cost and schedule confidence levels - asmc numbers with wide ranges – no surprise! ... 4 build...
TRANSCRIPT
Learn. Perform. Succeed
Cost and Schedule
Confidence Levels
Roberta Tomasini
Professor of Financial Management
Defense Acquisition University
(703) 805-3764
1
2
Outline
• Sample Program – Are we OK?
• What About Uncertainty?
• Create a Program Model
• Simulate the Range of Outcomes
• Sensitivity/Risk Drivers “Tornado Chart”
• Show Estimates as Ranges
• Risk and Opportunity
• Releasable Management Reserve
• Schedule Analysis
• Final Thoughts
3
OK?
Sample Program – Are we O.K.?
APB Objective/Threshold = $130M/$143M Budget = $141.20M
We can’t tell
Cost Estimate Example
Integration
Design $6.00
Fabricate subsystem prototypes $1.00
Subsystem Prototype testing $0.70
Demonstration
System Prototype Build $7.00
Reliability Growth Test/Redesign $0.80
System Developmental Testing $2.00
Operational Test $1.20
Producton/Fielding
Produce Systems $111.00
Initial Spares $10.00
Fielding/NETT $1.50
Total Program Acquisition Cost $141.20
4
What About Uncertainty?
• To get a better handle on range of program outcomes…
The team sits down and looks at the uncertain elements to build in risk.
What’s the least this could cost (Best Case)?
What’s the most probable cost (Most Likely)?
What’s the most it could end up costing (Worst Case)?
$140M (Worst case) $95M(Best Case)
$111M (Most Likely)
Produce Systems
Cost Estimate Example
Integration Design $6.00 Fabricate subsystem prototypes $1.00
Subsystem Prototype testing $0.70
Demonstration System Prototype Build $7.00
Reliability Growth Test/Redesign $0.80 System Developmental Testing $2.00 Operational Test $1.20
Producton/Fielding Produce Systems $111.00
Initial Spares $10.00 Fielding/NETT $1.50
Total Program Acquisition Cost $141.20
5
Create a Program Model Risk-Adjusted
• Then plug your distributions into a risk program
@RISK EXAMPLE
Point Estimate* Best Case Most Likely Worst Case Mean Value
Case
Integration
Design $6.00 $6.00 $6.00 $6.00 $6.00
Fabricate subsystem prototypes $1.00 $0.80 $1.00 $1.20 $1.00
Subsystem Prototype testing $0.70 $0.50 $0.70 $0.90 $0.70
Demonstration
System Prototype Build $7.00 $5.60 $7.00 $10.50 $7.70
Reliability Growth Test/Redesign $0.80 $0.60 $0.80 $1.20 $0.87
System Developmental Testing $2.00 $1.60 $2.00 $2.50 $2.03
Operational Test $1.20 $0.90 $1.20 $1.60 $1.23
Producton/Fielding
Produce Systems $111.00 $95.00 $111.00 $140.00 $115.33
Initial Spares $10.00 $8.00 $10.00 $12.00 $10.00
Fielding/NETT $1.50 $1.50 $1.50 $1.50 $1.50
Total Program Acquisition Cost $141.20 $120.50 $141.20 $177.40 $146.37
*Point Estimate should be the Program Office Estimate, which should be the Most Likely Case
6
Simulate the Range of Outcomes
•In Breach: <40% chance of coming in under threshold
•Under-funded: < 35% chance of coming in under budget
• Now we have a picture of our cost uncertainty
• Then run a Monte Carlo simulation
APB Threshold $143M
APB Objective $130M
Budget $141.2M
7
Sensitivity/Risk Drivers “Tornado Chart”
Correlations for Total Program Cost /Expected Value/F17
Correlation Coefficients
Operational Test / Expecte.../F10-.007
Fabricate subsyetem Protot.../F3-.019
System Developmental Testi.../F9-.024
Reliability Growth Testing.../F8 .042
System Prototype Build / E.../F7 .072
Initial Spares / Expected .../F14 .082
Subsystem Prototype testin.../F4 .089
Produce Systems / Expected.../F13 .989
-1 -0.75 -0.5 -0.25 0 0.25 0.5 0.75 1
• We can also see what drives our cost uncertainty Big numbers with wide ranges – no surprise!
Does this coincide with your risk cube?
8
Show Estimates as Ranges
Dec-0
5
Jan-0
6
Feb-0
6
Mar-
06
Apr-
06
Do
lla
rs (
M)
Time
Threshold
Objective
FY
11
FY
12
FY
10
FY
13
Cur
rent
9
Risk and Opportunity
Budget
Opportunity: Uncertainty covered by budget Risk: Uncertainty not covered by budget
10
Releasable Management Reserve
(No Right Answer)
• In the above case, what’s your releasable MR if your budget is $175M?
$153M?
$146.3667M?
• Concept: Releasable MR is budget beyond your desired confidence level
11
Schedule Analysis
• Schedule Analysis must be done in a tool
• MS Project, Primavera, …. with Monte Carlo tool
• Basic schedule…start 1 Jun with finish on Sept 3rd
• 3 events with duration
• Success oriented…no failure planned
ID Task Name Duration Start
1 Project 95 d 6/1/14
2 Start 0 d 6/1/14
3 Design Unit 30 d 6/1/14
4 Build Unit 40 d 7/1/14
5 Test Unit 25 d 8/10/14
6 Finish 0 d 9/3/14
6/1
6/1 6/30
7/1 8/9
8/10 9/3
9/3
May June July August September October
12
Schedule Triangular Probability Distribution
Relative
Likelihood
of
Occurring
Low Most Likely High
Threats
Opportunities
ID Task Nam e Rept ID Min Rdur ML Rdur Max Rdur Curve
1 Project 2 0 d 0 d 0 d 0
2 Start 0 0 d 0 d 0 d 0
3 Design Unit 0 20 d 30 d 45 d 2
4 Build Unit 0 35 d 40 d 50 d 2
5 Test Unit 0 20 d 25 d 50 d 2
6 Finish 0 0 d 0 d 0 d 0
13
Schedule Monte Carlo provides range
• 3 Sept less than 15% likely …
Date: 8/12/2013 3:42:21 PM
Samples: 5000
Unique ID: 2
Name: Project
Completion Std Deviation: 8.98 d
Confidence Interval: 0.25 d
Each bar represents 3 d
Completion Date
Fre
qu
en
cy
Cum
ula
tive
Pro
ba
bili
ty
9/13/14 8/20/14 10/15/14
0.1
0.2
0.3
0.4
0.5
0.6
0.7
0.8
0.9
0.02
0.04
0.06
0.08
0.10
0.12
Completion Probability Table
Prob Prob Date Date
0.05 8/31/14
0.10 9/2/14
0.15 9/4/14
0.20 9/5/14
0.25 9/7/14
0.30 9/8/14
0.35 9/10/14
0.40 9/11/14
0.45 9/12/14
0.50 9/13/14
0.55 9/14/14
0.60 9/15/14
0.65 9/17/14
0.70 9/18/14
0.75 9/20/14
0.80 9/21/14
0.85 9/23/14
0.90 9/26/14
0.95 9/29/14
1.00 10/15/14
Nominal 9/3 Finish Date
14
Final Thoughts
• QRA can lead to a better understanding of your program
• It won’t tell you for sure… what your program will cost
or how long it will take
• It will tell you… what your team really thinks your program will cost
how long your team really thinks it will take
what your team really thinks your probability of success is
potential risk/cost drivers
confidence level of your program now
confidence level after budget cuts
confidence level adjusted for risks and opportunities
• The power is in the team – not the tool
Additional DAU on-line resources:
CLB024 Cost Risk Analysis Introduction
CLM017 Risk Management
https://learn.dau.mil/html/clc/Clc1.jsp?cl=