darshan institute of enginnering & technology · 2019-11-19 · cop of vcr system refrigeration...
TRANSCRIPT
DARSHAN INSTITUTE OF ENGINNERING &
TECHNOLOGY
Department of Mechanical Engineering
Semester – VI
Refrigeration & Air Conditioning (2161908)
List of Experiments
Sr. No.
Title Starting
Date Completion
Date Sign Grade
1
To study and calculate capacity &
COP of Vapour Compression
Refrigeration (VCR) system.
2
To study and calculate capacity and
COP of Vapour Absorption
Refrigeration (VAR) system.
3
Study of Air Conditioning system and
calculate COP of Air Conditioning
system with the help of P-H Chart.
4
To carry out Heating process of fresh
air and find out relevant parameters
of air and also plot the process on
psychrometric chart.
5
To carry out Cooling process of fresh
air and find out relevant parameters
of air and also plot the process on
psychrometric chart.
6
To carry out Heating and
humidification process and find out
relevant parameters and also plot the
process on psychrometric chart.
7
To carry out Cooling and
humidification process and find out
relevant parameters and plot the
process on psychrometric chart.
8
To carry out Cooling and
dehumidification process and find
out relevant parameters and also plot
the process on psychrometric chart.
COP of VCR System
Refrigeration and Air Conditioning (2161908) Department of Mechanical Engineering
Darshan Institute of Engineering and Technology, Rajkot
1- 1
1. STUDY OF VAPOUR COMPRESSION REFRIGERATION SYSTEM
AND CALCULATE COP OF SYSTEM WITH THE HELP OF P-H CHART.
1. Objective:
To Study Refrigeration test rig and to study the vapour compression refrigeration cycle.
2. Aim:
To calculate co-efficient of performance with the help of P-h diagram (R 134a).
3. Nomenclature: Nom Column Heading Units Type
Cos Φ Power factor Given
Cp Specific heat of water kJ/kgoC Given
(C.O.P.)Rel(b) Relative co-efficient of performance for batch operation Calculated
(C.O.P.)Rel(c) Relative co-efficient of performance for continuous operation Calculated
(C.O.P.)Th Theoretical co-efficient of performance Calculated
(C.O.P.)Act(b) Actual co-efficient of performance. for batch operation Calculated
(C.O.P.)Act(c) Actual co-efficient of performance for continuous operation Calculated
CWAct Actual compression work kJ/kg Calculated
H1 Enthalpy of refrigerant at compressor inlet kJ/kg Calculated
H2 Enthalpy of refrigerant at compressor outlet kJ/kg Calculated
H3 Enthalpy of refrigerant at condenser outlet kJ/kg Calculated
H4 Enthalpy of refrigerant at evaporator inlet kJ/kg Calculated
I Ammeter reading Amp. Measured
m(b) Mass of water for batch operation kg/sec Calculated
m(c) Mass of water for continuous operation kg/sec Calculated
W Heater Wattage KW Given
P1 Pressure at compressor suction kg/cm2 Measured
P2 Pressure at compressor discharge kg/cm2 Measured
REAct(b) Actual Refrigeration effect for batch operation kJ/sec Calculated
REAct(c) Actual Refrigeration effect for continuous operation kJ/sec Calculated
T1 Temperature at compressor suction C Measured
T2 Temperature at compressor discharge C Measured
T3 Temperature at condenser outlet C Measured
T4 Temperature at evaporator inlet C Measured
T5 Temperature of water inlet for continuous operation C Measured
T6 Temperature of water in evaporator for batch cooling / water
outlet for continuous operation C Measured
T6i Temperature of water before cooling in batch operation C Measured
t Time min Measured
V Voltmeter reading Volts Measured
COP of VCR System
Refrigeration and Air Conditioning (2161908) Department of Mechanical Engineering
Darshan Institute of Engineering and Technology, Rajkot
1-2
Vwe Volume of water in evaporator for batch cooling Ltrs Measured
Vwr Flow rate of water through evaporator for continuous cooling LPH Measured
w Density of water kg/m3 Given
4. Introduction:
Refrigeration is the branch of science that deals with the process of reducing and
maintaining the temperature of a space or material below the temperature of the
surroundings. Heat must be removed from the body being refrigerated and transferred to
another body whose temperature is below that of the refrigerated body. This is widely
used for cooling of storage chambers in which perishable foods, drinks, and medicines are
stored. The refrigeration has also wide applications in submarine ships, aircrafts.
5. Theory:
5.1 Vapour Compression Cycle: The refrigerant starts at some initial state, passes through a series of processes in a definite
sequence and returns to the initial state. This series of processes is called a cycle.
The Standard Vapour Compression Cycle (SVCC) consists of the following processes as
shown in Fig. 1.1.
Process 1-2: Reversible adiabatic compression from the saturated vapour to a super heated
vapour condition.
Process 2-3: Reversible heat rejection at constant pressure (de-superheating and
condensation of the refrigeration)
Process 3-4: Irreversible constant enthalpy expansion from high pressure saturated liquid
to a low pressure liquid and small amount of vapour.
Process 4-1: Reversible heat absorption at constant pressure from space to be cooled.
Fig. 1.1 Pressure- Enthalpy Diagram
COP of VCR System
Refrigeration and Air Conditioning (2161908) Department of Mechanical Engineering
Darshan Institute of Engineering and Technology, Rajkot
1- 3
5.2 Standard Vapour Compressor Refrigeration System:
Standard vapour compressor refrigeration system consists of following basic
components as shown in Fig. 1.2.
Fig. 1.2 Schematic diagram of Vapour Compression Refrigeration System
Compressor:
The main function of compressor is to raise the pressure and temperature of the refrigerant
by the compression of the refrigerant vapour and then pump it into the condenser.
Condenser:
Condense the vapour refrigerant into the liquid refrigerant by condenser fan and passes it
into the receiver tank for recirculation.
Capillary Tube:
It expands the liquid refrigerant at high pressure to the liquid refrigerant at low pressure
so that a measured quantity of liquid refrigerant is passed into the evaporator.
Evaporator:
Evaporates the liquid refrigerant by absorbing the heat into vapour refrigerant and sends
back into the compressor.
Drier:
A drier is used in between the condenser and expansion device. The main function of the
drier is to absorb the moisture from the liquid refrigerant and filter the dust particles.
COP of VCR System
Refrigeration and Air Conditioning (2161908) Department of Mechanical Engineering
Darshan Institute of Engineering and Technology, Rajkot
1-4
Accumulator:
An accumulator is fitted in between the evaporator and compressor. It prevents the liquid
refrigerant from entering the compressor.
Co-efficient of Performance: The coefficient of performance of (C.O.P.) of a refrigerating cycle is defined as the ratio
of net refrigeration (output) to the compressor work (input).
CW
REPOC ..
41 HHRE
12 HHCW
12
41...HH
HHPOC
6. Description:
The set up demonstrates the basic principal of a refrigeration cycle. The test rig is
designed for the study of Vapour Compression Refrigeration Cycle. The set up consist of
voltmeter, ampere meter, energy meter, rotameter, and heater. Instrumentation is done to
measure the temperature & pressure wherever necessary.
7. Utilities Required:
Electricity Supply: Single Phase, 220 V AC, 50Hz, 5-15Amp. Combined socket with
earth connection.
Water Supply @ 2 LPM at 1 Bar.
Floor Drain required.
Floor Area Required: 1.5 m x 1m
8. Experimental Procedure:
8.1 Starting Procedure (For Batch Operation):
1. For batch operation fill known amount of water in the evaporator tank.
2. Put the temperature sensor T6 in the evaporator tank.
3. Note down the reading of temperature T6i.
4. Switch ON the mains power supply.
5. Switch ON the compressor.
6. Wait for 2-3 minutes to switch ‘ON’ the compressor.
7. Open the valves provided below the pressure gauges.
8. Switch ON the pump for 30 sec after every 10 minutes.
9. After 10 minutes, note the temperature sensors reading.
10. Note down the voltage and current.
11. Note down the time.
12. Note down the reading of pressure gauges.
13. Note all the reading after every 10 minute till the temperature of water in evaporator
comes constant.
14. Repeat the experiment for different volume of water.
15. Repeat the experiment by switching ‘ON’ the heater (load condition).
COP of VCR System
Refrigeration and Air Conditioning (2161908) Department of Mechanical Engineering
Darshan Institute of Engineering and Technology, Rajkot
1- 5
8.2 Starting Procedure (For Continuous Operation):
1. For continuous operation, open the valve and drain the water.
2. Connect pipe evaporator water outlet to drain.
3. Connect water supply to rotameter.
4. Set a flow rate of water with help of valve.
5. Put the temperature sensor T6 at evaporator water outlet.
6. Switch ON the mains power supply.
7. Switch ON the compressor.
8. Wait for 2-3 minutes to switch ‘ON’ the compressor.
9. Open the valves provided below the pressure gauges.
10. After 10 minutes, note the temperature sensors reading.
11. Note down the voltage and current.
12. Note down the time.
13. Note down the reading of pressure gauges.
14. Note all the reading after every 10 minute till the temperature of water in
evaporator comes constant.
15. Repeat the experiment for different flow rates of water.
16. Repeat the experiment by switching ‘ON’ the heater (load condition).
8.3 Closing Procedure:
1. Switch ‘OFF’ the main supply.
2. Close water supply to rotameter.
3. Open the valve to drain out the water.
9. Observation & Calculations:
9.1.a Data:
Power factor Cos Φ = 0.7
Density of water w = 1000 kg/m3
Specific heat of water Cp = 4.186 kJ/kgoC
Heater Capacity W = 0.5 KW
Evaporator Tank capacity = 30 Ltrs
9.1.b Observation Table:
T6i = ______oC Water filled in Evaporator tank = ____ Ltrs
For Batch Operation
Sr.
No
t
min
P1
kg/cm2
P2
kg/cm2
T1
(oC)
T2
(oC)
T3
(oC)
T4
(oC)
T5
(oC)
T6
(oC) Vwe
V
(Volts)
I
(Amp)
NA
NA
NA
COP of VCR System
Refrigeration and Air Conditioning (2161908) Department of Mechanical Engineering
Darshan Institute of Engineering and Technology, Rajkot
1-6
9.1. Calculations:
To Calculate Cop of the System
174.404847.0}548.3)04.0{( 1111 TPTH
082.413834.0}080.3)0183.0{( 2222 TPTH
441.194662.1}225.0)005.0{( 3233 TPTH
12
41..HH
HHPOC Th
43 HH
(A) For Batch Operation:
60 1000we w
b
Vm
t
kg/sec
)( 66 TTCmRE ipbActb
kJ/sec
1000
CosIVCWAct
(kJ/sec)
Act
bAct
bActCW
REPOC .)..(
Th
Act
lPOC
POCPOC b
b ..
...)..( Re
9.1.c Observation Table:
T6i = ______oC
For Continuous Operation
Sr.
No
t
min
P1
kg/cm2
P2
kg/cm2
T1
(oC)
T2
(oC)
T3
(oC)
T4
(oC)
T5
(oC)
T6
(oC)
Vwr
(LPH)
V
(Volts)
I
(Amp)
NA
NA
NA
(B) For Continuous Operation:
1000 3600wr w
c
Vm
(kg/sec)
)( 65 TTCmRE pccAct (kJ/sec)
1000
CosIVCWAct
(kJ/sec)
Act
cAct
cActCW
REPOC .)..(
Th
Act
clPOC
POCPOC c
..
...)..( Re
COP of VCR System
Refrigeration and Air Conditioning (2161908) Department of Mechanical Engineering
Darshan Institute of Engineering and Technology, Rajkot
1- 7
For Batch Operation
COP of VCR System
Refrigeration and Air Conditioning (2161908) Department of Mechanical Engineering
Darshan Institute of Engineering and Technology, Rajkot
1-8
For Continous Operation
COP of VCR System
Refrigeration and Air Conditioning (2161908) Department of Mechanical Engineering
Darshan Institute of Engineering and Technology, Rajkot
1- 9
10. Precautions & Maintenance Instructions:
1. Never run the apparatus if power supply is less than 180 volts and above 230 volts.
2. Do not start unit, before putting the water in the evaporator.
3. During the observation do note open the evaporator.
11. Troubleshooting:
If electric panel is not showing the input on the mains light, check the main supply.
12. Conclusion:
13. References:
1. Dossat, Roy J. (2004). Principles of Refrigeration. 4th Ed. ND: Pearson Education Pvt.
Ltd. pp 102-105,118-125
2. Jordan, Richard C. & Priester, Gayle B. (1966). Refrigeration & Air Conditioning. 2nd
Ed. ND: Prientice-Hall of India Pvt. Ltd. pp 16-23,423-429.
COP of VAR System
Refrigeration and Air Conditioning (2161908) Department of Mechanical Engineering
Darshan Institute of Engineering and Technology, Rajkot
2- 1
2. TO STUDY VAPOUR ABSORPTION REFRIGERATION SYSTEM
AND CALCULATE THE COP.
1. Objective:
To study Electrolux Refrigeration system.
2. Aim:
To determine COP of Vapour absorption refrigeration system.
3. Nomenclature:
Nom Column Heading Units Type
COP Co-efficient of Performance Calculated
T1 Temperature of generator oC Measured
T2 Temperature of condenser oC Measured
T3 Temperature of evaporator oC Measured
4. Introduction:
Electrolux refrigerator is a absorption type refrigeration system. In absorption
refrigeration system the vapour is drawn from the evaporator by absorption into liquid
having high affinity for refrigerant. The refrigerant is expelled from the solution by
application of heat and its temperature is increased. This refrigerant in the vapour
form passes to the condenser where heat is rejected and the refrigerant gets liquefied.
This liquid again flows to the evaporator at reduced pressure and the cycle is
completed.
Absorber:
The main function of Absorber is the absorption of the refrigerant vapour by its weak
solution in a suitable absorbent, forming a strong solution.
Condenser:
Condenses the vapour refrigerant into the liquid by condenser fan and passes it into
the receiver tank for recirculation.
Evaporator:
Evaporates the liquid refrigerant by absorbing the heat into vapour refrigerant and
sends back to next run.
5. Theory:
The flow of fluids in the system has been shown in the Fig. 2.1 with different
shadings and the index of these shadings also indicated in diagram. Vertical boiler or
generator in which an aqua solution of ammonia can range itself from distilled water
at the bottom of the boiler to strong ammonia vapour at the surface of liquid.
A water separator which is provided to remove water vapour so that they should not
enter the condenser, get condensed there and pass on to evaporator where chocking
might occur due to its freezing. The water vapour is formed in the boiler as some of
COP of VAR System
Refrigeration and Air Conditioning (2161908) Department of Mechanical Engineering
Darshan Institute of Engineering and Technology, Rajkot
2-2
the water may evaporate on application of heat to the boiler. The separator is a jacket
with liquid ammonia at pressure of about 14 bar gauge for which the saturation
temperature is about 40 ºC.
The dehydrate ammonia gas gets condensed to liquid in the condenser and gravitates
to ‘U’ tube which acts as seal for a gas to enter the evaporator, or any gas passing
from evaporator to condenser.
Fig. 2.1 Vapour Absorption Type Refrigeration System (Three Fluid)
In the evaporator, ammonia liquid comes across an atmosphere of hydrogen at about
12-bar gauge. The plant is charged to a pressure of about 14 bar. Hence due to
Dalton’s law of partial pressure the pressure of ammonia gas should fall to about 2 bar
gauge and the saturation temperature corresponding to about 2 gauge is about –10 ºC.
The temperature surrounding the evaporator is much higher than this. Thus ammonia
evaporates and produces the refrigerating effect by absorbing the latent heat of
vaporization at 2 bar gauge and about–10 ºC from the space to be refrigerated.
In order to ensure continuous action, hydrogen gas has to be removed from ammonia
vapors. This is done in the absorber where a descending spray of very weak ammonia
COP of VAR System
Refrigeration and Air Conditioning (2161908) Department of Mechanical Engineering
Darshan Institute of Engineering and Technology, Rajkot
2- 3
solution moseys the ascending mixture of ammonia vapour and hydrogen. Ammonia
vapour is readily absorbed with evaluation of heat so that absorber has to be water
jacketed or air cooled, otherwise evaporation may take place in this unit and the
absorption may cease.
Counter flow type liquid heat exchanger is placed in between absorber and the
generator. Thus weak liquid gets cooled and strong liquid solution gets heated, thus is
economized and better thermal efficiency obtained. The strong liquid solution from
the absorber is preheated on its way to generator or boiler and the weak solution on its
way to absorber is cooled. This cooling of weak liquid solution also helps absorption
and reduces the cooling of absorber by external source.
Working:
1. Strong ammonia solution flows from the absorber vessel to the boiler.
2. When the strong ammonia solution is heated in the boiler, bubbles of ammonia as
raises.
3. The ammonia vapour passes into the condenser.
4. Weak ammonia solution flows into the tube.
5. Air circulating over the fins of the condenser cool down the vapour and
condensing it in liquid ammonia.
6. Liquid ammonia flows through the pipe to the evaporator.
7. The hydrogen in the evaporator lowers the ammonia vapour pressure and makes it
evaporate.
8. This process extracts heat from the evaporator, which in turn extracts heat from
the food storage space. Thereby the temperature inside the refrigeration is
lowered.
9. The mixture of hydrogen and ammonia passes from the evaporator to the
absorber.
10. Weak ammonia solution is fed from the boiler system.
11. As it turns to the absorber vessel, it absorbs the ammonia from the
ammonia/hydrogen mixture and gets ready for another round in the boiler.
6. Utilities Required:
1. Electricity Supply: Single Phase, 220 VAC, 50 Hz, 5-15 amp socket with earth
connection.
2. Bench Area Required: 1 m x 0.5 m.
7. Experimental Procedure:
1. Ensure that all ON / OFF switches given on the panel are at OFF position.
2. Switch ON the main supply.
3. Switch ON the refrigerator.
4. Record the temperatures when the steady state is achieved.
COP of VAR System
Refrigeration and Air Conditioning (2161908) Department of Mechanical Engineering
Darshan Institute of Engineering and Technology, Rajkot
2-4
8. Observation & Calculation:
8.1 Observation Table: SR. No. T1 (oC) T2 (oC) T3 (oC)
8.2 Calculations:
15.27315.27315.273
15.27315.27315.273
321
213
TTT
TTTCOP
9. Precaution & Maintenance Instructions:
1. Never run the apparatus if power supply is less than 180 volts & above than 230 volts.
2. Unnecessary handling of equipment should be avoided.
3. Never open the refrigerator during the experiment.
10. Troubleshooting:
1. If electric panel is not showing the input on the mains light, check the main supply.
11. Conclusion:
12. References:
1. Domkundwar, Arora (1995). A Course in Refrigeration & Air Conditioning. 5th Ed.
IND: Dhanpat Rai & CO. (P) Ltd. pp 6.4- 6.5.
COP of Air Conditioning System
Refrigeration and Air Conditioning (2161908) Department of Mechanical Engineering
Darshan Institute of Engineering and Technology, Rajkot
3- 1
3. STUDY OF AIR CONDITIONING SYSTEM AND CALCULATE COP
OF AIR CONDITIONING SYSTEM WITH THE HELP OF P-H CHART
1. Objective:
To study the vapour compression air conditioning cycle and calculate the COP of the
Air conditioning cycle.
2. Aim:
To study the Vapour Compression air conditioning cycle.
To calculate Co-efficient of performance (COP) by the use of P-H diagram (R 22).
To measure dry bulb & wet bulb temperature of inlet and outlet air.
3. Nomenclature:
Nom Column Heading Units Type
Cos Φ Power Factor Given
Cp Specific heat of water kJ/kgoC Given
C.O.P.Th Theoretical Co-efficient of performance Calculated
RE Refrigeration Effect kJ/ kg Calculated
CW Compressor Work kJ/Kg Calculated
H1 Enthalpy of refrigerant at compressor inlet kJ/ kg Calculated
H2 Enthalpy of refrigerant at compressor outlet kJ/ kg Calculated
H3 Enthalpy of refrigerant at condenser outlet kJ/ kg Calculated
H4 Enthalpy of refrigerant at evaporator inlet kJ/ kg Calculated
P1 Pressure at compressor suction kg/cm2 Measured
P2 Pressure at compressor discharge kg/cm2 Measured
T1 Temperature at compressor suction C Measured
T2 Temperature at compressor discharge C Measured
T3 Temperature at condenser outlet C Measured
T4 Temperature at evaporator inlet C Measured
Tdi Dry Bulb Temperature of air at inlet of duct C Measured
Twi Wet Bulb Temperature of air at inlet of duct C Measured
Tdo Dry Bulb Temperature of air at outlet of duct C Measured
Two Wet Bulb Temperature of air at outlet of duct C Measured
ρa Density of air kg/m3 Given
Va Velocity of air flowing through duct m/sec Measured
X1 Humidity at inlet of duct kg/kg of dry air Measured
X2 Humidity at outlet of duct kg/kg of dry air Measured
X Change in Specific Humidity kg/kg of dry air Calculated
h1 Enthalpy of air at inlet of duct kJ/kg of dry air Calculated
h2 Enthalpy of air at outlet of duct kJ/kg of dry air Calculated
COP of Air Conditioning System
Refrigeration and Air Conditioning (2161908) Department of Mechanical Engineering
Darshan Institute of Engineering and Technology, Rajkot
3-2
4. Introduction:
Air conditioning is the simultaneous control of the temperature, humidity, motion and
purity of the atmosphere in a confined space. Air conditioning applies in the heating
season as well as in the cooling season. The Air conditioning has wide applications in
submarine ships, aircrafts and rockets. Air conditioning is associated with the human
comfort and controlling the humidity ratio.
Air conditioning means "preparing the air as per required conditions of temperature,
humidity and velocity. The conditions required are different for different applications,
e.g. a small room requires air at about 24 - 26 °C where humidity control is not so
important, or a building may be air conditioned for supplying air of 24 - 26°C
temperature & 50-60 % relative humidity. Measurement rooms in factories are to be
maintained at the temperature of -20 °C. So depending upon the requirement, the air
conditioning system is designed. A complete air conditioning system has the
following jobs.
1. Filtration of air, where it contains dirt or dust particles.
2. Deodorization of air.
3. Cooling of air in summer.
4. Dehumidification of air by cooling coil itself and again heating it, as may be
required in humid areas in summer.
5. Heating of air in winter.
6. Humidifying and heating of air as may be required in winter.
7. Circulating the conditioned air through the space to be air conditioned.
An air conditioning system may be provided with some or all the units required to
perform the above jobs, which is determined by conditioning requirements and cost
aspects. A window type air conditioner provides some filtration and cooling of air. In
large buildings, cooling, heating and humidification systems may be used, along with
partial recirculation of exhaust air. This is done as it will require a huge capacity plant
to condition the whole fresh air entering the space to be conditioned. Thus some air
from the exhausted air which is at a temperature lower than the ambient temperature
is mixed with the entering fresh air. Total recirculation is generally avoided in large
installations as the exhausted air contains odors.
The Air Conditioning Test Rig comprises of the following components.
1. A conditioning unit consisting of cooling coil, heaters and humidifier
2. Fan with circulating duct.
3. Control and measurement panel
V Voltmeter Reading Volts Measured
I Ampere meter reading Amp. Measured
COP of Air Conditioning System
Refrigeration and Air Conditioning (2161908) Department of Mechanical Engineering
Darshan Institute of Engineering and Technology, Rajkot
3- 3
5. Block Diagram:
Fig. 3.1 Line Diagram of Air Conditioning Apparatus
6. Theory:
Air conditioning may be defined as the process of removing heat from a substance
under controlled conditions. It also includes the process of reducing and maintaining
the temperature of a body below the general temperature of its surroundings. This is
widely used for cooling of storage chambers in which perishable foods, drinks, and
medicines are stored.
6.1 Vapour Compression Cycle The refrigerant starts at some initial state, passes through a series of processes in a
definite sequence and returns to the initial state. This series of processes is called a cycle.
The Standard Vapour Compression Cycle (SVCC) consists of the following processes as
shown in Fig. 3.2.
Process 1-2: Reversible adiabatic compression from the saturated vapour to a super
heated vapour condition.
Process 2-3: Reversible heat rejection at constant pressure (de-superheating and
condensation of the refrigeration)
Process 3-4: Irreversible constant enthalpy expansion from high pressure saturated liquid
to a low- pressure liquid and small amount of vapour.
Process 4-1: Reversible heat absorption at constant pressure from space to be cooled.
COP of Air Conditioning System
Refrigeration and Air Conditioning (2161908) Department of Mechanical Engineering
Darshan Institute of Engineering and Technology, Rajkot
3-4
Fig. 3.2 Pressure- Enthalpy Diagram
6.2 Standard Vapour Compressor Cycle
Standard vapour compressor refrigeration system consists of following basic
components as shown in Fig. 3.3.
Fig. 3.2 Schematic diagram of Vapour Compression Refrigeration System
COP of Air Conditioning System
Refrigeration and Air Conditioning (2161908) Department of Mechanical Engineering
Darshan Institute of Engineering and Technology, Rajkot
3- 5
Compressor:
The main function of compressor is to raise the pressure and temperature of the
refrigerant by the compression of the refrigerant vapour and then pump it into the
condenser.
Condenser:
Condense the vapour refrigerant into the liquid refrigerant by condenser fan and passes it
into the receiver tank for recirculation.
Capillary Tube:
It expands the liquid refrigerant at high pressure to the liquid refrigerant at low pressure
so that a measured quantity of liquid refrigerant is passed into the evaporator.
Evaporator:
Evaporates the liquid refrigerant by absorbing the heat into vapour refrigerant and sends
back into the compressor.
Co-efficient of Performance: The coefficient of performance of (C.O.P.) of a refrigerating cycle is defined as the ratio
between net refrigeration (output) and compressor work (input).
CW
REPOC ..
41 HHRE
12 HHCW
12
41...HH
HHPOC
7. Description:
The air-conditioning test rig unit is required to conduct experiments and demonstrate
the processes of heating, cooling, heating and humidification, cooling and
dehumidification, cooling and humidification of atmospheric air. The unit consists of
a compressor. Both evaporator and the air cooled condenser are mounted on board
with separate fans. Air is sucked from the room and is supplied to the room after
conducting the different processes. The system is provided with voltmeter, ampere
meter, digital temperature indicator, air heater, steam generator. The unit will be fitted
with all instrumentation facilities so that temperature and pressure can be measured at
different points in the air-conditioning system. Steam generator is provided from
which steam comes directly to the air inlet of air conditioning which is required for
humidification purpose. Heating coil is provided for heating of air and cooling coil is
provided for cooling and dehumidification of air. Suitable valves and fittings are fitted
in the pipe line of steam. Water level indicator is provided to safe guard of heater.
8. Utilities Required:
1. Electricity Supply: Single Phase, 220 VAC, 50 Hz, 5-15 Amp. Combined socket
with earth connection.
2. Floor Area Required: 2 m x 1 m
COP of Air Conditioning System
Refrigeration and Air Conditioning (2161908) Department of Mechanical Engineering
Darshan Institute of Engineering and Technology, Rajkot
3-6
9. Experimental Procedure:
Starting Procedure:
1. Switch ‘ON’ the compressor.
2. Wait for 2-3 minutes for switch ‘ON’ the compressor.
3. Open the valves of pressure gauges.
4. After 10 minutes note down the reading of temperature sensor.
5. Note down the reading of pressure gauges.
6. Note down the reading of inlet and outlet temperature of air.
7. Note down the reading of temperature and pressure after every 10 minutes till the
temperature of outlet of air come constant.
Closing Procedure:
1. Switch off the compressor.
2. Switch off the mains power supply.
10. Observation & Calculations:
10.1 Data:
Cos Φ = 0.7
a = 1.21 kg/m3
10.2 Observation Table:
Va= …………… m/sec
Sr.
No.
t
min
P1
kg/cm2
P2
kg/cm2
T1
(C)
T2
(C)
T3
(C)
T4
(C)
Tdi
(C)
Twi
(C)
Tdo
(C)
Two
(C) V I
10.3 Calculations:
To Calculate COP of the System:
723.415)652.0()98.1011.0( 1111 TPTH
723.415)652.0()98.1011.0( 2222 TPTH
93.199228.1 33 TH
12
41..HH
HHPOC Th
43 HH
COP of Air Conditioning System
Refrigeration and Air Conditioning (2161908) Department of Mechanical Engineering
Darshan Institute of Engineering and Technology, Rajkot
3- 7
1000
CosIVCW
kJ/sec
To calculate the specific humidity X1 and enthalpy of air h1 at temperature Tdi & Twi.
__________1 X (kg/kg of dry air)
1 __________h (kJ/kg of dry air) [from psychrometric chart]
To calculate the specific humidity X2 and enthalpy of air h2 at temperature Tdo & Two
__________2 X (kg/kg of dry air)
2 __________h (kJ/kg of dry air) [from psychrometric chart]
Heat rejected from the air = Change in enthalpy of air = Refrigerating effect
R.E. = h1 – h2
= (kJ/kg of dry air)
COP of Air Conditioning System
Refrigeration and Air Conditioning (2161908) Department of Mechanical Engineering
Darshan Institute of Engineering and Technology, Rajkot
3-8
COP of Air Conditioning System
Refrigeration and Air Conditioning (2161908) Department of Mechanical Engineering
Darshan Institute of Engineering and Technology, Rajkot
3- 9
11. Precautions & Maintenance Instructions:
1. Operate the Valves gently.
2. Never run the apparatus if power supply is less than 180 volts and above 230
volts.
3. Duct should be free from dust particles.
12. Troubleshooting:
1. If electric panel is not showing the input on the mains light, check the main
supply.
2. If voltmeter showing the voltage given to heater but ampere meter does not, check
the connection of heater in control panel.
13. Conclusion:
14. References:
1. Dossat, Roy J. (2004). Principles of Refrigeration. 4th Ed. ND: Pearson Education
Pvt. Ltd. pp 125-126.
2. Jordan, Richard C. & Priester, Gayle B. (1966). Refrigeration & Air Conditioning.
2nd Ed. ND: Prientice-Hall of India Pvt. Ltd. pp 444-447,455-466.
3. S.C. Arora, S Domkundwar (1995). A Course In Refrigeration And Air
Conditioning. 5th Ed. Dhanpat Rai & Sons pp 16.1-16.24.
4. Psychometric Chart.
Sensible Heating
Refrigeration and Air Conditioning (2161908) Department of Mechanical Engineering
Darshan Institute of Engineering and Technology, Rajkot
4- 1
4. TO CARRY OUT THE HEATING PROCESS OF FRESH AIR & FIND
OUT RELEVANT PARAMETERS ON AIR CONDITIONING TEST RIG
AND TO PLOT THE PROCESS ON PSYCHROMETRIC CHART
1. Objective:
To study the heating of air in air conditioning test rig and perform experiment to
calculate the change in relevant parameters of air during heating process.
2. Aim:
To measure dry bulb & wet bulb temperature of inlet and outlet air.
Plot the process on Psychrometric chart.
Calculate the heat supplied during heating process.
3. Nomenclature:
4. Introduction:
Air conditioning means "preparing the air as per required conditions of temperature,
humidity and velocity. The conditions required are different for different applications,
e.g. a small room requires air at about 24 - 26 °C where humidity control is not so
important, or a building may be air conditioned for supplying air of 24 - 26°C
temperature & 50-60 % relative humidity. Measurement rooms in factories are to be
maintained at the temperature of -20 °C. So depending upon the requirement, the air
conditioning system is designed. A complete air conditioning system has the
following jobs.
1. Filtration of air, where it contains dirt or dust particles.
2. Deodorization of air.
3. Cooling of air in summer.
Nom Column Heading Units Type
Tdi Dry Bulb Temperature of air at inlet of duct C Measured
Twi Wet Bulb Temperature of air at inlet of duct C Measured
Tdo Dry Bulb Temperature of air at outlet of duct C Measured
Two Wet Bulb Temperature of air at outlet of duct C Measured
ρa Density of air kg/m3 Given
Va Velocity of air flowing through duct m/sec Measured
X1 Humidity at inlet of duct kg/kg of dry air Measured
X2 Humidity at outlet of duct kg/kg of dry air Measured
X Change in Specific Humidity kg/kg of dry air Calculated
h1 Enthalpy of air at inlet of duct kJ/kg of dry air Calculated
h2 Enthalpy of air at outlet of duct kJ/kg of dry air Calculated
V Voltmeter Reading Volts Measured
I Ampere meter reading Amp. Measured
Sensible Heating
Refrigeration and Air Conditioning (2161908) Department of Mechanical Engineering
Darshan Institute of Engineering and Technology, Rajkot
4-2
4. Dehumidification of air by cooling coil itself and again heating it, as may be
required in humid areas in summer.
5. Heating of air in winter.
6. Humidifying and heating of air as may be required in winter.
7. Circulating the conditioned air through the space to be air conditioned.
An air conditioning system may be provided with some or all the units required to
perform the above jobs, which is determined by conditioning requirements and cost
aspects. A window type air conditioner provides some filtration and cooling of air. In
large buildings, cooling, heating and humidification systems may be used, along with
partial recirculation of exhaust air. This is done as it will require a huge capacity plant
to condition the whole fresh air entering the space to be conditioned. Thus some air
from the exhausted air which is at a temperature lower than the ambient temperature
is mixed with the entering fresh air. Total recirculation is generally avoided in large
installations as the exhausted air contains odors.
The Air Conditioning Test Rig comprises of the following components.
1. A conditioning unit consisting of cooling coil, heaters and humidifier.
2. Fan with circulating duct.
3. Control and measurement panel.
5. Block Diagram:
Fig. 4.1 Line Diagram of Air Conditioning Apparatus
Sensible Heating
Refrigeration and Air Conditioning (2161908) Department of Mechanical Engineering
Darshan Institute of Engineering and Technology, Rajkot
4- 3
6. Theory:
The heating of air, without any change in its specific humidity, is known as sensible
heating. Let air at temperature Td1 passes over a heating coil of temperature Td3 as
shown in Fig. 4.2. It may be noted that the temperature of air leaving the heating
coil(Td2) will be less than Td3. The process of sensible heating, on the psychometric
chart, is shown by horizontal line 1-2 extending from left to right as shown in Fig. 4.2.
The point 3 represents the surface temperature of the heating coil.
The heat absorbed by the air during sensible heating may be obtained from the
psychometric chart by the enthalpy difference (h2-h1) as shown in figure. It may be
noted that the specific humidity during the sensible heating remains constant (i.e. W1
= W2). The dry bulb temperature from td1 to td2 and relative humidity Φ1 to Φ2
Heat added,
Q = h2 - h1
= Cpa(td2-td1) + Wcps(td2-td1)
Sensible heating of the air is important when the air conditioner is used as the heat
pump to heat the air. In the heat pump the air is heated by passing it over the
condenser coil or the heating coil that carry the high temperature refrigerant. In some
cases the heating of air is also done to suit different industrial and comfort air-
conditioning applications where large air conditioning systems are used.
Fig. 4.2 Sensible Heating Process on Psychrometric chart
Sensible Heating
Refrigeration and Air Conditioning (2161908) Department of Mechanical Engineering
Darshan Institute of Engineering and Technology, Rajkot
4-4
In general the sensible heating process is carried out by passing the air over the
heating coil. This coil may be heated by passing the refrigerant, the hot water, the
steam or by electric resistance heating coil. The hot water and steam are used for the
industrial applications.
Like the sensible cooling, the sensible heating process is also represented by a straight
horizontal line on the psychrometric chart. The line starts from the initial DB
temperature of air and ends at the final temperature extending towards the right (see
the figure). The sensible heating line is also the constant DP temperature line.
7. Description:
The air-conditioning test rig unit is required to conduct experiments and demonstrate
the processes of heating, cooling, heating and humidification, cooling and
dehumidification, cooling and humidification of atmospheric air. The unit consists of
a compressor. Both evaporator and the air cooled condenser are mounted on board
with separate fans. Air is sucked from the room and is supplied to the room after
conducting the different processes. The system is provided with voltmeter, ampere
meter, digital temperature indicator, air heater, steam generator. The unit will be fitted
with all instrumentation facilities so that temperature and pressure can be measured at
different points in the air-conditioning system. Steam generator is provided from
which steam comes directly to the air inlet of air conditioning which is required for
humidification purpose. Heating coil is provided for heating of air and cooling coil is
provided for cooling and dehumidification of air. Suitable valves and fittings are fitted
in the pipe line of steam. Water level indicator is provided to safe guard of heater.
8. Utilities Required:
1. Electricity Supply: Single Phase, 220 VAC, 50 Hz, 5-15 Amp. Combined socket
with earth connection.
2. Floor Area Required: 2 m x 1 m
9. Experimental Procedure:
Starting Procedure:
1. Switch ‘ON’ the main power supply.
2. Switch ‘ON’ the air heater.
3. After 10 minutes note down the temperature of ambient air by rotating sling
psychomotor and also of conditioned air by putting sling psychomotor in front of
air duct. Repeat the experiment till the temperature of outlet of air become
constant.
Closing Procedure:
1. Switch OFF the heater.
2. Switch OFF the main power supply.
Sensible Heating
Refrigeration and Air Conditioning (2161908) Department of Mechanical Engineering
Darshan Institute of Engineering and Technology, Rajkot
4- 5
10. Observation & Calculations:
10.1 Data:
Cos Φ = 0.7
a = 1.21 kg/m3
10.2 Observation Table:
Va= …………… m/sec
Sr. No. t min Tdi (C) Twi (C) Tdo (C) Two (C) V I
10.3 Calculations:
To calculate the specific humidity X1 and enthalpy of air h1 at temperature Tdi & Twi.
__________1 X (kg/kg of dry air)
1 __________h (kJ/kg of dry air) [from psychrometric chart]
To calculate the specific humidity X2 and enthalpy of air h2 at temperature Tdo & Two
__________2 X (kg/kg of dry air)
2 __________h (kJ/kg of dry air) [from psychrometric chart]
For Sensible Heating Process X1 = X2
Heat added to the air = Change in enthalpy of air
= h2 – h1
= (kJ/kg of dry air)
Sensible Heating
Refrigeration and Air Conditioning (2161908) Department of Mechanical Engineering
Darshan Institute of Engineering and Technology, Rajkot
4-6
Sensible Heating
Refrigeration and Air Conditioning (2161908) Department of Mechanical Engineering
Darshan Institute of Engineering and Technology, Rajkot
4- 7
11. Precautions & Maintenance Instructions:
1. Operate the Valves gently.
2. Never run the apparatus if power supply is less than 180 volts and above 230
volts.
3. Duct should be free from dust particles.
12. Troubleshooting:
1. If electric panel is not showing the input on the mains light, check the main
supply.
2. If voltmeter showing the voltage given to heater but ampere meter does not, check
the connection of heater in control panel.
13. Conclusion:
14. References:
1. Dossat, Roy J. (2004). Principles of Refrigeration. 4th Ed. ND: Pearson Education
Pvt. Ltd. pp 125-126.
2. Jordan, Richard C. & Priester, Gayle B. (1966). Refrigeration & Air Conditioning.
2nd Ed. ND: Prientice-Hall of India Pvt. Ltd. pp 444-447,455-466.
3. S.C. Arora, S Domkundwar (1995). A Course in Refrigeration And Air Conditioning.
5th Ed. Dhanpat Rai & Sons pp 16.1-16.24.
4. Psychometric Chart.
Sensible Cooling
Refrigeration and Air Conditioning (2161908) Department of Mechanical Engineering
Darshan Institute of Engineering and Technology, Rajkot
5- 1
5. TO CARRY OUT THE COOLING PROCESS OF FRESH AIR & FIND
OUT RELEVANT PARAMETERS ON AIR CONDITIONING TEST RIG
AND TO PLOT THE PROCESS ON PSYCHROMETRIC CHART
1. Objective:
To study the cooling of air in air conditioning test rig and perform experiment to
calculate the change in relevant parameter of air during cooling process.
2. Aim:
To measure dry bulb & wet bulb temperature of inlet and outlet air.
Plot the process on Psychrometric chart.
Calculate the heat rejected during cooling process.
3. Nomenclature:
Nom Column Heading Units Type
Cos Φ Power Factor Given
Cp Specific heat of water kJ/kgoC Given
C.O.P.Th Theoretical Co-efficient of performance Calculated
RE Refrigeration Effect kJ/ kg Calculated
CW Compressor Work KJ/Kg Calculated
H1 Enthalpy of refrigerant at compressor inlet kJ/ kg Calculated
H2 Enthalpy of refrigerant at compressor outlet kJ/ kg Calculated
H3 Enthalpy of refrigerant at condenser outlet kJ/ kg Calculated
H4 Enthalpy of refrigerant at evaporator inlet kJ/ kg Calculated
P1 Pressure at compressor suction kg/cm2 Measured
P2 Pressure at compressor discharge kg/cm2 Measured
T1 Temperature at compressor suction C Measured
T2 Temperature at compressor discharge C Measured
T3 Temperature at condenser outlet C Measured
T4 Temperature at evaporator inlet C Measured
Tdi Dry Bulb Temperature of air at inlet of duct C Measured
Twi Wet Bulb Temperature of air at inlet of duct C Measured
Tdo Dry Bulb Temperature of air at outlet of duct C Measured
Two Wet Bulb Temperature of air at outlet of duct C Measured
ρa Density of air kg/m3 Given
Va Velocity of air flowing through duct m/sec Measured
X1 Humidity at inlet of duct kg/kg of dry air Measured
X2 Humidity at outlet of duct kg/kg of dry air Measured
X Change in Specific Humidity kg/kg of dry air Calculated
h1 Enthalpy of air at inlet of duct kJ/kg of dry air Calculated
h2 Enthalpy of air at outlet of duct kJ/kg of dry air Calculated
Sensible Cooling
Refrigeration and Air Conditioning (2161908) Department of Mechanical Engineering
Darshan Institute of Engineering and Technology, Rajkot
5-2
4. Introduction:
Air conditioning means "preparing the air as per required conditions of temperature,
humidity and velocity. The conditions required are different for different applications,
e.g. a small room requires air at about 24 - 26 °C where humidity control is not so
important, or a building may be air conditioned for supplying air of 24 - 26°C
temperature & 50-60 % relative humidity. Measurement rooms in factories are to be
maintained at the temperature of -20 °C. So depending upon the requirement, the air
conditioning system is designed. A complete air conditioning system has the
following jobs.
1. Filtration of air, where it contains dirt or dust particles.
2. Deodorization of air.
3. Cooling of air in summer.
4. Dehumidification of air by cooling coil itself and again heating it, as may be
required in humid areas in summer.
5. Heating of air in winter.
6. Humidifying and heating of air as may be required in winter.
7. Circulating the conditioned air through the space to be air conditioned.
An air conditioning system may be provided with some or all the units required to
perform the above jobs, which is determined by conditioning requirements and cost
aspects. A window type air conditioner provides some filtration and cooling of air. In
large buildings, cooling, heating and humidification systems may be used, along with
partial recirculation of exhaust air. This is done as it will require a huge capacity plant
to condition the whole fresh air entering the space to be conditioned. Thus some air
from the exhausted air which is at a temperature lower than the ambient temperature
is mixed with the entering fresh air. Total recirculation is generally avoided in large
installations as the exhausted air contains odors.
The Air Conditioning Test Rig comprises of the following components.
1. A conditioning unit consisting of cooling coil, heaters and humidifier
2. Fan with circulating duct.
3. Control and measurement panel
V Voltmeter Reading Volts Measured
I Ampere meter reading Amp. Measured
Sensible Cooling
Refrigeration and Air Conditioning (2161908) Department of Mechanical Engineering
Darshan Institute of Engineering and Technology, Rajkot
5- 3
5. Block Diagram:
Fig. 5.1 Line Diagram of Air Conditioning Apparatus
6. Theory:
Cooling of the air is one of the most common psychrometric processes in the air
conditioning systems. The basic function of the air-conditioners is to cool the air
absorbed from the room or the atmosphere, which is at higher temperatures. The
sensible cooling of air is the process in which only the sensible heat of the air is
removed so as to reduce its temperature, and there is no change in the moisture
content (kg/kg of dry air) of the air. During sensible cooling process the dry bulb
(DB) temperature and wet bulb (WB) temperature of the air reduces, while the latent
heat of the air, and the dew point (DP) temperature of the air remains constant. There
is overall reduction in the enthalpy of the air.
In the ordinary window or the split air conditioner the cooling of air is carried out by
passing it over the evaporator coil, also called as the cooling coil. The room air or the
atmospheric air passes over this coil carrying the refrigerant at extremely low
temperatures, and gets cooled and passes to the space which is to be maintained at the
comfort conditions.
In general the sensible cooling process is carried out by passing the air over the coil.
In the unitary air conditioners these coils are cooled by the refrigerant passing through
them and are called also called evaporator coils. In central air conditioners these coils
are cooled by the chilled water, which is chilled by its passage through the evaporator
of the large air conditioning system. In certain cases the coil is also cooled by the
some gas passing inside it.
Sensible Cooling
Refrigeration and Air Conditioning (2161908) Department of Mechanical Engineering
Darshan Institute of Engineering and Technology, Rajkot
5-4
The sensible cooling process is represented by a straight horizontal line on the
psychrometric chart. The line starts from the initial DB temperature of the air and
ends at the final DB temperature of the air extending towards the left side from high
temperature to the low temperature (see the figure below). The sensible cooling line is
also the constant DP temperature line since the moisture content of the air remains
constant. The initial and final points on the psychrometric chart give all the properties
of the air.
Fig. 5.2 Sensible Cooling Process on Psychrometric chart
7. Description:
The air-conditioning test rig unit is required to conduct experiments and demonstrate
the processes of heating, cooling, heating and humidification, cooling and
dehumidification, cooling and humidification of atmospheric air. The unit consists of
a compressor. Both evaporator and the air cooled condenser are mounted on board
with separate fans. Air is sucked from the room and is supplied to the room after
conducting the different processes. The system is provided with voltmeter, ampere
meter, digital temperature indicator, air heater, steam generator. The unit will be fitted
with all instrumentation facilities so that temperature and pressure can be measured at
different points in the air-conditioning system. Steam generator is provided from
which steam comes directly to the air inlet of air conditioning which is required for
humidification purpose. Heating coil is provided for heating of air and cooling coil is
Sensible Cooling
Refrigeration and Air Conditioning (2161908) Department of Mechanical Engineering
Darshan Institute of Engineering and Technology, Rajkot
5- 5
provided for cooling and dehumidification of air. Suitable valves and fittings are fitted
in the pipe line of steam. Water level indicator is provided to safe guard of heater.
8. Utilities Required:
1. Electricity Supply: Single Phase, 220 VAC, 50 Hz, 5-15 Amp. Combined socket
with earth connection.
2. Floor Area Required: 2 m x 1 m
9. Experimental Procedure:
Starting Procedure:
1. Switch ‘ON’ the compressor.
2. Wait for 2-3 minutes for switch ‘ON’ the compressor.
3. Open the valves of pressure gauges.
4. After 10 minutes note down the reading of temperature sensor.
5. Note down the reading of pressure gauges.
6. Note down the reading of temperature and pressure after every 10 minutes till the
temperature of outlet of air come constant.
Closing Procedure:
1. Switch off the compressor.
2. Switch off the mains power supply.
10. Observation & Calculations:
10.1 Data:
Cos Φ = 0.7
a = 1.21 kg/m3
10.2 Observation Table:
Va= …………… m/sec
Sr.
No.
t
min
P1
kg/cm2
P2
kg/cm2
T1
(C)
T2
(C)
T3
(C)
T4
(C)
Tdi
(C)
Twi
(C)
Tdo
(C)
Two
(C) V I
10.3 Calculations:
To Calculate COP of the System:
723.415)652.0()98.1011.0( 1111 TPTH
723.415)652.0()98.1011.0( 2222 TPTH
93.199228.1 33 TH
Sensible Cooling
Refrigeration and Air Conditioning (2161908) Department of Mechanical Engineering
Darshan Institute of Engineering and Technology, Rajkot
5-6
12
41..HH
HHPOC Th
43 HH
1000
CosIVCW
KJ/sec
To calculate the specific humidity X1 and enthalpy of air h1 at temperature Tdi & Twi.
__________1 X (kg/kg of dry air)
1 __________h (kJ/kg of dry air) [from psychrometric chart]
To calculate the specific humidity X2 and enthalpy of air h2 at temperature Tdo & Two
__________2 X (kg/kg of dry air)
2 __________h (kJ/kg of dry air) [from psychrometric chart]
For Sensible Cooling Process X1 = X2
Heat rejected from the air = Change in enthalpy of air = Refrigerating effect
R.E. = h1 – h2
= (kJ/kg of dry air)
Sensible Cooling
Refrigeration and Air Conditioning (2161908) Department of Mechanical Engineering
Darshan Institute of Engineering and Technology, Rajkot
5- 7
Sensible Cooling
Refrigeration and Air Conditioning (2161908) Department of Mechanical Engineering
Darshan Institute of Engineering and Technology, Rajkot
5-8
11. Precautions & Maintenance Instructions:
1. Operate the Valves gently.
2. Never run the apparatus if power supply is less than 180 volts and above 230
volts.
3. Duct should be free from dust particles.
12. Troubleshooting:
1. If electric panel is not showing the input on the mains light, check the main
supply.
2. If voltmeter showing the voltage given to heater but ampere meter does not, check
the connection of heater in control panel.
13. Conclusion:
14. References:
1. Dossat, Roy J. (2004). Principles of Refrigeration. 4th Ed. ND: Pearson Education
Pvt. Ltd. pp 125-126.
2. Jordan, Richard C. & Priester, Gayle B. (1966). Refrigeration & Air Conditioning.
2nd Ed. ND: Prientice-Hall of India Pvt. Ltd. pp 444-447,455-466.
3. S.C. Arora, S Domkundwar (1995). A Course In Refrigeration And Air Conditioning.
5th Ed. Dhanpat Rai & Sons pp 16.1-16.24.
4. Psychometric Chart.
Heating and Humidification
Refrigeration and Air Conditioning (2161908)
Department of Mechanical Engineering
Darshan Institute of Engineering and Technology, Rajkot
6- 1
6. TO CARRY OUT THE HEATING AND HUMIDIFICATION PROCESS
OF FRESH AIR & FIND OUT RELEVANT PARAMETERS ON AIR
CONDITIONING TEST RIG AND TO PLOT THE PROCESS ON
PSYCHROMETRIC CHART
1. Objective:
To study the heating and humidification process of air in air conditioning test rig and
perform experiment to calculate the change in relevant parameter of air during
process.
2. Aim:
To measure dry bulb & wet bulb temperature of inlet and outlet air.
Plot the process on Psychrometric chart.
Calculate the heat supplied during heating process.
Calculate the amount of water vapour add during the process.
3. Nomenclature:
4. Introduction:
Air conditioning means "preparing the air as per required conditions of temperature,
humidity and velocity. The conditions required are different for different applications,
e.g. a small room requires air at about 24 - 26 °C where humidity control is not so
important, or a building may be air conditioned for supplying air of 24 - 26°C
temperature & 50-60 % relative humidity. Measurement rooms in factories are to be
maintained at the temperature of -20 °C. So depending upon the requirement, the air
conditioning system is designed. A complete air conditioning system has the
following jobs.
Nom Column Heading Units Type
Tdi Dry Bulb Temperature of air at inlet of duct C Measured
Twi Wet Bulb Temperature of air at inlet of duct C Measured
Tdo Dry Bulb Temperature of air at outlet of duct C Measured
Two Wet Bulb Temperature of air at outlet of duct C Measured
ρa Density of air kg/m3 Given
Va Velocity of air flowing through duct m/sec Measured
X1 Humidity at inlet of duct kg/kg of dry air Measured
X2 Humidity at outlet of duct kg/kg of dry air Measured
X Change in Specific Humidity kg/kg of dry air Calculated
h1 Enthalpy of air at inlet of duct kJ/kg of dry air Calculated
h2 Enthalpy of air at outlet of duct kJ/kg of dry air Calculated
V Voltmeter Reading Volts Measured
I Ampere meter reading Amp. Measured
Heating and Humidification
Refrigeration and Air Conditioning (2161908) Department of Mechanical Engineering
Darshan Institute of Engineering and Technology, Rajkot
6-2
1. Filtration of air, where it contains dirt or dust particles.
2. Deodorization of air.
3. Cooling of air in summer.
4. Dehumidification of air by cooling coil itself and again heating it, as may be
required in humid areas in summer.
5. Heating of air in winter.
6. Humidifying and heating of air as may be required in winter.
7. Circulating the conditioned air through the space to be air conditioned.
An air conditioning system may be provided with some or all the units required to
perform the above jobs, which is determined by conditioning requirements and cost
aspects. A window type air conditioner provides some filtration and cooling of air. In
large buildings, cooling, heating and humidification systems may be used, along with
partial recirculation of exhaust air. This is done as it will require a huge capacity plant
to condition the whole fresh air entering the space to be conditioned. Thus some air
from the exhausted air which is at a temperature lower than the ambient temperature
is mixed with the entering fresh air. Total recirculation is generally avoided in large
installations as the exhausted air contains odors.
The Air Conditioning Test Rig comprises of the following components.
1. A conditioning unit consisting of cooling coil, heaters and humidifier
2. Fan with circulating duct.
3. Control and measurement panel
5. Block Diagram:
Fig. 6.1 Line Diagram of Air Conditioning Apparatus
Heating and Humidification
Refrigeration and Air Conditioning (2161908)
Department of Mechanical Engineering
Darshan Institute of Engineering and Technology, Rajkot
6- 3
6. Theory:
In heating and humidification psychrometric process of the air, the dry bulb
temperature as well as the humidity of the air increases. The heating and
humidification process is carried out by passing the air over spray of water, which is
maintained at temperature higher than the dry bulb temperature of air or by mixing air
and the steam.
When the ordinary air is passed over the spray of water maintained at temperature
higher than the dry bulb temperature of the air, the moisture particles from the spray
tend to get evaporated and get absorbed in the air due to which the moisture content of
the air increase. At the same time, since the temperature of the moisture is greater
than the dry bulb temperature of the air, there is overall increase in its temperature.
During heating and humidification process the dry bulb, wet bulb, and dew point
temperature of the air increases along with its relative humidity. The heating and
humidification process is represented on the psychrometric chart by an angular line
that starts from the given value of the dry bulb temperature and extends upwards
towards right (see the Fig. 6.2 below).
Fig. 6.2 Heating and Humidification Process on Psychrometric chart
Heating and Humidification
Refrigeration and Air Conditioning (2161908) Department of Mechanical Engineering
Darshan Institute of Engineering and Technology, Rajkot
6-4
7. Description:
The air-conditioning test rig unit is required to conduct experiments and demonstrate
the processes of heating, cooling, heating and humidification, cooling and
dehumidification, cooling and humidification of atmospheric air. The unit consists of
a compressor. Both evaporator and the air cooled condenser are mounted on board
with separate fans. Air is sucked from the room and is supplied to the room after
conducting the different processes. The system is provided with voltmeter, ampere
meter, digital temperature indicator, air heater, steam generator. The unit will be fitted
with all instrumentation facilities so that temperature and pressure can be measured at
different points in the air-conditioning system. Steam generator is provided from
which steam comes directly to the air inlet of air conditioning which is required for
humidification purpose. Heating coil is provided for heating of air and cooling coil is
provided for cooling and dehumidification of air. Suitable valves and fittings are fitted
in the pipe line of steam. Water level indicator is provided to safe guard of heater.
8. Utilities Required:
1. Electricity Supply: Single Phase, 220 VAC, 50 Hz, 5-15 Amp. Combined socket
with earth connection.
2. Floor Area Required: 2 m x 1 m
9. Experimental Procedure:
Starting Procedure:
1. Switch ‘ON’ the main power supply.
2. Switch ‘ON’ the air heater.
3. Allow steam to pass through the pipe and slowly open the wet steam vent valve to
release wet steam from the pipe.
4. Close the wet steam vent valve.
5. Rotate psychrometer and note down the ambient temperature of air.
6. After 10 minutes note down the temperature of air by putting sling psychrometrer
in front of air duct.
7. Note down the reading of pressure gauges and temperature sensors.
8. Repeat the experiment till the temperature of outlet of air become constant
Closing Procedure:
1. Switch OFF the heater.
2. Stop steam supply by closing the steam valve.
3. Switch OFF the main power supply.
10. Observation & Calculations:
10.1 Data:
Cos Φ = 0.7
a = 1.21 kg/m3
Heating and Humidification
Refrigeration and Air Conditioning (2161908)
Department of Mechanical Engineering
Darshan Institute of Engineering and Technology, Rajkot
6- 5
10.2 Observation Table:
Va= …………… m/sec
Sr. No. t (min) Tdi (C) Twi (C) Tdo (C) Two (C) V I
10.3 Calculations:
To calculate the specific humidity X1 and enthalpy of air h1 at temperature Tdi & Twi.
__________1 X (kg/kg of dry air)
1 __________h (kJ/kg of dry air) [from psychrometric chart]
To calculate the specific humidity X2 and enthalpy of air h2 at temperature Tdo & Two
__________2 X (kg/kg of dry air)
2 __________h (kJ/kg of dry air) [from psychrometric chart]
Amount of water vapour added to air = 12 XXX
= (kg/kg of dry air)
Heat added to the air = Change in enthalpy of air
= h2 – h1
= (kJ/kg of dry air)
Heating and Humidification
Refrigeration and Air Conditioning (2161908) Department of Mechanical Engineering
Darshan Institute of Engineering and Technology, Rajkot
6-6
Heating and Humidification
Refrigeration and Air Conditioning (2161908)
Department of Mechanical Engineering
Darshan Institute of Engineering and Technology, Rajkot
6- 7
11. Precautions & Maintenance Instructions:
1. Operate the Valves gently.
2. Never run the apparatus if power supply is less than 180 volts and above 230
volts.
3. Duct should be free from dust particles.
12. Troubleshooting:
1. If electric panel is not showing the input on the mains light, check the main
supply.
2. If voltmeter showing the voltage given to heater but ampere meter does not, check
the connection of heater in control panel.
13. Conclusion:
14. References:
1. Dossat, Roy J. (2004). Principles of Refrigeration. 4th Ed. ND: Pearson Education
Pvt. Ltd. pp 125-126.
2. Jordan, Richard C. & Priester, Gayle B. (1966). Refrigeration & Air Conditioning.
2nd Ed. ND: Prientice-Hall of India Pvt. Ltd. pp 444-447,455-466.
3. S.C. Arora, S Domkundwar (1995). A Course In Refrigeration And Air Conditioning.
5th Ed. Dhanpat Rai & Sons pp 16.1-16.24.
4. Psychometric Chart.
Cooling and Humidification
Refrigeration and Air Conditioning (2161908) Department of Mechanical Engineering
Darshan Institute of Engineering and Technology, Rajkot
7- 1
7. TO CARRY OUT THE COOLING AND HUMIDIFICATION PROCESS
OF FRESH AIR & FIND OUT RELEVANT PARAMETERS ON AIR
CONDITIONING TEST RIG AND TO PLOT THE PROCESS ON
PSYCHROMETRIC CHART
1. Objective:
To study the cooling and humidification process of air in air conditioning test rig and
perform experiment to calculate the change in relevant parameter of air during
process.
2. Aim:
To measure dry bulb & wet bulb temperature of inlet and outlet air.
Plot the process on Psychrometric chart.
Calculate the heat rejected during process.
Calculate the amount of water vapour add during the process.
3. Nomenclature:
Nom Column Heading Units Type
Cos Φ Power Factor Given
Cp Specific heat of water kJ/kgoC Given
C.O.P.Th Theoretical Co-efficient of performance Calculated
RE Refrigeration Effect kJ/ kg Calculated
CW Compressor Work kJ/Kg Calculated
H1 Enthalpy of refrigerant at compressor inlet kJ/ kg Calculated
H2 Enthalpy of refrigerant at compressor outlet kJ/ kg Calculated
H3 Enthalpy of refrigerant at condenser outlet kJ/ kg Calculated
H4 Enthalpy of refrigerant at evaporator inlet kJ/ kg Calculated
P1 Pressure at compressor suction kg/cm2 Measured
P2 Pressure at compressor discharge kg/cm2 Measured
T1 Temperature at compressor suction C Measured
T2 Temperature at compressor discharge C Measured
T3 Temperature at condenser outlet C Measured
T4 Temperature at evaporator inlet C Measured
Tdi Dry Bulb Temperature of air at inlet of duct C Measured
Twi Wet Bulb Temperature of air at inlet of duct C Measured
Tdo Dry Bulb Temperature of air at outlet of duct C Measured
Two Wet Bulb Temperature of air at outlet of duct C Measured
ρa Density of air kg/m3 Given
Va Velocity of air flowing through duct m/sec Measured
X1 Humidity at inlet of duct kg/kg of dry air Measured
X2 Humidity at outlet of duct kg/kg of dry air Measured
Cooling and Humidification
Refrigeration and Air Conditioning (2161908) Department of Mechanical Engineering
Darshan Institute of Engineering and Technology, Rajkot
7-2
4. Introduction:
Air conditioning means "preparing the air as per required conditions of temperature,
humidity and velocity. The conditions required are different for different applications,
e.g. a small room requires air at about 24 - 26 °C where humidity control is not so
important, or a building may be air conditioned for supplying air of 24 - 26°C
temperature & 50-60 % relative humidity. Measurement rooms in factories are to be
maintained at the temperature of -20 °C. So depending upon the requirement, the air
conditioning system is designed. A complete air conditioning system has the
following jobs.
1. Filtration of air, where it contains dirt or dust particles.
2. Deodorization of air.
3. Cooling of air in summer.
4. Dehumidification of air by cooling coil itself and again heating it, as may be
required in humid areas in summer.
5. Heating of air in winter.
6. Humidifying and heating of air as may be required in winter.
7. Circulating the conditioned air through the space to be air conditioned.
An air conditioning system may be provided with some or all the units required to
perform the above jobs, which is determined by conditioning requirements and cost
aspects. A window type air conditioner provides some filtration and cooling of air. In
large buildings, cooling, heating and humidification systems may be used, along with
partial recirculation of exhaust air. This is done as it will require a huge capacity plant
to condition the whole fresh air entering the space to be conditioned. Thus some air
from the exhausted air which is at a temperature lower than the ambient temperature
is mixed with the entering fresh air. Total recirculation is generally avoided in large
installations as the exhausted air contains odors.
The Air Conditioning Test Rig comprises of the following components.
1. A conditioning unit consisting of cooling coil, heaters and humidifier
2. Fan with circulating duct.
3. Control and measurement panel
X Change in Specific Humidity kg/kg of dry air Calculated
h1 Enthalpy of air at inlet of duct kJ/kg of dry air Calculated
h2 Enthalpy of air at outlet of duct kJ/kg of dry air Calculated
V Voltmeter Reading Volts Measured
I Ampere meter reading Amp. Measured
Cooling and Humidification
Refrigeration and Air Conditioning (2161908) Department of Mechanical Engineering
Darshan Institute of Engineering and Technology, Rajkot
7- 3
5. Block Diagram:
Fig. 7.1 Line Diagram of Air Conditioning Apparatus
6. Theory:
Cooling and humidification process is one of the most commonly used air
conditioning application for the cooling purposes. In this process the moisture is
added to the air by passing it over the stream or spray of water which is at temperature
lower than the dry bulb temperature of the air. When the ordinary air passes over the
stream of water, the particles of water present within the stream tend to get evaporated
by giving up the heat to the stream. The evaporated water is absorbed by the air so its
moisture content, thus the humidity increases. At the same time, since the temperature
of the absorbed moisture is less than the DB bulb temperature of the air, there is
reduction in the overall temperature of the air. Since the heat is released in the stream
or spray of water, its temperature increases.
One of the most popular applications of cooling and humidification is the evaporative
cooler, also called as the desert cooler. The evaporative cooler is the sort of big box
inside which is a small water tank, small water pump and the fan. The water from the
tank is circulated by the pump and is also sprayed inside the box. The fan blows
strong currents of air over the water sprays, thus cooling the air and humidifying it
simultaneously. The evaporative cooler is highly effective cooling devise having very
low initial and running cost compared to the unitary air conditioners. For cooling
purposes, the cooling and humidification process can be used only in dry and hot
climates like desert areas, countries like India, China, Africa etc. This cooling process
cannot be used in hot and high humidity climates.
Cooling and Humidification
Refrigeration and Air Conditioning (2161908) Department of Mechanical Engineering
Darshan Institute of Engineering and Technology, Rajkot
7-4
The cooling and humidification process is also used in various industries like textile,
where certain level of temperature and moisture content has to be maintained. In such
cases large quantity of water is sprayed, and large blowers are used to blow the air
over the spray of water.
During the cooling and humidification process the dry bulb of the air reduces, its wet
bulb and the dew point temperature increases, while its moisture content and thus the
relative humidity also increases. Also, the sensible heat of the air reduces, while the
latent heat of the air increases resulting in the overall increase in the enthalpy of the
air.
Cooling and humidification process is represented by an angular line on the
psychrometric chart starting from the given value of the dry bulb temperature and the
relative humidity and extending upwards toward left.
Fig. 7.2 Cooling and Humidification Process on Psychrometric chart
7. Description:
The air-conditioning test rig unit is required to conduct experiments and demonstrate
the processes of heating, cooling, heating and humidification, cooling and
dehumidification, cooling and humidification of atmospheric air. The unit consists of
a compressor. Both evaporator and the air cooled condenser are mounted on board
with separate fans. Air is sucked from the room and is supplied to the room after
conducting the different processes. The system is provided with voltmeter, ampere
Cooling and Humidification
Refrigeration and Air Conditioning (2161908) Department of Mechanical Engineering
Darshan Institute of Engineering and Technology, Rajkot
7- 5
meter, digital temperature indicator, air heater, steam generator. The unit will be fitted
with all instrumentation facilities so that temperature and pressure can be measured at
different points in the air-conditioning system. Steam generator is provided from
which steam comes directly to the air inlet of air conditioning which is required for
humidification purpose. Heating coil is provided for heating of air and cooling coil is
provided for cooling and dehumidification of air. Suitable valves and fittings are fitted
in the pipe line of steam. Water level indicator is provided to safe guard of heater.
8. Utilities Required:
1. Electricity Supply: Single Phase, 220 VAC, 50 Hz, 5-15 Amp. Combined socket
with earth connection.
2. Floor Area Required: 2 m x 1 m
9. Experimental Procedure:
Starting Procedure:
1. Switch ‘ON’ the main power supply.
2. Switch ‘ON’ the compressor.
3. Wait for 2-3 minutes for switch ‘ON’ the compressor.
4. Open the valves of pressure gauges.
5. Allow steam to pass through the pipe and slowly open the wet steam vent valve to
release wet steam from the pipe.
6. Close the wet steam vent valve.
7. Rotate psychrometer and note down the ambient temperature of air.
8. After 10 minutes note down the temperature of air by putting sling psychrometrer
in front of air duct.
9. Note down the reading of pressure gauges and temperature sensors.
10. Repeat the experiment till the temperature of outlet of air become constant.
Closing Procedure:
1. Switch OFF the compressor.
2. Stop steam supply by closing the steam valve.
3. Switch OFF the main power supply.
10. Observation & Calculations:
10.1 Data:
Cos Φ = 0.7
a = 1.21 kg/m3
Cooling and Humidification
Refrigeration and Air Conditioning (2161908) Department of Mechanical Engineering
Darshan Institute of Engineering and Technology, Rajkot
7-6
10.2 Observation Table:
Va= …………… m/sec
Sr.
No.
t
(min)
P1
kg/cm2
P2
kg/cm2
T1
(C)
T2
(C)
T3
(C)
T4
(C)
Tdi
(C)
Twi
(C)
Tdo
(C)
Two
(C) V I
10.3 Calculations:
To Calculate COP of the System:
723.415)652.0()98.1011.0( 1111 TPTH
723.415)652.0()98.1011.0( 2222 TPTH
93.199228.1 33 TH
12
41..HH
HHPOC Th
43 HH
1000
CosIVCW
kJ/sec
To calculate the specific humidity X1 and enthalpy of air h1 at temperature Tdi & Twi.
__________1 X (kg/kg of dry air)
1 __________h (kJ/kg of dry air) [from psychrometric chart]
To calculate the specific humidity X2 and enthalpy of air h2 at temperature Tdo & Two
__________2 X (kg/kg of dry air)
2 __________h (kJ/kg of dry air) [from psychrometric chart]
Amount of water vapour added to air = 12 XXX
= (kg/kg of dry air)
Heat rejected from the air = Change in enthalpy of air = Refrigerating effect
R.E. = ∆h
= (kJ/kg of dry air)
Cooling and Humidification
Refrigeration and Air Conditioning (2161908) Department of Mechanical Engineering
Darshan Institute of Engineering and Technology, Rajkot
7- 7
Cooling and Humidification
Refrigeration and Air Conditioning (2161908) Department of Mechanical Engineering
Darshan Institute of Engineering and Technology, Rajkot
7-8
11. Precautions & Maintenance Instructions:
1. Operate the Valves gently.
2. Never run the apparatus if power supply is less than 180 volts and above 230
volts.
3. Duct should be free from dust particles.
12. Troubleshooting:
1. If electric panel is not showing the input on the mains light, check the main
supply.
2. If voltmeter showing the voltage given to heater but ampere meter does not, check
the connection of heater in control panel.
13. Conclusion:
14. References:
1. Dossat, Roy J. (2004). Principles of Refrigeration. 4th Ed. ND: Pearson Education
Pvt. Ltd. pp 125-126.
2. Jordan, Richard C. & Priester, Gayle B. (1966). Refrigeration & Air Conditioning.
2nd Ed. ND: Prientice-Hall of India Pvt. Ltd. pp 444-447,455-466.
3. S.C. Arora, S Domkundwar (1995). A Course In Refrigeration And Air Conditioning.
5th Ed. Dhanpat Rai & Sons pp 16.1-16.24.
4. Psychometric Chart.
Cooling and Dehumidification
Refrigeration and Air Conditioning (2161908) Department of Mechanical Engineering
Darshan Institute of Engineering and Technology, Rajkot
8- 1
8. TO CARRY OUT THE COOLING AND DEHUMIDIFICATION
PROCESS OF FRESH AIR & FIND OUT RELEVANT PARAMETERS ON
AIR CONDITIONING TEST RIG AND TO PLOT THE PROCESS ON
PSYCHROMETRIC CHART
1. Objective:
To study the cooling and dehumidification process of air in air conditioning test rig
and perform experiment to calculate the change in relevant parameter of air during
process.
2. Aim:
To measure dry bulb & wet bulb temperature of inlet and outlet air.
Plot the process on Psychrometric chart.
Calculate the heat rejected during process.
Calculate the amount of water vapour removed during the process.
3. Nomenclature:
Nom Column Heading Units Type
Cos Φ Power Factor Given
Cp Specific heat of water kJ/kgoC Given
C.O.P.Th Theoretical Co-efficient of performance Calculated
RE Refrigeration Effect kJ/ kg Calculated
CW Compressor Work kJ/Kg Calculated
H1 Enthalpy of refrigerant at compressor inlet kJ/ kg Calculated
H2 Enthalpy of refrigerant at compressor outlet kJ/ kg Calculated
H3 Enthalpy of refrigerant at condenser outlet kJ/ kg Calculated
H4 Enthalpy of refrigerant at evaporator inlet kJ/ kg Calculated
P1 Pressure at compressor suction kg/cm2 Measured
P2 Pressure at compressor discharge kg/cm2 Measured
T1 Temperature at compressor suction C Measured
T2 Temperature at compressor discharge C Measured
T3 Temperature at condenser outlet C Measured
T4 Temperature at evaporator inlet C Measured
Tdi Dry Bulb Temperature of air at inlet of duct C Measured
Twi Wet Bulb Temperature of air at inlet of duct C Measured
Tdo Dry Bulb Temperature of air at outlet of duct C Measured
Two Wet Bulb Temperature of air at outlet of duct C Measured
ρa Density of air kg/m3 Given
Va Velocity of air flowing through duct m/sec Measured
X1 Humidity at inlet of duct kg/kg of dry air Measured
X2 Humidity at outlet of duct kg/kg of dry air Measured
Cooling and Dehumidification
Refrigeration and Air Conditioning (2161908) Department of Mechanical Engineering
Darshan Institute of Engineering and Technology, Rajkot
8-2
4. Introduction:
Air conditioning means "preparing the air as per required conditions of temperature,
humidity and velocity. The conditions required are different for different
applications, e.g. a small room requires air at about 24 - 26 °C where humidity control
is not so important, or a building may be air conditioned for supplying air of 24 -
26°C temperature & 50-60 % relative humidity. Measurement rooms in factories are
to be maintained at the temperature of -20 °C. So depending upon the requirement, the
air conditioning system is designed. A complete air conditioning system has the
following jobs.
1. Filtration of air, where it contains dirt or dust particles.
2. Deodorization of air.
3. Cooling of air in summer.
4. Dehumidification of air by cooling coil itself and again heating it, as may be
required in humid areas in summer.
5. Heating of air in winter.
6. Humidifying and heating of air as may be required in winter.
7. Circulating the conditioned air through the space to be air conditioned.
An air conditioning system may be provided with some or all the units required to
perform the above jobs, which is determined by conditioning requirements and cost
aspects. A window type air conditioner provides some filtration and cooling of air. In
large buildings, cooling, heating and humidification systems may be used, along with
partial recirculation of exhaust air. This is done as it will require a huge capacity plant
to condition the whole fresh air entering the space to be conditioned. Thus some air
from the exhausted air which is at a temperature lower than the ambient temperature
is mixed with the entering fresh air. Total recirculation is generally avoided in large
installations as the exhausted air contains odors.
The Air Conditioning Test Rig comprises of the following components.
1. A conditioning unit consisting of cooling coil, heaters and humidifier
2. Fan with circulating duct.
3. Control and measurement panel
X Change in Specific Humidity kg/kg of dry air Calculated
h1 Enthalpy of air at inlet of duct kJ/kg of dry air Calculated
h2 Enthalpy of air at outlet of duct kJ/kg of dry air Calculated
V Voltmeter Reading Volts Measured
I Ampere meter reading Amp. Measured
Cooling and Dehumidification
Refrigeration and Air Conditioning (2161908) Department of Mechanical Engineering
Darshan Institute of Engineering and Technology, Rajkot
8- 3
5. Block Diagram:
Fig. 8.1 Line Diagram of Air Conditioning Apparatus
6. Theory:
The process in which the air is cooled sensibly and at the same time the moisture is
removed from it is called as cooling and dehumidification process. Cooling and
dehumidification process is obtained when the air at the given dry bulb and dew point
(DP) temperature is cooled below the dew point temperature.
Let us understand the cooling and dehumidification process in more details. When the
air comes in contact with the cooling coil that is maintained at the temperature below
its dew point temperature, its DB temperature starts reducing. The process of cooling
continues and at some point it reaches the value of dew point temperature of the air.
At this point the water vapor within the air starts getting converted into the dew
particles due to which the dew is formed on the surface of the cooling and the
moisture content of the air reduces thereby reducing its humidity level. Thus when the
air is cooled below its dew point temperature, there is cooling as well as
dehumidification of air.
The cooling and dehumidification process is most widely used air conditioning
application. It is used in all types of window, split, packaged and central air
conditioning systems for producing the comfort conditions inside the space to be
cooled. In the window and split air conditioners the evaporator coil or cooling coil is
maintained at temperature lower than the dew point temperature of the room air or the
atmospheric air by the cool refrigerant passing through it. When the room air passes
over this coil its DB temperature reduces and at the same time moisture is also
Cooling and Dehumidification
Refrigeration and Air Conditioning (2161908) Department of Mechanical Engineering
Darshan Institute of Engineering and Technology, Rajkot
8-4
removed since the air is cooled below its DP temperature. The dew formed on the
cooling coil is removed out by small tubing. In the central air conditioning systems
the cooling coil is cooled by the refrigerant or the chilled water. When the room air
passes over this coil, it gets cooled and dehumidified.
In the general the cooling and dehumidification process is obtained by passing the air
over coil through which the cool refrigerant, chilled water or cooled gas is passed.
During the cooling and dehumidification process the dry bulb, wet bulb and the dew
point temperature of air reduces. Similarly, the sensible heat and the latent heat of the
air also reduce leading to overall reduction in the enthalpy of the air. The cooling and
dehumidification process is represented by a straight angular line on the
psychrometric chart. The line starts from the given value of the DB temperature and
extends downwards towards left.
Fig. 8.2 Cooling and Dehumidification Process on Psychrometric chart
7. Description:
The air-conditioning test rig unit is required to conduct experiments and demonstrate
the processes of heating, cooling, heating and humidification, cooling and
dehumidification, cooling and humidification of atmospheric air. The unit consists of
a compressor. Both evaporator and the air cooled condenser are mounted on board
with separate fans. Air is sucked from the room and is supplied to the room after
conducting the different processes. The system is provided with voltmeter, ampere
Cooling and Dehumidification
Refrigeration and Air Conditioning (2161908) Department of Mechanical Engineering
Darshan Institute of Engineering and Technology, Rajkot
8- 5
meter, digital temperature indicator, air heater, steam generator. The unit will be fitted
with all instrumentation facilities so that temperature and pressure can be measured at
different points in the air-conditioning system. Steam generator is provided from
which steam comes directly to the air inlet of air conditioning which is required for
humidification purpose. Heating coil is provided for heating of air and cooling coil is
provided for cooling and dehumidification of air. Suitable valves and fittings are fitted
in the pipe line of steam. Water level indicator is provided to safe guard of heater.
8. Utilities Required:
1. Electricity Supply: Single Phase, 220 VAC, 50 Hz, 5-15 Amp. Combined socket
with earth connection.
2. Floor Area Required: 2 m x 1 m
9. Experimental Procedure:
Starting Procedure:
1. Close valves below the pressure gauges
2. Open the funnel and air vent valve of steam generator.
3. Fill water in the steam generator upto 3/4th of its capacity by observing the level of
water in level indicator.
4. Switch ‘ON’ the main power supply.
5. Switch ‘ON’ the heater of steam generator and set the temperature of steam with
the help of DTC (100-120oC). And wait until steam temperature reaches to desired
value.
6. Switch ‘ON’ the compressor.
7. Wait for 2-3 minutes for switch ‘ON’ the compressor.
8. Open the valves of pressure gauges.
9. Allow steam to pass through the pipe and slowly open the wet steam vent valve to
release wet steam from the pipe.
10. Close the wet steam vent valve.
11. Switch ‘ON’ the air heater.
12. Rotate psychrometer and note down the ambient temperature of air.
13. After 10 minutes note down the temperature of air by putting sling psychrometrer
in front of air duct.
14. Note down the reading of pressure gauges and temperature sensors.
15. Repeat the experiment till the temperature of outlet of air become constant.
Closing Procedure:
1. Switch OFF the compressor.
2. Stop steam supply by closing the steam valve.
3. Switch OFF the air heater.
4. Switch OFF the main power supply.
Cooling and Dehumidification
Refrigeration and Air Conditioning (2161908) Department of Mechanical Engineering
Darshan Institute of Engineering and Technology, Rajkot
8-6
10. Observation & Calculations:
10.1 Data:
Cos Φ = 0.7
a = 1.21 kg/m3
10.2 Observation Table:
Va= …………… m/sec
Sr. No. t
(min)
P1
Bar
P2
Bar
T1
(C)
T2
(C)
T3
(C)
T4
(C)
Tdi
(C)
Twi
(C)
Tdo
(C)
Two
(C) V I
10.3 Calculations:
To Calculate COP of the System:
723.415)652.0()98.1011.0( 1111 TPTH
723.415)652.0()98.1011.0( 2222 TPTH
93.199228.1 33 TH
12
41..HH
HHPOC Th
43 HH
1000
CosIVCW
kJ/sec
To calculate the specific humidity X1 and enthalpy of air h1 at temperature Tdi & Twi.
__________1 X (kg/kg of dry air)
1 __________h (kJ/kg of dry air) [from psychrometric chart]
To calculate the specific humidity X2 and enthalpy of air h2 at temperature Tdo & Two
__________2 X (kg/kg of dry air)
2 __________h (kJ/kg of dry air) [from psychrometric chart]
Amount of water vapour removed from air = 1 2X X X
= (kg/kg of dry air)
Heat rejected from the air = Change in enthalpy of air
= h1 - h2
= (kJ/kg of dry air)
Cooling and Dehumidification
Refrigeration and Air Conditioning (2161908) Department of Mechanical Engineering
Darshan Institute of Engineering and Technology, Rajkot
8- 7
Cooling and Dehumidification
Refrigeration and Air Conditioning (2161908) Department of Mechanical Engineering
Darshan Institute of Engineering and Technology, Rajkot
8-8
11. Precautions & Maintenance Instructions:
1. Operate the Valves gently.
2. Never run the apparatus if power supply is less than 180 volts and above 230
volts.
3. Duct should be free from dust particles.
12. Troubleshooting:
1. If electric panel is not showing the input on the mains light, check the main
supply.
2. If voltmeter showing the voltage given to heater but ampere meter does not, check
the connection of heater in control panel.
13. Conclusion:
14. References:
1. Dossat, Roy J. (2004). Principles of Refrigeration. 4th Ed. ND: Pearson Education
Pvt. Ltd. pp 125-126.
2. Jordan, Richard C. & Priester, Gayle B. (1966). Refrigeration & Air Conditioning.
2nd Ed. ND: Prientice-Hall of India Pvt. Ltd. pp 444-447,455-466.
3. S.C. Arora, S Domkundwar (1995). A Course In Refrigeration And Air Conditioning.
5th Ed. Dhanpat Rai & Sons pp 16.1-16.24.
4. Psychometric Chart.