Copyright © 2014 by McGraw-Hill Education (Asia). All rights reserved.
1717
Project Management
![Page 2: Copyright © 2014 by McGraw-Hill Education (Asia). All rights reserved. 17 Project Management](https://reader036.vdocuments.us/reader036/viewer/2022070413/5697bfc21a28abf838ca49fb/html5/thumbnails/2.jpg)
17-2
Learning ObjectivesLearning Objectives
Discuss the behavioral aspects of projects in terms of project personnel and the project manager.
Discuss the nature and importance of a work breakdown structure in project management.
Give a general description of PERT/CPM techniques.
Construct simple network diagrams.
![Page 3: Copyright © 2014 by McGraw-Hill Education (Asia). All rights reserved. 17 Project Management](https://reader036.vdocuments.us/reader036/viewer/2022070413/5697bfc21a28abf838ca49fb/html5/thumbnails/3.jpg)
17-3
Learning ObjectivesLearning Objectives
List the kinds of information that a PERT or CPM analysis can provide.
Analyze networks with deterministic times. Analyze networks with probabilistic times. Describe activity “crashing” and solve
typical problems.
![Page 4: Copyright © 2014 by McGraw-Hill Education (Asia). All rights reserved. 17 Project Management](https://reader036.vdocuments.us/reader036/viewer/2022070413/5697bfc21a28abf838ca49fb/html5/thumbnails/4.jpg)
17-4
Unique, one-time operations designed to Unique, one-time operations designed to accomplish a specific set of objectives in a accomplish a specific set of objectives in a limited time frame.limited time frame.
Build A
A Done
Build B
B Done
Build C
C Done
Build D
Ship
JAN FEB MAR APR MAY JUN
On time!
ProjectsProjects
![Page 5: Copyright © 2014 by McGraw-Hill Education (Asia). All rights reserved. 17 Project Management](https://reader036.vdocuments.us/reader036/viewer/2022070413/5697bfc21a28abf838ca49fb/html5/thumbnails/5.jpg)
17-5
Examples:Olympics GamesMoviesConstructing shopping complexMerging 2 companiesPutting on a playPolitical campaignNew productsAdvertising campaignsSoftware development…
ProjectsProjects
![Page 6: Copyright © 2014 by McGraw-Hill Education (Asia). All rights reserved. 17 Project Management](https://reader036.vdocuments.us/reader036/viewer/2022070413/5697bfc21a28abf838ca49fb/html5/thumbnails/6.jpg)
17-6
Project ManagementProject Management
How is it different? Limited time frame Narrow focus, specific objectives Less bureaucratic
Why is it used? Special needs Pressures for new or improved products
or services
![Page 7: Copyright © 2014 by McGraw-Hill Education (Asia). All rights reserved. 17 Project Management](https://reader036.vdocuments.us/reader036/viewer/2022070413/5697bfc21a28abf838ca49fb/html5/thumbnails/7.jpg)
17-7
Project ManagementProject Management
What are the Key Metrics Time Cost Performance objectives
What are the Key Success Factors? Top-down commitment Having a capable project manager Having time to plan Careful tracking and control Good communications
![Page 8: Copyright © 2014 by McGraw-Hill Education (Asia). All rights reserved. 17 Project Management](https://reader036.vdocuments.us/reader036/viewer/2022070413/5697bfc21a28abf838ca49fb/html5/thumbnails/8.jpg)
17-8
Project ManagementProject Management
What are the Major Administrative Issues? Executive responsibilities
Project selection Project manager selection Organizational structure
Organizational alternatives Manage within functional unit Assign a coordinator Use a matrix organization with a project leader
![Page 9: Copyright © 2014 by McGraw-Hill Education (Asia). All rights reserved. 17 Project Management](https://reader036.vdocuments.us/reader036/viewer/2022070413/5697bfc21a28abf838ca49fb/html5/thumbnails/9.jpg)
17-9
Project ManagementProject Management
What are the tools? Work breakdown structure Network diagram Gantt charts Risk management
![Page 10: Copyright © 2014 by McGraw-Hill Education (Asia). All rights reserved. 17 Project Management](https://reader036.vdocuments.us/reader036/viewer/2022070413/5697bfc21a28abf838ca49fb/html5/thumbnails/10.jpg)
17-10
Deciding which projects to implement
Selecting a project manager
Selecting a project team
Planning and designing the project
Managing and controlling project resources
Deciding if and when a project should be terminated
Key DecisionsKey Decisions
![Page 11: Copyright © 2014 by McGraw-Hill Education (Asia). All rights reserved. 17 Project Management](https://reader036.vdocuments.us/reader036/viewer/2022070413/5697bfc21a28abf838ca49fb/html5/thumbnails/11.jpg)
17-11
Project ManagerProject Manager
Responsible for:
Work QualityHuman Resources TimeCommunications Costs
![Page 12: Copyright © 2014 by McGraw-Hill Education (Asia). All rights reserved. 17 Project Management](https://reader036.vdocuments.us/reader036/viewer/2022070413/5697bfc21a28abf838ca49fb/html5/thumbnails/12.jpg)
17-12
Temptation to understate costs
Withhold information
Misleading status reports
Falsifying records
Compromising workers’ safety
Approving substandard work
Ethical IssuesEthical Issues
![Page 13: Copyright © 2014 by McGraw-Hill Education (Asia). All rights reserved. 17 Project Management](https://reader036.vdocuments.us/reader036/viewer/2022070413/5697bfc21a28abf838ca49fb/html5/thumbnails/13.jpg)
17-13
Project Life CycleProject Life Cycle
Concept
DefinitionDefinition
PlanningPlanning
ExecutionExecution
TerminationTermination
Man
agem
ent
![Page 14: Copyright © 2014 by McGraw-Hill Education (Asia). All rights reserved. 17 Project Management](https://reader036.vdocuments.us/reader036/viewer/2022070413/5697bfc21a28abf838ca49fb/html5/thumbnails/14.jpg)
Work Breakdown Structure
Project XProject X
Level 1
Level 2
Level 3
Level 4
Figure 17.2
![Page 15: Copyright © 2014 by McGraw-Hill Education (Asia). All rights reserved. 17 Project Management](https://reader036.vdocuments.us/reader036/viewer/2022070413/5697bfc21a28abf838ca49fb/html5/thumbnails/15.jpg)
17-15
Planning and SchedulingPlanning and Scheduling
MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
Locate new facilities
Interview staff
Hire and train staff
Select and order furniture
Remodel and install phones
Move in/startup
Gantt Chart
Figure 17.3
![Page 16: Copyright © 2014 by McGraw-Hill Education (Asia). All rights reserved. 17 Project Management](https://reader036.vdocuments.us/reader036/viewer/2022070413/5697bfc21a28abf838ca49fb/html5/thumbnails/16.jpg)
17-16
PERT and CPMPERT and CPM
PERT: Program Evaluation and Review Technique
CPM: Critical Path Method
Graphically displays project activities Estimates how long the project will take Indicates most critical activities Shows where delays will not affect project
![Page 17: Copyright © 2014 by McGraw-Hill Education (Asia). All rights reserved. 17 Project Management](https://reader036.vdocuments.us/reader036/viewer/2022070413/5697bfc21a28abf838ca49fb/html5/thumbnails/17.jpg)
17-17
The Network DiagramThe Network Diagram
Network (precedence) diagram: diagram of project activities that shows sequential relationships by the use of arrows and nodes.
Activity-on-arrow (AOA): a network diagram convention in which arrows designate activities.
Activity-on-node (AON): a network diagram convention in which nodes designate activities.
Activities: steps in the project that consume resources and/or time.
Events: the starting and finishing of activities, designated by nodes in the AOA convention.
![Page 18: Copyright © 2014 by McGraw-Hill Education (Asia). All rights reserved. 17 Project Management](https://reader036.vdocuments.us/reader036/viewer/2022070413/5697bfc21a28abf838ca49fb/html5/thumbnails/18.jpg)
17-18
The Network DiagramThe Network Diagram
Path Sequence of activities that leads from the starting
node to the finishing node Critical path
The longest path; determines expected project duration
Critical activities Activities on the critical path
Slack Allowable slippage for path; the difference
between the length of path and the length of critical path
![Page 19: Copyright © 2014 by McGraw-Hill Education (Asia). All rights reserved. 17 Project Management](https://reader036.vdocuments.us/reader036/viewer/2022070413/5697bfc21a28abf838ca49fb/html5/thumbnails/19.jpg)
17-19
Project Network: Activity on ArrowProject Network: Activity on Arrow
1
2
3
4
5 6
Locatefacilities
Orderfurniture
Furnituresetup
InterviewHire andtrain
Remodel
Move in
Figure 17.4
AOA
![Page 20: Copyright © 2014 by McGraw-Hill Education (Asia). All rights reserved. 17 Project Management](https://reader036.vdocuments.us/reader036/viewer/2022070413/5697bfc21a28abf838ca49fb/html5/thumbnails/20.jpg)
17-20
Project Network: Activity on NodeProject Network: Activity on Node
Move in
Figure 17.4
1
2
3
5
6
Locatefacilities
Orderfurniture
Furnituresetup
Interview
Remodel
4
Hire andtrain
7S
AON
![Page 21: Copyright © 2014 by McGraw-Hill Education (Asia). All rights reserved. 17 Project Management](https://reader036.vdocuments.us/reader036/viewer/2022070413/5697bfc21a28abf838ca49fb/html5/thumbnails/21.jpg)
17-21
Network ConventionsNetwork Conventions
a
b
c ab
c
a
b
c
d
a
b
c
Dummyactivity
![Page 22: Copyright © 2014 by McGraw-Hill Education (Asia). All rights reserved. 17 Project Management](https://reader036.vdocuments.us/reader036/viewer/2022070413/5697bfc21a28abf838ca49fb/html5/thumbnails/22.jpg)
17-22
Time EstimatesTime Estimates
Deterministic
Time estimates that are fairly certain
Probabilistic
Estimates of times that allow for variation
![Page 23: Copyright © 2014 by McGraw-Hill Education (Asia). All rights reserved. 17 Project Management](https://reader036.vdocuments.us/reader036/viewer/2022070413/5697bfc21a28abf838ca49fb/html5/thumbnails/23.jpg)
17-23
Example 1Example 1
1
2
3
4
5 6
8 weeks
6 weeks
3 weeks
4 weeks9 weeks
11 weeks
1 week
Locate
facilities
Order
furniture Fu
rnitu
re
setup
InterviewHire
and train
RemodelMove in
DeterministicDeterministictime estimatestime estimates
Figure 17.5
![Page 24: Copyright © 2014 by McGraw-Hill Education (Asia). All rights reserved. 17 Project Management](https://reader036.vdocuments.us/reader036/viewer/2022070413/5697bfc21a28abf838ca49fb/html5/thumbnails/24.jpg)
17-24
Example 1 SolutionExample 1 Solution
P a t h L e n g t h( w e e k s )
S l a c k
1 - 2 - 3 - 4 - 5 - 61 - 2 - 5 - 61 - 3 - 5 - 6
1 82 01 4
206
Critical PathCritical Path
![Page 25: Copyright © 2014 by McGraw-Hill Education (Asia). All rights reserved. 17 Project Management](https://reader036.vdocuments.us/reader036/viewer/2022070413/5697bfc21a28abf838ca49fb/html5/thumbnails/25.jpg)
17-25
Network activities ES: early start EF: early finish LS: late start LF: late finish
Used to determine Expected project duration Slack time Critical path
Computing AlgorithmComputing Algorithm
![Page 26: Copyright © 2014 by McGraw-Hill Education (Asia). All rights reserved. 17 Project Management](https://reader036.vdocuments.us/reader036/viewer/2022070413/5697bfc21a28abf838ca49fb/html5/thumbnails/26.jpg)
17-26
Probabilistic Time EstimatesProbabilistic Time Estimates
Optimistic time Time required under optimal conditions
Pessimistic time Time required under worst conditions
Most likely time Most probable length of time that will be
required
![Page 27: Copyright © 2014 by McGraw-Hill Education (Asia). All rights reserved. 17 Project Management](https://reader036.vdocuments.us/reader036/viewer/2022070413/5697bfc21a28abf838ca49fb/html5/thumbnails/27.jpg)
17-27
Probabilistic EstimatesProbabilistic Estimates
Activitystart
Optimistictime
Most likelytime (mode)
Pessimistictime
to tptm te
Figure 17.8
Beta Distribution
![Page 28: Copyright © 2014 by McGraw-Hill Education (Asia). All rights reserved. 17 Project Management](https://reader036.vdocuments.us/reader036/viewer/2022070413/5697bfc21a28abf838ca49fb/html5/thumbnails/28.jpg)
17-28
Expected TimeExpected Time
te = to + 4tm +tp
6
te = expected timeto = optimistic timetm = most likely timetp = pessimistic time
![Page 29: Copyright © 2014 by McGraw-Hill Education (Asia). All rights reserved. 17 Project Management](https://reader036.vdocuments.us/reader036/viewer/2022070413/5697bfc21a28abf838ca49fb/html5/thumbnails/29.jpg)
17-29
VarianceVariance
(tp – to)2
36
= varianceto = optimistic timetp = pessimistic time
![Page 30: Copyright © 2014 by McGraw-Hill Education (Asia). All rights reserved. 17 Project Management](https://reader036.vdocuments.us/reader036/viewer/2022070413/5697bfc21a28abf838ca49fb/html5/thumbnails/30.jpg)
17-30
Example 5Example 5
1-3-4a
3-4-5d
3-5-7e
5-7-9f
2-4-6b
4-6-8h
2-3-6g 3-4-6
i
2-3-5c
Optimistictime
Most likelytime
Pessimistictime
![Page 31: Copyright © 2014 by McGraw-Hill Education (Asia). All rights reserved. 17 Project Management](https://reader036.vdocuments.us/reader036/viewer/2022070413/5697bfc21a28abf838ca49fb/html5/thumbnails/31.jpg)
17-31
Example 5: Time EstimatesExample 5: Time Estimates
2.83a
4.00d
5.0e
7.0f
4.00b
6.0h
3.33g 4.17
i
3.17c
Tabc = 10.0Tdef = 16.0Tghi = 13.50
![Page 32: Copyright © 2014 by McGraw-Hill Education (Asia). All rights reserved. 17 Project Management](https://reader036.vdocuments.us/reader036/viewer/2022070413/5697bfc21a28abf838ca49fb/html5/thumbnails/32.jpg)
17-32
Path ProbabilitiesPath Probabilities
Z = Specified time – Path meanPath standard deviation
Z indicates how many standard deviationsof the path distribution the specified timeis beyond the expected path duration.
![Page 33: Copyright © 2014 by McGraw-Hill Education (Asia). All rights reserved. 17 Project Management](https://reader036.vdocuments.us/reader036/viewer/2022070413/5697bfc21a28abf838ca49fb/html5/thumbnails/33.jpg)
17-33
17Weeks
Weeks
Weeks
Weeks
10.0
16.0
13.5
1.00
1.00
a-b-c
d-e-f
g-h-i
Example 6Example 6
![Page 34: Copyright © 2014 by McGraw-Hill Education (Asia). All rights reserved. 17 Project Management](https://reader036.vdocuments.us/reader036/viewer/2022070413/5697bfc21a28abf838ca49fb/html5/thumbnails/34.jpg)
17-34
Time-Cost Trade-Offs: CrashingTime-Cost Trade-Offs: Crashing
Crash: shortening activity duration
Procedure for crashing Crash the project one period at a time
Only an activity on the critical path
Crash the least expensive activity
Multiple critical paths: find the sum of crashing the least expensive activity on each critical path
![Page 35: Copyright © 2014 by McGraw-Hill Education (Asia). All rights reserved. 17 Project Management](https://reader036.vdocuments.us/reader036/viewer/2022070413/5697bfc21a28abf838ca49fb/html5/thumbnails/35.jpg)
17-35
Time-Cost Trade-Offs: CrashingTime-Cost Trade-Offs: Crashing
TotalcostTotalcost
ShortenShorten
ShortenShorten
Cumulativecost of crashing
Cumulativecost of crashing
Expected indirect costsExpected indirect costs
Optimum
CRASHCRASH
Figure 17.11
![Page 36: Copyright © 2014 by McGraw-Hill Education (Asia). All rights reserved. 17 Project Management](https://reader036.vdocuments.us/reader036/viewer/2022070413/5697bfc21a28abf838ca49fb/html5/thumbnails/36.jpg)
17-36
6a
4d
5c
10b
9 e
2f
Example 7Example 7
![Page 37: Copyright © 2014 by McGraw-Hill Education (Asia). All rights reserved. 17 Project Management](https://reader036.vdocuments.us/reader036/viewer/2022070413/5697bfc21a28abf838ca49fb/html5/thumbnails/37.jpg)
17-37
Advantages of PERTAdvantages of PERT
Forces managers to organize
Provides graphic display of activities
Identifies Critical activities
Slack activities1
2
3
4
5 6
![Page 38: Copyright © 2014 by McGraw-Hill Education (Asia). All rights reserved. 17 Project Management](https://reader036.vdocuments.us/reader036/viewer/2022070413/5697bfc21a28abf838ca49fb/html5/thumbnails/38.jpg)
17-38
Limitations of PERTLimitations of PERT
Important activities may be omitted
Precedence relationships may not be correct
Estimates may include a fudge factor
May focus solelyon critical path
1
2
3
4
5 6
142 weeks
![Page 39: Copyright © 2014 by McGraw-Hill Education (Asia). All rights reserved. 17 Project Management](https://reader036.vdocuments.us/reader036/viewer/2022070413/5697bfc21a28abf838ca49fb/html5/thumbnails/39.jpg)
17-39
Goldratt’s Critical ChainGoldratt’s Critical Chain
Goldratt’s insight on project management Time estimates are often pessimistic Activities finished ahead of schedule often go
unreported With multiple projects, resources needed for one
project may be in use for another
![Page 40: Copyright © 2014 by McGraw-Hill Education (Asia). All rights reserved. 17 Project Management](https://reader036.vdocuments.us/reader036/viewer/2022070413/5697bfc21a28abf838ca49fb/html5/thumbnails/40.jpg)
17-40
Computer aided design (CAD) Groupware (Lotus Notes) CA Super Project Harvard Total Manager MS Project Sure Track Project Manager Time Line
Project Management SoftwareProject Management Software
![Page 41: Copyright © 2014 by McGraw-Hill Education (Asia). All rights reserved. 17 Project Management](https://reader036.vdocuments.us/reader036/viewer/2022070413/5697bfc21a28abf838ca49fb/html5/thumbnails/41.jpg)
17-41
Imposes a methodology
Provides logical planning structure
Enhances team communication
Flags constraint violations
Automatic report formats
Multiple levels of reports
Enables what-if scenarios
Generates various chart types
Advantages of PM SoftwareAdvantages of PM Software
![Page 42: Copyright © 2014 by McGraw-Hill Education (Asia). All rights reserved. 17 Project Management](https://reader036.vdocuments.us/reader036/viewer/2022070413/5697bfc21a28abf838ca49fb/html5/thumbnails/42.jpg)
17-42
Risk: occurrence of events that have undesirable consequences Delays
Increased costs
Inability to meet specifications
Project termination
Project Risk ManagementProject Risk Management
![Page 43: Copyright © 2014 by McGraw-Hill Education (Asia). All rights reserved. 17 Project Management](https://reader036.vdocuments.us/reader036/viewer/2022070413/5697bfc21a28abf838ca49fb/html5/thumbnails/43.jpg)
17-43
Identify potential risks
Analyze and assess risks
Work to minimize occurrence of risk
Establish contingency plans
Risk ManagementRisk Management
![Page 44: Copyright © 2014 by McGraw-Hill Education (Asia). All rights reserved. 17 Project Management](https://reader036.vdocuments.us/reader036/viewer/2022070413/5697bfc21a28abf838ca49fb/html5/thumbnails/44.jpg)
17-44
SummarySummary
Projects are a unique set of activities
Projects go through life cycles
PERT and CPM are two common techniques
Network diagrams
Project management software available