december 16, 2013 1:00 – 2:45. mpm team agenda 1.review of mpm program and team 2.consensus items...
TRANSCRIPT
Statewide Mobility Performance Measures and
FDOT Modal Office Coordination Meetings
December 16, 20131:00 – 2:45
MPM Team Agenda
1. Review of MPM Program and Team2. Consensus items document3. Upcoming activities4. Discussion
FDOT Modal Office Agenda
1. (Consensus items – previously addressed)2. Availability of modal data and measures3. Additional modal definitions4. Discussion
Statewide Mobility Performance Measures Team Purpose
To provide guidance and support to FDOT and the state’s MPOs on multimodal mobility performance measures including reporting for internal and MAP-21 purposes
Consensus on approach and measures
Consensus in approach and measures
MPOs
Others
Summary of Outreach• MPOAC – January 29, 2013 and October 30, 2013
• Multimodal Coordination Team – March 12 and August 8, 2013
• FDOT Mobility Performance Measures Team - April 9 and 10 (Orlando), June 17 (webinar), October 7, 2013
• FDOT Executive Board – November 21, 2013
• Mobility Performance Measures Summits - December, 2012 and January, 2013
• FDOT Travel Time Reliability Coordination Group - March 11, 2013 and September 10, 2013
Summary of Outreach• FDOT District 4 Planning and Operations – May 8, June
18, August 15, 2013
• Broward MPO – May 7, June 17, August 14, September 25, 2013
• FDOT District 6 ITS and TSM&O – May 7, 2013
• FDOT District 6 – August 15, 2013
• FDOT District 7 – August 21, September 18, 2013
• Florida Section ITE – June 21, 2013
• Hillsborough MPO – August 21, 2013
• Miami-Dade MPO – October 1, 2013
aaaaaaaaaaaaaaaa
MAP-21 Requirements
Moving Ahead for Progress in the 21st Century
8
USDOT wants States and MPOs to do performance based planning
ISTEA/TEA-21 MAP-21
Multimodal
Public Involvement
Performance Measures
9
Get out in front
Positive
Supportive
Florida DOT’s Perspective
“We track progress toward meeting our own goals”
“FDOT is committed to being leaders and innovators in this
vitally important area of transportation management”
Ananth PrasadFDOT Secretary
MAP-21 Mobility Performance Measures Schedule
SpringWinter
USDOT Notice of Proposed Rulemaking
2013
Spring
States set targets
2014
Effective date of final rule
MPOs set targets
2015 2016
90 daycomment
period
USDOT establishes measures
FallSpring
11
Performance Targets
MPODesire forCoordination
12
States and MPOs must integrate performance plans into a performance-based process
FDOT Draft MAP-21 Recommendations
• Vehicle miles traveled
• % travel meeting generally acceptable operating conditions
• Travel time reliability
• Delay
• % miles severely congested
FDOT Draft MAP-21 Freight Recommendations
• Combination truck miles traveled
• Travel time reliability
• Combination Truck Delay
• % miles severely congested
FDOT TranStat’s Intent• FDOT will provide analysis of all required
MAP-21 mobility performance measures – For the state as a whole (not by Districts)– Each MPO (has the option to use or not)
• Comparable measurements for road networks– MAP-21 networks– State Highway System
FDOT Central Office Roles:
Coordinate statewide efforts on MPM Program
Produce and report on statewide MAP-21 measures
Produce annual TranStat Source Book
Provide additional MPMs
National Performance Measures Research Data Set (NPMRDS)
Lead development of targets and support MPOs
Develop and provide training in 2014
Central Office
District Office
MPO
Provide input to Central Office on MPM program
Implement FDOT projects/programs to implement Federal and State goals/objectives and document activities
Develop own MPMs within districts, if appropriate
Coordinate with MPOs and Regional MPOs
• Provide MAP-21 mobility performance measure analyses developed by the Central Office
• Provide technical support• Provide advice on setting goals and objectives
FDOT District Offices Roles:
Central Office
District Office
MPO
MPOs Roles:
• Comply with MAP-21– Use calculated results provided by FDOT, if desired– Report to FHWA as required– Develop performance targets– Include in LRTPs and Congestion Management Plans to
evaluate alternatives, programming/prioritization of projects• Develop own MPMs, if appropriate• Coordination with other MPOs, if appropriate
Central Office
District Office
MPO
National Performance Management Research Data Set (NPMRDS)
• Average travel times• Every 5 minutes, 24 hours, 7 days a week
• For entire National Highway System• Provided by HERE – Formerly Nokia/Navteq• Segmentation = Traffic Message Channel
(TMC)• Data for freight (from ATRI) and passenger
NPMRDS • Availability
– Data on systems• Interstate - beginning in October 2011• NHS – beginning in July 2103
– Data to be provided monthly 2 weeks after month’s end• Licensing agreements
– FDOT signed December 2• Only 1 FDOT person can sign (TranStat C.O., Paul O’Rourke)
– No other offices or any District
• Can not be provided to other entities (MPOs, local governments)
– Each MPO must sign if desire data (Caution!)• Concerns about Florida’s Open Records Laws (FDOT added language before
signing)• FDOT has communicated with MPOAC (Gougelman, Glassman)
MAP-21 National Goal Areas for the
Federal Aid Highway Program
Does not address mobility in general
Not multimodal in scope
For FDOT
purposes, not MAP-21
People and Freight 4
All major modes
Features of Florida’s Draft Statewide Mobility Performance Measures
www.dot.state.fl.us/planning/statistics/mobilitymeasures/
22
Definitions
• Recommended for statewide consistency• Measures are auto and truck oriented• Future versions will incorporate more modes
Future Activities
• Statewide consensus items finalize – 12/13
• Keep Statewide Team active, – Possibly quarterly annual meetings– Refine measures and methods
Fu
ture
Dir
ect
ion
Develop and deliver a Training and Users Guide
Implementation of measures into LRTPs and CMPs
Conduct research related to Strategic Highway Research Program (SHRP2)
Evaluate impact of safety on the MPMs
Develop freight origin/destination measures
Conduct research regarding accessibility measures
Evaluate NPMRDS for use in the Source Book and MAP-21
Develop targets
Consider MPMs for multimodal corridors
MPM Team Agenda
1. Review of MPM Program and Team2. Consensus items document3. Upcoming activities4. Discussion