DEN BUSINESS EDUCATION COURSESUpcoming AIM Facility and Tenant Finish Projects
Dave Mashburn
Facilities Supervisor
December 11, 2019
65
AGENDA
The supervisors who manage AIM Facility projects will review the 2020 design
and construction projects.
• On Call Tasks Coming Up
• R-22
• PC Air Plant
• Wally Park
• Sewer Repairs
• Guard House Replacements
• Flat Roof
• Restroom Remodel
R-22 REPLACEMENT PHASE 2 PROJECTAIRPORT INFRASTRUCTURE MANAGEMENT
DON SAAL, PE – PROGRAM MANAGER
ALFONSO VARGAS – PROJECT MANAGER
December 11, 2019
9
• Phase CUP Chiller• (3) 4150T Chillers Replaced
• Phase 1, 1R – AOB & CCA• ~38 Units to be replaced
• Phase 2 – Terminal Complex & Airfield• ~200 Units to be replaced
• Phase 3 – Pena & Air Cargo Facilities• ~33 Units to be replaced
• Phase 4 – South Campus Facilities• ~40 Units to be replaced
• AGTS• HVAC replacement for 15 train
cars (17-31)
PROJECT PLAN
Phase 1R
Phase 2 – D/B
Phase 3
Phase 4
Phase Cup Chiller
3
• EPA Phase out of R-22
• No longer produced as of January 2010
• Ban on sale and use as of January 2015
• Complete ban as of January 2020
• Exception for recovered/ recycled/ reclaimed R-22 for use in existing systems
• The Airport Campus
• Phase 2 - Replace approximately 200 pieces of equipment that use R-22
PROJECT PURPOSE
6
Figure 2: Server room – Evaporator UnitFigure 1: CRAC unit
PICTURES OF CURRENT CONDITION
Figure 3: Server room – Evaporator Unit Figure 3: Condensing Unit
10
PROJECT SCHEDULE: PHASE 2
300
365
300
365
160
160
160
90
2022
Q1 Q2
2021
Q1 Q2 Q3 Q4Q4Q1 Q2 Phase
2019
Q4 Days
Q3 Q3
2020
Permitting
Construction
Concourse B
Concourse C
Outer Buildings
Closeout
Design
Contract Procurement
Today
Concourse A & C Pre-Conditioned Air Plant Re-LifeDesign Tollgate
Kristian Jonsson– Project Manager
DENVER INTERNATIONAL AIRPORT
December, 2019
74
• Concourse A & C Pre-Conditioned Air Plants – Basement Level Center Core
PROJECT OVERVIEW
75
• Re-Life of PCA Plant
• New Structural Floor and equipment pads (approximately 1250 SF)
• New chillers
• New heat exchangers
• New pumps
• Hydronic piping
• New expansion tanks
• New VFDs
• Updated controls to coordinate with EMCS
• Updated electrical to correspond to new equipment above
• Maintain ROW for Baggage
• Maintain area for future/potential Thermal Energy Storage system
PROJECT SCOPE
76
• Capacity
• Demands for Concourse expansions
• Improved operation efficiency
• Structural
• Heaving slab on grade
• Age
• Equipment end-of-life
• R-22 Phase Out in 2020
PROJECT PURPOSE
77
• Capacity
• Structural
• Age
BACKGROUND
Current
Load (Tons)
Current
Load (%)
Current
Deficiency
(Tons)
Load @ Full
Expansion
(Tons)
Current
Load (%)
Deficiency @
Full Expansion
(Tons)
CCA 1634 240% (954) 3456 508% (2776)
CCC 1094 161% (414) 2066 304% (1386)
Current Design Considerations - Cooling Load*
78
PICTURES
Figure 1: Expansion Joint
Figure 2: Slab heave at chiller pad
80
• On-Call Designer (Wong Strauch Architects, NTP 5/4/2018)
• SD, 30%, 60%, 100%, and IFC Submittal Packages
• Construction (Invitation to Bid)
• Phasing demo/construction at CCA & CCC
• Phasing demo at each concourse to maintain operation
• Switch over from old system to new will have minimal downtime
• Long lead time on chillers (included in schedule/risks)
PROJECT PLAN
81
SCHEDULE
Year 2018 2019 2020
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
• Design
• DDS Plan
Review
• Procure GC
• Procure Equip.
• CCA Demo
• CCA Build
• CCC Demo
• CCC Build
• Closeout
• Annual Budget $1,000,000 $28,000,000 $2,508,702
269 days
116 days
110 Days
160 days
150 days
150 days
160 days
90 days
*Anticipated finish of Concourse Expansion in 2020.
GC NTP
45 Days
Today
86
PROJECT RISKS AND MITIGATION
RISK MITIGATIONCOST TO REPOND
STATUS
Gate PCA Closures Accept 600,000 Open
Phasing of Construction Accept 600,000 Open
Temporary Equipment Procurement
Transfer 600,000 Open
Downtime of the PCA System during Construction
Transfer 1,000,000 Open
Long lead times for Equipment
Reduce 600,000 Open
Premature Failure of Equipment
Accept 1,000,000 Open
Design Issues w/ Low Bid Reduce 600,000 Open
Geotechnical/Structural issues/unknowns
Accept 200,000 Open
Construction access Transfer 1,300,000 Open
Tea Schook – Project Sponsor & Kristian Jonsson – Project Manager
December, 11 2019
Wally Park RelocationAIM Development
91
• Capacity• Rental companies have outgrown or will outgrow current leaseholds within 5
years and more land area is needed to lease to them.• Need to group rental companies into “families”
• Improved Services• Additional land for rental companies to add capacity or the potential for a
new tenant• Improved rental car customer service • New Wally Park facility will better accommodate growing customer base • Having “families” together will consolidate rental car bussing.
• Sponsor recommended solutions• Relocate Wally Park to SW corner of Gun Club Rd. and Pena• Three options were reviewed with many stakeholders including planning to
decide upon the recommended location
CURRENT ISSUE/REASON FOR THE PROJECT
92
• Existing Location
ADDITIONAL INFORMATION
93
• Site B selected for Wally Park Relocation
• A & C not being selected due to other projects moving forward on those sites
CURRENT STATE: PLANNING PROCESS
94
• Potential lay out of “families”
FUTURE STATE: PLANNING PROCESS
95
PICTURES OF CURRENT CONDITION
• Existing Wally Park on 78th next to Alamo
PROJECT RISKS AND MITIGATION
# Risk Description OwnerDate
IdentifiedResponse Action to Be Taken
Cost to
RespondStatus
1 Environmental mitigation
may require greater
measures than originally
anticipated
Contractor 8/21/2018 Mitigate Anticipated lead times have
been built into the initial
construction schedule.
N/A N/A Identified, Contractor
must be on board to
address these risks
Risk Identification Response PlanningMonitoring and
Control Date, Status,
and Review
Comments
The End
CONCOURSE A, B, C SEWER REPAIRSU.P.S. SEWER REPAIRS
RACHAEL BRAY
PROJECT MANAGER
DECEMBER 11 2019
99
• Rachael Bray, Project Manager
• wish we could be here, again…
CONCOURSE A, B, C SEWER REPAIRS
100
• Rachael Bray, Project Manager
• Purpose
• Background
• Scope
• Concourse Basement Sumps
• Concourse A – complete…
• Concourses B & C – funding in process, to proceed in 2020
• DSBO and Estimates
• AGTS Train Wash Drain Modification – completed
• Under East Baggage Tunnel – pipe lining in 2021
• Utility Tunnel – pipe replacement in 2021
CONCOURSE A, B, C SEWER REPAIRS
101
CONCOURSE A, B, C SEWER REPAIRS
-On Call Design (current)-‘Phased’ Projects through 2021-Competitive Bid Construction – 2020-2021
Tunnel Sewer RepairsUnder E. Baggage Tunnel
Utility Tunnel
102
CONCOURSE A, B, C SEWER REPAIRS
-ON Call Design (current)-‘Phased’ Projects through 2021-Competitive Bid Construction – 2020-2021
Tunnel Sewer Repairs
Under E. Baggage TunnelUtility Tunnel
103
U.P.S. SEWER REPAIRS
South Cargo, Building B
UPS Delta
Bathroom sewer back-upsReplacement of drainage pipesDesign 2020On-Call Construction 2020
104
U.P.S. SEWER REPAIRS
Sewage Back-up in Men’s Room
UPCOMING AIM FACILITY PROJECTSGUARD HOUSE REPLACEMENTSFLAT ROOF REPLACEMENTS
SALLY DOLES, PE - FACILITY SERVICES
DECEMBER 11, 2019
107
GUARD HOUSE REPLACEMENTS
Scope of Work:• Guard houses at Gates 1 and 4 to be replaced• Existing guard houses to remain operational during construction• Current design intent is to utilize pre-fabricated modular structures
Status/Schedule:• Bid documents complete in Q2 2020• Task Notice for Proposals: Q3 2020• Estimated Construction Start: Q3 2020
108
GUARD HOUSE REPLACEMENTS
Gate 1 Approximate Layout
109
GUARD HOUSE REPLACEMENTS
Gate 4 Approximate Layout
110
GUARD HOUSE REPLACEMENTS
Additional Project Info:• Design could be revised to ground up structure• DSBO goal based on on-call GC contract
Project manager:• Sally Doles/Megan Catalfomo• 303-342-2055/303-342-2741• [email protected]• [email protected]
111
FLAT ROOF REPLACEMENTS
Scope of Work:• Replace roofs of several buildings around DEN campus• Replacements include White EPDM and standing seam metal roof• Contractor to utilize sub to complete roofing repair documents
Status/Schedule:• Task Notice for Proposals: Q2 2020• Estimated Construction Start: Q3 2020
Poor drainage/Black EPDM
Standing Seam Roof Damage
Multiple Repairs/Black EPDM
112
FLAT ROOF REPLACEMENTS
Additional Project Info:• DSBO goal based on on-call GC contract
Project manager:• Sally Doles• 303-342-2055• [email protected]
113
CONCOURSE RESTROOMS REMODELS AT DEN
Ellice WeaverProject Manager
December 11, 2019
115
• Reason for the Project
• Background
• Scope
• 2019-2020 Status / Schedule
• Define project requirements 2019
• Request funding for the upcoming year: Jan 2020
• Receive funding: Feb 2020
• Design Team Onboard: Mar 2020
• Competitive Bid Construction: Jun/Jul 2020
CONCOURSE RESTROOMS REMODELS
116
HOW THEY LOOK NOW
117
HOW THEY LOOK NOW
118
NEW LOOK
119
NEW LOOK
• Concept layout design similar to new concourse expansion design