delay analisis

Upload: carlosgrande

Post on 04-Apr-2018

215 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/30/2019 delay analisis

    1/10

    Delay AnalysisBy Bruce Stephan

    Page 1

    I. Introduction

    A. Most construction disputes involve delay

    B. Each critical delay event should be analyzed

    C. Proving cause and effect is essential

    D. A convincing presentation is required

    II. Delay Claims

    A. Generally involves gray area

    B. Usually involves elements difficult to prove

    1. Suspended/Disruption of activities

    2. Out-of-sequence performance of work

    3. Acceleration directed or constructive

    4. Productivity losses

    5. Compensable extended duration of project

    C. CONTRACT DELAYS

    CONTRACTOR

    DELAYS

    OWNER DELAYS THIRD PARTY

    DELAYS (GR 8.10)

    Lack of proper resources Differing Site

    Conditions

    Acts of God

    Lack of proper planning Design Changes Weather

    Underestimation of

    duration

    Suspension Labor Strikes

    Material delivery delays Other Prime

    Contractor delays

    Utilities

    Subcontractor delays Late site access Acts of the Government

    Failure to follow schedule Later permits Acts of the State

    Acts of others beyond

    parties control

  • 7/30/2019 delay analisis

    2/10

    Delay AnalysisBy Bruce Stephan

    Page 2

    1. ** Note that the Owner may be due a credit for overhead or other time-related costs when an event occurs which shortens the Contract Time.

    Type Of Delay Cause Of Delay Time

    Extension

    Kor

    Delay

    Costs

    Owner

    Delay

    Costs

    INEXCUSABLE

    DELAYS

    Due solely to contractor No No Yes

    EXCUSABLE

    DELAYS

    Outside control of Contractor See below

    Non-compensable Concurrent delays, 3d Party

    & Force Majeure

    Yes No No

    Compensable Due solely to Owner Yes Yes No

    III.Schedule Analysis Methods

    A. Total Time approach

    B. But-For approach (Collapsed As-Built)

    C. Impacted As-Planned

    D. Should-Have-Been approach (Acceleration)

    E. Window Analysis

  • 7/30/2019 delay analisis

    3/10

    Delay AnalysisBy Bruce Stephan

    Page 3

    IV.Requests For Time

    V. Windows Method - Recognized Standard For Delay Analysis

    A. The impact of each change, or delay, on the previously charted sequences must befitted into the network. . . . Activities that were not critical prior to the new event may

    be rendered critical; and conversely, formerly critical activities may develop float.Whether the change or delay affects the critical path must be determined on the basis

    of conditions existing immediately prior to its occurrence. Norair Engineering Corp.,

    ENG BCA Nos. 3804, et al., 90-1 BCA P 22,327 at p. 112,205

    VI.Delay Analysis Windows Methodology

    A. Research Delay

    1. Read Contractors Claim

    2. Compare Baseline to As-Built Schedule

    3. Talk to Field Personnel, Designer, Owner, Contractor

    4. Analyze schedule reports to determine timing of delay

    5. Review field reports, correspondence, meeting minutes

    6. Using the information gained:

    ORIGINAL SCHEDULE

    as-built schedule

    Contract Finish

    Actual

    Finish

    schedule in effect at time of delay

    Requested TimeExtension

    Impacting events

    WINDOWS ANALYSIS

    TOTAL TIME APPROACH

  • 7/30/2019 delay analisis

    4/10

    Delay AnalysisBy Bruce Stephan

    Page 4

    7. Determine start and end dates of delay or extra work

    8. Determine affected activities

    9. Create a chart summarizing your findings

    10.Baseline/As Built

    B. Determine start date for delay & select schedule

    1. Determining proper schedule to use for analysis

    a) Use schedule in effect at start of delay

    b) Determining delay Start is subject to negotiation

    c) Consumed float automatically accounted for

    d) Time Extension measured from current delay

    (1)Presumes any delay to that was caused by other party

    e) May have to create schedule if not updated

    2. Methodology for Creating Schedule Updates (if needed)

  • 7/30/2019 delay analisis

    5/10

    Delay AnalysisBy Bruce Stephan

    Page 5

    C. Verify schedule update and modify as needed

    1. Schedule updates may need to be revised if:

    a) Does not reflect how work was planned

    b) Baseline logic improperly revised

    c) Constraints affect schedule calculation

    d) Actual starts and finishes are incorrect

    e) Prior impacts analyzed in earlier period

    (1)Adjust Milestones to reflect prior time adjustments

    (2)Include subnets for all delays previously analyzed

    2. How to determine if revision needed

    a) Compare baseline and latest schedule update

    b) Check impacted result against as-built

    c) Talk to field personnel familiar with work

    3. Sample Schedule Needing Revision

    Baseline

    Revised

    Baseline

    As Built

    Revise logic

    Remove Constraints

    Move data dateInput Actual Starts& Finishes(based on daily

    reports)

    Unimpacted

    Update 1

    Automatically transfer

    actual starts & finishes

    for select periods

    Unimpacted

    Update 2

    Unimpacted

    Update 3

    Impacted

    Update 3

    Copy

    Unimpacted

    Schedule and

    add delay

    activity

    Create Updates by copying

    revised baseline and moving

    data date to desired period

  • 7/30/2019 delay analisis

    6/10

    Delay AnalysisBy Bruce Stephan

    Page 6

    The longest path goes through

    kitchen work. This path was

    driven by a constrained start

    and a 10-day lag

    The schedule did not contain

    a contractually-required logic

    tie showing the B Wing work

    done by the end of summer

    recess. However, if the tie

    were made the schedule

    would have incorrectly shown

    a very late finish

    In the original schedule, all the

    B-Wing activities were lumped

    together. However, only the

    work east of the corridor had

    to be done by the end of

    Summer Recess

  • 7/30/2019 delay analisis

    7/10

    Delay AnalysisBy Bruce Stephan

    Page 7

    4. Thorough Document Revisions

    The longest

    path goes

    through kitchenwork. This path

    was driven by a

    constrained

    start and a 10-

    day lag

    A report of all

    changes is

    included as

    Attachment A

  • 7/30/2019 delay analisis

    8/10

    Delay AnalysisBy Bruce Stephan

    Page 8

    D. Add delay activities to show impact to schedule

    E. Determine successor and tie in to new activity

    F. Calculate and measure impact to project completion

    Steel Supplier submitted its steel shop drawings on 4/17, and expected approval 4/24. Design changes and a lack

    of dimensions delayed approval until 6/25. This caused a 41-day slippage to Project Completion (11/16/01-

    12/27/01)

    Yellow bars = Un-impacted schedule

    Pink bars =Impacted schedule

    Black bars = As-built schedule

    LEGEND:

  • 7/30/2019 delay analisis

    9/10

    Delay AnalysisBy Bruce Stephan

    Page 9

    G. Concurrent Delay Analysis

    1. Repeat the analysis for other sides delays

    a) Limit to critical delays

    2. Hard to determine if one delay tracking to other3. Does not have to be during same time period

    H. Verify dates against as-built & analyze mitigation

    I. Consider other options

    1. No cost logic changes (preferential logic)

    2. Low cost mitigation (2nd crew, equipment, etc.)

    3. Acceleration (overtime, etc.)

    4. Re-define Interim Milestone (defer scope)

    5. Transfer scope to follow-on Contractor

    Obviously, these are only useful if work is ongoing

    VII. Dispute Resolution

    Calculated

    time is laterthan actual

    Completion

    date

  • 7/30/2019 delay analisis

    10/10

    Delay AnalysisBy Bruce Stephan

    Page 10

    A. Negotiation Strategies

    1. Inform client/management of 3 possible dollar amounts

    a) Starting Position (white only)

    b) Realistic settlement offer (middle of grey)

    c) Final offer (all gray and white- no black)

    2. Get Independent evaluation of position

    3. Be prepared to give something away

    VIII. Summary

    A. Run comparisons and challenge client

    B. Use Windows Analysis

    C. Schedule Update just prior to delay

    D. Show Causation

    E. Consider Concurrency

    F. Compare results to As-Built

    G. Consider Alternatives to extending time

    CLEAR

    ENTITLEMENT

    DEBATABLE ENTITLEMENT NO

    ENTITLEMENT

    CHANGE ORDER/CLAIM ENTITLEMENT GRADIENT