decommissioning of nuclear facilities decommissioning planning · pdf filedecommissioning of...

37
International Atomic Energy Agency Decommissioning of Nuclear Facilities Decommissioning of Nuclear Facilities Decommissioning Planning Decommissioning Planning Lawrence E. Boing Lawrence E. Boing IAEA Regional Workshop IAEA Regional Workshop Manila, The Philippines Manila, The Philippines September 15 September 15 - - 19, 2008 19, 2008

Upload: dangdang

Post on 17-Feb-2018

241 views

Category:

Documents


8 download

TRANSCRIPT

Page 1: Decommissioning of Nuclear Facilities Decommissioning Planning · PDF fileDecommissioning of Nuclear Facilities Decommissioning Planning ... Decommissioning Planning 2 International

International Atomic Energy Agency

Decommissioning of Nuclear FacilitiesDecommissioning of Nuclear Facilities

Decommissioning PlanningDecommissioning Planning

Lawrence E. BoingLawrence E. Boing

IAEA Regional Workshop IAEA Regional Workshop Manila, The PhilippinesManila, The PhilippinesSeptember 15September 15--19, 200819, 2008

Page 2: Decommissioning of Nuclear Facilities Decommissioning Planning · PDF fileDecommissioning of Nuclear Facilities Decommissioning Planning ... Decommissioning Planning 2 International

Decommissioning Planning 2 International Atomic Energy Agency

Lesson ObjectivesLesson Objectives

• Understand the overall planning process as it applies to decommissioning including economic inputs and preliminary studies

• Understand the key points in the planning process• Understand the cost estimation process including

the use of a Work Breakdown Structure (WBS) and its interface with scheduling used in decommissioning planning

• Understand the importance of early planning for effective decommissioning

NOTE: This lesson has been modified to reflect both a summary of ‘conceptual’ material and practicalconsiderations

Page 3: Decommissioning of Nuclear Facilities Decommissioning Planning · PDF fileDecommissioning of Nuclear Facilities Decommissioning Planning ... Decommissioning Planning 2 International

Decommissioning Planning 3 International Atomic Energy Agency

Planning ProcessPlanning Process

• General Planning• General thoughts for the licensee to consider

• Initial Planning• Planning that is conceptual in nature

• Ongoing Planning• Incorporation of details from new information

• Final Planning• Detailed planning prior to conduct of field activities

Decommissioning of a facility is a PROJECT and should be operated using sound project planning principles and project management techniques

Page 4: Decommissioning of Nuclear Facilities Decommissioning Planning · PDF fileDecommissioning of Nuclear Facilities Decommissioning Planning ... Decommissioning Planning 2 International

Decommissioning Planning 4 International Atomic Energy Agency

General PlanningGeneral Planning• Successful decommissioning depends on careful

and organized planning• The planning requirements have to be consistent

with regulatory requirements• A detailed project scope is mandatory for initiating

even the most general planning• The extent, content and degree of detail of planning

depends on the complexity and hazard potential of the installation

• One goal of the planning process is the development of a decommissioning plan

Page 5: Decommissioning of Nuclear Facilities Decommissioning Planning · PDF fileDecommissioning of Nuclear Facilities Decommissioning Planning ... Decommissioning Planning 2 International

Decommissioning Planning 5 International Atomic Energy Agency

General PlanningGeneral Planning

• Three stages of planning are normally used:• Initial Planning• On-going Planning• Final Planning

• Again, the degree of detail will vary from facility to facility and will increase from initial to final decommissioning planning

• Pertinent facility records are critical in the development of the Decommissioning Plan

Page 6: Decommissioning of Nuclear Facilities Decommissioning Planning · PDF fileDecommissioning of Nuclear Facilities Decommissioning Planning ... Decommissioning Planning 2 International

Decommissioning Planning 6 International Atomic Energy Agency

Initial PlanningInitial Planning

• An initial Decommissioning Plan shall be prepared and submitted with each construction application for a new facility

• This plan would contain a lower level of detail than that which would be contained in the final Decommissioning Plan

• Operating facilities without an initial Decommissioning Plan should prepare one without undue delay

Page 7: Decommissioning of Nuclear Facilities Decommissioning Planning · PDF fileDecommissioning of Nuclear Facilities Decommissioning Planning ... Decommissioning Planning 2 International

Decommissioning Planning 7 International Atomic Energy Agency

Ongoing PlanningOngoing Planning

• During on-going facility operations, the Decommissioning Plan shall be routinely reviewed, updated and made more comprehensive with respect to:

• Technological advances• Incidents/abnormal operating events• Regulations and government policy• Cost estimates and financial provisions

• Additionally - to be incorporated into the Decommissioning Plan are:

• Safety considerations, and • Any significant systems and structural

changes

Page 8: Decommissioning of Nuclear Facilities Decommissioning Planning · PDF fileDecommissioning of Nuclear Facilities Decommissioning Planning ... Decommissioning Planning 2 International

Decommissioning Planning 8 International Atomic Energy Agency

Details of the Decommissioning Details of the Decommissioning Planning ProcessPlanning Process

• Project Scope• Selecting the Decommissioning Strategy• Economic Inputs to the Decision Process• Project Initiation • Transition Phase• Project Execution• Project Controls• Project Closeout

Page 9: Decommissioning of Nuclear Facilities Decommissioning Planning · PDF fileDecommissioning of Nuclear Facilities Decommissioning Planning ... Decommissioning Planning 2 International

Decommissioning Planning 9 International Atomic Energy Agency

Project ScopeProject Scope

• Scope for the project is difficult to quantify• Better the definition of scope, more effective the

planning process

• Project cost and schedule are affected by answers to the following• Facilities and area that bounds the project• Expected end-state for the affected facilities and

area• Type and distribution of contaminants• Final release criteria to be met

Page 10: Decommissioning of Nuclear Facilities Decommissioning Planning · PDF fileDecommissioning of Nuclear Facilities Decommissioning Planning ... Decommissioning Planning 2 International

Decommissioning Planning 10 International Atomic Energy Agency

Selecting the Decommissioning StrategySelecting the Decommissioning Strategy

• Once the overall project scope is determined, the decommissioning strategy is selected. Three main approaches are considered• Immediate dismantlement• Deferred dismantlement for some defined period• Entombment

• In general, each approach will be evaluated using a cost-benefit analysis methodology

• Both economic as well as non-economic inputs are typically used to support a site-specific decision for the optimal method of decommissioning

Page 11: Decommissioning of Nuclear Facilities Decommissioning Planning · PDF fileDecommissioning of Nuclear Facilities Decommissioning Planning ... Decommissioning Planning 2 International

Decommissioning Planning 11 International Atomic Energy Agency

Economic Inputs to the Decision Process Economic Inputs to the Decision Process • Cost estimates for each decommissioning strategy

is considered• Decommissioning funding approaches

• Fully funded external fund• Annual budget allocation

• The effects of project delays • timing to begin the project • delays once the project is in progress

• Projections on growth rates for decommissioning funds

• Projections on interest rates• Evaluation of the variability in these parameters

Page 12: Decommissioning of Nuclear Facilities Decommissioning Planning · PDF fileDecommissioning of Nuclear Facilities Decommissioning Planning ... Decommissioning Planning 2 International

Decommissioning Planning 12 International Atomic Energy Agency

Initial Decommissioning PlanInitial Decommissioning Plan• Basic information on the complexity of the facility

decommissioning• Establishes a funding mechanism and collection

process• Lists assumptions for decommissioning• Describes the procedures and requirements for

collection of data during• Construction• Operation• Maintenance

• Provides input to engineering design of the facility• Update regularly as changes occur

Page 13: Decommissioning of Nuclear Facilities Decommissioning Planning · PDF fileDecommissioning of Nuclear Facilities Decommissioning Planning ... Decommissioning Planning 2 International

Decommissioning Planning 13 International Atomic Energy Agency

Decommissioning PlanDecommissioning Plan--ContentsContents

• Introduction• Facility Description• Decommissioning

Strategy• Project Management• Decommissioning

Activities• Surveillance and

Maintenance• Waste Management• Cost Estimate and

Funding Mechanisms

• Safety Assessment• Environmental

Assessment• Health and Safety• Quality Assurance• Emergency Planning• Physical Security and

Safeguards• Final Radiological

Survey

• Appendices if necessary

Page 14: Decommissioning of Nuclear Facilities Decommissioning Planning · PDF fileDecommissioning of Nuclear Facilities Decommissioning Planning ... Decommissioning Planning 2 International

Decommissioning Planning 14 International Atomic Energy Agency

Decommissioning Plan Decommissioning Plan --Decommissioning StrategyDecommissioning Strategy

• Objectives of Project

• Decommissioning alternatives considered

• Safety principles and criteria for each

• Details of alternatives studied

• Selection and justification of preferred strategy

Page 15: Decommissioning of Nuclear Facilities Decommissioning Planning · PDF fileDecommissioning of Nuclear Facilities Decommissioning Planning ... Decommissioning Planning 2 International

Decommissioning Planning 15 International Atomic Energy Agency

Decommissioning Plan Decommissioning Plan ––Decommissioning StrategyDecommissioning Strategy

• Specific information for each strategy considered• Regulatory• Safety- radiological and non-radiological• Schedule• Cost• Waste types and volumes• Dose estimates- worker and public• Technology• Social factors

Page 16: Decommissioning of Nuclear Facilities Decommissioning Planning · PDF fileDecommissioning of Nuclear Facilities Decommissioning Planning ... Decommissioning Planning 2 International

Decommissioning Planning 16 International Atomic Energy Agency

Decommissioning Plan Decommissioning Plan ––Project ManagementProject Management

• Legal and regulatory requirements• Organization and responsibilities• Safety culture• Training and qualifications• Resources and staffing levels,

Contractor support• Schedules

Page 17: Decommissioning of Nuclear Facilities Decommissioning Planning · PDF fileDecommissioning of Nuclear Facilities Decommissioning Planning ... Decommissioning Planning 2 International

Decommissioning Planning 17 International Atomic Energy Agency

Decommissioning Plan Decommissioning Plan ––Waste ManagementWaste Management

• Identification of individual waste streams• Characterization of waste streams• Procedures

• Waste handling• Packaging

• Calculations • Correlation factors• Waste volume estimates by type• Transportation

• Waste disposition

Page 18: Decommissioning of Nuclear Facilities Decommissioning Planning · PDF fileDecommissioning of Nuclear Facilities Decommissioning Planning ... Decommissioning Planning 2 International

Decommissioning Planning 18 International Atomic Energy Agency

Decommissioning Plan Decommissioning Plan --Cost Estimate and Funding MechanismCost Estimate and Funding Mechanism

• Cost Estimate• Base on Decommissioning Project Work

Breakdown Structure activities and schedule• Includes labour, expense and capital• Develop appropriate contingency• Identify all assumptions

• Funding Mechanism• Detail funding collection process throughout

life• Identify contingency funding• Develop cost estimates for contingency restart

Page 19: Decommissioning of Nuclear Facilities Decommissioning Planning · PDF fileDecommissioning of Nuclear Facilities Decommissioning Planning ... Decommissioning Planning 2 International

Decommissioning Planning 19 International Atomic Energy Agency

Project InitiationProject Initiation

• Project initiation begins when the decision is made to permanently shut down a facility and proceed to implementation of the decommissioning strategy.

Page 20: Decommissioning of Nuclear Facilities Decommissioning Planning · PDF fileDecommissioning of Nuclear Facilities Decommissioning Planning ... Decommissioning Planning 2 International

Decommissioning Planning 20 International Atomic Energy Agency

Project InitiationProject Initiation

• Key tasks for project initiation include:• Planning the transition of the existing staff from

operations to decommissioning• Setting up a management organization• Evaluating whether to use outside Contractor or

to self-perform the project• Identifying resources and how to obtain them• Performing preliminary site characterizations to

bound the scope of the work• Preparing baseline cost and schedule estimates

to monitor and control expenditures• Evaluating fuel disposition options

Page 21: Decommissioning of Nuclear Facilities Decommissioning Planning · PDF fileDecommissioning of Nuclear Facilities Decommissioning Planning ... Decommissioning Planning 2 International

Decommissioning Planning 21 International Atomic Energy Agency

Transition Phase ActivitiesTransition Phase Activities

• Following permanent shutdown of the facility, the activities necessary to prepare the facility for decommissioning are begun. These activities include:• Site characterization• Regulatory notifications and any required initial

public interactions • Implementation of revised safety and

authorization bases• Staff reorganization • Bid specification preparation – as appropriate

Page 22: Decommissioning of Nuclear Facilities Decommissioning Planning · PDF fileDecommissioning of Nuclear Facilities Decommissioning Planning ... Decommissioning Planning 2 International

Decommissioning Planning 22 International Atomic Energy Agency

Development of theDevelopment of theWork Breakdown Structure (WBS)Work Breakdown Structure (WBS)

• Categorize cost elements and work activities into logical groupings

• Identify direct or indirect relationships• Work groupings

• Typically related to the accounting system used for budgeting

• Track major elements against decommissioning costs

• WBS elements• Generally arranged in a hierarchical format • Top level of the WBS is the overall project• Subsequent levels used to track increasing levels of

detail in the project

Page 23: Decommissioning of Nuclear Facilities Decommissioning Planning · PDF fileDecommissioning of Nuclear Facilities Decommissioning Planning ... Decommissioning Planning 2 International

Decommissioning Planning 23 International Atomic Energy Agency

Work Breakdown StructureWork Breakdown Structure

• WBS element levels• Six levels may be adequate for a single

decommissioning project• Decommissioning programs with multiple

projects may use 8 or more WBS levels• Costs may be "rolled up" to Level 3 or Level 4

summary costs for management information

• Project management/ accounting software• Usually identifies categories of costs • Compares to the chart of accounts• Integrates WBS format for project reporting

Page 24: Decommissioning of Nuclear Facilities Decommissioning Planning · PDF fileDecommissioning of Nuclear Facilities Decommissioning Planning ... Decommissioning Planning 2 International

Decommissioning Planning 24 International Atomic Energy Agency

Levels of Cost EstimatingLevels of Cost Estimating

• There are different levels of “Accuracy” used when performing a decommissioning cost estimate

• Typical levels of accuracy in cost estimates are:• Order of magnitude -30% to +50%

• Based on similar project scope• Budgetary -15% to +30%

• Use some drawings but not site specific• Definitive -5% to +15%

• Site specific and very detailed; based on drawings and a detailed review of required activities and their costs

Page 25: Decommissioning of Nuclear Facilities Decommissioning Planning · PDF fileDecommissioning of Nuclear Facilities Decommissioning Planning ... Decommissioning Planning 2 International

Decommissioning Planning 25 International Atomic Energy Agency

Contents of a Cost EstimateContents of a Cost Estimate

• Description of the overall facility• Portions included in the cost estimate

• All assumptions• Summary of information by major task

• Cost• Man-hours and labor categories• Staffing levels• Waste volumes• Uncertainties• Contingencies• Backup details on development of cost to allow

independent review• Funding mechanisms

Page 26: Decommissioning of Nuclear Facilities Decommissioning Planning · PDF fileDecommissioning of Nuclear Facilities Decommissioning Planning ... Decommissioning Planning 2 International

Decommissioning Planning 26 International Atomic Energy Agency

Project SchedulingProject Scheduling

• Project schedule • Developed during project planning• Based on a WBS approach• Integrates resources, cost and activity duration• Requires graphical output

• Critical activities • Plan and coordinate lead time for resources• Schedule budget to ensure activity success

• Identify key elements (i.e. waste shipments)• Make a detailed list of tasks for each key element• Tie each line item in the schedule to resources

and duration to complete the task

Page 27: Decommissioning of Nuclear Facilities Decommissioning Planning · PDF fileDecommissioning of Nuclear Facilities Decommissioning Planning ... Decommissioning Planning 2 International

Decommissioning Planning 27 International Atomic Energy Agency

Project SchedulingProject Scheduling• Specific elements in a project schedule may include:

• Preliminary site characterization• Safety assessment and licensing documentation• Preparation of the Decommissioning Plan• Obtaining required permits and approvals• Facility design/ engineering/ modifications to support

decommissioning• Decontamination• Dismantlement and demolition• Waste management• Final radiological survey• License termination actions

Page 28: Decommissioning of Nuclear Facilities Decommissioning Planning · PDF fileDecommissioning of Nuclear Facilities Decommissioning Planning ... Decommissioning Planning 2 International

Decommissioning Planning 28 International Atomic Energy Agency

Research Reactor DecommissioningResearch Reactor Decommissioning–– WBS ExampleWBS Example

JANUS Reactor Decommissioning ProjectANL-East Site, IL

Project Management (1.0)

Surveillance & Maintenance (2.0) Preparation Rooms and Dose RoomsDecommissioning (3.0)

Reactor & Reactor EquipmentRoom Decommissioning (4.0)

Decontamination & Restoration (5.0)

Project Management & Staff (1.1)

Engineering & ProceduresSupport (1.2)

Equipment & Materials (1.3)

Project Close-Out (1.4)

General Preparations (3.1)

Storage Tubes (3.2)

Low Dose Rooms (3.3)

Biological Control Room (3.4)

High Dose Rooms (3.5)

Reactor Tank (4.1)

Reactor Equipment Room (4.2)

Page 29: Decommissioning of Nuclear Facilities Decommissioning Planning · PDF fileDecommissioning of Nuclear Facilities Decommissioning Planning ... Decommissioning Planning 2 International

Decommissioning Planning 29 International Atomic Energy Agency

X ResearchReactor

1

Pre-planning1.1

DecommissioningPlanning

1.3

DecommissioningActivities

1.4

TransitionActivities

1.2

Etc.1.x

DecontaminationPrimary Systems

1.4.1

DecontaminationSecondary Systems

1.4.2

Dismantleequipment in

Room 1A1.4.3

Dismantleequipment in

Room 1B1.4.3

Etc.1.4.x

General deconof room1.4.3.1

Remove allpiping1.4.3.2

Remove tank1A-2

1.4.3.3

Remove tank1A-2

1.4.3.4

Etc.1.4.3.x

Ensure pipingIs drained1.4.3.2.1

Disconnect Pipingfrom tank 1A-1

1.4.3.2.2

Disconnect Pipingfrom tank 1A-2

1.4.3.2.3

Etc.1.4.3.2.x

Example of a WBS to Level 5

Page 30: Decommissioning of Nuclear Facilities Decommissioning Planning · PDF fileDecommissioning of Nuclear Facilities Decommissioning Planning ... Decommissioning Planning 2 International

Decommissioning Planning 30 International Atomic Energy Agency

Example WBS Based ScheduleExample WBS Based Schedule

WBS # Task Name

Labor Hours

(x 1000)

Budget (includes labor) (x 1000€)

T = - 3 Months T = 0

T = 3 Months

T = 6 Months

T= 9 Months

T = 12 Months

T = 15 Months

T = 18 Months

T = 24 Months

1 Decommission Research Reactor 20001.1 Pre-shutdow n planning 301.2 Final Shutdow n === Milestone1.3 Preliminary Studies 301.4 Project Execution 1905

1.4.1 Decommissioning Activities 17401.4.1.1 Decon/Remove Auxilary Systems 8701.4.1.2 Decon/Remove Reactor Systems 8701.4.2 Final Status Surveys 1501.4.3 Confirmatory Surveys 151.4.4 License Termination === Milestone1.5 Closeout Actions 35

1.5.1 Non-radiological remediation 251.5.2 Demobilization 51.5.3 Closeout Documentation 5

Page 31: Decommissioning of Nuclear Facilities Decommissioning Planning · PDF fileDecommissioning of Nuclear Facilities Decommissioning Planning ... Decommissioning Planning 2 International

Decommissioning Planning 31 International Atomic Energy Agency

Cost Estimating ConsiderationsCost Estimating Considerations

• Provisions to protect the workers• Provisions to protect the environment• Regulatory framework within which the

decommissioning must be performed• Project management staff of both the licensee &

the decommissioning contractor (if one is used)• Radioactive waste disposal or storage sites

• Low, intermediate and high-level wastes• Transportation

Black box / general cost estimates donot work !!!

Page 32: Decommissioning of Nuclear Facilities Decommissioning Planning · PDF fileDecommissioning of Nuclear Facilities Decommissioning Planning ... Decommissioning Planning 2 International

Decommissioning Planning 32 International Atomic Energy Agency

Some Practical ConsiderationsSome Practical Considerations

• You will likely encounter• Different fabrication techniques and materials of

construction than shown in records• Inaccurate and missing drawings• Different radiological conditions and/or other hazards• Accessibility issues (structural obstructions, radiological

hazards, etc)• Have a plan and work the plan• Evaluate alternative approaches to undertake the

work – self-perform or contract out• Poor planning often leads to major schedule and

funding issues for the management staff – scope, cost and schedule

Page 33: Decommissioning of Nuclear Facilities Decommissioning Planning · PDF fileDecommissioning of Nuclear Facilities Decommissioning Planning ... Decommissioning Planning 2 International

Decommissioning Planning 33 International Atomic Energy Agency

Some Practical ConsiderationsSome Practical Considerations

• Consider select staff augmentation or use of independent experts to support the work even if contracting or self-performing

• Don’t ‘under characterize’ the site or facility• Don’t overlook any regulatory hold or reviews in

scheduling work• Don’t ‘rush to action’ – sometimes ‘to go fast you

need to go slow’

• Review project specific examples from two decommissioning project sites

Page 34: Decommissioning of Nuclear Facilities Decommissioning Planning · PDF fileDecommissioning of Nuclear Facilities Decommissioning Planning ... Decommissioning Planning 2 International

Decommissioning Planning 34 International Atomic Energy Agency

SummarySummary

• Decommissioning is an orderly, phased final step in the life of a nuclear facility

• Focus on the shutdown/ transition is a key step in the decommissioning process

• Planning for decommissioning is an ongoingprocess

• The Decommissioning Plan is the single document that captures information for the project

• Project schedule, controls and execution were discussed with respect to project planning

• Numerous IAEA reference documents are available

Failing to plan is planning to fail!

Page 35: Decommissioning of Nuclear Facilities Decommissioning Planning · PDF fileDecommissioning of Nuclear Facilities Decommissioning Planning ... Decommissioning Planning 2 International

Decommissioning Planning 35 International Atomic Energy Agency

ReferencesReferences• IAEA Safety Report No. 26 Safe Enclosure of Nuclear

Facilities During Deferred Dismantling (2002)• IAEA Safety Report No. 45 Standard Format and

Content of Safety Related Decommissioning Documents (2005)

• IAEA TRS No. 382 Design and Construction of Nuclear Power Plants to Facilitate Decommissioning (1997)

• IAEA TRS No. 399 Organization and Management for Decommissioning of Large Nuclear Facilities (2000)

• IAEA TRS No. 414 Decommissioning of Small Medical, Industrial and Research Facilities (2003)

• IAEA TRS No. 446 Decommissioning of Research Reactors: Evolution, State of the Art, Open Issues (2006)

http://www-pub.iaea.org/MTCD/publications/publications.asp

Page 36: Decommissioning of Nuclear Facilities Decommissioning Planning · PDF fileDecommissioning of Nuclear Facilities Decommissioning Planning ... Decommissioning Planning 2 International

Decommissioning Planning 36 International Atomic Energy Agency

ReferencesReferences• IAEA WS-G-5.1 – Release of Sites from Regulatory

Control on Termination of Practices• IAEA TECDOC-1133 Decommissioning of WWER-

Type Nuclear Power Plants (2000)• IAEA TECDOC-1394 Planning, Managing, and

Organizing the Decommissioning of Nuclear Facilities: Lessons Learned (2004)

• IAEA TECDOC-1476 Financial Aspects of Decommissioning (2005)

• IAEA TECDOC-1478 Selection of Decommissioning Strategies: Issues and Factors (2005)

• IAEA Waste Safety Guide No. WS-R-2 Predisposal Management of Radioactive Waste, Including Decommissioning (2000)

• IAEA Technical Report Series No. 386 Decommissioning of Nuclear Facilities Other than Reactors (1998)

Page 37: Decommissioning of Nuclear Facilities Decommissioning Planning · PDF fileDecommissioning of Nuclear Facilities Decommissioning Planning ... Decommissioning Planning 2 International

Decommissioning Planning 37 International Atomic Energy Agency

ReferencesReferences• IAEA WS-R-5 Decommissioning of Facilities Using

Radioactive Material (2006)• IAEA Safety Series Guide WS-G-2.1 Decommissioning of

Nuclear Power Reactors and Research Reactors• IAEA Safety Series Guide WS-G-2.2 Decommissioning of

Medical, Industrial, and Research Facilities• IAEA Safety Series Guide WS-G-2.4 Decommissioning of

Nuclear Fuel Cycle Facilities• IAEA Technical Reports Series No. 346, Cleanup and

Decommissioning of a Nuclear Reactor After a Severe Accident (1993)

• IAEA Technical Reports Series No. 351, Planning and Management for the Decommissioning of Research Reactors and Other Small Nuclear Facilities (1993)

• IAEA Technical Reports Series No. 365, Decontamination of Water Cooled Reactors (1994)