daily welding machine inspection checklist
DESCRIPTION
ChecklistTRANSCRIPT
DAILY WELDING MACHINE INSPECTION CHECKLIST
Contractor : Welding machine no. : Location : Month : Year
Description 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 Remarks
WELDING MACHINE
In good working condition
Provided with earthing or grounding
Provided with drip tray (Dry)
Fire extinguisher is available
Fire extinguisher is available
TERMINALS /JOINTS
In good working condition
Secured and effectively insulated
CABLES
Properly insulated and no exposed cables
Size of cable suitable for voltage supply
Hang up to prevent tripping hazard
Hang on insulated hook or material
Cables and joints are proper and in good condition
ELECTRODE HOLDER / CLAMP
Electrode holder is free from defects
Return cable clamp is free from defects
Detach electrodes when not in use
WORK AREA
No combustible or flammable materials
Fire blanket is provided
Maintain good housekeeping
ForemanSignature
Supervisor Signature