23 March 2011 Ian Brawn 1 Demonstrator Slice Possibilities and Timetable • Motivation • Implications • Staging • Schedule • Conclusions

Upload: afi

Post on 04-Feb-2016

36 views

Category:

Documents


0 download

DESCRIPTION

Demonstrator Slice Possibilities and Timetable. Motivation Implications Staging Schedule Conclusions. Why?. What do we seek to accomplish by building a demonstrator system? Prove viability of concept and technology Verify inter-operability of modules - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Demonstrator Slice Possibilities and Timetable

23 March 2011 Ian Brawn 1

Demonstrator Slice Possibilities and Timetable

• Motivation• Implications• Staging• Schedule• Conclusions

Page 2: Demonstrator Slice Possibilities and Timetable

23 March 2011 Ian Brawn 2

Why?

• What do we seek to accomplish by building a demonstrator system?– Prove viability of concept and technology – Verify inter-operability of modules– Test functionality of system as a whole

• Explore the phase space of module interactions• Uncover any limits not obvious in isolation

– Catch any bugs before we build the final system– Provide a development platform for firmware and software– Gain experience with the system

• Control• Monitoring• Readout

– Gain experience interfacing with external hardware• Uncover any deficiencies in their hardware or ours

– Build working relationship with external colleagues

Page 3: Demonstrator Slice Possibilities and Timetable

23 March 2011 Ian Brawn 3

Implications for the Demonstrator

• Demonstrator should…• Have full functionality of final system

– Complete slice through processing chain• Be capable of interfacing to every external system required by final system, or

prototypes/demonstrators of such• Process sufficiently wide area to allow adequate test of algorithms

– Eg, data sharing between modules for e/ algorithm; de-clustering– What does sufficiently wide mean for global, topological algorithms?

• Contain at least 1 prototype for every type of module in the system– For more technically challenging/unprecedented modules these should be

preceded by demonstrators

• Demonstrator: To be useful in the demonstrator system, demonstrator module is a scaled down version of proposed module; same functionality, fewer instances

• Prototype: no anticipated design differences from proposed module

Page 4: Demonstrator Slice Possibilities and Timetable

23 March 2011 Ian Brawn 4

coursetowers

coursetowers

L0A

The Final Demonstrator

L0 Muon

L0 Topo (global)

L0 CTP

L1 Topo (global)

L1 CTP

CalROD

fine granularity minitowers

• Above picture presupposes an architecture on which we haven’t settled– calorimeter feature extraction (eg, jet, e/) handled by 2 types of module,

A/B• This is what we work towards, not what we start with

Track Trigger

L1 Muon

L01L0 Calo FEX A

L0 Calo FEX B

L1 Calo FEX

Page 5: Demonstrator Slice Possibilities and Timetable

23 March 2011 Ian Brawn 5

coursetowers

coursetowers

L0A

The Final Demonstrator

L0 Muon

L0 Topo (global)

L0 CTP

L1 Topo (global)

L1 CTP

CalROD

ROD ROD ROD ROD

fine granularity minitowers

• Above picture presupposes an architecture on which we haven’t settled– calorimeter feature extraction (eg, jet, e/) handled by 2 types of module,

A/B• This is what we work towards, not what we start with

Track Trigger

L1 Muon

L01L0 Calo FEX A

L0 Calo FEX B

L1 Calo FEX

Page 6: Demonstrator Slice Possibilities and Timetable

23 March 2011 Ian Brawn 6

coursetowers

coursetowers

L0A

The Final Demonstrator

L0 Muon

L0 Topo (global)

L0 CTP

L1 Topo (global)

L1 CTP

CalROD

ROD ROD ROD ROD

fine granularity minitowers

• Above picture presupposes an architecture on which we haven’t settled– calorimeter feature extraction (eg, jet, e/) handled by 2 types of module,

A/B• This is what we work towards, not what we start with

TCM

Track Trigger

L1 Muon

GBT

L01L0 Calo FEX A

L0 Calo FEX B

L1 Calo FEX

Page 7: Demonstrator Slice Possibilities and Timetable

23 March 2011 Ian Brawn 7

Staging

• Can’t produced everything at once staging required• Factors determining schedule

– Allocation of modules to institutes determines what we can build in parallel• Not attempted to address that here• Obvious demonstrator/prototypes should be built by institute building

final item– Some modules are of more use in isolation than others– Availability of external hardware to which we want to interface

• Mitigation strategies for scheduling problems– Standardized optical links allow modules to be connected in alternative

configurations• Eg, bypass L0 CTP or use L0Topo as test source for L0 Calo FEX A

– Implement DAQ buffering, readout, GBT in FPGA on each board, allowing ROD to be bypassed.

• All of these options require custom firmware • Take care not to generate large firmware overheads not necessary for final

system

Page 8: Demonstrator Slice Possibilities and Timetable

23 March 2011 Ian Brawn 8

External Systems

• Muons– RPCs (amongst other things) being upgraded– MUCTPI being upgraded (under study) source for e/ veto?

• Calorimeter – Digitized front ends– Trigger data to arrive via ROD– Hybrid analogue/digital RODs available in ATLAS Q3+Q4 2013– Available for full Calorimeter 2015–2017

• Track trigger– FTK (Fast Tracker)

• Real-time track processor• Receives events at L1A rate from RODs• Output = 300 tracks/event (@ 3 x 1034)• 1st prototypes arriving in 2012, • Barrel-only system 2014• Full system 2016

– Use FTK as proto track?• CTP• GBTx

– (Rad hard) ASIC submissions 2011– Firmware implementation available now

Page 9: Demonstrator Slice Possibilities and Timetable

23 March 2011 Ian Brawn 9

Level 0 Staging

• Stage 1 Ready 2013–L0 Calo FEX A

• Connects to Calo hybrid RODs• Run parasitically, in tandem with

current trigger & compare results–L0 Topo

• Connects to …–L0 Calo FEX A (multiple), CMM+

+, FTK, MUCTPI, CTP

• Path from RODL0CTP data• Stage 2

–ROD• Connects to (DAQ via) GBT,

L0 Calo FEX A, L0 Topo• Only at this point does demonstrator

start to look like final system to on-line software

• Stage 3–L0 Calo FEX B

• Lower priority because doesn’t provide new external interface

–TCM (Timing and Control Module)• If necessary

CalprotoRODs

L0 Calo FEX A

Page 10: Demonstrator Slice Possibilities and Timetable

23 March 2011 Ian Brawn 10

Level 0 Staging

• Stage 1 Ready 2013–L0 Calo FEX A

• Connects to Calo hybrid RODs• Run parasitically, in tandem with

current trigger & compare results–L0 Topo

• Connects to …–L0 Calo FEX A (multiple), CMM+

+, FTK, MUCTPI, CTP

• Path from RODL0CTP data• Stage 2

–ROD• Connects to (DAQ via) GBT,

L0 Calo FEX A, L0 Topo• Only at this point does demonstrator

start to look like final system to on-line software

• Stage 3–L0 Calo FEX B

• Lower priority because doesn’t provide new external interface

–TCM (Timing and Control Module)• If necessary

L0 Muon

L0 Topo (global)

L0 CTP

CalprotoRODs

L0 Calo FEX A

CMM++

FTK

Page 11: Demonstrator Slice Possibilities and Timetable

23 March 2011 Ian Brawn 11

Level 0 Staging

• Stage 1 Ready 2013–L0 Calo FEX A

• Connects to Calo hybrid RODs• Run parasitically, in tandem with

current trigger & compare results–L0 Topo

• Connects to …–L0 Calo FEX A (multiple), CMM+

+, FTK, MUCTPI, CTP

• Path from RODL0CTP data• Stage 2

–ROD• Connects to (DAQ via) GBT,

L0 Calo FEX A, L0 Topo• Only at this point does demonstrator

start to look like final system to on-line software

• Stage 3–L0 Calo FEX B

• Lower priority because doesn’t provide new external interface

–TCM (Timing and Control Module)• If necessary

L0 Muon

L0 Topo (global)

L0 CTP

CalprotoRODs

ROD ROD

L0 Calo FEX A

CMM++

FTK

Page 12: Demonstrator Slice Possibilities and Timetable

23 March 2011 Ian Brawn 12

Level 0 Staging

• Stage 1 Ready 2013–L0 Calo FEX A

• Connects to Calo hybrid RODs• Run parasitically, in tandem with

current trigger & compare results–L0 Topo

• Connects to …–L0 Calo FEX A (multiple), CMM+

+, FTK, MUCTPI, CTP

• Path from RODL0CTP data• Stage 2

–ROD• Connects to (DAQ via) GBT,

L0 Calo FEX A, L0 Topo• Only at this point does demonstrator

start to look like final system to on-line software

• Stage 3–L0 Calo FEX B

• Lower priority because doesn’t provide new external interface

–TCM (Timing and Control Module)• If necessary

L0 Muon

L0 Topo (global)

L0 CTP

CalprotoRODs

ROD ROD

L0 Calo FEX A

L0 Calo FEX B

TCM

CMM++

FTK

Page 13: Demonstrator Slice Possibilities and Timetable

23 March 2011 Ian Brawn 13

Level 1 Staging

• Slower schedule than L0– Connects to downstream modules on slower schedules than Calo ROD

prototypes, for example.– Whereas L0 looks similar to current trigger pipelined, fixed latency, FPGA-

based, etc L1 is less familiar and less well defined• Extended demonstrator programme • Possibility of using COTS (Commercial Off-The-Shelf) boards initially

– Eg, to evaluate GPU- or CPU-based implementations of algorithms– Run parasitically from L0 demonstrator

• Design consideration for L0 Topo demonstrator• Conceivable some subset of L1 will be built using COTS. However, any custom

hardware will need to be prototyped, and maybe demonstrated before that.• Programme:

– COTS-based, algorithm demonstrator technology demonstrator prototype

– Scheduling overlaps with L0 programme• Design so that L0CTP can be bypassed

Page 14: Demonstrator Slice Possibilities and Timetable

23 March 2011 Ian Brawn 14

Supporting Hardware

• TCM (Timing and Control Module)– Do we need/want a module for clock distribution and packet routing for

control and readout? (GBT)– Coupled to backplane architecture– Initially avoid by placing this functionality on individual cards– May require TCM for final system

• DSS (Data Source/Sink)– Do we need/want a module to act as a generic source/sink of test data for

the demonstrator system?– Fill gaps in system due to unavailable modules (internal/external)– Use of standard interfaces (eg, SNAP12) could render h/w comparatively

simple• Compared to DSS for current system

– Use of standard interfaces may render unnecessary• But this might not save us any work due to increased f/w load

• Schedule presented here assumes TCM required but not DSS

Page 15: Demonstrator Slice Possibilities and Timetable

23 March 2011 Ian Brawn 15

Existing Schedule (1)

Page 16: Demonstrator Slice Possibilities and Timetable

23 March 2011 Ian Brawn 16

Existing Schedule (2)

Page 17: Demonstrator Slice Possibilities and Timetable

23 March 2011 Ian Brawn 17

Existing Schedule (3)

Page 18: Demonstrator Slice Possibilities and Timetable

23 March 2011 Ian Brawn 18

Existing Schedule (4)

Page 19: Demonstrator Slice Possibilities and Timetable

23 March 2011 Ian Brawn 19

Existing Schedule (5)

Page 20: Demonstrator Slice Possibilities and Timetable

23 March 2011 Ian Brawn 20

Existing Schedule (6)

Page 21: Demonstrator Slice Possibilities and Timetable

23 March 2011 Ian Brawn 21

Schedule Caveats & Notes

• The following schedule is only a sketch– More detailed schedule unwarranted due to uncertainties in project

• Assumes architecture for system that is by no means certain• Mostly, only hardware design and production shown

– Schedule for specification, firmware, software, etc, must be inferred• Under estimates minimum no. iterations of demonstrator/prototype modules

built• Under estimates extent to which tasks can be run in parallel

– No attempt to split tasks between institutes

Page 22: Demonstrator Slice Possibilities and Timetable

23 March 2011 Ian Brawn 22

Slice Demo Schedule

Page 23: Demonstrator Slice Possibilities and Timetable

23 March 2011 Ian Brawn 23

Conclusions

• There is a lot of new hardware to be built– These hardware modules need to interact with each other– A demonstrator system is a necessity

• We should take advantage of any prototypes/demonstrators of the external systems with which we need to interact

• Planning will be more accurate once we have well-defined responsibilities within L1Calo

• Effort required for alternative firmware configurations and supporting modules must not be neglected

• Even with a minimal programme of demonstrators and prototype modules there is much to design, build and test

• Keep our eyes on the final goal — Phase 2 system in 2021– Bonus if demonstrator can add functionality to live trigger before this– Must let this distract us from our primary goal