demand response assessment for eastern interconnection · 3 managed by ut-battelle for the u.s....
TRANSCRIPT
Demand Response Assessment for Eastern Interconnection
Youngsun Baek, Stanton W. Hadley, Rocio Martinez, Gbadebo Oladosu, Alexander M. Smith, Fran Li, Paul Leiby
and Russell Lee
Prepared for FY12 DOE–CERTS Transmission Reliability R&D
Internal Program Review
September 20, 2012
2 Managed by UT-Battelle for the U.S. Department of Energy
DOE National Laboratory Studies Funded to Support FOA 63 • DOE set aside $20 million from transmission funding for
national laboratory studies. • DOE identified four areas of interest:
1. Transmission Reliability 2. Demand Side Issues 3. Water and Energy 4. Other Topics
• Argonne, NREL, and ORNL support for EIPC/SSC/EISPC and the EISPC Energy Zone is funded through Area 4.
• Area 2 covers LBNL and NREL work in WECC and ORNL/Georgia Tech studies (DR and EE) for the Eastern Interconnection (EI).
3 Managed by UT-Battelle for the U.S. Department of Energy
Study Objective and Tasks for Area 2 • Objective: Estimation of Demand Response (DR) potential peak load
reductions in EI to inform states and stakeholders for assessment of transmission infrastructure requirements
• Update inputs • Revise key assumptions and
relationships • Construct scenarios • Conduct sensitivity analysis
and stochastic simulations • Report DR potential by census
division and state
Tasks: 1. Review existing national DR
studies and projections 2. Assess EI-DR potential with
FERC’s NADR model and Monte Carlo technique
3. Estimate costs for DR programs implementation and system impacts/benefits with ORCED model
4 Managed by UT-Battelle for the U.S. Department of Energy
Our Reporting of EI Excludes West and Texas
Coverage of EI on NERC Map Census Regions and Divisions
5 Managed by UT-Battelle for the U.S. Department of Energy
FERC’s Original Efforts and ORNL’s Improvements • FERC contractors built the National Assessment of
Demand Response (NADR) model to estimate DR potential. – The NADR model and analysis report were released in 2009. – NADR estimates future peak load impacts under DR participation
assumptions. • FERC has conducted bi-annual surveys of Demand
Response and Advanced Metering (FERC-731) since 2006. • ORNL updated the parameters, extended the projection
period, and added algorithms to improve NADR. – ORNL used 2010 FERC-731 to update some primary parameters. – ORNL extrapolated the number of DR customers not reporting to
FERC-731 and incorporated that number into NADR. – ORNL brought in other data sources (e.g., EIA, Brattle Group).
6 Managed by UT-Battelle for the U.S. Department of Energy
Types of DR Programs used by ORNL-NADR • Pricing Programs – Customers are offered time-varying
electricity rates on a prior-notice or real-time basis. – Rates are typically higher during peak hours. – Enabling Technologies, devices that automatically reduce
customer load in response to price signals, may be combined with some pricing programs to enhance load impacts.
• Direct Load Control – Customers receive monthly compensation for allowing utilities to control their appliances, such as water heaters and central air conditioners. – This requires installation of special controller technologies upon
appliances.
7 Managed by UT-Battelle for the U.S. Department of Energy
Types of DR Programs used by ORNL-NADR (cont.) • Interruptible Tariffs – Customers receive a reduced
electricity rate or monthly compensation for agreeing to reduce their consumption by specified amounts upon utility’s request. – Typically, only medium and large-sized commercial and industrial
customers may enroll in these programs.
• Other – Medium and large-sized commercial and industrial customers are incentivized to reduce their load through various mechanisms. – Examples include Demand Bidding, Capacity Bidding, Aggregator/
Curtailment Service Provider programs, and System Reliability Event programs.
8 Managed by UT-Battelle for the U.S. Department of Energy
ORNL-NADR Scenarios and Key Factors
BAU Optimistic BAU
Aggressive Deployment
Full Deployment
AMI deployment Partial deployment
Partial deployment
Full deployment
Full deployment
Dynamic pricing participation (of eligible)
Today’s level Voluntary (opt-in); 5%
Default (opt-out): 60 to 70%
Universal (mandatory) 100%
Eligible customers using enabling technology
None None 57% 100%
Basis for non-pricing participation rate
Baseline level Best practices estimate
Best practices estimate
Best practices estimate
9 Managed by UT-Battelle for the U.S. Department of Energy
Optimistic BAU: Impacts from Non-Reporting Entities
• Only 52% of all utilities returned data to FERC for the 2010 survey.
• Only 16% of all utilities reported DR programs. • The ORNL conservative scenario (i.e., BAU) assumes that
non-reporting utilities have no DR programs. • The ORNL optimistic scenario assumes that non-reporting
utilities have the same level of customer participation in DR as reporting utilities in the same group. – ORNL updated participation rates based on regressions using 2008
EIA and 2010 FERC survey data.
10 Managed by UT-Battelle for the U.S. Department of Energy
EI Summer Peak Demand Forecast by ORNL-NADR
11 Managed by UT-Battelle for the U.S. Department of Energy
Limited Peak Hours for DR modeling and Possibility of Overestimation • NADR assumes DR applies to 4 hours for
top 15 days (limited 60 hours). At low DR penetration, the assumption works.
• However, at high DR penetration, it is a more realistic modeling to shave the peak load from the top and spread DR impact over more hours to clip peak.
• Therefore, the actual %PLR would be smaller than the %PLR calculated by ORNL-NADR.
5
10
15
20
25
30
Jul31 Aug01 Aug02 Aug03 Aug04 Aug05 Aug06
GW
System Load
With DR Base
!"#$%&' ()#$%&' *"+,$%&' -+$#+,$%&' *."/,$%&' 0/1$%&' !%2"/$%&'
5
10
15
20
25
30
Jul31 Aug01 Aug02 Aug03 Aug04 Aug05 Aug06
GW
System Load
With DR Base
!"#$%&' ()#$%&' *"+,$%&' -+$#+,$%&' *."/,$%&' 0/1$%&' !%2"/$%&'
Notch DR modeling (ORNL-NADR)
Smart DR modeling (Smart ORCED model)
0%
10%
20%
30%
40%
50%
EMM Region
% PLR calculated by ORNL-‐NADR % PLR calculated by Smart ORCED model
12 Managed by UT-Battelle for the U.S. Department of Energy
Potential Peak Reduction from Demand Response in EI, 2030
• Under BAU and optimistic BAU, the largest gains through interruptible tariffs and other DR • A significant growth in pricing programs (with and without enabling technologies) is noticed
under the Aggressive and Full Deployment scenarios. • DLC has a significant impact in the residential and small C&I sectors. • The majority of DR comes from large C&I customers primarily through interruptible tariffs
and capacity and load bidding. • In the residential sector, most untapped potential for DR comes from the pricing programs.
13 Managed by UT-Battelle for the U.S. Department of Energy
Demand Response Potential by Census Division and Scenario, 2030
!• The regions show the largest existing (BAU) impacts have both wholesale demand
response programs and utility/load serving entity programs. • Central air conditioning saturation plays a key role in determining the magnitude of
the Aggressive and Full Deployment demand response potentials.
14 Managed by UT-Battelle for the U.S. Department of Energy
Top 10 states in System Peak in 2030
0 10,000 20,000 30,000 40,000 50,000 60,000 70,000
MW
• FL does not have the highest penetration of demand response, though it is the number-one state in system peak.
• PA and NY have actively deployed high levels of demand response to cope with their high system peak demand.
!Top 10 States in System Peak (Y-axis: % Peak Load Reduction)
15 Managed by UT-Battelle for the U.S. Department of Energy
Monte Carlo Simulation for Pricing Programs • Stochastic simulation for the impact of dynamic pricing
programs – Allow random variation of previously fixed values for key
parameters to improve modeling of peak price elasticity
POTENTIAL LOAD REDUCTION FROM DYNAMIC PRICING PROGRAMS (MAINE, 2019) – An example of Monte Carlo simulation results
16 Managed by UT-Battelle for the U.S. Department of Energy
Monte Carlo Simulation for Pricing Programs (Cont.)
Ra,o of CPP to
Ave. Price
Mean (GW)
Lower (GW)
Upper (GW)
Pricing with Enabling
Technology
5 52 41 64
10 78 60 93
15 94 74 118
Pricing without Enabling
Technology
5 33 27 40
10 49 40 57
15 59 47 73
• An Example Result for Full Deployment Scenario, 2030
17 Managed by UT-Battelle for the U.S. Department of Energy
Demand Response Supply Curve for EIPC Study
0
500
1,000
1,500
2,000
2,500
0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%
$/M
Wh
% of Maximum DR Available
DR 6-Block Supply Curve
Eff. CT w/o CO2
Ineff. CT w/ CO2
Model Curve w/ allocated non-price DR
5-Block Supply Curve Only with Pricing Programs in 2030
6-Block Supply Curve and Model Curve with Allocated Non-Pricing DR in 2030
18 Managed by UT-Battelle for the U.S. Department of Energy
DR Cost Analysis
• DR is tied to Advanced Metering Infrastructure (AMI). – AMI is necessary to enable many DR programs. – The NADR model uses AMI deployment to proxy DR participation.
• ORNL reviewed data on AMI deployment costs and utility AMI deployment plans
• ORNL incorporated industry learning and economies-of-scale into cost calculations.
19 Managed by UT-Battelle for the U.S. Department of Energy
Cost Estimates
Scenario Meters IT Systems Communications Network
Deployment Management
Annualized AMI O&M
High 243 65 66 81 23
Medium 190 27 43 63 7
Low 129 11 11 28 4
!
Estimated Cost-per-Meter of Various AMI System Component ($)
20 Managed by UT-Battelle for the U.S. Department of Energy
Demand Response (DR) Benefits
• Oak Ridge Competitive Electricity Dispatch (ORCED) model simulates regional dispatch of generation to meet demand.
• With the reductions in demand during peak hours, ORCED calculates changes in generation and unserved energy, price, cost, and greenhouse gas emissions of utilities.
• DR benefits include: – System peak impact – System reliability impact – Reduced system costs – Environmental benefits
DR Benefit Case Regional % Peak Load Reduction
No DR (Reference Case) 0%
DR-Notch-BAU 1 – 10% (Ave. 5%)
DR-Smart-BAU 1 – 10% (Ave. 5%)
DR-Smart-Optimistic BAU 8 – 22% (Ave. 15%)
DR-Smart-Aggressive Deployment
16 – 35% (Ave. 23%)
DR-Smart-Full Deployment 19 – 47% (Ave. 30%)
21 Managed by UT-Battelle for the U.S. Department of Energy
Geographical Classification for Benefits Analysis
229U.S. Energy Information Administration | Annual Energy Outlook 2011
!"#$%&'()*'+,
!"#$%&'!()''*+&,-%","-.'/0%1&-'/23$+&'%&#"245
Source: U.S. Energy Information Administration, O!ce of Energy Analysis.
!"
!!
!#
!$
""
"!
"#
!%
!&
$
!'
(
%
)
!
"
'&
!)
!(
*
!*
! "#! $%&'! $%&('!)**! +#! ,%&&! ,%&&!)**! -#! .%($! .%(!$/01! 2#! .%(3! .%(!3401! 5#! 6$3$! 67&&!648!$9:*/9;! <#! 6=&3! 67&&!6=&>3401?@4014A! B#! 6=CD! 67&&!CE9:!D0*/9;! F#! 6=G7! 67&&!GH01/14!6=! I#! %,&$! %,&!$/01!"J#! %,&.! %,&!.K?@K:/9! ""#! %,&3! %,&!3401
!"+#! L%M)! L$%&!M4*1/!"-#! L%N3! L$%&!N/148/O!"2#! L%L$! L$%&!LEP1@4/014A9!"5#! L%&$! L$%&!&491A/*!"<#! L%Q&! L$%&!Q)&)%!"B#! L76(! L77!6EA1@!"F#! L7L(! L77!LEP1@!"I#! )R6.! 3$&&!LEP1@8401!+J#! &).S! 3$&&!&/*KTEA9K/!+"#! 6377! 3$&&!6EA1@8401!++#! %.7)! 3$&&!%E?UK40
EIA’s Electricity Market Module Regions
22 Managed by UT-Battelle for the U.S. Department of Energy
Impact on System Reliability
-‐20%
-‐10%
0%
10%
20%
30%
40%
50%
60%
70%
Reserve Margin in 2030
No DR
BAU-‐Notch
Full Deployment-‐Smart
23 Managed by UT-Battelle for the U.S. Department of Energy
Change in Cost by DR
• Other factors reported such as change in reserve margins, average cost, and CO2 emissions
0
50
100
150
200
250
300
350
400 $/MWh
Avoided Cost during Peak Hours Average GeneraSon Cost
24 Managed by UT-Battelle for the U.S. Department of Energy
Future Research Directions
• Revise DR program participation rates • Investigate demand reduction potential at the program
and appliance level • Update econometric estimation of load profiles for each
state and customer type • Investigate duration and timing of DR programs
25 Managed by UT-Battelle for the U.S. Department of Energy
Contact information for Further Discussions
• Youngsun Baek ([email protected]) • Stan Hadley ([email protected])