cv indra lukman new r21
TRANSCRIPT
![Page 1: CV indra lukman new r21](https://reader036.vdocuments.us/reader036/viewer/2022071702/55c42f3cbb61ebc1628b463e/html5/thumbnails/1.jpg)
INDRA LUKMAN Address: Sevilla Cluster AA 09, Kencana Loka, BSD ,
South Tangerang/Banten,Indonesia 15317 Home Phone: +62-21-29012845 | Mobile No.: +62-8111922922
E-mail Address: [email protected] Nationality: Indonesia
KEY QUALIFICATIONS:
PROJECT MANAGEMENT
PROJECT ENGINEERING
PROJECT CONSTRUCTION
PROJECT COORDINATOR
PROJECT CONTROL
PROJECT ESTIMATOR
ELECTRICAL & AUTOMATION ENGINEERING
MAINTENANCE
PERSONAL DATA: Place/date of birth : Padang ,West Sumatera, Indonesia/22 Oktober 1960 Marital Status : Married Religion : Moslem PROFESSIONAL EXPERIENCE: June 1986 July -1987 : PT.CITACONAS-Beca Worley International(New Zealand ),Indonesia
as an Electrical Engineer surveyor in T & D Development Study outside Java for PLN
Aug 1987 July -1988 : PT.Pupuk Kaltim (Fertilizer Plant),Indonesia
as management Trainee in Pupuk Kaltim Unit III new Plant Project
Aug 1988 May -1989 : PT.Oteessa -Merlin Gerin,Indonesia
as Design Engineer for Electrical Switchgear and Substation
Oct 1989 Sept -1990 : PT.Krakatau Steel ,Indonesia
as Management Trainee in Wire Rod Mill Oct 1990 June -1993 : PT.Krakatau Steel ,Indonesia as Electrical , Automation & Instrumentation Maintenance Engineer in Wire Rod Mill (Responsible for Maintenance of Electrical,Automation & Instrumentation ).
![Page 2: CV indra lukman new r21](https://reader036.vdocuments.us/reader036/viewer/2022071702/55c42f3cbb61ebc1628b463e/html5/thumbnails/2.jpg)
Indra Lukman Page 2
as Project Supervision of WRM Expansion Project Phase 1 (ABB) (Pre Finishing Mill , Finishing mill 100m/s, Water Cooling treatment, Laying Head & Pinch Roll, Stelmor conveyor, Coil Reforming), for Electrical & Automation Installation
Construction & Installation of : Trafo 20KV/6KV 1 x 10 MVA ,Trafo 6 KV/400V 2 x 1 MVA, Switchgear 6 KV, Motor Control Centre, Main Distribution Panel, DCS Panel, 8 x Converter Motor Drive Panel, Battery charger & UPS system, 2 x 5 MW Motor, 2 x 1 MW motor, 4 x 500 KW motor, Sensor & Instrument Proximity switch, Limit switch, Pressure switch, Flow switch, Level switch, Hot metal detector, pulse encoder : 4000 unit, Selenoid valve, Actuator : 1000 unit, Cable tray –Ladder , Pulling & connecting Power Cable & Cable control, Cable Power Testing & Megger test , I/O test.
July 1993 June -1995 : PT.Krakatau Steel ,Indonesia as Ass. Superintendent in Wire Rod Mill
(Coordinator & responsible for maintenance of Electrical, Automation & Instrumentation )
as Project Coordinator of Upgrading Reheating Furnace Project ( LOI-LVE)
for Electrical ,Automation & Instrumentation Installation & Commissioning Construction ,Installation & commissioning of : Motor Control Centre, Main Distribution Panel, DCS Panel, 6 x Inverter Motor Drive Panel, Battery charger & UPS system, 2 x 75 KW Motor, 2 x 15 kW motor, 2 x 100 KW motor, Sensor & Instrument Proximity switch, Limit switch, Pressure switch, Flow switch, Level switch, Hot metal detector, pulse encoder : 50 unit, Selenoid valve, Actuator : 20 unit, Cable tray –Ladder , Pulling & connecting Power Cable & Cable control, Cable Power Testing & Megger test , I/O test, Function test, No-load test, Hot Commissioning test)
June 1996 Jan -1999 : PT.Krakatau Steel ,Indonesia as Superintendent in Wire Rod Mill & Billet Steel Plant (Coordinator & responsible for maintenance of Automation & Instrumentation )
as Project Coordinator of WRM Second line Expansion Project phase 2 (ABB-Danieli-POMINI-Sund Bistra) (Pre Roughing Mill, Water descaler, Intermediate Mill, Pre Finishing Mill , Finishing mill 100m/s, Water Cooling treatment, Laying Head & Pinch Roll, Stelmor conveyor, Coil Reforming, Compactor & Coil Handling)
for Electrical ,Automation & Instrumentation Design Engineering , Software development, Installation & Commissioning Engineering of Basic design: Load Flow analyze, Short circuit calculation, Voltage drop calculation, Process Flow diagram (PFD), Piping Instrument diagram (PID), SLD, Plant destination, Cable Diagram, Functional description Engineering of Detail design : Flow chart for DCS, Static Display, Cable route, Panel & control desk assembly drawing, Circuit Diagram, Cable Schedule, lighting layout & Assembly drawing, Bill of Quantity Software Development: Programming DCS of Pre Roughing Mill Inter locking & sequence, Start –stop auto, Cascade loop control, Lubrication & Hydraulic system Pump station, Water cooling treatment & Stelmor conveyor cooling treatment control, Switchgear 6kv interlocking. Construction & Installation of : Trafo 20KV/6KV 1 x 10 MVA ,Trafo 6 KV/400V 8 x 1 MVA, Switchgear 6 KV, Motor Control Centre, Main Distribution Panel, DCS Panel, 8 x Converter Motor Drive Panel, Battery charger & UPS system, 2 x 5 MW Motor, 2 x 1 MW motor, 8 x 500 KW motor, 4 x 200 kw motor, 6 x 100 kw motor, 20 x 15 kw motor, Sensor & Instrument Proximity switch, Limit switch, Pressure switch, Flow switch, Level switch, Hot metal detector, pulse encoder : 6000 unit, Selenoid valve, Actuator : 1200 unit, Cable tray –Ladder , Pulling & connecting Power Cable & Cable control,
![Page 3: CV indra lukman new r21](https://reader036.vdocuments.us/reader036/viewer/2022071702/55c42f3cbb61ebc1628b463e/html5/thumbnails/3.jpg)
Indra Lukman Page 3
Cable Power Testing & Megger test , I/O test, Cable Power Megger test , Function test, No-load test, Hot Commissioning test)
as Project coordinator of WRM New Walking Beam Reheating Furnace (Krosaki)
for Electrical ,Automation & Instrumentation Detail Design , Software development, Installation & Commissioning Construction ,Installation & commissioning of : Trafo 6 KV/400V 1 x 2 MVA, Motor Control Centre, Main Distribution Panel, DCS Panel, 12 x Inverter Motor Drive Panel, Battery charger & UPS system, 12 x 75 KW Motor, 6 x 15 kW motor, 2 x 100 KW motor, Sensor & Instrument Proximity switch, Limit switch, Pressure switch, Flow switch, Level switch, Hot metal detector, pulse encoder : 150 unit, Selenoid valve, Actuator : 70 unit, Cable tray –Ladder , Pulling & connecting Power Cable & Cable control, Cable Power Testing & Megger test , I/O test, Function test, No-load test, Hot Commissioning test)
as Project Coordinator of BSP upgrading Project (Danieli- CONCAST-VAI) (Continuous Casting Mill ) for Electrical.Automation & Instrumentation Engineering design Engineering of Basic design: Load Flow analyze, Short circuit calculation, Voltage drop calculation, Process Flow diagram (PFD), Piping Instrument diagram (PID), SLD, Plant destination, Cable Diagram, Functional description Engineering of Detail design : Flow chart for DCS, Static Display, Cable route, Panel & control desk assembly drawing, Circuit Diagram, Cable Schedule, lighting layout & Assembly drawing, Bill of Quantity
Febr 1999 July -2008 : PT.Krakatau Steel ,Indonesia as Automation Chief Engineer (Technical Advisor for New & retrofit of Automation Project for all Plant/Mill) Aug 2002 Jan -2003 : as Project Coordinator of Continuous Pickling Line & Acid Regenerator Plant
CRM (ABB)PT.Krakatau Steel ,Indonesia
for Electrical ,Automation & Instrumentation Detail Design , Software development, Installation & Commissioning (ABB). Engineering of Basic design: Load Flow analyze, Short circuit calculation, Voltage drop calculation, Process Flow diagram (PFD), Piping Instrument diagram (PID), SLD, Plant destination, Cable Diagram, Functional description Engineering of Detail design : Flow chart for DCS, Static Display, Cable route, Panel & control desk assembly drawing, Circuit Diagram, Cable Schedule, lighting layout & Assembly drawing, Bill of Quantity Software Development: Programming DCS of Continuous pickling Inter locking & sequence, Start –stop auto, Cascade loop control, Grease,Lubrication & Hydraulic system Pump station, Coil compactor control, continuous Welding auto system, Switchgear 6kv interlocking. Construction & Installation of : Trafo 6 KV/400V 1 x 1 MVA, Switchgear 6 KV, Motor Control Centre, Main Distribution Panel, DCS Panel, 8 x Converter Motor Drive Panel, Battery charger & UPS system, 8 x 500 KW motor, 4 x 200 kw motor, 6 x 100 kw motor, 20 x 15 kw motor, Sensor & Instrument Proximity switch, Limit switch, Pressure switch, Flow switch, Level switch, Hot metal detector, pulse encoder : 100 unit, Selenoid valve, Actuator : 40 unit, Cable tray –Ladder , Pulling & connecting Power Cable & Cable control, Cable Power Testing & Megger test , I/O test, Cable Power Megger test , Function test, No-load test, Hot Commissioning test)
![Page 4: CV indra lukman new r21](https://reader036.vdocuments.us/reader036/viewer/2022071702/55c42f3cbb61ebc1628b463e/html5/thumbnails/4.jpg)
Indra Lukman Page 4
June 2004 July -2008 : PT.Krakatau Engineering (Engineering, Procurement & Construction) As Technical Advisor June 2006 Sept -2010 PT.Sinar Inti Elektrindo Raya, Jakarta ,Indonesia As an BU Head of EPC-PM (Automation ,Electrical & Instrumentation)
· Developing operational strategic plans and generally overseeing their implementation to ensure maximum Human resources capacity utilization towards achieving the group’s strategy, growth and profit objectives.
· Implementing ISO 9001, HSE, and all Occupational Health and Safety to company.
· Responsible for formulating policies, programs, and objectives affecting the schedule, quality, and cost of manufactured products. Directing and co- coordinating production according to quality and quantity specifications within cost objectives.
· Identify and adapt technological advances to meet the group’s competitive objectives within the marketplace.
· Lead the implementation of strategic resource allocation, organization structure, leadership, sourcing and integration and techniques for improved efficiencies and adherence to best practice.
· Providing strong leadership to the employees, ensuring high morale, team work and good employee relations, at all levels, including on the shop floor.
· Tender and meeting with clients and vendors to bring new business. · Be a business partner or act as advisor to bring more good business. · Report duties to Chief Executive Officer / Owner.
As a Project coordinator
List Of Project
o Biodiesel 50 ton /day Turn key Project (Basic & Detail design Engineering, Software development, Procurement, Detail design Engineering, Construction & Installation, Test & Commissioning for Electrical, Automation and Instrumentation) , Jakarta Engineering of Basic design: Load Flow analyze, Short circuit calculation, Voltage drop calculation, Process Flow diagram (PFD), Piping Instrument diagram (PID), SLD, Plant destination, Cable Diagram, Functional description Engineering of Detail design : Flow chart for DCS, Static Display, Cable route, Panel & control desk assembly drawing, Circuit Diagram, Cable Schedule, lighting layout & Assembly drawing, Bill of Quantity Software Development: Programming DCS of Skid 1 & 2 Inter locking & sequence, Skid 3 & 4 Inter locking & sequence , Start –stop auto, batch control, Grease,Lubrication & Hydraulic system Pump station, MDP interlocking. Construction & Installation of :
Trafo 6 KV/400V 1 x 1 MVA, Switchgear 6 KV, Motor Control Centre, Main Distribution Panel, DCS Panel, 8 x Inverter Motor Drive Panel, Battery charger & UPS system, 8 x 10 KW motor,4 x 7.5 Kw Motor, Sensor & Instrument Proximity switch, Limit switch, Pressure switch, Flow switch, Level switch, flow meter, Temperature switch : 80 unit, Selenoid valve, Actuator : 22 unit, Cable tray –Ladder , Pulling & connecting Power Cable & Cable control, Cable Power Testing & Megger test , I/O test, Cable Power Megger test , Function test, No-load test, Hot Commissioning test)
o BioEthanol Turn key Project (Basic & Detail design Engineering, Software development, Procurement, Detail design Engineering, Construction & Installation, Test & Commissioning for Electrical, Automation and Instrumentation), Lampung Engineering of Basic design: Load Flow analyze, Short circuit calculation, Voltage drop calculation, Process Flow
![Page 5: CV indra lukman new r21](https://reader036.vdocuments.us/reader036/viewer/2022071702/55c42f3cbb61ebc1628b463e/html5/thumbnails/5.jpg)
Indra Lukman Page 5
diagram (PFD), Piping Instrument diagram (PID), SLD, Plant destination, Cable Diagram, Functional description Engineering of Detail design : Flow chart for DCS, Static Display, Cable route, Panel & control desk assembly drawing, Circuit Diagram, Cable Schedule, lighting layout & Assembly drawing, Bill of Quantity Software Development: Programming DCS of Screw conveyor Inter locking & sequence, Hammer mill Inter locking & sequence , Vibro screen Inter locking & sequence, Elevator bucket Inter locking & sequence,Hopper & storage tank interlocking & sequence, Start –stop auto, batch control, Grease,Lubrication system Pump station, MDP interlocking. Construction & Installation of : Trafo 6 KV/400V 1 x 1 MVA, Switchgear 6 KV, Motor Control Centre, Main Distribution Panel, DCS Panel, 12 x Inverter Motor Drive Panel, Battery charger & UPS system, 12 x 7,5 KW motor, 6 x 5 Kw Motor, Sensor & Instrument Proximity switch, Limit switch, Pressure switch, Flow switch, Level switch, flow meter, Temperature switch : 110 unit, Selenoid valve, Actuator : 42 unit, Cable tray –Ladder , Pulling & connecting Power Cable & Cable control, Cable Power Testing & Megger test , I/O test, Cable Power Megger test , Function test, No-load test, Hot Commissioning test)
o Material Handling of Sugar Plant turn key Project(Basic & Detail design Engineering, Software development, Procurement, Detail design Engineering, Construction & Installation, Test & Commissioning for Electrical, Automation and Instrumentation), Cilegon Engineering of Basic design: Load Flow analyze, Short circuit calculation, Voltage drop calculation, Process Flow diagram (PFD), Piping Instrument diagram (PID), SLD, Plant destination, Cable Diagram, Functional description Engineering of Detail design : Flow chart for DCS, Static Display, Cable route, Panel & control desk assembly drawing, Circuit Diagram, Cable Schedule, lighting layout & Assembly drawing, Bill of Quantity Software Development: Programming DCS of Conveyor Inter locking & sequence, Start –stop auto, batch control, grease system Pump station, MDP interlocking. Construction & Installation of : Trafo 6 KV/400V 1 x 500 KVA, Switchgear 6 KV, Motor Control Centre, Main Distribution Panel, DCS Panel, 4 x Inverter Motor Drive Panel, 4 x 50 KW motor, 2 x 5 Kw Motor, Sensor & Instrument Proximity switch, Limit switch, Pulse encoder : 40 unit, Selenoid valve: 10 unit, Cable tray –Ladder , Pulling & connecting Power Cable & Cable control, Cable Power Testing & Megger test , I/O test, Cable Power Megger test , Function test, No-load test, Hot Commissioning test)
o Talen Barge Loading Conveyor turn key project (Basic & Detail design Engineering, Software development, Procurement, Detail design Engineering, Construction & Installation, Test & Commissioning for Electrical, Automation and Instrumentation) , East Kalimantan Engineering of Basic design: Load Flow analyze, Short circuit calculation, Voltage drop calculation, Process Flow diagram (PFD), Piping Instrument diagram (PID), SLD, Plant destination, Cable Diagram, Functional description Engineering of Detail design : Flow chart for DCS, Static Display, Cable route, Panel & control desk assembly drawing, Circuit Diagram, Cable Schedule, lighting layout & Assembly drawing, Bill of Quantity Software Development: Programming DCS of Conveyor Inter locking & sequence, Start –stop auto, grease system Pump station, MDP interlocking.
![Page 6: CV indra lukman new r21](https://reader036.vdocuments.us/reader036/viewer/2022071702/55c42f3cbb61ebc1628b463e/html5/thumbnails/6.jpg)
Indra Lukman Page 6
Construction & Installation of : Trafo 6 KV/400V 1 x 1 MVA, Switchgear 6 KV, Motor Control Centre, Main Distribution Panel, DCS Panel, 4 x Inverter Motor Drive Panel, 4 x 150 KW motor, 4 x 35 Kw Motor, Sensor & Instrument Proximity switch, Limit switch, Pulse encoder : 40 unit, Selenoid valve: 10 unit, Cable tray –Ladder , Pulling & connecting Power Cable & Cable control, Cable Power Testing & Megger test , I/O test, Cable Power Megger test , Function test, No-load test, Hot Commissioning test)
o Kayan Crusher plant & Barge loading conveyor turn key project (Basic & Detail design Engineering, Software development, Procurement, Detail design Engineering, Construction & Installation, Test & Commissioning for Electrical, Automation and Instrumentation) , East Kalimantan Engineering of Basic design: Load Flow analyze, Short circuit calculation, Voltage drop calculation, Process Flow diagram (PFD), Piping Instrument diagram (PID), SLD, Plant destination, Cable Diagram, Functional description Engineering of Detail design : Flow chart for DCS, Static Display, Cable route, Panel & control desk assembly drawing, Circuit Diagram, Cable Schedule, lighting layout & Assembly drawing, Bill of Quantity Software Development: Programming DCS of Crusher Inter locking & sequence, Barge loading conveyor Inter locking & sequence Start –stop auto, grease system Pump station, MDP interlocking. Construction & Installation of : Trafo 6 KV/400V 1 x 2 MVA, Switchgear 6 KV, Motor Control Centre, Main Distribution Panel, DCS Panel, 6 x Inverter Motor Drive Panel, 4 x 250 KW motor, 4 x 75 Kw Motor, 2 x 15 kw motor, Sensor & Instrument Proximity switch, Limit switch, Pulse encoder : 60 unit, Selenoid valve: 12 unit, Cable tray –Ladder , Pulling & connecting Power Cable & Cable control, Cable Power Testing & Megger test , I/O test, Cable Power Megger test , Function test, No-load test, Hot Commissioning test)
o Berau Lati 3 Crusher Plant , Skyline Conveyor & Barge loading conveyor turn key project (Basic & Detail design Engineering, Software development, Procurement, Detail design Engineering, Construction & Installation, Test & Commissioning for Electrical, Automation and Instrumentation), Berau, East kalimantan Engineering of Basic design: Load Flow analyze, Short circuit calculation, Voltage drop calculation, Process Flow diagram (PFD), Piping Instrument diagram (PID), SLD, Plant destination, Cable Diagram, Functional description Engineering of Detail design : Flow chart for DCS, Static Display, Cable route, Panel & control desk assembly drawing, Circuit Diagram, Cable Schedule, lighting layout & Assembly drawing, Bill of Quantity Software Development: Programming DCS of Crusher Inter locking & sequence, Skyline conveyor Inter locking & sequence, tripper Inter locking & sequence , Barge loading conveyor Inter locking & sequence Start –stop auto, grease & lubrication system Pump station, MDP interlocking. Construction & Installation of : Trafo 6 KV/400V 2 x 2 MVA, Switchgear 6 KV, Motor Control Centre, Main Distribution Panel, DCS Panel, 6 x Inverter Motor Drive Panel, 6 x 350 KW motor, 8 x 75 Kw Motor, 2 x 15 kw motor, Sensor & Instrument Proximity switch, Limit switch, Pulse encoder : 140 unit, Selenoid valve: 40 unit, Tunnel Lighting : 200 unit, Field Lighting : 250 unit, Road Lighting : 200 unit, Cable tray –Ladder , Pulling & connecting Power Cable & Cable control, Cable Power Testing & Megger test , I/O test, Cable Power Megger test , Function test, No-load test, Hot Commissioning
![Page 7: CV indra lukman new r21](https://reader036.vdocuments.us/reader036/viewer/2022071702/55c42f3cbb61ebc1628b463e/html5/thumbnails/7.jpg)
Indra Lukman Page 7
test)
o IKPP Switch-yard SCADA & Monitoring turn key project , Perawang,
Riau
o Gas turbine 2 x 20 MW ,Electrical & Instrumentation Refurbishment for
John Brown Engineering (England), at Bandung.
o New Crusher Plant , Skyline Conveyor, Under line conveyor & Barge loading conveyor turn key project ,Lati Upgrade 4 (LUG4), PT.Berau coal, Berau, East Kalimantan Engineering of Basic design: Load Flow analyze, Short circuit calculation, Voltage drop calculation, Process Flow diagram (PFD), Piping Instrument diagram (PID), SLD, Plant destination, Cable Diagram, Functional description Engineering of Detail design : Flow chart for DCS, Static Display, Cable route, Panel & control desk assembly drawing, Circuit Diagram, Cable Schedule, lighting layout & Assembly drawing, Bill of Quantity Software Development: Programming DCS of Crusher Inter locking & sequence, Skyline conveyor Inter locking & sequence, tripper Inter locking & sequence , Barge loading conveyor Inter locking & sequence Start –stop auto, grease & lubrication system Pump station, MDP interlocking. Construction & Installation of : Genset 4 x 2 MVA,Trafo 6 KV/400V 4 x 2 MVA, Switchgear 6 KV, Motor Control Centre, Main Distribution Panel, DCS Panel, 10 x Inverter Motor Drive Panel, 10 x 350 KW motor, 10 x 75 Kw Motor, 4 x 15 kw motor, Sensor & Instrument Proximity switch, Limit switch, Pulse encoder : 260 unit, Selenoid valve:60 unit, Tunnel Lighting : 250 unit, Field Lighting : 350 unit, Road Lighting : 400 unit, Cable tray –Ladder , Pulling & connecting Power Cable & Cable control, Cable Power Testing & Megger test , I/O test, Cable Power Megger test , Function test, No-load test, Hot Commissioning test)
o New Crusher Plant , Skyline Conveyor, Under line conveyor & Barge loading conveyor turn key project ,Sambarata Upgrade1 (SUG4), PT.Berau coal, Berau, East Kalimantan Engineering of Basic design: Load Flow analyze, Short circuit calculation, Voltage drop calculation, Process Flow diagram (PFD), Piping Instrument diagram (PID), SLD, Plant destination, Cable Diagram, Functional description Engineering of Detail design : Flow chart for DCS, Static Display, Cable route, Panel & control desk assembly drawing, Circuit Diagram, Cable Schedule, lighting layout & Assembly drawing, Bill of Quantity Software Development: Programming DCS of Crusher Inter locking & sequence, Skyline conveyor Inter locking & sequence, tripper Inter locking & sequence , Barge loading conveyor Inter locking & sequence Start –stop auto, grease & lubrication system Pump station, MDP interlocking. Construction & Installation of : Genset 4 x 2 MVA, Trafo 6 KV/400V 4 x 2 MVA, Switchgear 6 KV, Motor Control Centre, Main Distribution Panel, DCS Panel,12 x Inverter Motor Drive Panel, 12 x 350 KW motor, 10 x 75 Kw Motor, 8 x 15 kw motor, Sensor & Instrument Proximity switch, Limit switch, Pulse encoder : 340 unit, Selenoid valve: 60 unit, Tunnel Lighting : 400 unit, Field Lighting : 450 unit, Road Lighting : 300 unit, Cable tray –Ladder , Pulling & connecting Power Cable & Cable control, Cable Power Testing & Megger test , I/O test, Cable Power Megger test , Function test, No-load test, Hot Commissioning test)
![Page 8: CV indra lukman new r21](https://reader036.vdocuments.us/reader036/viewer/2022071702/55c42f3cbb61ebc1628b463e/html5/thumbnails/8.jpg)
Indra Lukman Page 8
o Meratus Rotary Kiln 350.000. ton/year Turn Key Project, Tanah Bumbu,
Batu licin ,South Kalimantan.
Engineering of Basic design: Load Flow analyze, Short circuit calculation, Voltage drop calculation, Process Flow diagram (PFD), Piping Instrument diagram (PID), SLD, Plant destination, Cable Diagram, Functional description Engineering of Detail design : Flow chart for DCS, Static Display, Cable route, Panel & control desk assembly drawing, Circuit Diagram, Cable Schedule, lighting layout & Assembly drawing, Bill of Quantity Software Development: Programming DCS of Rotary Kiln Inter locking & sequence, Skyline conveyor Inter locking & sequence, Reformer Inter locking & sequence , Close loop control, Start –stop auto, Hydraulic, grease & lubrication system Pump station, MDP interlocking. Construction & Installation of : Co-generation power Plant 2 x 15 MVA, Trafo 6 KV/400V 10 x 2 MVA, Switchgear 6 KV, Motor Control Centre, Main Distribution Panel, DCS Panel,30 x Inverter Motor Drive Panel, 4 x 500 KW motor, 10 x200 Kw Motor, 8 x 75 kw motor, 40 x 15 kw motor,Sensor & Instrument Proximity switch, Limit switch, Pulse encoder , Pressure switch, Level switch, flow switch, flow meter, Temperature switch: 8000 unit, Selenoid valve: 1000 unit, Tunnel Lighting : 100 unit, Field Lighting : 650 unit, Road Lighting : 300 unit, Cable tray –Ladder , Pulling & connecting Power Cable & Cable control, Cable Power Testing & Megger test , I/O test, Cable Power Megger test , Function test, No-load test, Hot Commissioning test)
Oct 2010 Dec -2013 PT.Permata Prima Indonusa (EPC) , Jakarta ,Indonesia As a Managing director
· Safety, Health, Environment and Quality: Ensure that the organization operates its business within the compliance to all OHSAS policies and regulations.
· Cost and Productivity: keep operational and CAPEX costs at a minimal to effectively continue to maximize storage capacity and expand market share.
· Profit: given the constraints of the facilities, maintain and develop the customers such that the profits and the long term sustainability of the profits are optimised
· Enhanced Customer Service: ensure that staff appreciate and are able to speedily and
· Quality products and services: ensure development of disciplined method to improve operations processes by leading team in developing a quality focused work culture by aligning old and new mindsets to embrace a common perspective, spearhead cross-departmental quality initiatives to deliver quality products at lowest cost, fastest time
· Human Resource Capability: ensure a strong bench strength of internal capability by working closely with managers to attract, identify, coach, motivate and develop a stable internal core set of talent through broadening their overall cross training and skill-set repertoire such that talent can be regionally transferable for any operational expansion efforts, hence spreading the consistency and standard of technology and knowledge across the network
· Customer relations: build and maintain excellent working relationships with management
· Supplier relations: build and maintain high level relationships with key suppliers and business partners, in close cooperation with local and industry management, to establish continuous clarity regarding business goals, whilst leveraging business opportunities with them
· Reporting: ensure regular review and reporting of progress in realization of business plans and results
![Page 9: CV indra lukman new r21](https://reader036.vdocuments.us/reader036/viewer/2022071702/55c42f3cbb61ebc1628b463e/html5/thumbnails/9.jpg)
Indra Lukman Page 9
And As a Project Director Of
· Project manager Plans, directs, and coordinates activities of designated project to ensure that goals or objectives of project are accomplished within prescribed time frame and funding parameters.
· Reviews project proposal or plan to determine time frame, funding limitations, procedures for accomplishing project, staffing requirements, and allotment of available resources to various phases of project.
· Establishes work plan and staffing for each phase of project, and arranges for recruitment or assignment of project personnel.
· Confers with project staff to outline work plan and to assign duties, responsibilities, and scope of authority.
· Directs and coordinates activities of project personnel to ensure project progresses on schedule and within prescribed budget.
· Reviews status reports prepared by project personnel and modifies schedules or plans as required. Prepares project reports for management, client, or others.
· Confers with project personnel to provide technical advice and to resolve problems.
· May also coordinate project activities with activities of government regulatory or other governmental agencies.
· Responsible for overall quality and management of major projects or programs.
· Research current education and training needs. · Research grant funding sources. · Develop grant proposals. · Oversee budget and ensure financial accountability. · Hire personnel for program/project implementation. · Train staff. · Typically responsible for supervision of classified staff. · Supervise program delivery, assess client needs.
· Recognize and solve potential problems and evaluate project/program effectiveness.
· Established operating procedures for project/program. Ensure procedures meet program goals.
· Provide program content expertise, which may include delivering in-service training and direct programming.
· Conducts research and write reports/articles. List Of Project
o Pusher Reheating Furnace 30 t/h Upgrading (conversion from Fuel oil to Fuel gas) Turnkey Project (Mechanical, Electrical, Automation & Instrumentation), Barmill, PT. Krakatau Wajatama, Cilegon, , Indonesia Engineering of Basic design: Load Flow analyze, Short circuit calculation, Voltage drop calculation, Process Flow diagram (PFD), Piping Instrument diagram (PID), SLD, Plant destination, Cable Diagram, Functional description Engineering of Detail design : Flow chart for DCS, Static Display, Cable route, Panel & control desk assembly drawing, Circuit Diagram, Cable Schedule, lighting layout & Assembly drawing, Bill of Quantity Software Development: Programming DCS of Material handling Inter locking & sequence,Combustion close loop control, Dillution control, Air chamber Pressure closeloop control,Start –stop auto, Grease,Lubrication & Hydraulic system Pump station, Switchgear 6kv interlocking. Construction & Installation of : Trafo 6 KV/400V 1x 1 MVA, Switchgear 6 KV, Motor Control Centre, Main Distribution Panel, DCS Panel, 8 x Converter Motor Drive Panel, Battery charger &
![Page 10: CV indra lukman new r21](https://reader036.vdocuments.us/reader036/viewer/2022071702/55c42f3cbb61ebc1628b463e/html5/thumbnails/10.jpg)
Indra Lukman Page 10
UPS system, 8 x 75 KW motor, 15 x 15 kw motor, Sensor & Instrument Proximity switch, Limit switch, Pressure switch, Flow switch, Level switch, Hot metal detector, pulse encoder : 80 unit, Selenoid valve, Actuator : 40 unit, Cable tray –Ladder , Pulling & connecting Power Cable & Cable control, Cable Power Testing & Megger test , I/O test, Cable Power Megger test , Function test, No-load test, Hot Commissioning test)
o Walking Beam Reheating Furnace 60 t/h Upgrading (conversion from Fuel oil to BiFuel :fuel gas& fuel oil) Turnkey Project (Mechanical, Electrical, Automation & Instrumentation), Section Mill, PT.Krakatau Wajatama, Cilegon, , Indonesia Engineering of Basic design: Load Flow analyze, Short circuit calculation, Voltage drop calculation, Process Flow diagram (PFD), Piping Instrument diagram (PID), SLD, Plant destination, Cable Diagram, Functional description Engineering of Detail design : Flow chart for DCS, Static Display, Cable route, Panel & control desk assembly drawing, Circuit Diagram, Cable Schedule, lighting layout & Assembly drawing, Bill of Quantity Software Development: Programming DCS of Material handling Inter locking & sequence,Combustion close loop control, Dillution control, Air chamber Pressure closeloop control,Start –stop auto, Grease,Lubrication & Hydraulic system Pump station, Switchgear 6kv interlocking. Construction & Installation of : Trafo 6 KV/400V 1 x 1 MVA, Switchgear 6 KV, Motor Control Centre, Main Distribution Panel, DCS Panel, 8 x Converter Motor Drive Panel, Battery charger & UPS system, 8 x 100 KW motor, 20 x 15 kw motor, Sensor & Instrument Proximity switch, Limit switch, Pressure switch, Flow switch, Level switch, Hot metal detector, pulse encoder : 120 unit, Selenoid valve, Actuator : 60 unit, Cable tray –Ladder , Pulling & connecting Power Cable & Cable control, Cable Power Testing & Megger test , I/O test, Cable Power Megger test , Function test, No-load test, Hot Commissioning test)
o MG set drive Upgrading (conversion to Converter Drive) Turnkey Project
( Electrical, Automation & Instrumentation) , Barmill, PT.Krakatau Wajatama, Cilegon, Indonesia
o Belt Scale Installation & Upgrading Project (Mechanical, Electrical,
Automation & Instrumentation), PT.Krakatau Steel, Cilegon, , Indonesia
o Revamping R10 COLD SAW and STACKING MACHINE (Electrical,
Automation & Instrumentation), Turnkey Project Section Mill , PT.Krakatau Wajatama, Cilegon, , Indonesia
o IP4 & Lakitan Terminal Coal Handling Facility Document tender (Mechanical, Electrical, Automation & Instrumentation),Engineering project, PT. Sriwijaya Bintang Energi,Muara Lakitan, Sumatera Selatan , Indonesia Engineering of Basic design: Load Flow analyze, Short circuit calculation, Voltage drop calculation, Process Flow diagram (PFD), Piping Instrument diagram (PID), SLD, Plant destination, Cable Diagram, Functional description Engineering of Detail design : Flow chart for DCS, Static Display, Cable route, Panel & control desk assembly drawing, Circuit Diagram, Cable Schedule, lighting layout & Assembly drawing, Bill of Quantity
![Page 11: CV indra lukman new r21](https://reader036.vdocuments.us/reader036/viewer/2022071702/55c42f3cbb61ebc1628b463e/html5/thumbnails/11.jpg)
Indra Lukman Page 11
o Lubuk Tutung Terminal Coal Handling Facility Document tender (Mechanical, Electrical, Automation & Instrumentation ), Engineering Project ,PT.Bakti Energi Persada , LUBUK TUTUNG, KEC. MUARA WAHAU, KAB.KUTAI TIMUR, EAST KALIMANTAN, Indonesia Engineering of Basic design: Load Flow analyze, Short circuit calculation, Voltage drop calculation, Process Flow diagram (PFD), Piping Instrument diagram (PID), SLD, Plant destination, Cable Diagram, Functional description Engineering of Detail design : Flow chart for DCS, Static Display, Cable route, Panel & control desk assembly drawing, Circuit Diagram, Cable Schedule, lighting layout & Assembly drawing, Bill of Quantity
o Terminal Coal Handling Facility Document tender (Mechanical, Electrical, Automation & Instrumentation), Engineering Project ,PT.Indomining, Sanga-Sanga, Kutai Kartanegara, EAST KALIMANTAN, Indonesia Engineering of Basic design: Load Flow analyze, Short circuit calculation, Voltage drop calculation, Process Flow diagram (PFD), Piping Instrument diagram (PID), SLD, Plant destination, Cable Diagram, Functional description Engineering of Detail design : Flow chart for DCS, Static Display, Cable route, Panel & control desk assembly drawing, Circuit Diagram, Cable Schedule, lighting layout & Assembly drawing, Bill of Quantity
o Terminal Coal Handling Facility Document tender (Mechanical, Electrical, Automation & Instrumentation), Engineering Project , PT.Atlas Resources Tbk, Lahat, KEC. Muara Enim, KAB.Musi Banyuasin , SOUTH SUMATERA , Indonesia
Engineering of Basic design: Load Flow analyze, Short circuit calculation, Voltage drop calculation, Process Flow diagram (PFD), Piping Instrument diagram (PID), SLD, Plant destination, Cable Diagram, Functional description Engineering of Detail design : Flow chart for DCS, Static Display, Cable route, Panel & control desk assembly drawing, Circuit Diagram, Cable Schedule, lighting layout & Assembly drawing, Bill of Quantity
Dec 2013 Nov -2014 PT.CMIP (Engineering services & Trading) , Jakarta As a Director List Of Project
June 2014 -now
o Mechanical, Electrical, Automation & Instrumentation Engineering Services ( Engineering Consultant ) , Indarung VI Cement Plant On going Project , PT.Cement Padang/Indonesia, Padang, Indonesia as Lead Electrical & Instrument Engineer Engineering of Basic design: Load Flow analyze, Short circuit calculation, Voltage drop calculation, Process Flow diagram (PFD), Piping Instrument diagram (PID), SLD, Plant destination, Cable Diagram, Functional description Engineering of Detail design : Flow chart for DCS, Static Display, Cable route, Panel & control desk assembly drawing, Circuit Diagram, Cable Schedule, lighting layout & Assembly drawing, Bill of Quantity
![Page 12: CV indra lukman new r21](https://reader036.vdocuments.us/reader036/viewer/2022071702/55c42f3cbb61ebc1628b463e/html5/thumbnails/12.jpg)
Indra Lukman Page 12
Dec 2014 -now PT.Arkon Prima Indonesia (Fabricator &Engineering services) , Jakarta As a Staff Director List Of Project
o Pre Feasibility study for Bio-mass Power plant Preparation
WBS Man power Planning Schedule & S-Curve Budgeting proposal Proposal accepting by Management
Execution Market considerations
Demand/Costumers Supply/Competitors Marketing considerations for Biomass feedstock Marketing considerations for By-Product
Raw Material availability Organizational Structure
Commercial Management Biomass Supply chain Transmission Plant and Biomass supply chain personnel
Technical considerations Plant technology evaluation Biomass supply chain technical approach "Plant size,Location and equipment needs" FEED ENGINEERING
CIVIL & STRUCTURE MECHANICAL ELECTRICAL & INSTRUMENT
BASIC ENGINEERING CIVIL & STRUCTURE MECHANICAL ELECTRICAL & INSTRUMENT
BILL OF QUANTITY ENGINEERING ESTIMATE
Environmental and community considerations Plant Locations details Permits and Environmental protection measures Community impact
Financial Analysis Key Assumptions Finacial Analysis and data
Conclusions and Recommendations
![Page 13: CV indra lukman new r21](https://reader036.vdocuments.us/reader036/viewer/2022071702/55c42f3cbb61ebc1628b463e/html5/thumbnails/13.jpg)
Indra Lukman Page 13
ADDITIONAL EXPERIENCES: PT.Mitra Dinamika (Engineering Servives), Jakarta ,Indonesia 2007-2008 As an Executive Technical advisor PT.Krakatau Engineering (EPC-PM ), Cilegon ,Indonesia 2004-2005 As an Executive Technical advisor INTERNATIONAL DEVELOPMENT EXPERIENCE: ABB Industrial AB, Vasteras Sweden March-April , 1997 Lead Software Development Engineer
• Pre Roughing Mill automation software development Phase 1
ABB Industrial AB, Vasteras Sweden October-December , 1997 Lead Software Development Engineer
• Pre Roughing Mill automation software development Phase 2 EDUCATION: Bachelor degree, Electrical engineering August, 1985 Study of unit generators selection for electric power capacity in the oil industry-Caltex, Indonesia University of Indonesia, Jakarta, Indonesia Master Degree, Material Engineering October, 1996 Wire Rod cooling Treatment with Stelmor Process University of Wollongong, New South Wales, Australia CERTIFICATIONS/LICENSES: Relevant Trainings: 1988 : National Character Building P4 Type A Advanced level Duration of training- 3 weeks (26 September - 14 Oktober 1988) At Pusdiklat Krakatau Steel, Cilegon, Indonesia 1989 : Productivity Analisys for Corporate Duration of training- 2 weeks (19 July - 2 Agustus 1989) At Departemen Tenaga Kerja Republik Indonesia, Cilegon , Indonesia
: LeadershipTraining Duration of training- 2 weeks (23 January – 27 January 1989) At Pusdiklat, PT.Krakatau Steel, Cilegon , Indonesia 1991 : Steel High Speed No Twist Mill , ROD MILL operation & Rolling Practice
Duration of training- 6 weeks (26 July -6 September 1991) At BHP Steel, New Castle, Australia : Seminar system Instrumentasi dan Kontrol berbasis komputer
Duration of training- 2 days (6 February -7 February1991) At ITB , Bandung ,Indonesia. 1992 : B 20 , ABB Master Piece 200, Configuration & Operation
![Page 14: CV indra lukman new r21](https://reader036.vdocuments.us/reader036/viewer/2022071702/55c42f3cbb61ebc1628b463e/html5/thumbnails/14.jpg)
Indra Lukman Page 14
Duration of training- 1 week (23 April - 29 April 1992) At ABB Automation AB, Vasteras , Sweden : D 40 , ABB Master Piece 200, Service Duration of training- 1 week (4 May - 8 May 1992) At ABB Automation AB, Vasteras , Sweden : TLS 10 , ABB DC Drive Digital Converter Tyrak L Duration of training- 1 week (11 May - 15 May 1992) At ABB Automation AB, Vasteras , Sweden 1993 : Siemens S5 PLC Hardware, Installation & Programming : INOS Supervisory System :Configuration & Operation : ProOpt Optimisation Computer : Installation, Programming & Operation
Duration of training- 1 month (20 June - 21 July 1993 At LVE Verfahrens elektronik GmbH, Essen , West Germany (FRG)
: Total productive Maintenance Duration of training- 1 month (03 October 1995 – 11October 1995)
At PQM ,Jakarta 1996 : ABB MasterView 800 Configuration & Operation Duration of training- 1 week (15 January - 19 January 1996) At ABB Industry Pte Ltd, Singapore : ABB MasterView 800 Advanced Configuration & Operation Duration of training- 1 week (22 January - 26 January 1996) 1997 : IBM DB 2 Fundamental Duration of training- 1 week (9 January - 10 January 1997) At IBM, Cilegon , Indonesia 1998 : Out line of Equipment the Reheating Furnace for Wire Rod mill
: Specifications and function of each equipment : Operation and Maintenance for Electrical Equipment : Operation and Maintenance for Field Instrument Equipment
: ABB Control System Application for The Reheating Furnace Duration of Training - 2 months (20 October - 20 November 1998)
At Krosaki Furnace Manufacturing , Tokyo , Japan 1999 : Coaching The Winner Duration of training – 1 week (28,29, 30 April – 1 May 1999) At HRD Indonesia , Lembang, Bandung, Indonesia 2002 : Project Management Guide line- Workshop Duration of training- 1 week (14 May - 17 may 2002) At Project Management Institute, PT. Prosys Bangun Persada, Jakarta, Indonesia 2003 : T530 Configuring AC800M/C using Control builder M Professional
Duration of training- 1 week (29 September - 3 October 2003) At ABB Industry Pte Ltd, Singapore : T685 Configuring and Opertaing Proces Portal A with AC800M/C Connect
Duration of training- 1 week (6 October - 10 October 2003) At ABB Industry Pte Ltd, Singapore : ESQ leadership Training
Duration of training – 1 week ( 2 March – 4 march 2003) At Pusdiklat PT. Krakatau Steel, Cilegon , Indonesia 2004 : Project Management for Project Owner - Workshop Duration of training- 1 week (20 September - 24 September 2004)
![Page 15: CV indra lukman new r21](https://reader036.vdocuments.us/reader036/viewer/2022071702/55c42f3cbb61ebc1628b463e/html5/thumbnails/15.jpg)
Indra Lukman Page 15
At PT. Krakatau Engineering & PT. Tracon Industri, Cilegon , Indonesia 2014 : Training for The National Construction Experts Competencies Assessor Duration of training- 1 week (11 June – 13 June 2014) LPJKN, Jakarta , Indonesia
PROFESSIONAL AFFILIATIONS: Indonesia Engineer Association (PII) .Member No: 1015-02-003683 Indonesia Professional Engineer (IP) ,Member No: 1-02-00-000001-00 Indonesia Professional Engineer Association (PIPI), Member No: E.00434 Ahli Teknik Tenaga listrik - Utama , National Construction Services Development Board (LPJKN), Member No:144011040091064574 Head of Electrical Engineering Department, Indonesia Professional Engineer Association (PIPI) Assessors The National Construction Experts Competencies No: 1286/AKTK-LPJK /VII/2014, National Construction Services Development Board (LPJKN) SKILLS/LANGUAGES/GEOGRAPHICAL EXPERIENCE: Computer Skills: Microsoft Project,Microsoft Power Point, Microsoft Excel, Microsoft Word, CAD, Visio Languages: Indonesia (mother tongue); English (fluent); English (professional proficiency) REFERENCES: Robin Scowcroft President Director – PT.ESSAR Projects Indonesia Phone No.: +6281315501864| Email Address: [email protected] Anil Bathia VP Business development – ABB Sakti Industri Indonesia Phone No.: +628121087084| Email Address: [email protected] Kevin Mennell Chief Operating Officer – Essa Australasia Phone No.: +61409378599 | Email Address: [email protected] Herry Hendayanto Director of business & Operation II – PT.Krakatau Engineering, Indonesia Phone No.: +62811197860| Email Address: [email protected] Budijanto gunawan Manager of Costumer Management – Schneider Electric, Indonesia Phone No.: +62811800849| Email [email protected] Jasbir Singh VP Business Development – PT.ESSAR Projects Indonesia Phone No.: +628788184846| Email Address: [email protected]
![Page 16: CV indra lukman new r21](https://reader036.vdocuments.us/reader036/viewer/2022071702/55c42f3cbb61ebc1628b463e/html5/thumbnails/16.jpg)
Indra Lukman Page 16
Andi Soko Deputy Director Engineering & Construction – PT.Krakatau Posco Indonesia Phone No.: +628111680780| Email Address: [email protected] Dr.Ir.Daenulhay.MM President Commissioner – PT.Kerismas Witikco Makmur Phone No.: +6287174898989| Email Address: [email protected] Idham ZA.SE.MM President Director – PT.Peruri Wira timur , Security printing Phone No.: +628158302665| Email Address: [email protected] Ir.Imam purwanto Procurement & Logistic Director – PT.Krakatau Steel , Phone No.: +62811121689 | Email Address: [email protected] Ir.Montery Darwin Head of permanent Committee for Consultancy of Construction Services , Jakarta Chamber of Commerce & Industry (KADIN-DKI Jakarta) Phone No.: +62818140622 | Email Address: [email protected]