  • 8/19/2019 DBKL Osc - Manual Submision of Development Proposals Through the One Stop Center (Osc)

    1/189

     MANUAL SUBMISSION OFDEVELOPMENT PROPOSALS

    THROUGH THEONE STOP CENTER (OSC)CITY HALL KUALA LUMPUR

    DEWAN BANDARAYA

    KUALA LUMPUR

  • 8/19/2019 DBKL Osc - Manual Submision of Development Proposals Through the One Stop Center (Osc)

    2/189

     

    DEWAN BANDARAYA

    KUALA LUMPUR

    URUSETIA PUSAT SETEMPAT, JABATAN PERANCANGAN BANDARTingkat Bawah, Menara DBKL 2,

    Jalan Raja Laut, 50350 KUALA LUMPURTelefon : 03 - 2617 9000 Faks : 03 - 2694 3085

    http://jprb.dbkl.gov.my

  • 8/19/2019 DBKL Osc - Manual Submision of Development Proposals Through the One Stop Center (Osc)

    3/189

      City Hall Kuala Lumpur ONE STOP CENTER (OSC) MANUAL 

      PREFACE i 

      COMMITTEE ON THE PREPARATION OF THE ONE STOP CENTRE (OSC) ii 

    MANUALCITY HALL KUALA LUMPUR 

      MESSAGE FROM THE LORD MAYOR iii 

      FOREWARD

    ONE STOP CENTRE (OSC) CITY HALL KUALA LUMPUR iv

    -  INTRODUCTION v

    -  OBJECTIVE vi

    PART 1: PROCEDURE ON SUBMISSION OF APPLICATION

    SECTION A : SPECIFICATION ONSUBMISSION OF APPLICATION

    1.0  WHO CAN SUBMIT APPLICATIONS? 1

    2.0  APPLICATIONS THAT CAN BE SUBMITTED TO THE OSC 2

    2.1  Category of Applications 2

    2.1.1  Application on Land Matters 2

    2.1.2  Application on Planning Permission 2

    2.1.3  Application on Building Plans 3

    2.1.4 

    Application on Engineering Plans 3

    2.1.5  Application on Landscape Plans 3

    2.1.6  Other Applications 3

    2.1.7  Submission for records and Information 3

    2.2  Types of Applications 4

    2.3  Types of Development 6

    2.4  Scale of Development 6

       C   O   N   T   E   N   T   S

  • 8/19/2019 DBKL Osc - Manual Submision of Development Proposals Through the One Stop Center (Osc)

    4/189

     

    City Hall Kuala Lumpur ONE STOP CENTER (OSC) MANUAL 

    2.4.1 Large Scale 6

    2.4.2 Medium Scale 8

    2.4.3 Small Scale 8

    2.5 Categories of Projects 9

    SECTION B: DEPARTMENTS/AGENCIES INVOLVED

    1.0  DESIGNATION OF INTERNAL AND EXTERNAL DEPARTMENTS/AGENCIES CHKL 10

    1.1 

    Role of Internal Technical Departments that process and review applications 111.2  Role of external technical agencies that process and review applications 11

    1.3  Confirmation of differences between CHKL Technical Review Department 11

    and the Ministry of Housing and Local Government (MHLG)

    2.0  CHECKLIST FOR INTERNAL AND EXTERNAL DEPARTMENTS/AGENCIES 12

    SECTION C:APPLICATION PROCESS AND PROCEDURE

    1.0  HOW ARE APPLICATIONS PROCESSED? 18

    Flow Chart on the Development Application Procedure by the One Stop Centre 19

    -  Large Scale

    Flow Chart on the Development Application Procedure by the One Stop Centre 46-  Medium Scale

    Flow Chart on the Development Application Procedure by the One Stop Centre 62

    -  Small Scale

    Flow Chart on the Development Application Procedure by the One Stop Centre 74

    Record

       C   O   N   T   E

       N   T   S

  • 8/19/2019 DBKL Osc - Manual Submision of Development Proposals Through the One Stop Center (Osc)

    5/189

      City Hall Kuala Lumpur ONE STOP CENTER (OSC) MANUAL 

    PART 2 : PREPARATION OF APPLICATION DOCUMENT FORSUBMISSION

    SECTION A: DOCUMENTS REQUIRED TO BE SUBMITTED BY TYPES OF APPLICATION

    1.0 INTRODUCTION 79

    2.0 DOCUMENTS REQUIRED TO BE SUBMITTED BY CATEGORY OF APPLICATION 82

    2.1 On Land Matters 822.1.1 Land Matters (Conversion and Subdivision - PU) 82

    2.1.2  Land Matters (Surrender and realienation - PP) 83

    2.2 On Planning Permission (KM) 85

    2.2.1 Application forms required to be completed 85

    2.2.2 Plans 85

    2.2.3 Documents required to accompany applications 88

    2.3 On Building Plans (PB) 89

    2.3.1 Application Forms required to be completed 89

    2.3.2 Plans 90

    2.4 On Engineering Plans (PJ) 94

    2.4.1 Department of Infrastructure Planning (JPIF) 94

    2.4.2 Technical Departments CHKL 98

    2.4.3 External Technical Departments 101

    2.5 On Landscape Plans (PL) 104

    2.5.1 Application Forms to be completed 104

    2.5.2 Plans 104

    2.5.3 Documents required to accompany applications 105

       C   O   N   T   E   N   T   S

  • 8/19/2019 DBKL Osc - Manual Submision of Development Proposals Through the One Stop Center (Osc)

    6/189

     

    City Hall Kuala Lumpur ONE STOP CENTER (OSC) MANUAL 

    2.6 On Applications involving Public Transportation Unit, 107

    Department of Infrastructure Planning (UPA, JPIF)

    2.6.1 Application for approval on Public Transport Plan (Bus/Taxi Stops) 107

    2.6.2 Application for Approval on Pedestrian overhead crossings and 108

    covered walkways

    2.6.3 Application for Approval for Vehicle parking plan, Internal Traffic 109

    Circulation and Traffic Flows

    2.7 On Applications involving Drainage Unit, 111Department of Infrastructure Planning (US, JPIF)

    2.7.1 Application for approval for Stormwater Management Plan for 111

    medium and large scale developments (all developments)

    2.7.2 Application for approval on Rainwater Harvesting System for 112

    small scale developments

    (Residential - Bungalow/Semi-detached, terraces)

    2.7.3 Application for approval on Drainage Master Pan for small, 114medium and large scale developments

    (developments affecting main drain reserves/rivers)

    2.8 On applications involving the Department of Health and Environment (JKAS) 115

    2.8.1 Application forms to be completed 115

    2.8.2 Plans 115

    2.8.3 Documents required to accompany applications 115

    2.9 On Applications for Permits 116

    2.9.1 Permit for small construction works (residential building) 116

    2.9.2 Permit for small construction works (Shop house/office) 117

    2.9.3 Permit for Temporary Building 117

       C   O   N   T   E

       N   T   S

  • 8/19/2019 DBKL Osc - Manual Submision of Development Proposals Through the One Stop Center (Osc)

    7/189

      City Hall Kuala Lumpur ONE STOP CENTER (OSC) MANUAL 

    2.10 On submission for certification of completion and compliance (CCC) 119

    2.10.1 Application forms to be completed 119

    2.10.2 Plans 120

    2.10.3 Documents required to accompany applications 120

    2.11 On Building Plan applications for concurrent residential approval 121

    2.11.1 Application for building plan (with earthworks) 121

    2.11.2 Application for building plan (without earthworks) 122

    2.12 On Applications submitted for record 124

    2.12.1 Submission of sanitation plan 124

    2.12.2 Submission of Reinforced concrete plan 124

    2.13 On application for CFO 125

    2.13.1 Forms to be completed 125

    2.13.2 Plans 1252.13.3 Documents required to accompany application 126

    SECTION B : PROCESSING FEES FOR APPLICATIONS

    1.0  PLANNING PERMISSION 127

    2.0  BUILDING PLANS 128

    3.0 

    ENGINEERING PLANS 1294.0  LANDSCAPE PLANS 130

       C   O   N   T   E   N   T   S

  • 8/19/2019 DBKL Osc - Manual Submision of Development Proposals Through the One Stop Center (Osc)

    8/189

     

    City Hall Kuala Lumpur ONE STOP CENTER (OSC) MANUAL 

    PART 3: LIST OF GUIDELINES AND DEVELOPMENT EVALUATION

    CRITERIA

    SECTION A : LIST OF DEVELOPMENT GUIDELINES

    1.0 DEVELOPMENT GUIDELINES AND STANDARDS 131

    1.1 Guidelines on Planning Permission 131

    1.2 Guidelines on Building Plans 1321.3 Guidelines on Engineering Plans 133

    2.0 ACTS AND LEGISLATIONS

    SECTION B :DEVELOPMENT EVALUATION CRITERIA

    1.0 EVALUATION CRITERIA FOR PLANNING PERMISSION 1352.0 EVALUATION CRITERIA FOR BUILDING PLANS 150

    3.0 EVALUATION CRITERIA FOR ENGINEERING PLANS 160

    4.0 EVALUATION CRITERIA FOR LANDSCAPE PLANS 164

     APPENDIX 170

     

    APPENDIX 1 173-  Detailed Matrix of Forms and Checklists Used

     ONE STOP CENTRE MANUAL FOR DEVELOPMENT PLANNING APPLICATIONS 170

    COMMITTEE MEMBERS

       C   O   N   T   E

       N   T   S

  • 8/19/2019 DBKL Osc - Manual Submision of Development Proposals Through the One Stop Center (Osc)

    9/189

     

    City Hall Kuala Lumpur ONE STOP CENTER (OSC) MANUAL 

    LIST OF TABLES

    Table 1.1 : Types of Proposed Development Plan Applications to OSC City Hall 4

    Kuala Lumpur

    Table 1.2 : Types of Development 6

    Table 1.3 : MHLG Project Categories 9

    Table 1.4 : Special OSC Project Categories 9

    Table 1.5 : List of Internal Technical Departments/Agencies that Process and Evaluate 12

    Table 1.6 : List of External Technical Departments/Agencies that Process and Evaluate 13Table 1.7 : List of Technical Departments/Agencies Referred to by types of applications 13

    Table 1.8 : List of Technical Internal and External Departments/Agencies Referred 14

    to by types of applications

    Table 2.1 : List of Forms by application types 80

    Table 3.1 : Planning evaluation criteria for application for Planning Permission 136

    (Large scale projects)

    Table 3.2 : Planning evaluation criteria for Planning Permission applications 144(Small/medium scale)

    Table 3.3 : Evaluation criteria for Building Plan Application 157

    Table 3.4 : Evaluation criteria for Engineering Plan Application 160

    - Earthworks

    Table 3.5 : Evaluation criteria for Engineering Plan Application 162

    - Road and Drainage plans

    Table 3.6 : Evaluation criteria for Engineering Plan Application 163- Street Lighting Plan

    Table 3.7 : Evaluation criteria for Landscape Plan Application (Current) 164

    Table 3.8 : Evaluation criteria for Landscape Plan Aplication (A17) 168

       L   I

       S   T   O   F   T   A   B

       L   E   S

  • 8/19/2019 DBKL Osc - Manual Submision of Development Proposals Through the One Stop Center (Osc)

    10/189

     

    City Hall Kuala Lumpur (CHKL) has the

    objective to increase the awareness of

    ‘Principal Submitting Person (PSP) or

    “Submitting Person’ (SP) in submitting

    application to the One Stop Centre (OSC).

    CHKL in partnership with the Malaysian

    Institute of Planners (MIP), the Institute of

    Architects Malaysia (PAM) and the

    Associtaion of Consulting Engineers Malaysia

    (ACEM), has produced this Manual on theSubmission of Development Proposal

    Applications to the OSC CHKL.

    This Manual provides detailed explanations

    on the method, process and procedure that

    are involved in getting approvals for

    development projects within the FederalTerritory of Kuala Lumpur.

    This Manual is specific for CHKL as the laws

    pertaining to it differ from other local

    authorities in the country. The legislation

    adopted are the Federal Territory Planning

    Act 1982 (Act 267), the Street, Drainage andBuilding Act 1974 (Act 133), Building Bye Law

    (Federal Territory Kuala Lumpur) 1985 and

    the Earthworks Bye-Law (Federal Territory

    Kuala Lumpur) 1988.

    This Manual contains information on the

    schedule of fees for filing, checklist for plan

    submission, application forms and the list of

    planning, building and engineering

    guidelines.

    It also outlines the criteria used by the

    internal technical departments of CHKL in the

    evaluation and consideration of the

    development proposal application.

    To provide an even clearer picture of the

    whole process, this manual contains

    flowcharts for every type of application

    involved up to the issuance of the decision.

    The use of this Manual shall ensure that every

    application to CHKL is comprehensive,systematic and follows all procedures. Hence,

    it will be the guide for all involved in the

    submission of applications to the OSC CHKL.

       P   R   E   F   A   C   E

    City Hall Kuala Lumpur ONE STOP CENTER (OSC) MANUAL i

  • 8/19/2019 DBKL Osc - Manual Submision of Development Proposals Through the One Stop Center (Osc)

    11/189

     

    I would like to thank and congratulate all

    those involved in the production of the One

    Stop Centre Manual on Development Plan

    Application City Hall Kuala Lumpur. Those

    involved included the Malaysian Institute of

    Planners (MIP), the Institute of Landscape

    Architects Malaysia (PAM)and the

    Association of Consulting Engineers Malaysia

    (ACEM) together with City Hall and external

    technical agencies.

    As the capital city, Kuala Lumpur has an

    important role to spur development and be

    the lead catalyst in the National Key

    Economic Areas (NKEA) within the Greater

    Klang Valley. Consistent with this, City Hall

    Kuala Lumpur strives to improve andstrengthen its delivery and services in order

    to stimulate property development in the

    city.

    The OSC system that was launched by the

    Government in April 2007 was implemented

    by CHKL from July 2007 to coordinatedevelopment applications through the

    evaluation and approval process within the

    stipulated timeframe.

    CHKL consistently strives to improve its OSC

    system from time to time to ensure greater

    efficiency in issuing faster decisions with zero

    delays.

    In October 2010, the OSC was further

    strengthened with the launch of the on-line

    system known as the KUL-Submission.

    This system was developed to enable on line

    submission by the PSP/SP 24 hours 7 days a

    week (24/7). This system would enable a

    more efficient and transparent management

    of development applications.

    It is hoped that this Manual will provide a

    clear guide and information on the OSC

    system implemented by DBKL.

    Indirectly, the delivery system by CHKL will be

    more user friendly, thereby simplifying and

    facilitating the process of propertydevelopment in the city.

    Tan Sri Ahmad Fuad Bin Ismail

    Kuala Lumpur City Mayor

       M   E   S

       S   A   G   E   F   R   O

       M    T

       H   E   M   A

       Y   O   R

     

    City Hall Kuala Lumpur ONE STOP CENTER (OSC) MANUAL ii

  • 8/19/2019 DBKL Osc - Manual Submision of Development Proposals Through the One Stop Center (Osc)

    12/189

     

    ONE STOP CENTRE CITY HALL KUALA

    LUMPUR

    The One Stop Centre (OSC) was launched by the

    Right Honorable Prime Minister on the 13th April

    2007. The main goal and objective was to

    improve on the process and procedure in

    considering development applications, a vital

    aspect in the government’s ef forts to improve

    the public delivery system.

    In line with this aspiration the One Stop Centre

    City Hall Kuala Lumpur (OSC CHKL) was officiallly

    launched on the 3rd July 2007. The OSC CHKL is

    responsible to coordinate all development

    applications within the Federal Territory Kuala

    Lumpur to be processed within the time frame

    specified by the Ministry of Housing and LocalGovernment (MHLG).

    The OSC system has also given a choice for

    applicants to submit development proposals

    concurrently. The time frame for the concurrent

    application is 4 months compared with the

    previous practice of consecutive submissions,

    which took 1 to 2 years for processiing.

    Additionally, one of the objectives of the OSC is

    to encourage Build Then Sell (BTS) projects in

    line with the Government’s efforts to reduce

    bureaucracy, reduce the time frame for work

    process and protect the interests of the public,

    namely property purchasers.

    The functions of the OSC CHKL are as follows:

    i. 

    To receive development proposals (32 typesof applications)

    ii. 

    Distribute complete development proposals

    to the departments for processing and to

    technical departments/agencies for

    comments;

    iii.  Monitor copies of the feedback from

    technical departments/ agencies;

    iv. 

    Monitor the submission of endorsementpapers from processing departments withiin

    the time frame given;

    v.  Receive comments from internal technical

    departments of CHKL and from external

    departments/agencies;

    vi. 

    Coordinate all comments and endorsement

    from processing departments to prepare the

    agenda for the Technical Committee One

    Stop Centre (JKTPS) and the One Stop Centre

    Committee (JKPS);

    vii. 

    Manage the meetings of the KJTPS and the

    JKPS;

    viii.  Make reports on the status of development

    applications to the JKPS;

    ix. 

    Distribute the decision of the JKPS meetingto all technical processing and evaluation

    departments;

    x.  Monitor the issuance of the decisions by

    JKTPS and JKPS by the processing

    departments within 3 days of the minutes of

    meetings.

       P   R   E   F   A   C   E

    iii  City Hall Kuala Lumpur ONE STOP CENTER (OSC) MANUAL 

  • 8/19/2019 DBKL Osc - Manual Submision of Development Proposals Through the One Stop Center (Osc)

    13/189

     

    OBJECTIVES

    The OSC Manual on Submission of

    Development Plan Application City Hall Kuala

    Lumpur has the following objectives:

      To provide the applicant (PSP/SP) as well

    as stakeholders in the property industry a

    clear and comprehensive understanding

    of the OSC implementation;

      To comply with all specified rquirements

    and indirectly facilitate the submission,

    process, asessment and decision of the

    development application;

      Provide maximum impact on the

    effectiveness of the OSC implementation

    through clear and comprehensive

    understanding by all stakeholders on thefunctions and role of the OSC, application

    procedures, evaluation criteria process to

    the decision; thereby

      Avoid delays in the process and issuance

    of decisions caused by non-compliance of

    specified requirements due to unclearunderstanding of the OSC system of CHKL

    City Hall Kuala Lumpur ONE STOP CENTER (OSC) MANUAL iv

       P   R   E   F   A   C   E

  • 8/19/2019 DBKL Osc - Manual Submision of Development Proposals Through the One Stop Center (Osc)

    14/189

     

    INTRODUCTION

    The Manual on the Submission of

    Development Plan Application through the

    OSC Secretariat City Hall Kuala Lumpur will

    be in three (3) parts:

    Part 1: Definition of Application

    Submission Divided into 3 sections which are section A, Band C:

      Section A contains submission of

    applications specifying the project

    categories, type of application by

    development and scale;

      Section B contains the list of departments

    and agencies involved in the process and

    evaluation of the proposed development;

    and

      Section C contains the Process and

    Procedure of the Development

    Application in OSC that are shown

    through flow charts by scale of

    development and type of application. 

    Part 2: Preparation of Application

    Document for SubmissionDivided into two sections, A and B.

      Section A explains the requirements for

    submission, that is the forms and checklist

    used in the OSC registration and technical

    agencies involved.

      Section B contains the schedule of fees to

    assist in the registration of application at

    the OSC counter.

    Part 3: List of Guidelines and Criteria

    for Development EvaluationDivided into 2 sections, A and B:

      Section A contains the list of guidelines

    for reference by the PSP/SP;

     

    Section B contains the evaluation criteriafor development proposals used by

    processing departments in considering

    applications for approval.

       P   R   E   F   A   C   E

    v  City Hall Kuala Lumpur ONE STOP CENTER (OSC) MANUAL 

  • 8/19/2019 DBKL Osc - Manual Submision of Development Proposals Through the One Stop Center (Osc)

    15/189

     

    CONDITIONS FOR APPLICATION

    1.0 PERSONS WHO CAN SUBMIT

    APPLICATIONS

    Principle Submitting Persons (PSP) are as follows :

    i)  A person who is a registered ARCHITECT

    under the Architect’s Act 1967 (Act 117) and

    any other laws related to the registration of

    an architect and is allowed by that law to

    practice as an architect

    ii)  An engineer who is registered as a

    PROFESSIONAL ENGINEER under the

    Engineers’ Registration Act 1967 (Act 138)

    and any other laws related to the registrationof an engineer and is allowed by that law to

    practice as an engineer.

    iii)  A BUILDING PLAN DRAUGHTSMAN who is

    registered under the Architect’s Act 1967 (Act

    117). A draughtsman has specific limitations

    under the provisions of the Act 117

    The submitting person (SP) is as follows: 

    i)  A REGISTERED TOWN PLANNERregistered under subsection 15 Town

    Planners’ Act 1995 (Act 538)

    ii)  An engineer who is registered as a

    PROFESSIONAL ENGINEER under the

    Engineers’ Registration Act 1967 (Act

    138) and any other laws related to the

    registration of an engineer and is allowedby that law to practice as an engineer.

    iii)  A LANDSCAPE ARCHITECT registered

    under the Institute of Landscape

    Architects Malaysia -ILAM

    City Hall Kuala Lumpur ONE STOP CENTER (OSC) MANUAL  1

       P   A   R   T   1    S

       E   C   T   I

       O   N    A

     

  • 8/19/2019 DBKL Osc - Manual Submision of Development Proposals Through the One Stop Center (Osc)

    16/189

     

    2.0 APPLICATIONS THAT CAN BE

    SUBMITTED TO THE OSC 

    2.1 Categories of Application

    The categories of applications that can be

    submitted to the OSC are as follows:

      Land matters

      Planning permission

      Building plan

      Engineering plan

      Landscape plan

      Other applications, and

      Submission for information and record

    2.1.1  Application on Land Matters

    An application for approval on land matters

    concerning sub-division, change of conditions and

    surrender and re-alienation, involves the

    approval from the Land and Mines Department

    Federal Territories,

    2.1.2  Application for planning permission

    Planning permission involves applications for

    approval of the layout plan, change of land use

    zoning, application to increase population density

    and application for the approval of the proposed

    development. The application for planning

    permission encompasses:

      Contour plan (for sites above 1 acre) with

    intervals of 3 meters ( 10 feet)

      Cross section plan showing hill cutting (forsites on hill slopes), and land cut & fill;

      A tree plan showing all existing trees ( with a 1

    meter girder and above, taken 0.5 meter from

    ground level) and the proposed tree cutting /

    transfer plan;

      Telecommunication layout plan;

      A building sketch plan (to be appended with

    site plan)

      Parking layout plan and accessibility for the

    disabled; and

      Stormwater Management Plan based on the

    Manual on Environmentally Friendly Drainage

    (MSMA), Guidelines by the Ministry of Housing

    and Local Government and the Drainage and

    Irrigation Department.

    2  City Hall Kuala Lumpur ONE STOP CENTER (OSC) MANUAL 

       P   A   R   T   1    S

       E   C   T   I   O

       N    A

  • 8/19/2019 DBKL Osc - Manual Submision of Development Proposals Through the One Stop Center (Osc)

    17/189

     

    2.1.3 Application for Building Plan

    The application for building plan approval

    comprises of:  Fire Security Plan;

      Sewerage system reticulation plan;

      Electricity supply plan;

      Detailed plan on waste disposal system;

      Sprinkler system plan for the building;

      Detailed plan for car parking;

      Detailed plan and report on rainwater

    management system based on MSMA; and

      Pre-construction plan (Signage plan, hoarding

    plan, application for permit on access for

    construction lorries carrying loads

    (earth/construction materials /concrete) and

    application for management of construction

    waste.

      Accessibility for the disabled shall be shownin the building plan.

    2.1.4 Application for engineering plan

    Applications for engineering plan approvals

    comprise of:

      Earthworks plan;

      Road and Drainage plan

    -  Plan showing entry point for sewerage (if

    the proposal is a single residential

    development)

    -  Master drain/ river reserve plan (if

    affected); and

      Street lighting plan.

    2.1.5 Landscape Plan Application

    An application for the approval of a landscape

    plan encompasses:  Location Plan;

      Road and Drainage layout plan

    -  Road Cross Section Detailed plan

      Landscape plan

    -  Structural planting plan for shade trees and

    palms;

    -  Shrubs planting plan and soft landscape

    plan, and-  Roof top garden plan

    2.1.6 Other applications

    Other applications encompass:

      Permit for small construction

      Temporary permit for buildings/ pre-

    construction (hoarding/ signage/ construction

    waste/ routing for lorries with construction

    material loads)

      Certificate for occupancy

      Name of Building / name of housing

    development, and

      Road naming plan

    2.1.7 

    Submission for acknowledgement andrecord

    Submission of plans for acknowledgement and

    records are:

      Sanitation plan

      Concrete Structural plan

      Notice of staged structural completion (G1-G3)

    and

      Submission of Form F (CCC)

    City Hall Kuala Lumpur ONE STOP CENTER (OSC) MANUAL  3

     

  • 8/19/2019 DBKL Osc - Manual Submision of Development Proposals Through the One Stop Center (Osc)

    18/189

     

    2.2 Types of applications

    There are 32 types of applications that can be made to the OSC.These are listed in table 1.1 

    NO CODE APPROACH CATEGORY

    1. A01 4 SERENTAK (PU+KM+PB+PJ)

    4 concurrently

    LAND MATTERS (sub-division and change of conditions)

    PLANNING PERMISSION (Development Order)

    BUILDING PLAN

    ENGINEERING PLAN (Earthwork Plan + Road and Drainage Plan+ Street Lighting Plan)

    2. A02 4 SERENTAK (PP+KM+PB+PJ)

    4 concurrently

    LAND MATTERS (Surrender and Re-alienation)

    PLANNING PERMISSION (Development Order)

    BUILDING PLAN

    ENGINEERING PLAN (Earthwork Plan + Road and Drainage Plan

    + Street Lighting Plan)

    3. A03 3 SERENTAK (PU+KM+PB)

    3 concurrently

    LAND MATTERS (sub-division and change of conditions)

    PLANNING PERMISSION (Development Order)

    BUILDING PLAN

    4. A04 3  SERENTAK (PP+KM+PB)

    3 concurrently

    LAND MATTERS (Surrender and Re-alienation)

    PLANNING PERMISSION (Development Order)

    BUILDING PLAN

    5. A05 3 SERENTAK (PU+KM+PJ)

    3 concurrently

    LAND MATTERS (sub-division and change of conditions)

    PLANNING PERMISSION (Development Order)

    ENGINEERING PLAN (Earthwork Plan + Road and Drainage Plan

    + Street Lighting Plan)

    6. A06 3 SERENTAK (PP+KM+PJ)

    3 concurrently

    LAND MATTERS (Surrender and Re-alienation)

    PLANNING PERMISSION (Development Order)

    ENGINEERING PLAN (Earthwork Plan + Road and Drainage Plan+ Street Lighting Plan)

    7. A07 3 SERENTAK (KM+ PB+ PJ)

    3 concurrently

    PLANNING PERMISSION (Development Order)

    BUILDING PLAN

    ENGINEERING PLAN (Earthwork Plan + Road and Drainage Plan

    + Street Lighting Plan)

       P   A

       R   T   1    S

       E   C   T   I   O

       N    A

    4  City Hall Kuala Lumpur ONE STOP CENTER (OSC) MANUAL 

  • 8/19/2019 DBKL Osc - Manual Submision of Development Proposals Through the One Stop Center (Osc)

    19/189

     

    NO CODE APPROACH CATEGORY

    8. A08 2 SERENTAK (PU+KM)

    2 Concurrently

    LAND MATTERS (sub-division and change of

    conditions)

    PLANNING PERMISSION (Development Order)9. A09 2 SERENTAK (PP+KM)

    2 Concurrently

    LAND MATTERS (Surrender and Re-alienation)

    PLANNING PERMISSION (Development Order)

    10. A10 2 SERENTAK (KM+ PB)

    2 Concurrently

    PLANNING PERMISSION (Development Order)

    BUILDING PLAN

    11. A11 2 SERENTAK (KM + PJ )

    2 Concurrently

    PLANNING PERMISSION (Development Order)

    ENGINEERING PLAN (Earthwork Plan + Road and

    Drainage Plan + Street Lighting Plan)

    12. A12 2 SERENTAK (PB+PJ)

    2 Concurrently

    BUILDING PLAN

    ENGINEERING PLAN (Earthwork Plan + Road andDrainage Plan + Street Lighting Plan)

    13. A13 KM / KM (DASAR)

    PLANNING PERMISSION (KM) / KM POLICY

    PLANNING PERMISSION (Development Order)

    14. A14 PJ ENGINEERING PLAN (Earthwork Plan + Road and

    Drainage Plan + Street Lighting Plan)

    15. A15 EARTHWORKS PLAN

    16. A16 ROAD AND DRAINAGE AND STREET LIGHTING PLAN

    17. A17 LANDSCAPE PLAN

    18. A18 NAMING OF DEVELOPMENT PLAN19. A19 NAMING OF ROADS PLAN

    20. A20 STREET LIGHTING PLAN

    21. A21 ROADS AND DRAINAGE PLAN

    22. A22 SERENTAK (PU) CONCURRENTLY (PU)

    23. A23 SERENTAK (PP) CONCURRENTLY (PP)

    24. A24 EARTHWORKS PLAN AND ROAD AND DRAINAGE

    PLAN

    25. B1 BUILDNG PLAN

    26. B2 SMALL CONSTRUCTION WORKS27. B3 TEMPORARY BUILDING PERMIT

    28. B4 SANITATION PLAN

    29. B5 REINFORCED CONCRETE PLAN

    30. C1 APPLICATION FOR CERTIFICATE OF OCCUPANCY

    31. D1 NOTICE FORSTAGED COMPLETION OF

    SUBSTRUCTIURE

    32. D2 REPORT OF NON COMPLIANCE WITH CCC

    City Hall Kuala Lumpur ONE STOP CENTER (OSC) MANUAL  5

    Nota : KM Planning permission

    PB Building Plan

    PU Subdivision and Change of Condition

    PJ Engineering plan (Earthworks plan + Road and drainage plan + Road lighting plan)

    PP Surrender and alienation

  • 8/19/2019 DBKL Osc - Manual Submision of Development Proposals Through the One Stop Center (Osc)

    20/189

     

    2.3 Types of development

    The types of development for each applicationhave been determined as follows:

      Housing

      Mixed development

      commercial

      industry/ manufacturing

      Institutions

      Others

    A detailed list is shown in Table 1.2 : 

    Table 1.2 : Types of development

    CODE PROJECT

    CATEGORY

    EXPLANATION

    A RESIDENTIAL Residential projects

    only

    B MIXED

    DEVELOPMENT

    Several

    types of development

    within one

    development area;

    C COMMERCIAL Commercial centre only

    D INDUSTRY/

    MANUFACTURING

    Industrial Projects/

    manufacturing only

    E INSTITUTION Public institutions suchschools, mosques and

    others.

    F OTHERS Developments other

    than

    those listed above.

    2.4 Scale of development

    To ensure faster processing, each proposeddevelopment plan shall be categorized accordingto the scale of development.

    The scale of the development will determine thedepartment/agencies that are involved inproviding comments and to forward forconsideration by the OSA committe on large,medium and small scale projects.

    The development scale is divided into 3 types:  Large scale  Medium scale  Small scale

    2.4.1 Large scale

    Large scale projects involve all applications thatinvolve planning policies, technical issues such as:

    a.  Planning permission to change the land useand increase population density.

    b.  Planning permission of one or more freestanding building blocks for commerce,industry or institution with height exceeding 5

    storeys and floorspace exceeding 5,000 squarefeet.

    c.  Development of shophouse involving:-  3 lots or more-  Height exceeding 5 storeys

    6  City Hall Kuala Lumpur ONE STOP CENTER (OSC) MANUAL 

       P   A

       R   T   1    S

       E   C   T   I   O   N    A

     

  • 8/19/2019 DBKL Osc - Manual Submision of Development Proposals Through the One Stop Center (Osc)

    21/189

    d.  Application for residential development:

    -  In conflict with the layout plan and / or

    City Plan Kuala Lumpur (PBRKL 2020).-  Applications exceeding 5 units or height

    exceeding 5 floors within areas in

    compliance with the layout.

    e.  Planning permission for the development of

    religious building.

    f.  Subdivision-  Involviing all lots in highly sensitive

    residential areas such as Bukit Tunku,

    Taman Duta, Bukit Damansara, Bukit

    Persekutuan, Bukit Bandaraya, Sungai

    Penchala, areas around the National

    Palace and Bukit Gasing

    -  Exceeding 5 residential lots for other areas

    g.  Amalgamation exceeding 4 lots

    h.  Proposed developments on slopes of class III

    and IV and other environmentally sensitive

    areas (ESAs) as set in the Planning Guidelines

    for Development in Hilly areas and Slopes

    for the Federal Territory Kuala Lumpur,

    2010.

    i.  Proposed new developments or

    redevelopments involving areas zoned as

    conservation as shown in the PBRKL2020.

     j.  Proposed additional floor to an existing

    building with a height exceeding 5 storeys

    k.  Proposed new or amendment to a public

    transportation terminal

    l.  Proposed strata development

    m.  Appeal for :

    -  A technical requirement by the OSC

    committee

    -  Notice of Refusal

    -  Development charges

    -  Any extension of payment;-  Conditions of Development Order

    n.  All applications that do not fall under medium

    or small scale developments.

    City Hall Kuala Lumpur ONE STOP CENTER (OSC) MANUAL  7

     

  • 8/19/2019 DBKL Osc - Manual Submision of Development Proposals Through the One Stop Center (Osc)

    22/189

    2.4.2 Medium Scale

    Medium scale projects involve the followingapplications:

      A proposed development that complies with

    an approved layout and is not in conflict

    with the PBRKL 2020 for the following:

    -  Residential house : 2 to 5 units AND not

    exceeding 3 storeys

    -  Shophouse: Not exceeding 2 lots AND not

    exceeding 5 storeys in height.-  A Building block (commercial, industry and

    institution not including religious use)

     Not exceeding 2 storeys

     Total floorspace not exceeding 5,000

    square feet

     Additions and changes involving a

    floorspace area not exceeding 2,000

    square feet.

      Subdivision of land not exceeding 4

    residential lots in line with the area’s

    planning guidelines except for sensitive

    areas such as Bukit Tunku, Taman Duta,

    Bukit Damansara, Bukit Persekutuan, Bukit

    Bandaraya, Sungai Penchala, areas aroundthe National Palace and Bukit Gasing.

      Amalgamation of residential lots not

    exceeding 4 lots in line with the area’s

    planning guidelines.

      Change of use of a building in line with the

    landuse zoning (eg: shop/office into budget

    hotel, private college, entertainment centreor Spa centre)

      Temporary change of use of building not in

    line with the landuse zoning (such as

    residential to restaurant, office, children’s day

    care centre and kindergarten)

      Construction of temporary buildings

      Construction of telecommunication towers

      Additional floor to an existing shophouse

    provided the total height does not exceed 5

    storeys

      Extension of Development Order

      Naming and re-naming of building or

    development scheme

      Proposal to upgrade existing building facade

      Small addition or change not including freestanding buildings

    8  City Hall Kuala Lumpur ONE STOP CENTER (OSC) MANUAL 

       P   A

       R   T   1    S

       E   C   T   I   O   N    A

     

  • 8/19/2019 DBKL Osc - Manual Submision of Development Proposals Through the One Stop Center (Osc)

    23/189

    2.4.3 Small scale 

    Small scale projects involve concurrentapplications for proposed development for

    residential buildings as follows:

      Proposed addition and change to an existing

    house and;

      A new proposal for a single residential unit;

      Proposal to demolish and rebuild a single

    house.

    2.5 Project categoryThe categories of projects can be listed below:

      Project categories based on Ministry of

    Housing and Local Government

      Special OSC Category Projects

    TABLE 1.3 : Category of project by MHLG

    CODE PROJECT

    CATEGORY

    EXPLANATION

    A ORDINARY PROJECT Projects other than code

    B,C,D,E

    B BUILD THEN SELL

    PROJECTS

    Build then sell projects

    C GOVERNMENT

    PROJECT

    Projects implemented or

    coordinated by a

    Government

    implementing agency

    D HIGH IMPACT

    PROJECTS

    Projects approved by the

    National Investment

    Committee

    E FOREIGN

    INVESTMENT

    PROJECTS

    Projects endorsed by a

    Central or state agency as

    a foreign investment

    TABLE 1.4 : OSC Special project category

    CODE PROJECTCATEGORY EXPLANATION

    A PROJECTS WITH

    CONSTRUCTION

    COSTS EXCEEDING

    RM200 MILLION

    The proposed

    development involves

    construction costs

    exceeding RM 200 million

    B DEVELOPMENT

    PROJECTS

    EXCEEDING 10

    ACRES

    Proposed development

    involving an area above

    10 acres

    C REDEVELOPMENT

    PROJECTS

    Proposed comprehensive

    re-development of an

    area

    D SPECIAL PROJECTS Proposed developments

    involving special projects

    identified by the NKEA

    Greater KL, Economic

    Planning Unit (EPU) and

    the Public private

    Cooperation Unit (UKAS)E STRATEGIC

    PROJECTS

    Projects having a national

    strategic significance

    City Hall Kuala Lumpur ONE STOP CENTER (OSC) MANUAL  9

     

  • 8/19/2019 DBKL Osc - Manual Submision of Development Proposals Through the One Stop Center (Osc)

    24/189

    DEPARTMENTS/AGENCIES

    INVOLVED

    1.0 INTERNAL AND EXTERNAL

    DEPARTMENTS / AGENCIES CITY

    HALL KUALA LUMPUR

    This section will outline the role of technical

    agencies and departments that are referred to

    obtain the endorsement and evaluation on

    applications. They comprise internal

    departments of City Hall Kuala Lumpur as well as

    external agencies.

    The list of internal technical departments and

    external agencies are:

    INTERNAL TECHNICAL DEPARTMENTS.

      Department of Town Planning (JPRB)

      Department of Physical Planning (JPF)

      Department of Urban Design and Building

    (JRBB)

      Department of Infrastructure Planning (JPIF)

      Department of Health and Environment(JKAS)

      Landscape Evaluation Unit, JPRB

    EXTERNAL TECHNICAL AGENCIES

      Federal Territory Department of Land and

    Mines (PTGWP)  Communications and Multi-Media

    Corporation Malaysia (SKMM)

      Tenaga Nasional Berhad (TNB)

      Syarikat Bekalan Air Selangor (SYABAS)

      Solid Waste Management and Public

    Cleanliness Corporation (PPSPPA)

      Indah Water Konsortium (IWK)

      Department of Minerals and Geoscience

    Malaysia (JMG)

      Department of Fire and Rescue Services

    Malaysia (JBPM)

      Department of Environment (JAS)  (when

    required) 

       P   A

       R   T   1    S

       E   C   T   I   O   N    B

     

    10  City Hall Kuala Lumpur ONE STOP CENTER (OSC) MANUAL 

     

  • 8/19/2019 DBKL Osc - Manual Submision of Development Proposals Through the One Stop Center (Osc)

    25/189

    1.1 The role of internal technical departments

    that process and comment

    The role of internal technical departments

    involved in the processing of applications is

    to prepare working documents for the

    consideration and decision of the JKTPS/JKPS

    meeting. Other than that, there are also

    internal technical departments of CHKL that

    will comment on the application. (The

    technical departments involved inprocessing applications are in Table 1.5) 

    1.2  The role of external technical

    departments/agencies that process and

    comment

    There are also external technical

    departments that process applications andothers which provide comments as input in

    the preparation of the endorsement paper

    by the processing department.

    (Departments/agencies involved in providing

    comments are shown in Table 1.6)

    1.3 Confirmation of differentdepartments

    between MHLG and CHKL

    The internal and external departments/

    agencies CHKL involved in giving commets are

    different from that of the Ministry of Housing

    and Local Government (MHLG)

    Examples of the different departments are:

      Department of Health and Environment  Department of Infrastructure Planning

      Department of Physical Planning

    City Hall Kuala Lumpur ONE STOP CENTER (OSC) MANUAL  11

     

  • 8/19/2019 DBKL Osc - Manual Submision of Development Proposals Through the One Stop Center (Osc)

    26/189

    2.0 CHECKLIST TO CONFIRM INTERNAL AND EXTERNAL DEPARTMENTS/AGENCIES

    TABLE 1.5 : LIST OF INTERNAL TECHNICAL DEPARTMENTS THAT PROCESS AND COMMENT

    NO. INTERNAL DEPARTMENTS/AGENCIES ABBREVIATION PROCESS COMMENT

    1. Planning Evaluation Unit, Department of Town

    Planning

    UPP, JPRB    

    2. Landscape Evaluation Unit, Department of Town

    Planning

    UPL, JPRB    

    3. Department of Physical Planning JPF  4. Building Control Division,

    Department of Urban Design and Buildings

    BKB, JRBB    

    5. Urban Design and Heritage Division,

    Department of Urban Design and Buildings

    BRBW, JRBB  

    6. Roads Unit, Department of Infrastructure

    Planning

    UJ, JPIF    

    7. Public Transportation Unit,

    Department of Infrastructure Planning

    UPA, JPIF  

    8. Drainage Unit,Department of Infrastructure

    Planning

    US, JPIF  

    9. Urban Cleanliness Control Division,

    Department of Health and Environment

    BKPB, JKAS  

    10. Environment Division, Department of Health and

    Environment

    BAS, JKAS  

       P   A

       R   T   1    S

       E   C   T   I   O   N    B

     

    12  City Hall Kuala Lumpur ONE STOP CENTER (OSC) MANUAL 

     

  • 8/19/2019 DBKL Osc - Manual Submision of Development Proposals Through the One Stop Center (Osc)

    27/189

    TABLE 1.6 : LIST OF EXTERNAL DEPARTMENTS/AGENCIES THAT PROCESS AND COMMENT

    NO. INTERNAL DEPARTMENTS/AGENCIES ABBREVIATION PROCESS COMMENT

    1. Federal Territory Department of Land and

    Mines

    PTG WP    

    2. Communication and Multi Media

    Corporation Malaysia

    SKMM  

    3. Tenaga Nasional Berhad TNB  

    4. Selangor Water Supply Company SYABAS  

    5. Solid Waste and Public Cleanliness

    Corporation

    PPSP&PA  

    6. Indah Water Konsortium IWK  

    7. Department of Geo Science and Minerals

    Malaysia

    JMG  

    8. Department of Fire and Rescue Services JBPM  

    TABLE 1.7: LIST OF DEPARTMENTS/AGENCIES THAT ARE REFERRED ON TYPES OF APPLICATION

    Table 1.7 shows the checklist to determine the internal and external departments/ agencies involved in

    processing development applications in the OSC CHKL.

    NO. INTERNAL DEPARTMENTS/AGENCIES ABBREVIATION PROCESS COMMENT

    1. Federal Territory Department of Land and

    Mines

    PTG WP    

    2. Communication and Multi Media

    Corporation Malaysia

    SKMM  

    3. Tenaga Nasional Berhad TNB  

    4. Selangor Water Supply Company SYABAS  

    5. Solid Waste and Public Cleanliness

    Corporation

    PPSP&PA  

    6. Indah Water Konsortium IWK  

    7. Department of Geo Science and Minerals

    Malaysia

    JMG  

    8. Department of Fire and Rescue Services JBPM  

    City Hall Kuala Lumpur ONE STOP CENTER (OSC) MANUAL  13

     

  • 8/19/2019 DBKL Osc - Manual Submision of Development Proposals Through the One Stop Center (Osc)

    28/189

    TABLE 1.8 : LIST OF DEPARTMENTS/AGENCIES THAT ARE REFERRED TO BASED ON TYPES OF APPLICATION

    NO. TECHNICAL AGENCY LAND MATTERS(124A and 204D) PLANNINGPERMISSION BUILDING PLAN

    1. Deapartment of Mineral and Geo Science Not referred  

    2. Department of Fire and Rescue Services

    Malaysia

     

    Fire Safety Plan

    3. Department of Environment Not referred (but

    will be if required

    by OSC

    Committee)

    4. Tenaga Nasional Berhad (TNB) Not referred  

    5. Communication and Multi Media

    Corporation Malaysia

     

    6. Department of Drainage and Irrigation Not referred Not referred ( but

    will be if required

    by OSC

    Committee)

    Not referred

    7. Department ofLand and Mines      

    8. Indah Water Konsortium (IWK)  

    9. Public Works Department (PWD) Not referred Not referred

    10. Solid Waste and Public Services

    Corporation

       

    System Plan

    11. Department of Town & Country Planning Not referred

    12. State Water Authority  

    13. Department of Civil Aviation  

    14. Department of Urban Planning      

    15. Department of Urban Design and

    Building

       

    14  City Hall Kuala Lumpur ONE STOP CENTER (OSC) MANUAL 

       P   A

       R   T   1    S

       E   C   T   I   O   N    B

     

  • 8/19/2019 DBKL Osc - Manual Submision of Development Proposals Through the One Stop Center (Osc)

    29/189

    ENGINEERING PLAN PLANNING PERMISSION SUBSIDIARY PLAN

    EARTHWORKS

    PLAN

    ROAD AND

    DRAINAGE PLAN

    ROAD LIGHTING

    PLAN

    LANDSCAPE

    PLAN

    BUILDING/ RESIDENTIAL

    DEVELOPMENT NAME PLAN

    ROAD NAME

    PLAN

    Not referred Not referred

    Not referred Not referred

           

    City Hall Kuala Lumpur ONE STOP CENTER (OSC) MANUAL  15

     

  • 8/19/2019 DBKL Osc - Manual Submision of Development Proposals Through the One Stop Center (Osc)

    30/189

    Continued from page 14 and 15, Table 1.8 

    NO. TECHNICAL AGENCY LAND MATTERS(124A and 204D) PLANNINGPERMISSION BUILDING PLAN

    16. Roads Unit, Department of Infrastructure

    Planning     

    17. Drainage Unit, Department of

    Infrastructure Planning 

     

    SPAH Plan

    18.Department of Infrastructure Planning  

     

    Car Parking Plan

    19. Department of Physical Planning  

    20. Landscape Evaluation Unit      

    21. Urban Design and Heritage Division JRBB    

    22. Urban Cleanliness Control Division

    Department of Health and Environment

     

    Waste residue

    23. Department of Valuation and Property

    Management 

    24. Environment Division  

       P   A

       R   T   1    S

       E   C   T   I

       O   N    B

     

    16  City Hall Kuala Lumpur ONE STOP CENTER (OSC) MANUAL 

     

  • 8/19/2019 DBKL Osc - Manual Submision of Development Proposals Through the One Stop Center (Osc)

    31/189

    ENGINEERING PLAN PLANNING PERMISSION SUBSIDIARY PLAN

    EARTHWORKS

    PLAN

    ROAD AND

    DRAINAGE PLAN

    ROAD LIGHTING

    PLAN

    LANDSCAPE

    PLAN

    BUILDING/ RESIDENTIAL

    DEVELOPMENT NAME PLAN

    ROAD NAME

    PLAN     

     

     

         

    City Hall Kuala Lumpur ONE STOP CENTER (OSC) MANUAL  17

     

  • 8/19/2019 DBKL Osc - Manual Submision of Development Proposals Through the One Stop Center (Osc)

    32/189

    DOCUMENTS THAT NEED TO BE

    SUBMITTED BASED ONAPPLICATION TYPE

    1.0 INTRODUCTION

    This section explains the documents that will be

    submitted as a checklist for the applicant

    according to the needs by DBKL, whensubmitting the application.

    Refer Table 2.1 which shows the types of

    applications and relevant documents for

    submission based on the category of

    application.

       P   A   R   T   2

        S   E   C   T   I   O   N   A

     

    City Hall Kuala Lumpur ONE STOP CENTER (OSC) MANUAL  79

  • 8/19/2019 DBKL Osc - Manual Submision of Development Proposals Through the One Stop Center (Osc)

    33/189

     

  • 8/19/2019 DBKL Osc - Manual Submision of Development Proposals Through the One Stop Center (Osc)

    34/189

    TABLE 2.1 : The list of relevant forms based on the type of application

    CODE  TYPE OF FORM BASED ON

    DEVELOPMENT/APPLICATION  

    TYPE OF APPLICATION

       4   C   O   N   C   U   R   R   E   N   T

       P   U   +   K   M   +   P   B   +   P   J    )

       4   C   O   N   C   U   R   R   E   N   T

        (   P   P   +   K   M   +   P   B   +   P   J    )

       3   C   O   N   C   U   R   R   E   N   T

        (   P   U   +   K   M   +   P   B    )

       3   C   O   N   C   U   R   R   E   N   T

        (   P   P   +   K   M   +   P   B    )

       3   C   O   N   C   U   R   R   E   N   T

        (   P   U   +   K   M   +   P   J    )

       3   C   O   N   C   U   R   R   E   N   T

        (   P   P   +   K   M   +   P   J    )

       3   C   O   N   C   U   R   R   E   N   T

        (   K   M   +   P   B   +   P   J    )

       2   C   O   N   C   U   R   R   E   N   T

        (   P   U   +   K   M    )

       2   C   O   N   C   U   R   R   E   N   T

        (   P   P   +   K   M    )

       2   C   O   N   C   U   R   R   E   N   T

        (   K   M   +   P   B    )

       2   C   O   N   C   U   R   R   E   N   T

        (   K   M   +   P   J    )

       2   C   O   N   C   U   R   R   E   N   T

        (   P   B   +   P   J    )

       P   L   A   N   N   I   N   G

       P   E   R   M   I   S   S   I   O   N

       E   N   G   I   N   E   E   R   I   N   G

       P   L   A   N   S

    A01 A02 A03 A04 A05 A06 A07 A08 A09 A10 A11 A12 A13 A14

    A.  FORM FOR LAND MATTERS

    (SUBDIVISION AND CONVERSION/

    PU) 

         

    B.  FORM FOR LAND MATTERS

    (SURRENDER AND RE-

    ALIENATION/PP)

        

     

    C.  FORM FOR PLANNING

    PERMISSION                       

    D.  FORM FOR ENGINEERING PLANS                  

    E.  FORM FOR KANDSCAPE PLAN

    F.  FORM FOR NAMING OF

    DEVELOPMENT

    G.  FORM FOR NAMING OF ROADSH.  FORM FOR BUILDING PLANS            

    I.  FORM FOR BUILDINGPLANS

    (SMALL SCALE/OSA)    

    J.  FORM FOR PERMIT APPLICATION

    K.  FORM FOR BUILDING PLANS (FOR

    RECORDS)

    L.  ISSUANCE OF CFO, FORM FOR

    THE BUILDING

    M.  FORM RELATED TO BUILDING

    PLAN TO OBTAIN COMPLETION

    AND CCC COMPLIANCE (CCC)

    N. FORM FOR ACCESSIBILITY

    STATEMENT                         

    80  City Hall Kuala Lumpur ONE STOP CENTER (OSC) MANUAL 

     

  • 8/19/2019 DBKL Osc - Manual Submision of Development Proposals Through the One Stop Center (Osc)

    35/189

    TYPE OF APPLICATION

       E   A   R   T   H   W   O   R

       K   S

       P   L   A   N

       R   O   A   D

       A   N   D   D   R   A   I   N   A   G   E

       P   L   A   N   A   N   D

       S   T   R   E   E   T

       L   I   G   H   T   I   N   G   P   L   A   N

       L   A   N   D   S   C   A   P   E

       P   L   A   N

       N   A   M   I   N   G

       O   F

       D   E   V   E   L   O   P   M   E   N   T

       P   L   A   N

       S   T   R   E   E   T

       N   A   M   E   P   L   A   N

       S   T   R   E   E   T

       L   I   G   H   T   I   N   G   P   L   A   N

       R   O   A   D

       A   N   D

       D   R   A   I   N   A   G   E

       P   L   A   N

       C   O   N   C   U   R   R   E   N   T

         (   P   U    )

       C   O   N   C   U   R   R   E   N   T

         (   P   P    )

       E   A   R   T   H   W   O   R

       K   S

       P   L   A   N

       B   U   I   L   D   I   N   G   P

       L   A   N

       S   M   A   L   L

       W   O   R   K   S   P   E   R   M   I   T

       T   E   M   P   O   R   A   R   Y

       B   U   I   L   D   I   N   G   P

       E   R   M   I   T

       S   A   N   I   T   A   T   I   O   N

       P   L   A   N

       R   E   E   N   F   O   R   C   E

       D

       C   O   N   C   R   E   T   E

       C   F   O   A   P   P   L   I   C   A   T   I   O   N

       N   O   T   I   C   E   O   F

       C   O   M   L   E   T   I   O   N

     ,

       S   T   A   G   E   D

       I   N   F   R   A   S   T   R   U   C   T   U   R   E

    A15 A16 A17 A18 A19 A20 A21 A22 A23 A24 B1 B2 B3 B4 B5 C1 D1

       

             

     

     

      

     

       

       

     

     

     

    City Hall Kuala Lumpur ONE STOP CENTER (OSC) MANUAL  81

  • 8/19/2019 DBKL Osc - Manual Submision of Development Proposals Through the One Stop Center (Osc)

    36/189

     

  • 8/19/2019 DBKL Osc - Manual Submision of Development Proposals Through the One Stop Center (Osc)

    37/189

    -  Lien holder

    -  A caveator

     Proof of ownership

     

    Individual application

    -  Copy of the identity card of the

    registered owner

    -  A copy of the Power of Attorney

    registered with the PTG - if the owner

    has delegated his powers

     Application by Registered Owner

    (Company)-  A copy of the Memorandum of

    Association

    -  Form 24 Companies Act

    -  Form 49 Companies Act

    -  A copy of the Power of Attorney

    registered with the PTG - if the owner

    has delegated his powers

     

    Application by Institute/Association/Corporation

    -  A copy of the Institute/Association/

    Corporation’s Constitution 

    -  A letter to confirm the appoitment of the

    officer who is authorized to sign on the

    application and plan.

     Trustee

    - A copy of the Trust Deed

     4 copies of the latest site photographs in 5R

    size

     Proof of current Quit Rent payment

     Copy of the Development Order (if there is

    already one)

    -  Valid letter issued by CHKL (if the

    Development Order has not been issued)

    2.1.2 Pertaining to Land Matters (Surrender and

    Realienation - PP)

    Application on land matters involves approval

    from the Federal Territory Department of Land

    and Mines on subdivision, conversion and

    surrender and re-alienation.

    i. Application Forms to be completed:

     Checklist form for application for land

    development under section 204D (Surrender

    and Realienation) National Land CodeSIMULTANEOUS or SEPARATE application. Note:

    If application involves surrender of part only (section 200 NLC),

    please complete the relevant checklist and submit together with

    Form 7D

     3 copies Form 12D Application for Surrender

    and Re-alienationNote:

    The completed form shall be made by:

     

    Company

    -  Sealed and signed by two (2) Company

    Directors provided under Companies Act

    1965

      Institute/Association/Corporations

    -  Sealed and signed by person authorized

    according to the Constitution.

     

    Trustee-  Shall be signed by the registered Board of

    Trustees

    ii. 

    Plan

     Simultaneous application

    -  10 copies draft pre-computation plan

    City Hall Kuala Lumpur ONE STOP CENTER (OSC) MANUAL  83

     

  • 8/19/2019 DBKL Osc - Manual Submision of Development Proposals Through the One Stop Center (Osc)

    38/189

     Separate application

    -  21 copies pre-computation plan certified

    by DBKL or 10 copies draft pre-

    computation plan (for applications

    already approved - development order

    yet to be issued)

     A copy of the Layout Development Order)

    that was approved by DBKL if the

    Development Order has been issued.

    iii. 

    Documents required to be submittedtogether with the application

     The latest title search/ certified copy of land

    ownership together with the plan (must be

    within the validity period of 3 months fron

    the date issued)

     Original title - to be submitted to the PTGIf

    the original title is held/ kept by the

    mortgage holder, a copy of the applicationletter to the mortgage holder to supply the

    original copy shall be apended)

     Approval letter from the stkeholders (if

    any):

    -  Mortagage holder

    -  Lease holder

    -  Lien holder

    - A caveator

     Proof of ownership

    - Individual application

     Copy of identity card

     A copy of the Power of Attorney registered

    with the PTG - if the owner has delegated

    his powers

     Application by Registered Owner (Company)

    - Copy of the Memorandum Article of

    Association

    - Form 24 Companies Act

    - Form 49 Companies Act

    - A copy of the Power of Attorney registered

    with the PTG - if the owner has delegated

    his powers

     Application by Institute/ Association/

    Corporation

    - Copy of the Institute’s/Association’s/Corporation’s Constitution 

    -  Letter certifying the signatory of the person

    authorized to sign on the application and

    plans.

     Trustee

    -  A copy of the Trust Deed

    -  4 copies of existing/ latest site photos of 5R

    size-  Proof of payment of current quit rent

    -  Copy of the development order (if there is

    one already)

    -  Letter issued by DBKL which is still valid (if

    the Development Order has not been

    issued)

    2.2 About Planning Permission

    2.2.1  Application Forms to be filled: 

     Registration Form for submission of

    development application to OSC

     Digital checklist form Planning permission

    application (FORM SKP)

       P   A

       R   T   2

        S   E   C   T   I   O   N   A

     

    84  City Hall Kuala Lumpur ONE STOP CENTER (OSC) MANUAL 

     

  • 8/19/2019 DBKL Osc - Manual Submision of Development Proposals Through the One Stop Center (Osc)

    39/189

     Document checklist form for Application for

    Planning Permission (FORM KM-01)

     Application Form for Planning Permission

    based on the type of application. Choose the

    form based on the type of application

    submitted:

    -  Form 1 Rule 2(1) - Planning permission for

    land subdivision/amalgamation

    -  Form 2 Rule 2(3) - application for change of

    land use zoning

    -  Form 3 Rule 2(3) - Application to increase

    density-  Form 3 Rule 2(3) - Change of Use of a

    Building

    -  Form 1A Rule 2(1) - Commercial Use /

    Limited Commercial Use

    -  Form 1B Rule 2(1) - Residential

    -  Form 1C Rule 2(1) - Industry

    -  Form 1E Rule 2(1) - Educational Use

    - Form 1FRule 2(1) - Institutional Use

    -  Form 1GRule 2(1) - Hotel

    -  Form 1HRule 2(1) - Petrol Station

    -  Form 1JRule 2(1) - All other uses other than

    the ones stated

    -  Application Form for the naming of the

    development scheme

     Form on Official Confirmation for

    Construction works/earthworks Form on Confirmation of Fee Payment for

    Planning Permission Process

     Form for Development Control: Buildiing

    Control Access Statement - The planning

    needs to include access from public services

    such as bus stops and commuter station to

    the nearest building and access between

    buildings. 

    2.2.2 Plan

    The number of plans to be submitted depends on

    the type of application. Choose the types of plans

    and application made based on the following list:

    i. Subdivision/ amalgamation of land

    22 copies of plans with the following

    breakdown :

     

    Plan for JPRB- 10 copies site plan with location plan

     Additional plans for the comments by

    technical agencies

    -  12 copies site plan with the location plan

    ii. Plan for the Change of Landuse zoning (for

    applications involved with the change in

    landuse only)

     

    Plan for JPRB-  12 copies site plan with location plan

    iii. 

    Plan for the increase in density (for

    applications involved in the increase in density

    only)

     Plans for JPRB

    -  12 copies site plan with location plan

    iv. Proposed Development Plan

    The number of plans to be submitted dependson the scale of the proposed development

    based on the following categories: 

     Large scale projects

    30 copies of the plan with the following

    breakdown:

    City Hall Kuala Lumpur ONE STOP CENTER (OSC) MANUAL  85

     

    A

  • 8/19/2019 DBKL Osc - Manual Submision of Development Proposals Through the One Stop Center (Osc)

    40/189

     Plans for JPRB

    -  5 copies site plan with location plan

    -  7 complete sets containing site plan,

    location plan and building sketch plan.

      Additional plans for the comments of

    technical agencies/ departments

    -  8 copies site plan with location plan

    -  10 sets complete plan containing site

    plan, location plan and building sketch

    plan.

      Medium scale projects

     Plans for JPRB

    -  5 copies site plan with location plan

    -  7 complete sets containing site plan,

    location plan and building sketch plan.

      Additional plans for the comments of

    technical agencies/ departments

    - 8 copies site plan with location plan

    -  8 complete sets containing site plan,

    location plan and building sketch plan.

     Small scale projects

     Plan for JPRB

    -  5 copies site plan with location plan

    -  7 complete sets containing site plan,

    location plan and building sketch plan.

      Additional plans for the comments of

    technical agencies/ departments

    -  5 copies site plan with location plan

    -  4 complete sets containing site plan,

    location plan and building sketch plan.

    Note:

    i. 

    All plans shall be signed by the legitimate owner and applicant

    ii.  Landsubdivision/ amalgamation plans to be signed by a registered

    Town Planner

    iii. Plans are to be folded following the plan format (title block) in

    accordance to the guidelines.

    iv. 

    For new applications of large and medium sized projects,thebuilding sketch plan shall contain:

      Landscape concept plan-  Showing the proposed hard and soft landscape concept

    layout within the development plot. This will consist of a

    central open/ green space (minimum 10%), perimeter

    planting (2m), buffer zone and roadside planting

    -  The plan shall also show:

      The type of planting proposed with the schedule, image

    and name of the specie (common name/botanical name)

      Site view drawings and cross section of the landscape

    development proposal

      Photos within and surrounding the development site.

    -  All landscape plans must be signed by a landscape

    architect registered with ILAM or any other

    authorized/ accredited body

    -  The landscape concept plans shall be in colour.

      Building design planPlan containing perspective drawings with specifications

    showing external finishes, texture and colour scheme and a site

    photograph.

      Car parking layout plan

    Plan showing the number of car parking bays, layout, internal

    traffic circulation, proposed ingress and egress, size and

    accessibility for the disabled, in particular to the nearest public

    transport facility to the proposed building.

      Stormwater Management plan for large and medium scale

    projects (all developments) based on the Environmentally

    Friendly Drainage Manual (MSMA). The layout/ site plan has to

    show:

    -  Main drain reserve, river, natural water groove and existing

    detention pond-  Location, type and size of proposed facility

    -  On site detention (OSD, RWH and other facilities) proposed)

    -  Followed by confirmation of PSP as follows:

    “I confirm the Stormwater Management provided

    and to be built comply with the Guidelines of the

    Ministry of Housing and Local Government and the

    Department of Drainage and Irrigation” 

       P   A

       R   T   2

        S   E   C   T   I   O   N   A

     

    86  City Hall Kuala Lumpur ONE STOP CENTER (OSC) MANUAL 

     

  • 8/19/2019 DBKL Osc - Manual Submision of Development Proposals Through the One Stop Center (Osc)

    41/189

      The rainwater harvesting system for small scale projects

    (Bungalow/ Semi-detached/ Terrace). The following shall be

    shown on the plan:-

    -  Mark the proposed system on the layout/ site plan

    - Location, type and size of the proposed rainwater harvestingsystem

    -  Mark on the plan the main element that shows the RWH

    system

    -  Followed by the confirmation by the PSP as follows:

    ”I confirm the Stormwater Management provided

    and to be built comply with the Guidelines of the

    Ministry of Housing and Local Government and the

    Department of Drainage and Irrigation” 

      Mark the location of the manhole and telecommunication

    cabinet on the proposed site plan and endorsed by any one of

    the Network Service Provider licenced by the Communications

    and Multi Media Corporation Malaysia (SKMM)

      Mark on the plan the refuse chamber/ solid waste collection

    centre, recycling centre and bulk waste in the proposed plan;

    For multi storey building, mark the location and size of the

    refuse chamber on every floor. The plan must also indicate the

    entry and exit and road width to the central waste collectionfacility.

      Plan for obtaining support on water supply from SYABAS (to be

    submitted for all new developments)

    -  A copy of the layout, land subdivision and amalgamation

    plan

    -  I copy of the surveyed plan certified by a registered surveyor

    to the actual temporary bench mark (TBM) in the datum

    OSD? Spot Level in the planning layout

      Pre-computation plan (for concurrent application under section

    124A and 204D)

    - 10 copies per pre-computation plan

    2.2.3 Documents required to be submitted

    together with the application:

     A copy of the land title or Sales & Purchase

    (S&P) agreement endorsed by a

    Commissioner of Oaths.

     A copy of the latest receipt for payment of

    Assessment.

     5 perspective plans showing different views

    (covering front view, right view, left view, back

    view and night lighting) to show a realistic

    image of the proposed development. The plans

    need to also illustrate developments in the

    surrounding areas with any proposed facade

    changes or new proposed amendments by

    showing all sides of the proposed building.

    Each drawing shall be on A1 size on glossypaper and mounted.

      If the development involves approval on land

    matters, please refer to the list of documents in

    paragraph 2.1

    City Hall Kuala Lumpur ONE STOP CENTER (OSC) MANUAL  87

     

    A

  • 8/19/2019 DBKL Osc - Manual Submision of Development Proposals Through the One Stop Center (Osc)

    42/189

    Note:

    Perspective drawings size A1 for large scale projects, size A2 for

    medium scale projects and size A3 for small scale projects.

      2 copies site photos size A3

      A softcopy complying with Guidelines on Digital Application

      2 surveyed plans showing clearly datum, spot level and lot

    boundary (for new developments only)

      2 contour plans on scale 3 meter (for site of more than 1 acre)

     

    2 cross section plans showing cut (for sites on hill slope), filland excavation (if affected)

      2 copies of tree plan showing existing tree ( with more than 1

    meter girth measured 0.5 meter from ground level), and

    affected by the proposed development.

      10 sets development proposal report prepared by a registered

    planner/ architect (for large and medium scale projects only)

      A copy of the receipt for fee payment in filing the application

    2.3 About Building Plans (PB))

    2.3.1 Application forms that are required to be

    filled: 

    i.  Registration of submission of development

    application form to OSC DBKL.

    ii.  Submission of Building Plans/ Structure

    Form (By Law 4(1) (c) and 15(2)) FORM A.

    iii. 

    Checklist of Document for Building Plan

    application form (FORM PB-01)

    iv.  Checklist of Building Plan (FORM DBKL-JRB-L-

    SP-01)

    v. 

    Checklist of Building Design and Lighting

    Impact (FORM OSC/BRBW-01).

    vi.  Form on acceptance of appointment of

    registered consultant engineer/architect

    responsible for design (car parking, Traffic

    flow schemes, public transportation facilities/

    pedestrian walkways/bicycle lanes/TrafficImpact analysis) (FORM JPB/KP/1(1)).

    vii. 

    Confirmation on appointment by developer/

    owner (FORM JPB/KP/1(2)) responsible for

    the supervision (car parking area, traffic flow

    scheme, public transport facility/ pedestrian

    walkways/bicycle lanes/traffic impact

    analysis).

    viii. Acceptance of appointment by registered

    consultant engineer/architect (FORM

    JPB/KP/1(3)) responsible for the supervision

    of (car parking area, traffic flow scheme,

    public transport facility/ pedestrian

    walkways/ bicycle lanes/ traffic impact

    analysis).

    ix. 

    Form for permit of transport of materials.

    x.  Checklist for rain water management system

    (SPAH) (FORM OSC/JSPS-01).

    xi. 

    Checklist for Drainage and river reserve for

    building plan (FORM OSC/JSPS-03).

       P   A   R   T   2

        S   E   C   T   I

       O   N   A

     

    88  City Hall Kuala Lumpur ONE STOP CENTER (OSC) MANUAL 

     

  • 8/19/2019 DBKL Osc - Manual Submision of Development Proposals Through the One Stop Center (Osc)

    43/189

    xii.  FORM G - Confirmation by consultant

    engineer on overall engineering works

    xiii. 

    FORM J - Confirmation on appointment of

    consultant engineer

    xiv. FORM M - Submission of drainage master

    plan/ rain water management system/

    rainwater harvesting and undertaking

    xv. 

    Checklist on solid waste requirements

    (FORM PPSPPA-PB).

    xvi. Checklist on Indah Water requirements

    (FORM IWK)

    xvii. 

    Checklist on requirements by Tenaga

    Nasional Berhad (FORM TNB)

    xviii. Checklist on Fire Prevention Plan (Form

    JBPM)

    xix. 

    Copy of confirmation of PSP that has been

    accepted by SKMM.

    xx.  Appointment of panel of contractor s for

    the disposal of construction materials(FORM BKPB-01)

    xxi. Registration of application form for

    Standard Plan for Renovation (PSU) of

    existing terrace house.

    xxii.  (FORM JPRB-PSU) - (if affecting a housing

    development scheme)

    xxiii. 

    Development Control form: Building Control

    Access Statement.

    xxiv. Checklist: Guideline on provision of facilities

    for the disabled (OKU)

    2.3.2  Plans

    i. 

    Planning permission plan approved by the

    Department of Town Planning (JPRB). (No

    need if application is made concurrently with

    the application on Planning permission).

    ii. 

    Sketch plan (size A3/A4) and tabulation of

    Gross Floor area.

    iii.  Building Plan

    a. 2 sets complete building plans signed on

    every sheet as contained in FORM A.

     Location plan (suitable scale)

     Site Plan (min. scale 1:1000)

     Floor plan (min. scale: 1:100)

     Cross section plan (min. scale: 1:100) and

     

    Elevation plan (min. scale 1:100)b.

     

    Applications for amendments to a plan

    must quote the reference number of the

    approved building plan.

    c. Accessibility Statement plan must be shown

    in the building plan.

    City Hall Kuala Lumpur ONE STOP CENTER (OSC) MANUAL  89

     

    A

  • 8/19/2019 DBKL Osc - Manual Submision of Development Proposals Through the One Stop Center (Osc)

    44/189

    iv.  Standard plans for renovation shall be

    clipped together with every building plan.

    (For new housing schemes involving semi-

    detached and terraces and titles will be

    issued saparately.

    a. Complete standard plan set

    b. Show the proposed adition and

    renovation to the semi-detached and

    terraces.

    c. 

    At least 3 alternative standard plan shall

    be submitted together with image/

    perspective drawings.

    v.  Building Design plan

    a. 

    For all new developments:

     1 set complete building plan (showing

    finishes, texture and colour scheme)

     1 set Lighting Impact plan (showing the

    location of lighting on the facade, roof,pillars, landscape and public areas)

     2 sets of perpective plans on A2 size

    showing front view, back view, right

    and left views (state also the finishes,

    testure and colour scheme) including

    for 2 standard plans.

     Show the facilities for the disabled

    incorporating the guidelines by SIRIM Comply with the design checklist (free

    standing building, terrace and multi

    storey building)

    b. For proposed addition/ change involving

    renovation of building design / facade:

     1 set complete building plan

    c. 

    Existing/ Latest photos of site and

    surrounding areas

    d. 

    Requirements for Stormwater Management

     Location, type and size of rainwater on

    site storage to be indicated on the plan;

     Confirmation by the PSP as follows:

    “I confirm the Stormwater management / Rain waterharvesting system to be provided shall be built based

    on the Guideline by the Mininstry of Housing and

    Local Government and the Department of Drainage

    and Irrigation before the CCC is issued.” 

    e. 

    Requirement on City Cleanliness

     The location for the central solid waste

    collection system to be shown on the

    building plan and certified by the PSP as

    follows:

    “I confirm the solid waste collection system that will

    be built / provided shall comply with the

    requirements of the Department of Health and

    Environment before the CCC is issued” 

       P   A   R   T   2

        S   E   C   T   I   O   N   A

     

    90  City Hall Kuala Lumpur ONE STOP CENTER (OSC) MANUAL 

     

  • 8/19/2019 DBKL Osc - Manual Submision of Development Proposals Through the One Stop Center (Osc)

    45/189

    vi.  Requirement for vehicle parking area (all

    developments requiring parking bays for

    cars/ buses, lorries/ motorcycles)

    a. 

    Location/ siting of the vehicle parkingarea to be indicated on the building plan

    and shall be certified by the PSP as

    follows:

    “I confirm the number of vehicle parking bays that

    shall be built/provided comply with the total

    number prescribed in the Development Order

    approval for this development and with theapproval by the Department of Infrastructure

    Planning before the certification of completion and

    compliance (CCC) is issued.” 

    vii.  Department of Town Planning (JPRB)

    a. One complete set of building plans. (To

    ensure the development complies with

    the planning requirements)

    viii. Land and Mines Office, Federal Territory

    (PTGWP)

    (Not required to be included if the

    development only involves amendment,

    renovation, addition and modification to the

    existing building)

    a. 

    1 set location plan and site plan for

    comments and review by PTGWP.

    (To ensure the development complies with

    the requirements on land matters

    (subdivision and conversion or surrender

    and realienation)

    ix.  Fire and Rescue Services Department (JBPM)

    (Not required if the development does not

    require Fire Department requirements) 

    a. 

    Plan, specification and documentationbased on the JBPM checklist 

    (To ensure the development complies with

    the Fire department’s requirement) 

    x.  Road Unit, Department of Infrastructure

    Planning (UJ, JPIF)

    (Not required if the development does not

    involve

    a. 1 complete set building plans

    (To ensure the development complies with

    requirements of earthworks and or road

    works & drains)

    xi. 

    Department of Civil Aviation

    (Not required if the building height does notexceed 45 meters AGL [Above Ground Level])

    a. 1 complete set building plan for JPA’s

    comments

    (To ensure buildings with a height of 45

    meter AGL and above, comply with the

    regulation on the Use of Obstace Lights])

    City Hall Kuala Lumpur ONE STOP CENTER (OSC) MANUAL  91

     

    A

  • 8/19/2019 DBKL Osc - Manual Submision of Development Proposals Through the One Stop Center (Osc)

    46/189

    xii.  Tenaga Nasional Berhad (TNB)

    (Not required if the development does not

    involve the supply of electricity or additional

    load supply)

    a. 

    Plan, specification and document based

    on TNB’s checklist 

    (To ensure the development is consistent

    with the demand for supply of electricity or

    additional load supply)

    xiii. 

    Indah Water Konsortium (IWK)

    Not required if the development involves

    amendments, renovation, addition and

    modification to the existing building or

    development that already has connections

    to the public sewerage system)

    a. 

    Plan and specification as well as

    documents based on the IWK’s checklist) 

    (To ensure the development is consistentwith the demands/ needs for a

    reticulation system and/or sewerage

    treatment plant)

    xiv. Drainage Unit, Department of Infrastructure

    Planning (US, JPIF) 

    (Not required if the development involves

    amendments, renovation, addition andmodification to the existing building)

    a. Plan and technical report on stormwater

    management based on the MSMA

    concept (Environmentally Friendly

    Drainage System Manual) for all

    developments based on the JPIF checklist.

    (to ensure the development is consistent

    with the requirements of MSMA)

    xv. 

    Public Transportation Unit, Department

    of Infrastructure Planning (UPA, JPIF)

    (Not required if the development does not

    involve the provision of vehicle parking

    bays)

    a. Plan and specification and documentation

    based on the JPIF checklist 

    (To ensure the development is consistent

    with the provision of vehicle parking

    spaces)

    xvi. 

    Landscape Assessment Unit, JPRB

    (Not required if the development is not

    required to provide open spaces, green spaces

    and landscape areas)

    a. 

    1 set Location Plan and Site Plan forevaluation by the Landscape Assessment

    Unit.

    (To ensure the development is consistent

    with the provision of open space, green and

    landscape areas)

    xvii. Solid Waste Management and Public

    Cleanliness Corporation (PPSPPA). (Not required if the development involves

    amendments, renovation, addition and

    modification to the existing building)

    a. Plan and specification and documentation

    for the solid waste chamber based on the

    checklist PPSPPA for all new developments.

       P   A   R   T   2

        S   E   C   T   I   O   N   A

     

    92  City Hall Kuala Lumpur ONE STOP CENTER (OSC) MANUAL 

     

  • 8/19/2019 DBKL Osc - Manual Submision of Development Proposals Through the One Stop Center (Osc)

    47/189

    (To ensure a consistent development with

    the provision of a collection system/solid

    waste disposal)

    xviii. 

    City Cleanliness Control Division,

    Department of Helth and the Environment

    a. Application to appoint the services of a

    contractor from the panel to manage

    construction waste based on the checklist

    by the BKPB for all developments.

    b. 

    (To ensure the development is consistent

    with the demands/need for provision of a

    container for construction waste and

    identification of a site to dispose of the

    construction waste) 

    xix. 

    Environment Control Division (BKAS),

    Department of Health and the

    Environment. (Not required if the proposedbuilding height does not exceed 60 meters

    AGL (Above Ground Level)

    a. 

    Plan and specification along with

    documents based on the checklist by

    BPAS.

    (to ensure the development is consistent

    with the demand/need for provision of

    sprinkler system for buildings with a heightof 60 meters AGL (Above Ground Level)

    2.4 Engineering Plans (PJ)

    2.4.1  Department of Infrastructure Planning (JPIF)

    i. 

    Application forms required to be completed:

    a. Applications for approval of Earthworks

     Form JKA 1:

    Form for submission of earthworks

    proposal

     Form JKA 3:

    Form for confirmation on constructionsupervisory works by the consultant

    engineer

     Form KT1:

    Form for calculation of earthworks fees

    b. Application for exemption from submission

    of earthworks plan

     

    Form JKA 1:Form for submission of earthworks

    proposal

     Form JKA 2:

    Form for exemption from Bye Law

    Requirements (FTKL) 1988. The form to

    be endorsed by the consultant engineer

    that piling works and retaining wall are

    not required. Justification for theexemption shall conform to the types of

    minor earthworks allowed as stated on

    page 2, Form JKA 2.

     FormJKA 3:

    Form for confirmation of construction

    supervision works by consultant engineer.

    City Hall Kuala Lumpur ONE STOP CENTER (OSC) MANUAL  93

     

    A

  • 8/19/2019 DBKL Osc - Manual Submision of Development Proposals Through the One Stop Center (Osc)

    48/189

    c. For the approval of main entry of

    sewerage plan

     FormJKA 1:

    Form for submission of proposed

    earthworks

     FormJKA 3:

    Form on confirmation for construction

    works supervision by consultant

    engineer.

    d. 

    Application for approval of Road and

    Drainage plan

     FormJKA 1:

    Form for submission of proposed

    earthworks plan

     FormJKA 3:

    Form for confirmation of construction

    supervision works by consultant

    engineer

    e. Application for approval of Street Lighting

    plan

     FormJKA 1:

    Form for submission of proposed

    earthworks plan

      Form JKA 3:

    Form for confirmation of constructionsupervision works by consultant

    engineer

    ii. 

    Plans

    a. 

    Application for approval of Earthworks

    plan

    Four (4) sets complete earthworks plan :

     Key plan

     Location plan

     Site layout plan

     

    Site plan must show the cut (red colour)/

    fill (blue colour), existing/proposed levels.

     Engineering Survey site plan including

    neighbouring lots.

     Detailed plans:-

    -  Cross section plan showing cut and fill

    (coloured consistent with site plan) -

    minimum 2 cross section longitudinaland 2 horizontal.

    -  Detail components (silt trap/ wash

    trough/ temporary earth drains/

    interlocking paver and others - the

    location of each component to be

    shown on the site plan.

     Piling plan (if required) - the layout of the

    piles (state the system for piling) Retaining wall plan (if required) - location

    of the retaining wall on the site plan and

    detail elements.