demand response assessment for eastern interconnection · 3 managed by ut-battelle for the u.s....

25
Demand Response Assessment for Eastern Interconnection Youngsun Baek, Stanton W. Hadley, Rocio Martinez, Gbadebo Oladosu, Alexander M. Smith, Fran Li, Paul Leiby and Russell Lee Prepared for FY12 DOE–CERTS Transmission Reliability R&D Internal Program Review September 20, 2012

Upload: others

Post on 01-Aug-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Demand Response Assessment for Eastern Interconnection · 3 Managed by UT-Battelle for the U.S. Department of Energy Study Objective and Tasks for Area 2 • Objective: Estimation

Demand Response Assessment for Eastern Interconnection

Youngsun Baek, Stanton W. Hadley, Rocio Martinez, Gbadebo Oladosu, Alexander M. Smith, Fran Li, Paul Leiby

and Russell Lee

Prepared for FY12 DOE–CERTS Transmission Reliability R&D

Internal Program Review

September 20, 2012

Page 2: Demand Response Assessment for Eastern Interconnection · 3 Managed by UT-Battelle for the U.S. Department of Energy Study Objective and Tasks for Area 2 • Objective: Estimation

2 Managed by UT-Battelle for the U.S. Department of Energy

DOE National Laboratory Studies Funded to Support FOA 63 • DOE set aside $20 million from transmission funding for

national laboratory studies. • DOE identified four areas of interest:

1.  Transmission Reliability 2.  Demand Side Issues 3.  Water and Energy 4.  Other Topics

• Argonne, NREL, and ORNL support for EIPC/SSC/EISPC and the EISPC Energy Zone is funded through Area 4.

• Area 2 covers LBNL and NREL work in WECC and ORNL/Georgia Tech studies (DR and EE) for the Eastern Interconnection (EI).

Page 3: Demand Response Assessment for Eastern Interconnection · 3 Managed by UT-Battelle for the U.S. Department of Energy Study Objective and Tasks for Area 2 • Objective: Estimation

3 Managed by UT-Battelle for the U.S. Department of Energy

Study Objective and Tasks for Area 2 •  Objective: Estimation of Demand Response (DR) potential peak load

reductions in EI to inform states and stakeholders for assessment of transmission infrastructure requirements

•  Update inputs •  Revise key assumptions and

relationships •  Construct scenarios •  Conduct sensitivity analysis

and stochastic simulations •  Report DR potential by census

division and state

Tasks: 1.  Review existing national DR

studies and projections 2.  Assess EI-DR potential with

FERC’s NADR model and Monte Carlo technique

3.  Estimate costs for DR programs implementation and system impacts/benefits with ORCED model

Page 4: Demand Response Assessment for Eastern Interconnection · 3 Managed by UT-Battelle for the U.S. Department of Energy Study Objective and Tasks for Area 2 • Objective: Estimation

4 Managed by UT-Battelle for the U.S. Department of Energy

Our Reporting of EI Excludes West and Texas

Coverage of EI on NERC Map Census Regions and Divisions

Page 5: Demand Response Assessment for Eastern Interconnection · 3 Managed by UT-Battelle for the U.S. Department of Energy Study Objective and Tasks for Area 2 • Objective: Estimation

5 Managed by UT-Battelle for the U.S. Department of Energy

FERC’s Original Efforts and ORNL’s Improvements •  FERC contractors built the National Assessment of

Demand Response (NADR) model to estimate DR potential. –  The NADR model and analysis report were released in 2009. –  NADR estimates future peak load impacts under DR participation

assumptions. •  FERC has conducted bi-annual surveys of Demand

Response and Advanced Metering (FERC-731) since 2006. • ORNL updated the parameters, extended the projection

period, and added algorithms to improve NADR. –  ORNL used 2010 FERC-731 to update some primary parameters. –  ORNL extrapolated the number of DR customers not reporting to

FERC-731 and incorporated that number into NADR. –  ORNL brought in other data sources (e.g., EIA, Brattle Group).

Page 6: Demand Response Assessment for Eastern Interconnection · 3 Managed by UT-Battelle for the U.S. Department of Energy Study Objective and Tasks for Area 2 • Objective: Estimation

6 Managed by UT-Battelle for the U.S. Department of Energy

Types of DR Programs used by ORNL-NADR • Pricing Programs – Customers are offered time-varying

electricity rates on a prior-notice or real-time basis. –  Rates are typically higher during peak hours. –  Enabling Technologies, devices that automatically reduce

customer load in response to price signals, may be combined with some pricing programs to enhance load impacts.

• Direct Load Control – Customers receive monthly compensation for allowing utilities to control their appliances, such as water heaters and central air conditioners. –  This requires installation of special controller technologies upon

appliances.

Page 7: Demand Response Assessment for Eastern Interconnection · 3 Managed by UT-Battelle for the U.S. Department of Energy Study Objective and Tasks for Area 2 • Objective: Estimation

7 Managed by UT-Battelle for the U.S. Department of Energy

Types of DR Programs used by ORNL-NADR (cont.) •  Interruptible Tariffs – Customers receive a reduced

electricity rate or monthly compensation for agreeing to reduce their consumption by specified amounts upon utility’s request. –  Typically, only medium and large-sized commercial and industrial

customers may enroll in these programs.

• Other – Medium and large-sized commercial and industrial customers are incentivized to reduce their load through various mechanisms. –  Examples include Demand Bidding, Capacity Bidding, Aggregator/

Curtailment Service Provider programs, and System Reliability Event programs.

Page 8: Demand Response Assessment for Eastern Interconnection · 3 Managed by UT-Battelle for the U.S. Department of Energy Study Objective and Tasks for Area 2 • Objective: Estimation

8 Managed by UT-Battelle for the U.S. Department of Energy

ORNL-NADR Scenarios and Key Factors

BAU Optimistic BAU

Aggressive Deployment

Full Deployment

AMI deployment Partial deployment

Partial deployment

Full deployment

Full deployment

Dynamic pricing participation (of eligible)

Today’s level Voluntary (opt-in); 5%

Default (opt-out): 60 to 70%

Universal (mandatory) 100%

Eligible customers using enabling technology

None None 57% 100%

Basis for non-pricing participation rate

Baseline level Best practices estimate

Best practices estimate

Best practices estimate

Page 9: Demand Response Assessment for Eastern Interconnection · 3 Managed by UT-Battelle for the U.S. Department of Energy Study Objective and Tasks for Area 2 • Objective: Estimation

9 Managed by UT-Battelle for the U.S. Department of Energy

Optimistic BAU: Impacts from Non-Reporting Entities

• Only 52% of all utilities returned data to FERC for the 2010 survey.

• Only 16% of all utilities reported DR programs. •  The ORNL conservative scenario (i.e., BAU) assumes that

non-reporting utilities have no DR programs. •  The ORNL optimistic scenario assumes that non-reporting

utilities have the same level of customer participation in DR as reporting utilities in the same group. –  ORNL updated participation rates based on regressions using 2008

EIA and 2010 FERC survey data.

Page 10: Demand Response Assessment for Eastern Interconnection · 3 Managed by UT-Battelle for the U.S. Department of Energy Study Objective and Tasks for Area 2 • Objective: Estimation

10 Managed by UT-Battelle for the U.S. Department of Energy

EI Summer Peak Demand Forecast by ORNL-NADR

Page 11: Demand Response Assessment for Eastern Interconnection · 3 Managed by UT-Battelle for the U.S. Department of Energy Study Objective and Tasks for Area 2 • Objective: Estimation

11 Managed by UT-Battelle for the U.S. Department of Energy

Limited Peak Hours for DR modeling and Possibility of Overestimation •  NADR assumes DR applies to 4 hours for

top 15 days (limited 60 hours). At low DR penetration, the assumption works.

•  However, at high DR penetration, it is a more realistic modeling to shave the peak load from the top and spread DR impact over more hours to clip peak.

•  Therefore, the actual %PLR would be smaller than the %PLR calculated by ORNL-NADR.

5

10

15

20

25

30

Jul31 Aug01 Aug02 Aug03 Aug04 Aug05 Aug06

GW

System Load

With DR Base

!"#$%&' ()#$%&' *"+,$%&' -+$#+,$%&' *."/,$%&' 0/1$%&' !%2"/$%&'

5

10

15

20

25

30

Jul31 Aug01 Aug02 Aug03 Aug04 Aug05 Aug06

GW

System Load

With DR Base

!"#$%&' ()#$%&' *"+,$%&' -+$#+,$%&' *."/,$%&' 0/1$%&' !%2"/$%&'

Notch DR modeling (ORNL-NADR)

Smart DR modeling (Smart ORCED model)

0%  

10%  

20%  

30%  

40%  

50%  

EMM  Region  

%  PLR  calculated  by  ORNL-­‐NADR   %  PLR  calculated  by  Smart  ORCED  model  

Page 12: Demand Response Assessment for Eastern Interconnection · 3 Managed by UT-Battelle for the U.S. Department of Energy Study Objective and Tasks for Area 2 • Objective: Estimation

12 Managed by UT-Battelle for the U.S. Department of Energy

Potential Peak Reduction from Demand Response in EI, 2030

•  Under BAU and optimistic BAU, the largest gains through interruptible tariffs and other DR •  A significant growth in pricing programs (with and without enabling technologies) is noticed

under the Aggressive and Full Deployment scenarios. •  DLC has a significant impact in the residential and small C&I sectors. •  The majority of DR comes from large C&I customers primarily through interruptible tariffs

and capacity and load bidding. •  In the residential sector, most untapped potential for DR comes from the pricing programs.

Page 13: Demand Response Assessment for Eastern Interconnection · 3 Managed by UT-Battelle for the U.S. Department of Energy Study Objective and Tasks for Area 2 • Objective: Estimation

13 Managed by UT-Battelle for the U.S. Department of Energy

Demand Response Potential by Census Division and Scenario, 2030

!•  The regions show the largest existing (BAU) impacts have both wholesale demand

response programs and utility/load serving entity programs. •  Central air conditioning saturation plays a key role in determining the magnitude of

the Aggressive and Full Deployment demand response potentials.

Page 14: Demand Response Assessment for Eastern Interconnection · 3 Managed by UT-Battelle for the U.S. Department of Energy Study Objective and Tasks for Area 2 • Objective: Estimation

14 Managed by UT-Battelle for the U.S. Department of Energy

Top 10 states in System Peak in 2030

0 10,000 20,000 30,000 40,000 50,000 60,000 70,000

MW  

•  FL does not have the highest penetration of demand response, though it is the number-one state in system peak.

•  PA and NY have actively deployed high levels of demand response to cope with their high system peak demand.

!Top 10 States in System Peak (Y-axis: % Peak Load Reduction)

Page 15: Demand Response Assessment for Eastern Interconnection · 3 Managed by UT-Battelle for the U.S. Department of Energy Study Objective and Tasks for Area 2 • Objective: Estimation

15 Managed by UT-Battelle for the U.S. Department of Energy

Monte Carlo Simulation for Pricing Programs • Stochastic simulation for the impact of dynamic pricing

programs –  Allow random variation of previously fixed values for key

parameters to improve modeling of peak price elasticity

POTENTIAL LOAD REDUCTION FROM DYNAMIC PRICING PROGRAMS (MAINE, 2019) – An example of Monte Carlo simulation results

Page 16: Demand Response Assessment for Eastern Interconnection · 3 Managed by UT-Battelle for the U.S. Department of Energy Study Objective and Tasks for Area 2 • Objective: Estimation

16 Managed by UT-Battelle for the U.S. Department of Energy

Monte Carlo Simulation for Pricing Programs (Cont.)

Ra,o  of    CPP  to  

Ave.  Price  

Mean  (GW)  

Lower  (GW)  

Upper  (GW)  

Pricing  with  Enabling  

Technology  

5   52   41   64  

10   78   60   93  

15   94   74   118  

Pricing  without  Enabling  

Technology  

5   33   27   40  

10   49   40   57  

15   59   47   73  

•  An Example Result for Full Deployment Scenario, 2030

Page 17: Demand Response Assessment for Eastern Interconnection · 3 Managed by UT-Battelle for the U.S. Department of Energy Study Objective and Tasks for Area 2 • Objective: Estimation

17 Managed by UT-Battelle for the U.S. Department of Energy

Demand Response Supply Curve for EIPC Study

0

500

1,000

1,500

2,000

2,500

0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%

$/M

Wh

% of Maximum DR Available

DR 6-Block Supply Curve

Eff. CT w/o CO2

Ineff. CT w/ CO2

Model Curve w/ allocated non-price DR

5-Block Supply Curve Only with Pricing Programs in 2030

6-Block Supply Curve and Model Curve with Allocated Non-Pricing DR in 2030

Page 18: Demand Response Assessment for Eastern Interconnection · 3 Managed by UT-Battelle for the U.S. Department of Energy Study Objective and Tasks for Area 2 • Objective: Estimation

18 Managed by UT-Battelle for the U.S. Department of Energy

DR Cost Analysis

• DR is tied to Advanced Metering Infrastructure (AMI). –  AMI is necessary to enable many DR programs. –  The NADR model uses AMI deployment to proxy DR participation.

• ORNL reviewed data on AMI deployment costs and utility AMI deployment plans

• ORNL incorporated industry learning and economies-of-scale into cost calculations.

Page 19: Demand Response Assessment for Eastern Interconnection · 3 Managed by UT-Battelle for the U.S. Department of Energy Study Objective and Tasks for Area 2 • Objective: Estimation

19 Managed by UT-Battelle for the U.S. Department of Energy

Cost Estimates

Scenario Meters IT Systems Communications Network

Deployment Management

Annualized AMI O&M

High 243 65 66 81 23

Medium 190 27 43 63 7

Low 129 11 11 28 4

!

Estimated Cost-per-Meter of Various AMI System Component ($)

Page 20: Demand Response Assessment for Eastern Interconnection · 3 Managed by UT-Battelle for the U.S. Department of Energy Study Objective and Tasks for Area 2 • Objective: Estimation

20 Managed by UT-Battelle for the U.S. Department of Energy

Demand Response (DR) Benefits

• Oak Ridge Competitive Electricity Dispatch (ORCED) model simulates regional dispatch of generation to meet demand.

• With the reductions in demand during peak hours, ORCED calculates changes in generation and unserved energy, price, cost, and greenhouse gas emissions of utilities.

• DR benefits include: –  System peak impact –  System reliability impact –  Reduced system costs –  Environmental benefits

DR Benefit Case Regional % Peak Load Reduction

No DR (Reference Case) 0%

DR-Notch-BAU 1 – 10% (Ave. 5%)

DR-Smart-BAU 1 – 10% (Ave. 5%)

DR-Smart-Optimistic BAU 8 – 22% (Ave. 15%)

DR-Smart-Aggressive Deployment

16 – 35% (Ave. 23%)

DR-Smart-Full Deployment 19 – 47% (Ave. 30%)

Page 21: Demand Response Assessment for Eastern Interconnection · 3 Managed by UT-Battelle for the U.S. Department of Energy Study Objective and Tasks for Area 2 • Objective: Estimation

21 Managed by UT-Battelle for the U.S. Department of Energy

Geographical Classification for Benefits Analysis

229U.S. Energy Information Administration | Annual Energy Outlook 2011

!"#$%&'()*'+,

!"#$%&'!()''*+&,-%","-.'/0%1&-'/23$+&'%&#"245

Source: U.S. Energy Information Administration, O!ce of Energy Analysis.

!"

!!

!#

!$

""

"!

"#

!%

!&

$

!'

(

%

)

!

"

'&

!)

!(

*

!*

! "#! $%&'! $%&('!)**! +#! ,%&&! ,%&&!)**! -#! .%($! .%(!$/01! 2#! .%(3! .%(!3401! 5#! 6$3$! 67&&!648!$9:*/9;! <#! 6=&3! 67&&!6=&>3401?@4014A! B#! 6=CD! 67&&!CE9:!D0*/9;! F#! 6=G7! 67&&!GH01/14!6=! I#! %,&$! %,&!$/01!"J#! %,&.! %,&!.K?@K:/9! ""#! %,&3! %,&!3401

!"+#! L%M)! L$%&!M4*1/!"-#! L%N3! L$%&!N/148/O!"2#! L%L$! L$%&!LEP1@4/014A9!"5#! L%&$! L$%&!&491A/*!"<#! L%Q&! L$%&!Q)&)%!"B#! L76(! L77!6EA1@!"F#! L7L(! L77!LEP1@!"I#! )R6.! 3$&&!LEP1@8401!+J#! &).S! 3$&&!&/*KTEA9K/!+"#! 6377! 3$&&!6EA1@8401!++#! %.7)! 3$&&!%E?UK40

EIA’s Electricity Market Module Regions

Page 22: Demand Response Assessment for Eastern Interconnection · 3 Managed by UT-Battelle for the U.S. Department of Energy Study Objective and Tasks for Area 2 • Objective: Estimation

22 Managed by UT-Battelle for the U.S. Department of Energy

Impact on System Reliability

-­‐20%  

-­‐10%  

0%  

10%  

20%  

30%  

40%  

50%  

60%  

70%  

Reserve  Margin    in  2030  

No  DR  

BAU-­‐Notch  

Full  Deployment-­‐Smart  

Page 23: Demand Response Assessment for Eastern Interconnection · 3 Managed by UT-Battelle for the U.S. Department of Energy Study Objective and Tasks for Area 2 • Objective: Estimation

23 Managed by UT-Battelle for the U.S. Department of Energy

Change in Cost by DR

• Other factors reported such as change in reserve margins, average cost, and CO2 emissions

0  

50  

100  

150  

200  

250  

300  

350  

400  $/MWh  

Avoided  Cost  during  Peak  Hours   Average  GeneraSon  Cost  

Page 24: Demand Response Assessment for Eastern Interconnection · 3 Managed by UT-Battelle for the U.S. Department of Energy Study Objective and Tasks for Area 2 • Objective: Estimation

24 Managed by UT-Battelle for the U.S. Department of Energy

Future Research Directions

• Revise DR program participation rates •  Investigate demand reduction potential at the program

and appliance level • Update econometric estimation of load profiles for each

state and customer type •  Investigate duration and timing of DR programs

Page 25: Demand Response Assessment for Eastern Interconnection · 3 Managed by UT-Battelle for the U.S. Department of Energy Study Objective and Tasks for Area 2 • Objective: Estimation

25 Managed by UT-Battelle for the U.S. Department of Energy

Contact information for Further Discussions

• Youngsun Baek ([email protected]) • Stan Hadley ([email protected])