cx. 0fp/cf ccc fl[ copy - bureau of reclamation · only a portion of the normal flow channel, as...
TRANSCRIPT
PAP - 4
CX. 0FP/CF ccc Fl[ COPY
BUWFAU OF RECLAMATION
HYDRAULIC LABORATORY
HYDRAULICS BRANCH OFFICIAL FILE COPY
M
United States Department of the Interior Bureau of Reclamation
Branch of Design and Construction Denver Federal Center
CONSTRUCTION TO COPE WITH FAST-FLOWING WATER
by
J. W. Ball
Engineer, Hydraulic Laboratory Section
Research and Geology Division
Advance print of a paper to be presented at the Conference for Construction Engineers to be held in Denver, Colorado, February 6 to 10, 1950.
CONSTRUCTION TO COPE WITH FAST-FLOWING WATER*
by
J. W. Ball
1. The importance of constructing engineering structures to cope with fast-flowing water can be realized only when those in charge of the work fully understand what takes place when high-velocity water passes over constructed surfaces. The purpose of this talk will be to point out some of the actions which occur when this is the case, and how they affect construction.
2. The two most troublesome of these actions are eddying and cavi-tation. Both result in erosion of the surfaces. High-velocity eddies will pick up loose material from a riverbed or adjacent banks and cause erosion by abrasion while cavitation will cause damage by pitting.
3. Eddying is usually caused by unbalanced flow conditions set up by construction requirements or unsymmetrical operation of a structure after completion. The concentration of large quantities of water over only a portion of the normal flow channel, as was necessary during the construction of Grand Coulee Dam, is an example. The eddy current shown in figure 1 moved large quantities of rock, huge boulders, steel piles, and other construction material (figure 2) dropped near the toe of the dam, upstream into the bucket section where severe erosion occurred as shown by figures 3 and 4. The eroded material has smooth irregular sur-faces which in the case of concrete, have the appearance of having been ground and polished; and in the case of metal, appear as grooves having been gouged out with a chisel. Precautions against this type of damage during construction and operation would include:
a. Evenly distributing the flow, if possible b. Removal of loose material in the eddy area c. Preventing debris or other construction materials
to accumulate in possible eddy areas and d. Stabilizing the ground surfaces in the eddy area by
placing heavy rock or other material on them. Although of considerable concern to the construction engineer, the eddying action is usually, but not always, of a temporary nature and of short duration and can be tolerated as such. On the other hand, once conditions are present to induce cavitation the action will take place whenever there is flow unless some corrective measure is taken.
*For presentation at Conference for Construction Engineers of the Bureau of Reclamation; Denver, Colorado, February 6-10, 1950.
4. The damage produced by cavitation occurs in regions low-pressure and high-water velocf..ties where there are severe changes of alinement in the surface over which the water is flowing as indicated in figure 5, or where there is too rapid an increase in cross-sectional area of the water passage. The surface is rough and has the appearance of be-ing formed of numerous small crater-like depressions or pits and thus the action is called pitting. The piece of steel and concrete test specimens ` on this platform are examples. (Section of Ross Dam penstock and concrete blocks.)
5., Before discussing the subject of cavitation further, an attempt will be made to define the word in as nontechnical terms as possible.
6. Cavitation is the action which takes place in an extremely low-pressure region at the boundary of the flowing water when the pressure is reduced to the vapor pressure of the water. The action consists of the formation, movement, and collapse of vapor cavities (often called bubbles) in the low-pressure region. The cavities or bubbles form at the upstream edge of the region and are carried downstream to a point where the pres-sure increases and where they collapse or implode (opposite of explode) instantaneously. This action will be shown clearly in motion pictures shown to,you at the end of this discussion.
7. The instantaneous collapse causes the water particles surround-ing the bubble to move toward the center at an extremely high velocity and the impact of the water particles on each other as they come together produces a tremendous concentrated force which causes disintegration of a minute area of any surface on which this action occurs.
8. For many years the words "cavitation" and "pitting" have been used interchangeably as referring to both the cavitation action and the damage this action inflicts. Recently the engineering profession has attempted to limit the word "cavitation" to the action of, the formation, movement, and collapse of the vapor cavities, and the word "pitting" to the actual damage to materials by the cavitation action. This damage, therefore, is now termed pitting or cavitation-erosion-=not cavitation.
9. The general appearance of cavitation is a white, milky cloud resembling steam, as shown in figure 6. As a matter of fact, the cloud is a cold, low-pressure steam in the form of bubbies (cavitation bubbles). The cavitation action occurs with such rapidity that it cannot be studied in detail visually. Motion pictures taken at, speeds up to 20,000 frames per second have been used to study the phenomenon. These will be shown later.
10. Considerable noise and vibration accompanies cavitation. The noise may be of a hissing, crackling, or popping sound, depending upon the intensity of the cavitation and other physical flow characteristics such as -the masses of water and structure involved. For instance, the noise accompanying the cavitation in this small venturi meter (demonstration model), where the water velocity is relatively low, is of a hissing nature,
2
while that in a test apparatus in the laboratory is more of a crackling or popping nature as indicated by the sound from this speaker which is attached to the apparatus operating in the.laboratory. Figure 7 shows a section through this apparatus. (Note the expanding section and posi-tion of concrete test blocks.) Some of the damaged test blocks are shown in figure 8.
11. The noise accompanying cavitation is known to all hydraulic engineers as crepitation.
12. From our discussion of cavitation, it is evident that the best method of preventing its occurrence from the construction standpoint is to see that the surfaces over which high-velocity water is to pass are smooth, continuous, and free of offsets and undulations.
13. The commonest sources of dangerous irregularities are the off-sets which often occur at construction ,joints. It is not easy to prevent these offsets but they can be eliminated, and they must be eliminated if these channels for fast-flowing water are to operate freely from damage due to cavitation.
14. Hydraulic 3ngineers have realized for a long time that it is extremely difficult and in many cases impracticable to eliminate completely these surface irregularities, and some tests have been conducted to deter-mine what tolerances could be permitted. It has been difficult to make the test facilities represent the field conditions where wide variations in water depth and velocity are encountered, and the data on surface tol- erances for high-velocity flow are still meager. The specifications for the surfaces of the Hungry Horse Dam Spillway Tunnel and other similar structures are based on this information.
15. The irregularities in the surfaces of the Hungry Horse Spillway Tunnel, where high-velocity flow is expected, are limited to gradual de-pressions or rises in which the slopes or bevels to and from the low or high points vary from 1/4 inch in 20 inches to 1/4 inch in 100 inches. The flatter bevel is specified for the lower vertical bend of the tunnel and in the bottom portion of the horizontal section downstream from the bend where the velocities will be the highest, and where water passes over the surfaces whenever the spillway operates. The steeper bevels are permitted in other sections where the velocities are lower and the tend-ency for cavitation is much less.
16. The tolerances may or may not be on the conservative side. It is hoped that they are and that future investigation will show that they can be eased. However, until such time as we have proof that these toler-ances are too strict, we must continue to use them.
17. We have many examples which will illustrate the importance and necessity of using tolerances which will prevent damage by cavitation. One example concerns erosion by cavitation of the draft-tube surfaces of one of the units of the right powerhouse at Grand Coulee Dam when needle
3
valves were placed to discharge their flow into the tubes for the release of water during the repair of underwater portions of the spillway. Figure 9 shows the extent of damage after 23-hour operation of one of the valves. A survey of the area revealed that the surface was not contin-uous but had an offset of one-half inch as illustrated in figure 10. Through inquiry, it was learned that during construction one edge of a steel form had been deformed to coincide with the edges of the already placed adjacent concrete. The cha,ge in the form resulted in a one-half inch discontinuity, ideal for producing cavitation when high-velocity water passed over it. An area in which the pressure was reduced to the vapor pressure of water formed immediately downstream from the discon-tinuity. Cavitation occurred in this area and caused pitting a short distance downstream. The damage was accelerated when an old patch in the area was torn out by the pressure changes and vibrations accompany-the cavitation. As a corrective measure, the concrete was removed from the area to a depth of about 18 inches and the surface repaired to elim-inate the severe recession in the surface as illustrated in figure 10. There was no damage in this area by subsequent operations as shown in figure 11, although above the repair further damage was caused by loss of a patch.
18. It should be pointed out here that had the draft tube been used only for handling the usual discharge from the turbine, the veloci-ties would have been low and there would have been no cavitation.
19. The motion picture "Formation and Collapse of Cavitation Cavities," to be shown in concluding this discussion will show the cavi-tation action as described at the beginning of this talk.
20. After viewing the film, you will realize that the designer can do much to eliminate cavitation in his designs, but that the surfaces must be smooth and continuous if the design is to remain free of cavitation. In other words, we must stress that clean, smooth, continuous surfaces free of offsets and irregularities must be provided where fast moving water is concerned. A "gob" of set concrete clinging to the surface is sufficient to induce cavitation, and care should be taken to remove any "foreign" material from the flow surfaces before a structure is placed in operation. The responsibility to provide satisfactory surfaces must be assumed by the construction men. It is better to keep within the specified close tolerances during construction rather than grind or re-pair the surfaces after construction is complete or damage has been done after the structure is placed in operation.
Figure 1. Eddy induced by flow distribution at Grand Coulee Dam--1940 Flood Season.
Figure 2. Material removed from spillway bucket--Grand Coulee Dam.
•- -9G
.890
1 .._-'-- 900 '— ----- ; •..-"
SEC. T-T
V
Q 0 3
Q El. ',00.00-
.c
'FI
V SEC. U-U
444'toAxis r face of east --427.5'toAxis------ training wall' '
"`1 V__ ,n7A ,̂ - I'EI 9W..00
<-- 393' to Axis I "Of{set 7efh I
45°chamrer- 172 60
fLO~ ~ t--•g
Offset worn away'
SEC. A-A
4"to121~.
2- to 6" ir9"
r --X SEa B•B
TRANSVERSE JOINT
is-12'to ZO"--'I
6" or2"• a `'F
t--- SEC. C-C
TRANSVERSE JOINT
t 427.5'toAxis4 6' to 12"
Apex level --
Y ' Form rods
SEC. D-D
/ !• ----427.5'to Axis --- E1. 900 T~ - - y Apex rounded'
• ~ - Form rods l U
SEC. V-V SEC. E-E O O 10
SCALE o" FEET
Ar- I
E!. 87
rs, excavated rock and cobbles-
\
890 ...............
H b 1 c 1 EL 874.41
v,
Z IL El. 895.!8
....... ......
SEC. Z-Z 499.35' TO AXIS - I . .
?00,00 4
r w
}
0
EL 900. 00 s `';'': ! ;', ; containing boulders
____..%~ •: ''..._......._896
.. ......
----
-. ee
_-~
BLOCK 31 BLOCK 38
PLAN sec. A_X
419.5' TO AXIS
f EI 900.00
12"to 18": = \\
2f' Max. -.
Pour lines- SEC. N-IV
NOTE
This drawing indicates the conditions existing in the spillway bucket as of
- March 1943. Data obtained from inspections made at later dates are availob for inspection of the offices of the Bureau of Reclamotion,Coulee Dam, Washington.
SEC. Y•Y 427.5' TO AXIS
8L 6, Dia Outlet conduits ----------------------
FITT-
IN N I I I N N r~
1 4 ti ti 1 1 1 1 ti ti I I Q Q I Q Q 51 i 50 ,~ I 491 1 48 i 471 N 46 I' 451 44 31 1 N, 42 41 40 ' CAI I'll
----- I I
1 1 i
1 1 I I I I I I j -i-+'
1
~ I
39 38 N, 37 vQ~i 36 35
E i
--- ------- ----- 8'-6' Dia Outlet condurt5
7!!-.i~2 - E + --r~-- N 64 63i 62 i fill 60 59! 5T S6 N i 55!1 ~i - 54 53 v~ 52
11 I i t I I' I 11 I I I
F' __Vertical 1 1 1
6 i crack ! 1 - —
1 r
,Crack i ~l Crack an I ~; ' : ! i I I Spalledarea=' l 1 E 1 G! , z SPall l i i t I ~._ 1 ' 4- -_ - -1 EI.912± _. --- -_ I ' I ' 1
EL 874.41= H~ v9A r
,+F IR /. a a `~ y,
vim, I ~Ei I • !E; f• Y~c
-E1B7260 k De oslt to EI 879 Mar ,;': r y¢I 6 Max dePf'' _ F std ..... Fr-- y fir3 . " >
E ~, e i
34 do 33 ~ 34 v)31 4 i ~Jk I
F X Q
Q
G m M 1 ' r---Approximate water surface at elevation 938# -- --ji " I : 1 I , I I ~ I - I -Small r k •- :I .Spell &crac yam_ ~ •. I
r i , c a s •. I - - -I- 'spalled off I I
II II - - s, area not inspected:
e % 18"deep., E F ' 8y; B eY e
/•d °Boulder °"30~ .o q P. a~! I a z 8oulder ,a_deevi R f r ' Ar "('_ Ar>J BV 1•~8
f aPt I
/ 4 r D > ~ o ~l-
. N
Toe of concrete—, Limit of river fill - -gvC
i qG5-_:
,j : 900' ~ -•
: ' - --- -- - _, 'Goncrete' -
P L A N
•r4~la''~•, 10 0 50 1010 1"fD3 El 872.6
,-9, SCALE or FEET
FLO
VOr185
SEC. F•F : EL 885±
£1.872.6 6 4275toAxis-- El. 900
'Rlverfilf rr- SEC. U-J • L
340'- TO AXIS EL 890- ------ --------- - ------- O.W. CONDUITS- BLOCK 45 ~vo
\ STA-24+85
ft-880 SEC. G-G
! t-~ O
>+ _ El 900 F~`Yy .Offset worn away _. ____-_-.-- El
4275 to Axis---- ------------ "w Riv
,-El. 874.3 :: -River fill P 9"•-2 - ----- -- -- £1890 yJ " -- -f(_ 890
Gravel.;.. - -
EI.880 Gravel' -
SEC. 14-H STA•24+95 STA. 25+25
"- 355.85tDAx1s-
~ i~ TOFFset with Ei soo - E
LL 900 z•, 45"Chamfer ----_:_------ - r ,l Rlv 3s_> ;: °=-River fill
w r £.874.3 EI.890 ,i E1890_
i Gravel c=• I EC@@4 r `6"to/2" J__ _ _
.r.~av ~ ------ - ------ Gravel •:>="
SEC. K-K STA-25+05 STA-25+35
< 427.5'toAxis-- i% E I-900
E19 Et. 900 ------ -- -- -------
"4 1"Comb ;River fill River fill EL 890
vZa------- - £1.890
-------- ---- --
Grove
-- -
/ 3"to 12" E188o Gravel tr:;. ____ E1880-
:•>.. SEC. L-L
S TA.25+ l5 STA. 25+4.5
' r y '
I
1 emit i - .L1 of rver fill Boulders excavated rock and cobbles N d aF vI H
F
G
EXPLANATION
Erosion 1" to 3"
Erosion 3'to 9'
Erosion Tfo 18'
Erosion over 18'
Sand, gravel and boulders
© Surface ground smooth. ® Surface rough-aggregate protrudes
from surface ® Small shallow potholes O Spall 2' long by 10' max. depth. O Surface pocked with depressions up
to 12' max. depth. ® Crack ® Grout stop exposed for ]'to 4! along joint. OS Form rods exposed © Form rods exposed I2'to IT bent upstream. G Dry patches in blocks 40-1 and J worn
appreciably. © Velocity measuring piers gone-on J block
brass olateedlsplaced (found in bucket).
UNITED STATES DEPARTMENT OF THE INTERIOR
BUREAU OF RECLAMATION COLUMBIA BASIN PIOJECT-WASHINGTON
GRAND COULEE DAM RESULTS OF
SPILLWAY BUCKET INSPECTION MARCH 1943
DRAWN_ 4 Y. D. ~• ~:R--SUBMITTED.__./ _YC'I__
TRACED---'W?-.__._-_.RECOMMENDED ----̀ ~"' -'-~ CWs.-T. CHECKED______R_ __K_APPRDVED.__6x: Fd.,4r= R
A-3610-I ICOULEE DAM, WASH. APRIL 7 1943
FIGURE
-E[ 885±
Z A~ El. 895.18-;,
- ___-__-
` E1. 900. _'~''
J'Z
------------ 896
i
PoMole containing boulders
I
-6'- ---7' --a "El. 895.18
P/V
SEC. Z-Z 439.35' ,TO AX15
Grave
Grave
Grc
PLAN
Grave,
:1.900
ver -Fill -L890--
SEC. J-J rL1x 340'_ TO AXIS
O. W. CONDUI TS -BLOCK 45
to Axis--- El. 900
Ri ver fill
EL 890
Gravel - ------ _-----------El 880
STA. 25+25
EI. 900
°. °r Ri ver fill
--~ -----El 890
m Gravel
STA. 25+35
STA. 25+45
12" to 18111,' \
t
22' Max. - ~— -'
This drawing indicates the conditions existing in the spillway bucket as of March 1943. Data obtained from inspections made at later dates are available for inspection at the offices of the Bureau of Rec la motion ,'Coulee Dam, Washington.
Figure 4. Erosion of Spillway Bucket--Grand Coulee Dam--Inspection March 1943•
SEC. N-N Pour lines"'
-~ 427 5 tOAXiS-- El. 900
I EL 890
-------------------------EL 860
STA. 24+85 1
El. 900
Ri ver {ill
-6. 890
El. 880
El. 900
ver {ill El. 890
El. 880
El. goo
Ri ver {ill El. 890
El. 880
_ ------89B
------ - , •._ ., , - --------896 ------------ -- ------894
8,2
- 884
- - ---862
- -- -876
_ - f74
BLOCK 31 1 BLOCK 38
El 900.00
STA• 24+ 95
STA.25+05
STA.25+I5
V
~ Y - 8' -- !,;-El 89 2. 00
n Y
?00.00
!X`— i
k Q
V) r N
SEC. Y- Y 4 2 7.5' TO AXIS
10 Ln
~I
F~ 0
-REGION OF LOW PRESSURE .:p WHERE CAVITATION OCCURS
, -PITTING OCCURS HERE ,,
~-~ CONTRACTION: O. o JOINT :p' a..
V.
FIGURE 5 COMMON MISALIGNMENTS INDUCING CAVITATION
w
EXPOSURE /1100 SF-C. VELOCITY
CAVITATION CONE
Figure 6. Appearance of Cavitation.
r ~
r
t. BUREAU
UNITED STATESINTERIORDEPARTMENT OF THE
OF RECLAMATION DESIGN DA TA
s„ CAVITATIO N FOR EVALUATING RESISTANCE .
x CONCRETE. PROTECTIVE COATINGS
DRAWN ,
w .. .. ~
Figure 8. Cavitation-erosion of concrete specimens.
!t
Figure 9. Erosion caused, by operation of temporary needle valve in draft tube—Grand. Coulee Dam.
F` O
-REGION OF LOW PRESSURE d WHERE CAVITATION OCCURS
:. PITTING OCCURS HERE
CONTRACTION J 01 N
FIGURE IO JOINT MISALIGNMENT AND REPAIR METHOD OF DRAFT TUBE AT GRAND COULEE DAM
It
Figure 11. Repaired area (lower portion of photograph) shows no damage by subsequent operations. Loss of patch (upper portion of photograph) caused new erosion.