cost efficiency of the design plans for the market street drainage improvements project
TRANSCRIPT
Running head: COST EFFICIENCY OF THE MARKET STREET TUNNEL 1
Cost Efficiency of the Design Plans For
The Market Street Drainage Improvements Project
Katie Kassouf
Academic Magnet High School
COST EFFICIENCY OF THE MARKET STREET TUNNEL 2
Abstract
Since its establishment, the City of Charleston, South Carolina, has sought to develop an
efficient drainage system to relieve its downtown streets from flash flooding. Urban flooding
occurs most frequently during the summer months and can result from periods of high tide and
heavy rain. To alleviate this problem, the City of Charleston launched the Market Street
Drainage Improvements Project in an effort to install stormwater drainage networks in the
downtown area. Through this study, the researcher will evaluate the cost efficiency of Division II
of this project in terms of the money saved by the City of Charleston.
COST EFFICIENCY OF THE MARKET STREET TUNNEL 3
Table of Contents
Cost Efficiency of the Design Plans For ......................................................................................... 4
The Market Street Drainage Improvements Project ....................................................................... 4 Statement of Need ........................................................................................................................... 4 Main Goal ....................................................................................................................................... 6
Methods........................................................................................................................................... 7 Significance..................................................................................................................................... 8
Applicability.................................................................................................................................... 9 Chapter II: Review of Literature ................................................................................................... 10 Constructing Flood Relief Systems for the City of Charleston .................................................... 11
Initial Drainage Design: Network of Brick Arches ................................................................... 11 Sanitation System Improvements and the Plum Island Wastewater Treatment Plant ............... 13
Development and Deterioration of the Original Cooper River Tunnel ..................................... 14 Emergency Sewer System Replacement Program .................................................................... 16 1984 Master Drainage and Floodplain Management Plan by Davis & Floyd, Inc. .................. 17
Calhoun Street East Drainage Improvements Project ............................................................... 19 Market Street Drainage Improvements Project ......................................................................... 20
Division III : Spring/Fishburne Drainage Project ..................................................................... 24 Change Order for the Design of the Market Street Tunnel........................................................... 27
Increased Depth of the Market Street Tunnel............................................................................ 28
Decreased Slope of the Market Street Tunnel ........................................................................... 35 Connection to Concord Street Pump Station vs. Calhoun Street Tunnel .................................. 38
Final Lining of the Market Street Tunnel .................................................................................. 39 Elimination of Ground Freezing at Junction of Market Street and Calhoun Street Tunnels .... 40
Chapter III: Methods ..................................................................................................................... 43
Materials........................................................................................................................................ 44 Procedures ..................................................................................................................................... 44
Evaluation ..................................................................................................................................... 46 Conclusion .................................................................................................................................... 46 Chapter IV..................................................................................................................................... 47
Increased Depth of the Market Street Tunnel ............................................................................... 47 Decreased Slope of the Market Street Tunnel .............................................................................. 54
Connection to Concord Street Pump Station vs. Calhoun Street Tunne l ..................................... 55 Final Lining of the Market Street Tunnel ..................................................................................... 57 Elimination of Ground Freezing ................................................................................................... 58
Total Savings................................................................................................................................. 59 Chapter V ...................................................................................................................................... 60
Principal Findings and Interpretation of Data............................................................................... 60 Implications................................................................................................................................... 61 Limitations .................................................................................................................................... 62
Summary ....................................................................................................................................... 62 References ..................................................................................................................................... 64
COST EFFICIENCY OF THE MARKET STREET TUNNEL 4
Cost Efficiency of the Design Plans For
The Market Street Drainage Improvements Project
Since its founding, the City of Charleston, South Carolina, has struggled to find a
solution to the excessive flooding that plagues its downtown streets. Urban flooding results from
a combination of high tides, heavy rain, near sea level elevation, flat topography, and a lack of
adequate drainage systems in the downtown area (Cabiness, Kirk, O’Connell, & Swartz, 2012).
Furthermore, Charleston is part of the Low Country, a region consisting of “low-lying terrain”
that naturally retains an “abundance of water” due to its proximity to the Atlantic Ocean (GORP,
2010, p. 1). The Low Country’s table-top topography and close-to sea level elevation prevent
accumulated surface water from draining quickly; thus, an event as minor as a high tide can
potentially “result in hours of standing water” (Cabiness et al., 2012). The most severe flooding
occurs in the downtown areas closest to Charleston Harbor when heavy rain coincides with high
tidal events (O’Connell, 2013). Such flooding poses health hazards to drivers, pedestrians, and
residents in the Charleston area. Although several different drainage systems have been
implemented in Charleston since the mid-1800s, none of them have proven adequate. Hence, the
City of Charleston launched the Market Street Drainage Improvements Project in 2006 to combat
problematic downtown flooding (Kirk, n.d.-a). Ultimately, this thesis will examine the cost
efficiency of this current design in terms of the money saved by the City of Charleston during the
course of the project.
Statement of Need
Simply stated, stormwater is excess ground surface water created by events such as heavy
rains and high tides; furthermore, large concentrations of stormwater can produce flooding in
areas that do not possess adequate drainage infrastructure. Since the mid-1800s, several types of
COST EFFICIENCY OF THE MARKET STREET TUNNEL 5
stormwater collection systems have been implemented in Charleston to decrease regional
flooding. As early as 1837, solutions to this problem were prompted by the mayor’s offer of a
$100 gold piece for the best proposed flood relief system (Slade, 2013). Following this generous
proposition, city engineers constructed the first drainage design ever attempted in Charleston: a
network of brick arches installed in the downtown area (O’Connell, 2013). Although this system
provided minimal flood relief, it did not prove efficient for the City of Charleston because of its
small size (Drolet, Cabiness, Swartz, & O’Connell, 2012). City engineers continued to struggle
with inadequate designs for several years. Then, in 1984, Davis & Floyd, Inc., produced a Master
Plan to improve the city’s stormwater collection systems. Unlike the network of brick arches, the
1984 Master Plan divided and directed Charleston’s stormwater into catch basins situated around
the city (O’Connell, 2013). In 1997, Davis & Floyd, Inc., in association with URS Corporation,
initiated preparations for a key component of this Master Plan, called the Market Street Drainage
Improvements Project (O’Connell, 2013). City officials selected a deep tunnel system as the
design for this project to protect the urban and historic structures surrounding the proposed
project location, an intersection in downtown Charleston. Specifically, a deep tunnel system is a
network of large, underground sewers that stores excess water until it can be released at a desired
location (Milwaukee Metropolitan Sewer District, n.d.). However, a lack of funding prevented
the city from launching Division I of this project until 2006 (Kirk, n.d.-a). In July 2012, city
officials awarded the contract for Division II to the joint venture of Triad Midwest Mole
(O’Connell, 2013). Upon receiving the contract for the project, the joint venture proceeded to
make several significant changes to the original construction plans for the Market Street Tunnel
to increase the safety of the tunnel installation process. While several tunneling systems have
been implemented in Charleston in the past to provide flood relief and wastewater conveyance
COST EFFICIENCY OF THE MARKET STREET TUNNEL 6
for the area, no cost efficiency study has been conducted on any of these construction projects to
date. Furthermore, no cost analysis has been performed for the construction of an inner-city deep
tunnel system for the Charleston area. Hence, this thesis will provide a cost efficiency analysis of
the construction methods used to install the Market Street Tunnel and will compare that data to
the projected cost of the tunnel as indicated by the original blueprints for the project.
Main Goal
The governing question for this thesis is, how have the proposed changes to the original
plans for the Market Street Drainage Improvements Project affected the cost efficiency of this
design in terms of the money saved by the City of Charleston?
The initial designs for the Market Street Tunnel were created in 1997 by Davis & Floyd,
Inc., in association with URS Corporation, to provide flood relief for downtown Charleston
(O’Connell, 2013). However, Triad Midwest Mole proposed that specific areas of the plans be
changed in order to increase project efficiency. Thus, the purpose of this study is to examine the
modifications made to the construction plans for the Market Street Tunnel and to quantify the
money the city has saved because of these alterations.
Due to Charleston’s nearly sea level elevation, flat topography, and proximity to the
Atlantic Ocean, the city experiences severe flash flooding during periods of high tide and heavy
rain (Cabiness et al., 2012). Thus, the Market Street Tunnel is being installed to help compensate
for a lack of adequate drainage systems in the downtown area. The goal of this improvements
project is to spare residents the danger of traveling on flooded roads and to improve urban health
conditions by draining stormwater from street surfaces (Slade, 2013). Additionally, this thesis
satisfies a gap in the civil engineering field by providing a detailed cost analysis on a tunneling
project in Charleston. To the best of the researcher’s knowledge, no substantial cost efficiency
COST EFFICIENCY OF THE MARKET STREET TUNNEL 7
study has ever been conducted for a deep tunnel system in this area. Furthermore, this thesis may
provide a point of reference for future tunnel contractors in Charleston by demonstrating how
certain construction methods can increase the economic efficiency, and ultimately the success, of
their own projects. Therefore, this thesis may prove useful to current and future experts in the
civil engineering field.
Methods
To collect data for this thesis, the researcher has performed a cost-analysis of the
construction methods used to implement the Market Street Drainage Improvements Project.
Specifically, the researcher has focused on the modifications made to the original plans by Davis
& Floyd, Inc. A cost efficiency comparison between the altered portions of the 1997 blueprints
and the corresponding sections of the current design has provided the researcher grounds upon
which to estimate the amount of money the City of Charleston has saved during the course of the
project. To substantiate this cost analysis, the researcher has collected quotes for materials,
wages for laborers, and operating and installation costs for construction equipment. In addition,
the researcher has consulted design engineers from Triad Midwest Mole to verify that the
collected data is correct. Moreover, the researcher has calculated the difference between the costs
of the proposed Davis & Floyd, Inc. plans and the modified designs by Triad Midwest Mole.
Therefore, the researcher has estimated the amount of money saved by the City of Charleston as
a result of the design alterations to the Market Street Tunnel.
This thesis is classified as a case study because it only focuses on one construction
project in the civil engineering field. Furthermore, the researcher has collected qualitative and
quantitative data and has used inductive reasoning to develop conclusions that satisfy both the
governing question and the informational gap. Qualitative data consists of the researcher’s
COST EFFICIENCY OF THE MARKET STREET TUNNEL 8
analysis of the engineering techniques used to modify the 1997 blueprints for the Market Street
Tunnel. These construction methods are discussed in detail and in relation to how they contribute
to the overall cost efficiency of the project. Next, the researcher has gathered all quantitative data
through a cost comparison between the revised design for the tunnel and the original system
developed by Davis & Floyd, Inc. Hence, the researcher has used these quantities to estimate the
total amount of money saved by the City of Charleston as a result of the project alterations.
The researcher has evaluated the worth of the data by confirming that they can be used to
answer the governing question. In addition, the advisor and mentor have assisted the researcher
in determining the value of the qualitative and quantitative data. The mentor’s opinion of the data
has proven especially crucial because the mentor is an expert on the topic of the Market Street
Tunnel. Furthermore, the mentor has guided the researcher in selecting the most significant
modifications to study. Ultimately, the data have been deemed successful by the researcher, the
advisor, and the mentor because they clearly explain how the modified construction methods
used to install the Market Street Tunnel have saved the City of Charleston money.
Significance
The Market Street Drainage Improvements Project is a significant area of research
because it is only the second deep stormwater tunnel system to be installed in Charleston.
Furthermore, it is Charleston’s second tunnel design to include drop shafts and a connection to a
stormwater pump station. To clarify, a drop shaft is a vertical pipe that carries water from
shallow surface drainage systems to a deeper tunnel network (Williamson, 2001). Hence, the
Market Street Tunnel itself is filling an informational gap in the civil engineering field by
confirming the overall success of the deep tunnel system as a drainage design for downtown
Charleston. Furthermore, the conclusions drawn from this study are significant as far as
COST EFFICIENCY OF THE MARKET STREET TUNNEL 9
application in the civil engineering field because they indicate construction methods that can be
used to improve the cost efficiency of deep tunnel projects. Thus, professional engineers could
use this thesis to improve the cost of their own tunneling techniques and to save their clients time
and money. In addition, several stormwater tunnels are currently being implemented in
downtown Charleston, and the success of the modifications made to the Market Street Tunnel
may influence the design of these developing projects. Therefore, the most important aspect of
the researcher’s study is the cost efficiency analysis of the engineering methods used to install
the Market Street Tunnel.
Applicability
The conclusions drawn through this thesis can be used by professionals within the civil
engineering field to improve the cost efficiency of their own tunneling projects. An engineer or
company could extend the implications of the researcher’s data by using similar construction
methods to decrease the cost of installing a deep tunnel system on an island or near an inland
body of water, such as a lake. Ultimately, the study will enhance the researcher’s knowledge of
deep tunnel designs and their applicability to the Charleston area.
COST EFFICIENCY OF THE MARKET STREET TUNNEL 10
Chapter II: Review of Literature
The Market Street Drainage Improvements Project is a tunnel system designed by Davis
& Floyd, Inc., in association with URS Corporation, to alleviate flash flooding in downtown
Charleston. The tunnel was completed by Triad Midwest Mole in 2014, and it spans parts of
Market and Concord streets. Although the term, Market Street Tunnel, applies to the deep tunnel
system as a whole, the researcher will refer specifically to the Concord Street portion as the
Concord Street Tunnel and to the Market Street portion as the Market Street Tunnel. The
researcher adopted these terms from documents composed by Triad Midwest Mole. Furthermore,
the researcher will clarify whether the discussion refers to the Concord Street section, the Market
Street section, or the entire Market Street Tunnel. Moreover, this thesis will examine the cost
efficiency of the design used for the Market Street Tunnel in terms of the money saved by the
City of Charleston. In addition, the following review of literature will investigate prior
stormwater and sewage systems implemented in Charleston, including the mid-1800s network of
brick arches in the downtown area, the development of the Plum Island Wastewater Treatment
Plant, the 1984 Master Plan by Davis & Floyd, Inc., the Emergency Sewer System Replacement
Program, and, finally, the Market Street Drainage Improvements Project. Topics that will not be
covered in this study are the cost efficiency of prior system designs, minor tunneling projects that
did not substantially impact flooding in the Charleston area, and structural alterations that were
not included in the change order submitted by Triad Midwest Mole to the City of Charleston.
Currently, there is no existing cost analysis on tunneling projects in the Charleston area;
therefore, the data collected through this thesis not only satisfies an informational gap, but also
provides a point of comparison for cost efficient versus non-cost efficient construction methods
for deep tunnel systems in the City of Charleston.
COST EFFICIENCY OF THE MARKET STREET TUNNEL 11
Constructing Flood Relief Systems for the City of Charleston
Beginning in the mid-1800s, the City of Charleston, South Carolina, sought to develop an
efficient drainage design to provide flood relief for its downtown streets. As aforementioned, the
most severe flooding occurs in areas closest to Charleston Harbor when heavy rain and high tides
coincide (O’Connell, 2013). Such flooding endangers the mobility and health of drivers,
pedestrians, and residents of the downtown area, as well as those working in major, local
establishments such as hospitals, schools, law firms, and banks.
To combat urban flooding, city engineers have implemented several drainage designs in
downtown Charleston. However, none of these systems has proven adequate in removing
substantial amounts of stormwater from street surfaces. One of the key challenges engineers face
when drafting and constructing drainage tunnels for the Low Country is the region’s close-to sea
level elevation (O’Connell, 2013). For drainage systems to be effective, pipelines and tunnels
must have slopes that enable them to transport excess water, via gravity, from the ground surface
to another location. However, even moderately sloped structures installed in Charleston tend to
be at or below tidal zones, thus rendering the infrastructure useless during high tides (Cabiness et
al., 2012). Thus, when the Calhoun Tunnel, a deep tunnel system, provided significant flood
relief for a part of downtown Charleston, city engineers used it as a model during the
development of the Market Street Drainage Improvements Project (Kirk, n.d.-a). Ultimately, this
thesis will examine the economic implications of this deep tunnel design in terms of the money
saved by the City of Charleston.
Initial Drainage Design: Network of Brick Arches
The first drainage design attempted in downtown Charleston was a network of brick
arches installed during the mid-1800s (O’ Connell, 2013). These arches served as an
COST EFFICIENCY OF THE MARKET STREET TUNNEL 12
interconnected gravity network that transported stormwater from city streets to the Cooper and
Ashley Rivers (O’ Connell, 2013). In other words, the negative slope of the drainage structure
conveying urban runoff resulted in the gravitational movement of the stormwater from the street
surface to the outfall, or terminal opening, of the pipeline. Although this system provided
minimal flood relief, it did not prove adequate for the City of Charleston because of its small size
(Drolet et al., 2012). Constructed to be five ft. wide by four ft. high, city engineers intentionally
undersized the arches to increase the scouring velocities of the system (City of Charleston, 2012 :
Drolet et al., 2012). Simply stated, they believed that a smaller drainage design would reduce
sedimentation within the system during periods of flooding or high tide. However, this theory did
not prove valid as the arches became clogged with silt and other debris (Drolet et al., 2012).
Additional problems stemmed from the inefficiency of the gravity system and the gate valves
installed at the outfalls. The gravity system design failed to effectually convey stormwater to the
Cooper and Ashley Rivers, especially during periods of high tide (O’Connell, 2013). Generally,
gravity networks are difficult to implement on the Charleston peninsula because even moderate
slopes will position the infrastructure at or below tidal zones, thus rendering the system useless
(Drolet et al., 2012). In fact, “areas which can be protected by gravity flow require much larger
diameter conduits than would be required for more steeply sloping areas” (Davis & Floyd, Inc.,
1984). Furthermore, faulty gate valves positioned at the outfalls of the system contributed to
clogging because they created a bottleneck of stormwater and debris (O’Connell, 2013).
Specifically, valves modify the conveyance of hydraulic fluids by increasing, decreasing, or
stopping the flow of substances (Tooling U-SME, 2013; Plastomatic Valves, Inc., 2013).
Compared to other valves, the gate valve is unique because it is composed of a plate-like
obstruction that can be lifted or lowered to control the movement of fluid through a pipeline
COST EFFICIENCY OF THE MARKET STREET TUNNEL 13
(Tooling U-SME, 2013). In this case, the gate valves were installed to prevent backflow from the
Cooper and Ashley Rivers from entering the gravity system; however, when large amounts of
debris and sediment prevented the valves from closing properly, the brick arches became useless
as a drainage system. Ultimately, the brick arches did not prove sufficient as a water conveyance
system for the City of Charleston.
Sanitation System Improvements and the Plum Island Wastewater Treatment Plant
Following this design failure, engineers divided the Charleston peninsula into 13
collection basins that transferred sewage directly to the Charleston Harbor (Drolet et al., 2012-a).
The outfalls of the gravity lines that conveyed water from the basins to the harbor did not prove
efficient during periods of high tide (Drolet et al., 2012-a). To counter this problem, Charleston
Water System, [CWS], added pump stations to this system in the 1920s (Drolet et al., 2012-a).
The added pressure from the pumps successfully prevented the harbor outfalls from becoming
clogged with debris.
However, negative environmental impacts caused by the release of raw sewage into the
harbor culminated in reduced fish populations, swimming restrictions, and a general public
protest (Drolet et al., 2012). In 1963, the South Carolina state legislature passed the Charleston
Harbor Pollution Law, which required the city to install wastewater treatment systems by 1970
(Charleston Water System, n.d.). Specifically, the term wastewater refers to “any water that has
been adversely affected in quality” (Integrated Engineers, Inc., n.d., p. 1). Wastewater differs
from stormwater in that wastewater requires significantly more treatment before being safely
released into the environment. Thus, CWS began developing methods to improve the quality of
the city’s wastewater (Drolet et al., 2012). From 1968 to 1971, the City of Charleston
constructed a wastewater treatment facility located across the Ashley River and west of the
COST EFFICIENCY OF THE MARKET STREET TUNNEL 14
Charleston peninsula (Charleston Water System, n.d. : Drolet et al., 2012). This facility was
named the Plum Island Wastewater Treatment Plant and is still in operation today. Furthermore,
city officials decided that wastewater conveyance tunnels should be constructed to transport
sewage from urban areas to this treatment facility. As a result, CWS installed the Charleston
Sewer Test Tunnel in 1966, modeling it after the original water tunnels implemented further
inland in 1928 (Drolet et al., 2012). When this test tunnel proved effective, city officials awarded
contracts for the construction of a sewer tunnel collection system that would convey sewage
from urban Charleston to the Plum Island Wastewater Treatment Plant (Charleston Water
System, n.d.). Infrastructure within this system included the Original Cooper River Tunnel, the
Original Ashley River Tunnel, the Original Harbor Tunnel, and the Original West Ashley Tunnel
(Drolet et al., 2012). When engineers completed this network in the early 1970s, it greatly
improved the quality of water released into the Charleston Harbor (Drolet et al., 2012).
Development and Deterioration of the Original Cooper River Tunnel
The Original Cooper River Tunnel significantly influenced the design of the Market
Street Tunnel due to its location along Concord Street. Following the enactment of the
Charleston Harbor Pollution Law in 1963, CWS installed the Cooper River Tunnel in 1969 to
transport sewage from Charleston to the Plum Island Wastewater Treatment Plant (Drolet et al.,
2012; Charleston Water System, n.d.). Like other wastewater tunnels constructed in the 1960s,
the Cooper River Tunnel was modeled after water supply tunnels located north of Charleston.
CWS engineers noted that these older tunnels had remained fully functional without a lining;
thus, they believed that the Cooper River Tunnel needed little, if any, ground support. As far as
structural design, the Cooper River Tunnel was comprised of a Prestressed Concrete Cylinder
Pipe [PCCP] supported by steel ribs and wooden lagging and situated at the bottom of a
COST EFFICIENCY OF THE MARKET STREET TUNNEL 15
horseshoe-shaped excavation within the Cooper Marl (Drolet et al., 2012; Klecan, Horner, &
Robison, n.d.). To clarify, “the Cooper Marl is a . . . homogenous, olive green, highly calcareous,
phosphatic, fossiliferous, clayey sand and silt” composition located 30-60 ft. below ground level
across the Charleston Peninsula (Drolet et al., 2012). In addition, “the Cooper Marl is an
excellent tunneling medium as it exhibits sufficient standup time for erection of initial support
yet it is soft enough to excavate by shovel and air spade if desired” (Drolet et al., 2012). Thus,
CWS engineers did not fill the annular space between the PCCP and the tunnel lining because of
the durable nature of the Cooper Marl and the sound structural integrity of older, unlined tunnels.
However, CWS failed to realize the difference in strength between the Cooper Marl located near
the older tunnels and that which encased the Cooper River Tunnel. The layer more commonly
distributed north of Charleston, and thus near the sites of the water supply tunnels, is classified as
either the Parkers Ferry or Harleyville Formations, whereas the substance found in downtown
Charleston is of the Ashley Formation (Klecan et al., n.d.). Of the three, the Ashley Formation is
the weakest type because it has less compressive strength and less carbonaceous bonding than
the Parkers Ferry and Harleyville Formations (Klecan et al., n.d.). In other words, the Ashley
Formation has had less time to consolidate, or settle, than the Parkers Ferry and Harleyville
Formations, and its geological composition prevents it from being as stable as the latter two
substances. The combination of these two factors resulted in “the strength of the Cooper Marl
[being] lower than the circumferential stresses around the [Cooper River Tunnel]. Consequently,
many sections of [this tunnel] became “overstressed.” The tunnel sidewalls . . . failed initially in
compression, and without adequate support the zone of failure quickly extended upwards over
the tunnel” (Klecan et al., n.d.). To clarify, the ground surrounding the tunnel excavation area
was too weak to remain standing without additional ground support. As the walls grew weaker,
COST EFFICIENCY OF THE MARKET STREET TUNNEL 16
sections of the top of the tunnel began to fall and damage the PCCP, thus rendering the tunnel
useless as a water conveyance mechanism. Furthermore, the void between the PCCP and the ribs
and lagging allowed hydrogen sulfide gas to accumulate and to corrode the PCCP (Drolet et al.,
2012). When holes formed in the PCCP, sewage leaked into the tunnel and caused further
deterioration (Drolet et al., 2012). Hence, when CWS hired commercial divers in the 1990s to
inspect the sewage system servicing the Plum Island Wastewater Treatment Plant, city officials
immediately launched the Emergency Sewer System Replacement Program to repair the Cooper
River Tunnel and other sewage conveyance tunnels. In 2005, CWS finally abandoned the Cooper
River Tunnel in favor of the newly constructed Cooper River Replacement Tunnel (Drolet et al.,
2012).
Emergency Sewer System Replacement Program
In the 1990s, CWS hired commercial divers to inspect the sewer system conveying
wastewater to the Plum Island Wastewater Treatment Plant (Drolet et al., 2012). The divers
found this system in a severe state of disrepair; problems included corrosion, collapsed
supporting structures called ribs, holes in the conveyance pipes within the tunnels, and a
dangerous accumulation of sludge (O’Connell, 2013). Engineers employed by the city feared that
these structural damages could culminate in blockages within the tunnels, thus causing an
overflow in urban sewers and the prevention of wastewater treatment at the Plum Island Plant
(O’Connell, 2013). To avoid such a catastrophe, CWS began a fast-tracked sewer system
replacement program that would assume the functions of the older, damaged tunnel network.
CWS divided this construction project into multiple phases. The initial phase, the Harbor Tunnel,
was completed in 2001, followed by the Ashley Sewer Tunnel in 2006 and the Cooper Sewer
Tunnel in 2008 (O’Connell, 2013). In addition to this new sewer system, an extension tunnel was
COST EFFICIENCY OF THE MARKET STREET TUNNEL 17
implemented within the same year to convey sewage from Daniel Island to the Plum Island Plant
(O’Connell, 2013). Furthermore, construction of the West Ashley Sewer Tunnel began in 2013
and is expected to be completed in 2015 (Charleston Water System, n.d.). The City of
Charleston’s “sewer tunnel replacement program is the single largest infrastructure program in
the utility’s history” (O’Connell, 2013, p. 5). Moreover, this systematic repair and replacement
operation has successfully prevented severe blockages within sewage conveyance tunnels in the
Charleston area and has reduced backflow within local stormwater systems. Thus, sewage
treatment has continued, uninterrupted, at the Plum Island Wastewater Treatment Plant.
1984 Master Drainage and Floodplain Management Plan by Davis & Floyd, Inc.
The next proposal to improve the City of Charleston’s drainage systems was a Master
Plan developed in 1984 by Davis & Floyd, Inc. (O’Connell, 2013). This design divided and
directed Charleston’s stormwater into basins situated around the city (O’Connell, 2013). By
definition, “a drainage basin is an area from which the runoff generated is discharged via one
outfall system” (Davis & Floyd, Inc., 1984, p. 2). Physical characteristics of such basins,
including “topography, land use, type and extent of development, soil and surface cover, and
[other] environmental features,” influence the amount of stormwater runoff from a given area,
and thus the type of drainage systems needed to convey this runoff (Davis & Floyd, Inc., 1984, p.
2). Field surveys of the “Study Area,” or the region bounded by “the corporate limits of the City
of Charleston as of May 1984,” resulted in the proposal of 182 individual drainage basins as part
of the Master Plan (Davis & Floyd, Inc., 1984, p. 2). Each of these basins had a designated
outfall in the Cooper River, the Ashley River, the Stono River, or the James Island Creek (Davis
& Floyd, Inc., 1984). This Study Area was subdivided into four distinct regions: Peninsula, West
Ashley, James Island, and Johns Island (Davis & Floyd, Inc., 1984). In addition, field surveys
COST EFFICIENCY OF THE MARKET STREET TUNNEL 18
provided further information regarding the topography of the Study Area. Surface elevations in
this region range from mean sea level, [MSL], or 0 ft., to 25 ft. above MSL; moreover, surface
slopes generally measure 1% or less, and they tend to slant toward one of the main tributaries,
i.e. the Cooper River, the Stono River, etc. (Davis & Floyd, Inc., 1984). As a result of these flat
slopes, the overland flow velocities within the drainage basins are low, causing stormwater
runoff to accumulate more quickly at specific points along the ground (Davis & Floyd, Inc.,
1984). Hence, the flat surface slopes of the Study Area contribute to flooding on the Charleston
peninsula.
Other environmental features of the Study Area that influenced the design of the
proposed drainage facilities include soil types, historic sites, and tidal wetlands. According to the
field surveys, the Study Area consists mostly of clay and fine sand, both of which are surficial
geology of marine or fluvial origin. Based on the composition of the Study Area, engineers from
Davis & Floyd, Inc. concluded that overland runoff velocities from unpaved areas would be
retarded, a large portion of the area’s rainfall would be absorbed into the ground or into
surrounding vegetation, and the slopes of drainage ditches would suffer erosion unless protected,
or unless the overland flow velocities did not surpass 2-3 ft. per second. Additionally, the City of
Charleston developed the new drainage designs so that they would not harm the existing historic
structures within the Study Area. Engineers took precautions during the excavation and
construction phases of this Master Plan to ensure the preservation of intrinsic infrastructure
above and below ground. However, tidal wetlands proved to be the most significant
environmental feature that influenced the development of the drainage basins. Marshlands within
the Study Area “provide a nursery and source of food for various forms of aquatic life;
[furthermore, they] are located along the Cooper River, Ashley River, Stono River and James
COST EFFICIENCY OF THE MARKET STREET TUNNEL 19
Island Creek” (p. 5). To implement or modify drainage structures in these areas, the City of
Charleston had to obtain a permit from the state. Thus, engineers also took precautions to
maintain the integrity of these marshes as much as possible during the construction phase of the
Master Plan.
Furthermore, engineers employed by the city planned improvements projects based on
the intensity of each community’s need for flood relief (O’ Connell, 2013). This massive project
was subdivided into four phases. In the initial phase, engineers assessed the conditions and
capacities of the existing drainage systems in each community, and they made recommendations
regarding potential improvements to each design (Davis & Floyd, Inc., 1984). These evaluations
were based on each system’s capacity deficiency, repair cost, degree of need for improvement,
and the extent to which the proposed improvements would increase public health and safety
(Davis & Floyd, Inc., 1984). Secondly, the City of Charleston had to obtain financial support to
execute these proposed improvements (Davis & Floyd, Inc., 1984). The third phase entailed the
development of blueprints and specifications for these proposals (Davis & Floyd, Inc., 1984).
Lastly, the planned changes for each community’s flood relief system were implemented (Davis
& Floyd, Inc., 1984). Only stormwater lines measuring 24” or greater in diameter were modified,
as the City of Charleston considered these to be the most significant drainage facilities providing
flood relief for the Study Area (Davis & Floyd, Inc., 1984). Projects that served as components
to this Master Plan include the Calhoun Street East Drainage Improvements Project, the Market
Street Drainage Improvements Project, and the Spring/Fishburne Drainage Project.
Calhoun Street East Drainage Improvements Project
Initiated in 1999, the Calhoun Street East Drainage Improvements Project was the first
stormwater drainage design installed in the Charleston area that included a deep tunnel system,
COST EFFICIENCY OF THE MARKET STREET TUNNEL 20
drop shafts, and a stormwater pump station (Kirk, n.d.-b). The city awarded the contract for this
tunnel to a joint venture between Triad Engineering and Bradshaw Construction Corporation.
This joint venture installed one of the branches of the tunnel network under Calhoun Street and
continued it from Marion Square to Concord Street (Kirk, n.d.-b). Another branch conveyed
stormwater under Meeting Street, from Mary Street to Marion Square. Furthermore, drop shafts
were installed along Meeting and Calhoun streets to transport water from the street surface to the
deep tunnel (Kirk, n.d.-b). The access shaft was the first component to be installed, and it
spanned a diameter of 30 ft.; additionally, the branches of the deep tunnel had diameters of 8-ft.
(Kirk, n.d.-b). To clarify, an access, or working, shaft is “a vertical excavation to gain access to
tunnels or mines from the surface” (Bickel & Kuesel, 1982, p. 2). Generally, tunnel engineers
construct the access shaft first so they can work directly on the infrastructure being installed
underground. The Calhoun Street tunnel system is still in effect today, and it carries urban
stormwater from downtown Charleston to the Concord Pump Station (Kirk, n.d.-b). This pump
station transfers the stormwater directly to Charleston Harbor.
Market Street Drainage Improvements Project
In 1997, Davis & Floyd, Inc. initiated the preparations for the construction of the Market
Street Drainage Improvements Project (O’Connell, 2013). City officials selected a deep tunnel
system, rather than an open-cut excavation, as the design for this project to ensure minimal
surface disruptions in the downtown area. Such disruptions could have included traffic detours,
utility relocations, temporary business closures, equipment vibrations, and potential
infrastructure damages. To clarify, an open-cut excavation is one in which engineers dig
downward from the ground surface throughout the course of the project. Additionally, installed
drop shafts would transport stormwater, rather than sewage, directly from the street to this deep
COST EFFICIENCY OF THE MARKET STREET TUNNEL 21
tunnel. Thus, the proposed tunnel would help to relieve surface flooding by conveying massive
amounts of stormwater from the drop shafts to the Concord Pump Station. However, a lack of
funding prevented the City of Charleston from launching construction of this massive project.
Once financial backing for the project was secured, city officials awarded the contract for the
second phase to Triad Midwest Mole in July 2012 (O’Connell, 2013). The city subdivided the
Market Street Drainage Improvements Project into three phases, called Division I, Division II,
and Division III.
In 2006, the City of Charleston initiated construction of Division I. This phase entailed
the improvement of surface water collection systems along Concord Street, the modification of
the controls of the Concord Pump Station, and the installation of an additional pump at this pump
station (Kirk, n.d.-a). The alterations to the pump station’s controls enabled the facility to accept
more water from the newly installed surface collection systems. Additionally, engineers
implemented a fourth pump to increase the maximum capacity of the facility from 90,000
gallons per minute to 120,000 gallons per minute (City of Charleston, 2012). The purpose of this
large accommodation was to prepare the pump station for a massive inflow of stormwater from
the anticipated Division II drainage system (City of Charleston, 2012).
Division II began in 2012 and involves the installation of a 20 ft. diameter, 140 ft. deep
access shaft at the intersection of Market and Concord streets, the excavation of three 54 in. drop
shafts at the intersections of Market and State streets, Market and Anson streets, and Market and
Church streets, the implementation of an emergency outfall on Concord Street, the construction
of a 9 ft. diameter tunnel under Market Street extending from the access shaft to Church Street,
and the installation of another 9 ft. diameter tunnel under Concord Street spanning from the
COST EFFICIENCY OF THE MARKET STREET TUNNEL 22
access shaft to the Concord Pump Station (City of Charleston, 2012). The City of Charleston
divided Division II of the Market Street Drainage Improvements Project into three sub-phases.
Phases 1-3 : Division II : Market Street Drainage Improvements Project. During
Phase 1, or the Initial Investigation, the Triad-Midwest Mole joint venture measured the
dimensions of the brick arch drainage structure located beneath Market Street (Kirk, n.d.-a). The
purpose of this exploration was to evaluate the stability and the size of the brick arch. Such
information would help the engineers to avoid damaging it during the installation of the drop
shafts along Market Street. Prior to the commencement of Division II, city officials had decided
to preserve the brick arches because of their intrinsic value (O’Connell, 2013). Thus, Triad
Midwest Mole engineers took precautions to avoid destroying these underground artifacts during
the construction phase of Division II.
In Phase 2, called the Pre-Excavation, the joint venture dug out a 30 ft. by 30 ft. by 20 ft.
area of road along Market Street to remove abandoned pipelines from the proposed tunnel site
(Kirk, n.d.-a). The engineers extracted this debris to facilitate the installation of the drop shafts
along Market Street. Following the extraction of all impeding utilities from the site, the joint
venture restored the excavated area to its original condition so that a normal flow of traffic could
resume on Market Street (Kirk, n.d.-a).
Phase 3, referred to as Drilling and Construction, includes the installation of the access
shaft, the drop shafts, the emergency outfall, and the deep tunnel network (Kirk, n.d.-a). The
access and drop shafts are intended to replace the existing brick arches beneath Market and
Concord streets (City of Charleston, 2012). In addition, each of the three drop shafts are covered
with a 3 ft. diameter grate to drain flood water from street surfaces (Kirk, n.d.-a). This
stormwater is transported down the drop shafts to the deep tunnel system, from the deep tunnel
COST EFFICIENCY OF THE MARKET STREET TUNNEL 23
to the Concord Pump Station, and finally to Charleston Harbor. Moreover, to construct the deep
tunnel that runs underneath Market and Concord streets, Triad Midwest Mole used a method
called open-faced drilling, or open-faced tunneling. Simply stated, open-faced drilling means that
the face of the TBM is exposed to the dirt excavated during operation. Furthermore, another
significant portion of this project is the emergency outfall, an extra drainage pipeline attached to
the access shaft to prevent the tunnel system from becoming blocked if the Concord Pump
Station ceases to work (Davis & Floyd, Inc., 2012-a). Because this pump station is powered
electrically, the pumps are liable to stop functioning during tropical storms and hurricanes. In
such cases, the fluid movement within the Market Street Tunnel would halt, and the water level
would continue to rise within the system as city streets became inundated. Therefore, the design
by Davis & Floyd, Inc. required Triad Midwest Mole to place the emergency outfall 15 ft.
underground to ensure a downward movement of water from the city streets at all times (Davis &
Floyd, Inc., 2012-a). This outfall is 54 in. in diameter, and its terminal opening is in Charleston
Harbor (Davis & Floyd, Inc., 2012-a). Additionally, a Tideflex valve installed at the terminal exit
prevents an influx of seawater from compromising the outfall’s drainage efficiency (Davis &
Floyd, Inc., 2012-a). Specifically, a Tideflex valve is specialized for pipeline outfall and manhole
installations because it allows water to flow in a singular direction (Tideflex, n.d.). Thus, water is
able to flow out of the emergency outfall, but not into it. Although the emergency outfall makes
the Market Street Tunnel a nearly foolproof drainage design, a combination of circumstances
could still prevent fluid movement from the city streets to the harbor. Collectively, a hurricane or
other major flooding event, a malfunction or power-outage at the Concord Pump Station, and a
high tide preventing water from leaving the emergency outfall could invalidate the drainage
efficiency of the Market Street Tunnel and thus augment urban flooding. Aside from these
COST EFFICIENCY OF THE MARKET STREET TUNNEL 24
extreme conditions, the Market Street Drainage Improvements Project is equipped to
significantly decrease the amount of flooding along Market and Concord streets in downtown
Charleston.
Division III : Spring/Fishburne Drainage Project
In 1968, a six-lane expressway known as the Septima Clark Parkway, or the
“Crosstown,” was constructed as part of U.S. Highway 17 to connect the Ashley River bridges to
the Cooper River bridges (Cabiness et al., 2012). However, the asphalt surface of this highway
created additional stormwater runoff that could not be properly drained by the existing,
undersized system (Cabiness et al., 2012). Consequently, heavy rainfall creates bodies of
standing water that render the Crosstown impassable to vehicles, oftentimes for several hours;
therefore, the inadequate drainage system used to remove surface water from the Septima Clark
Parkway contributes to heavy urban flooding that, in turn, prevents citizens from reaching vital
entities including the Medical University of South Carolina, [MUSC], Roper Hospital, the
Citadel, the City of Charleston police department, the City of Charleston fire department,
schools, churches, businesses, and neighborhoods (Cabiness et al., 2012). As a result, a
component of the 1984 Master Drainage and Floodplain Management Plan by Davis & Floyd,
Inc. is the US17 Septima Clark Parkway Transportation Infrastructure Reinvestment Project, also
known as the Spring/Fishburne Drainage Project (Davis & Floyd, Inc., 1984). The purpose of
this project is to alleviate flooding on the Crosstown and to ensure vehicular mobility on this
highway at all times, regardless of environmental conditions. The area directly affected by this
project comprises 20% of the Charleston peninsula, including commercial and residential areas
(Cabiness et al., 2012). In addition, the Spring/Fishburne design consists of five major parts: the
installation of new, improved surface collection systems in drainage basins within the project
COST EFFICIENCY OF THE MARKET STREET TUNNEL 25
area, the drilling of several drainage shafts from the surface, the boring of 12 ft. diameter
stormwater tunnels that will connect to the afore-mentioned shafts, the implementation of a
pump station along the Ashley River, and the construction of a 550 ft. outfall from this new
pump station to the river itself (Cabiness et al., 2012). Moreover, the design of the
Spring/Fishburne Drainage Project will merit sustainable solutions for travelers using the
Septima Clark Parkway. First, and most importantly, this drainage system will reduce surface
flooding along the highway, thus enabling safer mobility for vehicles and pedestrians alike.
Secondly, an adequate stormwater drainage system will prevent the dilution of saltwater bodies
within the project area (Cabiness et al., 2012). Saltwater bodies require a certain quantity of
brackish water in order to maintain an equilibrium with the surrounding environment; plants and
animals that live in or near saline waters rely on a specific concentration of brackish water to
survive. The Spring/Fishburne Drainage Project would prevent substantial amounts of freshwater
runoff from flooding tidal flats and diluting the salt concentration of brackish tributaries
(Cabiness et al., 2012). Thirdly, an improved drainage system will enhance the quality of the
stormwater being released into the Ashley River because the more quickly runoff is drained from
the highway, the less time is available for it to become stagnant and polluted (Cabiness et al.,
2012). Additionally, a desiltation chamber and a screening mechanism will be installed in the
new pump station to remove debris from the runoff before it is released into the Ashley River
(Cabiness et al., 2012). The desiltation chamber will cleanse the water of silt, sand, and other
unwanted sediments; the screening mechanism will catch debris larger than 2 in. (Cabiness et al.,
2012). Finally, the Spring/Fishburne Project will decrease the city’s use of fossil fuels by
improving traffic mobility on the Crosstown; in other words, an increased efficiency of vehicular
transportation will help eliminate idling motorists on this highway, thus reducing fuel
COST EFFICIENCY OF THE MARKET STREET TUNNEL 26
consumption as well as the emission of greenhouse gasses (Cabiness et al., 2012). Clearly, the
drainage design of the Spring/Fishburne Project will prove beneficial to the environment, to
motorists, and to pedestrians traveling on the Septima Clark Parkway. The City of Charleston has
yet to award the contract for the tunnels and shafts division of this project.
COST EFFICIENCY OF THE MARKET STREET TUNNEL 27
Change Order for the Design of the Market Street Tunnel
As aforementioned, the general design for the Market Street Drainage Improvements
Project is a deep tunnel system connected to three drop shafts, an emergency outfall, and the
Concord Pump Station. Following Triad Midwest Mole’s acceptance of the contract for Division
II, the joint-venture hired a subcontractor, Terracon Consultants, Inc., to gain more information
regarding the current condition of an abandoned tunnel along Concord Street (Terracon
Consultants, Inc., 2012). Installed by CWS in 1969 as the Original Cooper River Tunnel, this
deserted infrastructure was part of the initial wastewater tunnel collection system that conveyed
sewage from Charleston to the Plum Island Wastewater Treatment Plant (Drolet et al., 2012-a).
Furthermore, Terracon Consultants, Inc. utilized a Piezocone Penetration Test [CPTu] to gather
data regarding this tunnel (Terracon Consultants, Inc., 2012). Typically, geotechnical engineers
use CPTu’s to determine the quality and stratigraphy of soil (Zebra Environmental, 2012). The
basic components of the CPTu used by Terracon Consultants, Inc., consist of a probe encased in
a cone that is hydraulically pushed through the ground (Davis & Floyd, Inc., 2012-b). As the
cone is forced through the soil at a steady rate of 2 cm per second, “measurements of tip and side
resistance and porewater pressure” are stored on a portable computer (Davis & Floyd, Inc., 2012-
b, p. 3). Terracon Consultants, Inc. used the CPTu to survey the intersection of Concord and
Market streets, the length of Concord Street, and the area surrounding the Concord Pump Station
(Terracon Consultants, Inc., 2012). Based on the collected data, Terracon observed that two of
their cones “intercepted the tunnel shallower than the design depth of 100 feet” and that this
discrepancy “may be associated with a past collapse of the tunnel” (Terracon Consultants, Inc.,
2012). Additionally, Terracon concluded that the Cooper River Tunnel “could be located in close
proximity (laterally) to the new drainage tunnel which may impact tunnel design and/or its
COST EFFICIENCY OF THE MARKET STREET TUNNEL 28
alignment” (Terracon Consultants, Inc., 2012). To avoid constructing the Market Street Tunnel
too close to the deteriorated Cooper River Tunnel, Triad Midwest Mole submitted a change order
to the City of Charleston in October 2012 that proposed several significant alterations to the
structural design of the tunnel. Among other changes, Triad-Midwest Mole proposed “to lower
the elevation of the drainage tunnel; [to] change its slope to maximize its separation from the
identified void; and [to] realign its connection to the [Concord] Street Pump Station to lower the
new tunnel connection cost” (M. Horton, personal communication, January 29, 2013, p. 1). City
officials approved this change order on February 25, 2013. Furthermore, the researcher has
classified the following alterations as significant to the Market Street Drainage Improvements
Project because each of them was included within this change order.
Increased Depth of the Market Street Tunnel
One of the most significant alterations included within the change order was a drastic
increase in the depth of the Market Street Tunnel and the connecting drop shafts. According to
the original blueprints, Davis & Floyd, Inc. designed the access shaft to be 30 ft. in diameter and
to connect to the tunnel at a depth of 80 ft. (Davis & Floyd, Inc., 2008-c). The drainage tunnel
would then have sloped down to a terminating depth of 138 ft., at which point it would have
connected to the existing Calhoun Tunnel (Davis & Floyd, Inc., 2008-c). The water conveyed by
these joined tunnels would have been transported directly to the Concord Pump Station (Davis &
Floyd, Inc., 2008-c). However, the geotechnical report submitted by Terracon Consultants, Inc.
caused Triad Midwest Mole to question the safety of constructing their new tunnel beside the
Original Cooper River Tunnel. In fact, Terracon’s data and the original drawings for the project
indicated that the Market Street Tunnel would have nearly intersected the Cooper River Tunnel
at a depth of 100 ft. (Davis & Floyd, Inc., 2008-c : Terracon Consultants, Inc., 2012).
COST EFFICIENCY OF THE MARKET STREET TUNNEL 29
Furthermore, Terracon reported that the Cooper River Tunnel “appears to deviate from the
documented location” at this depth (Terracon Consultants, Inc., 2012). Although Terracon
offered an estimated 9 ft. buffer zone between the two tunnels, their experts could not provide an
accurate measurement of the width of this area because they could not pinpoint the exact location
of the Cooper River Tunnel (Terracon Consultants, Inc., 2012). In addition, Triad Midwest Mole
was concerned about the implications of excavating their tunnel in close proximity to dilapidated
infrastructure. Because sections of the top of the Cooper River Tunnel had collapsed, it was
possible that water from the Atlantic Ocean could seep into this tunnel, through the buffer zone,
and then into the Market Street Tunnel during the latter’s excavation (M. J. Kassouf, personal
communication, July 22, 2014). This potential complication would be irreparable, and it would
result in the complete destruction of the Market Street Tunnel (M. J. Kassouf, personal
communication, July 22, 2014). More importantly, the water would destroy the TBM or, worse,
drown workers unable to escape from an impromptu collapse (M. J. Kassouf, personal
communication, July 22, 2014).
To circumvent these hazards, Triad Midwest Mole included a proposal for changing the
dimensions of the Market Street Tunnel and the connecting shafts in their change order. The joint
venture suggested a terminal depth of 140 ft. and a decreased diameter of 20 ft. for the access
shaft (Triad Midwest Mole Joint Venture, 2012). Although Triad Midwest Mole was capable of
constructing an access shaft with a 30 ft. diameter, their engineers felt that the larger size was not
necessary (M.J. Firestone, personal communication, July 30, 2014). Moreover, the original 54 in.
diameter of the drop shafts remained the same, but their final depth was extended from 80 ft. to
140 ft. so as to maintain their connection to the lowered drainage tunnel (P.J. Kassouf, personal
communication, July 23, 2014). By increasing the depth of these shafts, Triad Midwest Mole
COST EFFICIENCY OF THE MARKET STREET TUNNEL 30
lowered the elevation of the drainage tunnel and thus provided for a substantially larger buffer
zone of 40 ft. between the Cooper River Tunnel and the Market Street Tunnel (Terracon
Consultants, Inc., 2012). The joint venture’s engineers felt that this buffer zone would more than
protect the structural integrity of the Market Street Tunnel during Phase 3 of Division II (P. J.
Kassouf, personal communication, July 31, 2014).
To construct the access shaft, Triad Midwest Mole modeled their installation procedure
after a method that Triad had used successfully in 1999 to build the Calhoun Street East
Drainage Improvements Project (Triad Midwest Mole Joint Venture, 2012-b). First, the joint
venture created a shaft footprint by leveling the area around the future access shaft so as to
remove debris from the ground surface (Triad Midwest Mole Joint Venture, 2012-b). Next, the
engineers laid a 6 in. layer of #57 stone along the top of the footprint to serve as a base for a
subsequent 4 in. layer of concrete, referred to as sacrificial concrete leveling (Triad Midwest
Mole Joint Venture, 2012-b). To clarify, #57 stone is a commonly used construction aggregate
that is typically ¾ in. in size and is composed of various types of crushed rock, including
limestone, traprock, washed gravel, granite, argillite, and quartzite (Braen, 2013). The stone and
concrete layers served as a foundation on which the engineers built a caisson shaft cutting shoe, a
20 ft. diameter steel ring that was later attached to the bottom of a caisson shaft to ease its
descent through the ground (Triad Midwest Mole Joint Venture, 2012-b). Specifically, a caisson
is “a shaft of concrete or steel which can be sunk through the ground by excavating the ground
within the perimeter of the lower edge, with the rate of sinking frequently controlled by
compressed air” (Proctor & White, 1977, p. 245). Commonly known as the sinking caisson
method, this construction strategy enabled the joint venture to avoid compromising the ground
stability of the excavation area. Then, the engineers constructed steel forms with which to pour
COST EFFICIENCY OF THE MARKET STREET TUNNEL 31
concrete for the initial 4 ft. of the caisson shaft (Triad Midwest Mole Joint Venture, 2012-b).
Furthermore, the engineers poured the concrete around a set of rebar, or steel bars, so as to
reinforce the strength of this shaft. The engineers arranged the rebar so that steel hoops encircled
standing bars; additionally, the hoops were spaced one vertical foot apart from each other, and
the bars were spaced one horizontal foot apart from each other. The rebar was located 18” from
the inside wall of the access shaft. Moreover, the wet concrete was allowed to set until it reached
a strength of 1000 pounds per square inch [psi] (Triad Midwest Mole Joint Venture, 2012-b).
Engineers slowly sunk this caisson, which was 4 ft. in length, 20 ft. in diameter, and 18 in. thick,
by excavating the ground on the inside of the structure using a Caterpillar 302.5C Mini
Hydraulic Excavator (Caterpillar, 2007 : P. J. Kassouf, personal communication, February 10,
2015). Any excess ground water that rose within the caisson was removed with a Grindex
electrical submersible drainage pump and a Godwin sub-prime electric submersible pump and
deposited into a sanitary manhole on site (Grindex, n.d. : Godwin Pumps, n.d. : Triad Midwest
Mole Joint Venture, 2012-b). When the caisson was submerged 4 ft. into the ground, the
engineers assembled the steel forms for the next segment of the shaft and repeated the process of
pouring and sinking the caissons until the entire access shaft was completed (Triad Midwest
Mole Joint Venture, 2012-b). Additionally, the engineers allowed 6 ft. of the rebar within each
segment to remain exposed above ground so as to ease the process of connecting the shaft pieces.
After installing one portion of the shaft, the engineers used rebar tying wire manufactured by
Concreate Welded Wire Reinforcing Co. to connect the 6 ft. of free rebar to the rebar of the next
segment; thus, the engineers ensured the structural integrity of the entire caisson by
implementing rebar within the walls of the shaft (Concreate Welded Wire Reinforcing Co., n.d. :
P. J. Kassouf, personal communication, February 10, 2015).
COST EFFICIENCY OF THE MARKET STREET TUNNEL 32
Furthermore, the concrete segments following the initial 4 ft. caisson measured 14 ft. in
length and 20.3 ft. in diameter; moreover, the additional 4 in. width of these pieces allowed for
the strategic installment of 1 in. steel piping along the access shaft wall (Triad Midwest Mole
Joint Venture, 2012-b). This piping provided a medium through which the engineers could pump
slurry, a mixture of bentonite and water, into the annular space between the access shaft wall and
the ground. Engineers used a FM13V model Ditch Witch slurry pump for this purpose (Ditch
Witch, n.d. : P. J. Kassouf, personal communication, February 10, 2015). Moreover, bentonite is
defined as “a naturally occurring clay” that “has a large capacity for absorbing water. In
suspension, it is a liquid when agitated, and a gel if left to stand. The liquid suspension can be
injected into a permeable soil mass and allowed to congeal in the voids, thereby decreasing
permeability” (Bickel & Kuesel, 1982, p. 218). In other words, Triad Midwest Mole engineers
pumped slurry into the annular space between the access shaft wall and the surrounding soil so as
to keep the water pressure around the shaft consistent with that of the ground water table, or, in
this case, with sea level (Bickel & Kuesel, 1982). Maintaining the equilibrium of the water table
allowed the engineers to further ensure the ground stability of the excavation area.
After Triad Midwest Mole constructed the first 85 ft. of the access shaft, engineers
installed a concrete bearing pad to prevent this top section of the caisson from sinking (Triad
Midwest Mole Joint Venture, 2013-a). This circular bearing pad was 2 ft. thick and extended 4 ft.
7 in. from the inside of the access shaft wall (Triad Midwest Mole Joint Venture, 2013-a). To
implement this structure, engineers used air spades to hand-mine the Cooper Marl surrounding
the caisson shaft before pouring any concrete. To clarify, both the clay spades and the #95LA3
model air diggers comprising the air spades were manufactured by Ingersoll-Rand (Ingersoll
Rand, 2015-a, 2015-b : P. J. Kassouf, personal communication, February 10, 2015).
COST EFFICIENCY OF THE MARKET STREET TUNNEL 33
Furthermore, the engineers mined one fourth of the bearing pad at a time to ensure the security of
the initial 85 ft. of the access shaft. Therefore, at least three fourths of the shaft bottom was
supported by stable ground at any given time during the excavation of the bearing pad (M. J.
Kassouf, personal communication, December 31, 2014). Due to the stability of the Cooper Marl,
the engineers did not need to use forms when pouring concrete for the bearing pad (P. J. Kassouf,
personal communication, February 10, 2015). Following the construction of the bearing pad, the
engineers continued to mine the access shaft until it reached its terminal depth of 140 ft.
However, Triad Midwest Mole chose to support the 15 ft. of caisson between the bearing pad
and the bottom of the access shaft with liner plates and steel ribs rather than with concrete and
rebar (Triad Midwest Mole Joint Venture, 2012-b). These standard liner plates with corrugations
were manufactured by DSI Underground Systems Inc. (DSI Underground Systems Inc., n.d. : P.
J. Kassouf, personal communication, February 10, 2015). Had the engineers chosen to line the
final 15 ft. of the access shaft with concrete and rebar before the end of the project, they would
have had to mine through these materials to adjust the tunnel headings for the Market Street and
Concord Street sections of the tunnel (M. J. Kassouf, personal communication, December 31,
2014 : P. J. Kassouf, personal communication, February 10, 2015). Thus, the engineers chose to
use liner plates as temporary support for this section of the shaft so as to increase project
efficiency (M. J. Kassouf, personal communication, December 31, 2014 : P. J. Kassouf, personal
communication, February 10, 2015). Although installing steel ribs complicated the readjustment
of the Market Street and Concord Street tunnel headings, Triad Midwest Mole’s design engineer,
Arup Texas Inc., required the joint venture to use them (P. J. Kassouf, personal communication,
February 10, 2015).
COST EFFICIENCY OF THE MARKET STREET TUNNEL 34
Subsequently, the engineers used a Putzmeister 20Z-Meter Truck-Mounted Concrete
Boom Pump to fill the annular space surrounding the caisson shaft with grout (Putzmeister
America, Inc., 2013 : P. J. Kassouf, personal communication, February 10, 2015). Again, the 1
in. steel piping surrounding the caisson shaft served as a medium through which the engineers
could pump fluids. As the grout gradually filled the space between the access shaft and the
ground, the engineers deposited the displaced slurry into a separate tank (Triad Midwest Mole
Joint Venture, 2012-b). Later, the engineers loaded the slurry onto a slurry tanker and hauled it
away from the site (Triad Midwest Mole Joint Venture, 2012-b).
Additionally, the engineers constructed three drop shafts along Market Street that
connected to the deep tunnel system at a depth of 130 ft. (Triad Midwest Mole Joint Venture,
2012-b). To successfully execute this phase, the engineers constructed a steel work deck over the
top of each drop shaft location to serve as a platform for the workers and a bearing pad for each
section of shaft casing (Triad Midwest Mole Joint Venture, 2013-b). This platform included a
hole in the center through which the engineers could lower sections of the casing into the ground
with a crane (Triad Midwest Mole Joint Venture, 2013-b). Furthermore, the drop shaft
installation procedure was divided into a drilling operation and a casing operation (Triad
Midwest Mole Joint Venture, 2013-b). During the initial stage, engineers used an AF 220
Hydraulic Drill Rig to spin a 70 in. diameter, 50 ft. long steel casing into the Cooper Marl to
serve as a protective outer shell for the interior of the drop shaft (Triad Midwest Mole Joint
Venture, 2013-b : IMT International, n.d.). The engineers implemented this casing by drilling 25
ft. of a 30 ft. long segment into the ground (Triad Midwest Mole Joint Venture, 2013-b). Leaving
the last 5 ft. exposed, the engineers used the steel platform to position the next 20 ft. long
COST EFFICIENCY OF THE MARKET STREET TUNNEL 35
segment so they could weld the two pieces together (Triad Midwest Mole Joint Venture, 2013-
b).
During this procedure, the engineers pumped slurry into the drill hole using a FM13V
model Ditch Witch slurry pump to ease the removal of displaced muck from the interior of the
shaft (Ditch Witch, n.d. : Triad Midwest Mole Joint Venture, 2013-b). Next, the engineers
installed a 54 in. diameter, 127 ft. long casing inside each of the 70 in. diameter casings (Triad
Midwest Mole Joint Venture, 2013-b). Moreover, the 70 in. diameter casing only surrounded the
initial 50 ft. of the other shaft because the remaining 77 ft. of the drop shaft was safely secured in
the Cooper Marl (Triad Midwest Mole Joint Venture, 2013-b). The second shaft was divided into
four 30 ft. long sections and one 7 ft. long section, and the engineers used the same installation
procedure to weld them together and to drill them into the ground (Triad Midwest Mole Joint
Venture, 2013-b). Each time a section of the 54 in. diameter shaft was implemented, a small
amount of slurry was displaced from the 70 in. diameter shaft and pumped to a slurry tanker
(Triad Midwest Mole Joint Venture, 2013-b). When the 54 in. diameter shaft was completed, the
remainder of the slurry was pumped to the slurry tanker and removed from the work site (Triad
Midwest Mole Joint Venture, 2013-b). Finally, the engineers filled the annular space between the
70 in. diameter casing and the 54 in. diameter casing with grout (Triad Midwest Mole Joint
Venture, 2013-b).
Decreased Slope of the Market Street Tunnel
According to the original blueprints by Davis & Floyd, Inc., the slope of the tunnel from
the access shaft to the Concord Pump Station was designed to be 2.34%, or decreasing 2.34 ft.
vertically per lateral 100 ft. (Davis & Floyd, Inc., 2008). However, Triad Midwest Mole
engineers objected to this plan because this drastic slope would have compromised the safety of
COST EFFICIENCY OF THE MARKET STREET TUNNEL 36
the workers in the tunnel. To construct the tunnel with this slope, the engineers would have
needed additional equipment and laborers. Specifically, the engineers would have required
hydraulic winches for the muck cars in the tunnel, multiple electrical submersible pumps, and
safety chains on any heavy objects that could have slid down the tunnel during excavation.
To clarify, hydraulic winches are tools that use a hydraulic motor to power spool rotation
by which to pull objects from one place to another (Hydraulic Winches: Hydraulic Winch, n.d.).
Because the engineers used railway cars to transport muck from the TBM to the access shaft, a
2.34% slope would have required the use of hydraulic winches so as to haul the cars through the
tunnel (P. J. Kassouf, personal communication, January 10, 2015). In fact, the joint venture
would have needed to use a minimum of two hydraulic winches within the tunnel to ensure the
safety of the laborers during excavation (P. J. Kassouf, personal communication, January 10,
2015). If one hydraulic winch broke while the TBM was in operation, the other would prevent
the railway cars from rolling backwards and crushing workers inside the tunnel (P. J. Kassouf,
personal communication, January 10, 2015). Furthermore, Triad Midwest Mole engineers would
have purchased TYS-32 Winch Misc M2030 model hydraulic winches from Markey Machinery
for this purpose (P. J. Kassouf, personal communication, January 10, 2015 : Markey Machinery,
n.d.).
In addition, a 2.34% slope would have created a significant flow of ground water from
the location of the access shaft to the lowest point of the tunnel. This fluid, coupled with the
slippery texture of the Cooper Marl, would have proven hazardous for workers walking through
the tunnel. Moreover, ground water contact with the TBM would have permanently damaged this
machinery. Therefore, the engineers would have needed to install several electrical submersible
pumps to transport ground water from the lowest point of the tunnel to the ground surface. Had
COST EFFICIENCY OF THE MARKET STREET TUNNEL 37
they constructed the tunnel with a 2.34% grade, the engineers would have employed two No:
PD605181-INT model Electrical Submersible Drainage pumps by Grindex during excavation (P.
J. Kassouf, personal communication, January 10, 2015 : Grindex, n.d.). One pump would have
been positioned near the TBM to transport water to the bottom of the access shaft (M. J. Kassouf,
personal communication, December 31, 2014). Then, the other pump would have moved the
water from the bottom of the access shaft to the ground surface (M. J. Kassouf, personal
communication, December 31, 2014). This hypothetical procedure does not differ greatly from
the actual ground water control method used during the installation of the tunnel; in fact, the only
discrepancy is that the engineers used a GSP/05/10/20 Sub-Prime Electric Submersible model
Godwin pump near the TBM instead (P. J. Kassouf, personal communication, January 10, 2015 :
Godwin Pumps, n.d.).
Lastly, the engineers would have needed heavy cables to secure any large objects that
could have slid down the length of the 2.34% grade tunnel. Specifically, Triad-Midwest Mole
would have employed the use of 2” Extra Improved Plow Steel, Right Regular Lay model cables
manufactured by Web Rigging Supply to secure heavy machinery (P. J. Kassouf, personal
communication, January 10, 2015 : Web Rigging Supply, n.d.). Moreover, additional project
costs would have resulted from a need for more laborers and excavation time. To implement a
tunnel with a 2.34% slope, the joint venture would have needed to hire at least four more
workers to operate the hydraulic winches and to monitor the integrity of the cables connecting
these devices to the railway cars (P. J. Kassouf, personal communication, January 10, 2015).
Furthermore, construction of said tunnel would have required an extra four months of mining,
thus increasing the overall cost of the project (P. J. Kassouf, personal communication, February
COST EFFICIENCY OF THE MARKET STREET TUNNEL 38
7, 2015). Ultimately, the joint venture chose to modify the proposed 2.34% grade of the tunnel to
0.082% to avoid worker fatalities and to increase project efficiency (Arup, 2013).
Connection to Concord Street Pump Station vs. Calhoun Street Tunnel
In the original blueprints for the Market Street Drainage Improvements Project, Davis &
Floyd, Inc. designed the Concord Street Tunnel to connect to the existing Calhoun Street Tunnel
(Davis & Floyd, Inc., 2008-a). From this junction, the water transported by both tunnels would
have been delivered to the Concord Street Pump Station and, ultimately, to Charleston Harbor.
However, Triad Midwest Mole raised several concerns regarding this proposed connection. First,
the Calhoun Street Tunnel has an 8 ft. diameter, whereas the Concord Street Tunnel, as depicted
in the initial drawings, would have had a 10 ft. diameter; therefore, Triad Midwest Mole would
have needed to disassemble a section of the Calhoun Street Tunnel to connect it to the Concord
Street Tunnel (Davis & Floyd, Inc., 2008-a). Secondly, Davis & Floyd, Inc. designed this
juncture to measure 90 degrees and to gradually decrease the diameter of the Concord Street
Tunnel from 10 ft. to 6 ft. at this point (Davis & Floyd, Inc., 2008-a). Even though the portion of
the Concord Street Tunnel adjoined to the Calhoun Street Tunnel would have measured less than
8 ft., Triad Midwest Mole was still concerned that this connection would destroy the Calhoun
Street Tunnel. Thirdly, the 90 degree juncture between the tunnels would have created an
imbalance of water pressure inside the Calhoun Street Tunnel (P. J. Kassouf, personal
communication, January 17, 2015). According to the blueprints by Davis & Floyd, Inc., the
portion of the Concord Street Tunnel connecting to the Calhoun Street Tunnel would have
occupied half of the top of the latter infrastructure; therefore, the water pressure would have
increased on that side of the tunnel only, causing cracks and an eventual collapse of the Calhoun
Street Tunnel (Davis & Floyd, Inc., 2008-a). To avoid destroying the Calhoun Street Tunnel,
COST EFFICIENCY OF THE MARKET STREET TUNNEL 39
Triad Midwest Mole proposed to excavate the Concord Street Tunnel in the shape of an S-curve
and to connect this infrastructure directly to an existing wet-well, or water containment vault, of
the Concord Pump Station (Triad Midwest Mole Joint Venture, 2012-a : Triad Midwest Mole
Joint Venture, 2012-b). Hence, the S-curve design enabled the engineers to preserve the Calhoun
Street Tunnel and to provide the Market Street Tunnel system with an outlet to Charleston
Harbor.
Final Lining of the Market Street Tunnel
In the original blueprints for the Market Street Tunnel, Davis & Floyd, Inc. provided for
the use of interlocking rebar and cast-in-place concrete as the final lining for the tunnel. The
rebar design would have resembled that used by Triad Midwest Mole during the construction of
the access shaft, with steel rods running laterally along the sides of the tunnel, periodically
interrupted by intersecting steel hoops (Davis & Floyd Inc., 2008-b : P. J. Kassouf, personal
communication, January 17, 2015). Moreover, the installation of the cast-in-place concrete
would have been similar to the procedure used by Triad Midwest Mole to construct the access
shaft caissons. Engineers would have placed steel forms along sections of unlined tunnel and
filled the forms with concrete. Once the concrete reached a specified strength, engineers would
have removed the forms from the tunnel, thus encasing the rebar in an impenetrable layer of
hardened concrete (Davis & Floyd Inc., 2008-b : P. J. Kassouf, personal communication, January
17, 2015). However, due to the stability of the Cooper Marl, Triad Midwest Mole felt that the
interlocking rebar would not be necessary to maintain the structural integrity of the tunnel (M. J.
Kassouf, personal communication, December 31, 2014). Thus, joint venture engineers elected to
use a cast-in-place concrete mix manufactured by Ready Mixed Concrete Company (M. J.
Kassouf, personal communication, December 31, 2014 : Ready Mixed Concrete Company,
COST EFFICIENCY OF THE MARKET STREET TUNNEL 40
2013). Furthermore, this mix included fibrillated polypropylene fibers that reinforced the
strength of the concrete (Ready Mixed Concrete Company, 2013). When incorporated at 1.5
pounds of fibers per cubic yard of concrete, the polypropylene fibers served as an acceptable
alternative to the interlocking rebar design because they strengthened the concrete mix and
ensured the integrity of the tunnel liner (BASF Construction Chemicals, LLC, 2008). While not
as strong as the rebar, Triad Midwest Mole engineers believed that the fibers would sufficiently
reinforce the tunnel liner. Therefore, the joint venture included a request to use polypropylene
fibers instead of rebar in the project change order.
Elimination of Ground Freezing at Junction of Market Street and Calhoun Street Tunnels
The initial project designs by Davis & Floyd, Inc. include the use of ground freezing to
stabilize the soil around the junction between the Concord Street Tunnel and the Calhoun Street
Tunnel. To clarify, ground freezing involves “[converting] pore water into ice by the continuous
circulation of a cryogenic fluid within a system of small diameter, closed-end pipes installed in a
pattern consistent with the shape of the area to be treated” (Moretrench, n.d., p. 1). These pipes
are installed vertically in the ground and connected in a series-parallel formation (Moretrench,
n.d.). Furthermore, “the frozen pore water acts as a bonding agent, fusing together particles of
soil or rock to significantly increase compressive strength and impart impermeability”
(Moretrench, n.d., p. 1). Ground freezing can be executed in any type of soil and in permeable or
fissured rock; moreover, this procedure is most cost efficient “in difficult, disturbed or sensitive
ground” (Moretrench, n.d., p. 2). Additional conditions that merit ground freezing as a cost
effective method for achieving ground stabilization include “ground where penetrability drilling,
jet grouting, clamshell excavation, or other vertical cut-off tools is limited,” “filled ground and
ground containing man-made obstructions,” “virgin ground containing cobbles, boulders, or an
COST EFFICIENCY OF THE MARKET STREET TUNNEL 41
irregular soil [or] rock interface,” and “ground that has been disturbed due to unstable conditions
or water inflow” (Moretrench, n.d., p. 1).
Had Triad Midwest Mole followed Davis & Floyd, Inc.’s plans, they would have used
brine as a cooling agent to freeze the ground water around the tunnels’ junction (P. J. Kassouf,
personal communication, January 17, 2015). In fact, “chilled calcium chloride brine is the most
commonly used cooling agent” for ground freezing procedures because it is practical for long-
term freezing periods that may range from several weeks to several months (Moretrench, n.d., p.
2). To install chilled calcium chloride brine, engineers pump the substance down a drop tube to
the bottom of a freeze pipe and allow it to travel through a series-parallel formation of other
freeze pipes until it returns to a refrigeration plant to be chilled and recirculated (Moretrench,
n.d.). As the brine is pumped from the ground surface to the bottom of a freeze pipe, it withdraws
heat from the surrounding soil and thus solidifies the ground (Moretrench, n.d.). Provided that
engineers install the freeze pipes correctly, brine freezing cools the ground in a consistent, even
manner. When the ground has reached a desired stability, engineers use slightly warmer brine to
maintain the extent of the ground freezing present (Moretrench, n.d.). Furthermore, brine
freezing is typically applied during the construction of shafts, large, circular, open excavations,
horizontal tunnels, and tunnel crown supports (Moretrench, n.d.).
Triad Midwest Mole expostulated connecting the Concord Street Tunnel to the existing
Calhoun Street Tunnel because this jointure would have destroyed the Calhoun Street Tunnel.
However, the City of Charleston’s approval of the change order allowed Triad Midwest Mole to
connect the Concord Street Tunnel to a wet-well in the Concord Pump Station instead. Thus, the
change order removed the need for ground freezing during the course of the project.
Furthermore, had the change order not been approved, Triad Midwest Mole would have objected
COST EFFICIENCY OF THE MARKET STREET TUNNEL 42
to ground freezing based on their experience with construction in the Cooper Marl. Due to the
marl’s strength, joint venture engineers felt that “the effectiveness of the ground freezing in the
Cooper Marl” was questionable (Triad Midwest Mole Joint Venture, 2012). Ultimately, Triad
Midwest Mole eliminated the use of ground freezing during the course of the Market Street
Drainage Improvements Project due to the approved connection between the Concord Street
Tunnel and the Concord Pump Station and to the stability of the Cooper Marl.
COST EFFICIENCY OF THE MARKET STREET TUNNEL 43
Chapter III: Methods
When Triad Midwest Mole received the contract for Division II of the Market Street
Drainage Improvements Project, they proposed several modifications to facilitate the tunnel
installation process. Furthermore, the governing question for this thesis is: how have the
proposed changes to the original plans for the Market Street Drainage Improvements Project
increased the cost efficiency of this design in terms of the money saved by the City of
Charleston? As aforementioned, the Market Street Tunnel is significant to civil engineers
because it is only the second deep stormwater tunnel system to be installed in Charleston.
Therefore, the results of this thesis satisfy an informational gap in the professional field because
no such cost analysis has been performed for a tunneling project in this area. Therefore, the
researcher has conducted this study to fill a gap in the civil engineering field, as well as to
provide a point of reference for engineers who wish to improve the cost efficiency of tunneling
projects in Charleston.
The methodology for this study involves an inductive analysis of the qualitative and
quantitative data collected by the researcher. The qualitative data is derived from the review of
literature, in which the researcher discusses the engineering techniques used to modify the
original 1997 blueprints. In addition, the quantitative data is the estimated amount of money
saved by the City of Charleston as a result of the alterations made to these plans. The products of
this data analysis are a cost efficiency evaluation of the engineering techniques used to change
the initial construction plans, as well as a cumulative quantity representing the amount of money
saved by the City of Charleston as a result of the project change order.
COST EFFICIENCY OF THE MARKET STREET TUNNEL 44
Materials
The researcher selected population samples from the pool of alterations made to the
original plans for the Market Street Drainage Improvements Project. The researcher chose design
modifications to study based on whether they were included in the project change order.
Specifically, the researcher investigated the increased depth of the tunnel, the decreased slope of
the tunnel, the final lining for the tunnel, the tunnel’s connection to the Concord Pump Station,
and the elimination of ground freezing during the course of the project. To substantiate the cost
analysis of these structural changes, the researcher has used project submittals, tunnel drawings,
equipment quotes and specifications, copies of Triad Midwest Mole’s original bid tab, and letters
of correspondence between Triad Midwest Mole, Black & Veatch Corporation, and Davis &
Floyd, Inc.
Procedures
The researcher followed a chronological procedure to collect and to analyze data. First,
the researcher assembled qualitative data within the review of literature by explaining the
engineering techniques used to modify the original blueprints for the tunnel. The researcher
worked with the mentor and Triad employees to acquire academic sources that supported the
joint venture’s decision to alter the proposed drainage system. Furthermore, the qualitative data
within the review of literature serves as the basis for the presentation and analysis of the
quantitative data included in Chapter IV. Thus, the researcher has used the explanations of the
engineering methods to demonstrate how the alterations to the initial plans affected the cost
efficiency of the Market Street Drainage Improvements Project. Within Chapters IV and V, the
researcher has examined the cost of the modified plans and has compared them to the cost of the
original design. Ultimately, this cost comparison has allowed the researcher to approximate the
COST EFFICIENCY OF THE MARKET STREET TUNNEL 45
amount of money saved by the City of Charleston as a result of the change order proposed by
Triad Midwest Mole.
The researcher’s methods are justified by similar studies conducted in the civil
engineering field. Two such bodies of literature are Benefit—Cost Analysis of Delta Water
Conveyance Tunnels, published by the Eberhardt School of Business, and Underground Unit
Cost Analysis, published by International Linear Collider. The former source discusses a cost
analysis of the design and implementation of a Delta Water deep tunnel conveyance system. This
particular study is relevant to the researcher’s thesis because the Market Street Tunnel is also a
deep tunnel network. Similarly, Underground Unit Cost Analysis examines the cost efficiency of
a construction project that culminated in the installation of a tunnel in Illinois. Although the
project discussed in the latter source is not a deep tunnel, the study is still largely similar to the
procedure outlined in the researcher’s methodology. Hence, the researcher’s strategies are
supported by earlier studies that have been conducted within the civil engineering field.
However, the researcher did not collect qualitative data from either source because neither can be
used to defend the engineering techniques involved with the construction of the Market Street
Tunnel. Moreover, the unique geology and geography of the Charleston area prevent the
researcher from comparing the Market Street Drainage Improvements Project to any other
tunneling excavation outside of downtown Charleston. Therefore, the researcher has relied on
tunnel drawings and design specifications to uphold the methods used by Triad Midwest Mole in
installing the Market Street Tunnel.
The researcher has analyzed the quantitative data presented in Chapter IV using
arithmetic and tables. Moreover, these results have been discussed thoroughly in Chapter V in
terms of how they affected the cost efficiency of the Market Street Drainage Improvements
COST EFFICIENCY OF THE MARKET STREET TUNNEL 46
Project. Furthermore, the most important points of the quantitative data will be displayed in a
powerpoint presentation during the researcher’s oral defense.
Evaluation
The accuracy of the qualitative and quantitative data will be determined by the mentor, as
he is an expert on the topic of the Market Street Tunnel. Furthermore, the researcher’s study will
be deemed a success if it clearly answers the governing question by explaining how the modified
engineering methods used to construct the Market Street Tunnel affected the cost efficiency of
the project as a whole. Additionally, the study must provide a cumulative estimate of the money
saved by the City of Charleston as a result of these design changes. If the quantitative data
indicates that the project change order did not save the City of Charleston money, the
researcher’s thesis may still be considered successful as long as the researcher answers the
governing question.
Conclusion
The conclusion of the thesis is a cost efficiency evaluation of the engineering techniques
used to modify the original construction plans for the Market Street Tunnel. To confirm the
validity of the data, the researcher has carefully checked the calculations used to determine the
amount of money saved by the City of Charleston as a result of these design alterations. In
addition, the researcher has verified the data’s accuracy with the mentor, who has access to
information regarding the project change order. Due to the inductive nature of this thesis, the
data has solely answered the governing question instead of confirming or rejecting hypotheses
made by the researcher.
COST EFFICIENCY OF THE MARKET STREET TUNNEL 47
Chapter IV
Increased Depth of the Market Street Tunnel
Modified Portion of
the Market Street
Tunnel
Construction
Procedure
Cost Before
Change
Order
Cost After
Change
Order
Cost Before
Change
Order - Cost
After Change
Order
Access Shaft
Standard Preconstruction Procedures to Prepare
for Mining of Concord Street Tunnel
$200,000.00 $280,000.00 -$80,000.00
Standard Preconstruction Procedures to Prepare
for Mining of Market Street Tunnel
$200,000.00 $250,000.00 -$50,000.00
Restoration of Parking Lot, Removal of Wooden Fence and
Gravel
$0.00 $25,000.00 -$25,000.00
Curb Restoration along
Concord Street
$0.00 $25,000.00 -$25,000.00
Demobilize Tunnel Equipment
$100,000.00 $130,000.00 -$30,000.00
Additional Costs for
the Access Shaft Only
Included in the
Change Order
Concrete Lift #6:
Concrete Form, Rebar Tying Wire, Concrete
Pour, and Caisson Sinking
$200,000.00 -$200,000.00
COST EFFICIENCY OF THE MARKET STREET TUNNEL 48
Concrete Lift #7: Concrete Form, Rebar Tying Wire, Concrete
Pour, and Caisson Sinking
$200,000.00 -$200,000.00
Concrete Lift #8: Concrete Form, Rebar Tying Wire, Concrete
Pour, and Caisson Sinking
$200,000.00 -$200,000.00
Concrete Lift #9: Concrete Form, Rebar Tying Wire, Concrete
Pour, and Caisson Sinking
$200,000.00 -$200,000.00
Concrete Lift #10: Concrete Form, Rebar Tying Wire, and
Concrete Pour
$200,000.00 -$200,000.00
Bottom of Access
Shaft: Bearing Pad, Steel Ribs, and Liner Plates
$270,000.00 -$270,000.00
Layer of #57 Stone on Access Shaft Bottom
and Pouring of Concrete Floor Slab
$100,000.00 -$100,000.00
Pour Concrete Wall Connecting Floor Slab
to Bearing Pad
$180,000.00 -$180,000.00
Market Street Tail
Tunnel Excavation
$200,000.00 -$200,000.00
Concord Street Tail Tunnel Excavation
$200,000.00 -$200,000.00
Drop Shafts
Prepare Work Area A:
Intersection of Market Street and State Street
$35,000.00 $50,000.00 -$15,000.00
COST EFFICIENCY OF THE MARKET STREET TUNNEL 49
Drill Drop Shaft A $115,000.00 $244,000.00 -$129,000.00
Demobilize Work Area A
$10,000.00 $20,000.00 -$10,000.00
Asphalt Pavement Restoration Shaft A
$10,000.00 $20,000.00 -$10,000.00
Prepare Work Area B: Intersection of Market Street and Anson
Street
$35,000.00 $50,000.00 -$15,000.00
Drill Drop Shaft B $115,000.00 $244,000.00 -$129,000.00
Demobilize Work Area B
$10,000.00 $20,000.00 -$10,000.00
Asphalt Pavement
Restoration Shaft B
$10,000.00 $20,000.00 -$10,000.00
Prepare Work Area C:
Intersection of Market Street and Church Street
$35,000.00 $50,000.00 -$15,000.00
Drill Drop Shaft C $115,000.00 $244,000.00 -$129,000.00
Demobilize Work
Area C
$10,000.00 $20,000.00 -$10,000.00
Asphalt Pavement Restoration Shaft C
$10,000.00 $20,000.00 -$10,000.00
Additional Costs for
the Drop Shafts Only
Included in the
Change Order
Mobilization of
Equipment
$120,000.00 -$120,000.00
Tunnels Including
Adits: Market Street
Tunnel
TBM Setup and Launch
$100,050.00 $100,050.00
Installation of Additional TBM
$150,000.00 $190,000.00 -$40,000.00
COST EFFICIENCY OF THE MARKET STREET TUNNEL 50
Attachments and First Railroad Track for First Five-Muck-Car
Train at 32 ft. from Access Shaft Bottom
Installation of
Additional Short Conveyor Belt for
Muck Removal at 140 ft. from Access Shaft Bottom
$200,000.00 $225,000.00 -$25,000.00
*Installation of
Second Railroad Track for the Market
Street Tunnel Eliminated from Construction
Procedures Following Submission and
Approval of Change Order
Installation of Second
Railroad Track for Second Five-Muck-
Car Train at 300 ft. from Access Shaft Bottom
$100,000.00 $125,000.00
Installation of Railroad Track Switch for
Operational Two Train Mining
$0.00 $15,000.00 -$15,000.00
Two Crew Shifts to
Mine from Tunnel Excavation Station 41+00 to Station
45+55 (Davis & Floyd, Inc., 2008-d)
$450,000.00 $480,000.00 -$30,000.00
Two Crew Shifts to
Mine from Tunnel Excavation Station
45+55 to Station 50+11 (Davis & Floyd, Inc., 2008-d)
$450,000.00 $480,000.00 -$30,000.00
Installation of Final
Tunnel Liner from Station 38+00 to
Station 50+00 (Davis & Floyd, Inc., 2008-d)
$600,000.00 $625,000.00 -$25,000.00
Additional Costs for
Market Street Tunnel
Mining Only
Included in the
TBM Setup and Launch to Mine
Market Street Tail Tunnel
$160,000.00 -$160,000.00
COST EFFICIENCY OF THE MARKET STREET TUNNEL 51
Change Order
Tunnels Including
Adits: Concord Street
Tunnel
Mobilization of AF 220 Hydraulic Drill
Rig for Drilling of Concrete Down Holes
$0.00
TBM Setup and Launch
$175,000.00 $175,000.00
Installation of
Additional TBM Attachments and First
Railroad Track for First Five-Muck-Car Train at 32 ft. from
Access Shaft Bottom
$150,000.00 $190,000.00 -$40,000.00
Installation of Additional Short
Conveyor Belt for Muck Removal at 140
ft. from Access Shaft Bottom
$150,000.00 $190,000.00 -$40,000.00
Installation of Second Railroad Track for
Second Five-Muck-Car Train at 300 ft.
from Access Shaft Bottom
$100,000.00 $125,000.00 -$25,000.00
Additional Costs for
Concord Street
Tunnel Mining Only
Included in the
Change Order
Mobilization of AF 220 Hydraulic Drill
Rig for Drilling of Concrete Down Holes
$130,000.00 -$130,000.00
Total Cost Before Change Order Total Cost After Change Order Total Savings
$3,635,050 $6,592,000 -$2,956,950
Regarding the installation of the access shaft, “Standard Preconstruction Procedures” for
both the Market Street and Concord Street Tunnels involved the engineers checking the integrity
of the mining equipment, especially the TBM, before beginning the excavation process (P. J.
Kassouf, personal communication, February 22, 2015). Next, the “Floor Slab” is simply the
concrete floor of the access shaft. Thirdly, the “Tail Tunnel” that the engineers excavated was a
COST EFFICIENCY OF THE MARKET STREET TUNNEL 52
small space adjoined to the access shaft that resembled a partially mined tunnel. In total, the
engineers constructed two tail tunnels: one for the Market Street Tunnel and one for the Concord
Street Tunnel. To clarify, the purpose of the tail tunnels was to provide additional room in the
bottom of the access shaft so that the engineers could easily crane lift the muck cars to ground
level, empty them, and return them to the shaft during the mining process (P. J. Kassouf,
personal communication, February 22, 2015). While the cars were being emptied, the locomotive
used to haul them would be parked within the tail tunnel, thus providing the engineers more
room to attach dirt-filled muck cars to the crane cable (P. J. Kassouf, personal communication,
February 22, 2015). Hence, by enlarging the size of the access shaft bottom, the tail tunnels
facilitated the excavation of both the Market Street and Concord Street tunnels.
Concerning the implementation of the drop shafts, “Prepare Work Area” refers to the
engineers’ placement of caution signs and fences around the future construction site of each drop
shaft (P. J. Kassouf, personal communication, February 22, 2015). Moreover, the “Installation of
Additional Short Conveyor Belt” listed under the sections entitled, “Tunnels Including Adits:
Market Street Tunnel,” and “Tunnels Including Adits: Concord Street Tunnel,” indicates the
joint venture’s use of a conveyor belt to transport displaced muck from the TBM to the muck
cars (P. J. Kassouf, personal communication, February 22, 2015). As stated in the table, at 140 ft.
from the bottom of the access shaft, the engineers installed more lengths of conveyor belt in
order to remove muck from the tunnels more quickly (P. J. Kassouf, personal communication,
February 22, 2015). Next, the “Concrete Down Holes” entry under, “Tunnels Including Adits:
Concord Street Tunnel,” refers to part of the process used to line the tunnel shafts with concrete.
Every lateral 800 ft., the joint venture drilled a hole down to the depth of the tunnel, lined the
hole with steel, positioned a hose over the empty concrete forms surrounding the tunnel, and
COST EFFICIENCY OF THE MARKET STREET TUNNEL 53
pumped concrete through the hose to fill the forms (P. J. Kassouf, personal communication,
February 22, 2015). Thus, the term “Concrete Down Holes” is a name given to the holes drilled
into the ground during this procedure. Finally, any reference to the mobilization or
demobilization of equipment simply indicates the transportation of tools and machinery to and
from a construction site.
COST EFFICIENCY OF THE MARKET STREET TUNNEL 54
Decreased Slope of the Market Street Tunnel
Equipment Needed to Mine Tunnel with 2.34% Grade Cost of
Equipment
Minimum of Two TYS-32 Winch Misc M2030 Hydraulic Winches by Markey Machinery
$95,000.00
Two No: PD605181-INT Electrical Submersible Drainage Pumps by
Grindex
$17,200.00
6000 ft. of 2 in. Extra Improved Plow Steel, Right Regular Lay Cables by Web Rigging Supply
$82,314.00
Minimum of Four Laborers to Operate Hydraulic Winches and to Monitor
the Integrity of Cables
$220,000.00
Additional Four Months of Excavation Time $544,000.00
Total Savings
$958,514.00
The data for the overall cost of decreasing the slope of the Market Street Tunnel is based
on quotes from equipment manufacturing companies and conversations between the researcher
and Paul Kassouf, Stephen O’Connell, and Matthew Kassouf. Because the joint venture did not
mine the tunnel at a 2.34% slope, it is not necessary for the researcher to include “Before Change
Order” and “After Change Order” columns within this table because none of the listed equipment
was used during the excavation of the tunnel.
COST EFFICIENCY OF THE MARKET STREET TUNNEL 55
Connection to Concord Street Pump Station vs. Calhoun Street Tunnel
Construction Procedure Before Change
Order: Cost to
Connect Concord
Street Tunnel to
Calhoun Street
Tunnel
After Change
Order: Cost to
Connect Concord
Street Tunnel to
Concord Pump
Station
Cost Before
Change Order
– Cost After
Change Order
Set up for Transition Tunnel Connecting Concord Street
Tunnel to Calhoun Street Tunnel
$0.00
Inspection of Calhoun Tunnel $10,000.00 $10,000.00
Transition Tunnel Excavation
*Following the change order, the
transition tunnel was designed with different dimensions to connect the Concord Street
Tunnel to the Concord Street Pump Station wet well.
$75,000.00 $40,000.00 $35,000.00
Set Concrete Forms and Pour Concrete for Transition Tunnel
$95,000.00 $40,000.00 $55,000.00
Strip Concrete Forms, Clean and
Patch Final Transition Tunnel Liner
$5000.00 $8000.00 -$3000.00
Set Flumes to Drain Calhoun Tunnel
$25,000.00 $25,000.00
Break Out Calhoun Tunnel $30,000.00 $30,000.00
Clean Transition Tunnel Connecting Concord Street
Tunnel to Calhoun Street Tunnel
$10,000.00 $10,000.00
Probe Cooper Marl from Concord Street Tunnel to
Concord Street Pump Station Wet Well
$40,000.00 -$40,000.00
Inspect Concord Street Pump Station and Remove Debris from Wet Well
$30,000.00 -$30,000.00
COST EFFICIENCY OF THE MARKET STREET TUNNEL 56
Drain Concord Street Pump Station Wet Well
$25,000.00 -$25,000.00
Break Out Concord Street Pump
Station Wet Well Wall
$50,000.00 -$50,000.00
Post Construction Cleanup and
Demobilization of Equipment
$10,000.00 -$10,000.00
Total Cost Before Change Order Total Cost After Change Order Total Savings
$250,000.00 $243,000.00 $7000.00
To clarify, “Inspection of Calhoun Tunnel,” means that the engineers would have walked
through the Calhoun Tunnel to note any large debris that could have inhibited their construction
of the transition tunnel (P. J. Kassouf, personal communication, March 7, 2015). Next, the
“Flumes” that the engineers would have used to drain the Calhoun Tunnel are drainage pipes.
Lastly, the joint venture needed to “Probe [the] Cooper Marl from [the] Concord Street Tunnel to
[the] Concord Street Pump Station Wet Well” to ensure that no air pockets had formed above the
concrete connecting these two structures (P. J. Kassouf, personal communication, March 7,
2015). Had the engineers allowed air pockets to form in the Cooper Marl, the stability of the
ground directly above this section of concrete would have been compromised. In other words,
the Cooper Marl would have settled around the concrete, thus creating potholes and other such
cave ins at ground level.
COST EFFICIENCY OF THE MARKET STREET TUNNEL 57
Final Lining of the Market Street Tunnel
Construction
Procedure
Cost Before
Change Order
Cost After
Change Order
Cost Before Change Order –
Cost After Change Order
Installation of
Rebar
$200,000.00 $200,000.00
Installation of Tie-Wire
$50,000.00 $50,000.00
Steel Forms $48,000.00 $96,000.00 -$48,000.00
Concrete Down
Holes
$160,000.00 $360,000.00 -$200,000.00
Total Cost Before Change Order Total Cost After Change Order Total Savings
$458,000.00 $456,000.00 $2000.00
Due to the change order, the joint venture used a cast-in-place concrete mix containing
polypropylene fibers to line the tunnel. However, the cost of pouring the concrete did not change
as a result of the change order. Furthermore, the engineers used steel forms inside the tunnel to
set the concrete mix.
COST EFFICIENCY OF THE MARKET STREET TUNNEL 58
Elimination of Ground Freezing
Construction Procedure Cost Before Change Order
Traffic Control for Concord Street $5000.00
Mobilization of Equipment $100,000.00
Brine Installation $500,000.00
Brine Maintenance $200,000.00
Post Construction Cleanup and Demobilization of Equipment $28,000.00
Total Savings
$833,000.00
The data for the overall cost of using ground freezing at the junction between the
Concord Street and Calhoun Street tunnels is based on quotes from equipment manufacturing
companies and conversations between the researcher and Paul Kassouf, Stephen O’Connell, and
Matthew Kassouf. Because the joint venture did not use the ground freezing method, it is not
necessary for the researcher to include “Before Change Order” and “After Change Order”
columns within this table because none of the listed equipment was used during the excavation
of the tunnel.
COST EFFICIENCY OF THE MARKET STREET TUNNEL 59
Total Savings
Modification Total Savings
Increased Depth -$2,956,950
Decreased Slope $958,514
Connection to PS $7000
Final Lining $2000
Elimination of Ground Freezing $833,000
-$1,156,436
COST EFFICIENCY OF THE MARKET STREET TUNNEL 60
Chapter V
Through this thesis, the researcher has examined the cost efficiency of the Market Street
Drainage Improvements Project in terms of the money saved by the City of Charleston. To
conduct this case study, the researcher has identified five major modifications made to the
original design plans for this tunneling project. By analyzing the construction process associated
with each blueprint revision, the researcher has compiled qualitative data that explains each
design revision. Additionally, the researcher has assembled quantitative data in the form of price
charts that correspond to each structural alteration. In this way, the researcher has established
sufficient information to draw conclusions regarding the cost efficiency of the Market Street
Drainage Improvements Project.
Principal Findings and Interpretation of Data
From the most expensive revision to the least expensive, the blueprint modifications are
the increase in the tunnel’s depth, the decrease in the tunnel’s slope, the elimination of ground
freezing at the tunnel’s junction with the Calhoun Street Tunnel, the tunnel’s connection to the
Concord Pump Station, and the tunnel’s specialized concrete liner. First, the augmented depth of
the tunnel raised the cost of the project by nearly three million dollars; however, this was the
only alteration that increased overall project expenses. Next, decreasing the tunnel’s slope and
eliminating the use of ground freezing lowered project costs by nearly one hundred thousand
dollars each. In addition, the tunnel’s connection to the Concord Pump Station rather than the
Calhoun Street Tunnel decreased project expenses by seven thousand dollars. Finally, the
changes to the cast-in-place concrete tunnel liner saved the City of Charleston two thousand
dollars.
COST EFFICIENCY OF THE MARKET STREET TUNNEL 61
Based on the qualitative and quantitative data, the researcher can conclude that the
increased depth of the Market Street Tunnel proved the most expensive for the City of
Charleston because it affected the entire structure of the tunnel. By lowering the tunnel, Triad
Midwest Mole provided for a significantly wider buffer zone between the Market Street Tunnel
and the deteriorated Cooper River Tunnel. Additionally, this decision required the joint venture
to increase the depth of the adjoining tunnel shafts. Because more material was needed to
construct the access and drop shafts, the cost of installing the tunnel increased substantially.
Although the construction procedures required to extend the tunnel shafts increased total project
costs by approximately 1.6 million dollars, these design changes did not comprise the majority of
the cost differences between the original blueprints and the modified plans.
Following the increased depth of the tunnel, the most expensive design modifications
were the decreased tunnel slope and the elimination of ground freezing. Unlike the former
alteration, however, these structural changes saved the City of Charleston money because they
involved the subtraction of materials from construction procedures. By changing the slope of the
tunnel from 2.34% to 0.082%, Triad Midwest Mole avoided the use of additional equipment,
laborers, and time to construct the tunnel. Similarly, removing ground freezing from the design
plans made it unnecessary for the joint venture to purchase extra equipment and to hire a
subcontractor to install brine. Thus, the decreased tunnel slope and the elimination of ground
freezing saved the City of Charleston money because they both simplified the construction of the
Market Street Tunnel.
Implications
Because the Market Street Drainage Improvements Project is the second deep tunnel
system to be installed in Charleston, the success of this drainage network will confirm this design
COST EFFICIENCY OF THE MARKET STREET TUNNEL 62
as a solution to flash flooding for the downtown area. Furthermore, the efficiency of this
stormwater tunnel, coupled with that of the Calhoun Tunnel, may prompt the City of Charleston
to initiate similar deep tunneling projects in the future. Moreover, the design changes regarding
the tunnel liner and the use of ground freezing may encourage civil engineers to further test the
stability of the Cooper Marl. Because this geological substance has proven durable in past
tunneling projects, it is likely that tunneling engineers in Charleston will continue to rely on its
strength in the future.
Limitations
The most significant limitations that the researcher encountered during the course of this
study resulted from the written discussions of the decreased tunnel slope and the elimination of
ground freezing. Because the costs for these procedures were determined using lists of
hypothetical materials, the researcher cannot guarantee that the data assembled for these
alterations is completely accurate. However, the information presented as qualitative and
quantitative data for both of these design modifications has been approved by Triad Midwest
Mole engineers. Moreover, an additional limitation arose during the discussion of Division III of
the Market Street Drainage Improvements Project. This phase of construction is currently under
bid; thus, the researcher was not able to fully explain the effect this stage will have on urban
flash flooding in Charleston. Despite this lack of information, this limitation does not affect the
researcher’s ability to answer the governing question.
Summary
The researcher’s purpose in conducting this study was to examine the proposed changes
to the original plans for the Market Street Drainage Improvements Project and to analyze how
COST EFFICIENCY OF THE MARKET STREET TUNNEL 63
these modifications affected the cost efficiency of the project in terms of the money saved by the
City of Charleston. According to the researcher’s calculations, the City of Charleston did not
save money as a result of the blueprint alterations. In fact, the difference between the cost of the
initial design and the cost of the design after the change order is $1,156,436. While the revisions
made to the plans for the Market Street Tunnel decreased the cost efficiency of the construction
process, the researcher is confident that they increased the time efficiency and the safety of the
project as a whole. Moreover, modifications that helped to ensure on-site safety included the
increased tunnel depth, the decreased tunnel slope, and the tunnel’s connection to the Concord
Pump Station rather than the Calhoun Street Tunnel. Hence, three out of the five alterations
analyzed by the researcher significantly contributed to the engineers ’ safety during the tunnel’s
excavation. Although the City of Charleston could have saved money by rejecting the project
change order, the cheaper design by Davis & Floyd, Inc. may have come at the cost of worker
fatalities, irreparable breaches within the Concord Street and Calhoun Street tunnels, and the
overall failure of Division II. Ultimately, the modifications to the original construction plans for
the Market Street Drainage Improvements Project decreased the cost efficiency of this project by
$1,156,436.
COST EFFICIENCY OF THE MARKET STREET TUNNEL 64
References
Arup. (2013). Tunnel Alignment Key Plan (Job No. 226651-00). Houston, TX: Arup Texas Inc.
Barry, A. B. (n.d.). Surveying. Retrieved from
www.state.nj.us/transportation/eng/documents/survey.
BASF Construction Chemicals, LLC (2008). MasterFiber F70. Cleveland, OH: BASF
Construction Chemicals, LLC.
Bickel, J. O. & Kuesel, T. R. (1982). Tunnel Engineering Handbook. New York, NY: Van
Nostrand Reinhold Company Regional Offices.
Braen, D. (2013). Crushed Stone Grades: Complete Guide. Retrieved from
http://www.braenstone.com/crushed-stone-grades.
Cabiness, L. S., Kirk, S. A., O’Connell, S. A., Swartz, J. T. (2012). Sustainable underground
solutions for an above ground problem. Available from http://books.google.com.
Caterpillar. (2007). 302.5C Mini Hydraulic Excavator. Retrieved from www.ritichiespecs.com.
Charleston Water System. (n.d.). The regulatory revolution. Retrieved from
www.charlestonwater.com/water_history_part3.
Charleston Water System. (n.d.). West Ashley Tunnel (Phase V). Retrieved from
www.charlestonwater.com/water_history_part3.
City of Charleston. (2012). Market Street Drainage Improvement Project Division II—tunnels &
shafts. (Public Information). Retrieved from www.charleston-sc.gov.
Concreate Welded Wire Reinforcing Co. (n.d.). Rebar Tying Wire. Retrieved from
http://www.reinforcingmesh.net/reinforcing-steel/rebar-tie-wire.html.
Davis & Floyd, Inc. (1984). Master Drainage and Floodplain Management Plan. Charleston,
SC: Davis & Floyd, Inc.
COST EFFICIENCY OF THE MARKET STREET TUNNEL 65
Davis & Floyd, Inc. (2008-a). Tunnel Connection to Existing Calhoun Tunnel (Job No.
30407.00). Charleston, SC: Davis & Floyd, Inc.
Davis & Floyd, Inc. (2008-b). Break-In Tunnel and Headwall Geometry (Job No. 30407.00).
Charleston, SC: Davis & Floyd, Inc.
Davis & Floyd, Inc. (2008-c). Profile-Concord Street Tunnel (Job No. 30407.00). Charleston,
SC: Davis & Floyd, Inc.
Davis & Floyd, Inc. (2008-d). Tunnel and Shaft Location Plan I (Job No. 30407.00). Charleston,
SC: Davis & Floyd, Inc.
Davis & Floyd, Inc. (2012-a). Market Street Drainage Improvements Division II Tunnels and
Shafts (Job No. 30407.00). Charleston, SC: Davis & Floyd, Inc.
Davis & Floyd, Inc. (2012-b). Contract Documents and Construction Specifications for Market
Street Drainage Improvements. (Job No. 30407.00). Charleston, SC: Davis & Floyd, Inc.
Davis & Floyd, Inc. (2012-c). Addendum No. 3. (Job No. 30407.00). Charleston, SC: Davis &
Floyd, Inc.
Ditch Witch. (n.d.). FM13V-Service. Retrieved from www.ditchwitch.com/trenchless/fluid-
management/fm13v.
Drolet, L. F., Cabiness, L. S., Swartz, J. T., O’Connell, S. A. (2012). “Boring” Old Charleston—
Tunneling and Trenchless Technology Key to Charleston’s Infrastructure. In M. Fowler,
R. Palermo, R. Pintabona, & M. Smithson (Eds.), North American Tunneling (765-771).
Colorado: Society for Mining, Metallurgy, and Exploration, Inc.
DSI Underground Systems Inc. (n.d.). Standard Liner Plates With Corrugations. Retrieved from
www.dsiunderground.com/products/.../underground.../liner-plates.html.
COST EFFICIENCY OF THE MARKET STREET TUNNEL 66
Great Outdoor Recreation Pages, [GORP], (2010). The Low Country. Retrieved from
http://www.gorp.com.
Grindex. (n.d.) Electrical submersible drainage pump. Retrieved from
http://www.grindexpump.com.
Godwin Pumps. (n.d.) GSP/05/10/20 Sub-Prime Electric Submersible Pumps. Retrieved from
www.godwinpumps.com.
Hydraulic Winches: Hydraulic Winch. (n.d.). In Engineering Dictionary online. Retrieved from
http://www.engineering-dictionary.com.
IMT International. (n.d.). AF 220 Hydraulic Drill Rig. Retrieved from www.imtspa.com.
Ingersoll Rand. (2015-a). Air Digger, 1850 BPM, 47.0 CFM. Retrieved from
www.ingersollrandproducts.com.
Ingersoll Rand. (2015-b). 5-1/2” Clay Spade. Retrieved from www.ingersollrandproducts.com.
Integrated Engineers, Inc. (n.d.). Wastewater—definition of. Retrieved from
http://www.environmental-expert.com/services/wastewater-definition-of.
Kirk, S. A. (n.d.-a). Market St. drop shaft construction. Retrieved from www.charleston-
sc.gov/index.aspx.
Kirk, S. A. (n.d.-b). Project description. Retrieved from www.charleston-sc.gov/index.aspx.
Klecan, W. F., Horner, R. L., & Robison, M. J. (n.d.). Tunneling in the Cooper Marl of
Charleston, South Carolina. OneMine, 927-939. Retrieved from
http://www.onemine.org/index.cfm.
Markey Machinery. (n.d.) Markey Machinery TYS-32 Winch Misc M2030. Retrieved from
http://www.mymarinetracker.com.
COST EFFICIENCY OF THE MARKET STREET TUNNEL 67
Milwaukee Metropolitan Sewer District, Wastewater Treatment. (n.d.). Deep tunnel—how it
works. Retrieved from http://www.mmsd.com/deeptunnelhowitworks.aspx.
Moretrench. (n.d.). Ground Freezing. Rockaway, New Jersey: Moretrench.
O’Connell, S. (2013). A change in ground conditions necessitates fast-track design changes.
Available from http://books.google.com.
Plastomatic Valves, Inc. (2013). Definition of a valve. Retrieved from
http://www.plastomatic.com/definition.html.
Proctor, R. V., & White, T. L. (1977). Earth Tunneling with Steel Supports. Youngstown, OH:
Commercial Shearing, Inc.
Putzmeister America, Inc. (2013). 20Z-Meter Truck-Mounted Concrete Boom Pump. Sturtevant,
WI: Putzmeister America, Inc.
Ready Mixed Concrete Company. (2013). Submittal No.: 16409. Charleston, SC: Ready Mixed
Concrete Company.
Slade, D. (2013, June 21). City plans to fix downtown’s submerged streets by 2020. The Post
and Courier, p. A1.
Terracon Consultants, Inc. (2012). Report on Location of Abandoned CPW Tunnel.
(Specification Section 02400). Charleston, SC: Terracon Consultants, Inc.
Tideflex. (n.d.) Tideflex Check Valves. Retrieved from http://www.tideflex.com.
Triad Midwest Mole Joint Venture (2009-a). Calhoun Street Pump Station Break-In
Construction Sequence (Job No. 226651-00). Charleston, SC: Triad-Midwest Mole Joint
Venture.
Triad Midwest Mole Joint Venture (2009-b). Tunnel Alignment Key Plan (Job No. 226651-00).
Charleston, SC: Triad-Midwest Mole Joint Venture.
COST EFFICIENCY OF THE MARKET STREET TUNNEL 68
Triad Midwest Mole Joint Venture. (2012-a). Cost Reduction Proposal #1. Walton Hills, OH:
Triad Engineering.
Triad Midwest Mole Joint Venture. (2012-b). Submittal 02305-01-A_Shaft Construction Work
Plan. Mt. Pleasant, SC: Triad Engineering.
Triad Midwest Mole Joint Venture. (2013-a). Access Shaft Drawings and Design Calcs. Mt.
Pleasant, SC: Triad Engineering.
Triad Midwest Mole Joint Venture. (2013-b). Drop Shaft Construction Work Plan. Mt. Pleasant,
SC: Triad Engineering.
Tooling U-SME. (2013). What is the definition of “gate valve”? Retrieved from
www.toolingu.com/definition-570120-31734-gate-valve.html.
Web Rigging Supply. (n.d.) Extra Improved Plow Steel, Right Regular Lay. Retrieved from
http://www.webriggingsupply.com.
Williamson, S. (2001). Drop structure design for wastewater and stormwater collection systems.
Retrieved from http://www.pbworld.com/pdfs/publications/monographs/williamson.pdf.
U.S. Department of Transportation Research and Innovative Technology Administration [RITA].
(n.d.). ITS Joint Program Office. Retrieved from http://www.its.dot.gov.
Zebra Environmental. (2012). Cone Penetration Test. Retrieved from
http://www.zebraenv.net/cpt.htm.