cost benefit analysis of natural gas transmission projects · pdf filecost benefit analysis of...
TRANSCRIPT
Cost Benefit Analysis
of Natural Gas Transmission Projects The EIB approach
Nicola Pochettino
European Investment Bank
entsog. 5th TYNDP Workshop, Brussels, 20th June 2012 1
Contents
The European Investment Bank
Value added and project requirements
Cost Benefit Analysis
A methodology for natural gas transmission, LNG terminals and
underground gas storage projects
CBA Case Study
Underground Gas Storage Project
Security of Supply
A key selection criterion for energy infrastructure projects
entsog. 5th TYNDP Workshop, Brussels, 20th June 2012 2
The European Investment Bank Value added and project requirements
entsog. 5th TYNDP Workshop, Brussels, 20th June 2012 3
Pillar I
Support for EU priority objectives
Pillar II
Assessment of project quality and soundness
Pillar III
Financial benefits of EIB funds
Technical assistance
Value Added of EIB’s lending activities The three pillars as guideline to project investment
entsog. 5th TYNDP Workshop, Brussels, 20th June 2012 4
Be consistent with at least one of EIB’s objectives
Be reasonably mature and with good permitting prospects
Be technically sound;
Use of proven technologies and setting-out of necessary countermeasures to
overcome operational problems of the (new) interconnected system
Be financially viable
Show an acceptable economic return (benefits offset the costs);
Analysis of alternatives, EIB’s economic criteria
Comply with National, EU and EIB’s procurement policy
EU Procurement Directive, EIB’s Guide to Procurement (also applied to non-EU
projects)
Comply with National, EU and EIB’s environmental and social standards
EU Environmental Directives (EIA, Habitats, Birds etc.), EIB’s Statement on
Environmental Principles and Standards (also applied to non-EU projects)
Project Requirements
entsog. 5th TYNDP Workshop, Brussels, 20th June 2012 5
Cost Benefit Analysis A methodology for natural gas transmission, LNG
terminals and underground gas storages
entsog. 5th TYNDP Workshop, Brussels, 20th June 2012 6
To identify the project is necessary to:
state scale and dimension
analyse the market where the gas will be placed
establish the need for additional infrastructure through a market and/or
system study
describe the engineering features of the infrastructure:
basic functional data
physical features
other features (in particular gas system structure and building techniques)
Project identification Natural gas grids, terminals and storage
entsog. 5th TYNDP Workshop, Brussels, 20th June 2012 7
Key information required:
energy demand (average and peak);
seasonal and long-term trends and demand curve for a typical day;
for UGS, typical injection-withdrawal cycle (seasonal, daily, etc.).
time horizon: networks 25 years; LNG/UGS 20 years
price forecast
The option analysis should consider possible alternatives:
within the same infrastructure
possible realistic alternatives for producing the energy required
Feasibility and option analysis Natural gas grids, terminals and storage
entsog. 5th TYNDP Workshop, Brussels, 20th June 2012 8
Generally quantified as the revenue from the sale of energy and evaluated by
estimating the community’s willingness to pay for energy:
quantifying the costs the user must incur to acquire energy
taking into account the project’s load factor / utilisation rates
In case of UGS/LNG, the economic analysis quantifies the main roles for
storage and their associated benefits (or avoided costs):
Seasonal storage, valued at the difference between the price of summer and winter
gas (value of swing);
Peak shaving, estimated by costing the alternative fuels;
Security of supply, calculated on the same basis used for the peak shaving issue
System technical benefits, valued at the avoided cost of additional facilities (e.g.
compressor stations)
Economic Analysis: benefits Natural gas grids, terminals and storage
entsog. 5th TYNDP Workshop, Brussels, 20th June 2012 9
Costs
Capital expenditures
Operating expenditures
Externalities
Environmental
Security of supply
Sensitivity and risk analysis
Capex, opex
Mix and dynamics of critical inputs:
demand dynamics (i.e. forecasts of: growth rates, demand elasticity, load
factors, etc.);
the dynamics of the prices of gas and of the substitute fuels
For UGS, the length of the working gas cycle
…
Economic Analysis: costs and externalities Natural gas grids, terminals and storage
entsog. 5th TYNDP Workshop, Brussels, 20th June 2012 10
CBA Case Study Underground Gas Storage Project
entsog. 5th TYNDP Workshop, Brussels, 20th June 2012 11
The underground gas storage (UGS) project consists of the conversion of
an onshore depleted gas field into an UGS.
The reservoir is situated 2500 m subsurface. The project involves the
drilling and completion of 10 new wells (6 for injection/withdrawal, 3 for
observation and 1 for liquids reinjection), a compression and processing
plant and a 10 km pipeline between the plant and the national grid.
The core elements of project implementation are scheduled to be
undertaken from 2012 until 2015.
The project is important and urgent for the Country’s energy sector. UGS
facilities in the Country, which are considered part of the gas transportation
system, are regulated.
It will mainly be used to cope with seasonal variations in gas demand and
will also reinforce the capacity of the Country’s gas system to meet peak
demand requirements as well as managing potential supply shortfalls.
UGS Project identification 1/2
entsog. 5th TYNDP Workshop, Brussels, 20th June 2012 12
The project is planned to operate at reduced injection volumes first two
years in order to monitor reservoir conditions, before stepping up to full
capacity in the third year of operations (2018).
The planned total gas storage volume of 1.0 Gm3 with 0.7 Gm3 of working
and 0.3 Gm3 of cushion gas is technically feasible. The operating regime at
full capacity envisages injection over a 5 to 6 month period and withdrawal
of the 1.0 Gm3 of working gas over a 4 month period.
The average injection rate is planned to be 5.5 Mm3/day and the average
withdrawal rate is 8.3 Mm3/day. The peak withdrawal rate is 15 Mm3/day,
which represents ca. 10% of the Country’s peak daily gas demand.
This rate, could in principle supply gas for 65 days starting from a full
reservoir.
The storage’s investment cost is EUR 700/m3
Annual operating costs are estimated at 3% of capex
UGS Project identification 2/2
entsog. 5th TYNDP Workshop, Brussels, 20th June 2012 13
The economic analysis of the storage facility has identified and quantified
three main roles for storage and their associated benefits (or avoided costs)
as discussed briefly below:
seasonal storage, valued at the difference between the value of
summer and winter gas (value of swing), which averaged 0.7 EUR/GJ
over the last decade.
value of peak shaving, estimated by costing the alternative fuels, which
have been assumed to be gasoil (for residential) and fuel oil for
power/industry. The number of peak shaving days has been estimated
in 30 days per annum.
security of supply, estimated as the value of gas of the avoided
interruption, multiplied by probability weighted expected volume of
interrupted supply covered by the storage. The number of days
possibly concerned by supply disruption issues (= total 120 winter days
x 1% probability of event) is 1.2 per annum.
UGS Economic analysis
entsog. 5th TYNDP Workshop, Brussels, 20th June 2012 14
The economic rate of return (ERR) of the project is calculated at 7.5%.
In the event that the facility can not be used at full capacity due to reservoir
limitations, sensitivity analysis shows that the ERR reduces by 1%-point for
each 10% reduction in working gas capacity.
Another approach to the assessment of the economic profitability of the
project would be to evaluate the best alternative to the project.
Closest option is deemed to be an LNG regasification plant.
If the UGS were not built, seven150,000 m3 LNG tanks would need to
be constructed and operated.
In this case, the economic cash flow is the difference in costs (capex +
opex + externalities) between the LNG facility and the UGS, which also
leads to an economic rate of return of about 7.5%.
UGS Economic rate of return
entsog. 5th TYNDP Workshop, Brussels, 20th June 2012 15
Security of Supply A key selection criterion for energy infrastructure
projects
entsog. 5th TYNDP Workshop, Brussels, 20th June 2012 16
Security of supply is a fundamental pillar of energy policy, particularly
for countries heavily dependent on foreign supplies
Difficult task is to translate this goal into economically sound decisions
The value of energy security is relevant in the assessment of the
economic viability of energy projects
Market-centric definition of energy security: the availability of a regular
supply of energy at an affordable price (IEA, 2001)
Availability – physical element
Affordability – pricing element
Broader definitions of energy security include:
Accessibility – geopolitical element
Acceptability – environmental element
Evaluating Security of Supply Defining a tool to prioritise and select energy projects
entsog. 5th TYNDP Workshop, Brussels, 20th June 2012 17
Energy security possesses public good characteristics and relates to
problems of market failures:
Incomplete markets for security of supply
Incomplete and asymmetric information
Grid externalities (spill-over effects on others not priced in the market)
This means that:
the market is not able to provide the right level of security in all circumstances
public intervention could be justified
externalities or, alternatively, the willingness-to-pay for security non satisfied
through the market should be evaluated
Energy Security and Market Failures Features of externality
entsog. 5th TYNDP Workshop, Brussels, 20th June 2012 18
External costs need to be identified, quantified, and translated in monetary
terms (i.e. convert externality in a unit value, e.g. €/MWh)
• Quantifying the level of the externality is the most useful approach with respect
to providing policy guidance
• It represents a useful tool to internalize the externality and correct this market
failure.
To determine the optimal security level, the following tasks should be
performed:
1. Evaluating the likelihood of events (such as supply disruptions, price shocks,
price volatility…) leading to negative consequences;
2. Assessing the damage incurred by society because of these events;
3. Identifying tools to limit the likelihood of these events and/or to restrict the
damage they provoke;
4. Calculating the costs of implementing each of these tools for mitigation and
adaptation.
The right level of security of supply Conceptual steps
entsog. 5th TYNDP Workshop, Brussels, 20th June 2012 19
In line with the definition of energy security, a methodology evaluates the
two constituent components separately:
Energy Security = Physical availability component + Pricing component
The physical availability component relates to the infrastructure under
consideration taking into account the costs associated with compliance
with the N-1 rule and equals:
total discounted costs to comply with the N-1 standard
total discounted energy supplied by the project
The pricing component depends on the country’s exposure to price
volatility and equals the cost to hedge the such volatility
The methodology can help: • evaluate and compare different energy projects
• establish energy policies
A methodology To quantify and monetize security of energy supply
entsog. 5th TYNDP Workshop, Brussels, 20th June 2012 20
http://www.eib.org/
Tel: (+352) 43 79 - 22000
For more information
entsog. 5th TYNDP Workshop, Brussels, 20th June 2012 21