Basis IMFA

    79/146

    2 x 60 MW THERMAL

    POWER PLANT, IMFA,

    ORISSA

    DESIGN BASIS REPORT

    MECHANICALPP 067 M B01 0 1 79

    Cooling media Condensate

    8.3.6. MAKE-UP WATER

    The normal DM water make up to the power cycle shall account for the loss

    of water from the system due to blowdown from the boilers (considered @ 1 %normal & 3 % maximum), loss of steam from service air ejectors, deaerator losses

    and leakage of water from the system. DM water from DM water storage tank will

    be transferred to overhead condensate storage tank (CST) by DM water transfer

    pumps. Make-up for above losses is provided in condenser hotwell through gravity

    from this CST through a control valve. The control valve will be sized for 3 %make-up water requirement.

    8.3.7. CONTROL PHILOSOPHY

    Condenser hotwell level shall be maintained by regulating condensate flow

    POWER DIVISION THERMAX LIMITED

    Project Document Title Doc. No. Rev. Sheet

    2 x 60 MW THERMAL

  • 7/21/2019 Design Basis IMFA

    80/146

    2 x 60 MW THERMAL

    POWER PLANT, IMFA,

    ORISSA

    DESIGN BASIS REPORT

    MECHANICALPP 067 M B01 0 1 80

    9. WATER SYSTEM

    9.1. PLANT WATER SYSTEM

    9.1.1. RAW WATER SYSTEM &RAW WATER RESERVOIR

    Water from Mahanadi river will be pumped by means of raw water intake

    pumps to the raw water reservoir. The raw intake pumps and piping upto raw

    water reservoir are in Owners scope. The EPC contractors scope starts from the

    raw water reservoir.

    Raw Water Reservoir, for collection and storage of raw water, of total

    capacity 10,000 m3 in two (2) compartments along with gates and accessories

    shall be provided. Inside and bottom surface shall be lined with impermeable

    HDPE lining of thickness 1 mm. Design and construction of the reservoir shall be

    done in such a fashion that no water can escape from the reservoir through

    POWER DIVISION THERMAX LIMITED

    Project Document Title Doc. No. Rev. Sheet

    2 x 60 MW THERMAL

  • 7/21/2019 Design Basis IMFA

    81/146

    2 x 60 MW THERMAL

    POWER PLANT, IMFA,

    ORISSA

    DESIGN BASIS REPORT

    MECHANICALPP 067 M B01 0 1 81

    9.1.2. RAW WATER PRE-TREATMENT PLANT &CLARIFIED WATER TANK

    The water pre-treatment plant mainly comprises of cascade aeration cum

    stilling chamber (1 x 100 %), inlet channel with parshall flume (1 x 100 %), flash

    mixture (1 x 100 %), flocculation tank (1 x 100 %), Klari-tube settlers (2 x 100 %),

    sludge sump (1 x 100 %) and sludge transfer pumps (2 x 100 %).

    Various chemical preparation and injection systems in the raw water pre-

    treatment plant shall be designed generally based on the following guidelines:

    Alum : 60 ppm

    Polyelectrolyte : 1 ppm

    Sodium

    Hypochlorite

    : Equivalent to 5 ppm chlorine

    Chemical house to accommodate chlorination system, storage space for

    chemicals, chemical solution preparation tanks, dosing pumps, MCC, Control

    Room etc and all other accessories shall be provided

    POWER DIVISION THERMAX LIMITED

    Project Document Title Doc. No. Rev. Sheet

    2 x 60 MW THERMALS G AS S O

  • 7/21/2019 Design Basis IMFA

    82/146

    2 x 60 MW THERMAL

    POWER PLANT, IMFA,

    ORISSA

    DESIGN BASIS REPORT

    MECHANICALPP 067 M B01 0 1 82

    Clarified water pump house will also house fire water pumps. A dead

    capacity, as per the requirement of TAC, to supply firewater in case of emergency,

    will be kept below the minimum submergence level of clarified water storage tank.

    The clarified water storage tank shall meet the entire water requirement of

    the various power plant consumers like DM water, cooling tower make-up water,service water, potable water, fire water etc. The water balance diagram showing

    the water requirement by various consumers is attached in Annexure-II.

    9.1.3. MAIN COOLING TOWER MAKE-UP SYSTEM

    Make-up water needs to be supplied to the main cooling tower to recover

    the water lost in CT blowdown, evaporation & drift losses and SSF backwashing.

    This make-up water to main cooling tower is supplied by 2 x 100 % main CT make

    up pumps from the clarified water storage tank.

    The main cooling water make-up requirement has been calculated as

    POWER DIVISION THERMAX LIMITED

    Project Document Title Doc. No. Rev. Sheet

    2 x 60 MW THERMALDESIGN BASIS REPORT

  • 7/21/2019 Design Basis IMFA

    83/146

    POWER PLANT, IMFA,

    ORISSA

    DESIGN BASIS REPORT

    MECHANICALPP 067 M B01 0 1 83

    Capacity of pumps with 10% Margin : 380 m3/hr

    9.1.4. DMFEED-CUM-AUXILIARY COOLING TOWER MAKE-UP SYSTEM

    Make-up water needs to be supplied to the auxiliary cooling tower to

    recover the water lost in CT blowdown and evaporation & drift losses. This make-

    up water to auxiliary cooling tower is supplied by 3 x 50 % DM feed-cum-auxiliary

    CT make up pumps. A tapping is taken after dual media filter header to supply a

    better quality filtered water as a make-up to auxiliary cooling tower.

    The auxiliary cooling water make-up requirement has been calculated as

    follows:

    Auxiliary cooling water requirement for the

    auxiliary coolers

    : 1,976 m3/hr

    Cooling Range (from 40C to 33C) : 7 deg C

    POWER DIVISION THERMAX LIMITED

    Project Document Title Doc. No. Rev. Sheet

    2 x 60 MW THERMALDESIGN BASIS REPORT

  • 7/21/2019 Design Basis IMFA

    84/146

    POWER PLANT, IMFA,

    ORISSA

    DESIGN BASIS REPORT

    MECHANICALPP 067 M B01 0 1 84

    potable water + filter backwash water

    = 29 + 20.25 + 3 + 1.25

    = 53.5 m3/hr

    Number of DM feed-cum-auxiliary CT makepumps & DMF : 3 x 50 %

    Capacity of DM feed-cum-auxiliary CT makepumps & DMF with 10% Margin : 30 m3/hr

    9.1.5. DEMINERALIZATION WATER SYSTEM

    The filtered water from DMF is fed to a DM Plant (2 x 25 m3/hr capacity) to

    generate boiler quality water. A tapping is taken after duel media filters to store

    filtered water in a filtered water storage tank of capacity 40 m3. Potable water (3

    m3/hr) and backwashing water for DMF (1.25 m3/hr) will be fed from this filtered

    water storage tank.

    POWER DIVISION THERMAX LIMITED

    Project Document Title Doc. No. Rev. Sheet

    2 x 60 MW THERMALDESIGN BASIS REPORT

  • 7/21/2019 Design Basis IMFA

    85/146

    POWER PLANT, IMFA,

    ORISSA

    DESIGN BASIS REPORT

    MECHANICALPP 067 M B01 0 1 85

    Bed (MB) exchanger. Acid and alkali measuring tanks (common to both streams)

    with ejectors shall form part of the system to provide these chemicals for

    regeneration. Hydrochloric acid and sodium hydroxide shall be the chemicals

    used for this purpose.

    The DM Plant shall be designed to operate continuously for 18 hoursbefore regeneration of the exhausted resin in the ion exchangers. The

    regeneration of the exchangers shall be completed in a maximum period of 6

    hours. Regeneration water heater for regeneration of anion resins will be

    provided.

    The waste from the regenerated waste of DM plant shall be collected in

    drain pits near the vessels and routed through acid/alkali proof lined trenches to a

    neutralizing pit. Acid or alkali as required shall be dosed in this pit and the effluent

    shall be neutralized by recirculation before being pumped to the guard pond.

    POWER DIVISION THERMAX LIMITED

    Project Document Title Doc. No. Rev. Sheet

    2 x 60 MW THERMALDESIGN BASIS REPORT

  • 7/21/2019 Design Basis IMFA

    86/146

    POWER PLANT, IMFA,

    ORISSA

    DESIGN BASIS REPORT

    MECHANICALPP 067 M B01 0 1 86

    shall also be provided.

    Design quality of treated water at the DM Plant outlet shall be maintained

    with silica content maximum : 0.02 ppm and conductivity not to exceed 0.1

    micromho/cm.

    9.1.6. DMWATER DISTRIBUTION SYSTEM

    DM Water from the DM water storage tanks shall be pumped by 2 x 100%

    DM transfer (power cycle make-up) pumps of capacity 17 m/hr (with 10 % margin

    on cycle make-up water requirement i.e. 15.4 m/hr). Power cycle make-up pumps

    shall be located outdoor near the DM water storage tank. The DM water shall be

    stored in the Condensate Storage Tank (CST). The CST tank shall be horizontal

    cylindrical steel tank with capacity sufficient to hold 3% make-up water

    requirement of two (2) hours i.e. 30 m. The tank shall be designed as per IS:803

    and provided with inlet, outlet, drain, overflow and vent connections. Power cycle

    POWER DIVISION THERMAX LIMITED

    Project Document Title Doc. No. Rev. Sheet

    2 x 60 MW THERMALDESIGN BASIS REPORT

  • 7/21/2019 Design Basis IMFA

    87/146

    POWER PLANT, IMFA,

    ORISSA

    DESIGN BASIS REPORT

    MECHANICALPP 067 M B01 0 1 87

    Type of pump Horizontal centrifugal

    Location of pumps Near clarified water tank

    Capacity of each service water tank m 1 or 2 (as required)

    Selected pump capacity with margin m/hr 6

    Location of tank STG Building, DM plant

    building, Pre-treatmentplant building, ESPcontrol room-cum-compressor house, Ashhandling area etc.

    Distribution of service water from tank By gravity

    9.1.8. POTABLE WATER SYSTEM

    A tapping is taken after Duel media filters to store a filtered water in a

    filtered water storage tank of capacity 40 m3. The potable water treatment further

    comprises of dosing with sodium hypochlorite for chlorination. Two (2) nos. pumps

    f it 3 3/h h h ll b id d t t t bl t i t t

    POWER DIVISION THERMAX LIMITED

    Project Document Title Doc. No. Rev. Sheet

    2 x 60 MW THERMAL

    POWER PLANT IMFADESIGN BASIS REPORT

    PP 067 M B01 0 1 88

  • 7/21/2019 Design Basis IMFA

    88/146

    POWER PLANT, IMFA,

    ORISSA

    DESIGN BASIS REPORT

    MECHANICALPP 067 M B01 0 1 88

    house, Administrativebuilding, Medical building,canteen, store, workshopetc.

    Distribution of potable water from potablewater tank

    By gravity

    9.2. COOLING WATER SYSTEM

    9.2.1. MAIN COOLING WATER SYSTEM FOR CONDENSER

    9.2.1.1. System Description

    The main cooling water system will be used to cool the circulating water

    used for condensing steam in the surface condenser.

    Main cooling water system for surface condenser will be closed cycle

    cooling system employing a cooling tower common for two units, cooling water

    pumping system, CW treatment system and associated piping & valves.

    POWER DIVISION THERMAX LIMITED

    Project Document Title Doc. No. Rev. Sheet

    2 x 60 MW THERMAL

    POWER PLANT IMFADESIGN BASIS REPORT

    PP 067 M B01 0 1 89

  • 7/21/2019 Design Basis IMFA

    89/146

    POWER PLANT, IMFA,

    ORISSAMECHANICAL

    PP 067 M B01 0 1 89

    will be vertical turbine type pumps located in a pump house at the end of the fore

    bay. There will be a total of three (3) number of CW pumps, one will be working

    for each unit and the third will remain as common stand by. Overhead EOT c