3March 10, 2016 Format of Today’s Discussion DR Testing broken down into discrete stages of the testing lifecycle. For each stage, identify issues & challenges. Openly discuss ways to address or mitigate impact.TRANSCRIPT
![Page 1: CSC DR Testing – a Discussion Ben Scheltus 13 March, 2014 Client Logo](https://reader036.vdocuments.us/reader036/viewer/2022090107/5a4d1be17f8b9ab0599df583/html5/thumbnails/1.jpg)
CSC
DR Testing – a Discussion
Ben Scheltus13 March, 2014
Client Logo
![Page 2: CSC DR Testing – a Discussion Ben Scheltus 13 March, 2014 Client Logo](https://reader036.vdocuments.us/reader036/viewer/2022090107/5a4d1be17f8b9ab0599df583/html5/thumbnails/2.jpg)
2 May 14, 2023
Recent large waves hit the lighthouse and harbour at high tide at Newhaven in Sussex, EnglandSource – Reuters – Luke McGregor.
![Page 3: CSC DR Testing – a Discussion Ben Scheltus 13 March, 2014 Client Logo](https://reader036.vdocuments.us/reader036/viewer/2022090107/5a4d1be17f8b9ab0599df583/html5/thumbnails/3.jpg)
3 May 14, 2023
Format of Today’s Discussion
• DR Testing broken down into discrete stages of the testing lifecycle.• For each stage, identify issues & challenges. • Openly discuss ways to address or mitigate impact.
![Page 4: CSC DR Testing – a Discussion Ben Scheltus 13 March, 2014 Client Logo](https://reader036.vdocuments.us/reader036/viewer/2022090107/5a4d1be17f8b9ab0599df583/html5/thumbnails/4.jpg)
4 May 14, 2023
Funding & Approvals
Issue/Challenge Strategy/MitigationPoor understanding by management on value/purpose of DR testing.
Leverage BIA. Applicable regulations?Executives sign off on DR Strategy & required investment.
Generally, purpose and value of DR is not well understood.
Value business processes in the BIA and use it to build the business case.
A DRP exists – but never tested properly.
Highlight exposure and importance of testing in a changing environment.
Estimating the effort. Regularly collect previous testing cost data
![Page 5: CSC DR Testing – a Discussion Ben Scheltus 13 March, 2014 Client Logo](https://reader036.vdocuments.us/reader036/viewer/2022090107/5a4d1be17f8b9ab0599df583/html5/thumbnails/5.jpg)
5 May 14, 2023
Planning
Issue/Challenge Strategy/MitigationTechnical recovery procedures development.
Start early, follow up regularly and highlight their importance.
Scheduling a new system test into a large on going program.
Management approved test schedule. Defined in policy? Lock down scope tightly.
Criteria for retesting a system that has been tested previously.
Establish in DR Strategy. Clear definitions.
Timing of new systems test. Carefully consider key activity dates in the organisation. Well communicated and approved test schedule
Type of test – simulation or failover. Many small tests or one big one?
Consider maturity of organisation, previous experience and availability of skilled resources.
![Page 6: CSC DR Testing – a Discussion Ben Scheltus 13 March, 2014 Client Logo](https://reader036.vdocuments.us/reader036/viewer/2022090107/5a4d1be17f8b9ab0599df583/html5/thumbnails/6.jpg)
6 May 14, 2023
Test Execution
Issue/Challenge Strategy/MitigationSchedule – time of day, day of week? International time zones.
Consult widely with the business. Defined in the Test Plan document.
Appropriate participation by stakeholders.
Early buy in from the business
Communications & escalations. Communications plan agreed in advance with milestones and contact lists.
Scope creep. Locked in scope in Test Plan. Gaps identified during test are documented and included in future test.
![Page 7: CSC DR Testing – a Discussion Ben Scheltus 13 March, 2014 Client Logo](https://reader036.vdocuments.us/reader036/viewer/2022090107/5a4d1be17f8b9ab0599df583/html5/thumbnails/7.jpg)
7 May 14, 2023
Reporting & Documentation
Issue/Challenge Strategy/MitigationOrganising Test Reports. Regularly revisit suitability of structure
and be adaptable to change if necessary.
Appropriate detail. Importance of Executive Summary and conclusions.
When things don’t work as planned. Unemotional language in report. You test to identify issues.
Timeliness Ensure reports are published promptly.
Candour Substantiate the bad news.
![Page 8: CSC DR Testing – a Discussion Ben Scheltus 13 March, 2014 Client Logo](https://reader036.vdocuments.us/reader036/viewer/2022090107/5a4d1be17f8b9ab0599df583/html5/thumbnails/8.jpg)
8 May 14, 2023
Maintenance
Issue/Challenge Strategy/MitigationChange management Have clearly established rules for what
size/scope of change warrants a re-test.Change management systems.
Maintaining currency of DRP. Regularly review document.
Maintaining compliance. Track changes in regulations.
Rapidly changing business environment.
Regularly revisit BIA.