Eidgenössisches Nuklearsicherheitsinspektorat ENSI Swiss Federal Nuclear Safety Inspectorate ENSI Decommissioning in Switzerland Technical post-operation in Mühleberg NPP IDN-Meeting 5 7 December 2017, Vienna Thomas Ernst-Simonnot; Deputy Section Head Decommissioning

Upload: others

Post on 24-Mar-2020

9 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Decommissioning in Switzerland Technical post …...Decommissioning in Switzerland Technical post-operation in Mühleberg NPP IDN-Meeting 5 – 7 December 2017, Vienna Thomas Ernst-Simonnot;

Eidgenössisches Nuklearsicherheitsinspektorat ENSI

Swiss Federal Nuclear Safety Inspectorate ENSI

Decommissioning in

Switzerland

Technical post-operation

in Mühleberg NPP

IDN-Meeting 5 – 7 December 2017, Vienna

Thomas Ernst-Simonnot; Deputy Section Head Decommissioning

Page 2: Decommissioning in Switzerland Technical post …...Decommissioning in Switzerland Technical post-operation in Mühleberg NPP IDN-Meeting 5 – 7 December 2017, Vienna Thomas Ernst-Simonnot;

Experience in Decommissioning

2

Installation Operation time Decommissioning VAKL Lucens 1968-1969 Decommissioned 1995/2004

PSI RR DIORIT 1960-1977 End of nuclear dismantling activites

Uni Genève RR 1958-1987 Decommissioned 1989

PSI RR SAPHIR 1957-1994 End of nuclear dismantling activites

PSI VVA* 1974-2002 Decommissioning phase 2**

PSI RR PROTEUS 1968-2011 Decommissioning order expected

Uni Basel RR 1960-2015 Decommissioning project

* Test incinerator facility for LAW

** Dismantling of the combustion furnace

PSI: SAPHIR

DIORIT

PROTEUS

VVA

Lucens

Genève

Uni Basel

Thomas Ernst-Simonnot / ENSI / Decommissioning in Switzerland

Page 3: Decommissioning in Switzerland Technical post …...Decommissioning in Switzerland Technical post-operation in Mühleberg NPP IDN-Meeting 5 – 7 December 2017, Vienna Thomas Ernst-Simonnot;

Status current projects

3 Thomas Ernst-Simonnot / ENSI / Decommissioning in Switzerland

Pilot incineration plant at PSI

• Incineration of low active waste at 1200 °C

• Decommissioning project is granted

• Preparatory work for decommissioning

completed (restricted access area,

ventilation system, operating regulations)

• Dismantle phase 1 started: March 2016

• Documents for phase 2 approval expected

Page 4: Decommissioning in Switzerland Technical post …...Decommissioning in Switzerland Technical post-operation in Mühleberg NPP IDN-Meeting 5 – 7 December 2017, Vienna Thomas Ernst-Simonnot;

Status current Projects

4 Thomas Ernst-Simonnot / ENSI / Decommissioning in Switzerland

Basel University

Research Reactor AGN-211-P

• Complete core (highly enriched

Uranium) transported to the U.S.

• Decommissioning project

is submited

Page 5: Decommissioning in Switzerland Technical post …...Decommissioning in Switzerland Technical post-operation in Mühleberg NPP IDN-Meeting 5 – 7 December 2017, Vienna Thomas Ernst-Simonnot;

Decommissioning of Mühleberg NPP

5

Owner BKW

Boiling Water Reactor

373 MWe / 1097 MWth

GE BWR 4 / Mark 1

Start of commercial operation: November 1972

Fuel pond inside on service floor

Second torus for venting-system

Safety systems on the lower floor

Thomas Ernst-Simonnot / ENSI / Decommissioning in Switzerland

Oktober 2013: BKW decided to cease power operation by the end of 2019

Page 6: Decommissioning in Switzerland Technical post …...Decommissioning in Switzerland Technical post-operation in Mühleberg NPP IDN-Meeting 5 – 7 December 2017, Vienna Thomas Ernst-Simonnot;

Timetable of the preparation process

6

12/2015 Submission of BKW application letter and decommissioning project

01/2016 –

09/2017

Completeness check by authorities SFOE/ENSI/FOEN Revision by BKW Public hearing (Possibility of objection) Safety assessment and expert report by ENSI (Statement of NSC) Statements from cantons and federal authorities (FOEN)

10/2017 Exchange of involved authorities

06/2018 Decommissioning order (licence) from DETEC

2018 … Complaint/litigation (Federal Administrative Court, Federal Court)

Thomas Ernst-Simonnot / ENSI / Decommissioning in Switzerland

Page 7: Decommissioning in Switzerland Technical post …...Decommissioning in Switzerland Technical post-operation in Mühleberg NPP IDN-Meeting 5 – 7 December 2017, Vienna Thomas Ernst-Simonnot;

Decommissioning project

7

Decommissioning Project (Main report)

Security measures (Part 3)

Environmental impact report (Part 2)

Accident analysis & emergency preparedness

measures (Part 1)

Application

letter

Thomas Ernst-Simonnot / ENSI / Decommissioning in Switzerland

Page 8: Decommissioning in Switzerland Technical post …...Decommissioning in Switzerland Technical post-operation in Mühleberg NPP IDN-Meeting 5 – 7 December 2017, Vienna Thomas Ernst-Simonnot;

Nine requests in the application letter

8

Application

letter

1. Decommissioning order for direct dismantling according to the submitted

decommissioning project

2. Limitation of the scope of the decommissioning activities according to the

submitted decommissioning project

3. Dividing of the decommissioning activities into three decommissioning phases

4. Release of BKW from the liability to guarantee nuclear safety and security

and termination of supervision by the competent authorities after completion of the

radiological clearance measurements

5. Implementation of “Preparatory Measures" after final cease of operation

6. Definition of limits for radioactive discharges

7. Definition of the organisational structure according to the submitted

decommissioning project

8. Issuance of the required approvals by ENSI for the decommissioning phases as

well as the activities defined in Art. 47, Nuclear Energy Ordinance

9. Definition of provisions for the withdrawal and return of cooling water from and

to the Aare river

Thomas Ernst-Simonnot / ENSI / Decommissioning in Switzerland

Page 9: Decommissioning in Switzerland Technical post …...Decommissioning in Switzerland Technical post-operation in Mühleberg NPP IDN-Meeting 5 – 7 December 2017, Vienna Thomas Ernst-Simonnot;

NEA + WENRA Choice:

Immediate dismantling - Deferred dismantling

NPP Muehleberg:

Fuel on-site: – Modifications to transfer the fuel (pond) in autarkic mode

– Preparatory measures to optimize dismantling starting point

9 Thomas Ernst-Simonnot / ENSI / Decommissioning in Switzerland

Decommissioning strategy

Page 10: Decommissioning in Switzerland Technical post …...Decommissioning in Switzerland Technical post-operation in Mühleberg NPP IDN-Meeting 5 – 7 December 2017, Vienna Thomas Ernst-Simonnot;

Decommissioning phases

10

AS: status

1) based on supervisory process with ENSI

2) final assessment report ENSI source: BKW

Thomas Ernst-Simonnot / ENSI / Decommissioning in Switzerland

Page 11: Decommissioning in Switzerland Technical post …...Decommissioning in Switzerland Technical post-operation in Mühleberg NPP IDN-Meeting 5 – 7 December 2017, Vienna Thomas Ernst-Simonnot;

29.10.2013: Decision of BKW to cease power operation in

the end of 2019

14.11.2013: ENSI-disposal with regard to shut down KKM by the end

of 2019 (18 requirements)

Requirement 1 concerned provisions for dismanteling

19.12.2014: Concept of BKW for the safe technical post-operation

phase

03.12.2015: ENSI-disposal with regard to further power operation of

KKM to the end of 2019 (5 requirements)

Requirement 4 concerned the installation of an independent

spent fuel pool system

10.12.2015: ENSI-disposal with regard to «technical post-operation»

of KKM (10 Requirements)

• Objective: Establishment of the safe technical post-

operation phase (supervisory procedures with ENSI)

Technical post-operation initial position

Thomas Ernst-Simonnot / ENSI / Decommissioning in Switzerland 11

Page 12: Decommissioning in Switzerland Technical post …...Decommissioning in Switzerland Technical post-operation in Mühleberg NPP IDN-Meeting 5 – 7 December 2017, Vienna Thomas Ernst-Simonnot;

Approval of the technical post-operation

• Deterministic safety analysis

• Probabilistic safety analysis

• List of still required and no longer required systems

• System changes with safety reviews

• Process "taking out of service" (Systems and components)

• Nuclear fuel: loading strategy for containers & transportation planning

• Retroactive effects of changes and taking out of service

• Organisation, personnel etc.

Thomas Ernst-Simonnot / ENSI / Decommissioning in Switzerland 12

Application documents are expected in December 2017

Page 13: Decommissioning in Switzerland Technical post …...Decommissioning in Switzerland Technical post-operation in Mühleberg NPP IDN-Meeting 5 – 7 December 2017, Vienna Thomas Ernst-Simonnot;

13

B

A

C

D

Preparatory measures

A: Unload the reactor pressure vessel (transfer of spent fuel to the spent fuel pool)

B: Installation of the safety grade spent fuel pool cooling system (ARBEK-Project)

C: Removal of mobile equipment in the reactor building at +29m

D: Removal of components in the turbine hall and Installation of the material treatment

facilities

Thomas Ernst-Simonnot / ENSI / Decommissioning in Switzerland

Activities establishment of technical post-

operation and preparatory measures

Page 14: Decommissioning in Switzerland Technical post …...Decommissioning in Switzerland Technical post-operation in Mühleberg NPP IDN-Meeting 5 – 7 December 2017, Vienna Thomas Ernst-Simonnot;

Backfitting project ARBEK

ARBEK-B: Modification of operation systems

ARBEK-S: new, emergency secured safety-system for spent fuel

cooling

ARBEK-N: Additional emergency facilities (Utilization Hilltop-

reseroir for coolingwater supply and and spent fuel

pool water injection by mobile equipment)

ARBEK-Z: Additional plug between spent fuel pool an reactor

cavity

ARBEK-R: protective measures to ensure no negative retroactive

effects of changes and taking out of service

Establishment of technical post-operation

Autarkic mode of the spent fuel pool

Thomas Ernst-Simonnot / ENSI / Decommissioning in Switzerland 14

Page 15: Decommissioning in Switzerland Technical post …...Decommissioning in Switzerland Technical post-operation in Mühleberg NPP IDN-Meeting 5 – 7 December 2017, Vienna Thomas Ernst-Simonnot;

Cooling system in technical post-operation

15 Thomas Ernst-Simonnot / ENSI / Decommissioning in Switzerland

Page 16: Decommissioning in Switzerland Technical post …...Decommissioning in Switzerland Technical post-operation in Mühleberg NPP IDN-Meeting 5 – 7 December 2017, Vienna Thomas Ernst-Simonnot;

Dismantling strategy phase 1

16

A Removal of spent fuel from the site E Installation of material treatment equipment

B Disassembly of the torus incl. linked systems F Disassembly of remaining systems and initiation of

decontamination of facilities and buildings C Disassembly of emergency core cooling

system / systems for decay heat removal G Disassembly of block transformer A1

D Disassembly of reactor internals Source: BKW

Thomas Ernst-Simonnot / ENSI / Decommissioning in Switzerland

Page 17: Decommissioning in Switzerland Technical post …...Decommissioning in Switzerland Technical post-operation in Mühleberg NPP IDN-Meeting 5 – 7 December 2017, Vienna Thomas Ernst-Simonnot;

Dismantling strategy phase 2

17

A Disassembly of spent fuel pool cooling systems

B Disassembly of pool internals

C Disassembly of reactor pressure vessel (RPV)

D Removal of personnel and material airlocks

E Disassembly of drywell components

F Disassembly of steam pipes and feed water pipes

G Disassembly of upper part of the biological shield

H Disassembly of drywell steel liner

I Disassembly of steam dryer and moisture separator

storage pool liner and RPV cavity

J Disassembly of all remaining systems, e.g. reactor

water clean up system

K Decontamination of facilities and buildings

L Operation of material treatment equipment

M Disassembly of systems in the SUSAN-building

Source: BKW

Thomas Ernst-Simonnot / ENSI / Decommissioning in Switzerland

Page 18: Decommissioning in Switzerland Technical post …...Decommissioning in Switzerland Technical post-operation in Mühleberg NPP IDN-Meeting 5 – 7 December 2017, Vienna Thomas Ernst-Simonnot;

Final state after nuclear dismantling

18

1 SUSAN-building 19 Steam dryer and moisture separator storage pool

3 Reactor building (Secondary containment) 21 Turbine hall

17 Spent fuel pool

Source: BKW

Thomas Ernst-Simonnot / ENSI / Decommissioning in Switzerland

Page 19: Decommissioning in Switzerland Technical post …...Decommissioning in Switzerland Technical post-operation in Mühleberg NPP IDN-Meeting 5 – 7 December 2017, Vienna Thomas Ernst-Simonnot;

Where do the dismantled materials end up?

19

Source: BKW

Thomas Ernst-Simonnot / ENSI / Decommissioning in Switzerland

Page 20: Decommissioning in Switzerland Technical post …...Decommissioning in Switzerland Technical post-operation in Mühleberg NPP IDN-Meeting 5 – 7 December 2017, Vienna Thomas Ernst-Simonnot;

20

Thomas Ernst-Simonnot / ENSI / Decommissioning in Switzerland

Für mehr Informationen besuchen Sie uns auf:

www.ensi.ch

http://twitter.com/#!/ENSI_CH

www.ifsn.ch

Thanks for your attention.