NAVAL MOBILE CONSTRUCTION BATTALION FIVE Commanding Officer: CDR D. L. Fleisch Executive Officer: LCDR R. B. Tomiak Command Master Chief: CMDCM (SCW) R. J. Moon Deployment Completion Report Okinawa

Upload: others

Post on 22-Aug-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Deployment Completion Report · 2016. 11. 29. · for the entire seven months. TRAINING . ... ITEMPO days accumulated quickly for the 680-personnel Battalion during the deployment

NAVAL MOBILE CONSTRUCTION BATTALION FIVE Commanding Officer: CDR D. L. Fleisch Executive Officer: LCDR R. B. Tomiak Command Master Chief: CMDCM (SCW) R. J. Moon

Deployment Completion

Report

Okinawa

Page 2: Deployment Completion Report · 2016. 11. 29. · for the entire seven months. TRAINING . ... ITEMPO days accumulated quickly for the 680-personnel Battalion during the deployment

2001

Page 3: Deployment Completion Report · 2016. 11. 29. · for the entire seven months. TRAINING . ... ITEMPO days accumulated quickly for the 680-personnel Battalion during the deployment

3100 Ser S3

From: Commanding Officer, U.S. Naval Mobile Construction Battalion FIVE To: Distribution Subj: SUBMISSION OF DEPLOYMENT COMPLETION REPORT Ref: (a) COMCBPAC/COMCBLANTINST 3121 (Draft) (b) NMCB FIVE OPORDER, dated 17 July 2001 Encl: (1) NMCB FIVE Deployment Completion Report 1. Enclosure (1) is forwarded in accordance with reference (a). 2. Per reference (b), NMCB FIVE executed a very successful deployment to Camp Shields, Okinawa, Japan from 08 May 2001 to 14 December 2001, with details deployed to Atsugi, Japan; Chinhae, South Korea; Iwakuni, Japan; Pohang, South Korea; Sasebo, Japan; and Yokosuka, Japan. The Battalion also deployed three Deployments-for-Training to Ketchikan, Alaska; Dili, East Timor; and Everett, Washington. Incoporated into the deployment was a highly successful Air Det field exercise in the Central Training Area of Okinawa and training at the Marine Jungle Warfare Training Center. D. L. FLEISCH Distribution: OPNAV (N44) COMNAVFACENGCOM (FAC-SEABEE) COMTHIRDNCB (N3) COMSECONDNCB (N3) COM 31ST NCR CECOS NMCB FOUR NMCB ONE

Page 4: Deployment Completion Report · 2016. 11. 29. · for the entire seven months. TRAINING . ... ITEMPO days accumulated quickly for the 680-personnel Battalion during the deployment

TABLE OF CONTENTS

CHAPTER PAGE I Executive Summary……………………………………………… 1-1 II Administrative……………………………………………………. 2-1 III Training/Armory/Communications………………………………. 3-1 IV Operations………………………………………………………... 4-1 Safety………………………………………………………… 4-2 Mainbody

Project Summaries……………………………………….. CO Discretionary Projects……………………………….. Camp Maintenance………………………………………. Labor Distribution………………………………………..

4-10 4-22 4-23 4-24

Detail Atsugi Project Summaries………………………………………. OIC Discretionary Projects……………………………… Camp Maintenance……………………………………… Labor Distribution……………………………………….

4-25 4-31 4-31 4-32

Detail Chinhae Project Summaries………………………………………. OIC Discretionary Projects……………………………… Camp Maintenance……………………………………… Labor Distribution……………………………………….

4-33 4-35 4-35 4-36

Detail Iwakuni Project Summaries………………………………………. OIC Discretionary Projects……………………………… Camp Maintenance……………………………………… Labor Distribution……………………………………….

4-37 4-41 4-41 4-42

Detail Pohang Project Summaries………………………………………. OIC Discretionary Projects……………………………… Camp Maintenance……………………………………… Labor Distribution……………………………………….

4-43 4-45 4-45 4-46

Detail Sasebo Project Summaries………………………………………. OIC Discretionary Projects……………………………… Camp Maintenance……………………………………… Labor Distribution……………………………………….

4-47 4-55 4-55 4-56

Detail Yokosuka Project Summaries………………………………………. OIC Discretionary Projects……………………………… Camp Maintenance……………………………………… Labor Distribution……………………………………….

4-57 4-62 4-62 4-63

Page 5: Deployment Completion Report · 2016. 11. 29. · for the entire seven months. TRAINING . ... ITEMPO days accumulated quickly for the 680-personnel Battalion during the deployment

Contingency Operations

DFT Alaska Road……………………………………..… DFT East Timor………………………………………… DFT Everett, Washington……………………………….

4-64 4-65 4-66

V Supply/Logistics/Equipment……………………………………. 5-1 APPENDIX 1 Lessons Learned……….………………………………………… A1-14 2 Commendatory Correspondence………………………………… B1-3

Page 6: Deployment Completion Report · 2016. 11. 29. · for the entire seven months. TRAINING . ... ITEMPO days accumulated quickly for the 680-personnel Battalion during the deployment

1-1

EXECUTIVE SUMMARY

From 8 May to 14 December 2001, NMCB FIVE executed a successful Okinawan deployment. The Battalion was spread throughout the Pacific with six detail sites as well as three Deployments for Training in Alaska, East Timor, and Everett, Washington. Also, one Seabee was sent to Laos to participate in Joint Task Force – Full Accounting and one Officer participated in Operation Ulchi Focus Lens in Korea. Incorporated into the deployment was a successful Air Detachment field exercise in the Central Training Area of Okinawa. ADMINISTRATION During this deployment the Administration Department has successfully processed 252 transfers and receipts, processed reservist personnel, and administered exams. The Battalion had 182 personnel advance during the deployment! NMCB FIVE is proud to have retained 61% of its personnel during the deployment. Dental readiness and medical readiness were both above 95% for the entire seven months. TRAINING NMCB FIVE completed 5,041 mandays of training during the deployment. Military skills and physical fitness were the primary concentrations. The training during the Exercise Driven Training week of round robin combat skills and the Air Detachment Field Exercise, Operation Kennel Bear, was the majority of the Battalion’s military training, however, some early military training was gained by the participants in the Marine Jungle Warfare Training Center course. The training department worked hard to upgrade the Battalion indoctrination program by adding SCWS topics and security clearance paperwork. The Battalion also focused on training personnel for the Seabee Combat Warfare Specialist program, qualifying 148 people on deployment. OPERATIONS Safety was the Battalion’s primary goal. With constant diligence, the Battalion was able to improve its safety record from the last deployment in the Caribbean. NMCB FIVE completed 28,220 mandays of quality workmanship on camp maintenance, discretionary, and tasked construction projects for mainbody in Okinawa, Japan, detail sites in Atsugi, Iwakuni, Sasebo, and Yokosuka, Japan, Chinhae and Pohang, Korea, and Deployments for Training in Alaska, East Timor, and Everett, Washington. SUPPLY AND LOGISTICS The supply department worked hard to streamline processes, reduce backlogs, and achieve full supply accountability. The department processed 238 NORS and ANORS requisitions. The availability of CESE was held relatively constant starting at 89% at the beginning of deployment and reaching 88% at the end, with a spike to 97% after the BEEP. Also, the number of deadline CESE decreased from 13 to 8 over the deployment. Another important event was the swap of the TOA in the warehouse for a newer modular TOA. An outstanding deployment for the supply department as all inspections and assist visits were opportunities for visitors to see the “Professionals” shine!

Page 7: Deployment Completion Report · 2016. 11. 29. · for the entire seven months. TRAINING . ... ITEMPO days accumulated quickly for the 680-personnel Battalion during the deployment

2-1

ADMINISTRATION/SPECIAL STAFFS

ADMINISTRATION

The command’s retention program benefited from Personnel’s flexibility in completing 42 reenlistments. The clerk who processed 51 extensions and the separations mentioned above also expeditiously processed many short tasking reenlistments involving Selective Reenlistment Bonus (SRB) payments. In addition, 56 augment reservists called-up in support of Operation Enduring Freedom were completely processed within three days of their arrival. All personnel and pay issues were addressed, researched, and fixed. Substitute exams were promptly ordered and administered without discrepancies. Over the rest of the deployment, an additional 13 augment reservists were processed into the Battalion. Navy wide advancement examinations (Cycle 172) came and went without a hitch. The 11 September attacks delayed, but did not prevent the successful administration of 268 examinations in Okinawa, Korea, and Japan. Personnel also advanced 63 E2s and E3s during the deployment.

ADVANCEMENTS (PREVIOUS CYCLES) E4 E5 E6 Total

Time in Rate Eligible 82 121 34 237 Recommended 79 121 34 234 Participated 75 110 34 219 Advancements 49 25 4 78 Passed-Not-Advanced 18 77 27 178 Participated In Cycle 172 (September 2001) 268

During this deployment the Administration Department successfully processed 85 PCS transfers, 59 separations, four fleet reserve transfers, and 104 receipts. Superb planning and coordination with PSD Okinawa, PSD Port Hueneme, and with NMCB 5’s homeport liaison ensured trouble-free processing and a smooth transition to and from overseas.

Page 8: Deployment Completion Report · 2016. 11. 29. · for the entire seven months. TRAINING . ... ITEMPO days accumulated quickly for the 680-personnel Battalion during the deployment

2-2

NET RETENTION NMCB FIVE NAVY-WIDE SEABEE RATINGS

FY01 FY01 1st Term 50% 1st Term 56% 2nd Term 64% 2nd Term 65% Career 96% Career 87% Overall 61%

ITEMPO days accumulated quickly for the 680-personnel Battalion during the deployment. Over a period of five months, Personnel submitted over 1000 ITEMPO entries to keep the command’s counter updated. Personnel vigorously updated the primary and secondary next of kin information for 580 enlisted Page 2’s as per CNO directives. The 200 plus personnel assigned to details in mainland Japan; Korea; Everett, Washington; Dili, East Timor; and Alaska made the task more challenging, but did not hinder progress. Clerks also went to project sites to accommodate those who couldn’t make it to the office during normal working hours. In all, Personnel completed over 2500 Defense Joint Military Pay System (DJMS) transactions, Source Data System (SDS) events, and Diary Message Reporting System (DMRS) messages relating to pay and personnel data. The record vault was inventoried upon arrival and again before departing for homeport. Hardworking PN’s verified, purged, and updated over 580 records; completed more than 1400 service record entries; and created various electronic forms and three databases, which saved enormous man-hours and increased efficiency. This appears to be a short list of accomplishments, but it was a massive undertaking for an undermanned staff. Teamwork was the key to completing all of the tasking.

The Admin Office provided legal assistance, processed 47 passport applications, 565 cost/no cost TAD orders, 7 naturalization applications, over 430 FITREPS/EVALS, prepared over 300 personal awards and assisted in a Change of Command ceremony. Additionally, the department contributed immensely to the security of the Battalion by providing personnel as Interior Guards in the wake of terrorist attacks. The Assistant Security Manager processed over 100 security investigations during the deployment, ensuring all communicators and leadership had the security clearance necessary to perform all mission requirements.

Additionally, the Administrative Department provided 90% of the Command Operations Center communicators during the field exercise (FEX). The performance of the communications platoon was outstanding and received high marks from the brigade during the deployment FEX.

Page 9: Deployment Completion Report · 2016. 11. 29. · for the entire seven months. TRAINING . ... ITEMPO days accumulated quickly for the 680-personnel Battalion during the deployment

2-3

CHAPLAIN Protestant Divine Worship services were held every Sunday at the Camp Shields Chapel. Seabees actively attended Catholic and Latter Day Saint services at Kadena Air Force Base Chapels and Friday Muslim services at Camp Foster. Transportation to the various services was facilitated by shuttle bus provided by Alfa Company. The Camp Shields Chapel started a successful Chapel Band and a Luncheon Bible Study. Six Lay Readers, from the Muslim, Catholic, and Protestant faiths, were trained for support of the detachments and mainbody. The Command Religious Program also provided pastoral care and spiritual counseling, suicide awareness counseling, memorial services, the Battalion Change of Command invocation, retirements, re-enlistments, and oversight of the Command’s People with Exceptional Needs Program. The Camp Shields Chaplain’s Office, and Religious Ministries Team, provided leadership and support in a wide variety of areas impacting the spiritual health, morale and readiness of the Battalion. RP2 (SCW) Wright supervised the Camp Shields Library program providing coverage seven day per week, including evening library access, Monday through Friday. The Library supplied six trained watch-standers who worked extended hours in support of Seabees and the University of Maryland computer lab. The library provided boxes of paperback books for isolated detail sites such as Pohang, Korea; Ketchikan, Alaska; and the Jungle Warfare Training Center, Okinawa. Bookshelves were also obtained and paperback books provided for each lounge area in the junior enlisted quarters.

DENTAL

The Dental Department maintained dental readiness above 97% throughout the deployment. As the staff at Camp Shields rendered care for main body, the Details had their dental exams and work completed at their hosting bases, if available. Through regular contact with the Details, the department was able to maintain an accurate DENMIS database of the battalion’s personnel. Detail personnel in areas without easily accessible dental care had their exams and a majority of their routine work completed prior to deployment.

Contact with 3rd Dental Battalion and the Branch Dental Clinics enabled NMCB FIVE to use all available resources. Services provided from outside the command included periodontal surgeries and complex endodontic cases. The 3rd

Dental Battalion also played an integral role in providing our

Page 10: Deployment Completion Report · 2016. 11. 29. · for the entire seven months. TRAINING . ... ITEMPO days accumulated quickly for the 680-personnel Battalion during the deployment

2-4

clinic with supplies. Their accounting department held and kept track of our money for dental supplies. When supplies were required, we would send the 3rd Dental Battalion an order with a list of supplies and they processed the paperwork for the purchase. This efficient ordering process expedited our quarterly supply purchases. We utilized Naval Hospital Okinawa’s Oral Surgery Department for sedation cases and emergencies as necessary. Dental work for personnel living and working on remote camps was coordinated through the dental clinics on those remote camps, such as at Camp Schwab and Camp Futenma. This enabled our personnel to take less time out of the workday, by removing the transportation time required in a return to Camp Shields for a dental appointment.

MEDICAL NMCB FIVE’s deployment to Okinawa, Japan and various detail sites was rewarding. Extensive measures were taken to prevent endemic diseases such as Japanese encephalitis and leptospirosis. Specific guidelines for chemoprophylaxis for leptospirosis in the Northern Training Area (NTA) were followed as well as for malaria in East Timor. All personnel were given the Japanese Encephalitis Virus series of shots prior to or upon arrival in Okinawa. Two Hospital Corpsmen participated in an intensive Jungle Warfare training course at Northern Training Area, Okinawa 16-23 June 01, in tandem with the 3rd Marines. Specific preventive efforts for malaria including chemoprophylaxis and DEET treatment of uniforms were taken. Medical briefs for personal hygiene and sexually transmitted diseases were also given to all personnel. Due to the rigorous nature of the course, over 30 Seabee and Marine participants were treated for soft-tissue injuries, heat casualties, and various skeletal injuries; although one required a land MEDEVAC. Two Hospital Corpsman also participated in a 3rd MEU sponsored Medical Jungle Combat Casualty Care Course 21-29 August 01.

MEDICAL SUMMARY Total Immunizations 1212 Total Audiology Tests 249 Total Laboratory Venipunctures 785 Total Prescriptions 1647 Total Patient Visits 1215 For Health Promotions, the Medical Department initiated Smoking Cessation classes for 10 Battalion personnel in August with a success rate of 30%. The course consists of weekly seminars for approximately 5 weeks and was facilitated by the Medical Officer and one Hospital Corpsman. In preparation for the smoking class, the Hospital Corpsman attended the Smoking Cessation Instructor Course at Navy Hospital, Camp Lester. Two blood drives were held with over 50 units being donated. In support of the Great American Smokeout, a 5K run was organized with prizes such as stadium seat cushions, sweatshirts, and ball caps. One hundred smoking cessation packages were distributed. Basic Life Support (CPR) classes were offered and over 150 personnel certified.

Page 11: Deployment Completion Report · 2016. 11. 29. · for the entire seven months. TRAINING . ... ITEMPO days accumulated quickly for the 680-personnel Battalion during the deployment

2-5

One Independent Duty Corpsman and one Hospital Corpsman participated in an Air Detachment field exercise that supported 126 personnel in the Central Training Area. The Medical Department set up a Basic Aid Station and treated a total of 30 patients. Patient injuries included burns, upper respiratory infections, soft tissue injuries, musculoskeletal injuries, and local infections. Daily water checks were conducted on all water sources. The medical team’s capabilities were heavily tested during multiple mass casualty and biological/chemical drills with training provided on MEDEVACs and CASREP reports. The Medical Department continued to place a high priority on HM training during this deployment. This included intensive in-house HM training given twice weekly by the Medical Officer and three times a week by the Independent Duty Corpsmen. The topics ranged from sick call procedures to military training. A departmental orientation and skills assessment checklist was also accomplished and accepted by 3rd Brigade as a tool for all Seabee Medical Departments. Two corpsman completed intravenous fluid transfer and suture certification at the Naval Hospital and one completed a three-day Introduction to Preventive Medicine course. Two Corpsmen obtained certification as Audiometric Technicians. One Emergency Vehicle Operators Course was held 12-14 June 01 certifying 12 personnel. Four personnel obtained Basic Life Support Instructor certification.

Page 12: Deployment Completion Report · 2016. 11. 29. · for the entire seven months. TRAINING . ... ITEMPO days accumulated quickly for the 680-personnel Battalion during the deployment

1155

3 - 11

TRAINING/COMMUNICATIONS/ARMORY

TRAINING

Military Training:

The first major event of the deployment for the Training Department was sending 54 Seabees to

attend the Jungle Warfare Training Course at the Northern Training Area’s (NTA’s) Jungle Warfare Training Center (JWTC). During this week of intense training our Seabees joined forces with 5 Army and 100 Marine personnel stationed in Okinawa. Although a unique mix of

Military personnel, they came together to conquer numerous tasks as one team. Some of the training they received included repelling from a 100-foot cliff and adventuring over a ravine

using rope bridges suspended 200 feet above the ground. Our Seabees, along with their Marine and Army comrades, concluded the five-day training evolution with a 6-hour endurance course that truly measured their “CAN DO” spirit.

Three Command Post Exercises (CPXs) were conducted over the course of the deployment.

These exercises helped train personnel and provided a means for self-evaluation of the Command, Control, and Communication techniques utilized by the Battalion. This was accomplished by simulating a contingency operation that took the Battalion through various

types of scenarios. On Saturday, 29 September 2001, two hundred and fifty personnel headed north to the weapons

ranges of Camp Hansen. The focus of this training evolution was on the crew-served weapons (60 mm mortars, M-60’s, M2’s, and MK-19’s). Other personnel were able to perform

familiarization fire with shotguns and 9 mm pistols on adjacent ranges. The 2nd Battalion, 5th Marines Instructors provided instruction on the weapons and lead the battalion personnel through a live fire exercise.

In addition to the live fire exercise, Battalion personnel were required to Battle Zero Out (BZO)

their weapons when they arrived in Okinawa. Additionally, all interior guard personnel were required to BZO their weapons before standing watch in Camp Shields.

Leadership and In Rate Training:

During the deployment, the Battalion sent 20 personnel to Leadership Continuum Mobile Training Team classes offered through Commander Fleet Activities Okinawa. All members successfully completed the training, a requirement for their promotion to the next grade.

NMCB FIVE also conducted in-rate training on Saturdays. This training emphasized the critical

skills that Seabees need to succeed on Navy advancement exams. Indoctrination and Sponsor Program:

Indoctrination: The command indoctrination program underwent a complete revision. The

following changes were made:

Page 13: Deployment Completion Report · 2016. 11. 29. · for the entire seven months. TRAINING . ... ITEMPO days accumulated quickly for the 680-personnel Battalion during the deployment

1255

3 - 12

- Addition of SCWS topics to the curriculum such as Naval Heritage, Tactics, First

Aid, Communications, and Administration, Command & Control.

- The S1 department added security clearance applications and the beginning stages of the military passport process.

The program currently operates on a five-day schedule and will continue to prosper with additional training to be added during the homeport period. Plans are in place for this period of

instruction to be taken over by the homeport liaison. Sponsorship: In June, the sponsorship program was added to the S7 shop. The purpose of this

program is to create a single standard tracking database for new additions to the command. This database is updated daily and disseminated to the company chiefs and company sponsor

coordinators. There is 100% contact made with each prospective gain through two venues: the first is a standard Naval message originating from the sponsorship office and the second is a personal letter from the assigned sponsor. Numerous sponsors are making first contact via e-

mail, a method gaining popularity amongst the company representatives. The program still has room for improvement; but it is a step in the right direction.

Seabee Combat Warfare Specialist (SCWS) Program:

The SCWS training personnel had their hands full from the onset of deployment. Evening SCWS

classes taught by subject matter experts (SME) were offered 4 nights a week, allowing for aggressive progress to be made by all.

On 23 and 24 August, the SCWS office conducted a

SCWS Fest. This evolution involved all hands and was geared specifically toward enabling personnel to jump ahead on SCWS qualification. Feedback

from the SCWS Fest was extremely positive because the training allowed hundreds of Seabees to

attain skills in specific areas that would have otherwise been difficult to schedule on their own.

During FY 01, the Battalion qualified 111 new SCWS warriors! In total, the battalion was able to qualify a total of 148 new warriors during our 7-month deployment.

Block Military Training and Deployed Field Exercise:

Wednesday thru Friday, 10 to 12 October 2001, were designated as Block Military Training Days. The focus of the Block Military training was to improve the overall effectiveness of the

FEX organization, to develop small unit leaders’ proficiency at reactionary management, and to provide opportunities for the application of problem solving skills in complex situations. Block

Page 14: Deployment Completion Report · 2016. 11. 29. · for the entire seven months. TRAINING . ... ITEMPO days accumulated quickly for the 680-personnel Battalion during the deployment

1355

3 - 13

Military Training is engineered to correct identified shortfalls in the overall combat readiness training of battalion personnel.

The battalion exercised its Contingency Organizations, such as the Chemical, Biological, and

Radiological (CBR) Warfare; Embarkation; Communication; and Air Detachment organizations. Eleven Marines from Camp Schwab provided intense hands-on training in the following areas: land navigation, CBR, patrolling, convoy operations, tactics, urban building clearing, and Enemy

Prisoner of War handling.

On Saturday, 13 October 2001, the Air Detachment moved into the training area at Combat Town, while the remaining personnel established a Combat Operations Center as well as conducting an embarkation exercise at Camp Shields. The Air Detachment established a security

perimeter and conducted various construction operations from the camp that was established at Combat Town on Camp Hansen. Marines and advisors from the Third Naval Construction

Brigade assisted in testing the Air Detachment’s response to CBR and conventional attacks.

COMMUNICATIONS AND ISD

a. Communications Shop: During the deployment to Camp Shields, Okinawa, the

communications shop identified and corrected over $6,000 worth of discrepancies. The ET’s maintained over 400 various pieces of communications gear in a mission ready status. The ET’s also assisted the CFAO electronics shop in trouble-shooting communications assets.

The communications shop identified short falls in

training areas of the communications platoon, company level communicators, forward observers, and AIRDET. A comprehensive training program

was created. Each portion of the training was tailored to the different levels of knowledge

required for the communicators. The training was provided early and improved proficiency was evident at the three CPX’s, during SCWS Fest, and

at the MILBLOCK training for FEX. The communications shop received the following new

communications assets and incorporated those items immediately into the CPX and/or FEX plan:

PRC-117 GRC-231 PRC-150 SB-3614

In addition to completing all tasks assigned by 3NCB, communications personnel developed a communications SOP and rewrote the requirements for the SCWS PQS due to the new

equipment additions. The ET’s conducted a complete operational test on all equipment to verify capability and readiness. This testing and inventory identified over $300K in required assets to

be 100 percent tactically ready. The communications shop also participated in an HF communications exercise between Okinawa, Guam, and Port Hueneme. A CONEX box was

Page 15: Deployment Completion Report · 2016. 11. 29. · for the entire seven months. TRAINING . ... ITEMPO days accumulated quickly for the 680-personnel Battalion during the deployment

1455

3 - 14

procured and equipped with shelves for the quick and safe mount-out, and establishment of communications equipment in a field environment. The ET’s methodically organized the

communication shop shelves to facilitate the wide range of equipment and support gear. To support increased security controls, the communications shop had Camp Maintenance personnel

install Unicam daytime cipher locks on both entry doors and a CDX-08 lock on the double door leading outside. The communications shop also coordinated and obtained ten VHF frequencies for operational and training use on the island.

b. Information Systems Department: During

the deployment to Camp Shields, Okinawa, ISD maintained a Local Area Network of 120 workstations and 4 servers. The ISD

department restructured the LAN to the original configuration in accordance with

the license agreement and setup. The first full system accreditation for an NCF computer system was completed on the

entire network per direction from the N6, 3NCB and G6, MCB Butler using

DODINST 5200.40, SECNAVINST 5239.3, and CPFINST 5239.3. All computer systems also were verified to be C2

compliant after the network support switched from Kadena AFB to the Marine Corps’s Okinawa Wide Area Network (OWAN). The network was updated with Windows NT Service Pack 6 and

Outlook 2000 office package. NORTON Anti Virus was set up as a corporate system to update the anti virus protection daily. The ISD department completed all of the 3NCB tasking for this deployment, which can be reviewed on the Camp Shields Intranet web site weekly report for S6.

In addition, the shop:

Installed a CISCO Switch in the server room. This installation reduced the number of fiber

switches required to one for the Internet connection.

Installed 8 CPU capable Servo Switches for the server room assets.

Installed four external modems to give Dispatch and the Galley access to the server 24 hours a day. Installed two additional telephone lines and two modems in the server room providing

dual access at all times.

Received multiple new parts of the TLAN and organized shelves for easy deployment of the

TLAN. Identified to 3NCB all TOA requirement shortages that need to be filled for the Battalion to be 100 percent capable in the field.

Updated and fully populated the Camp Shields Intranet WEB Page.

Upgraded the VTC phone lines and repaired the VTC module.

Completed all facets of the 3NCB tasks assignments.

In addition to the normal maintenance of the computers in camp, the ISD Staff provided

assistance with user level problem solving for over 200 software and hardware trouble calls. At the end of the deployment, the computer resources were 100% operational.

Page 16: Deployment Completion Report · 2016. 11. 29. · for the entire seven months. TRAINING . ... ITEMPO days accumulated quickly for the 680-personnel Battalion during the deployment

1555

3 - 15

ARMORY

NMCB FIVE operated the camp armory with three Gunner’s Mates. The armory supported all training evolutions such as the crew served weapons live fire, M16 BZO, Interior Guard, and local SEAL and Special Boat Teams. The armory stored the following:

Qty Item

650 M16

48 M203

175 9mm

16 M60

6 M2, 50Cal

6 MK19

6 Mortars

24 Shotgun

37 AN/PVS-7C

10 AN/TVS-5

4 AN/PVS-12

9 AN/PVS-4

2 AN/PVS-20

Page 17: Deployment Completion Report · 2016. 11. 29. · for the entire seven months. TRAINING . ... ITEMPO days accumulated quickly for the 680-personnel Battalion during the deployment

4-1

OPERATIONS

Emphasizing safety, quality and production, NMCB FIVE completed 28,220 mandays of tasking on camp maintenance, discretionary projects, and project tasking. This was split through 10% maintenance, 15% training, 3% CO Discretionary, and 72% tasked projects. At the beginning of the deployment, NMCB FIVE deployed the mainbody to Camp Shields; Detail sites at Chinhae and Pohang, Korea and at Atsugi, Iwakuni, Sasebo, and Yokosuka, Japan; and DFT Alaskan Roads to Ketchikan, Alaska. NMCB FIVE embarked DFT East Timor early in June. In late July, a DFT was sent to Everett, Washington to provide CBU 421 additional support. For Japan and Korea, frequent rainstorms impacted project progress early in the deployment, but weather was slightly more cooperative by the middle of the deployment, as it only rained during the typhoons. Four typhoons passed over Okinawa and various portions of the Japanese mainland during the deployment; the eye of one typhoon passed over Okinawa three times! NMCB FIVE responded with appropriate readiness preparations to each typhoon as it moved through the area. The crashes of the four commercial airliners on 11 September 2001 had a significant impact upon manday capability. Subsequent to that, Seabees were required to man security details in Okinawa and at Sasebo. Security checks at the base gates also caused the crews to spend time during the workday away from the projects. The President activated many reservists as a result of the terrorist attacks. Included in the reservists activated were 69 personnel from NMCB FIVE’s reserve augment unit. The augment personnel went from their hometowns to Port Hueneme for records, medical checks, and training beginning the week of 8 October 2001. The augment personnel then flew in groups to Okinawa, Japan beginning 20 October 2001. Upon arrival in Okinawa, all personnel were assigned to a one-week indoctrination course for the Battalion. The augment personnel were eventually distributed to the companies and details as follows: ALFA Company – 26, BRAVO Company – 4, CHARLIE Company – 1, HEADQUARTERS Company – 3, DFT Everett – 10, Detail Atsugi/Fuji – 8, Detail Iwakuni – 7, and Detail Sasebo – 10. Upon NMCB FIVE’s return to homeport the augment unit was chopped to NMCB 133 in Guam as a Detail, per 3NCB direction. NMCB FIVE completed the following number of mandays at each site listed below:

Site Training (MD)

Project (MD)

Total (MD)

Okinawa (Mainbody) 3235 12478 15713 Detail Atsugi 460 1867 2327 Detail Chinhae 127 1009 1136 Detail Iwakuni 316 2047 2363 Detail Pohang 169 1389 1558 Detail Sasebo 367 3524 3891 Detail Yokosuka 367 2712 3079 DFT Alaskan Road 0 1566 1566 DFT East Timor 0 1009 1009 DFT CBU 421 Support 0 619 619 Total 5041 28220 33261

Page 18: Deployment Completion Report · 2016. 11. 29. · for the entire seven months. TRAINING . ... ITEMPO days accumulated quickly for the 680-personnel Battalion during the deployment

4-2

SAFETY SUMMARY The battalion reduced the severity of the mishaps experienced by the battalion through oversight of project planning, training, education, daily inspections, and proactive use of Operational Risk Management (ORM). These measures reduced the 9 Lost Work Day (LWD) cases with 127 lost workdays experienced during the battalion’s previous deployment (to Puerto Rico), to 5 LWD cases with a total of 6 lost work days during this deployment. This is a significant achievement considering the Okinawa deployment included a field exercise and a one-week jungle survival training evolution, which was not part of the Puerto Rico deployment. ORM was at the forefront of all operations through the use of 2-week risk analysis and 2-week goals, which raised hazard awareness at all levels in the battalion. Enclosure (1) is a copy of the project JK8-812 (Construct Ship Platform, White Beach) 2-week goals for 24 July - 06 August, enclosure (2) is the planned 2-week risk analysis from the project package, and enclosure (3) is the crew’s adjustments to the original plan. The crew’s adjustments reflect the actual hazards present with regard to crew experience and reiterates the fact that the safety plan is a “living document”. Safety stand-downs were conducted immediately following mishaps to identify the cause, to identify corrective measures to prevent duplicate mishaps, and to refocus personnel on hazards present.

OKINAWA DEPLOYMENT 2001 MAY JUN JUL AUG SEP OCT NOV TOTAL Fatalities 0 0 0 0 0 0 0 0 Lost work days 1 0 0 0 0 4 1 6 Lost work day cases 1 0 0 0 0 3 1 5 Light duty days 35 198 66 100 73 146 68 686 Light duty day cases 6 16 11 9 5 9 7 63 First aid mishaps 16 15 19 22 22 13 12 119 GOV mishaps 6 15 10 6 3 8 2 50 Total mishaps reported (incl. 4 near mishaps)

29 46 40 37 30 33 22 237

Vehicle repair costs ($) $1,412 $219 $2987 $30,310 $355 $200 $35,483 Gov’t Vehicle Miles Driven

34,630 66,778 64,920 44,615 45,499 37,020 49,508 342,970

ON-DUTY MISHAPS MAY JUN JUL AUG SEP OCT NOV TOTAL First aid mishaps 7 11 15 9 18 10 9 79 Light duty day cases 3 7 4 6 4 5 3 32 Light duty days 24 75 24 83 59 111 49 425 Lost work day cases 1 0 0 0 0 3 1 5 Lost work days 1 0 0 0 0 4 1 6 Fatalities 0 0 0 0 0 0 0 0

Page 19: Deployment Completion Report · 2016. 11. 29. · for the entire seven months. TRAINING . ... ITEMPO days accumulated quickly for the 680-personnel Battalion during the deployment

4-3

OFF-DUTY MISHAPS MAY JUN JUL AUG SEP OCT NOV TOTAL

First aid mishaps 9 4 4 13 4 3 3 40 Light duty day cases 3 9 7 3 1 4 4 31

Light duty days 11 123 42 17 14 35 19 261 Lost work day cases 0 0 0 0 0 0 0 0

Lost work days 0 0 0 0 0 0 0 0 Fatalities 0 0 0 0 0 0 0 0

Page 20: Deployment Completion Report · 2016. 11. 29. · for the entire seven months. TRAINING . ... ITEMPO days accumulated quickly for the 680-personnel Battalion during the deployment

4-24

LABOR DISTRIBUTION SUMMARY FOR NMCB FIVE OKINAWA DEPLOYMENT – 2001 [MAINBODY]

MANDAYS MAY JUN JUL AUG SEP OCT NOV DEC TOTAL % TOTAL

DIRECT LABOR 982 2790 2946 3058 2314 2648 2661 0 17399 42%

INDIRECT LABOR 1429 2837 3870 3682 2553 2381 3637 217 20606 50%

READINESS/TRAINING 301 386 377 471 323 898 338 141 3235 8%

TOTAL 2712 6013 7193 7211 5190 5927 6636 358 41240 100%

# PERSONNEL 398 422 440 423 416 473 473 398

# DL PERSONNEL 132 137 144 138 138 151 141 141

# WORKDAYS

12 23 23 24 21 25 22 0

% DIRECT LABOR 33% 32% 33% 33% 33% 32% 30% 34%

MD CAPABILITY 1337 2659 2795 2795 2445 3185 2617 0

AVAILABILITY FACTOR

72% 90% 89% 95% 81% 83% 90% 55%

NOTES: 1. %Direct Labor = # Direct Labor/ # Personnel

2. MD Capability = (# Direct Labor) x (# Workdays) x (1.125) x (0.75) 3. Availability Factor = (Direct Labor MDs + R/T) / (MD Capability) x (0.75) 4. The low availability factor in December was due to most all projects completing

ahead of schedule and/or ahead of turn over expectations.

Page 21: Deployment Completion Report · 2016. 11. 29. · for the entire seven months. TRAINING . ... ITEMPO days accumulated quickly for the 680-personnel Battalion during the deployment

4-10

UPGRADE CAMP AND PERIMETER ROADS, JWTC JK1-847

Perform soil stabilization and provide drainage for camp roads in the Northern Training Area. The crew continually battled rain and typhoons, which washed away portions of completed work and half of the road in an area that is the only entrance to their original tasking. Only highly skilled operators were allowed on equipment working close to the edges due to the steep drop offs and muddy conditions. Soil stabilization should be done last (after installing U-ditch and catch basins) to increase productivity. Start WIP: 0% End WIP: 100% Project Data Personnel: 6 personnel Duration: May 2001 – December 2001 Mandays: 500 Material Cost: $100,000 Cost Savings: $175,000 Specifications: Soil stabilize 3000 feet of road, place U-ditch and catch basin for drainage, and

perform camp upgrades as requested by the customer.

The crew is beginning the placement of U-ditch sections along the road at the top of the hill.

The crew finished the U-ditches to the bottom of the hill and has placed the catch basins.

Page 22: Deployment Completion Report · 2016. 11. 29. · for the entire seven months. TRAINING . ... ITEMPO days accumulated quickly for the 680-personnel Battalion during the deployment

4-11

REPLACE SEWER LINE HALSEY ROAD WHITE BEACH JK8-806

The new sanitary sewer line provides an upgrade to the existing system and increases capacity for this area of the base. NMCB Five installed 500 feet of L-Curb, 300 feet of U-Ditch, and five steel grates for the gutters. The old and the new sewer lines were connected at one end of the street. The road was repaved and hydro-seed was placed in all the disturbed areas. Work was stopped to facilitate a change of command ceremony by request of the base commander. Before the work stoppage, the crew had received an approved Field Adjustment Request (FAR) to stop reroute the path of the sewer line away from a nearby pool and to stop the sewer line effort early. When approval to resume work came from the customer, the FAR approval had been rescinded and the original length of new sewer was reinstated with an allowance for rerouting away from the pool. Start WIP: 55% End WIP: 77% Project Data Personnel: 10 personnel Duration: October 2000 – April 2002 Mandays: 1750 Material Cost: $73,000 Cost Savings: $613,000 Specifications: This project involves replacing 1200 feet of 8-inch sanitary sewer line on a new

alignment. The project also includes the installation of 9 pre-cast manholes and removal and replacement of ditches, sidewalk, curb, and pavement as needed during construction.

A view of the project area after the work was stopped.

Photo taken by NMCB FOUR showing the shoring for the sewer line in place at turnover.

Page 23: Deployment Completion Report · 2016. 11. 29. · for the entire seven months. TRAINING . ... ITEMPO days accumulated quickly for the 680-personnel Battalion during the deployment

4-12

CONVERT EAST WING OF BUILDING 3597 TO FITNESS CENTER

JK6-864

The expansion of the MWR facility will provide a 910 square foot fitness center with sauna, male and female locker rooms and showers. The Seabees have been tasked with all work necessary to construct the building. Start WIP: 69% End WIP: 100% Project Data Personnel: 11 - 12 personnel Duration: January 1999 – November 2001 Mandays: 2546 Material Cost: $325,000 Cost Savings: $891,000 Specifications: This 910 square foot fitness center is connected to the MWR facility. The old

building was demolished when structural flaws were discovered. The building was reconstructed with a concrete floor, under-floor utilities, CMU block walls, a cast-in-place reinforced concrete roof, interior framing, wiring, plumbing, wallboard, trim, suspended ceiling, flooring, and installation of air conditioning units. The fire alarm system, bathroom tile, exterior roofing, and painting work were performed by CFAO contract. The crew was responsible for placing topsoil and shaping the site for drainage in preparation for a CFAO hydro-seeding contract.

The completed weight room portion of the Fitness Center.

Laying the first course of CMU blocks for the shower units.

Page 24: Deployment Completion Report · 2016. 11. 29. · for the entire seven months. TRAINING . ... ITEMPO days accumulated quickly for the 680-personnel Battalion during the deployment

4-13

CONSTRUCT RETAINING WALL, WHITE BEACH JK3-808

The crew had to overcome several challenges: archeological finds, torrential rain and associated mud, precarious power lines, 5,000 cubic yards of spoils, and suffocating heat and humidity. Wall construction consisted of the local Okinawan style—Kenchi block. Each block weighs 22 kilograms (48.5 pounds) and is arranged in a chevron shape vice square like traditional blocks. The crew took time to visit a Kenchi block construction project, observed locals installing the blocks, and was able to use lessons learned to maximize productivity. Start WIP: 18% End WIP: 91%. Project Data Personnel: 21 Duration: October 2000 – April 2002 Mandays: 3,314 Material Cost: $333,000 Cost Savings: $1,160,000 Specifications: Construct a 500 linear-foot Kenchi-block retaining wall at White Beach.

Finished wall has over 8,000 individual Kenchi blocks, 400 cubic meters of concrete, and 2,000 cubic yards of back fill. Included in the project is over 700 feet of grated drainage u-ditch, 200 feet of open drainage v-ditch, 500 feet of apron, 100 linear feet of 16-inch PVC pipe, catch basins, and over 13,000 square meters (145K square feet) of landscaping.

The retaining wall masonry has been completed.

Progress on the retaining wall when NMCB FIVE took over in May.

Page 25: Deployment Completion Report · 2016. 11. 29. · for the entire seven months. TRAINING . ... ITEMPO days accumulated quickly for the 680-personnel Battalion during the deployment

4-14

EXTEND SEAWALL, CAMP SCHWAB JK9-826

The crew overcame several challenges to produce a quality product. These challenges included: high lunar tides and storm surges that caused extensive rework, typhoon downtime, and an unforeseen site condition that required complete revision of the execution plan. Using prefabricated metal forms; each 10-meter wall section was filled with 54 cubic meters of concrete. The resultant section of wall weighs over 140 tons. The entire wall will have over 800 cubic meters (1,046 cubic yards) of 3,000 psi concrete. Start WIP: 27% End WIP 85%. Project Data Personnel: 21 Duration: October 2000 – March 2002 Mandays: 2,768 Material Cost: $440,000 Cost Savings: $969,000 Specifications: Construct a 156-meter (512-foot) concrete gravity wall 4.5 meters (15 feet) in

height. Additionally, the project provides a 3-meter wide concrete apron and a 0.8-meter wide by 0.55-meter deep U-ditch for the entire length of the Seawall, a 4.7-meter wide by 6.6-meter long concrete headwall at the midpoint, extensive backfill and over 800 square meters (8,000 square feet) of landscaping.

A picture of the completed concrete seawall taken from low tide. Backfill and U-ditch installation are underway behind the wall.

Excavation for the leveling pad.

Page 26: Deployment Completion Report · 2016. 11. 29. · for the entire seven months. TRAINING . ... ITEMPO days accumulated quickly for the 680-personnel Battalion during the deployment

4-15

CONSTRUCT SHIP PLATFORM, WHITE BEACH JK8-812

This showcase Steelworker project was an excellent environment for junior SWs to hone their technical skills. A technically challenging project, the crew meticulously planned and flawlessly executed the platform’s erection. Start WIP: 0% End WIP 100%. Project Data Personnel: 8 Duration: June 2001 – November 2001 Mandays: 379 Material Cost: $52,000 Cost Savings: $133,000 Specifications: Construct a 15-foot square by 25-foot tall metal ship platform. This metal

structure consisted of square tube main support members and cross members, three diamond plate mid platforms and a main platform, lifting eyelets, three ladder runs, and railings. The finished structure will be sand blasted and painted by local contractors.

The initial layout of the front and back of the platform.

Members of the crew stand on top of the completed platform waiting for the ribbon cutting ceremony.

Page 27: Deployment Completion Report · 2016. 11. 29. · for the entire seven months. TRAINING . ... ITEMPO days accumulated quickly for the 680-personnel Battalion during the deployment

4-16

CONSTRUCT YOKOHAMA FENDER STORAGE YARD, WHITE BEACH

JK8-809

An outstanding horizontal construction project! This project provided experience with earth moving and grading, forming and placing a concrete pad and asphalt paving. Lessons learned: A lightweight screed is a must to complete concrete placements this large. The crew worked very hard with a screed made of angle iron that weighed more than 400 pounds. Establishing drainage early paid off. The project was completed on time despite heavy rains and four typhoons. START WIP: 0% END WIP 100%. Project Data Personnel: 8-12 personnel Duration: May 2001 – November 2001 Mandays: 880 Material Cost: $207,000 Cost Savings: $308,000 Specifications: Stabilize area, pour a 97 by 215 foot pad, install U-ditch, construct and pave an

entrance road, install a security fence, and establish drainage.

The project started amongst mud and water. The crew is spreading and compacting select fill material to bring the site up to the desired

elevation.

The completed project! The finished product consists of a 210’ by 93’ concrete pad, security fence and gate, landscaping, and a paved road.

Page 28: Deployment Completion Report · 2016. 11. 29. · for the entire seven months. TRAINING . ... ITEMPO days accumulated quickly for the 680-personnel Battalion during the deployment

4-17

CONSTRUCT ONE PAVILION, CAMP HANSEN

JK6-857 This new 21-foot by 27-foot pavilion with wheel chair ramps provides a recreational facility for this area of Camp Hansen. The crew effectively used excess materials to minimize overall project costs. The minimum slump of concrete the pump truck could handle was 3”. Concrete finishing during the roof portion was especially challenging because of the roof’s slope and a 3” slump. Start WIP: 0% End WIP: 100% Project Data Personnel: 8 personnel Duration: August 2001 – November 2001 Mandays: 410 Material Cost: $39,000 Cost Savings: $144,000 Specifications: The crew constructed a 21 foot by 27 foot recreation pavilion which included

clearing the site, structural excavation, building forms and placing reinforcing steel and concrete for spread footings, columns, and roof structure. The crew completed all of the preparation work for a CFAO painting contract. The crew was responsible for placing topsoil and shaping the site for drainage in preparation for a CFAO hydro-seeding contract.

The crew is excavating for the footer and grade beams.

The completed pavilion after it was painted.

Page 29: Deployment Completion Report · 2016. 11. 29. · for the entire seven months. TRAINING . ... ITEMPO days accumulated quickly for the 680-personnel Battalion during the deployment

4-18

CONSTRUCT 3 BUS SHELTERS, CAMP FUTENMA JK0-846

Although this project is small in scope, it gave the crew an excellent opportunity for learning block and concrete construction. The crew performed superbly in all facets of planning, set-up, construction, and clean up. The project received favorable comments during the Brigade’s visit for the 45-day review. Start WIP: 0% End WIP 100%. Project Data Personnel: 6 Duration: June 2001—November 2001 Mandays: 315 Material Cost: $17,000 Cost Savings: $110,000 Specifications: Construct three 1.5-meter by 2.6-meter bus shelters. Each structure consists of a

concrete floor placed on leveled and compacted fill, a formed-in-place concrete bench, core-filled CMU block walls, and a mono-lithic concrete roof.

A picture of site #2 completed.

The crew placing footers.

Page 30: Deployment Completion Report · 2016. 11. 29. · for the entire seven months. TRAINING . ... ITEMPO days accumulated quickly for the 680-personnel Battalion during the deployment

4-19

REPLACE PAVEMENT, PSC JK7-881

This project involved construction of 230 linear feet of curb and gutter including three grated drop inlets. The drop inlets were connected to the existing storm drainage system using 70 feet of 12” PVC pipe. The project also included the removal and replacement of an asphalt driveway. Start WIP: 95% End WIP: 100% Project Data Personnel: 8 personnel Duration: July 2000 – November 2001 Mandays: 3368 Material Cost: $211,000 Cost Savings: $1,179,000 Specifications: Install three catch basins. Connect existing catch basins to new basins with 12”

PVC pipe. Place approximately 12 cubic meters of concrete for new gutter system. Install approximately 230 feet of pre-cast curb. Remove and replace asphalt driveway. Part of this project included removal and replacement of electrical utility lines, which was de-tasked by ROICC and will be accomplished by contract.

The finished project ready for hydro seeding.

Installation of storm drainage conduit as part of the curb and gutter system.

Page 31: Deployment Completion Report · 2016. 11. 29. · for the entire seven months. TRAINING . ... ITEMPO days accumulated quickly for the 680-personnel Battalion during the deployment

4-20

CONSTRUCT PAVILION, WHITE BEACH

JK8-804 This project was originally scheduled to be completed by the Reserve Component with NMCB oversight. When the Reserves could no longer support the project, it was turned over to NMCB FIVE to complete. NMCB FIVE began work on the project with the overhead roof forms already roughly in place. NMCB FOUR and NMCB FIVE had a working turnover on this project and were able to complete the forming for the roof. Start WIP: 48% End WIP 100%. Project Data Personnel: 8 Duration: March 2001 – August 2001 Mandays: 490 Material Cost: $20,000 Cost Savings: $172,000 Specifications: Construct a 600-square-foot concrete picnic pavilion to include concrete footers

and grade beams, a 6-inch thick concrete floor, six 1-foot by 1-foot concrete columns, and a concrete overhead roof. Install a French drain around the deck under the drip edge of the roof and finish with two concrete ramps on each side of the structure. Also included were 50 feet of curbing and asphalt, 40 feet of sidewalk and 3,000 square feet of landscaping.

The completed pavilion.

The crew is conferring with the Safety Officer just after turnover.

Page 32: Deployment Completion Report · 2016. 11. 29. · for the entire seven months. TRAINING . ... ITEMPO days accumulated quickly for the 680-personnel Battalion during the deployment

4-21

INTERIOR GUARD, DIRECT LABOR AND INTERIOR GUARD, INDIRECT LABOR

JK0-322 and JK0-323

This tasking was received subsequent to the terrorist attacks on the United States on 11 September 2001. Outstanding training on interior defense was provided along with familiarizat ion with the weapons carried. This project absorbed a significant portion of the mandays that would have been dedicated to other projects and was one of the reasons why the augment unit was activated. Start WIP: 0% End WIP 100%. Project Data Personnel: 31-57 personnel Duration: September 2001 – December 2001 Mandays: 2172 Material Cost: $0,000 Cost Savings: $0,000 Specifications: Establish an interior guard to provide security for the camp. The guard section

is composed of a section leader, roving patrols, and front gate security.

Interior Guard roving patrols walk the fence line looking for damage and any possible signs of intrusion.

The vehicle inspection team stands by for the next inspection. Two Battalion personnel and one civilian translator man the post.

Vehicles are inspected for explosives and other contraband.

Air Force personnel inspect identification cards and proper vehicle pass paper work at the front gate. They randomly

pick vehicles for complete inspection.

The front gate guard shack with barriers. Sand bags and barriers provide protection against any attacks. The guard shack is

equipped with a direct link phone to the Kadena security office.

Page 33: Deployment Completion Report · 2016. 11. 29. · for the entire seven months. TRAINING . ... ITEMPO days accumulated quickly for the 680-personnel Battalion during the deployment

4-22

CO DISCRETIONARY MAINBODY

PROJECT LISTING

MD’s EXPENDED

Construct Pull-up Bars Camp Hansen 1 Build Seahut, Camp Hansen 162 Sliding Rails, cut and weld, Camp Kinser 6 Remove C-130 Revetments, Kadena 6 Asphalt overlay on 1st street 31 Build Temporary Front Gate 25 JWTC Hardstands 2 Connect field shower drain to collection point, JWTC 23 Build award board, Camp Schwab 10 TOTAL MANDAYS 266

Marine Range Instructors on Camp Hansen will use this completed Seahut.

The pull-up bars were completed at Camp Hansen.

The external tank for a field shower was connected to the facility at JWTC. The tank was then properly installed in the ground and the area

was back-filled.

Page 34: Deployment Completion Report · 2016. 11. 29. · for the entire seven months. TRAINING . ... ITEMPO days accumulated quickly for the 680-personnel Battalion during the deployment

4-23

CAMP MAINTENANCE MAINBODY

CAMP MAINTENANCE TASKING MANDAYS ESA’s 1025 SJO’s 730 MCD’s 745 Completed MCD Projects: 47

Replace valves in Bldg 7216 (3 MCDs) 48 Install name plates in BEQ 45 Replace shower tile in Bldg 7216 73 Install ramp at Bldg 5001 53 Upgrade electrical system at Bldg 7146 149 Renovate Bldg 7142 22 Renovate stairwells at Bldg 7146 17 Repair handrail at Bldg 6106 13 Install exterior lighting at Bldg 6105 15 Armory lighting at Bldg 5001 21 Install ceiling fans at Bldg 7205 21 Replace electrical at Bldg 7148 15 Build tent boxes 11 Move canopy at Bldg 7147 15 Construct guard house at front gate 11 Move furniture at Bldg 7212 and 7147 57 Move refrigerators at Bldg 7216 13 Misc. MCDs (28 MCDs less than 10 MDs) 107

TOTAL MANDAYS EXPENDED 2500

Installation of a doorway in the CPO Mess.

Performing check of an electrical service panel.

Page 35: Deployment Completion Report · 2016. 11. 29. · for the entire seven months. TRAINING . ... ITEMPO days accumulated quickly for the 680-personnel Battalion during the deployment

4-25

CONSTRUCT DEBRIS STORAGE AREA AG0-864

This project will provide a dry-waste storage area for Naval Air Facility Atsugi’s Public Works Department. Detail personnel constructed all of the foundation and constructed the 6-inch thick reinforced-concrete walls, interior concrete pads, and ramps and installed stainless steel gates for two out of the five bays. Progress was significantly impacted by wet site conditions early in deployment. The project site is an old landfill, and ground swell of up to 12 inches was typical after heavy rains. Start WIP: 0% End WIP: 59%. Project Data Personnel: 6 Duration: May 2001 – July 2002 Mandays: 452 Material Cost: $108,000 Cost Savings: $158,000 Specifications: Construct five reinforced concrete dry-waste-storage bins with 6” thick walls and floor,

concrete access ramps, and catch basins and install double steel gates. The project also included 260 linear feet of concrete U-ditch, an oil-water separator, 75 linear feet of 6” diameter pipe connecting to the station storm drainage system, and a 6,200-square-foot, 4”-thick gravel hard stand.

A view of bays B and C with completed concrete pads, concrete ramps, and steel gates.

Crewmembers setting up batter boards in preparation for wall forms.

Page 36: Deployment Completion Report · 2016. 11. 29. · for the entire seven months. TRAINING . ... ITEMPO days accumulated quickly for the 680-personnel Battalion during the deployment

4-26

CONSTRUCT RETAINING WALL, BUILDING 70 AG0-865

This project will prevent erosion of a hillside into the street next to one of the installation’s fitness centers. The retaining wall project was a great learning experience for the four-member crew because many aspects of construction were incorporated into one project. Detail personnel excavated, placed the foundation and retaining wall, and installed drainage, a new concrete sidewalk, and traffic striping. A contract was awarded to manufacture and install the stainless steel pipe handrail upon completion of the project. Start WIP: 0% End WIP: 100%. Project Data Personnel: 4 Duration: May 2001 – November 2001 Mandays: 388 Material Cost: $41,000 Cost Savings: $136,000 Specifications: Construct 75 linear meters of new retaining wall; to include reinforcing steel, a drainage

system, welded stainless steel pipe handrails, a concrete sidewalk, and new sod.

The project site early in deployment, just after excavation began.

The completed project, pending the installation of the contracted handrail

Page 37: Deployment Completion Report · 2016. 11. 29. · for the entire seven months. TRAINING . ... ITEMPO days accumulated quickly for the 680-personnel Battalion during the deployment

4-27

CONSTRUCT SUPPLY WAREHOUSE AG7-848

The Supply warehouse project will provide much needed storage space for the installation’s Supply and MWR Departments. The crew was unable to start the project until late in the deployment. Detail personnel cleared and grubbed the project site and placed, leveled, and compacted 900 cubic meters of C40 gravel fill to bring the site up to grade. Start WIP: 0% End WIP 5%. Project Data Personnel: 3 Duration: September 2001 – August 2002 Mandays: 1200 Material Cost: $231,000 Cost Savings: $420,000 Specifications: Construct two 40’ by 100’ pre-engineered buildings. Work will include clearing and grubbing,

new fill and grading. New construction includes the installation of reinforced concrete foundations, pads, plumbing, lighting and wiring.

A little help from the Fire Department to aid compaction…

UT2 (SCW) Reed compacting the C40 gravel fill.

Page 38: Deployment Completion Report · 2016. 11. 29. · for the entire seven months. TRAINING . ... ITEMPO days accumulated quickly for the 680-personnel Battalion during the deployment

4-28

CONSTRUCT DISASTER PREPAREDNESS WAREHOUSE AG9-860

This project will provide Public Works NAF Atsugi with a storage space for disaster preparedness materials. The crew removed Public Works excess material, demolished existing concrete pads, installed new 6” thick concrete pads for a hardstand, installed a foundation and ramps, and erected the steel skeleton for the pre-engineered building. Frequent flooding after rain hampered crew progress. Start WIP: 0% End WIP 62%. Project Data Personnel: 5 Duration: May 2001 – January 2002 Mandays: 545 Material Cost: $130,000 Cost Savings: $191,000 Specifications: Construct a 30’ by 70’ pre-engineered building. The work includes the demolition of an

existing 10” thick concrete roadway and the relocation of various excess materials. New construction includes the installation of a reinforced concrete foundation, lighting, and wiring.

The project area has been cleared of other material. The layout for the project and cutting of the existing

concrete pad is in progress.

The concrete floor has been placed and the skeleton of the pre-engineered building is erected.

Page 39: Deployment Completion Report · 2016. 11. 29. · for the entire seven months. TRAINING . ... ITEMPO days accumulated quickly for the 680-personnel Battalion during the deployment

4-29

CONSTRUCT HEAD AT SUPPLY ADMINISTRATION OFFICE FJ1-809

This project will provide a much needed head facility for the Supply Administration office in building 413 at Camp Fuji. Currently, the office staff needs to walk to another building to use the head facilities, which is very inconvenient during the winter months. Detail personnel installed a sewer line and interior rough plumbing for the new head. Funding and material issues severely impacted the progress of this project. Start WIP: 0% End WIP 64%. Project Data Personnel: 3 Duration: August 2001 – February 2002 Mandays: 168 Material Cost: $14,000 Cost Savings: $59,000 Specifications: Work included the installation of 2 new toilets, 1 urinal, 2 partition walls, 1 sink, 50

linear meters of 4” PVC sewer line including 2 cleanouts, 15 linear meters of 1” water line, steel stud walls with gypsum wallboard, vinyl floor sheeting, and ceramic wall tile.

EO3 (SCW) Cadenas is excavating for the new sewer line with a rented Japanese

excavator.

The new 4 inch PVC sewer line, after successful head test, concrete encasement,

and backfill.

Page 40: Deployment Completion Report · 2016. 11. 29. · for the entire seven months. TRAINING . ... ITEMPO days accumulated quickly for the 680-personnel Battalion during the deployment

4-30

EXPAND ARMORY FJ0-806

The expand armory project will more than double the usable area of Camp Fuji’s armory. It will provide 7 weapon storage areas, each with their own weapons issue/return window. This will greatly reduce the time required for the training units to issue and return weapons. Detail personnel designed and then constructed an elaborate form system for the roof’s overhead concrete pour. Additionally, they installed wall and ceiling framing, gypsum wallboard, and a structural steel canopy. Start WIP: 46% End WIP 88%. Project Data Personnel: 6 Duration: October 2000 – March 2002 Mandays: 1430 Material Cost: $420,000 Cost Savings: $501,000 Specifications: Construct a 2,207-square-foot addition to the existing armory building 108. Work

included new perimeter fencing, perimeter U-ditch, reinforced concrete walls, new foundation, and suspended overhead concrete roof. Other work will include, a new 1,140-square-foot structural-steel canopy, new steel cages, a new furnace system, and electrical system installation. Security windows, the built up roof , the heating, ventilation, and air-conditioning system, and the fencing were activities that were contracted out.

Crewmembers begin to build formwork for the overhead roof placement.

Overhead concrete roof placement completed.

Page 41: Deployment Completion Report · 2016. 11. 29. · for the entire seven months. TRAINING . ... ITEMPO days accumulated quickly for the 680-personnel Battalion during the deployment

4-31

OIC DISCRETIONARY/CAMP MAINTENANCE DETAIL ATSUGI

PROJECT LISTING MANDAYS Clear fence line, fill sandbags 8 Improve shelter for Base Security 6 Install Shelving at Red Cross 2 Enlarge MLO Yard (concrete pads) 12 Additional detail parking (concrete pads) 12 Construct BBQ area at Camp Fuji 6 Organize MLO Yard 16

Install Coffer Dam for Fuel Tank 10 TOTAL MANDAYS 72 CAMP MAINTENANCE ESA’s 18

SJO’s 14 MCD’s 18

Install drainage U-ditch at detail Spaces 5 Painting of detail Spaces 5 Install door closers in detail heads 1 Repair of eyewash station 1 Miscellaneous MCDs 6 TOTAL MANDAYS 50

Drainage U-ditch installed in front of detail spaces alleviated a severe drainage problem that often resulted in 3 inches of standing water directly in front of detail spaces front door.

Shelving was installed in two closets at the American Red Cross office to increase

storage space.

Placement of excess concrete enlarged the MLO storage Yard behind the detail spaces.

Page 42: Deployment Completion Report · 2016. 11. 29. · for the entire seven months. TRAINING . ... ITEMPO days accumulated quickly for the 680-personnel Battalion during the deployment

4-32

LABOR DISTRIBUTION SUMMARY FOR NMCB FIVE OKINAWA DEPLOYMENT – 2001 [Atsugi]

MANDAYS MAY JUN JUL AUG SEP OCT NOV DEC TOTAL % TOTAL

DIRECT LABOR 149 449 435 388 308 472 525 0 2726 72%

INDIRECT LABOR 46 77 84 67 74 88 116 6 558 15%

READINESS/TRAINING 27 71 35 118 63 76 70 33 493 13%

TOTAL 222 597 554 573 445 636 711 39 3777 100%

# PERSONNEL 31 29 30 30 30 32 40 40

# DL PERSONNEL 25.5 23.5 24.5 24.5 24.5 26.5 32.5 32.5

# WORKDAYS

13 23 24 23 22 25 21 1

% DIRECT LABOR 82% 81% 82% 82% 82% 83% 81% 81%

MD CAPABILITY 298 486 529 507 485 596 614 29

AVAILABILITY FACTOR

47% 86% 71% 80% 61% 74% 78% 91%

NOTES: 1. %Direct Labor = # Direct Labor/ # Personnel

2. MD Capability = (# Direct Labor) x (# Workdays) x (1.125) x (0.8) 3. Availability Factor = (Direct Labor MDs + R/T) / (MD Capability) x (0.8) 4. The low availability factor for September was due to force protection conditions

and lost days from typhoons.

Page 43: Deployment Completion Report · 2016. 11. 29. · for the entire seven months. TRAINING . ... ITEMPO days accumulated quickly for the 680-personnel Battalion during the deployment

4-33

CONSTRUCT DECONTAMINATION STATION AT BALLFIELD KO0-838

Detail personnel took over this project just as the finish phase was starting. The crew placed the exterior curbs, the sidewalk, the stoop, and the air conditioning pad. The wiring and finish electrical, the backflow preventer and the finish utilities were completed in addition to hanging and finishing drywall and installing ceramic and vinyl tile. This project served to reinforce the importance of surface preparation in order to achieve outstanding results. Start WIP: 59% End WIP: 100%. Project Data Personnel: 4 Duration: December 2000 - September 2001 Mandays: 605 Material Cost: $62,000 Cost Savings: $212,000 Specifications: Construct a 25’ by 18’ bathroom facility to include female and male bathrooms complete

with shower rooms and locker areas. A ceramic tile and sheetrock finish, toilet partitions, and utilities for sinks, toilets, and showers are included as well. The electrical outlets and lighting fixtures were also installed.

The completed Decontamination Station.

Status of the project at turnover.

Page 44: Deployment Completion Report · 2016. 11. 29. · for the entire seven months. TRAINING . ... ITEMPO days accumulated quickly for the 680-personnel Battalion during the deployment

4-34

LIBRARY ADDITION KO0-839

This project was a very challenging addition that utilized every Seabee rate. A sewer line was rerouted. A septic tank and manhole were discovered during construction that had to be removed. While a very basic project, it was an outstanding training tool and will greatly benefit the Chinhae community. The crew developed some fine masons and refined their formwork skills. Start WIP: 0% End WIP 100%. Project Data Personnel: 5 Duration: July 2001 – November 2001 Mandays: 500 Material Cost: $53,000 Cost Savings: $175,000 Specifications: The project scope included constructing a 20’ by 30’ addition onto the existing library.

The building is constructed of CMU block and has electrical to provide lighting and fixtures.

Seabee project scope complete, exterior finish is contracted and nearing completion.

The site before breaking ground.

Page 45: Deployment Completion Report · 2016. 11. 29. · for the entire seven months. TRAINING . ... ITEMPO days accumulated quickly for the 680-personnel Battalion during the deployment

4-35

OIC DISCRETIONARY/CAMP MAINTENANCE DETAIL CHINHAE

PROJECT LISTING

Knee wall and curbs at security 67 Sidewalk at galley 81 Sewer line replacement 22

Planter boxes at school 25 Painted Seabee spaces 5

TOTAL MANDAYS 200 CAMP MAINTENANCE Retile BEQ passageways 14

Install P-trap in female head 25 Install drainline for A/C at BEQ 5 Miscellaneous spaces/BEQ work 6 TOTAL MANDAYS 42

A sidewalk replaces a worn path leading to the galley.

Faulty sewer line connections were repaired by UT3 Georgiadis.

Knee wall and curbs at security

Replaced floor tile and repainted the BEQ

Page 46: Deployment Completion Report · 2016. 11. 29. · for the entire seven months. TRAINING . ... ITEMPO days accumulated quickly for the 680-personnel Battalion during the deployment

4-36

LABOR DISTRIBUTION SUMMARY FOR NMCB FIVE OKINAWA DEPLOYMENT – 2001 [Chinhae]

MANDAYS MAY JUN JUL AUG SEP OCT NOV DEC TOTAL % TOTAL

DIRECT LABOR 70 277 191 170 138 183 165 0 1194 61%

INDIRECT LABOR 112 103 62 86 85 94 73 5 620 32%

READINESS/TRAINING 34 34 17 14 13 16 10 6 144 7%

TOTAL 216 414 270 270 236 293 248 11 1958 100%

# PERSONNEL 17 17 11 11 11 11 11 11

# DL PERSONNEL 14.5 14.5 8 8 8 8 8 8

# WORKDAYS

12 23 24 24 21 26 22 1

% DIRECT LABOR 85% 85% 73% 73% 73% 73% 73% 73%

MD CAPABILITY 157 300 173 173 151 187 158 7

AVAILABILITY FACTOR

53% 83% 96% 85% 81% 85% 89% 70%

NOTES: 1. %Direct Labor = # Direct Labor/ # Personnel

2. MD Capability = (# Direct Labor) x (# Workdays) x (1.125) x (0.8) 3. Availability Factor = (Direct Labor MDs + R/T) / (MD Capability) x (0.8)

Page 47: Deployment Completion Report · 2016. 11. 29. · for the entire seven months. TRAINING . ... ITEMPO days accumulated quickly for the 680-personnel Battalion during the deployment

4-37

REPLACE TRANSFORMER 2183

IWO-876 This project was part of an on-going base wide transformer upgrade project. The existing transformers were open type and some contain PCB’s. This transformer did not contain PCB’s. It provided excellent experience in high voltage electrical work. Start WIP: 0%. End WIP 100%. Project Data Personnel: 4 Duration: May 2001 – November 2001 Mandays: 321 Material Cost: $279,452 Cost Savings: $112,000 Specifications: Remove existing 900 KVA pad mounted transformer, primary and secondary distribution

switchboard, and associated wiring and conduits. Install a new 750 KVA compartment transformer, low voltage distribution switchboard, grounding system and associated wiring, conduits, and wire gutters. Provide new secondary feeders to connect to existing feeders to remain. Modify existing 2.3-meter high chain link fence to accommodate the new equipment.

The crew is removing the fence around the transformer that was removed.

A view of the new transformer and switchgear from the blue diesel generator in the picture on the left.

Page 48: Deployment Completion Report · 2016. 11. 29. · for the entire seven months. TRAINING . ... ITEMPO days accumulated quickly for the 680-personnel Battalion during the deployment

4-38

CONSTRUCT THREE PICNIC PAVILIONS

IWO-877 This project contributed to an on-going base wide improvement of picnic areas. The three pavilions benefit the residents of several barracks. They provided excellent experience in concrete placement, framing and roofing. Start WIP: 0%. End WIP 100%. Project Data Personnel: 5 Duration: May 2001 – October 2001 Mandays: 313 Material Cost: $35,996 Cost Savings: $110,000 Specifications: Excavate for footings and underground electrical conduit. Form and install reinforcing steel,

concrete footings, columns, and a 7-meter x 7-meter concrete floor. Construct timber-framed, hip roof with ridge vent and apply asphalt shingles to exposed roof surfaces. Prepare and paint columns and wood fascia. Install lighting and receptacles.

Completed third pavilion.

Placement of fill for the slab for the third pavilion is in progress. Footer holes are being

dug.

Page 49: Deployment Completion Report · 2016. 11. 29. · for the entire seven months. TRAINING . ... ITEMPO days accumulated quickly for the 680-personnel Battalion during the deployment

4-39

CONSTRUCT HIGH SCHOOL BALLFIELD

IWO-878 This project converted a former housing area into a useful outdoor recreation area for the local school and housing residents. It provided excellent experience in earthwork and fine grading. The scope of work was revised towards the end of the project requiring the crew to transport approximately 1000 cubic meters of select fill to the site instead of receiving the fill from a contractor delivery. The work remaining at the end of the deployment included the hauling of the fill to the site and fine grading to establish the correct elevations and drainage. Start WIP: 0%. End WIP 86%. Project Data Personnel: 4 Duration: June 2001 – December 2001 Mandays: 208 Material Cost: $113,000 Cost Savings: $73,000 Specifications: Remove curb, gutter, and subgrade from existing street, 385 square meters of concrete sidewalk,

26 catch basins with piping, 1 fire hydrant with piping, and 78 trees. Scarify existing sod, fill and grade approximately 20,400 square meters of area with approximately 5000 cubic meters of fill. Construct 40 meters of curb and gutter.

Seabees remove underground pipe and drainage structures.

The site is ready for final grading.

Page 50: Deployment Completion Report · 2016. 11. 29. · for the entire seven months. TRAINING . ... ITEMPO days accumulated quickly for the 680-personnel Battalion during the deployment

4-40

POST OFFICE ADDITION

IWO-879 This project provided much needed additional storage space to the north side post office. An excellent job for the Seabees, it provided multi-trade experience to the Seabees with an emphasis on overhead concrete and block work. Start WIP: 0%. End WIP 100%. Project Data Personnel: 8 Duration: May 2001 – December 2001 Mandays: 1065 Material Cost: $80,688 Cost Savings: $373,000 Specifications: Remove existing canopies, concrete porches, trees, sidewalk, asphalt, etc. Construct new 136

square meter CMU block addition to the existing north side post office to include: new concrete floor, reinforced CMU block walls, concrete columns/bond beams, sloped concrete roof w/ parapet, copper flashing, downspouts, and gutter. Apply cold built up roofing. Install a 3.6-meter roll up door, interior metal furring, insulation, and gypsum board sheeting. Install interior conduit, associated wiring, fluorescent lighting, and receptacles. Place a 72 square meter concrete driveway and 78 square meters of sod. Install 22 meters of new steam pipe including insulation and stations. Prepare and paint all new interior surfaces, the existing concrete building, and the new addition.

The crew is placing reinforcing steel for the concrete floor of the post office

addition.

The addition is complete.

Page 51: Deployment Completion Report · 2016. 11. 29. · for the entire seven months. TRAINING . ... ITEMPO days accumulated quickly for the 680-personnel Battalion during the deployment

4-41

OIC DISCRETIONARY / CAMP MAINTENANCE DETAIL IWAKUNI

PROJECT LISTING MANDAYS

Construct Fence at Softball Fields 25 Construct Simulator Pad 95

TOTAL MANDAYS 120 CAMP MAINTENANCE TASKING ESA’s 4

MCD’s 24 Completed MCD Projects: Total 4

Construct Horseshoe Pits 5 Install computers/rework office 5 Install ice machine 5

TOTAL MANDAYS 28

Simulator pad Fence at softball field to protect bleachers.

Page 52: Deployment Completion Report · 2016. 11. 29. · for the entire seven months. TRAINING . ... ITEMPO days accumulated quickly for the 680-personnel Battalion during the deployment

4-42

LABOR DISTRIBUTION SUMMARY FOR NMCB FIVE OKINAWA DEPLOYMENT – 2001 [Iwakuni]

MANDAYS MAY JUN JUL AUG SEP OCT NOV DEC TOTAL % TOTAL

DIRECT LABOR

127 306 279 341 347 372 417 0 2189 65%

INDIRECT LABOR 68 129 135 135 118 146 124 5 860 25%

READINESS/TRAINING 40 102 27 24 30 34 58 19 334 10%

TOTAL 235 537 441 500 495 552 599 24 3383 100%

# PERSONNEL 27 27 27 27 27 27 27 27

# DL PERSONNEL 19 19 19 19 19 19 19 19

# WORKDAYS

12 23 24 24 21 26 22 1

% DIRECT LABOR 70% 70% 70% 70% 70% 70% 70% 70%

MD CAPABILITY 205 393 410 410 359 445 376 17

AVAILABILITY FACTOR

65% 83% 60% 71% 84% 72% 100% 89%

NOTES: 1. %Direct Labor = # Direct Labor/ # Personnel

2. MD Capability = (# Direct Labor) x (# Workdays) x (1.125) x (0.8) 3. Availability Factor = (Direct Labor MDs + R/T) / (MD Capability) x (0.8) 4. Typhoons prevented work or training on several workdays during July.

Page 53: Deployment Completion Report · 2016. 11. 29. · for the entire seven months. TRAINING . ... ITEMPO days accumulated quickly for the 680-personnel Battalion during the deployment

4-43

CONSTRUCT “P-3” FACILITY PK7-836

Detail personnel installed a complex dry pipe fire suppression system, tiled and finished four bathrooms, corrected leaks in the windows and roof, insulated the roof, and installed the exterior stairs. The project provided the crew with some good experience in many aspects of construction. Start WIP: 75% End WIP 100%. Project Data Personnel: 10 Duration: March 2000 – November 2001 Mandays: 1570 Material Cost: $423,200 Cost Savings: $550,000 Specifications: Construct a two-story, 40’ by 100’ pre-engineered building. The building has a

reinforced concrete foundation, concrete floor, male and female shower and heads, interior metal stud framing with gypsum wallboard covering, and a fire alarm system with a fire sprinkler system.

Finished interior of one of the four large rooms.

Finished exterior of the building with the stairs installed.

Page 54: Deployment Completion Report · 2016. 11. 29. · for the entire seven months. TRAINING . ... ITEMPO days accumulated quickly for the 680-personnel Battalion during the deployment

4-44

INSTALL PERIMETER FENCE AND LIGHTS PK1-850

The project provided the crew with some good electrical and fence installation experience. This project instilled a great sense of accomplishment with some good experience in project management. Start WIP: 0% End WIP 100%. Project Data Personnel: 4 Duration: August 2001 – November 2001 Mandays: 350 Material Cost: $55,500 Cost Savings: $123,000 Specifications: The project scope included the installation of approximately 1,000 lineal feet of 8’ chain

link fence with 3 strands of barbed wire on top. Also, installation of twenty-one 25’ light poles around the camp with underground conduit and electrical connections.

Finished fence with new light poles

Excavation for the conduit has begun.

Page 55: Deployment Completion Report · 2016. 11. 29. · for the entire seven months. TRAINING . ... ITEMPO days accumulated quickly for the 680-personnel Battalion during the deployment

4-45

OIC DISCRETIONARY / MEC-P MAINTENANCE AND REPAIR DETAIL POHANG

PROJECT LISTING MANDAYS Construct CMU block wall at CNFK 49 Equipment Loading 25

Electrical Repairs at CNFK 20 PEB Repairs 35 Miscellaneous Projects 38 TOTAL MANDAYS 167 CAMP MAINTENANCE ESA’s 84

SJO’s 78 MCD’s 317

Construct New Detail Office Spaces 235 Barracks Room Construction 55 Security Gate Lighting 15 Re-roofing Well Sites 12 TOTAL MANDAYS 479

The crew started a CMU block wall at CNFK, enclosing a communications trailer. The work was great training for BU’s.

Detail Pohang shipped out 14 pieces of CESE, 12 to Okinawa and 2 to Port Hueneme.

Installation of the walls for the new offices spaces inside the tension fabric structure has started.

The camp maintenance crew installed carpet in the lounge.

Page 56: Deployment Completion Report · 2016. 11. 29. · for the entire seven months. TRAINING . ... ITEMPO days accumulated quickly for the 680-personnel Battalion during the deployment

4-46

LABOR DISTRIBUTION SUMMARY FOR NMCB FIVE OKINAWA DEPLOYMENT – 2001 [Pohang]

MANDAYS MAY JUN JUL AUG SEP OCT NOV DEC TOTAL % TOTAL

DIRECT LABOR 68 127 179 270 330 515 356 32 1877 62%

INDIRECT LABOR 75 130 231 265 122 87 150 6 1066 33%

READINESS/TRAINING 9 12 22 27 39 30 26 8 173 5%

TOTAL 152 269 432 562 491 632 532 46 3116 100%

# PERSONNEL 18 18 25 31 32 33 33 33

# DL PERSONNEL 6 6 11.75 16.75 16.75 18.75 18.75 18.75

# WORKDAYS

13 23 24 24 21 26 23 2

% DIRECT LABOR 33% 33% 47% 54% 52% 57% 57% 57%

MD CAPABILITY 70 124 254 362 317 439 388 34

AVAILABILITY FACTOR

88% 90% 63% 66% 93% 99% 79% 94%

NOTES: 1. %Direct Labor = # Direct Labor/ # Personnel

2. MD Capability = (# Direct Labor) x (# Workdays) x (1.125) x (0.8) 3. Availability Factor = (Direct Labor MDs + R/T) / (MD Capability) x (0.8)

The Availability Factors for July and August are low due to the arrival of the additional personnel late in those months.

Page 57: Deployment Completion Report · 2016. 11. 29. · for the entire seven months. TRAINING . ... ITEMPO days accumulated quickly for the 680-personnel Battalion during the deployment

4-47

CONSTRUCT PEB FIRE STATION, HARIO SHIMA SA0-885

A fully encompassing project, beginning with site preparation to the finish work on interior office spaces. Challenges for the crews included the correct alignment of the footers and anchor bolts to receive the steel pre-engineered building skeleton, overhead power distribution, and corrugated metal sheeting. The crew was able to complete the concrete foundation and floor, all under-floor utilities, the 3” water main, the U-ditch around the building, the pre-engineered building, the personnel and roll-up doors, the landscaping, and approximately 40% of the structural steel for the mezzanine. Start WIP: 0% End WIP: 69% Project Data Personnel: 11 personnel Duration: May 2001 - March 2002 Mandays: 1775 Material Cost: $476,000 Cost Savings: $621,000 Specifications: This project consists of construction of a 40’ by 100’ steel fabricated building to

include two engine bays, a 16’ by 16’ hose drying tower, and berthing and administrative spaces. Construction included the installation of a reinforced concrete floor and foundation, partition walls and ceilings, electrical distribution, lighting fixtures and outlets, and a heating, ventilation, and air conditioning system. The crew will also install a new overhead power distribution line and transformer, a communication line, and a new 3” water line to the facility. A septic system with a leach field will be installed through Public Works Shops.

The exterior of the Fire Station at the end of the deployment.

The site as it appeared prior to construction.

Page 58: Deployment Completion Report · 2016. 11. 29. · for the entire seven months. TRAINING . ... ITEMPO days accumulated quickly for the 680-personnel Battalion during the deployment

4-48

Page 59: Deployment Completion Report · 2016. 11. 29. · for the entire seven months. TRAINING . ... ITEMPO days accumulated quickly for the 680-personnel Battalion during the deployment

4-49

DEMO HARIO ORDNANCE FACILITY 3022 SA9-861

The crew painstakingly demolished the structure using reverse construction techniques, so as not to disturb the lead paint coated framework that was remediated by Public Works and subsequently taken down by the crews. The demolition cleared the way for a new ordnance storage pre-engineered building. Start WIP: 0% End WIP: 100% Project Data Personnel: 10 personnel Duration: May 2001 - June 2001 Mandays: 132 Material Cost: $16,000 Cost Savings: $46,200 Specifications: This project consisted of the demolition of an 85’ by 50’ wooden structure.

Work included all of the demolition requirements for wooden structures, asphalt roofing, concrete foundations, flooring, ramps, and interior electrical. The crew prepared the site for a future pre-engineered building installation by grading and providing drainage.

The area for the new building after demolition was completed.

The building is in the process of being carefully dismantled.

Page 60: Deployment Completion Report · 2016. 11. 29. · for the entire seven months. TRAINING . ... ITEMPO days accumulated quickly for the 680-personnel Battalion during the deployment

4-50

CONSTRUCT PEB HARIO ORDNANCE SITE 3022

SA9-862 The new foundation for the pre-engineered building (PEB) was placed on top of the existing concrete pad from the original wooden structure. The new building is 10’ larger than the original structure, allowing for additional storage space. Some challenges for the crew included the proper alignment of the footers and anchor bolts to receive the steel skeleton and corrugated sheet metal. Start WIP: 0% End WIP: 100% Project Data Personnel: 7 personnel Duration: June 2001 - November 2001 Mandays: 575 Material Cost: $97,000 Cost Savings: $201,000 Specifications: This is a project to construct a 60’ by 85’ pre-engineered metal building at the

Hario Shima ordnance facility site 3022 and provide related grounding systems to four existing lightning masts. The PEB was constructed in accordance with the manufacturer’s erection manual on top of a concrete foundation with access ramps. The PEB will include a sliding panel door, two personnel doors, windows, and louvers. There is no interior electrical wiring or plumbing associated with this PEB.

The completed building.

The initial site condition after the demolition of the original building is completed.

Page 61: Deployment Completion Report · 2016. 11. 29. · for the entire seven months. TRAINING . ... ITEMPO days accumulated quickly for the 680-personnel Battalion during the deployment

4-51

CONSTRUCT SCOREBOARD NIMITZ PARK SA0-888

The crew carefully excavated the new underground electrical trench through the ballfield and erected the new scoreboard. Challenges included ensuring that the existing grass was not damaged and open trenches in a facility open to the public. The project provided the community with an electric scoreboard for the only little league field at Commander Fleet Activities Sasebo. Start WIP: 0% End WIP: 100% Project Data Personnel: 5 personnel Duration: November 2001-November 2001 Mandays: 133 Material Cost: $14,000 Cost Savings: $47,000 Specifications: Erect a pre-fabricated scoreboard in accordance with manufacture’s

specifications. Installation included trenching for underground conduit with associated power and control circuitry for the scoreboard to an existing booth.

The scoreboard that was replaced.

The completed scoreboard.

Page 62: Deployment Completion Report · 2016. 11. 29. · for the entire seven months. TRAINING . ... ITEMPO days accumulated quickly for the 680-personnel Battalion during the deployment

4-52

SCOREBOARD AND BOOTH, HARIO SA0-889

The crew expertly constructed a CMU block and cast-in-place concrete booth, new underground power, and a scoreboard. Challenges include installation of new underground flexible conduit and associated wire, transition from the concrete to CMU block, and open trenches during the excavation. The project provided this remote housing facility with the first scoreboard and booth for the playing field, improving everyone’s morale. Start WIP: 0% End WIP: 100% Project Data Personnel: 4 personnel Duration: July 2001-November 2001 Mandays: 180 Material Cost: $26,000 Cost Savings: $63,000 Specifications: This project entailed the construction of a booth in addition to the installation of

an electric scoreboard in accordance with the manufacturer’s specifications. The booth was constructed from CMU block and concrete and covered with a steel corrugated roof. Installation of the scoreboard included trenching for flexible underground conduit with associated power and control circuitry from the scoreboard to the new booth.

The completed scoreboard.

The ballfield before construction.

Page 63: Deployment Completion Report · 2016. 11. 29. · for the entire seven months. TRAINING . ... ITEMPO days accumulated quickly for the 680-personnel Battalion during the deployment

4-53

GROUNDING SYSTEM, BUILDING 3022 SA0-884

The crew expertly installed the secondary grounding to the existing grid without any problems. The secondary grid provides redundant grounding for the new pre-engineered building that was also built by NMCB FIVE. Start WIP: 0% End WIP: 100% Project Data Personnel: 3 personnel Duration: September 2001 - October 2001 Mandays: 61 Material Cost: $5,000 Cost Savings: $21,000 Specifications: This project corrects deficiencies in the building’s current grounding system and

will allow storage of live ordnance in the facility. The project scope consists of placement of a copper secondary-grounding grid that ties into the existing primary grid. The existing grid ties each of the masts together through copper grounding rods housed in a pre-cast inspection hand hole through which the entire primary grounding system is connected. The existing lightning masts and hand holes will remain in place.

A view of the lightning rods and connections to the secondary grounding grid.

The initial site condition after the demolition of the original building is completed.

Page 64: Deployment Completion Report · 2016. 11. 29. · for the entire seven months. TRAINING . ... ITEMPO days accumulated quickly for the 680-personnel Battalion during the deployment

4-54

CONSTRUCT LCAC PEB, SAKIBE SA0-874

The crew was responsible for the installation of the roofing, siding, doors, and all electrical for this project. Challenges for this project include working in an area where winds are dominant, ensuring a tight fit for panels on the roof and sides, and the installation of a mechanical roll-up door. The project provided for much needed storage area for personnel working on Landing Craft Air Cushions. Start WIP: 59% End WIP: 100% Project Data Personnel: 7 personnel Duration: March 2001 - October 2001 Mandays: 511 Material Cost: $137,000 Cost Savings: $179,000 Specifications: The project included the construction of a 40’ by 100’ steel pre-engineered

building (PEB) in accordance with the manufacturer’s erection manual. The project also has a concrete floor with footings, finish electrical, lights, and outlets. The PEB includes two roll-up doors, two personnel doors, and windows.

A view of the outside of the building after completion.

Initial site condition at turnover.

Page 65: Deployment Completion Report · 2016. 11. 29. · for the entire seven months. TRAINING . ... ITEMPO days accumulated quickly for the 680-personnel Battalion during the deployment

4-55

CONSTRUCT PEB MEZZANINE, SAKIBE SA0-886

The crew was responsible for the forming and placing of concrete for footers and the deck, steel fabrication, erection, and welding, and all electrical for this project. Challenges for this project include working in conjunction with the crew for project SA0-874, placement of quality concrete, ensuring quality welds, and the installation of all of the electrical. The project nearly doubles the storage capacity of the new Landing Craft Air Cushion facility. Start WIP: 0% End WIP: 100% Project Data Personnel: 7 personnel Duration: May 2001 - October 2001 Mandays: 267 Material Cost: $115,000 Cost Savings: $93,000 Specifications: This project entails the construction of a 38’ wide by 50’ long by 10’ high steel

mezzanine in a newly constructed pre-engineered building. The mezzanine is composed of steel framing with a steel/concrete floor system, a steel column foundation, and two steel stairways. It also includes ceiling lights and perimeter 120-volt outlets. The mezzanine was designed for a 600 kg per square-meter live load.

The completed mezzanine after painting.

The concrete pad with a cutout for the mezzanine foundation.

Page 66: Deployment Completion Report · 2016. 11. 29. · for the entire seven months. TRAINING . ... ITEMPO days accumulated quickly for the 680-personnel Battalion during the deployment

4-56

OIC DISCRETIONARY/CAMP MAINTENANCE DETAIL SASEBO

PROJECT LISTING MANDAYS Security Augment 611

Demo and Reconstruct Concrete Pad at Port OPS Center 11 Construct Taxi Stand and Install Bench 20 Install Benches Tables & Trash-cans at Security Pavilion 9 Install Scoreboard at Fleet Gym 42 Construct Splash Blocks for Hario Ordnance Facility 9 Construct Metal Grate for Access Ramp 9

TOTAL MANDAYS 711 CAMP MAINTENANCE

MCD’s 50 Replace Lights and Ballasts in the Overhead Lights in the CM Shop 12

Install New Shop Equipment 12 Repair Concrete Curbing in the HAZMAT Locker 2 Repair Work for the Steel Shop 10 Alfa Shop Reorganization (tool room and ARP) 6 Field Day Spaces for Turnover 8

TOTAL MANDAYS 50

The new shop equipment that was installed.

The installed scoreboard at Fleet Gym. The new Taxi Stand and bench.

Page 67: Deployment Completion Report · 2016. 11. 29. · for the entire seven months. TRAINING . ... ITEMPO days accumulated quickly for the 680-personnel Battalion during the deployment

4-57

LABOR DISTRIBUTION SUMMARY FOR NMCB FIVE OKINAWA DEPLOYMENT – 2001 [Sasebo]

MANDAYS MAY JUN JUL AUG SEP OCT NOV DEC TOTAL %

TOTAL DIRECT LABOR 208 604 487 480 404 657 795 0 3635 69%

INDIRECT LABOR 96 192 200 192 168 208 184 0 1240 23%

READINESS/TRAINING 51 48 67 67 65 97 37 0 432 8%

TOTAL 355 844 754 739 637 962 1016 0 5307 100%

# PERSONNEL 36 35 35 35 35 36 46 37

# DL PERSONNEL 27 25 25 25 25 30 35 27

# WORKDAYS

12 24 25 24 21 26 23 0

% DIRECT LABOR 75% 71% 71% 71% 71% 83% 76% 73%

MD CAPABILITY 292 540 563 540 473 702 725 0

AVAILABILITY FACTOR

71% 97% 59% 81% 79% 86% 92% 100%

NOTES: 1. %Direct Labor = # Direct Labor/ # Personnel

2. MD Capability = (# Direct Labor) x (# Workdays) x (1.125) x (0.8) 3. Availability Factor = (Direct Labor MDs + R/T) / (MD Capability) x (0.8) 4. The drop in availability factor for July is due to personnel changes in the

detail.

Page 68: Deployment Completion Report · 2016. 11. 29. · for the entire seven months. TRAINING . ... ITEMPO days accumulated quickly for the 680-personnel Battalion during the deployment

4-57

APPRENTICESHIP PROGRAM YO1-601

Detail personnel were assigned to the Public Works Center to work alongside skilled Japanese journeymen. This program was the first ever instituted in Yokosuka, Japan. The Detail was originally tasked with 500 mandays, however due to the events of 11 September 2001, the program was shortened to 220 mandays. Challenges encountered were the language and customs barriers and different construction practices.

Project Data Personnel: 4 Duration: June 2001 - September 2001 Mandays: 220 Material Cost: $0 Cost Savings: $0 Specifications: The eight participants of the program were required to work the same schedule

as the PWC employees. The four Builders participated in an abbreviated version of PWC’s own in house apprenticeship program. The two Construction Electricians also participated in a similar version, but were taken out of the shop and into the field quicker to get more hands on experience. The two Utilitiesmen worked with the Emergency Service Division and went directly out into the field and received extremely valuable hands on Public Works experience.

BUCN Kastl and BU3 Pacheco are standing with the workers from PWC Yokosuka with whom they had worked.

UT3 Williams works on the seawater cooling system.

Page 69: Deployment Completion Report · 2016. 11. 29. · for the entire seven months. TRAINING . ... ITEMPO days accumulated quickly for the 680-personnel Battalion during the deployment

4-58

CONSTRUCT OFFICE SPACES PEB YO8-856

Detail personnel took over the project with only the grade beams and footers in place. The crew then backfilled and compacted in preparation for the placement of the first floor concrete, erected the structural steel, installed and placed concrete for the second floor, and then completed the rough and finish work. Start WIP: 50% End WIP 100%. Project Data Personnel: 11 Duration: October 2000 - November 2001 Mandays: 1969 Material Cost: $495,000 Cost Savings: $689,000 Specifications: Construct a two story, 40’ by 100’ pre-engineered building to serve as office

spaces for the Fleet Industrial and Supply Center (FISC), Tsurumi Site. The building is a Butler building with 3000 square feet of office spaces and 3000 square feet of storage and maintenance spaces. This facility includes male and female heads, complete with showers, locker rooms, sinks, and water closets.

The finished pre-engineered building.

Progress of the building at turnover.

Page 70: Deployment Completion Report · 2016. 11. 29. · for the entire seven months. TRAINING . ... ITEMPO days accumulated quickly for the 680-personnel Battalion during the deployment

4-59

F-69 INTERIOR MODS YO1-876

This project was a late addition to the Detail tasking. This project consisted of modifying the interior of Building F-69. These modifications will enable the Physical Security Engineering Field Activity to efficiently utilize a warehouse that is currently under construction and scheduled to finish in January 2002. Challenges encountered were the cramped and cluttered workspace above the ceiling, the requirement to keep the facility operational despite having to move 14 electrical power panels, and the demolition of two reinforced concrete vaults. Start WIP: 0% End WIP 100%. Project Data Personnel: 6 Duration: July 2001 - November 2001 Mandays: 550 Material Cost: $230,000 Cost Savings: $193,000 Specifications: Modify the existing interior layout of the facility to make it compatible with a

new warehouse that is being constructed by a civilian contractor while ensuring that the facility remains operational at all times. Demolish old walls and construct new walls to provide access to three large, roll-up doors via two 12’ wide hallways. In the demolition of the three walls, 14 power panels and the associated electrical circuits all had to be relocated to nearby walls.

The newly created office space where the old concrete vault originally stood.

The original configuration of the electrical panels on the wall of a concrete vault at

turnover.

Page 71: Deployment Completion Report · 2016. 11. 29. · for the entire seven months. TRAINING . ... ITEMPO days accumulated quickly for the 680-personnel Battalion during the deployment

4-60

REBUILD BUILDING A-65 YO4-821

Detail personnel took over the project with only finish work remaining. This facility will provide a bathhouse for the employees of the Ship Repair Facility in Yokosuka, Japan. The Detail was tasked with finishing the electrical, plumbing, drywall, doors, and finishes. Challenges encountered included constructability issues and identifying the proper materials. Start WIP: 87% End WIP 100%. Project Data Personnel: 4 Duration: May 2000 - October 2001 Mandays: 1290 Material Cost: $238,624 Cost Savings: $452,000 Specifications: Construct a 25’ by 48’ pre-engineered building to serve as a bathhouse for the

employees of the Ship Repair Facility, Yokosuka, Japan. The building contains an office space, men’s and women’s heads, showers, and locker rooms. The heads, locker rooms, and showers all have a mosaic tile floor and the showers have ceramic tile walls. The office has vinyl tiles for its flooring.

The front office space is completed.

Progress on the building interior at turnover.

Page 72: Deployment Completion Report · 2016. 11. 29. · for the entire seven months. TRAINING . ... ITEMPO days accumulated quickly for the 680-personnel Battalion during the deployment

4-61

FUJI DETAIL SPACES ESTABLISHMENT FJ1-813

This project was a late addition to the Detail tasking. The crewmembers moved all of Detail Yokosuka’s assets to Camp Fuji for the establishment of a permanent detail site. Start WIP: 0% End WIP 100%. Project Data Personnel: 10 Duration: October 2001 – December 2001 Mandays: 300 Material Cost: $20,000 Cost Savings: $105,000 Specifications: The change of permanent NMCB detail sites included moving all tools and parts

associated with 12 pieces of Civil Engineer Support Equipment, the Central Tool Room, office furniture, ADP assets, excess materials, and other support equipment. It also included basic renovation work, painting, cleaning, and patching drywall. The Detail is also tasked with setting up a Central Tool Room, the Construction Mechanic Shop, and all office spaces.

The old detail spaces at Yokosuka Naval Base. The new detail spaces at Camp Fuji.

Page 73: Deployment Completion Report · 2016. 11. 29. · for the entire seven months. TRAINING . ... ITEMPO days accumulated quickly for the 680-personnel Battalion during the deployment

4-62

OIC DISCRETIONARY/ CAMP MAINTENANCE DETAIL YOKOSUKA

PROJECT LISTING MANDAYS Pave Green Park 55 Construct boxes for FAST Marines 9 Install catch basins at the Tsurumi pre-engineered building 10 Build boxes for Security-AT/FP 3 Renovate building A-20 68 Install flooring and electrical work in building F-69 25 Construct stand for radar antenna 2 TOTAL MANDAYS 172 CAMP MAINTENANCE MCD’s 150

Facility inspection 4 Grounds maintenance 26 Patching windows in old facilities 2 Securing the camp for typhoon Pabuk 15

Securing the camp for typhoon Danas 15 Improving camp security 12 Painting the CM shop 17 Repainting the detail spaces 28 Preparations for turnover of spaces to CFAY 31 TOTAL MANDAYS 150

The park area was paved using decorative brick pavers, enhancing the appearance of the park.

New drywall has been hung to cover the existing damaged wall covering.

Page 74: Deployment Completion Report · 2016. 11. 29. · for the entire seven months. TRAINING . ... ITEMPO days accumulated quickly for the 680-personnel Battalion during the deployment

4-63

LABOR DISTRIBUTION SUMMARY FOR NMCB FIVE OKINAWA DEPLOYMENT – 2001 [Yokosuka]

MANDAYS MAY JUN JUL AUG SEP OCT NOV DEC TOTAL % TOTAL

DIRECT LABOR 176 378 480 436 351 489 745 0 3055 63%

INDIRECT LABOR 117 207 197 207 189 257 228 9 1411 29%

READINESS/TRAINING 41 49 41 66 34 74 29 33 367 8%

TOTAL 334 634 718 709 574 820 1002 42 4833 100%

# PERSONNEL 31 29 30 30 30 32 40 40

# DL PERSONNEL 25.5 23.5 24.5 24.5 24.5 26.5 32.5 32.5

# WORKDAYS

13 23 24 23 22 25 21 1

% DIRECT LABOR 82% 81% 82% 82% 82% 83% 81% 81%

MD CAPABILITY 298 486 529 507 485 596 614 29

AVAILABILITY FACTOR

58% 70% 79% 79% 64% 76% 100% 91%

NOTES: 1. %Direct Labor = # Direct Labor/ # Personnel

2. MD Capability = (# Direct Labor) x (# Workdays) x (1.125) x (0.8) 3. Availability Factor = (Direct Labor MDs + R/T) / (MD Capability) x (0.8) 4. Travel time of 2 hours per day per crewmember to Tsurumi is not accounted

for in the Manday Equivalent, therefore the lost production time (travel time) reduces the overall Availability Factor.

Page 75: Deployment Completion Report · 2016. 11. 29. · for the entire seven months. TRAINING . ... ITEMPO days accumulated quickly for the 680-personnel Battalion during the deployment

4-64

DFT ALASKAN ROAD JK0-667

The Alaska deployment provided an excellent environment to conduct blasting and quarry operations. The DFT completed 78 blasts during the 4-month deployment, creating 151,281 cubic yards of aggregate rock by detonating 125 Kilotons of explosives. In addition, 8 kilometers of existing road and 5 kilometers of untouched wilderness were continuously surveyed. Formal training included five days of turnover drilling with NMCB FOUR, four days of rock drilling training, and a one-week blasting fundamentals course. Start WIP: 0% End WIP:100% Project Data Personnel: 20 Duration: May 2001 – September 2001 Mandays: 1566 Material Cost: N/A Cost Savings: $548,000 Specifications: DFT Alaska members conducted surveying, drilling, and blasting operations in

support of the Joint Task Force Operation Alaskan Road. In addition, the DFT provided training in rock drilling operations to National Guard, Marine, and Army personnel. The road project will create a 14.8-mile stretch of road through untouched wilderness and granite rock-mountains along the west coast of Annette Island, Alaska. When complete, the road will provide the villagers of Metlakatla access to ferry service and supplies from the local town of Ketchikan. This is an Innovative Readiness and Training (IRT) project headed by Alaska Command (ALCOM).

Two drills operating on a large shot pattern (below). One of 78 blasts that NMCB 5 conducted during DFT Alaskan Road (right).

Page 76: Deployment Completion Report · 2016. 11. 29. · for the entire seven months. TRAINING . ... ITEMPO days accumulated quickly for the 680-personnel Battalion during the deployment

4-65

DFT EAST TIMOR JK1-687 and JK1-685

During the revolution of 1999, the water treatment plants were neglected and fell to ruin due to lack of maintenance and repair parts. NMCB FIVE assisted United States Support Group East Timor (USGET) with the construction and repair of three-water treatment plants in the Dili city limit: Benemauk, Bemos, and Lahane. These three WTP’s supply the entire Dili district with water.

Project Data Personnel: 12

Duration: May 2001 – Oct 2001

Mandays: 1009

Material Cost: $ 374,000

Cost Savings: $ 353,000

Specifications: Scope of work included installation of static mixers, cleaning of tanks and settlement ponds,

installation of perimeter security fence at Lahane reservoir, and replacement of deteriorated water lines. Developed the design of a new chlorinating system that requires less maintenance while providing a better source of chemicals for purification of the water entering the distribution system. Provided training to the local populace on correct maintenance for the water treatment plants. Also, improve community relations through projects in the community, improving the standard of living.

Operational testing of a new valve. View of a new static mixer installed at one of

the treatment plants.

A new water spigot installed outside a school as a part of the community

relations projects.

Page 77: Deployment Completion Report · 2016. 11. 29. · for the entire seven months. TRAINING . ... ITEMPO days accumulated quickly for the 680-personnel Battalion during the deployment

4-66

DFT EVERETT WASHINGTION CONSTRUCT PEB RECYCLING CENTER

EV1-805

This project provided an outstanding opportunity for steelworkers and builders to work on the erection of a pre-engineered building. The importance of correct placement of the structural members of the building was repeatedly emphasized. A Butler Industries technical representative demonstrated the correct assembly of the M-24 roof sheeting system. The crew was then able to quickly assemble the roof for the building. Start WIP: 25% End WIP: 96% Project Data Personnel: 6 Duration: August 2001 – January 2002 Mandays: 550 Material Cost: $163,000 Cost Savings: $193,000 Specifications: This project entails construction of a 75’ by 110’ pre-engineered building with

concrete footers, grade beam and four 27’6’’ by 75’ concrete floor placements. It also includes power installation for overhead lighting, office, and recycling equipment as well as installation of a deep sink with a heater. Drainage lines in designated areas of the concrete floors will be provided. In addition, the crew will install two overhead gas pipe heater manifolds.

The siding of the building is under construction.

The forms for the footers are being placed.

Page 78: Deployment Completion Report · 2016. 11. 29. · for the entire seven months. TRAINING . ... ITEMPO days accumulated quickly for the 680-personnel Battalion during the deployment

4-67

Page 79: Deployment Completion Report · 2016. 11. 29. · for the entire seven months. TRAINING . ... ITEMPO days accumulated quickly for the 680-personnel Battalion during the deployment

5-1

SUPPLY/LOGISTICS/EQUIPMENT

NMCB FIVE’s Supply Department had a very successful deployment supporting the Battalion’s construction mission. One major tasking early in the deployment was the swap out of the

existing Table of Allowance (TOA) with a new P25 TOA valued at over $39.2 million. This process began back at homeport with several planning meetings and strategy sessions between the Battalion and Third Brigade’s N43 shop. After the TOA arrived on island, coordination between Supply and Alfa Company ensured a very successful evolution, which was completed with minimal disruption to operations and ahead of schedule. Alfa Company removed the existing TOA from the Dehumidified Warehouse, staged the containers in the Supply Yard, and positioned the new containers in their appropriate locations within

the warehouse, incurring zero mishaps while drastically increasing the Battalion’s ability to respond to a contingency. One immediate advantage enjoyed by the Battalion was utilization of new tools which positively impacted projects and troop morale. The “Professionals” maintained their stellar reputation by successfully passing all inspections and assist visits, earning numerous kudos and “Bravo Zulus.” Several operations were recognized for their superb service, receiving praises of “Outstanding.” These were Financial Management, Services (Barber, Postal, and Food Service), Material Liaison Office (MLO) and Det Support. Other operations were just as impressive and maintained Supply’s reputation as a “Can Do” organization providing “Service to the Bees.” 1. OUTLET SUMMARIES: a. SUPPLY: The Supply Office was the driving force behind the successful Okinawa deployment, flawlessly managing three Operating Targets (OPTARs) valued at over $1.4 million. Five Storekeepers, assisted by three Japanese Nationals, processed repair part, consumable, and camp maintenance requisitions supporting Camp Shields and twelve construction projects throughout Okinawa. The requisitions included 124 NORS requisitions valued at $59,000 and 114 ANORS requisitions valued at $18,500. The Supply office also implemented an assertive tracking process to obtain timely status on outstanding requirements. The office also aggressively managed the Material Obligation Validation and Overaged Requisitions programs to yield over $25,000 in recouped OPTAR funds. Both main

Page 80: Deployment Completion Report · 2016. 11. 29. · for the entire seven months. TRAINING . ... ITEMPO days accumulated quickly for the 680-personnel Battalion during the deployment

5-2

body and detail sites effectively utilized the Government Purchase Card, which gave projects the added plus of receiving materials in a timelier manner, some on a “same day” basis. The Office significantly reduced the number of outstanding requirements by aggressively expediting procurement through the homeport staff, resulting in zero downtime for equipment and projects. The Supply Office also managed $920K in travel funds, processed over 1,800 deployment per diem orders and 100 travel orders. Supply personnel aggressively tracked outstanding travel requirements resulting in the successful liquidation and recoupment of over $50,000 in much needed travel funds.

b. FOOD SERVICE: Camp Shields’ galley underwent tremendous improvement during the deployment. Some of the improvements were new food production equipment, new floor tiling, ceiling fans with lights, a new air conditioning unit for the dry storeroom and installation of a new bumper on the loading dock. The Galley staff, working with the Camp Czar, initiated a $120,000 phased galley equipment replacement program that was previously non-existent. With time, money, and continued interest, the galley will one day compete for the Ney Award and will reach the “Five-Star” plateau. The Food Service Officer and Leading MS

revised the menu to include several special meals throughout the course of each month: Mongolian BBQ, Okinawan, Mexican, Italian, Hillbilly, Soul, and Surf-n-Turf nights. Our salad bar expanded to over 28 items, with a selection of at least eight fruit items per meal. The staff shined when the Navy Food Management teams from Hawaii and Japan, as well as Third Brigade’s Logistics Management Assist (LMA) Team, came aboard to review the operation. Inspectors were highly impressed with the high level of professional knowledge, morale, teamwork and eagerness. To the MS staff, a hearty and well-deserved “Can Do.”

c. DISBURSING: FIVE’s Disbursing Clerks helped stimulate the local economy, as well as the economy stateside, by accurately maintaining over 650 pay accounts that pumped over $2.3 million per pay period into the market. By utilizing the UMIDS system to offer real-time online access to members pay accounts, the DKs were able to maintain their superior customer service and continue to provide prompt solutions to pay discrepancies. The IATS system was another tool used to enhance

Page 81: Deployment Completion Report · 2016. 11. 29. · for the entire seven months. TRAINING . ... ITEMPO days accumulated quickly for the 680-personnel Battalion during the deployment

5-3

troop morale. The system computed all travel claims as well as the all-important deployment per diem payments. Even though most of the office’s functions are automated and most payments are done electronically, funds are still needed and were readily accessible from the Community Bank located on Kadena Air Base.

The Crow’s Nest, an in-camp MWR facility operated by CFAO, offered a personal check cashing service of $100 per person per day. This was in addition to Disbursing’s in-house check cashing policy for Battalion members. Disbursing did not offer currency exchange because of the easy access at the Crow’s Nest. d. POSTAL: NMCB FIVE offered a fully functional post office manned by three Postal Clerks who expeditiously received and processed over 45,000 pounds of mail. The Post Office provided services to both Battalion and non-Battalion customers that included all functions normally found at large scale post offices, including money orders, stamps, and a wide array of shipping materials, ringing up sales in excess of $60,000. Both incoming and outgoing mail was shipped through Kadena’s Air Terminal and took approximately 7 to 10 days to reach stateside destinations and arrive in country. Incoming mail was also processed through Commander Fleet Activities Okinawa’s (CFAO) postal facility, with the same 7 to 10 day window. Space available parcels took anywhere from 14 days to 2 months. Always looking to improve, the Post Office was wired to support an Integrated Retail Terminal that will bring the outlet up to standard with a typical stateside operation, NMCB FOUR should put the system in action. Latex gloves, surgical masks, and bleach for decontamination were issued to reduce the risk of bioterrorism associated with the tragic events of September 11. e. BERTHING: As part of the long-range camp improvement plan, Camp Shields underwent a continuing barracks renovation program during the Battalion’s deployment. This created a significant challenge for the Barracks Manager and his staff. Before arriving on camp, the Battalion was informed of the pending demolition of two occupied barracks in conjunction with the renovation of one barracks building, reducing the number of beds on Camp by 62. Building 7142 was finally completed and transferred to the Battalion in late summer, giving several First Class Petty Officers new rooms with vast improvements in appearance and functionality over the old rooms. Although the renovated facilities enhanced the resident’s quality of life tremendously, the ongoing construction limited space and forced many personnel to move from room to room. In addition, space for turnover was extremely tight. All E-4 and below personnel were tripled up and all E-5 personnel were doubled up. With the arrival of FIVE’s Augment unit, most residents of the Hilton were forced to live three to a room for approximately one week. This also happened when the Detail personnel returned to Camp in preparation for redeployment to homeport. With Building 7147 going down for demolition, the Chiefs were moved from their quarters to Building 7146, displacing the First Class Mess in the process. The First Class Mess resurfaced in Building 7141.

Page 82: Deployment Completion Report · 2016. 11. 29. · for the entire seven months. TRAINING . ... ITEMPO days accumulated quickly for the 680-personnel Battalion during the deployment

5-4

f. CENTRAL TOOL ROOM (CTR): The Storekeeper, Builders, Construction Electrician, Construction Mechanic, and Steelworkers assigned to CTR supported thirteen main body and camp maintenance projects throughout the island. CTR was responsible for the inventory, preventive maintenance, and management of a $1.4 M inventory. This consisted of 205 TOA and 55 augment tool kits, 2,896 shelf stock line items, 424 electrical tools, and 80 gas/pneumatic power tools. During the deployment, the staff completed several wall-to-wall inventories, in addition to their normal

workload. The staff was able to maintain customer service hours during the TOA swap by implementing an onsite TOA kit exchange schedule and lunchtime issue hours that minimized production delays and increased efficiency. The crew exchanged two hundred tool kits on-site during a three-week span. g. MATERIAL LIAISON OFFICE (MLO): MLO did an outstanding job of providing construction materials valued at over $700 K to all main body and camp maintenance projects, as well as to twenty-five Detail projects, despite issues with the prime vendor contract. The Office also expertly managed project funding in excess of $6.1 million for both main body and detail projects, enabling a transition between fiscal years with minimal work stoppages. During the Management Assist Visit (MAV) and the LMA, the outlet posted an inventory validity of 100 percent, receiving the highest praise from the Brigade and Regiment. The inspectors rated MLO as the best operation they had seen over the last three years. The shop also established a positive foundation for the succeeding Battalion (NMCB FOUR). h. CENTRAL SUPPLY AND RECEIVING (CSR): This outlet was used mainly to store supply consumables and stage incoming materials. It was also an integral contributor in the Detail and DFT supply pipeline, ensuring that urgently required material was shipped in a timely manner. One Second Class Storekeeper and two Third Class Storekeepers were assigned to the outlet. i. GREENS ISSUE/INFANTRY GEAR STOREROOM: Two Ship’s Servicemen and one Storekeeper manned the 782/Infantry Gear warehouse and maintained accountability over a $1.2 million inventory ensuring a validity rate of 99 percent. They also maintained complete accountability of the radiac inventory, something that became highly visible after the September 11 attack. Both SHs doubled as the Battalion Barber.

Page 83: Deployment Completion Report · 2016. 11. 29. · for the entire seven months. TRAINING . ... ITEMPO days accumulated quickly for the 680-personnel Battalion during the deployment

5-5

Although the majority of the 782 gear at Camp Shields is old and worn, the Greens Issue staff maintained the gear in the best ready-for-issue condition possible. Unfit for issue items were turned in to DRMO at Camp Kinser. The Battalion’s well-maintained warehouse received commendatory comments from the inspectors during the highly successful LMA. j. AUTOMATED REPAIR PARTS STOREROOM: One Storekeeper Second Class, one Storekeeper Seaman and one Construction Mechanic Constructionman re-engineered the Automotive Repair Parts process, improving parts availability by 15%, parts issue time to 15 minutes, and NORS turnaround time by 75%. ARP has been tasked with validating the CESE COSAL against the new P25M configuration, a very labor intensive process that will eventually yield an automotive repair parts TOA configured to support any contingency. Validation of the current 70,000 line item inventory is a top priority, but will be a turnover item with FOUR. 2. EQUIPMENT: Alfa Company became responsible for 252 pieces of Civil Engineer Support Equipment (CESE) upon arrival to Okinawa, Japan. Thirteen pieces of CESE were on deadline and equipment availability was 89% upon turnover in May 01. During the deployment, the deadline reached a high of thirteen pieces of CESE and a low of eight. During the 7 months on island, Alfa Company maintained the equipment availability at 88%. At turnover in December 01, 8 pieces of CESE were on deadline and equipment availability was at 94 percent. NMCB FIVE achieved these improvements despite the high equipment demands of 235,058 miles and 3,717 hours.

EQUIPMENT POPULATION (ORGANIC AND AUGMENT)

Vehicles Beep May 01

Jun 01 Jul 01 Aug 01

Sep 01 Oct 01 Nov 01

Beep

In Service 138 138 141 166 163 165 165 169 167 In Preservation

114 114 113 114 120 118 115 114 114

Total 252 252 254 280 283 283 280 283 281

Page 84: Deployment Completion Report · 2016. 11. 29. · for the entire seven months. TRAINING . ... ITEMPO days accumulated quickly for the 680-personnel Battalion during the deployment

5-6

PM & INTERIM REPAIR ERO SUMMARY

Month Repairs PM Total PM:INT Ratio May 01 49 48 97 .98:1 Jun 01 34 108 142 3.2:1 Jul 01 41 134 175 3.3:1 Aug 01 47 110 157 2.3:1 Sep 01 39 93 132 2.4:1 Oct 01 24 96 120 4:1 Nov 01 35 109 144 3.1:1 Total 240 601 841 2.5:1

EQUIPMENT AVAILABILITY STATUS (ORGANIC ONLY)

Beep May 01

Jun 01 Jul 01 Aug 01

Sep 01 Oct 01 Nov 01

Beep

On Deadline Auto Construction MHE

2 7 4

2 7 4

4 6 0

4 6 0

5 5 0

4 6 0

3 5 0

2 7 0

2 6 0

Total 13 13 10 10 10 10 8 9 8 % Availability

89%

89%

88%

85%

87%

87%

89%

88%

97%

Page 85: Deployment Completion Report · 2016. 11. 29. · for the entire seven months. TRAINING . ... ITEMPO days accumulated quickly for the 680-personnel Battalion during the deployment

Encl. 1 4-4

Project Title - JK8-812 Codes: O=Off Project Number - Ships Platform S=Start P=In Progress Company/Det - C. CO Period Covered 24 JUL to 06 AUG C=Complete SC=Start/Complete in 1 day Date: 24 Jul Page: 1 of 1 Construction Activity DATES Crew No. Title 24 25 26 27 28 29 30 31 1 2 3 4 5 6 Size Remarks 5000 cross-brace's p p p p t o p p p p p o o p 2 5015 top platform s p p p t o p p p p p o o p 1 pending on I-beam add-on 5050 weld elevation s p p p t o p 1 5020 weld elev up s p o o p 9 4 EO's, 5 SW's Assumptions: Needed to change schedule to do I-Beam reorder

Page 86: Deployment Completion Report · 2016. 11. 29. · for the entire seven months. TRAINING . ... ITEMPO days accumulated quickly for the 680-personnel Battalion during the deployment

Encl 2 4-5

TWO WEEK RISK ASSESSMENT PROJECT # JK8-812 SHIP'S PLATFORM DATE: 24 JUL 01 PG 1 OF 3 (1) ACTIVITY (2) HAZARDS (3) PRECAUTIONS/CHECKS (4) FREQ (5) PRIMARY RESPONSIBILITY (6) RAC

5000 Gas welding and cutting

Inspect torches at beginning of shift for leaking shutoff valves, couplings and tip connections D SW2 Barnett 1

Arc Welding and cutting

Only cable free from repair or splices for a minimum distance of 10' from the cable end to which the electrode holder is connected shall be used D SW2 Barnett 2

Fire

Move objects to be welded, cut or heated to a designated safe place

D SW2 Barnett 2

Arc welding caution signs

"Arc welding in progress" signs shall be visible at all times when work is being performed D SW2 Barnett 3

Arc welding ground cable

Ground return cable shall have a safe current carrying capacity equal to or greater than max. welder output

D SW2 Barnett 1

Power tools

All grinding machines shall be supplied with sufficient power to maintain spindle speed at safe levels D SW2 Barnett 3

Noise

Hearing protection will be worn when levels reach 84dB

D SW2 Barnett 4

5015 Falling

Employees working 6' or higher with an unprotected side shall be protected from falling by the use of guard rail systems/fall protection D SW2 Barnett 1

Gas welding and cutting

Inspect torches at beginning of shift for leaking shutoff valves, couplings and tip connections D SW2 Barnett 1

Arc Welding and cutting

Only cable free from repair or splices for a minimum distance of 10' from the cable end to which the electrode holder is connected shall be used D SW2 Barnett 1

Fire

Move objects to be welded, cut or heated to a designated safe place

D SW2 Barnett 2

Page 87: Deployment Completion Report · 2016. 11. 29. · for the entire seven months. TRAINING . ... ITEMPO days accumulated quickly for the 680-personnel Battalion during the deployment

Encl 2 4-6

TWO WEEK RISK ASSESSMENT PROJECT # JK8-812 SHIP'S PLATFORM DATE: 24 JUL 01 PG 2 OF 3 (1) ACTIVITY (2) HAZARDS (3) PRECAUTIONS/CHECKS (4) FREQ (5) PRIMARY RESPONSIBILITY (6) RAC

Arc welding caution signs

"Arc welding in progress" signs shall be visible at all times when work is being performed D SW2 Barnett 3

Arc welding ground cable

Ground return cable shall have a safe current carrying capacity equal to or greater than max. welder output D SW2 Barnett 1

Material handling

Prior to unloading steel, examine the load thoroughly to ensure load has not shifted or created a hazard for employees D SW2 Barnett 3

Power tools

All grinding machines shall be supplied with sufficient power to maintain spindle speed at safe levels D SW2 Barnett 3

5050 Gas welding and cutting

Inspect torches at beginning of shift for leaking shutoff valves, couplings and tip connections D SW2 Barnett 1

Arc Welding and cutting

Only cable free from repair or splices for a minimum distance of 10' from the cable end to which the electrode holder is connected shall be used D SW2 Barnett 1

Fire Move objects to be welded, cut or heated to a designated safe place D SW2 Barnett 2

Arc welding caution signs

"Arc welding in progress" signs shall be visible at all times when work is being performed D SW2 Barnett 3

Arc welding ground cable

Ground return cable shall have a safe current carrying capacity equal to or greater than max. welder output D SW2 Barnett 1

Power tools

All grinding machines shall be supplied with sufficient power to maintain spindle speed at safe levels D SW2 Barnett 3

Noise Hearing protection will be worn when levels reach 84dB D SW2 Barnett 4

5020 Gas welding and cutting

Inspect torches at beginning of shift for leaking shutoff valves, couplings and tip connections D SW2 Barnett 1

Page 88: Deployment Completion Report · 2016. 11. 29. · for the entire seven months. TRAINING . ... ITEMPO days accumulated quickly for the 680-personnel Battalion during the deployment

Encl 2 4-7

TWO WEEK RISK ASSESSMENT PROJECT # JK8-812 SHIP'S PLATFORM DATE: 24 JUL 01 PG 3 OF 3

(1) ACTIVITY (2) HAZARDS (3) PRECAUTIONS/CHECKS (4) FREQ (5) PRIMARY RESPONSIBILITY (6) RAC

Arc Welding and cutting

Only cable free from repair or splices for a minimum distance of 10' from the cable end to which the electrode holder is connected shall be used D SW2 Barnett 1

Fire Move objects to be welded, cut or heated to a designated safe place D SW2 Barnett 2

Falling

Employees working 6' or higher with an unprotected side shall be protected from falling by the use of guard rail sysemts/fall protection D SW2 Barnett 1

Framing

Employees working 6' or higher with an unprotected side shall be protected from falling by the use of guard rail sysemts/fall protection W SW2 Barnett 3

Rigging Inspect rigging equipment prior to use and during use to ensure it's safe D SW2 Barnett 1

Material handling

Prior to unloading steel, examine the load thoroughly to ensure load has not shifted or created a hazard for employees D SW2 Barnett 3

Tag line handling Use tag lines to control loads being handled by hoisting equipment D SW2 Barnett 4

Crane and derrick Comply with manufacturer's specifications and limitations D SW2 Barnett 1

Arc welding caution signs

"Arc welding in progress" signs shall be visible at all times when work is being performed D SW2 Barnett 3

Arc welding ground cable

Ground return cable shall have a safe current carrying capacity equal to or greater than max. welder output D SW2 Barnett 1

Noise Hearing protection will be worn when levels reach 84dB D SW2 Barnett 4

Power tools

All grinding machines shall be supplied with sufficient power to maintain spindle speed at safe levels D SW2 Barnett 3

Page 89: Deployment Completion Report · 2016. 11. 29. · for the entire seven months. TRAINING . ... ITEMPO days accumulated quickly for the 680-personnel Battalion during the deployment

Encl 2 4-8

Notes: (1) Activity: Activity Number assigned from project package that you will be working on in these 2 weeks. (2) Hazards: Hazards associated with that activity number. Taken straight from project Safety Plan. (3) Precautions/Checks: List what measures/checks will you implement to ensure the hazard is minimized. (4) Frequency: Daily (D), Weekly (W), or number of times during these 2 weeks if not re-occurring. (5) Primary Responsibility: Name the person responsible for monitoring the safety of the activity. Not always the Project Sup or Safety Sup. (6) RAC: RAC assigned to the activity. Taken straight off the project Safety Plan.

Page 90: Deployment Completion Report · 2016. 11. 29. · for the entire seven months. TRAINING . ... ITEMPO days accumulated quickly for the 680-personnel Battalion during the deployment

Encl. 3 4-9

TWO WEEK RISK ASSESSMENT PROJECT # JK8-812 SHIP'S PLATFORM DATE: 24 JUL 01 (1) ACTIVITY (2) HAZARDS (3) PRECAUTIONS/CHECKS (4) FREQ (5) PRIMARY RESPONSIBILITY (6) RAC

5000 fire; flame cut steal 1/8" to 1/4" Burns, flammable material D SW3 Schneider 3

burns; butt welding Wear leather D SW1 Barrett 3

Headache reading blueprints Aspirin take two D SW1 Barrett 4

Burns; Finish Welds Wear leather D SW1 Barrett 3

5015 Lifting; Fabricate Platforms use forklift, lift with leg D SW3 Schneider 2

5050 (Welding) Burns, Fire keep fire extinguisher on hand D SW3 Baileystobbs 3

5020 Shifting Load (crane operations) slings 2 EO1 Thompson 1

Notes: (1) Activity: Activity Number assigned from project package that you will be working on in these 2 weeks. (2) Hazards: Hazards associated with that activity number. Taken straight from project Safety Plan. (3) Precautions/Checks: List what measures/checks will you implement to ensure the hazard is minimized. (4) Frequency: Daily (D), Weekly (W), or number of times during these 2 weeks if not re-occurring. (5) Primary Responsibility: Name the person responsible for monitoring the safety of the activity. Not always the Project Sup or Safety Sup. (6) RAC: RAC assigned to the activity. Taken straight off the project Safety Plan.

Page 91: Deployment Completion Report · 2016. 11. 29. · for the entire seven months. TRAINING . ... ITEMPO days accumulated quickly for the 680-personnel Battalion during the deployment

B-1

RTTUZYUW RUYNTAR0018 3330400-UUUU--RUYNTAR. ZNR UUUUU R 281300Z NOV 01 ZYB FM COMNAVFORKOREA SEOUL KOR//00// TO NMCB FIVE INFO COM THIRD NCB PEARL HARBOR HI//00// COM THIRD NCB PEARL HARBOR HI//00// COM TWO ZERO NCR GULFPORT MS//00// COM THREE ONE NCR PORT HUENEME CA//00// COMFLEACT CHINHAE KOR//00// BT UNCLAS //N01000// MSGID/GENADMIN/COMNAVFORKOREA// SUBJ/BRAVO ZULU TO NMCB FIVE SEABEES// RMKS/1. I WOULD LIKE TO THANK THE SEABEES OF NMCB FIVE, DETAILS POHANG AND CHINHAE, FOR OUTSTANDING WORK DURING THEIR 7 MONTH DEPLOYMENT IN KOREA. THEY EXPENDED NEARLY 2000 MANDAYS OF DIRECT LABOR SAVING TO THIS REGION: THAT REPRESENTS MORE THAN 200K DOLLARS OF SAVING OVER CONTRACT LABOR COSTS. THEY CONSISTENTLY WORKED AROUND POTENTIAL SCHEDULING AND MATERIAL PROBLEMS, REMAINED FLEXIBLE, AND OVERCAME SIGNIFICANT CHALLENGES WITH CONSTRUCTION SCOPE OF WORK AND BUDGET MANAGEMENT. PROJECTS INCLUDED: CONSTRUCTION OF P-3 FACILITY, LIBRARY ADDITION, DECONTAMINATION STATIONS, AND INSTALLATION OF PERIMETER FENCE AND SECURITY LIGHTING. COMPLETION OF THESE PROJECTS ENHANCED OUR OPERATIONAL CAPABILITIES AND HAS SIGNIFCANTLY INCREASED QUALITY OF LIFE FOR ASSIGNED PERSONNEL. 2. SEABEES OF NMCB FIVE ARE COMMENDED FOR A JOB WELL DONE. LOOKING FORWARD TO THEIR RETURN TO KOREA. BZ. RADM JONES SENDS.// BT #0018 NNNN

Page 92: Deployment Completion Report · 2016. 11. 29. · for the entire seven months. TRAINING . ... ITEMPO days accumulated quickly for the 680-personnel Battalion during the deployment

B-2

ADMINISTRATIVE MESSAGE

ROUTINE

R 062347Z JAN 02 ZYB PSN 578161Q28

FM NAF ATSUGI JA//N00//

TO NMCB FIVE

INFO COM THRID NCB PEARL HARBOR HI//N00//

COM THREE ONE NCR PORT HUENEME CA//N00//

COM THREE OONE NCR PORT HUENEME CA//N00/

UNCLAS //N01650//

MSGID/GENADMIN/NAF ATSUGI JA/-/JAN//

SUBJ/BRAVO ZULU TO NMCB FIVE DET ATSUGI//

RMKS/1. I WOULD LIKE TO THANK THE SEABEES OF NMCB FIVE, DETAIL

ATSUGI, FOR THE GREAT WORK THEY ACCOMPLISHED DURING THEIR DEPLOYMENT

AT NAF ATSUGI. THEY COMPLETED THE RETAINING WALL LOCATED BY HALSEY

GYM, A HIGH VISIBILITY PROJECT WHICH HAS STOPPED THE EROSION OF AN

EMBANKMENT. THE DETAIL ALSO BROUGHT THE 2100-SF DISASTER

PREPAREDNESS WAREHOUSE AND DEBRIS STORAGE AREA PROJECTS TO AN

IMPRESSIVE 80 AND 50 PERCENT COMPLETION, RESPECTIVELY. THESE THREE

PROJECTS SAVED THIS COMMAND MORE THAN 490K DOLLARS IN CONTRACT LABOR

COSTS. ADDITIONALLY, NMCB FIVE DETAIL ATSUGI PROVIDED INDISPENSABLE

ASSISTANCE DURING FORCE PROTECTION CONDITION CHARLIE IN CLEARING

FENCE LINES, FILLING SANDBAGS, AND IMPROVING BASE SECURITY SHELTERS.

2. THE AMOUNT AND QUALITY OF WORK COMPLETED BY THIS DETAIL WHILE

OVERCOMING TECHNICAL DIFFICULTIES, INCLEMENT WEATHER, AND MATERIAL

DELAYS DURING A TIME OF UNUSUAL NATIONAL CIRCUMSTANCE CONSISTENTLY

IMPRESSED ME. THE DETAIL DEFINITELY LIVED UP TO THEIR "CAN DO"

SPIRIT. MY SINCERE THANK YOU IS NOT NEARLY ENOUGH TO REWARD THEIR

EFFORTS. WE LOOK FORWARD TO NMCB FIVE'S RETURN. CO SENDS.//

BT

NNNN

Page 93: Deployment Completion Report · 2016. 11. 29. · for the entire seven months. TRAINING . ... ITEMPO days accumulated quickly for the 680-personnel Battalion during the deployment

ADMINISTRATIVE MESSAGE

ROUTINE

R 090732Z JAN 02 ZYB PSN 622107Q18

FM COMFLEACT SASEBO JA//00//

TO NMCB FIVE//00/S3//

INFO COM THIRD NCB PEARL HARBOR HI//N3//

COM THIRD NCB PEARL HARBOR HI//N3//

CINCPACFLT PEARL HARBOR HI//N464//

CINCPACFLT PEARL HARBOR HI//N464//

UNCLAS //N05000//

MSGID/GENADMIN/COMFLEACT SASEBO JA//

SUBJ/BRAVO ZULU TO NMCB 5 DETAIL SASEBO//

POC/BUSTAMANTE/LCDR/PWO/-/TEL:252-3452

/EMAIL:[email protected]//

RMKS/1. BRAVO ZULU TO THE "PROFESSIONALS" OF NMCB 5 DETAIL SASEBO

FOR YOUR SUCCESSFUL DEPLOYMENT AT U.S. FLEET ACTIVITIES SASEBO JAPAN

FROM MAY 2001 TO NOVEMBER 2001. TRUE TO YOUR BATTALION'S LOGO, YOUR

UNIT PROVIDED PROFESSIONAL SERVICE AND PERFORMANCE ON AND OFF-DUTY

THAT FUTURE SEABEE DETS WILL BE HARD PRESSED TO MATCH. THANK YOU FOR

YOUR EFFORTS COMPLETING TASKED CONSTRUCTION PROJECTS AND SIX OIC

DISCRETIONARY PROJECTS COVERING COMMUNITY SERVICES, QUALITY OF LIFE

IMPROVEMENTS, AND BASE OPERATIONAL FACILITIES UPGRADES.

2. YOUR COMPLETION OF 3734 MAN DAYS OF CONSTRUCTION PROVIDED A LABOR

COST SAVINGS OF OVER $1.27M AND HAD A MAJOR IMPACT IN IMPROVING OUR

FLEET OPERATIONAL READINESS. THE CONSTRUCTION OF A WAREHOUISE WITH

MEZZANINE PROVIDED A MUCH NEEDED INCREASE TO THE BASE'S OVERALL

STORAGE CAPABILITY, THE CONSTRUCTION OF AN ORDNANCE FACILITY MAGAZINE

WILL GREATLY ENHANCE OUR ORDNANCE MISSION CAPABILITIES, AND THE CFAS

COMMUNITY WILL ALWAYS BE GRATEFUL FOR THE BALL FIELD SCOREBOARDS YOUR

SAILORS PROVIDED FOR OUR RECREATIONAL AREAS.

3. I ALSO WANT TO THANK ALL THE SUPPLY, ENGINEERING, AND SUPPORT

PERSONNEL AND MECHANICS FOR KEEPING THE PROJECTS GOING. SPECIAL

THANKS TO LT TIM MIN FOR HIS REMARKABLE SUPPORT AND LEADERSHIP. YOU

HAVE OUR COMMUNITY'S SINCERE THANKS AND ADMIRATION FOR THE HARD WORK

AND PROFESSIONALISM YOU CONTRIBUTED TO FLEET ACTIVITIES SASEBO. WE

WISH YOU FAIR WINDS AND FOLLOWING SEAS.

CAPT HILL SENDS.//

BT

NNNN

RTD:000-000/COPIES:

B-3