Data-Centric Approach for Project DeliveryMarc-Henri Cerar

January 31, 2017

Page 3: Data-Centric Approach for Project Delivery

Important

The material in this presentation has been prepared by Jacobs®.

Copyright and other intellectual property rights in this presentation vest exclusively with

Jacobs. Apart from any use permitted under applicable copyright legislation, no part of this

work may in any form or by any means (electronic, graphic, mechanical, photocopying,

recording or otherwise) be reproduced, copied, stored in a retrieval system or transmitted

without prior written permission.

Jacobs is a trademark of Jacobs Engineering Group Inc.

Copyright 2015 Jacobs Engineering Group Inc. All rights reserved.

Disclaimer

©

3

Page 4: Data-Centric Approach for Project Delivery

Presentation Topics

• About Jacobs

• Endeavour Overview

• Jacobs Data-Centric Project Delivery

• Path forward with AVEVA Engineering

• Path forward with Endeavour

• Questions

4

Page 5: Data-Centric Approach for Project Delivery

About Jacobs

• Jacobs is one of the world’s largest and most diverse providers of full-

spectrum technical, professional and construction services for

industrial, commercial and government organizations globally. The

company employs over 54,000 people and operates in more than 25

countries around the world. www.jacobs.com

Page 6: Data-Centric Approach for Project Delivery

Jacobs’ Business Lines

– Petroleum & Chemicals – serves Jacobs’ clients around the globe in oil & gas,

refining, chemicals, and mining & metals related opportunities.

– Buildings & Infrastructure – serves Jacobs’ clients around the globe in buildings

and infrastructure related opportunities.

– Aerospace & Technology – serves Jacobs’ global aerospace, defense and nuclear

clients.

– Industrial – covers inorganic chemicals, pulp & paper and manufacturing clients. The

Life Sciences global business unit is part of the Industrial line of business.

Page 7: Data-Centric Approach for Project Delivery

Endeavour OverviewIn an effort to reduce project commissioning timeline, and turn over more complete, and accurate information to the site engineering teams, some clients seek to develop maintenance packages during the project and turn over with system completion. This can be difficult due to the incomplete and often inaccurate information the project team has available. The effort to collect and manage project deliverables is known as Project Information Management (PIM).

AVEVA NET has provided the robust framework required to manage large blocks of data for PIM. It provided the Jacobs Project Information Management team with the agility and flexibility required in an ever fluid project environment.

7

Page 8: Data-Centric Approach for Project Delivery

Business Purpose and Goals

8

• Requirements Definition

• Data Integration

• Data Validation

• Data Maturity

• Deliver timely, accurate

– Data

– Drawings

– Documents

Endeavour

Integrate

Validate

Deliver

Page 9: Data-Centric Approach for Project Delivery

Data

I&C

Eng.

Database(SPI, etc.,)

Equip

Eng.

Database

Piping Eng.

Database(Lines, Valves,

Specialty Items)

3D Design(Bentley

PDS, PDMS

SP3D, etc.,)

Drawings(AutoCAD,

SPPID etc.,)

MS-Excel(Unstructured

Data, Data from

vendors,

design partners)

As-Built

Data(datasheets

etc.,)

RV

Data(Nameplate

data)

Schedule (Primavera)

Doc

Mgmt(JPI etc.,)

Procure-

Ment (JMMS,

SAP etc.,)Da

ta, D

ocs &

D

wg

s A

uth

oring

A

pp

s

Design/Data Integrity: Inconsistency Checking (across various source apps)

Design/Data Integrity: Error Reporting and Resolution (within respective source app)

Handover: Ongoing and Final Handover, Maturity Management, Data Conversion for Loading Client O&M Systems

Deviation Resolution

using RFI/Punchlist

Process

Inconsistency

Checks post IFC

En

deavo

ur

In-Progress

Docs

& Dwgs

Data, Docs, and Dwgs

Right 1st Time

Approved &

As-Built Docs

and Dwgs

Da

ta, D

ocs &

Dw

gs

use

rs &

de

live

rab

les

Commissioning(Automatically

pre-populated with

As-Specified data on

Client master forms)

O&M System

Load Files(Data Handover)

Construction QA,

Work Packages (Work Face Planning

Reports)

Automation

I/O Data

Metrics

Dashboard/Reports

>>> Pre IFC Post IFC/MC >>>

Client Requirements and Expectations(CAD Standards, Project Naming/Numbering Convention, Risk Assessments, ISO 15926, RI/Spec 1910, PIM Plan, and CMMS Load File Templates)

CM/Client

Procedures

Client Activity (Typical) Jacobs Activity (Typical)

Page 10: Data-Centric Approach for Project Delivery

Top 10 Pharmaceutical Company

10

Track Record of Success

We have strong client references, ongoing/repeat/program stories as well as client

approved savings to the tune of $1.7M on a $450M TIC project and $2.5M savings on

a $600M TIC project. These savings came in the form of labor cost avoidance

(automation), schedule acceleration and right first time (reduced rework) performance.

Page 11: Data-Centric Approach for Project Delivery

Top 10 Oil and Gas Company

11

Page 12: Data-Centric Approach for Project Delivery

Endeavour named as 2014 CIO 100 Award Winner

12

CIO magazine is a trade magazine for chief information officers and other IT leaders.

For the CIO 100 Award, companies had to demonstrate not

only that they were able to create new value using IT and to

execute their project well, but also that they did so in

uncommon, innovative ways: pioneering a new technology,

applying a familiar technology to a new purpose, setting the bar

higher for their competitors. The selection emphasized projects

that, due to their scope and impact, are helping propel

companies to a more profitable future. In short, these

organizations are technology leaders.

Page 13: Data-Centric Approach for Project Delivery

Endeavour named as 2014 CIO 100 Award Winner

13

CIO magazine is a trade magazine for chief information officers and other IT leaders.

• Locates, integrates and delivers quality-checked

engineering data via a secure Web-based viewing

portal

• Provides globally distributed engineering project

teams with one-stop access to the latest data,

reducing search time and increasing access to time-

sensitive information

Page 14: Data-Centric Approach for Project Delivery

Jacobs Data-Centric Project Delivery

• Going forward two applications will be key parts

of this strategy.

AVEVA Engineering to drive a data-centric collaboration

between disciplines which will enable greater work

efficiencies

Endeavour (AVEVA Net) will provide data alignment

across the full project spectrum of E-P-C delivery

14

Page 15: Data-Centric Approach for Project Delivery

15

Systems Map - Data-Centric ArchitectureFlexibility for Customer Specific Needs

Page 16: Data-Centric Approach for Project Delivery

Systems Map - Data-Centric Architecture

16

Page 17: Data-Centric Approach for Project Delivery

Systems Map - Data-Centric Architecture

17

Page 18: Data-Centric Approach for Project Delivery

Path Forward with AVEVA Engineering

• AVEVA Engineering is expected to become the P&C global

engineering database.

AVEVA Engineering is expected to replace Jacobs-developed legacy systems. EDB

as the engineering database in Europe with current usage over 750 users in more

than 15 offices. PDM for piping line management across offices in the America and

India.

• The deliverables to be produced include Basic Engineering Design

Data (BEDD), Datasheets, Equipment list, Speciality Items List, Line

List, Tie-In List, Instrument List, and Electrical Equipment List.

18

Page 19: Data-Centric Approach for Project Delivery

Plans/Ideas for future use of AVEVA Engineering

• Master Tag Register

• Mechanical Equipment Views

• Publish datasheets and lists for business process management

• Sub List for Heat Tracing

• Application Program Interface (API) to enable integration with other

systems and with calculation utilities

• Management of uses cases from process simulation software

• Material Selection Worksheets

19

Page 20: Data-Centric Approach for Project Delivery

Path Forward with Endeavour – Internal Focus

• Advanced Data Use

• Data Quality & Reporting

• KPIs and Metrics

• Construction & Commissioning

20

Page 21: Data-Centric Approach for Project Delivery

21

Query Page

18 Main Data View Report Templates

Page 22: Data-Centric Approach for Project Delivery

22

Query Report (colorful comparison)

18 Main Data View Report Templates

Page 23: Data-Centric Approach for Project Delivery

23

Data Quality Module

18 Main Data Quality Report Templates

Page 24: Data-Centric Approach for Project Delivery

24

Data Quality Report

18 Main Data Quality Report Templates

Page 25: Data-Centric Approach for Project Delivery

25

KPIs and Metrics

21 Main KPIs and Metrics Report Templates

Page 26: Data-Centric Approach for Project Delivery

Construction and Commissioning

26

3D Models via Web

Page 27: Data-Centric Approach for Project Delivery

27

Construction and Commissioning

Viewing P&IDs via Web with Navigation

Page 28: Data-Centric Approach for Project Delivery

28

Construction and Commissioning

Document Types Viewing

Page 29: Data-Centric Approach for Project Delivery

29

Construction and Commissioning

Customized Document Views and Navigation

Page 30: Data-Centric Approach for Project Delivery

Final Statement

Endeavour and AVEVA Engineering will provide

data alignment across the full project spectrum of

E-P-C delivery.

30

Page 32: Data-Centric Approach for Project Delivery

www.jacobs.com | worldwide10 February 2017 Jacobs© Copyright

Data-Centric Approach for Project DeliveryMarc-Henri Cerar