19-May-2011, E3D Users' Meeting, Uppsala 1
Derek McKay-BukowskiVolunteer Project Engineer, with support fromSodankylä Geophysical Observatory and STFC
19-May-2011, E3D Users' Meeting, Uppsala 2
Derek McKay-BukowskiVolunteer Project Engineer, with support fromSodankylä Geophysical Observatory and STFC
KAIRAKilpisjärvi Atmospheric
Imaging Receiver Array
LOFAR-Finland FI609
19-May-2011, E3D Users' Meeting, Uppsala Derek McKay-Bukowski, SGO & EISCAT-UK 3
KAIRA is a new VHF passive receiver system, which serves 3 main roles:
• Powerful expt. in its own right
• Test bed for EISCAT_3D
• Valuable extension of the LOFAR array
LOFAR
EISCAT
KAIRA
24-Jan-2011, Birmingham Derek McKay-Bukowski, SEPnet, LOFAR-UK 4
• Complete– 20 core stations
• Incl. SuperTerp
– 7 remote stations
– 6 international stations• 4 × Germany
• 1 × UK
• 1 × France
• Additional stations planned– 2 × Germany, 3 × Poland... and others!
• Still under construction
– 4 core stations
– 10 remote stations
• 9 × Netherlands
• 1 × Finland (Kilpisjärvi)
– 2 international stations
• 1 × Germany (Jülich)
• 1 × Sweden (Onsala)
• Solar imaging1fps@135MHZ
• All-sky imaging
• Simultaneous pulsar measurements
• Long-baseline, sub-arcsecond imaging
• Polarimetry
• Jovian spectroscopy100 fps@22MHz
• Plus IPS, Cosmic Rays, etc.17-Mar-2011, Sodankylä Derek McKay-Bukowski, SEPnet, LOFAR-UK 5
19-May-2011, E3D Users' Meeting, Uppsala Derek McKay-Bukowski, SGO & EISCAT-UK 6
• HBA (High Band Array) 120-240 MHz ... cf. E3D!
– 5m×5m tile, containing 16 crossed-dipoles
DE603 Tautenberg
19-May-2011, E3D Users' Meeting, Uppsala Derek McKay-Bukowski, SGO & EISCAT-UK 7
• LBA (Low Band Array) 30-80 MHz
– Angled dipole, ground plane, LNAs
DE604 Potsdam
19-May-2011, E3D Users' Meeting, Uppsala Derek McKay-Bukowski, SGO & EISCAT-UK 8
• LOFAR is split into stations
– Each combines HBA, LBA and DSP
150m
HBA
LBA
RF-container
UK608 Chilbolton
07-Sep-2010, SGO, Sodankylä Derek McKay-Bukowski, SGO & EISCAT-UK 9
• Standard station configurations
• Kit-like assembly
– 96LBA + 96HBA
48HBA + 96LBA
2×24HB + 96LBA
07-Sep-2010, SGO, Sodankylä Derek McKay-Bukowski, SGO & EISCAT-UK 10
• KAIRA = Modified remote station
• Semi-sparse array, full RF-capacity
– 96LBA + 96HBA
48HBA + 96LBA
2×24HB + 96LBA
19-May-2011, E3D Users' Meeting, Uppsala Derek McKay-Bukowski, SGO & EISCAT-UK 11
• The centre of LOFAR is the SuperTerp
– As mentioned in Richard Fallow’s IPS talk earlier
340m
Superterp, Exloo
07-Sep-2010, SGO, Sodankylä Derek McKay-Bukowski, SGO & EISCAT-UK 12
• Located at Kilpisjärvi (not far from the Riometer)
– Closest Finnish point to the Tromsø VHF transmitter
Tromsø VHF
19-May-2011, E3D Users' Meeting, Uppsala Derek McKay-Bukowski, SGO & EISCAT-UK 13
Tromsø VHF
• 1.6 MW tx at224 MHz
• In HBA freq. range(120–240 MHz)
• Similar to proposed E3D frequencies
07-Sep-2010, SGO, Sodankylä Derek McKay-Bukowski, SGO & EISCAT-UK 14
• Site for HBA... on roadworks spoil
– Challenge : Hard, rocky ground, frost, snow
• LBA located below the HBA
– Challenge : Peat, frost, snow, more snow.
19-May-2011, E3D Users' Meeting, Uppsala Derek McKay-Bukowski, SGO & EISCAT-UK 15
• LBA to be located on the tundra below the HBA
– Challenge : Tundra/peat, frost, snow, more snow.
19-May-2011, E3D Users' Meeting, Uppsala Derek McKay-Bukowski, SGO & EISCAT-UK 16
• Ground survey
– 08-Sep-2010
Photograph: Markku Postila
19-May-2011, E3D Users' Meeting, Uppsala Derek McKay-Bukowski, SGO & EISCAT-UK 17
• RFI survey
– 23-Sep-2010
Photograph: Markku Postila
19-May-2011, E3D Users' Meeting, Uppsala Derek McKay-Bukowski, SGO & EISCAT-UK 18
• Geo-survey
– Subterranean trailing radar
Photograph: Markku Postila
19-May-2011, E3D Users' Meeting, Uppsala Derek McKay-Bukowski, SGO & EISCAT-UK 19
• Two HBA tiles deployed 19-Oct-2010
– Ground tile and raised tile.
Photograph: Thomas Ulich
19-May-2011, E3D Users' Meeting, Uppsala Derek McKay-Bukowski, SGO & EISCAT-UK 20
• Fortnightly checks throughout winter
Photograph: Markku Postila
19-May-2011, E3D Users' Meeting, Uppsala Derek McKay-Bukowski, SGO & EISCAT-UK 21
• Winter-testing completed. Both tiles survived.
• Will increase the frameset to 1.5m height
Ground test tile
1m-highframeset
Saana
Raised test tile
KAIRA HBA area
Pikku Malla
Storage area
19-May-2011, E3D Users' Meeting, Uppsala Derek McKay-Bukowski, SGO & EISCAT-UK 23
• Snow loading
– 7.65 tonnes of compacted snow/ice
Summit ~1.5m
0.6m high HBA tile
1.0m frame
Each load between500 and 1000kg
7650kg total
15t digger
Measuring system used to assess applied load
19-May-2011, E3D Users' Meeting, Uppsala Derek McKay-Bukowski, SGO & EISCAT-UK 25
• Destroyed tile has been dissected
• Full photographic sequence and part inventory
• Failure-modes and local loading pressures... TBD
• Assessment of frame support and structure
• Remaining tile dismantled; intact parts kept
• Disposal of debris
• Ground-tile stripped, repaired and moved
• Now in storage, as spare and expansion19-May-2011, E3D Users' Meeting, Uppsala Derek McKay-Bukowski, SGO & EISCAT-UK 26
• Site clearing
– Test-kit, snow (for thaw), documentation and layout
19-May-2011, E3D Users' Meeting, Uppsala Derek McKay-Bukowski, SGO & EISCAT-UK 27
• Delivery of 336 frames
– 16-May-2011
19-May-2011, E3D Users' Meeting, Uppsala Derek McKay-Bukowski, SGO & EISCAT-UK 28
19-May-2011, E3D Users' Meeting, Uppsala Derek McKay-Bukowski, SGO & EISCAT-UK 29
Schedule for remainder of 2011
• 12th May – Final snow clearing, destructive testing• 16th May – Delivery of frames• 6th June – Start of site surveying and preparation• 18th June – Surveying for final HBA layout• 4th July – Start of HBA deployment• 25th July – Cabling commences• 1st August – HBA and electronics ready• Winter 2011-2012 – Testing with Tromsø VHF• Summer 2012 – Installation of the LBA
Active outreach campaign... multiple web-updates each day during the main part of the build. Web-log, Twitter, photo-gallery, articles, news, links, etc.
19-May-2011, E3D Users' Meeting, Uppsala 3019-May-2011, E3D Users' Meeting, Uppsala 30
@KairaProject
http://kaira.sgo.fi/
Tune in to Thomas Ulich’s two presentations onKAIRA science and the outreach programmes
With thanks to the entire KAIRA team at the Sodankylä Geophysical Observatory,as well as countless others from the RAL, FMI, LOFAR, EISCAT and SKA communities.
Thanks also to the EISCAT-UK support group and to RAL for their support for this visit.And finally, special thanks to Izabela, without whom none of this work would be possible.
19-May-2011, E3D Users' Meeting, Uppsala 3119-May-2011, E3D Users' Meeting, Uppsala 31
@KairaProject
http://kaira.sgo.fi/
Tune in to Thomas Ulich’s two presentations onKAIRA science and the outreach programmes
With thanks to the entire KAIRA team at the Sodankylä Geophysical Observatory,as well as countless others from the RAL, FMI, LOFAR, EISCAT and SKA communities.
Thanks also to the EISCAT-UK support group and to RAL for their support for this visit.And finally, special thanks to Izabela, without whom none of this work would be possible.