decommissioning planning for nuclear units at the ......2016-02-18 predec 2016, february 16-18,...

13
2016-02-18 PREDEC 2016, February 16-18, Lyon, France 1 Decommissioning Planning for Nuclear Units at the Oskarshamn Site Niklas Bergh Westinghouse Electric Sweden Thom Rannemalm, Jörgen Eriksson OKG

Upload: others

Post on 26-Dec-2019

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Decommissioning Planning for Nuclear Units at the ......2016-02-18 PREDEC 2016, February 16-18, Lyon, France 1 Decommissioning Planning for Nuclear Units at the Oskarshamn Site Niklas

2016-02-18 PREDEC 2016, February 16-18, Lyon, France 1

Decommissioning Planning for

Nuclear Units at the

Oskarshamn Site

Niklas Bergh Westinghouse Electric Sweden

Thom Rannemalm, Jörgen Eriksson OKG

Page 2: Decommissioning Planning for Nuclear Units at the ......2016-02-18 PREDEC 2016, February 16-18, Lyon, France 1 Decommissioning Planning for Nuclear Units at the Oskarshamn Site Niklas

• Introduction

• Decommissioning Process

• Present Activities at OKG

• Strategic Options for OKG

• Discussion

• Conclusions

• Near Term Future Works

2016-02-18 PREDEC 2016, February 16-18, Lyon, France 2

Agenda

Page 3: Decommissioning Planning for Nuclear Units at the ......2016-02-18 PREDEC 2016, February 16-18, Lyon, France 1 Decommissioning Planning for Nuclear Units at the Oskarshamn Site Niklas

• Permanent shutdown

– O1: 2032 2017

– O2: 2034 2016

– O3: 2045

2016-02-18 PREDEC 2016, February 16-18, Lyon, France 3

Introduction

BWR Unit Commissioned

Thermal

power [MW]

Electrical

power [MW]

Oskarshamn 1 1972 1 375 491

Oskarshamn 2 1974 1 800 620

Oskarshamn 3 1985 3 900 1 450

Page 4: Decommissioning Planning for Nuclear Units at the ......2016-02-18 PREDEC 2016, February 16-18, Lyon, France 1 Decommissioning Planning for Nuclear Units at the Oskarshamn Site Niklas

• Regulatory: – EIA for Defueling op.

– SAR for Dismantling

– EIA for Dismantling

– EURATOM Article 37

– Waste Management Plan

• Economical – SAR for Shutdown op.

2016-02-18 PREDEC 2016, February 16-18, Lyon, France 4

Decommissioning Process

Shutdown op. Decommissioning &

Dismantling Defueling op.

End of

commercial op.

- Environmental court

approval of EIA - SAR

- Environmental court

approval of EIA - SAR

POWER

OPERATION

DEFUELING SHUTDOWN

OPERATION

DISMANTLING

OPERATION

SITE RESTORATION

Fuel

removal Maintenance/

supervision

Equipment

dismantling and

waste

processing

Building

demolition

Planning

Ground

restor-

ation

Final shutdown Plant cleared

Partial dismantling

Page 5: Decommissioning Planning for Nuclear Units at the ......2016-02-18 PREDEC 2016, February 16-18, Lyon, France 1 Decommissioning Planning for Nuclear Units at the Oskarshamn Site Niklas

• Decommissioning Preparation Project (DPP) with subprojects – Strategy and Planning

– Licensing – Nuclear Regulator

– Licensing – Environmental Court

– HR

– Decommissioning preparation activities

• Development of decommissioning roadmap, licensing documents and identification of prioritized activities

• Will transit into line organisation as a new department in 3-5 months

2016-02-18 PREDEC 2016, February 16-18, Lyon, France 5

Present Activities at OKG

Page 6: Decommissioning Planning for Nuclear Units at the ......2016-02-18 PREDEC 2016, February 16-18, Lyon, France 1 Decommissioning Planning for Nuclear Units at the Oskarshamn Site Niklas

• The organizational model

– Using utility personnel

• Degree of self performance

– Procurement strategy

– Maintaining competence

• Timing between the decommissioning of unit

1 and 2

– When to go into decommissioning

– Length of defueling op., shutdown op.

2016-02-18 PREDEC 2016, February 16-18, Lyon, France 6

Strategic Options for OKG

Ongoing

Completed

Page 7: Decommissioning Planning for Nuclear Units at the ......2016-02-18 PREDEC 2016, February 16-18, Lyon, France 1 Decommissioning Planning for Nuclear Units at the Oskarshamn Site Niklas

• The waste management strategy – Waste streams

– Waste treatment options

– Final/Interim storage options

2016-02-18 PREDEC 2016, February 16-18, Lyon, France 7

Strategic Options for OKG

I Initial

Planning

II Defueling

III Inventory & Charac-terization

IV Deconta-mination

V Dismant-

ling

VI Waste

Manage-ment

VII Demo-lition

VIII Site

Clearan-ce

Define

End-State

requirements

Optimize

waste

handling,

clearance

Plan

dismantling

Apply

deconta-

mination

measures

Characterize

according to

WAC

Develop

Strategies

and Plans

Ongoing

Page 8: Decommissioning Planning for Nuclear Units at the ......2016-02-18 PREDEC 2016, February 16-18, Lyon, France 1 Decommissioning Planning for Nuclear Units at the Oskarshamn Site Niklas

• Separation of systems and buildings

between O1/O2 and O3

– Systems necessary for continued

power production at O3

– Shared systems needed for both

decommissioning and operation

– Definition of decommissioning

area

– Physical separation of systems

and buildings with a new

physical protection

2016-02-18 PREDEC 2016, February 16-18, Lyon, France 8

Strategic Options for OKG

Not started

Page 9: Decommissioning Planning for Nuclear Units at the ......2016-02-18 PREDEC 2016, February 16-18, Lyon, France 1 Decommissioning Planning for Nuclear Units at the Oskarshamn Site Niklas

• Decommissioning systems modification

– Ventilation

– Power supply

– Waste treatment systems

– Free release building/routes

– Handling systems

– Fire protection

– Transport routes

• Stakeholder engagement

– Stakeholder communications plan

2016-02-18 PREDEC 2016, February 16-18, Lyon, France 9

Strategic Options for OKG

Not started

Ongoing

Page 10: Decommissioning Planning for Nuclear Units at the ......2016-02-18 PREDEC 2016, February 16-18, Lyon, France 1 Decommissioning Planning for Nuclear Units at the Oskarshamn Site Niklas

• Prioritized activities, order of planning

activities

• Regulatory review time and approval

• Partial dismantling

• Dependency on final repository

• Physical separation of

site

• Maintaining personnel,

morale and critical skills

2016-02-18 PREDEC 2016, February 16-18, Lyon, France 10

Discussion

Page 11: Decommissioning Planning for Nuclear Units at the ......2016-02-18 PREDEC 2016, February 16-18, Lyon, France 1 Decommissioning Planning for Nuclear Units at the Oskarshamn Site Niklas

• O1 and O2 as one decommissioning project

• Defueling O1 finished 2018

• Defueling O2 finished mid 2017

• Nuclear dismantling start 2019

• Plant cleared 2025

• Target end date 2027 brown field

• Partial dismantling (flexibility) crucial for short schedule

• Prioritized activities: – Personnel change of mindset and critical skills

– Licensing documentation

– Procurement strategy

– Waste management strategy

• Frequent and open communication with regulators and stakeholders critical to success

2016-02-18 PREDEC 2016, February 16-18, Lyon, France 11

Conclusions

Page 12: Decommissioning Planning for Nuclear Units at the ......2016-02-18 PREDEC 2016, February 16-18, Lyon, France 1 Decommissioning Planning for Nuclear Units at the Oskarshamn Site Niklas

• Finalizing prioritized activities

• Decommissioning planning

• Dismantling sequences

• Radiological characterization

• Separation activities

• Physical protection

• Plant modifications for

decommissioning

2016-02-18 PREDEC 2016, February 16-18, Lyon, France 12

Near Term Future Works

Page 13: Decommissioning Planning for Nuclear Units at the ......2016-02-18 PREDEC 2016, February 16-18, Lyon, France 1 Decommissioning Planning for Nuclear Units at the Oskarshamn Site Niklas

2016-02-18 PREDEC 2016, February 16-18, Lyon, France 13

Thank you for your attention!