ded review matrix

Upload: josirma

Post on 13-Apr-2018

241 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/26/2019 DED Review Matrix

    1/52

    KENYA PIPELINE COMPANY LTD

    REVIEW OF THE DETAILED ENGINEERING DESIGN BY SHENGLI ENGINEERING & CONSULTING COMPANY

    LIMITED/KURRENT TECHNOLOGIES LTD RECEIVED ON 02 DECEMBER 2013 BY KPC

    S/No Document No. Page

    No.

    Item No Short Description KPC Remarks Position

    1) All Documents General General All documents to have

    KPC Logo together with

    SLECC logo on the page

    header.

    Agreed

    2) All Documents General General The documents do not

    include PS14 in the

    design scope of works.

    a) Refer 2c in the

    negotiation

    minutes.

    b) Refer item 6.4:Initial

    understanding of

    Line-1 page 143

    c) Objective under

    the Terms of

    Reference (page

    22of 37 of the

    signed contract).

    Consultant to clarify

    omission of PS14.

    a. SLECC: Maintains that

    the scope of works does

    not include PS14.

    b. KPC: The objective

    would not be achieved if

    PS14 is not in the scope

    of works therefore the

    DED as presented will

    not be approved in that

    form.

    c. It was agreed that SLECC

    shall submit a written

    explanation to KPC to

    justify why PS14 is not

    in the scope of works.

    3) General Project risk matrix Scope of services item

    (c) of the signed

    contract. The project

    risk matrix should be

    submitted before

    approval of the

    detailed engineering

    design.

    SLECC to comply with the

    contract.

    PR PROCESS

  • 7/26/2019 DED Review Matrix

    2/52

    S/No Document No. Page

    No.

    Item No Short Description KPC Remarks Position

    4) General Terminal facilities Tank inlet nozzles and

    Protection facilities

    Consultant to clarify

    whether the tank inlet

    valves, tank vent

    valves, etc. are capable

    of operating at the

    increased flow rates for

    the new pipeline.

    Consultant to verify if

    the surge relief

    facilities (tanks) are

    adequate to cater for

    the increased flow

    rates under the new

    project.

    a. SLECC: Are adequate for

    Phase I. Will undertake

    review for phase II and

    Phase III.

    b.

    KPC: SLECC to undertake

    the review so that KPC

    can determine if the

    facilities shall be

    upgraded in phase I, II

    or III.

    c. It was agreed that SLECC

    would provide the

    details.

    5) General General Draft Tender Documents Consultant to indicatewhat documents willcomprise the tender

    documents.

    Agreed: SLECC to provide

    the list of documents tocomprise the tender

    documents.

    6) Schedule of Prices and

    Rates

    3 1.1Notes on Pricing

    Item VI

    Bidder shall allow for all

    applicable Statutory Taxes

    and duties that include but

    not limited to the following:

    a) VAT @16% or as applicable

    b) Withholding Tax @ 3% or

    as applicable

    Revise to read Bidder

    shall allow for all

    applicable Statutory

    Taxes, duties and levies

    applicable in Kenya and

    in the country of origin.

    7) DD-EM-TS-PR-001-A 2 Opening statement This system defines SLECCdocument numbering

    Remove SLECC andrevise the sentence to

    reflect the assignment.

    Agreed

    8)

    9) DD-LINE1R-BD-PR-001-

    A

    2 2.1 ABBREVIATIONS Both F&G and FGS are given

    as Fire & Gas System

    Differentiate SLECC to correct the

    document

    10) DD-LINE1R-BD-PR-001-

    A

    3 2.1 ABBREVIATIONS MSR - Motor Spirit Regulator Delete the item since

    this grade is no longer

    available in the Kenyan

    Market.

    SLECC to delete.

  • 7/26/2019 DED Review Matrix

    3/52

    S/No Document No. Page

    No.

    Item No Short Description KPC Remarks Position

    11) DD-LINE1R-BD-PR-001-

    A

    14 3.1 PRODUCTS

    DEMAND FORECAST:

    Bullet 4

    A 20 inch line has major

    implications on pumping

    capacity and options shall be

    listed and explained by theconsultants engineering

    team

    Give reference for the

    document where this

    concern is addressed.

    SLECC to delete the

    statement

    12) DD-LINE1R-BD-PR-001-

    A

    3.1 PRODUCTS

    DEMAND FORECAST:

    Bullet 5

    a) The Isiolo refinery threat

    can only become real

    b) This confirmation can be

    expected in the course of

    2013.

    a) Replace threat

    with impact

    b) Year 2013 is over.

    Review and update

    the status.

    SLECC to review

    13) DD-LINE1R-BD-PR-001-

    A

    17 3.3 PRODUCT

    SOURCING

    PS1 is the initial station of

    Line 1 and located in

    Mombasa.

    Refer item 6.4: Initial

    understanding of Line-1

    page 143 in the signed

    contract document

    which reads thus The

    pipeline originates at

    the foreshore terminal

    at Mombasa from the

    onshore tank farm and

    transport the entire

    volume at Nairobi

    Terminal. Review the

    statement.

    Related to PS14 issue that is

    pending clarification from

    SLECC

    14) DD-LINE1R-BD-PR-001-

    A

    18 4.1 STEADY STATE

    ANALYSIS: In Phase III

    (2037~2044)

    Use all of the existing pumps

    in PS2, PS4, PS6 and PS8.

    SLECC to demonstrate

    how the existing

    pumps, dis-used for

    over 20 years (2016 to

    2037) will be de-

    commissioned and re-

    commissioned and

    perform as expected

    on return to service.

    SLECC to respond later.

  • 7/26/2019 DED Review Matrix

    4/52

    S/No Document No. Page

    No.

    Item No Short Description KPC Remarks Position

    15) DD-LINE1R-BD-PR-001-

    A

    19 4.2 TRANSIENT SURGE

    ANALYSIS

    ..are not exceeded for

    pipeline upset conditions

    Clarify upset

    conditions

    Abnormal conditions

    16) DD-LINE1R-BD-PR-001-

    A

    21 5: OVERVIEW OF

    EXISTING PIPELINE

    SYSTEM (LINE 1)

    5.1 PIPELINE The overview is silent

    on PS14.

    Consultant to include

    PS14 scope of works.

    Item in abeyance

    17) DD-LINE1R-BD-PR-001-

    A

    23 5.2: PS1 .discharge pressure

    limits are not exceeded by

    upset pipeline conditions.

    Clarify upset

    conditions

    Abnormal conditions

    18) DD-LINE1R-BD-PR-001-

    A

    29 6: SCOPE OF SERVICES-

    6.1 PREAMBLE

    Only one oil water treatment

    system will be installed in PS9

    for concentrate treatment.

    New oil water separator

    (OWS) will be installed in PS3,

    PS5 and PS7.

    Consultant to include

    design for OWS at PS1,

    PS10 and PS14 which

    are considered to be in

    phase I. Designs for

    phase II and III to

    ensure that the OWS in

    the respective stations

    are included.

    KPC: To decommission

    existing and design for the

    entire station at PS10.

    Currently no OWS at PS1

    SLECC to include.

    19) DD-LINE1R-BD-PR-001-

    A

    30 6.2 PHASED

    IMPLEMENTATION:

    Phase I

    Upgrade of firefighting

    systems in PS9, PS10 and

    PS12.

    All upgrade of

    firefighting facilities to

    be done in Phase I in all

    stations

    SLECC to review in line with

    the fire risk assessment

    report.

    20) DD-LINE1R-BD-PR-001-

    A

    30 6.2 PHASED

    IMPLEMENTATION:

    Phase III

    Complete intermediate pump

    stations of PS1, PS3, PS5 and

    PS7 with additional two new

    mainline pumps.

    Refer comments on

    item 4.1: Steady state

    analysis .

    SLECC to review

    21) DD-LINE1R-BD-PR-001-

    A

    36 6.3.6 PS9 PS9 is a depot for Nairobi

    Airport, which downloads DPK

    from line 1.

    a) PS9 Depot supplies

    JET-A1 to Jomo

    Kenyatta

    International

    Airport.

    b) PS9 receives JET-A1

    from Line-1 and

    not DPK. Change in

    SLECC to correct

  • 7/26/2019 DED Review Matrix

    5/52

    S/No Document No. Page

    No.

    Item No Short Description KPC Remarks Position

    all the other

    documents.

    22) DD-LINE1R-BD-PR-001-

    A

    39 7.5 PRESSURE RELIEF

    SYSTEM

    In addition to this, pilot

    operated safety valves shall

    be provided on the pipeline at

    each station inlet.

    Clarify pilot

    operated.

    SLECC to change to spring

    23) DD-LINE1R-BD-PR-001-

    A

    39 7.7 FLOW METERS Description of location of flow

    meters in the design

    No mention of flow

    meters for firefighting

    water system.

    Consultant to clarify.

    SLECC: Included in other

    documents.

    It was agreed SLECC would

    include the description.

    24) DD-LINE1R-BD-PR-001-

    A

    40 7.10 FIRE WATER NET

    WORK, FIRE DETECTION

    AND ALARM SYSTEM

    a. General Reference to

    NFPA code

    b. Statement - Fire water

    shall consist of foam

    preparation and injection

    system.

    c. Fire detection and alarm

    system for buildings

    a. Clearly specify

    applicable codes in

    every item used in

    the design.

    b. Clarify if this

    includes foam

    handlines and

    monitors in the

    design.

    c. Include fire

    suppression system

    for switch rooms.

    a. SLECC to cross reference

    the appropriate

    document for the codes.

    b. SLECC to include.

    c. SLECC to include.

    25) DD-LINE1R-BD-PR-001-

    A

    41 7.10 FIRE WATER NET

    WORK, FIRE DETECTION

    AND ALARM SYSTEM

    A fire detection alarm system

    covering all buildings, tank

    farm and pump shelter, shall

    be provided.

    Revise to read all new

    facilities.

    Connect to the existing

    fire alarm system

    SLECC: Agreed

    KPC: To provide the location

    of the existing fire alarm

    system26) DD-LINE1R-BD-PR-001-

    A

    41 7.12 OIL WATER

    SEPARATOR AND

    TREATMENT SYSTEM

    The new OWS are comprised

    an oil OWS capacity based on

    rainwater collection on

    process area

    This basis isnt

    sufficient. Design as per

    EPA standards defining

    drainage catchment

    area for the OWS and

    dimensions, volume of

    largest containment in

    the area, highest

    precipitation for

    SLECC to revise in

    accordance with EPA

  • 7/26/2019 DED Review Matrix

    6/52

    S/No Document No. Page

    No.

    Item No Short Description KPC Remarks Position

    region, hence flow rate

    in and out of OWS, etc.

    27) DD-LINE1R-BD-PR-001-

    A

    42 7.12 OIL WATER

    SEPARATOR AND

    TREATMENT SYSTEM

    The pre-separated water shall

    be loaded to road tanker

    through water lift pumps to

    PS9 for disposal.

    Provide holding ponds

    at every station for the

    pre-separated water.

    Included in the design

    28) DD-PS10-DW-WT-001-

    A Model (1)

    Drawing Oil water separator not

    provided. Consultant is

    connecting to existing system.

    Relocate existing OWS

    to a suitable location as

    determined in your fire

    risk assessment. Design

    to include new and

    existing facilities

    including the proposed

    new tanks.

    Agreed

    29) DD-LINE1R-BD-PR-001-

    A

    48 8.3 DISTANCE FROM

    BUILDING TO EDGE OFFIRE IN EACH PUMP

    STATION

    Fire risk assessment Refer to KPC comments

    on the fire riskassessment report.

    SLECC: Fire risk assessment

    is being updated.

    30) DD-LINE1R-BD-PR-001-

    A

    49 8.4 ASD AT THREE

    TERMINALS

    Fire risk assessment Refer to KPC comments

    on the fire risk

    assessment report.

    SLECC: Fire risk assessment

    is being updated.

    31) DD-LINE1R-BD-PR-001-

    A

    49 8.3/8.4: ASD for

    structures

    ASD for structures Relate findings to

    materials of building

    and determine safety

    requirements

    SLECC to review.

    32) DD-LINE1R-BD-PR-001-

    A

    49 8.5: ASD for Humans ASD for humans a. Relate findings in

    item 8.1 in

    determining safe

    locations for

    manual controls of

    firefighting system

    in the field.

    b. Apply to all

    stations.

    KPC: The automated system

    must have a manual system

    that is in consideration of

    the ASDs for humans.

    SLECC to review.

    33) DD-LINE1R-RP-PR-002 6 5 MODELED SCENARIOS Tripping one running pump Clarify the basis of the SLECC to Clarify

  • 7/26/2019 DED Review Matrix

    7/52

    S/No Document No. Page

    No.

    Item No Short Description KPC Remarks Position

    FOR 20 PIPELINE IN

    PHASE I

    and shutting down pumps at

    other stations in 30, 60, 90

    seconds intervals.

    choice for intervals of

    30 seconds upto 90

    seconds.

    34) DD-LINE1R-RP-PR-002 Whole document Transient surge analysis The pressures and flow

    indications at upstream

    and downstream

    stations does not agree

    with the reality.

    Consultant to clarify

    KPC: Pressure in the

    upstream stations decrease

    whereas the pumps are

    pumping against a closed

    system.

    SLECC: To review.

    35) DD-LINE1R-RP-PR-002 11 5.1.2 Inlet valve at PS1 closes Perform surge analysis

    for PS1-PS14 section.

    Section under abeyance.

    36) DD-LINE1R-RP-PR-003 23 4.2.5 Review on

    capacity of existing slop

    tank

    So it is recommended that the

    additional tank capacity be

    increased with 800m3with

    two new slop tanks each with

    400m3to be erected.

    Provide design basis for

    slop storage tanks

    capacity and the re-

    injection pumps

    ratings.

    Item 2.4.3 gives 600m3

    slop tank capacity

    SLECC to review and advice.

    37) DD-PLN-SPC-PL-001. 1 1 GENERAL According to process scheme,

    three new pipelines will be

    constructed from PHASE I to

    PHASE IV.

    There is no Phase IV.

    Revise appropriately.

    Agreed

    38) DD-PLN-SPC-PL-001. 4 3.2 From KP 442.7-444.3km, LINE

    1 is under the lawn of

    factories and there is no spacefor new pipeline to be

    installed by open-cut method.

    HDD method is

    recommended.

    This area has the ROW

    clearly marked and left

    out even though withinfactories. Excavation

    can be done.

    SLECC to verify on site and

    revise accordingly.

    39) DD-PLN-SPC-PL-001. 5 3.2 From KP 447.4-449.0km, the

    ROW ranges from 13 to 23m,

    and LINE1, LINE 2 and LINE4

    are existing. Within the 13m

    wide ROW, the new pipeline

    4No. pipelines in a

    space of 13m dont

    justify two lines to be

    in one ditch. Line

    1Replacement to be in

    Agreed. SLECC to revise

  • 7/26/2019 DED Review Matrix

    8/52

    S/No Document No. Page

    No.

    Item No Short Description KPC Remarks Position

    needs to be laid in one ditch

    with LINE 1 for about 500m.

    its own ditch. Revise

    appropriately.

    40) DD-PLN-SPC-PL-001. 46 17.5 RESPONSIBILITY Leaks, or breaks in the

    pipeline during the test which

    are a result of defective

    materials furnished by the

    Engineer shall be located and

    repaired by the Contractor,

    but cost thereof shall be paid

    by the Engineer as extra cost.

    There are no Free

    issue items in the

    contract hence

    Engineer will not

    supply any materials.

    Delete and revise the

    section Appropriately.

    Agreed. SLECC to delete.

    41) DD-LINE1R-DW-PR-

    008-A

    Drawing PS1 supply pipelines Provision for supply

    from KPRL to be 20

    and not 14

    Agreed. SLECC to revise.

    42) DD-LINE1R-DW-PR-

    008-A

    Drawing PS1 supply line from PS14 There should be no

    non-return valve on the

    line from PS14 to PS1

    Agreed. SLECC to revise

    43) DD-LINE1R-SPC-PR-

    001-A

    4 2.2 The safety

    requirement of pipeline

    system

    The safety requirement of

    pipeline system

    a. No mention of

    pumps start

    sequence

    protection;

    b. Include for

    firefighting system

    operation

    c. Include for OWS

    system

    a. Agreed. SLECC to

    include pump start

    sequence protection.

    b. Agreed. SLECC to revise.

    c. Agreed. SLECC to revise.

    44) DD-LINE1R-SPC-PR-001-A

    4 2.2.2 Discharge of mainpump

    When the main pump unitsare in parallel operation, if

    discharge high pressure

    switch gives an alarm, all the

    parallel main pumps are

    interlocked and stopped

    a. The pumps shouldbe configured to

    give 1st

    alarm and

    stop on 2ndalarm.

    b. Usage of the term

    Interlock is not

    clear as used here

    and item 2.3.2B(c).

    Page 9. Clarify

    KPC: Pump should not bestopped at once.

    a. Agreed. SLECC to revise.

    b. SLECC to clarify

    interlock.

    45) DD-LINE1R-SPC-PR- 9 2.3.2 Main process a. When the temperature a. Clarify the interlock a. SLECC to clarify

  • 7/26/2019 DED Review Matrix

    9/52

    S/No Document No. Page

    No.

    Item No Short Description KPC Remarks Position

    001-A system operation

    Item 2.3.2B(c)

    reaches to the high alarm

    value, the main pump is

    interlocked and stopped

    immediately.

    b. When the oil temperature

    of main pump motor

    bearings reaches to the

    high alarm value, the

    main pump is interlocked

    and stopped immediately.

    c. When the shell

    temperature reaches to

    the high alarm value, the

    main pump is interlocked

    and stopped immediately.

    in the three bullets.

    b. No start sequence

    protection and

    interlock system.

    interlock.

    b. Agreed. SLECC to

    include pump start

    sequence protection.

    46) DD-LINE1R-SPC-PR-001-A

    15 4.2.2 OperatorWorkstation

    Two station control operatorworkstations shall be located

    at the following Stations:

    PS9, 10 and 14 notincluded. Include or

    clarify the omission.

    SLECC to provideworkstations.

    47) DD-PS1-DW-PR-006-A Drawing Corrosion Inhibitor (CI)

    Package

    a. Dosing pump rating

    b. CI storage tank is common

    for both 14 and 20

    pipelines

    c. Vendor/Contractor

    a. The ratings of

    pumps 1A-P-

    901/902 are not

    indicated. The

    pump rating should

    be upto the highest

    design Flow rate

    for 20pipe.b. Design separate CI

    dosing systems for

    the 20 and 14

    pipelines.

    c. Remove vendor

    and replace with

    complete unit.

    This applies to all

    drawings/packages.

    a. Dosing pumps

    SLECC: Document

    included in the

    mechanical

    equipment

    documents.

    KPC: 16.2l/hr is

    based on 9ppm, at440m3/hr for the

    existing system

    which is not

    adequate. SLECC to

    review the design to

    use parameters for

    20 and 14

    respectively.

    Confirmation of

  • 7/26/2019 DED Review Matrix

    10/52

    S/No Document No. Page

    No.

    Item No Short Description KPC Remarks Position

    compliance to be

    included in QA/QC

    plan for the CI

    dosing.

    b. Agreed. SLECC to revise.

    c. Agreed.

    48) DD-PS1-DW-PR-007-A Plot Plan Plot Plan for PS1 The location for the

    new station doesnt

    consider economical

    utilization of land.

    Locate the station

    according to the fire

    risk assessment.

    SLECC to review.

    49) DD-PS10-DW-PR-002-A Plot Plan Piping for PS10 The piping at PS10

    should make provisionsfor connection to Lines

    2 & 4 through by-pass

    lines.

    Agreed

    50) DD-MLV-DW-PR-002 Drawing Typical 20 Block Valve

    Installation

    a. Chamber cover

    gauge to be

    minimum 8mm.

    b. Valve and Pipe

    should be the same

    diameter.

    c. Purpose oftransition Piece

    to be explained.

    d. Sealing between

    pipe and chamber

    wall to be water

    tight.

    a. Agreed.

    b. Agreed.

    c. SLECC to clarify.

    d. Mandatory.

    51) DD-MLV-DW-PR-003-A Drawing Mainline valve chambers a. There is no clear

    indication on the

    type of bottom

    a. Mandatory.

    b. SLECC to review. SLECC

    to review size of valves

  • 7/26/2019 DED Review Matrix

    11/52

    S/No Document No. Page

    No.

    Item No Short Description KPC Remarks Position

    floor finish. Should

    be concrete screed

    finish and

    waterproof walls.

    b. The size of the

    valve chamber is

    too big for a 20

    valve. Provide 1m

    clearance all-round

    the valve.

    from the vendor and

    design the valve

    chamber accordingly or

    3000mmx 2500mm

    whichever is smaller.

    52) DD-PS1-DW-WT-001-A Drawing Connect to existing Oil Water

    Drain Piping at PS1

    a. There is no

    indication where

    this pipe leads to.

    b. Connection to KPRL

    OWS not

    permitted.

    Agreed.

    There is no OWS at PS1

    53) DD-PS3-DL-FW-001

    &

    DD-PS3-SCH-FW-001

    PS3 Firefighting system Firefighting system - No foam

    protection system for station

    especially pump shed area

    Provide automated

    foam protection

    systems complete with

    monitors and handlines

    for pump shed area,

    etc.

    This shall apply to all

    stations

    To provide fixed automated

    monitor system.

    Agreed

    54) All documents General Process Risk Assessment - No

    risk assessment for stationand correlation with location

    and safety of control building,

    pump shed, etc.

    Complete the risk

    assessment and use itto review suitability of

    buildings locations and

    safety in all the

    stations.

    SLECC to refer NFPA 551

    with respect to the buildingsand revert

    55) DD-LINE1R-CL-FW-001 CALCULATION SHEETS

    FOR FIRE PROTECTION

    SYSTEM

    a) Calculations for

    firefighting water.

    b) Cooling water calculation

    c) Non-dyked spill areas

    protection; application

    a) Firefighting water

    calculations should

    not include the

    proposed new

    tanks. A decision

    a) Agreed.

    b) Refer NFPA 11. (KPC to

    clarify further).

    c) Agreed to review.

    d) SLECC: Has based

  • 7/26/2019 DED Review Matrix

    12/52

    S/No Document No. Page

    No.

    Item No Short Description KPC Remarks Position

    rate for Floroprotein (FP)

    6.5L/min .m2& others

    foams 4.1L/min .m2

    d) Surface application rate

    with fixed foam discharge

    outletsused 6.5L/min

    .m2

    has been made not

    to put up the

    additional tanks at

    PS9

    b) Cooling water

    protection system

    application rate

    of 4.1L/min .m2

    used for floating

    roof tanks instead

    of 12.2L/min .m2.

    Consultant to

    clarify.

    c) Review calculations

    for non-dyked

    areas.d) Should be 4.1L/min

    .m2. 6.5L/min .m2

    rate should be for

    handline and

    monitor systems

    calculations on KS1967.

    KPC recommends use of

    NFPA 11. To be

    56) DD-PS09-DW-FW-001-

    A

    Drawing New Fire water tanks 9-TK-

    803

    Review firefighting

    facilities at PS9 owing

    to the decision not to

    construct the new

    tanks.

    Agreed

    57) DD-PS09-DW-FW-008-

    A DD-PS10-DW-FW-

    012-A

    Drawing 9A-M-853A/B Hydraulic

    turbine

    10A-M-853A/B Hydraulic

    turbine

    Clarify the use and

    necessity for the

    hydraulic turbine.

    SLECC to confirm the rating

    of the standby generator

    and whether it can run the

    foam pump.

    58) DD-PS09-DW-FW-010-

    A

    PS9 Plot layout Tank farm dyked areas - there

    is no foam system protection

    a. Provide automated

    foam system

    protection c/w

    monitors and

    handlines.

    KPC to review and revert for

    dyked and non-dyked areas.

  • 7/26/2019 DED Review Matrix

    13/52

    S/No Document No. Page

    No.

    Item No Short Description KPC Remarks Position

    b. To apply to all

    stations.

    59) PD-PS09-SCH-FW-001 Equipment list Equipment list To be revised to

    include/exclude items

    after review of the

    comments on

    firefighting system

    Agreed

    60) DD-PS1-DW-FW-013-A Drawing Changamwe Terminal & Pump

    Station PS1: Toilet water

    supply and drainage piping

    installation.

    a. Changamwe is not

    a terminal but a

    pump station.

    Revise.

    b. The domestic

    water and drainage

    system are

    provided under fire

    fighting system forthe station.

    Relocate

    appropriately.

    a. Agreed.

    b. Agreed.

    61) DD-PS10-DW-FW-017-

    A

    Drawing Fire protection system piping

    layout

    (Same applies to PS12)

    a) No foam protection

    system for dyked

    areas, product

    reception area etc.

    To be included.

    b) Review foam tank

    capacity to includeabove

    requirements.

    c) Review equipment

    listDD-PS10-SCH-

    FW-001

    accordingly.

    KPC to review and revert for

    dyked and non-dyked areas.

    62) DD-LINE1R-SPC-FW-

    001

    GENERAL

    SPECIFICATION FOR

    FIREFIGHTING

    a) Cooling water pumps

    1. PS92 No each rated

    at 200l/s (720m3/hr)

    a) The rating of the

    pumps is

    exceptionally high.

    a) SLECC to review PS9

    firefighting

    requirements to exclude

  • 7/26/2019 DED Review Matrix

    14/52

    S/No Document No. Page

    No.

    Item No Short Description KPC Remarks Position

    on 1+1 mode

    2. PS106 No. each

    rated at 170l/s

    (612m3/hr) on 3+3

    mode.

    3. PS122 No. each

    rated at 130l/s

    (468m3/hr) on 1+1

    mode

    b) Foam water pumps

    1. PS92 No. each

    rated at 160l/s

    (576m3/hr) on 1+1

    mode.

    2. PS10- 2 No each rated

    at 220l/s (792m3/s) on1+1 mode and to use

    existing fire pumps.

    3. PS122 No. pumps

    each rated at 30l/s

    (108m3/hr) on 1+1

    mode and to use

    existing fire pumps.

    The consultant has

    not revised as per

    comments sent

    with regard to the

    fire risk

    assessment.

    a) Consultant must

    review the

    calculation for

    water

    requirements and

    the equipment

    ratings to be

    revised

    accordingly.

    b) Clarify use ofexisting pumps for

    foam water.

    Refer comments Nos

    26 & 27 of the matrix

    sent vide letter ref

    EN/PR/29/4/58 dated

    25th

    November 2013.

    the proposed new

    tanks.

    b) KPC/SLECC to jointly

    review.

    c) SLECC to confirm the

    condition, performance

    and suitability of the

    existing fire water

    pumps for foam water

    system. PS12 will not re-

    use existing fire water

    pumps. SLECC to review

    the

    condition/performance

    of the existing pumps

    and revert.

    63) DD-PS1-DW-BR-003-A

    DD-PS1-DW-BR-004-A

    Civil Works Drawings Roads a. Road layout plan

    shows 4m. Thedesign should cater

    for the largest

    vehicle, crane or

    truck.

    b. Turning radius is

    only 9m. Confirm

    that the can carry

    the 50ton truck

    crane. KPC

    recommends use of

    KPC: Allow dead weight and

    sizing of a Zoomlion truckcrane capacity 50ton.

    SLECC to review

  • 7/26/2019 DED Review Matrix

    15/52

    S/No Document No. Page

    No.

    Item No Short Description KPC Remarks Position

    Cabro Blocks

    pavement

    64) DD-PS1-DW-BR-006-A Civil works drawings Drainage works The design for the

    waste water pipe is not

    necessary. Consultant

    should consider open

    channel design to allow

    clearance of silt during

    maintenance

    Maintain open channel and

    wastewater piping

    separately.

    65) DD-PSXX1-DW-WT- Series of documents Water Treatment - OWS

    design

    a. Approval by NEMA,

    b. Allow for water

    recycling from

    downstream

    chambers into

    upstream

    chambers forbetter flexibility

    and worst case

    scenarios, e.g. DD-

    PS9-DW-WT-002 &

    003-As

    SLECC/Kurrent to seek

    NEMA approval.

    KPC expressed concern on

    the absence of the local

    partner to handle local

    regulatory matters.

    Schedule of Prices

    66) LINE1R-TD-001 6 1.1 Introduction Item

    1.1.1:

    a) The Client named in the

    Appendix to GI will

    invite pre-qualified

    bidders to submit tenders,b) The method of selection

    shall be as indicated by

    the procuring entity in the

    Appendix.

    a) CMT/CS to clarify

    on prequalified

    biddersin view of

    Legal Notice 114b) The method shall

    be least cost and

    not quality and

    cost based.

    Two stage evaluation.

    Agreed

    67) LINE1R-TD-001 6 1.1 Introduction Item

    1.1.7:

    The price to be charged for

    the tender document shall be

    Kshs.50,000.00.

    Cost of tender

    documents to be in

    accordance the

    SLECC to review as per

    Procurement Act and Legal

    notice 106, 109 and 114.

    1XX For PS3 to PS10

  • 7/26/2019 DED Review Matrix

    16/52

    S/No Document No. Page

    No.

    Item No Short Description KPC Remarks Position

    procurement laws and

    recent legislation.

    68) LINE1R-TD-001-A 6 1.1 Introduction Item

    1.1.11

    Bidders who choose not to

    enter into a joint venture

    must also provide a Power of

    Attorney signed by the legally

    authorized signatories of the

    company.

    Clarify the purpose of

    this clause

    Retained. SLECC clarified

    that this was for sole

    bidders.

    69) LINE1R-TD-001-A 6 1.1 Introduction Add new clause and add the

    following mandatory

    requirements.

    a) Compliance with

    Kenya Subsidiary

    Legislation - Legal

    Notice No 114 on

    the Public

    Procurement and

    Disposal

    (Preference andReservations)

    (Amendment)

    Regulations 2013

    with regard to

    participation by

    local entities.

    b) National

    Construction

    Authority

    certificate for localfirmsClass NCA-

    1.

    c) Tender Security to

    be in accordance

    with the law i.e.

    should not exceed

    2% of the

    estimated contract

    value.

    a) SLECC agreed to review.

    b) SLECC agreed to review

    c) SLECC agreed to review.

  • 7/26/2019 DED Review Matrix

    17/52

    S/No Document No. Page

    No.

    Item No Short Description KPC Remarks Position

    70) LINE1R-TD-001-A 7 1.2 Eligibility and

    Qualification Criteria

    Eligibility Criteria To be reviewed for a

    construction tender

    and to include all legal

    requirements.

    SLECC agreed to review.

    71) LINE1R-TD-001-A 8 1.3.2 Local

    participation

    Local participation Ensure compliance

    with Kenya Subsidiary

    Legislation - Legal

    Notice No 114 on the

    Public Procurement

    and Disposal

    (Preference and

    Reservations)

    (Amendment)

    Regulations 2013 with

    regard to participation

    by local entities.

    SLECC agreed to review.

    72) LINE1R-TD-001-A 52 34.6 Compensation for

    injury

    The Contractor shall, in

    accordance with the

    Workman's Compensation Act

    Chapter 236 of the laws of

    Kenya

    Replace workmen

    compensation Act Cap

    236 with Workmen

    Injury Benefits Act

    (WIBA) 2007

    SLECC agreed to review.

    73) LINE1R-TD-001-A 76 Clause 1Project

    Quality Assurance

    System Requirements

    Item: 1.2 Quality Plan a. Include as

    requirement for

    evaluation of

    technical proposal.

    b. To be reviewed atcontract signing

    SLECC agreed to review.

    74) LINE1R-TD-001-A 83 Clause 12Safety

    Precautions

    Safety Precautions Include requirement

    for Safety Plan for

    project activity

    SLECC to request for a

    project execution plan.

    75) LINE1R-TD-001-A 87 Clause 12 First Aid Outfits Provide first aid

    stations as per OSHA

    [2007] and subsidiary

    legislation

    SLECC agreed to review.

    76) LINE1R-TD-001-A 87 Clause 29 Fire Precautions Provide as per safety SLECC agreed to review.

  • 7/26/2019 DED Review Matrix

    18/52

    S/No Document No. Page

    No.

    Item No Short Description KPC Remarks Position

    plan for the project

    77) LINE1R-TD-001-A 93 Clause 36Transport

    for the Engineer and

    the Engineers

    Representative

    4 No. Isuzu Troopers, Model

    UBS 69, or latest equivalent

    diesel driven (3059 cc), 5

    speed manual, four door

    featuring.

    Comply with

    Procurement rules in

    Kenya

    SLECC agreed to review.

    78) LINE1R-TD-001-A 94 Clause 39 & 40 Dust Nuisance and pollution /

    waste management

    Provide as per project

    EMPRef. ESIA report

    SLECC to consult with

    Kurrent

    79) LINE1R-TD-002-A 5 PG/M6 Purchase, deliver, maintain

    and fuel 4 NO. double cabins

    4WD type vehicles and 1 NO.

    standard 4WD station wagon

    in employer's name under a

    "blue plate" as specified for

    the exclusive use of the

    Engineer for the duration ofthe Contract

    Dele under a "blue

    plate"

    a. Review the specification

    for the vehicles.

    b. Allow 8 vehicles

    exclusively for the use

    by the Engineer.

    80) LINE1R-TD-002-A 5 PG/M7 Allow for unpacking,

    inspecting, loading and

    transporting to site all Free

    Issue equipment from the

    Employers stores at Nairobi

    Terminal

    Delete item. There shall

    be no free- issue

    items under this

    contract.

    Agreed.

    81) LINE1R-TD-002-A 6 C/P/MP 2 Transport the field bends and

    shop bends to the work site

    Transportation of all

    pipe fittings, valves,

    etc. to be included inthe transportation of

    the mainline pipeline

    for ease of payments.

    No separate bill item for

    transportation to site as it is

    included in the supply ofmaterials. SLECC to revise.

    82) LINE1R-TD-002-A 7 to

    8

    C/P/MP 11.1 to 11.9 m/times Detail each crossing

    individually giving its

    length and any other

    necessary details such

    as chainage/location.

    SLECC: Agreed to review.

    83) LINE1R-TD-002-A 8 C/P/MP11.10 to 11.2 Swamp crossing (open cut), Delete items. Introduce SLECC agreed to review

  • 7/26/2019 DED Review Matrix

    19/52

    S/No Document No. Page

    No.

    Item No Short Description KPC Remarks Position

    High voltage line crossing,

    Water pipeline crossing,

    Existing product pipeline(LINE

    1/2/4) crossing

    a new bill item under

    Preliminary and

    General item as

    follows: - Allow for

    location and protection

    of existing services

    such as water pipes,

    swamps, existing

    product line etc at pipe

    crossings.

    84) LINE1R-TD-002-A 8 C/P/MR 12 Allow a provisional sum for

    liaising with local authorities

    and other relevant

    government departments for

    road or rail crossings including

    the necessary permits forexecution of the works.

    Move item to

    Preliminary and

    General items

    SLECC: Agreed to review.

    85) LINE1R-TD-002-A 10 C/P CR 26 Hydraulic protection in the

    form of retaining wall and

    cutoff wall to prevent the

    water from scouring the

    pipeline trench, all in

    accordance with specifications

    and detailed drawings. The

    materials usually adopt the

    mortar rubble masonry andconcrete.

    Hydraulic Protection

    for major river

    crossings are known

    and require to have

    properly designed

    protections with their

    individual bills of

    quantities, for ease of

    measurement forpayment purposes, as

    follows;

    1. Voi river

    2. Athi river

    3. Any other

    major rive, etc.

    SLECC: Agreed to review.

    86) LINE1R-TD-002-A 11 1.3.2.1 Civil & Road

    Works

    Excavations a. The schedule of

    rates and prices

    needs to be clear

    SLECC to review the civil

    works bills and revise to suit

    CESSM-3

  • 7/26/2019 DED Review Matrix

    20/52

    S/No Document No. Page

    No.

    Item No Short Description KPC Remarks Position

    for excavations of

    Trenches width e.g.

    >0.3m and depth

  • 7/26/2019 DED Review Matrix

    21/52

    S/No Document No. Page

    No.

    Item No Short Description KPC Remarks Position

    Average thickness0.25m excavations, consultant

    to specify that the

    borrow material shall

    be from the nearest

    approved borrow site.

    This applies to both the

    pipeline and the

    stations.

    91) LINE1R-TD-002-A all C/PS1/MP 32

    C/PS1/E 24

    C/PS1/IC 46

    2 years operational and

    maintenance spares and

    special tools for all mechanical

    equipment.

    Consultant to make it

    very clear in the tender

    document that the

    contractor must give a

    comprehensive list of

    a. Commissioning

    spares for

    everyequipment

    b. 2-year

    operating

    spares for

    every

    equipment

    SLECC to review

    92) LINE1R-TD-003-A 5 2.1.2 Construction

    Method Statements

    and Procedures

    The Contractor shall prepare

    and submit to the Employer

    for approval

    Change Employer to

    Engineer. Revise all

    documents to reflect

    the same.

    Agreed

    93) LINE1R-TD-003-A 6 2.1.6 Site Safety At all times during site

    construction, the Contractor

    shall comply with the

    Employers site safety

    procedures.

    Contractor to comply

    HSE legal and

    administrative

    framework in Kenya

    SLECC to revise the tender

    document.

    94) LINE1R-TD-003-A 7 2.2.6 Cleaning and

    Decommissioning of

    the existing Line-1

    The contractor shall take a

    suitable method to clean up

    of the existing Line-1 for

    decommissioning.

    Decommissioning

    procedure should be

    as per EMP in ESIA

    report for the project.

    SLECC to provide the

    procedure in the tender

    documents in accordance

    with the EMP and ESIA

  • 7/26/2019 DED Review Matrix

    22/52

    S/No Document No. Page

    No.

    Item No Short Description KPC Remarks Position

    reports approved by NEMA.

    95) LINE1R-TD-003-A 8 2.3.2 Firefighting

    system

    Build firefighting system,

    including one fire water tank

    and two fire pumps

    (1+1).

    a. Incorporate

    comments under

    related documents.

    b. Include

    comprehensive

    outline of tasks.

    KPC to clarify

    96) LINE1R-TD-003-A 98

    and

    102

    6.3 Form of Advance

    Payment Guarantee

    Advance payment No advance payment.

    Delete all reference to

    advance payment.

    SLECC: Agreed to revise.

    SLOP MANAGEMENT

    97) DD-LINE1R-RP-PR-003

    A

    13 4.1 Introduction The Section A is composed of

    75% product A and 25%

    product

    B

    Composition of slop to

    be based on 30% &

    70% for products A & B

    as basis for calculations

    Agreed. Review re-injection

    rates and slop tank

    capacities.

    98) DD-LINE1R-RP-PR-003A

    14 4.2.1 Calculation onAllowable MSP

    concentration in AGO

    1) Calculation formula

    When the product MSP isblended into AGO, the flash

    point of AGO is affected by

    10% of the boiling

    temperature of MSP. Based

    on 10% boiling temperature

    of MSP and the flash point of

    AGO,

    MSP has the finalboiling point elevated

    by 5oC from 205

    oC to

    210oC and not 10%, for

    AGO import at 66 and

    release to the

    marketers at 60 hence

    60C

    SLECC agreed to review.

    99) DD-LINE1R-BD-PR-001 38 7.4 CORROSION

    INHIBITOR INJECTIONPACKAGE

    The injection concentration

    for AGO is 9ppm and for MSPis 6ppm.

    a. Use 15ppm for

    AGO and 9ppm forMSP.

    b. Density of

    corrosion inhibitor

    is 0.944

    SLECC: To review.

    Hydraulic Protection

    100) DD-PLN-DW-WE-020-A Drawing KP784, KP785 Clarify the chainage. Clarify to remove confusion

    between KP reference

    points and KP chainage

    points

  • 7/26/2019 DED Review Matrix

    23/52

    S/No Document No. Page

    No.

    Item No Short Description KPC Remarks Position

    101) DD-PLN-SPC-WE-001-A 7 8.1 MASONRY INDEX: Compression intensity of the

    masonry (MPa)

    a. The type of mortar

    is not clear and it

    needs to be cross

    referenced to a

    local standard for

    ease of

    construction

    control. It is not

    understood what

    M7, 5 mortar is.

    b. Also U30, or U40

    are not understood

    in your design

    procedures, Please

    cross refer to local

    or internationalstandards.

    c. Clarify table.

    SLECC: Agreed to clarify.

    102) DD-PLN-SPC-PL-001 50 23.2 CONTRACTORS

    RESPONSIBILITIES

    Item 23.2.2: Procure and

    supply (if not provided by the

    Engineer) fill and dispose-off

    methanol and nitrogen, (if

    required)

    Delete (if not provided

    by the Engineer), (if

    required)

    SLECC: Agreed to revise

    103) DD-LINE1R-DW-CI-001-

    A

    Civil works general

    notes

    General notes a. Specifications

    notes for materials

    are not standard.For example Class

    35 for structural

    concrete and Class

    25 for Blinding

    concrete may not

    be economical.

    b. Control room

    buildings and

    equipment specs

    are not yet agreed

    a. SLECC: Agreed to adjust

    according to design.

    b. SLECC: Agreed toreview.

    c. KPC: SLECC has

    submitted standard

    notes. SLECC to submit

    the specifications.

    d. KPC to review the

    adequacy of the

    specifications and revert

  • 7/26/2019 DED Review Matrix

    24/52

    S/No Document No. Page

    No.

    Item No Short Description KPC Remarks Position

    upon since the

    consultant has not

    concluded the Fire

    risk assessment.

    More detailed

    designs are

    required for

    control rooms as a

    safety and disaster

    recovery facility

    with bigger safety

    margin.

    c. Specifications for

    civil works to be

    submitted.

    104) DD-LINE1R-MTO-CC-001A

    Material takeoff Protective materials take-off Justify the largepainting areas for

    underground piping in

    the stations.

    SLECC: To review thepainting areas

    105) LINE1R-TD-001 8 1.2.2 Mandatory

    requirements:

    Item F

    Undertaking to arrange for

    credible loan facility from a

    reputable financial institution

    up to a minimum of 70% of

    the project cost without

    anticipating a sovereign

    guarantee.

    KPC to advice further

    on this facility

    KPC to amend to suit the

    financing arrangements.

    106) LINE1R-TD-001 8 1.3.2 Local

    participation

    The desirable minimum

    shareholding for the local firm

    in the joint

    venture is 30%

    Revise to reflect Legal

    Notice 114.

    SLECC: Agreed to review

    107) LINE1R-TD-001 10 1.5 Tender Security-

    must be valid for 150

    days

    Item 1.5.1:

    The Tenderer shall furnish, as

    part of his Tender, a Tender

    security in amount of

    Kshs.2,000,000.00 or

    equivalent in USD.

    Revise to reflect Legal

    Notice 114.

    SLECC: Agreed to review to

    500,000/= USD or

    equivalent in Kenya shillings

  • 7/26/2019 DED Review Matrix

    25/52

    S/No Document No. Page

    No.

    Item No Short Description KPC Remarks Position

    108)

    109) LINE1R-TD-001 10 1.5 Tender Security-

    must be valid for 150

    days

    Item 1.5.1:

    Tender security shall be

    denominated in Kenya

    Shillings or in USD, and shall

    be in the form of a bank

    guarantee or a bank draft

    issued by a reputable bank

    located in Kenya or

    abroad.

    Delete abroad The

    entity issuing the

    guarantee must be

    registered and

    operating within Kenya.

    Agreed

    110) LINE1R-TD-001 11 1.6 Preparation of

    Technical Proposal

    Item 1.6.3

    While preparing the Technical

    Proposal..

    Amend the whole

    clause to suit a

    construction contract

    and not a service

    contract.

    SLECC to revise the entire

    clause

    111) LINE1R-TD-001 12 1.6 Preparation of

    Technical ProposalItem 1.6.4

    The Technical Proposal shall

    provide the following

    Amend the whole

    clause to suit aconstruction contract

    and not a service

    contract.

    SLECC to revise the entire

    clause

    112) LINE1R-TD-001 12 1.7 Preparation of

    Financial Proposal Item

    1.7.1

    In preparing the Financial

    Proposal..,

    Amend to reflect the

    BoQ prepared by the

    Consultants since this is

    not a service contract.

    SLECC to revise the entire

    clause

    113) LINE1R-TD-001 14 Item 1.10 Evaluation of Technical

    Proposal

    Amend the whole

    clause to suit a

    construction contractand not a service

    contract.

    SLECC to revise the entire

    clause

    114) LINE1R-TD-001 16 Item 1.11.3 The evaluation committee will

    determine.

    Amend to reflect the

    BoQ prepared by the

    Consultants since this is

    not a service contract.

    SLECC to revise the entire

    clause

    115) LINE1R-TD-001 16 Item 1.11.4 While comparing proposal

    prices between local and

    foreign firms participating in a

    Delete or amend to

    reflect Legal Notice 114

    and other regulatory

    SLECC to revise the entire

    clause

  • 7/26/2019 DED Review Matrix

    26/52

    S/No Document No. Page

    No.

    Item No Short Description KPC Remarks Position

    selection process framework

    116) LINE1R-TD-001 17 Item 1.11.5 The formulae for determining

    the Financial Score..

    Amend to reflect least

    cost based.

    SLECC to revise the entire

    clause

    117) LINE1R-TD-001 18 1.13 Negotiations and

    Contract Signing

    1.13.2 Negotiations will

    include a discussion of the

    Technical Proposal,

    Amend the whole

    clause to suit a

    construction contract

    and not a service

    contract.

    SLECC to revise the entire

    clause

    118) LINE1R-TD-001 18 1.13 Negotiations and

    Contract Signing

    1.13.4 Having selected the

    firm on the basis of, among

    other things..

    Amend the whole

    clause to suit a

    construction contract

    and not a service

    contract.

    SLECC to revise the entire

    clause

    119) LINE1R-TD-001 18 1.13 Negotiations and

    Contract Signing

    1.13.5 The negotiations will

    conclude

    Amend to reflect least

    cost based.

    SLECC to revise

    120) LINE1R-TD-001 18 1.13 Negotiations andContract Signing

    1.13.7 The selected firm isexpected to commence the

    Works on the date and at the

    location specified in Appendix

    A.

    Indicate whereAppendix A is provided.

    SLECC to revise to readwhen the Engineer issues

    notice to commence in

    accordance with the

    conditions of contract.

    121) LINE1R-TD-001 General Site Visit Provide a clause on

    mandatory site visit.

    Agreed to include a

    mandatory site visit

    122) LINE1R-TD-001 20 APPENDIX TO GENERAL

    INFORMATION (GI)

    a) General

    b) Item B

    c) Item M

    d) Item O

    a) Items to be cross

    referenced to the

    General

    Information.b) Revise method of

    selection to be

    least cost.

    c) Revise scoring

    criteria to reflect a

    construction

    contract and not a

    service contract.

    d) Delete formulae for

    a) Agreed to revise

    b) Agreed to revise

    c) Agreed to revise

    d) Agreed to revise

  • 7/26/2019 DED Review Matrix

    27/52

    S/No Document No. Page

    No.

    Item No Short Description KPC Remarks Position

    financial score.

    123) Cost Estimate 2 4.5: Customs duties

    and tax

    With Holding Tax is 20%.It's

    not applied to the cost of

    equipment and materials)

    Contractor to include in

    his rates the applicable

    taxes and duties.

    124) Fibre Optic Cable (FOC) a. FOC number of fibres

    cores

    b. Burying the FOC next

    to the pipe.

    a. Number of fibre

    cores to be

    changed from 8

    cores to 96 cores

    b. Burying of FOC to

    be below pipe and

    200 mm away from

    edge of pipe.

    Agreed SLECC to review as

    per KPC comment.

    125) Electrical - General Fault Levels Information supplied by M/S

    Kenya power

    a. Fault Levels

    supplied by M/S

    Kenya power not

    incorporated inelectrical design

    basis.

    b. Calculations have

    not been provided.

    SLECC to clarify the issue of

    the fault levels.

    126) Electrical - General Civil Works in Kenya

    Power Sub Station

    Consider provision of

    Civil works in Kenya

    Power side of

    substation like

    foundation for support

    structures andequipment/metering

    buildings in sub-

    stations.

    KPC to communicate a

    provisional sum for the KPLC

    sub-station civil to be

    included by SLECC in the

    BoQ.

    PR PROCESS

    127) Document Numbering

    DD-EM-TS-PR-001

    and DD-BD-PR-001

    1. PS1Changamwe

    Terminal and Pump

    Station;

    2. PS 5Mtito Andei Pigging

    &Pump Station;

    The Consultant to use

    the correct naming of

    the stations.

    Agreed. SLECC to revise to

    the correct names.

  • 7/26/2019 DED Review Matrix

    28/52

    S/No Document No. Page

    No.

    Item No Short Description KPC Remarks Position

    3. PS9Nairobi

    International Airport

    Bifurcation Station

    Embakasi Terminal, JKIA

    Storage Terminal and

    4. PS12Moi InternationalAirport Birfurcation

    Station

    128) DD-BD-PR-001 4 Section 2.1BASIC

    data

    1. PS9 KPC Terminal Station

    No. 9Embakasi

    2. PS10 KPC Terminal Station

    No. 10Nairobi

    The naming of PS 9 and

    PS 10 is different from

    item 2 above. Use

    proper naming

    throughout all the

    documents.

    Agreed. SLECC to revise to

    the correct names.

    129) DD-BD-PR-001 17 3.3 PRODUCT

    SOURCING

    Product Sourcing Revise paragraph 1 on

    product sourcing.

    Revise to indicate that most

    of the product is sourcedfrom (PS14) KOSF.

    130) DD-BD-PR-001 21 5.1 PIPELINE At present, KPC is installing

    the third pump to PS2, PS3,

    PS4, PS5, PS6, PS7 and PS8 to

    meet the increasing demand

    of product market, so all 8

    pump stations are running 2

    pumps frequently without

    standby pump now.

    Clarify the statement

    that all 8 stations are

    operating 2 pumps

    without standby.

    Note that PS1 has three

    pumps

    Revise the statement

    without standby

    131) DD-BD-PR-001 22and

    23

    5.2 PS1 and 5.3 PS2,PS4, PS6, PS8 The pump station controlvalve is designed with three

    Proportional integral

    derivative (PID) Controllers,

    which are measuring mainline

    pump suction pressure,

    station discharge pressure

    and pump discharge pressure.

    The statement isrepeated in page 22

    and page 23.

    Agreed to delete repeatedstatement.

    132) DD-BD-PR-001 27 5.8 PS12 PS12 is a depot for Mombasa

    airport, which downloads DPK

    a. Revise the

    paragraph as PS 1

    Agreed. SLECC to revise

  • 7/26/2019 DED Review Matrix

    29/52

    S/No Document No. Page

    No.

    Item No Short Description KPC Remarks Position

    from PS1, stores the oil in the

    tanks and transfers the oil to

    the airport after

    sedimentation.

    is not a storage

    facility but a pump

    station.

    b. Revise DPK to JET-

    A1

    133) DD-BD-PR-001 Surge Analysis ReportCavitations at High points

    What is the effect ofcavitations on the high

    point

    Agreed. SLECC to indicate

    134) DD-LINE1R-DW-PR-

    005A-007A

    Pumps from flow serve Pumps are not

    necessarily to be

    supplied by Flowserve.

    Agreed to replace

    costomer with contractor.

    Replace flowserve with

    vendor.

    135) DD-LINE1R-RP-PR-001-

    A

    8 Roughness of pipeline

    inner wall

    Consulting with pipeline

    manufacturer

    Clarify the issue on

    consulting with

    pipeline manufacturer

    on roughness ofpipeline

    Agreed to revise the

    statement

    136) DD-LINE1R-SPC-PR-

    002-A

    4 DPK-Jet Oil (Aviation

    oil) and Kerosene

    Clear description of

    DPK- Dual Purpose

    Kerosene

    Agreed to revise

    137) DD-LINE1R-SPC-PR-001 2 2.1 The requirement of

    pipeline control

    3 levels of control are

    described but manual control

    taken as highest priority.

    Clarify whether the

    design prefers manual

    control in some

    facilities as opposed to

    other controls that are

    described.

    Agreed to revise so that

    manual control taken as

    highest priority is deleted

    138) DD-LINE1R-DL-PL-001 Inlet/outlet drawings Drawing for PS 10 is

    missing

    Included in other drawing

    139) DD-LINE1R-SPC-PR-

    002-A

    14 Utility connection to

    pumps

    Provide utility connection to

    pumps to allow for flushing

    with service water

    This is not necessary Agreed to delete

    140) DOCUMENT NUMBER:

    DD-PS1-DAT-EL-011

    and DOCUMENT

    NUMBER: DD-LINEIR-

    1 of

    2

    Data Sheet For

    Mainline Pump Motor

    15 Cont. Output Rating:

    3200kW (To suit driven plant)

    The sizing of Prime

    Mover (Motor) at 3200

    kW is not explained

    SLECC: Agreed to submit

    motor sizing calculations.

  • 7/26/2019 DED Review Matrix

    30/52

    S/No Document No. Page

    No.

    Item No Short Description KPC Remarks Position

    SPC-EL-009

    PIPELINE

    141) DOCUMENT NUMBER:

    DD-PLN-SPC-PL-001

    4 3.2 THE EXISTING

    RIGHT-OF-WAY

    From KP 434.6-442.7km, KPC

    has a 30m wide ROW except

    for some sections which are

    occupied by industries. Inthese narrow areas there are

    some structures including

    fences, walls and gates which

    shall be restored after the

    construction of the pipeline.

    During removal of

    existing structures such

    as fences, walls and

    gates the consultantshould ensure that

    photographs of the

    existing walls, fences,

    lawns and gates are

    taken to avoid claims

    from owners that the

    restoration has not

    been done properly.

    Information to Consultants

    during implementation.

    Agreed

    142) DOCUMENT NUMBER:

    DD-PLN-SPC-PL-001

    6 3.3.2 National Park

    8.2 DEPTH

    From KP: 139.98-229.67km,

    pipeline needs to cross theTsavo National Park (both east

    and west park), and from KP:

    426.61-434.12km needs to

    cross the Nairobi National

    Park. The approval from

    relevant authorities shall be

    obtained before construction.

    Depth of pipeline trench

    within National Park shall be

    deeper for safety reasons asper chapter 8.2 and relevant

    drawings. And it is the

    responsibility of Contractors

    to follow the requirements of

    the relevant authorities.

    a. Clarify why the

    trenches within theNational Parks

    should be deeper

    than others.

    b. BoQ to be revised

    accordingly

    a. Agreed to maintain

    standard depth.b. Agreed to review

    Agreed to revise the

    BoQ items accordingly.

    143) DOCUMENT NUMBER:

    DD-PLN-SPC-PL-001

    21 7.4 CUTTING DOWN OF

    TREES

    All cut-down trees shall

    remain the sole property of

    the Engineer. Trimmed trunks

    shall either be stacked along

    Clarify. The Contractor

    should ensure that they

    obtain permit to cut

    trees from KFS and that

    Agreed to revise the

    statement.

  • 7/26/2019 DED Review Matrix

    31/52

    S/No Document No. Page

    No.

    Item No Short Description KPC Remarks Position

    the ROW or removed to a

    place specified by the

    Engineer.

    there should be

    consultation with the

    plot owners on the

    ownership of cut down

    trees.

    144) DOCUMENT NUMBER:DD-PLN-SPC-PL-001

    41 15 BACK-FILLING OFTHE TRENCH

    The trench shall not be back-filled until Engineer has

    approved the fit and cover of

    the pipe in place in the trench

    and has approved starting the

    back-filling operation.

    A tentative period inwhich the engineer

    should approve

    backfilling of trench

    should be given to

    avoid and/or minimize

    accident.

    Agreed to revise indicatingthe maximum duration that

    the trench shall remain

    open, measures to be taken

    to facilitate crossing of open

    trenches etc.

    DOCUMENT NUMBER:

    DD-PLN-SPC-PL-001

    12 4.4.3 Detailed

    distribution of steel

    pipe

    Detailed distribution of steel

    pipe in The National Park

    The thickness of steel

    pipe along the National

    Parks is provided as

    508 x 9.5.This thicknessis the same as those of

    river crossings, schools

    and tarmac roads.

    Please clarify.

    a. Clarify the

    enhanced

    thickness.

    b. BoQ to be revised

    accordingly

    a. Agreed to review

    according to design

    pressure profiles.

    b. Agreed to revise theBoQ items accordingly

    Line 1RCorrosionControl

    145) DD-LINE1R-SPC-CC-001 23 6.13.3 Painting Colour

    Schedule

    Fire Water Main

    Foam lines

    Colour: Red

    Colour: Cream

    Agreed

    146) DD-LINE1R-SPC-CC-002 2

    4

    a) Item 3 Definitions

    b) Item 5 General

    Requirements of

    Equipment Supplier

    c) 6.1, 6.2, 6.3, & 6.4:

    % Solids

    a) Client

    b) Electrical Resistance and

    Corrosion coupons

    c) LITTLE

    a) Clarify

    b) Include training for

    KPC Engineers in

    the scope of supply

    a. Agreed to remove

    ambiguity since in some

    instances the client is

    the contractor when

    procuring from a

    vendor.

  • 7/26/2019 DED Review Matrix

    32/52

    S/No Document No. Page

    No.

    Item No Short Description KPC Remarks Position

    d) 6.2 Tags

    e) 9.1 CorrosionCoupons (CC)

    f) 9.2 ElectricalResistance

    Probe(ER)

    d) Tag numbers for ER and

    CC

    e) TechnicalRequirement

    f) TechnicalRequirement

    c) Give a % numerical

    value

    d) Each ER and CC

    e) To be supplied

    complete withinserting and

    retrieval tools

    f) To be supplied

    complete with

    inserting and

    retrieval tools, data

    downloading

    equipment and

    manipulation

    software

    b. Agreed

    c. SLECC to provide a

    numerical figure.

    d. Agreed to provide

    separate tags.

    e. Agreed to make it clearthat the contractor shall

    provide the inserting

    and retrieval tools as a

    complete package.

    147) DD-LINE1-SPCH-CC-001 Item 5 Special Tools for Operation

    and Maintenance

    One set for each type

    (CC & ER)

    Agreed

    PLN

    148) DD-PLN-SPC-CC-001 2 Item 5: Survey Chainage Give GPS coordinates

    corresponding to the

    chainage

    Agreed. Data to be revised

    to combine the GPS co-

    ordinates and chainage

    149) 5 & 7 Item 5.2, 5.3, 5.4 & 5.5

    and 6.4

    Survey Within the consultants

    scope and findings

    should be tabulated

    and reported to theEngineer in the DED

    Agreed.

    150) 9 Item 9.2 & 9.3: CP

    Equipment and Ground

    bed

    TR and ICCP Anodes a. CP Station: Provide

    detailed design for

    ground bed

    locating, sizing and

    TR capacity for

    Engineers

    approval.

    b. Thereafter, locate

    Agreed.

  • 7/26/2019 DED Review Matrix

    33/52

    S/No Document No. Page

    No.

    Item No Short Description KPC Remarks Position

    ground beds and

    advice on possible

    land acquisition.

    c. Key CP material

    and quantities in

    BOQ should bebased on the

    detailed design.

    151) Item 9.5.1 SLECC recommendation Use XLPE/PVC cables Agreed

    152) 10 Item 9.6.3, 9.6.4 &

    9.6.5

    Cable to Pipe Connections Select one method Agreed. Use the cost

    effective method.

    153) 11 Item 9.7.4 Cased Crossings Include test facility for

    the casings

    Agreed

    154) 13 Item 9.10.4 & 10.5 solid-state de-coupler As in item 9.8.3 Agreed

    17 Appendix B: Current density for 3LPE of

    10A/m2

    a. Justify the

    assumption.Current density for

    composite installed

    pipeline at end of

    design life: as per

    BS7361 Clauses

    4.3.1.2 pages 34

    and 35 or any other

    standard used in

    the CP.

    b. Provide design lifeof the pipeline

    based on quality of

    steel, pipeline

    thickness, coating,

    internal corrosion

    inhibitor, water

    displacement, CP,

    residual corrosion

    allowance etc.

    a. Use BS 7361

    b. Agreed SLECC to provideeconomic design life of

    the pipeline and

    operating period to

    guarantee the same.

  • 7/26/2019 DED Review Matrix

    34/52

    S/No Document No. Page

    No.

    Item No Short Description KPC Remarks Position

    These are missing

    in all the

    documents.

    155) DD-PLN-SPC-CC-002 1 Item 1.1.2, 1.1.4, 6.0 &

    6.3: normal and

    reinforced 3LPE

    Type of 3LPE coating for soft

    and rocky areas

    As agreed earlier in

    PED: normal & soft

    padding

    Agreed SLECC to review.

    156) 16 Item 7.5.1 Cross-head or annular

    extrusion technique

    As agreed in PED:

    extrusion technique

    Use one type of 3LPE.

    157) DD-PLN-SPC-CC-003 Item 1.1.5 & 1.9.1 3LPE heat shrinkable Specify DFT for

    copolymer adhesiveor

    be explicit on DD-PLN-

    SPC-CC-002

    Agreed

    158) DD-PLN-SPC-CC-004 Document Title PATING Correct to painting Agreed

    159) 17 Appendix A: Item 1 Coating Schedule Explain the alternative Wrong statement. To be

    deleted.

    160) DD-PLN-SPC-CC-004 Scope CP commissioning Procedure Document notconsidered adequate in

    addressing pre-

    commissioning data.

    No reference to:

    a. Effectiveness of

    temporary CP

    before ICCP

    connection;

    isolation of SA

    b. Effectiveness ofelectrical isolation

    c. Holiday test

    records

    d. Soil resistivity

    records

    e. 3rd party

    crossings/parallelis

    m effects as

    measured

    Agreed: SLECC to improvethe document.

  • 7/26/2019 DED Review Matrix

    35/52

    S/No Document No. Page

    No.

    Item No Short Description KPC Remarks Position

    f. Natural/native

    potential

    measurements

    g. Etc.

    161) Drawings: DD-PLN-DL-

    CC-001 to 007

    Negative Junction Box,

    numbers for each station,Anode Negative Junction Box,

    jumper cable (also in DD-PLN-

    SPC-CC-001 Item 9.6), etc.

    Purpose and

    installation detailsambiguous/not clear

    for the application.

    Distinguish Junction

    boxes and test stations

    for each purpose.

    Generate detailed drgs

    for current drain points

    to the pipeline, etc as

    per the detailed design.

    Agreed: SLECC to improve

    the installation details.

    162) DD-PLN-MTO-CC-001.A CP material take off Should be based ondetailed design for CP

    station capacity and

    ground bed sizing

    Agreed: To revise thequantities after concluding

    the detailed design.

    163) DD-PLN-MTO-CC-003.A Heat shrinkable No mention of epoxy

    and copolymer

    quantities

    Agreed: SLECC to review the

    quantities of epoxy

    164) DD-PLN-MTO-CC-004.A Painting area 900m2 Segregate for each

    paint scheme colour

    Agreed

    165) DD-PLN-SPC-PL-001 1 &4 Item 1 &3.2 9.5mm thick pipe & Deeptrench for special crossings

    and urban districts

    Clarify underlyingreason(s) for either and

    both

    Agreed SLECC to reviewaccordingly.

    166) Whole doc HDD and Auger bore:

    recommended

    Simply specify Agreed SLECC to specify and

    not recommend.

    167) 35 Item 10.4 When pipeline and FOC cross

    road or river by HDD, the

    optimized construction

    method shall be

    specify Agreed SLECC to specify.

  • 7/26/2019 DED Review Matrix

    36/52

    S/No Document No. Page

    No.

    Item No Short Description KPC Remarks Position

    168) 5 Item 3.2-1 DD-PLN-SPC-PL-001 Show in the drg stated Agreed SLECC to correct the

    drawing No.

    169) Item 4.4.2 Corrosion Allowance (CA):

    The calculated thickness for

    mainline is 7.8mm, and the

    design wall thickness isrounded up to

    8.7mm. It means there is

    0.9mm of margin.

    Quotes from ASME B31.4,

    PEABODY's CONTROL OF

    PIPELINE CORROSION,

    NORSOK STANDARD DESIGN

    PRINCIPLES

    (M-DP-001, MATERIALS

    SELECTION)

    Contradiction and

    dismissal:

    no mention of design

    life of the pipeline,no clear CI design

    dosing scheme and

    costs based on water

    content data in

    product,

    no regular pigging

    design and interval for

    the water

    displacement,

    No CA calculation andadditional steel cost,

    no clear final holiday

    level estimated for the

    installed pipeline and

    the CP design

    correlation at end of

    life of the pipeline.

    The total pipeline

    corrosion control

    scheme not holistic for

    common goal.

    No reason for the

    rounding off of the wall

    thickness from

    calculated hoop stress,

    T. The design basis, DD-

    LINE1R-BD-PR-001-A,

    item 7.3 not consistent

    with the quotes.

    Consultant to clarify

    Agreed SLECC to review to

    reflect KPC comments.

  • 7/26/2019 DED Review Matrix

    37/52

    S/No Document No. Page

    No.

    Item No Short Description KPC Remarks Position

    the design life

    (economic design life

    for the installed 20

    pipeline) as relates to

    the proposed CC

    methods and ownopinion for no CA for

    the known operating

    parameters and

    environment of the 20

    pipeline.

    170) 44 Item 16 Item 9.6 DD-PLN-SPC-CC-001:

    Test stations, drain points etc

    Cable terminations to

    the line pipe not clearly

    stated and at what

    stage in the

    construction; anyconstruction

    procedure?

    Agreed SLECC to cross

    reference documents on

    corrosion control and

    pipeline construction.

    171) Isolating Joint as in (DD-

    LINE1R-SPC-MA-013, DD-

    LINE1R-DAT-MA-013)

    Testing & Installation

    during pipeline

    construction not

    stated.

    Agreed.

    172) Installation of heat shrinkable Installation & testing

    not stated

    Agreed

    173) Open cut & Auger bore: casing

    electrical isolation and end

    sealing from carrier pipe

    Installation and testing

    not stated.

    Agreed

    174) Valve chambers: electrical

    isolation and sealing

    Installation and testing

    not stated

    Agreed

    175) DD-PLN-DW-PL-006 Current interaction from ICCP

    Systems

    No mention of possible

    current interaction and

    proposed mitigation

    measures

    Agreed SLECC to review

    176) DD-PLN-DW-PL-008 Backfilling material Revise proposals to suit

    normal 3LPE

    Agreed type 2

  • 7/26/2019 DED Review Matrix

    38/52

    S/No Document No. Page

    No.

    Item No Short Description KPC Remarks Position

    thickness and special

    cases

    177) DD-PLN-CL-CC-001.A 1 Item 4 Design data: 30a, 3LPE, soil

    resistivity 30-m

    Design life for CP or for

    the installed pipeline?

    Clarify

    Agreed SLECC to give

    analysis of different options

    on economic life of pipeline

    and hence design life for CP.178) DD-LINE1R-SPC-MA-

    003

    13 Item 9 All pipe bends shall be coated

    as shown in the project

    documents

    What documents?

    Please show.

    Agreed SLECC to clarify.

    179) DD-LINE1R-BD-EL-001 14 Item 9.1 Larger motor 1. Clarify if meant

    Main Pump

    Motor.

    2. No description of

    VFD and an

    outline of how it

    works in thedocument.

    3. How the control

    philosophy

    interlinks with I &

    C.

    4. No specification

    and data sheet

    docs for the

    proposed VFD

    1. Agreed main pump

    motor

    2. Agreed to review on

    VFD

    180) DD-LINE1R-BD-IN-001A 9 Overview of control concept Page 9 of 20. SLECC has

    proposed the following

    control modes, i.e.

    Remote (SCADA), Local

    remote (HMI), Local

    remote (touch screen),

    Local equipment

    control. The following

    mode should be added:

    Local control from PCS

    Agreed

  • 7/26/2019 DED Review Matrix

    39/52

    S/No Document No. Page

    No.

    Item No Short Description KPC Remarks Position

    Panel by use of Push

    buttons (e.g. Pump

    start, pump load, etc).

    181) DD-LINE1R-BD-IN-001A 11 Overview of control concept Page 11 of 20. Add

    item 5.1.4. Local Panel

    control. This level ofcontrol provides direct

    control of pumps,

    valves, etc from the

    PCS panel by use of

    push buttons.

    a. KPC: Mainly mainline

    pump valves plus

    strainer valves. PumpSTART/STOP sequence

    b. SLECC: Agreed to review

    182) DD-LINE1R-BD-IN-001A 13 Overview of control concept Page 13 of 20. Item

    6.20. An ESD shall be

    initiated by. Add

    Flame detection in

    pump shed.

    Agreed

    183) DD-LINE1R-SPC-IN-002 Specification for PCS and ESD

    System

    Add to the

    specifications the

    statement The Pump

    monitoring system

    shall have internal

    safety barriers.

    Agreed to add in the PMS

    documents

    184) DD-LINE1R-SPC-IN-002 Item 8.2 Specification for PCS and ESD

    System

    On item 8.2, add the

    statement An ESD

    shall be initiated by

    flame detection in the

    mainline pump shed.

    Agreed.

    185) DD-LINE1R-SPC-IN-002 Specification for PCS and ESD

    System

    Add the specification:

    The Preferred PLC

    Control system- 1.

    Schneider 2. Allen

    Bradley.

    Agreed

    186) DD-LINE1R-SPC-IN-002 25 Specification for PCS and ESD

    System

    On documentation,

    page 25 of 27, there is

    a statement An

    Agreed to correct

  • 7/26/2019 DED Review Matrix

    40/52

    S/No Document No. Page

    No.

    Item No Short Description KPC Remarks Position

    operation and

    maintenance manual

    giving all information

    required to operate

    and maintain the

    interface detector shallbe submitted by the

    supplier. Interface

    detector should be

    changed to Process

    control system.

    187) DD-LINE1R-SPC-IN-003 Specification for Motor

    operated Valves

    Add : Preferred makes-

    1. Rotork.

    Agreed

    188) DD-LINE1R-SPC-IN-004 Specification for ESD valve

    actuator

    Add preferred makes:-

    1. Rotork.

    Agreed

    189) DD-LINE1R-SPC-IN-006 Specification for Fieldinstrumentation

    All references toexplosion proof class

    Exd should be EExd.

    Agreed

    190) DD-LINE1R-SPC-IN-006 Specification for Field

    instrumentation

    Preferred makes:

    a. Rosemount

    b. Siemens

    c. ABB

    d. Honeywell

    Agreed

    191) DD-LINE1R-SPC-IN-007 Specification for Fire alarm

    system

    Fire alarm panel: To

    comply with standards

    EN-54, and NFPA 72.

    Agreed

    192) DD-LINE1R-SPC-IN-009 Specification for

    Instrumentation installation

    a. Item 6.2 lists free

    issue items. Delete

    as there shall not

    be free issue items

    b. - Item 6.3: Please

    delete the word

    Morendat from

    The scope of work

    for the

    a. Agreed

    b. Agreed

  • 7/26/2019 DED Review Matrix

    41/52

    S/No Document No. Page

    No.

    Item No Short Description KPC Remarks Position

    instrumentation

    installation of

    Morendat Pump

    station.

    193) DD-LINE1R-SPC-IN-

    0011

    Specification for Liquid

    ultrasonic flow meter

    This item should

    undergo a factoryacceptance test

    witnessed by owners

    Engineers.

    Agreed

    194) DD-LINE1R-SPC-IN-

    0012

    Specification for Flow

    computer

    This item should

    undergo a factory

    acceptance test

    witnessed by owners

    Engineers

    Agreed

    195) DD-MLV-DW-PR-004A Pig signaller Remove: TO

    MORENDAT P.S fromdrawing labeled: PLAN

    ON INSPECTION

    CHAMBER.

    Agreed

    196) DD-MLV-DW-PR-015-A,

    013A, 012A

    MLV-108A, 107A, MLV

    106A ETC

    BLOCK VALVE Put chainage: KM in

    drawing.

    Agreed

    197) DD-MLV-DW-PR-015-A,

    013A, 012A

    Block Valve KM 153.5 Delete this chamber

    since isolation will be

    from KM 172 (PS4) and

    137.37.

    Block valve KM153 will

    not be accessible at

    night.

    SLECC to review the location

    and explain the necessity of

    the block valve at this

    location.

    SLECC to adjust accordingly

    198) DD-PS1-MTO-PR-002-A Item 34 Clarify comment:

    including backstop

    Clarify and correct

    accordingly

    199) DD-PS1-SCH-PR-001-A Item 14 Re-Injection Pump Demonstrate how the

    capacity and head of

    re-injection pump has

    been arrived at

    Agreed. Pump is adequate

  • 7/26/2019 DED Review Matrix

    42/52

    S/No Document No. Page

    No.

    Item No Short Description KPC Remarks Position

    (Q=10M^3/HR,

    h=600m).

    LINE1R-TD-001 TENDER DOCUMENTS

    FORPROCUREMENT,

    CONSTRUCTION,

    TESTINGANDCOMMISSIONING

    200) 30 Form of tender Performance guarantee Delete sourcing from

    an insurance company

    Agreed

    201) 30 The tender, together with

    your written acceptance

    thereof, shall constitute a

    binding contract between us.

    This is in contravention

    to the procurement

    law as no contract

    should be in place until

    agreement is signed.

    Agreed SLECC to review

    accordingly.

    202) 31 Appendix to form of

    tender

    Security is 10% of the lump

    sum price.

    Replace with contract

    price as this is not alump sum contract.

    Agreed.

    203) 31 Time for completion is 18

    months.

    Propose that the

    bidders indicate the

    construction period.

    Agreed SLECC to leave the

    period blank for bidders to

    fill.

    204) Conditions of contract

    Part II

    205) Item 1.1a(v) Engineers representative is

    SLECC

    Replace SLECC with

    SLECC/Kurrent JV

    Agreed

    206) 1.1b(i), (iv) BOQ replaced with schedule

    of prices

    Retain Bill of Quantities

    instead of schedule ofprices in the entire

    document.

    Agreed SLECC to use BOQ

    throughout the tenderdocument.

    207) 4.1 Total subcontract ceiling at

    30%

    Replace 30% with 40%

    to comply with the

    procurement law.

    Agreed SLECC to replace

    30% with 40% to comply

    with procurement law.

    208) 5.2 Priority of contract document Order to be similar to

    the one in the

    agreement.

    Nevertheless the

    Agreed SLECC to review

    Priority order in clause 5.2

    should be in the same order

    as in the agreement.

  • 7/26/2019 DED Review Matrix

    43/52

    contractors general

    obligations to be after

    conditions of contract.

    209) 6.2 provided to or deleted Reinstate the deletion Agreed

    210) 6.3 Delete the words "drawings

    or" in lines 3 and 4

    Reinstate the deletion 1. KPC position is for SLECC

    to retain words

    "drawings or" in lines 3

    and 4 of clause 6.3. Thisis because the contract

    is not an EPC contract as

    SLECC are the designers.

    2. SLECC position is to

    delete the words

    "drawings or"

    3. Agreed SLECC to retain

    the words.

    211) 6.4 Delete the words "drawing or"

    in line 2

    Reinstate the deletion Agreed SLECC to retain the

    words.

    212) 6.5 Delete the words "drawings

    or" in line 1

    Reinstate the deletion Agreed SLECC to retain the

    words.

    213) 7.1 Delete the words "drawing

    and" in line 2

    Reinstate the deletion Agreed SLECC to retain the

    words.

    214) 7.2a All the permanent and

    temporary

    works shall be designed and

    constructed by the Contractor

    Delete the addition as

    the design and

    construction drawings

    are prepared by the

    consultants.

    Agreed SLECC to review as

    they are the designer.

    215) 8.1 Permits and authorization Add in the list all

    levies imposed by

    national and county

    laws

    Agreed SLECC to add in the

    list all levies imposed by

    national and county laws

    216) 11.1 Replacement that accuracy of

    data provided by the Client is

    not guaranteed

    Retain the original

    clause in FIDIC

    Agreed

    217) 12.1 Replace the words "Bills of Retain Bill of Quantities Agreed

  • 7/26/2019 DED Review Matrix

    44/52

    Quantities" with the words

    "Schedule of Prices"

    instead of schedule of

    prices

    218) 15.2 Engineer registered by the

    Engineer's Registration Board

    (ERB) of Kenya

    Replace with Engineers

    Board of Kenya (EBK)

    Agreed SLECC to replace

    219) 19.1(xv) part time HSE officer Replace with full time Agreed

    220) 19.1(v) Rock blasting near settlement

    areas shall be properlycoordinated with the relevant

    officers

    Rock blasting not

    permitted due to safetyconsiderations

    Agreed

    221) 55.1 BOQ replaced with schedule

    of prices

    Retain BOQ instead of

    schedule of prices

    Agreed

    222) 55.2 BOQ replaced with schedule

    of prices

    Retain BOQ instead of

    schedule of prices

    Agreed

    223) 58.4 BOQ replaced with schedule

    of prices

    Retain BOQ instead of

    schedule of prices

    Agreed

    224) 60.8 .he shall be deemed to have

    agreed that he accepts thetotal Contract Price as set

    out.

    Replace agreed that

    he accepts the totalcontract price as set

    out in with accepted

    Agreed

    225) 60.11(a) This being a firm fixed price

    contract, the Contractor is

    deemed to have.....

    Delete the sentence as

    this is a re-measurable

    contract.

    Agreed

    226) 60.11(b) Schedule of Prices Replace with bill of

    quantities

    Agreed

    227) 70.1 fixed lump sum Replace with fixed

    rates contract

    Agreed

    228) 80(1) Contractor to provide mealsfor meetings Delete Agreed

    229) 80(2) Contractor to provide office

    for engineers representative

    Delete as this is

    repeated in

    contractors general

    obligations

    Agreed

    230) 80(3) Contractor to provide 2 SUV

    vehicles at each site for the

    consultants

    Delete as this

    contradicts the

    consultancy contract.

    Agreed

    231) 80(4) Contractor to provide Delete as this Agreed

  • 7/26/2019 DED Review Matrix

    45/52

    accommodation and meals for

    consultants

    contradicts the

    consultancy contract.

    232) 80(5) Contractor shall allow a sum

    of Kshs 30,000.00 every

    month for the Engineer's

    Representative miscellaneous

    account

    Delete as this

    contradicts the

    consultancy contract.

    Agreed

    233) 80(6) For all the documents to besubmitted by the Contractor

    to the Employer or the

    Engineer, the same shall be

    submitted to the Engineers

    Representative for review and

    check first so as to facilitate

    the review and approval of the

    Engineer.

    Delete Agreed to retain thestatement.

    234) 81 credible loan facility from a

    reputable financial institutionup to a minimum of 70% of

    the project

    Delete Agreed SLECC to delete as it

    will be dealt with at thecover letter.

    Contractors general

    obligations

    235) Clause 2 Programme to be submitted

    within 14days

    Harmonize with Clause

    14.1 of the conditions

    of contract with

    28days.

    Agreed

    236) 6.1 and 6.2 Involvement of Engineer in

    vetting the procurement

    process of the contractor

    This is a contractors

    internal task and the

    engineer should

    minimize input.

    Agreed

    237) 7 O&M manuals to be

    submitted where required.

    This should not be

    optional and further

    indicate the period

    when these should be

    submitted.

    Agreed all O&M to be

    submitted before take over.

    238) 15 accommodation and three

    meals for the personnel of

    Delete Agreed

  • 7/26/2019 DED Review Matrix

    46/52

    Engineers

    Representative

    239) 18 Contractor shall provide one

    quickset level, tripod, a multi-

    meter and torch, 5 meter

    staff, one 30 meter steel tape,

    one 30 meter linen tape, 6

    ranging rods for the exclusiveuse of the Engineer.

    Confirm that these are

    adequate for the

    survey work. These to

    revert to contractor at

    completion of the

    project.

    Agreed

    240) 23 The Contractor shall provide

    at each site two four-wheel

    driven SUVs with dedicated

    drivers for the transportation

    of the personnel of the

    Engineers Representative

    Delete as it contradicts

    the contract.

    Agreed

    241) 31 The levels of benchmarks shall

    be based on local harbor

    datum.

    Clarify meaning Agreed this means sea level.

    242) 33 Signboard to be display, at the

    junction of the access road

    leading to the Site of the

    Works

    Specify the number

    and the locations

    Agreed SLECC to review and

    include in the entrance to

    existing pump stations and

    depots/terminals.

    243) 34 Office for Engineer and

    Engineers Representative

    1. Specify

    location for the

    offices

    including the

    main site

    management

    office.

    2. Specify rating

    for the 4

    desktops.

    Laptop to be i5

    processor and

    not intel

    Pentium.

    1. Agreed

  • 7/26/2019 DED Review Matrix

    47/52

    3. Conference

    rooms to

    accommodate

    20 people

    Delete para on

    consultants

    accommodation.244) 35 Meals for meetings and Kshs

    30,000 petty cash for

    consultants

    Delete all. Agreed

    245) 36 4 isuzu troopers for engineer

    and vehicles for consultants

    Provide 6 vehicles for

    the engineer of

    superior specifications

    and delete transport

    for consultants.

    Agreed

    246) Form of Agreement

    247) Priority of contract documents Recommend1. Contract

    agreement

    2. For of tender

    3. Appendix to

    form of tender

    4. Conditions of

    contract part II

    5. Conditions of

    contract Part I

    6. Negotiation

    minutes

    7. Specifications

    8. Drawings

    9. BOQ

    10.Schedule of

    rates and

    dayworks

    11.Schedules and

    annexes

    Agreed SLEC to review asper KPC comment.

  • 7/26/2019 DED Review Matrix

    48/52

    248) Signing by parties Allow for a provision

    for contractor to sign.

    Agreed

    249) Tender Security Forfeiting the Tender security Wording to be

    consistent with Clause

    1.5.7 of the General

    information and avoid

    reference to clauses for

    it to stand alone.

    Agreed

    250) Reference to uniform rules for

    demand guarantees

    Delete Agreed

    251) Performance

    guarantee

    Employer to give reasons for

    breach

    Delete as Clause 10.3

    has been expunged

    Agreed

    252) Performance certificate Replace with defects

    liability certificate

    Agreed

    253) Reference to uniform rules for

    demand guarantees

    Delete Agreed

    254) Advance Guarantee Guarantee form Delete as this is not

    applicable. Insert aclause in the General

    Information section to

    emphasize on the same

    Agreed

    LINE1R-TD-002 Schedule of prices and rates

    255) Notes Item (v) Accordance with the

    Directions for Measurement

    and Pricing included in the

    Standard and Special

    Specifications.

    Refer to clause 57.1 of

    the conditions of

    contract on method of

    measurement

    Agreed

    256) PG/M2 Allow for the management of

    specialist

    subcontractors

    Delete as they are all

    domestic

    Agreed

    257) PG/M5 Establish, furnish and maintain

    office accommodation for the

    exclusive use of the Engineer

    for the duration of the

    Contract

    Specify that there will

    be 1 main office and 2

    satellite offices

    SLECC to review

    258) PG/M6 4 double cabs and 1 station

    wagon vehicles

    Increase to 8 for the

    exclusive use by the

    Agreed SLECC to review the

    Number and dont specify

  • 7/26/2019 DED Review Matrix

    49/52

    Engineer double cabs.

    259) PG/M7 Allow for unpacking,

    inspecting, loading and

    transporting to site all Free

    Issue equipment from the

    Employers stores

    Delete as there will be

    no free issue items

    Agreed

    260) Add PG/M7 Demobilization Add an item for

    demobilization

    Agreed

    261) Add PG/M8 Locating and protection of

    existing services

    Add item for locating

    and protection of

    existing services

    Agreed

    262) Pipeline mechanical

    bills1.3

    263) C/P/MP7 Shop bends in pcs/m Use pcs as unit of

    measurement

    Agreed but include degree

    ranges in the number.

    264) C/P/MP8 Shop bends in pcs/m Use pcs as unit of

    measurement

    Agreed but include degree

    ranges in the number.

    265) C/P/MP9 Ball gear Replace with gearoperated ball valve

    Agreed

    266) C/P/MP11.1 to 11.4 Cro