  • 8/13/2019 Copy of Surulipatty Road

    1/52

    Estimate Amount 3740000 LAKHS

    Package No :

    District : THENI

    EXISTING FEATURES OF THE ROAD:

    NECESSITY OF THE ROAD:

    PAVEMENT DESIGN:

    GSB "C"WBM II

    Layer

    WBM III

    Layer

    Gravel WBM

    Km : 0 / 0 - 3/7 250 100 75 75 0 0 75 75

    PROPOSAL AND PROVISIONS MADE IN THE ESTIMATE:

    CONSTRUCTION OF EMBANKMENT:

    The road passing through wet lands has earthen surface with varies formation width from 6-8

    metres, which is Sufficient for upgrading the road. Therefore, L.A. Proposal is not initiated. There are lot of

    light Jungles on both sides of the road which are proposed for Clearance. There are existing CD work in this

    road proposed for Re Construction.

    Improvement of road from Cumbum To Surulipatty Road Km 0/8-3/6

    The road for Consideration to the Malaiyandipuram would rejuvenate activation of the people to

    ascend their present status and up gradation of the road with rural road connectivity promotes access to

    economic and social Services and thus generating agricultural incomes by transporting their agricultural

    products to the nearest town Reddiyarchathram. The road Connectivity would assure to ensure that its

    benefits accrue to the people of the villages. This road connects main road to go to schools, colleges,

    marketing Places and near by hospitals.

    PAVEMENT DESIGN has been done by computing traffic census on Average of 3 days and CBR

    value of the site soil.

    Soil samples are collected from the road and, tests are conducted. The results are tabulated below:

    KM Type of soilCBR

    Value

    Pavement

    thick

    required

    (in mm)

    Existing crust

    thickness (in mm)

    Balance

    thickness

    required

    (in mm)

    Total

    Thickness

    proposed

    It is proposed to upgrade the road to O.D.R. standards to a formation width of 7.50 m and

    Carriageway width of 3.75 m with formation slopes 2: 1 and slope in cutting 1: 1

    The formation level is already kept above the adjacent ground level . Embankment is formed by

    using the cut earth available on the road. Cut earth available @ road side would be used @ the same

    section and balance earth can be conveyed and used to other locations. Embankment earth work is

    thoroughly compacted to achieve 97% of dry density. Formation of earth work shall be carried out as per

    MORD CL: 301.

    Existing Crust is taken into account for Pavement design.

    Proposed Pavement Thickness

    (in mm)

    NABARD SCHEME 2010 - 2011

    (Ministry of Rural Development, Govt. of India)

    Block : K . MYLADUM PARAI

  • 8/13/2019 Copy of Surulipatty Road

    2/52

    WBM GRADE II:

    WBM GRADE III:

    TACK COAT RS-1:

    PREMIX CARPET:

    GEOMETRIC:

    The grade of WBM-III layer over the grade II, consisting of grade of aggregates 53mm 22.4mm is

    proposed and compacted. WBM layer shall not be less than 75mm keeping the width of 3.75 m and work

    shall be as par MORD-Technical specification clause 405.

    Tack coat over the primed surface should be applied with bitumen emulsion-RS-1 @ the rate of 0.25

    to 0.30 kg per sqm as par MORD-Technical specification clause 503.

    WBM grade II consisting of grade of aggregates 63mm 45mm is proposed as a bottom layer over

    the sub base to a consolidated thickness of 7.5cm and width of 3.75 m. The work shall be carried out as per

    MORD-Technical specification clause 405.

    This work consists of preparation, laying and compaction of an open graded premix surfacing of 20

    mm thickness with bitumen S-65 i.e. 60/70 grade @ the rate of 1.46kg per one sqm and a seal coat-type-A

    to be applied to the surface immediatel

    The road runs in Plain terrain having dry/wet lands. The road becomes inconvenience to the public

    during Rainy seasons. The ruling gradient 1 in 30 in plain terrain is adopted as far as Possible.

  • 8/13/2019 Copy of Surulipatty Road

    3/52

    1) Terrain Classification : Plain / Rolling Terrain

    2) Design Speed : 50 km/h

    3) Land width :

    4) Roadway width : 6 m available for entire stretch

    5) : 7.5 m (Outer to outer)

    6) Carriage width : Available 3.75 m.

    7) Camber for bituminous : Camber for B.T. surface = 3%

    8) Annual rain fall : > 1000 mm

    9) ADT in the year of Traffic Coun : 161

    Base Year Traffic AADT (T) = : 200

    Traffic Category : T4

    10) Road Length : 3600 m

    HORIZONTAL CURVES:

    VERTICAL CURVES:

    Minimum required land remains width 9m but in some

    places it is found less, due to encroachments by adjacent

    land owners

    Road way width for CD Stru

    There are Horizontal curves which are maintained as it is and necessary provisions are made for

    extra width at curves.

    Since the road is proposed to up grade to O.D.RS Standard, for safety and comport all grade

    changes exceeding 1.0 percent i.e. 0.01 are introduced in the alignment. Vertical curves are designed to the

    requirements @ needed locations and exis

    General : 6 m roadway width with a single lane of 3.75 m is proposed. Ruling gradient of one in 30 isproposed with a camber of 3.0%

  • 8/13/2019 Copy of Surulipatty Road

    4/52

    CROSS DRAINAGE WORKS:

    900

    1660

    2900

    ROAD PROTECTIVE WORKS:

    Km SideLength

    (m)

    Height(m)

    1 R 200.00 1.20

    LUMP SUM PROVISIONS:

    The road width available on the culverts is maintained with formation width of 7.5 m

    There are no Existing culverts and 8 New culverts which are proposed for construction of Cross Drainage

    purpose in this road at the location tabulated below.

    Ch. (m)

    EXISTING CD DETAILS PROPOSED CD DETAILS

    Type Condition

    Single span of 1 m RCC slab culvert Good

    Type

    Good

    40 m Causeway Good

    Provision for Name board, Sign board, KM Stone, HM Stone and guide stones and Information board.

    Protective works were proposed wherever necessary in this road as tabulated below.

    Km : 3/2-3/4

    Rate : The rate analysis for all items of the road works incorporated in the estimate have been

    prepared in accordance with Standard data book for rate analysis for rural roads released by M.O.R.D and

    unit rates are prepared based on State PWD and Highways Schedule of rates for the year 2009 -2010

    Single span of 1 m RCC slab culvert

    Lump sum provisions are made for the following items of works

    Preparation for DPR Preperation Charges

    Provision for Labour Welfare fund @ 0.3%

    Provision for Contingencies.

  • 8/13/2019 Copy of Surulipatty Road

    5/52

    1 Name of work :Improvement of road from Cumbum

    To Surulipatty Road Km 0/8-3/6

    2Name of scheme under which work is

    taken up: NABARD ROAD

    Classification of road Rural roads

    Whether administrative sanction of

    Govt. obtained

    a. G.O MS No./Collector No. :

    b. Length : 2800

    c. Amount of sanction :

    4Whether nomenclature length

    amount is as per G.O : Yes

    5 Change in scope of sanction : No

    6 Amount of estimate now prepared :

    7

    Whether the estimate amount is

    within allowable limits of power of

    sanction of competent authority

    : Yes

    8Revised administrative sanction if

    any: No

    9

    Whether the following details are

    enclosed, site plan, index map,

    alignment of road

    : Yes

    10

    Whether L.S and C.S workingdrawing data with quarry chart ,

    quarry map, counter signed by

    concerned Engineer, detailed

    estimate, abstract estimate,

    specification report etc. are enclosed

    : Yes

    1Whether alternative alignment are

    studied: Existing Alignment has been followed

    2

    If so whether details of each

    alignment their merits and demerits

    are given in the estimate and only

    the best is selected

    : --

    3Is the alignment approved by

    Competent Authority: Yes

    II. ALIGNMENT

    CHECKLIST FOR ROAD WORKS FOR SCRUTINY AND SANCTION OF ESTIMATES

    I. GENERAL

    3

    :

    :

  • 8/13/2019 Copy of Surulipatty Road

    6/52

    4

    Whether the reference of the bench

    mark which has been used for

    carrying out survey is mentioned

    whether permanent benchmark is

    also indicated

    : TBM

    5Whether Geological conditions have

    been studied: Yes

    6 What are the gradients adopted : Ruling Gradients

    III. PAVEMENT

    a. To what standards the road is

    formed or improved ODR/VR: O.D.R Standards

    b. What is the traffic intensity that is

    considered CBR curveC Curve

    2

    Whether pavement is scientifically

    designed based on soaked CBR value

    of sub-grade and sub-base materials

    : Yes

    IV. ALIGNMENT

    1

    Whether L.S and C.S are taken at

    specified intervals and quantity

    worked out

    : Yes

    2

    Are the standards adopted in all

    aspects like width, side slope and

    right of way?

    :

    3

    Is the lead earth suitable for

    foundation? Whether provision is

    made for conveying good earth for

    forming the approach if necessary.

    : No

    4

    approved with reference to

    availability and suitability? Whether

    provision is made for extra lead and

    : Not Applicable

    5 Whether horizontal alignment isdesigned with suitable horizontal

    and vertical curves

    : Yes

    6

    Whether the road level has been

    fixed corresponding to the bridge

    estimate if any to the project and the

    reference bench mark.

    : Yes

    1

  • 8/13/2019 Copy of Surulipatty Road

    7/52

    7

    Whether soaked CBR value of the

    sub grade is found out and pavement

    is suitably designed?

    : Yes

    8Whether suitable sub base of

    minimum CBR 15% is provided.: Yes

    9

    Whether the WBM is for compacted

    thickness? If so is 33.33% extracollection provided for.

    : Yes

    10

    Is adequate provision for L.A made,

    whether land acquisition found and

    schedule are available?

    : Does not Arise

    11Whether Suitable wearing coat is

    proposed.: Yes

    1 Whether current year rates adopted : 2010-2011

    2

    Whether the foundation earthwork

    rates including for loading charges

    and obtaining labour, materials etc.

    completed.

    : Yes

    3

    Whether any provisions is made for a

    rate for removal of sand upto sill

    level without baling?

    : Does not Arise

    4

    Whether concrete rate is including

    side formwork, baling out water etc.,

    complete and vibration charges.

    : Yes

    5

    e er orma on ra e s nc us ve

    of compaction allowances and

    watering complete if so it bases on

    : Yes

    6

    Whether the rates for items and

    checked with reference to Standard

    Data Book and the provision is

    adequate.

    : Yes

    1

    Whether the estimate is provided

    with adequate provision for the

    following items?

    2Provision of Land Acquisition to be

    paid if any?Does not Arise

    V. RATES

    VI. OTHER ITEMS

  • 8/13/2019 Copy of Surulipatty Road

    8/52

    3 Provision for Cross Drainage Works No

    4

    Provision for Name Board, Guide

    Stone, Km stones, Improvements to

    Geometrics and Approach etc.,

    Yes

    5Provision for Quality Control and

    Testing

    Does not Arise

    6Provision for Store shed, Watchman

    pay and Inspection shed etc.,Does not Arise

    7Provision for Establishment and

    contingenciesDoes not Arise

    8 Provision for Diversion if any Does not Arise

    9Provision for Variation in Cost of

    MaterialsDoes not Arise

    10Any Special provision on that

    particular type if required.Not Necessary

    1

    Certified that the particulars

    furnished above are based on siteinspection and are correct.

    Yes

    2

    Certified that the provisions made

    under L.S are adequate and donot

    warrant revision

    Yes

    1 Estimate Amount 3740000

    2Monetary limit for the sanctioning

    authority

    3 Sanction Number and date

    VII. WHETHER THE FOLLOWING CERTIFICATES FURNISHED.

    TECHNICAL SANCTION

  • 8/13/2019 Copy of Surulipatty Road

    9/52

    SPECIFICATION REPORT TO ACCOMPANY THE ESTIMATE FOR THE WORK OF

    ESTIMATE AMOUN 3740000

    Name of District : THENI

    Name of Union : CUMBUM

    Existing Condition : Worn out WBM

    Scheme : NABARD

    Administrative Sanction No :

    Necessity : The existing surface of the road is Earthern road.

    There are many wheeltrack and undulations in this road hence it isvery inconveniet for public. It is necessary to

    improvements this road for the use of public toa length of 3.7 KM.

    Provisions : 1) Clearing the Scrub jungles.

    2)

    3)

    4)

    5) Difference in cost of Bitumen etc.,

    6)

    Provisions : 1) Pcc 1 : 3 : 6

    2) Pcc 1 : 2 : 4 for pier and abutment

    3) Mix 1 : 11/2 : 3 for Rcc work

    4) Steel Fe 415 N/mm2

    5) Cover bot and Sides 40mm

    6) Us Gravel for Back filling work

    7) Difference in cost of Materials etc.,

    Improvement of road from Cumbum To Surulipatty Road Km 0/8-3/6

    Applying tack coat over WBM surface using

    Providing Premix carpet with seal coat tupe 'A'

    Collection and laying U.S.Gravel on side berms

    Provisions for HM stone and KM stone etc.

  • 8/13/2019 Copy of Surulipatty Road

    10/52

    8)

    This estimate has been prepared, adopted current schedule of rates for the

    year on 2010-2011. On sanction this work will be carried out as per sanctionedestimate and higher authorities instructions.,

    Provisions for Weep hole pipes and Filter

  • 8/13/2019 Copy of Surulipatty Road

    11/52

    Reach Name

    of

    Kind of metal Lead in

    KM

    Cost of material Conveyan

    ce

    Stacking

    charges

    Storagg

    e

    Total

    Cement 1 4350.00 3.50 - 4353.50

    Steel upto

    16mm dia1 37750.00 3.50 - 37753.50

    Steel above

    u to 16 mm1 37750.00 3.50 - - 37753.50

    and for morta 43 110.00 194.90 0.00 304.90

    Sand for fillin 43 110.00 194.90 0.00 304.90

    40 mm ISS 7 560.00 39.20 0.00 599.20

    25 mm ISS 7 480.00 39.20 0.00 519.20

    20 mm ISS 7 780.00 39.20 0.00 819.20

    12 mm ISS 7 720.00 39.20 3.15 762.35

    6 mm ISS 7 360.00 39.20 3.15 402.35

    ough Stone[M 7 262.00 39.20 0.00 301.20

    ough Stone[R 7 228.00 39.20 0.00 267.20

    Bond Stone 7 360.00 39.20 0.00 399.20

    90mm IRC 7 243.00 39.20 3.15 285.35

    75mm IRC 7 272.00 39.20 3.15 314.35

    63mm IRC 7 350.00 39.20 3.15 392.35

    53mm IRC 7 425.00 39.20 3.15 467.35

    46.50mm IRC 7 571.00 39.20 3.15 613.35

    45mm IRC 7 571.00 39.20 3.15 613.35

    LEAD STATEMENT

    KM- 0/0 - 1/0

    Improvement of road from Cumbum To Surulipatty Road Km 0/8-3/6

    DISTRICT : THENI BLOCK :

  • 8/13/2019 Copy of Surulipatty Road

    12/52

    37.50mm IRC 7 583.00 39.20 3.15 625.35

    26.50mm IRC 7 550.00 39.20 3.15 592.35

    25mm IRC 7 550.00 39.20 3.15 592.35

    22.4mm IRC 7 800.00 39.20 3.15 842.35

    13.2 mm IRC 7 739.00 39.20 3.15 781.35

    11.2 mm IRC 7 503.00 39.20 3.15 545.35

    6.70 mm IRC 7 374.00 39.20 3.15 416.35

    7 374.00 39.20 3.15 416.35

    7 374.00 39.20 3.15 416.35

    7 331.00 39.20 3.15 373.35

    7 73.00 39.20 3.05 115.25umen

    1 41230.35 0.00 - 41230.35tumen

    1 35600.00 0.00 - 35600.00

    Site Gravel 6 97.00 33.60 3.05 133.65

    WBM Gr II 7 399 39.20 3.15 441.18

    WBM Gr III 7 540.3 39.20 3.15 582.65

    26.4mm IRC 7 550.00 39.20 3.15 592.35

    11.2 mm IRC 7 503.00 39.20 3.15 545.358&2.36mm IR 7 331.00 39.20 3.15 373.35

    6.70 mm IRC 7 374.00 39.20 3.15 416.35

    Quarry Dust 7 73.00 39.20 3.15 115.35

    Emulsion Tar 1 42209.00 0 - 42209.00

    Reach Name

    of

    Kind of metal Lead in

    KM

    Cost of material Conveyan

    ce

    Stacking

    charges

    Storagg

    e

    Total

    Cement 2 4350.00 7.00 - 4357.00

    KM- 1/0 - 2/0

    6.00 mm IRC

    5.60 mm IRC

    4.75 mm IRC&Below

    Quarry Dust

  • 8/13/2019 Copy of Surulipatty Road

    13/52

    Steel upto

    16mm dia2 37750.00 7.00 - 37757.00

    Steel above

    upto 16 mm2 37750.00 7.00 - 37757.00

    and for morta 44 110.00 198.20 0.00 308.20

    Sand for fillin 44 110.00 198.20 0.00 308.20

    40 mm ISS 8 560.00 44.80 0.00 604.80

    25 mm ISS 8 480.00 44.80 0.00 524.80

    20 mm ISS 8 780.00 44.80 0.00 824.80

    12 mm ISS 8 720.00 44.80 3.15 767.95

    6 mm ISS 8 360.00 44.80 3.15 407.95

    ough Stone[M 8 262.00 44.80 0.00 306.80

    ough Stone[R 8 228.00 44.80 0.00 272.80

    Bond Stone 8 360.00 44.80 0.00 404.80

    90mm IRC 8 243.00 44.80 3.15 290.95

    75mm IRC 8 272.00 44.80 3.15 319.95

    63mm IRC 8 350.00 44.80 3.15 397.95

    53mm IRC 8 425.00 44.80 3.15 472.95

    46.50mm IRC 8 571.00 44.80 3.15 618.95

    45mm IRC 8 571.00 44.80 3.15 618.95

    37.50mm IRC 8 583.00 44.80 3.15 630.95

    26.50mm IRC 8 550.00 44.80 3.15 597.95

    25mm IRC 8 550.00 44.80 3.15 597.95

    22.4mm IRC 8 800.00 44.80 3.15 847.95

    13.2 mm IRC 8 739.00 44.80 3.15 786.95

    11.2 mm IRC 8 503.00 44.80 3.15 550.95

    6.70 mm IRC 8 374.00 44.80 3.15 421.95

  • 8/13/2019 Copy of Surulipatty Road

    14/52

    8 374.00 44.80 3.15 421.95

    8 374.00 44.80 3.15 421.95

    8 331.00 44.80 3.15 378.95

    8 73.00 44.80 3.05 120.85umen

    1 41230.35 0 - 41230.35tumen

    1 35600.00 0 - 35600.00

    Site Gravel 7 97.00 39.20 3.05 139.25

    WBM Gr II 8 399 44.80 3.15 446.78

    WBM Gr III 8 540.3 44.80 3.15 588.25

    26.4mm IRC 8 550.00 44.80 3.15 597.95

    11.2 mm IRC 8 503.00 44.80 3.15 550.95

    8&2.36mm IR 8 331.00 44.80 3.15 378.95

    6.70 mm IRC 8 374.00 44.80 3.15 421.95

    Quarry Dust 8 73.00 44.80 3.15 120.95tumen

    1 36100.00 0 - 36100.00

    Reach Name

    of

    Kind of metal Lead in

    KM

    Cost of material Conveyan

    ce

    Stacking

    charges

    Storagg

    e

    Total

    Cement 3 4350.00 10.50 - 4360.50

    Steel upto

    16mm dia3 37750.00 10.50 - 37760.50

    Steel above

    u to 16 mm3 37750.00 10.50 - 37760.50

    and for morta 45 110.00 201.50 0.00 311.50

    Sand for fillin 45 110.00 201.50 0.00 311.50

    40 mm ISS 9 560.00 50.40 0.00 610.40

    25 mm ISS 9 480.00 50.40 0.00 530.40

    KM- 2/0 - 3/0

    6.00 mm IRC

    5.60 mm IRC

    4.75 mm IRC&Below

    Quarry Dust

  • 8/13/2019 Copy of Surulipatty Road

    15/52

    20 mm ISS 9 780.00 50.40 0.00 830.40

    12 mm ISS 9 720.00 50.40 3.15 773.55

    6 mm ISS 9 360.00 50.40 3.15 413.55

    ough Stone[M 9 262.00 50.40 0.00 312.40

    ough Stone[R 9 228.00 50.40 0.00 278.40

    Bond Stone 9 360.00 50.40 0.00 410.40

    90mm IRC 9 243.00 50.40 3.15 296.55

    75mm IRC 9 272.00 50.40 3.15 325.55

    63mm IRC 9 350.00 50.40 3.15 403.55

    53mm IRC 9 425.00 50.40 3.15 478.55

    46.50mm IRC 9 571.00 50.40 3.15 624.55

    45mm IRC 9 571.00 50.40 3.15 624.55

    37.50mm IRC 9 583.00 50.40 3.15 636.55

    26.50mm IRC 9 550.00 50.40 3.15 603.55

    25mm IRC 9 550.00 50.40 3.15 603.55

    22.4mm IRC 9 800.00 50.40 3.15 853.55

    13.2 mm IRC 9 739.00 50.40 3.15 792.55

    11.2 mm IRC 9 503.00 50.40 3.15 556.55

    6.70 mm IRC 9 374.00 50.40 3.15 427.55

    9 374.00 50.40 3.15 427.55

    9 374.00 50.40 3.15 427.55

    9 331.00 50.40 3.15 384.55

    9 73.00 50.40 3.05 126.45umen

    1 0.00 0 - 0.00tumen

    1 35600.00 0 - 35600.00

    Site Gravel 8 97.00 44.80 3.05 144.85

    WBM Gr II 9 399 50.40 3.15 452.38

    4.75 mm IRC&Below

    Quarry Dust

    6.00 mm IRC

    5.60 mm IRC

  • 8/13/2019 Copy of Surulipatty Road

    16/52

    WBM Gr III 9 540.3 50.40 3.15 593.85

    26.4mm IRC 9 550.00 50.40 3.15 603.55

    11.2 mm IRC 9 503.00 50.40 3.15 556.55

    8&2.36mm IR 9 331.00 50.40 3.15 384.55

    6.70 mm IRC 9 374.00 50.40 3.15 427.55

    Quarry Dust 9 73.00 50.40 3.15 126.55tumen

    1 36100.00 0 - 36100.00

    Reach Name

    of

    Kind of metal Lead in

    KM

    Cost of material Conveyan

    ce

    Stacking

    charges

    Storagg

    e

    Total

    Cement 4 4350.00 14.00 - 4364.00

    Steel upto

    16mm dia4 37750.00 14.00 - 37764.00

    Steel above

    upto 16 mm4 37750.00 14.00 - 37764.00

    and for morta 46 110.00 204.80 0.00 314.80

    Sand for fillin 46 110.00 204.80 0.00 314.80

    40 mm ISS 10 560.00 56.00 0.00 616.00

    25 mm ISS 10 480.00 56.00 0.00 536.00

    20 mm ISS 10 780.00 56.00 0.00 836.00

    12 mm ISS 10 720.00 56.00 3.15 779.15

    6 mm ISS 10 360.00 56.00 3.15 419.15

    ough Stone[M 10 262.00 56.00 0.00 318.00

    ough Stone[R 10 228.00 56.00 0.00 284.00

    Bond Stone 10 360.00 56.00 0.00 416.00

    90mm IRC 10 243.00 56.00 3.15 302.15

    75mm IRC 10 272.00 56.00 3.15 331.15

    63mm IRC 10 350.00 56.00 3.15 409.15

    KM-3/0 -3/6

  • 8/13/2019 Copy of Surulipatty Road

    17/52

    53mm IRC 10 425.00 56.00 3.15 484.15

    46.50mm IRC 10 571.00 56.00 3.15 630.15

    45mm IRC 10 571.00 56.00 3.15 630.15

    37.50mm IRC 10 583.00 56.00 3.15 642.15

    26.50mm IRC 10 550.00 56.00 3.15 609.15

    25mm IRC 10 550.00 56.00 3.15 609.15

    22.4mm IRC 10 800.00 56.00 3.15 859.15

    13.2 mm IRC 10 739.00 56.00 3.15 798.15

    11.2 mm IRC 10 503.00 56.00 3.15 562.15

    6.70 mm IRC 10 374.00 56.00 3.15 433.15

    10 374.00 56.00 3.15 433.15

    10 374.00 56.00 3.15 433.15

    10 331.00 56.00 3.15 390.15

    10 73.00 56.00 3.05 132.05umen

    1 41230.35 - 41230.35tumen

    1 35600.00 0 - 35600.00

    Site Gravel 9 97.00 50.40 3.05 150.45WBM Gr II 10 399 56.00 3.15 457.98

    WBM Gr III 10 540.3 56.00 3.15 599.45

    26.4mm IRC 10 550.00 56.00 3.15 609.15

    11.2 mm IRC 10 503.00 56.00 3.15 562.15

    8&2.36mm IR 10 331.00 56.00 3.15 390.15

    6.70 mm IRC 10 374.00 56.00 3.15 433.15

    Quarry Dust 10 73.00 56.00 3.15 132.15tumen

    1 36100.00 0 - 36100.00

    4.75 mm IRC&Below

    Quarry Dust

    6.00 mm IRC

    5.60 mm IRC

  • 8/13/2019 Copy of Surulipatty Road

    18/52

  • 8/13/2019 Copy of Surulipatty Road

    19/52

    1. Basic Price

    2. Deduct cost of drum

    3. Sub-Total

    4. Excise Duty @ 14%

    5. Education Cess @ 2%

    6.Higher Secondary Education Cess on

    ED @ 1%

    7. Billable Price

    8. VAT @ 4%

    9. Total invoice value

    10. Storage Charges at %5 on basic price

    11. Total invoice value

    12. Conveyance Charges for

    a) 80/100 Grade Bitumen

    2 X 15 KM X Rs.0.99924 / KM

    b) 60/70 Grade Bitumen

    2 X 15 KM X Rs.0.9924 / KM

    b) Bitumen Emulsion

    1 X 64 KM X Rs.1.4 / KM

    340

    3700.00

    33053.84 40700.00

    33024.07 37000.00 339

    29.77

    1331.65 1373.15 144

    32532680.1031692.42

    31423.17 31230473.48

    1218.94 1256.93 12

    383844.823728.62

    37.29

    74.57 76.90

    38.45

    26633.00

    0.00 0.00

    27463.0026633.00 2734

    Bitumen

    EmulsioEx. Coimbatore. Ex. Coimba

    15

    288427463.00

    DISTRICT : BLOCK :

    Total Price =

    Sl.No.

    RATE OF BITUMEN.

    80/100 Grade

    BitumenEx. Coimbatore

    Description

    60/70 Grade

    Bitumen

  • 8/13/2019 Copy of Surulipatty Road

    20/52

    .60

    .33

    .73

    .00

    .73

    .43

    .30

    .60

    .55

    .28

    .00

    re.

    .00

    00

  • 8/13/2019 Copy of Surulipatty Road

    21/52

    Sl.No. Quantity Rate per A

    1 m2

    2 m3

    3

    Rate Per Amount Rate Amount Rate A

    1 Cost of Gravel 133.65 m3 133.65 139.25 139.25 144.85

    1.00 Hire & Labour Charges 2.78 m3 2.78 2.78 2.78 2.78

    Rate for 1 m3 136.43 142.03

    Rate Per Amount

    1 Cost of Gravel 150.45 m3

    150.45

    KM4/0

    KM 1/0 Km 2/0 Km 3/0

    Providing and Laying Gravel Soling to compacted thick including cost & conveyance of gravel from

    approved sources to work site including labour for spreading, watering and compacting by Power roller to

    achieve the required Proctor density at 100% compaction at optimum moisture content and hire & fuelcharges for power roller , water sprinkler and all other incidental charges such as traffic barricading and

    providing danger lights etc, complete.

    Clearing and grubbing road land including uprooting wild vegetation, grass, bushes, shrubs, saplings and

    trees of girth upto 300 mm, removal of stumps of such trees cut earlier and disposal of unserviceable

    materials and stacking of serviceable material to be used or auctioned, upto a lead of 1000 m includingremoval and disposal of top organic soil not exceeding 150 mm in thickness as per Technical Specification

    Clause 201.

    Earthwork excavating & depositing on bank with init ial lead of 10m & initial lift of 2m in hard stiff clay, stiff

    black cotton, hard red earth, shales, murrum, gravel, stoney earth and earth mixed with small size boulders

    SS 20 A including laying and spreading in layers of 250 mm loose thick each , sectioning , watering and

    compacting etc, complete as per MOST 301 - 305.

    Improvement of road from Cumbum To Surulipatty Road Km 0/8 3/6THENI

    Description of work

    DISTRICT : BLOCK : CUMBUM

    Road Data

  • 8/13/2019 Copy of Surulipatty Road

    22/52

    1.00 Hire & Labour Charges 2.78 m3 2.78

    Rate for 1 m3 153.23

    5

    Rate Per Amount Rate Amount Rate

    1.00 Cost of 63 - 11.2 mm IRC HBG metal 582.65 m3 582.65 588.25 588.25 593.85

    0.24 Cost of Gravel 133.65 m3 32.08 139.25 33.42 144.85

    10.00 Hire & Labour Charges 114.26 10m2 114.26 114.26 114.26 114.26

    Rate for 10 m2 728.99 735.93

    Rate for 1 m3 971.99 981.24

    Rate Per Amount

    1.00 Cost of 63 - 11.2 mm IRC HBG metal 599.45 m3

    599.45

    0.24 Cost of Gravel 150.45 m3 36.11

    10.00 Hire & Labour Charges 114.26 10m2 114.26

    Rate for 10 m2 749.82

    Rate for 1 m3 999.76

    6

    Providing and laying tack coat over the WBM surface using 4.00 Kg of bituminous emulsion for 10

    sqm.Including cost of bituminous emulsion which will be supplied by the department at section stores and

    its cost will be recovered as per special condition appended including labour charges for preparing the

    surface for laying tack coat and for applying required quantity of bituminous emulsion by mechanical sprayer

    including hire and fuel charges for all tools and plants employed etc., complete as per clause 503 of

    MoRT&H specification.

    Km : 0 / 0 - 6/0

    KM4/0

    Provi ing an aying 75mm compacte t ic WBM Gr.IIIusing 1 cum o 63mm to 11.2mm IRC HBG meta

    and 0.24 cum of Gravel for blindage for 10sqm. Of 75mm compacted thick (the blindage material shall have

    PI value less than 6%) including cost and conveyance of all materials from approved quarry to worksite and

    stacking to departmental gauge for pre-measurement as directed by the departmental officers including

    labour for spreading metal and gravel hand packing to camber and grade lines blinding with required

    quantity of gravel forming edge bunds watering with all leads for good water slurrying rolling and

    consolidation by power roller and finishing has per MoRT&H 404 (III revision) including hire and fuel charges

    for power roller and water sprinkler and all other tools and plants employed therefor and all other incidental

    KM 1/0 Km 2/0 Km 3/

  • 8/13/2019 Copy of Surulipatty Road

    23/52

    Rate Per Amount

    4.00 Cost of Bitumen Emulsion 42209.00 MT 168.84

    10.00 Labour & Hire charges 77.80 10m2 77.80

    1.00 Hire Charges for Bitumen Sprayer 12.00 10m2 1.20

    Rate for 10 m2 247.84

    Rate for 1 m2 24.78

    7

    Rate Per Amount Rate Amount Rate

    0.18 Cost of 13.2 mm IRC metal 781.35 m3 140.64 786.95 141.65 792.55

    0.09 Cost of 11.2 mm IRC metal 545.35 m3 49.08 550.95 49.59 556.55

    0.09 Cost of 6.7 mm IRC metal 416.35 m3 37.47 421.95 37.98 427.55

    24.40 Cost of Bitumen 41230.35 MT 1006.02 41230.35 ###### 35600.00

    10.00 Labour & Hire charges for P.C & S.C 258.48 10 m2 258.48 258.48 258.48 258.48

    1.00 Hire charges for P.C & S.C 58.13 10 m2 5.81 58.13 5.81 58.13

    Rate for 10 m2 1497.50 ######

    Rate for 1 m2 149.75 149.95

    Km 3/0

    Providing and laying open graded premix carpet of 20 mm compacted thickusing 0.18cum of 13.20

    mm IRC size HBG machine crushed chips and 0.09 cum of 11.20 mm IRC HBG machine crushed chips with

    14.6 Kg of bitumen for 10 sqm of premix carpet including laying of seal coat typeAover the premix carpet

    using 0.09 cum of 6.7mm IRC size HBG machine crushed chips with 9.8 Kg of bitumen per 10 sqm including

    cost and conveyance of chips and stacking them to departmental gauge for pre-measurements including

    cost of bitumen which will be supplied by the department at departmental section stores and its cost will be

    recovered as per special condition appended including heating the bitumen and metal mixing the materials

    in mini hot mix plant for premix carpet including spreading the same and finishing and compacting the same

    by power rolling to the specified lines and grades including all labour charges application of bitumen for seal

    coat over the premix carpet and spreading the seal coat and power roller rolling seperately as per MoRT&H

    specification 509 and 513 (III revision) including all labour charges hire and fuel charges for mini hot mix

    plant power roller 80 100 KN capacity and all other tools and plants employed therefore etc., complete.

    KM 1/0 Km 2/0

  • 8/13/2019 Copy of Surulipatty Road

    24/52

    Rate Per Amount

    0.18 Cost of 13.2 mm IRC metal 798.15 m3 143.67

    0.09 Cost of 11.2 mm IRC metal 562.15 m3 50.59

    0.09 Cost of 6.7 mm IRC metal 433.15 m3 38.98

    24.40 Cost of Bitumen 41230.35 MT 1006.02

    10.00 Labour & Hire charges for P.C & S.C 258.48 10 m2 258.48

    1.00 Hire charges for P.C & S.C 58.13 10 m2 5.81

    Rate for 10 m2 1503.55

    Rate for 1 m2 150.36

    1 M2

    KM4/0

    Scarifying Existing Granular Surface to a Depth of 50 mm by Manual Means

    Scarifying existing granular surface to a depth of 50 mm and disposal of scarified material with a lift upto 3 m and leads upto 10

    per Technical Specification Clause 301.4.

  • 8/13/2019 Copy of Surulipatty Road

    25/52

    DISTRICT : THENI

    Sl.No Description Nos Length Breadth Depth Quantity Unit

    1

    Ch 800-1000 2 200.00 1.000 400.00

    Ch 1000-2000 2 1000.00 1.000 2000.00

    Ch 2000-3000 2 1000.00 1.000 2000.00

    ` Ch 3000-3600 2 600.00 1.000 1200.00

    5600.00

    -2240.00

    3360.00 sqm

    2

    Ch 800-1000 2 200.00 1.000 0.300 120.00 cum

    Ch 1000-2000 2 1000.00 1.000 0.300 600.00 cum

    Ch 2000-3000 2 1000.00 1.000 0.300 600.00 cum

    Ch 3000-3600 2 600.00 1.000 0.300 360.00 cum

    1680.00

    3

    Ch 800-1000 1 200.00 3.750 750.00sqm

    Ch 1000-2000 1 1000.00 3.750 3750.00sqm

    Ch 2000-3000 1 1000.00 3.750 3750.00sqm

    ` Ch 3000-3600 1 600.00 3.750 2250.00sqm

    10500.00 sqm3500.00 sqm

    4

    Ch 800-1000 1 200.00 3.750 0.075 56.25 Cum

    56.25 Cum

    Ch 1000-2000 1 1000.00 3.750 0.075 281.25 Cum

    281.25 Cum

    Ch 2000-3000 1 1000.00 3.750 0.075 281.25 Cum

    Deduct 2m Culvert Ch 2400m -1 2.40 3.750 0.075 -0.68 Cum

    ` Deduct 2m Culvert Ch 2950m -1 2.40 3.750 0.075 -0.68 Cum

    279.90 Cum

    Ch 3000-3600 1 600.00 3.750 0.075 168.75 Cum

    Bell mouth ((11.25+3.75)/2) 1 10.00 7.500 0.075 5.63 Cum

    174.38 Cum

    DETAILED ESTIMATEImprovement of road from Cumbum To Surulipatty Road Km 0/8-3/6

    Clearing and grubbing road land including uprooting wild vegetation, grass, bushes, shrubs, saplings

    and trees of girth up to 300mm, removal of stumps of such trees cut earlier and disposal of

    unserviceable materials and stacking of serviceable material t

    Deduct 40% voids

    BLOCK : CUMBUM

    Construction of embankment with approved material obtained from borrow pits with a lift up to 1.5

    m, transporting to site, spreading, grading to required slope and compacting to meet requirements

    with a lead up to 1000 m as per Technical Specification cla

    Scarifying Existing Granular Surface to a Depth of 50 mm by Manual Means

    Providing laying, spreading and compacting stone aggregates of specific sizes to water bound

    macadamIIIspecification including spreading in uniform thickness, hand packing, rolling with three

    wheel 80 100 KN static roller in stages to proper grade and cam

  • 8/13/2019 Copy of Surulipatty Road

    26/52

    5

    Ch 800-1000 1 200.00 3.750 750.00 Sqm

    750.00 Sqm

    Ch 1000-2000 1 1000.00 3.750 3750.00 Sqm

    3750.00 Sqm

    Ch 2000-3000 1 1000.00 3.750 3750.00 Sqm

    3750.00 Sqm

    Ch 3000-3600 1 600.00 3.750 2250.00 Sqm

    Bell mouth ((11.25+3.75)/2) 1 10.00 7.500 75.00 Sqm

    2325.00 Sqm

    10575.00 Sqm

    6

    Ch 800-1000 1 200.00 3.750 750.00 Sqm750.00 Sqm

    Ch 1000-2000 1 1000.00 3.750 3750.00 Sqm

    3750.00 Sqm

    Ch 2000-3000 1 1000.00 3.750 3750.00 Sqm

    3750.00 Sqm

    Sqm

    Ch 3000-3600 1 600.00 3.750 2250.00 Sqm

    Bell mouth ((11.25+3.75)/2) 1 10.00 7.500 75.00 Sqm

    2325.00 Sqm

    7

    No. of Village - 2 No. 1 2 2 Nos.8 3

    9 15 Nos.

    10

    11 Contingencis and other unforeseen items L.S

    Reinforced cement concrete M15 grade Hecto meter stone of standard design

    Construction of Retaining wall/ CD works (As per sub estimate)

    Providing and applying tack coat with Bitumen emulsion (RS 1) using emulsion distributor

    at the rate of 4 kg /10 sqm on the prepared granular surface treated with primer & cleaned

    With Hydraulic broom as per Technical Specification clause 503 and as dir

    Providing laying and rolling of open grade premix carpet of 20 mm thickness composed of

    13.2 mm to 5.6 mm aggregates either using penetration grade bitumen or emulsion to required

    line, grade and level to serve as Seal Coat on a previously prepared base

    Providing and erecting direction and place identfication Board

    Reinforced cement concrete M15 grade Kilometer stone of standard design

  • 8/13/2019 Copy of Surulipatty Road

    27/52

    DISTRICT : BLOCK : CUMBUM

    Sl.No unit Quantity Rate Amount

    Ch 800 - 3600 sqm 3360.00 1.70 5 712

    Ch 800 - 3600 cum 1680.00 33.65 56 532

    Ch 800 - 3600 sqm 3500.00 3.75 13 125

    Ch 800-1000 sqm 56.25 971.99 54 674

    Ch 1000-2000 sqm 281.25 981.24 2 75 974

    Ch 2000-3000 sqm 279.90 990.49 2 77 238

    Ch 3000-3600 sqm 174.38 999.76 1 74 333

    Ch 800 - 3600 sqm 10575.00 24.78 2 62 049

    Ch 800-1000 sqm 750.00 149.75 1 12 313

    Ch 1000-2000 sqm 3750.00 149.95 5 62 313

    Ch 2000-3000 sqm 3750.00 136.42 5 11 575

    Ch 3000-3600 sqm 2325.00 150.36 3 49 587

    Difference in cost of material 2.8x20000 56 000

    Each 2 4000.00 8 000

    Each 3 260.00 780

    Each 15 130.00 1 950

    10 2m Slab culvert 2 96 513

    11 2m Slab culvert 2 96 513

    33 15 180

    12 different in cost of material

    3.6x20000 72 000

    13 Provision for Labour Welfare 0.3%

    - 4 10 000 9 946

    6 Providing laying and rolling of open grade premix carpet of 20 mm thickness

    composed of 13.2 mm to 5.6 mm aggregates either using penetration grade bitumen oremulsion to required line, grade and level to serve as wearing course on a previously

    ABSTRACT ESTIMATE

    Reach

    Providing laying, spreading and compacting stone aggregates of specific sizes to Water

    bound macadam Grade III specification including spreading in uniform thickness, hand

    packing, rolling with three wheel 80 100 KN static roller in stages to proper gra

    Improvement of road from Cumbum To Surulipatty Road Km 0/8-3/6

    THENI

    1 Clearing and grubbing road land including uprooting wild vegetation, grass, bushes,

    shrubs, saplings and trees of girth up to 300mm, removal of stumps of such trees cut

    earlier and disposal of unserviceable materials and stacking of serviceable material t

    Sub total

    8 Reinforced cement concrete M15 grade Kilometer stone

    9 Reinforced cement concrete M15 grade Hecto meter stone

    7 Providing and erecting direction and place identfication Board

    2 Construction of embankment with approved material obtained from roadway cutting

    with a lift up to 1.5 m, transporting to site, spreading, grading to required slope and

    compacting to meet requirements with a lead up to 1000 m as per Technical

    3 Scarifying Existing Granular Surface to a Depth of 50 mm by Manual Means

    4

    5 Providing and applying tack coat with Bitumen emulsion (RS ) using emulsion

    distributor at the rate of 0.275 kg / sqm on the prepared granular surface treated with

    primer & cleaned With Hydraulic broom as per Technical Specification clause 503 and

  • 8/13/2019 Copy of Surulipatty Road

    28/52

    14 provision for future PWD shedule

    of rate 10% 3 31 518

    15 Contingencis and other unforeseen items 11 356

    Total estimate amount Rs. 37 40 000

  • 8/13/2019 Copy of Surulipatty Road

    29/52

    =

    =

    =

    =

    =

    =

    =

    =

    =

    =

    =

    [email protected] [email protected]

    Rs

    Rs

    Mazdoor I Class

    Mazdoor II Class

    Rs. 123.00

    Rs. 111.00

    Mason I Class

    Mason II Class

    Rs. 190.00

    Rs. 172.00

    Carpenter I Class

    Rs. 195.00

    Rs. 175.00

    Carpenter II Class Rs. 175.00

    Rs

    Cost of furnace oil Rs. 26.16

    Fitter I Class

    Cost of kerosine

    Cost of diesel

    Rs. 37.52

    Rs. 40.00

    Rs. 160.00Fitter II Class

    mailto:[email protected]:[email protected]:[email protected]:[email protected]
  • 8/13/2019 Copy of Surulipatty Road

    30/52

    . 139.00

    . 125.00

    . 143.00

  • 8/13/2019 Copy of Surulipatty Road

    31/52

    1

    1.00 SI. No. 62 SS20 B 31.60 m3

    1.00 Add 100% For Earth work 31.60 m3

    Rate per 1.00cum

    2

    Rate Per Amount Rate Amount

    1.00 Cost of Sand 304.90 m3

    304.90 308.20 308.20 311.50

    1.00 Refilling with Sand 9.00 m3

    9.00 9.00 9.00 9.00

    Rate per 1.00cum 313.90 317.20

    Rate Per Amount

    1.00 Cost of Sand 314.80 m3

    314.80

    1.00 Refilling with Sand 9.00 m3

    9.00

    Rate per 1.00cum 323.80

    KM 4/0

    Km

    Improvement of road from Cumbum To Surulipatty Road Km 0/8 3/6DISTRICT : THENI BLOCK : Cumbum

    Earth work Excavation for Foundation in all soils and Sub Soil to full depth as may be

    directed except in hard rock requiring blasting but inclusive of shoring strutting and

    requiring the sides of foundation.

    Supplying and Filling foundation and basementwith filling sandin layers not more than

    15cm . Thick well ramed, watered and compacted Complete complying with stanard

    specification.

    KM 1/0 Km 2/0

  • 8/13/2019 Copy of Surulipatty Road

    32/52

    3

    Rate Per Amount Rate Amount Rate

    9.00 40mm ISS HBG metal 599.20 m3 5392.80 604.80 5443.20 610.40

    4.50 Cement mortar 1 : 4 1872.16 m3

    8424.72 1876.72 8445.24 1881.28

    1.80 Mason II class 195.00 Each 351.00 195.00 351.00 195.00

    17.70 Mazdoor I category 123.00 Each 2177.10 123.00 2177.10 123.00

    14.10 Mazdoor II category 111.00 Each 1565.10 111.00 1565.10 111.00

    Rate per 10cum 17910.72 17981.64

    Rate per 1.00cum 1791.07 1798.16

    Rate Per Amount

    9.00 40mm ISS HBG metal 616.00 m3

    5544.00

    4.50 Cement mortar 1 : 4 1885.84 m3

    8486.281.80 Mason II class 195.00 Each 351.00

    17.70 Mazdoor I category 123.00 Each 2177.10

    14.10 Mazdoor II category 111.00 Each 1565.10

    Rate per 10cum 18123.48

    Rate per 1.00cum 1812.35

    4

    Rate Per Amount Rate Amount Rate

    KM 4/0

    Cement concrete 1 : 3 : 6 mix using 40mm HBG metal for foundation including watering

    wherever necessary and laid in layers of not more than 15cm thick., compacting etc.,

    complete complying with standard specifications and as directed.

    KKM 1/0 Km 2/0

    Cement concrete 1 : 4 : 8 mix using 40mm HBG metal for foundation including watering

    wherever necessary and laid in layers of not more than 15cm thick., compacting etc.,

    complete complying with standard specifications and as directed.

    KM 1/0 Km 2/0 K

  • 8/13/2019 Copy of Surulipatty Road

    33/52

    9.00 40mm ISS HBG metal 599.20 m3

    5392.80 604.80 5443.20 610.40

    4.50 Cement mortar 1 : 3 2394.58 m3

    10775.61 2399.56 10798.02 2404.54

    1.80 Mason II class 195.00 Each 351.00 195.00 351.00 195.00

    17.70 Mazdoor I category 123.00 Each 2177.10 123.00 2177.10 123.00

    14.10 Mazdoor II category 111.00 Each 1565.10 111.00 1565.10 111.00

    Rate per 10cum 20261.61 20334.42Rate per 1.00cum 2026.16 2033.44

    Rate Per Amount

    9.00 40mm ISS HBG metal 616.00 m3

    5544.00

    4.50 Cement mortar 1 : 3 2409.52 m3

    10842.84

    1.80 Mason II class 195.00 Each 351.00

    17.70 Mazdoor I category 123.00 Each 2177.10

    14.10 Mazdoor II category 111.00 Each 1565.10

    Rate per 10cum 20480.04

    Rate per 1.00cum 2048.00

    5

    Rate Per Amount Rate Amount Rate

    9.00 20mm ISS HBG metal 819.20 m3

    7372.80 824.80 7423.20 830.40

    4.50 Cement mortar 1 : 4 1872.16 m3

    8424.72 1876.72 8445.24 1881.28

    1.80 Mason II class 175.00 Each 315.00 175.00 315.00 175.00

    17.70 Mazdoor I category 123.00 Each 2177.10 123.00 2177.10 123.00

    14.10 Mazdoor II category 111.00 Each 1565.10 111.00 1565.10 111.00

    Rate per 10cum 19854.72 19925.64

    KM 4/0

    Cement concrete 1 : 2 : 4 mix using 20mm HBG metal for foundation including watering

    wherever necessary and laid in layers of not more than 15cm thick., compacting etc.,

    complete complying with standard specifications and as directed.

    KM 1/0 Km 2/0 Km

  • 8/13/2019 Copy of Surulipatty Road

    34/52

    Rate per 1.00cum 1985.47 1992.56

    Rate Per Amount Rate Amount Rate

    9.00 20mm ISS HBG metal 836.00 m3

    7524.00

    4.50 Cement mortar 1 : 4 1885.84 m3

    8486.28

    1.80 Mason II class 175.00 Each 315.00

    17.70 Mazdoor I category 123.00 Each 2177.10

    14.10 Mazdoor II category 111.00 Each 1565.10

    Rate per 10cum 20067.48

    Rate per 1.00cum 2006.75

    6

    Rate Per Amount Rate Amount Rate

    10.00 Rough stone for Masonry301.20 m

    3

    3012.00 306.80 3068.00 312.401.00 Bond stone 399.20 m3

    399.20 404.80 404.80 410.40

    3.40 Cement mortar 1 : 5 1558.71 m3

    5299.61 1563.02 5314.27 1567.32

    7.10 Mason I class 195.00 Each 1384.50 195.00 1384.50 195.0010.60 Mason II class 175.00 Each 1855.00 175.00 1855.00 175.0014.10 Mazdoor I category 123.00 Each 1734.30 123.00 1734.30 123.0014.10 Mazdoor II category 111.00 Each 1565.10 111.00 1565.10 111.00

    Rate per 10cum 15249.71 15325.97Rate per 1.00cum 1524.97 1532.60

    Rate Per Amount

    10.00 Rough stone for Masonry 318.00 m3

    3180.00

    1.00 Bond stone 416.00 m3

    416.00

    3.40 Cement mortar 1 : 5 1571.63 m3

    5343.54

    7.10 Mason I class 195.00 Each 1384.50

    KM 4/0 Km 5/0 K

    Random Rubble Masonry in cement Mortar 1 : 5 for foundation and basement usingNew Stones

    including necessary provision for Bond stones with simultaneous flush pointing with the

    same mortar above ground level complying with standard specifications.

    KM 1/0 Km 2/0

    KM 4/0

    K

  • 8/13/2019 Copy of Surulipatty Road

    35/52

    10.60 Mason II class 175.00 Each 1855.0014.10 Mazdoor I category 123.00 Each 1734.30

    14.10 Mazdoor II category 111.00 Each 1565.10

    Rate per 10cum 15478.44

    Rate per 1.00cum 1547.84

    7

    Rate Per Amount Rate Amount Rate

    9.00 20mm ISS HBG metal 819.20 m3

    7372.80 824.80 7423.20 830.40

    4.50 Cost of Sand 304.90 m3

    1372.05 308.20 1386.90 311.50

    4.308 Cost of Cement 4353.50 MT 18754.88 4357.00 18769.96 4360.50

    3.50 Mason II class 175.00 Each 612.50 175.00 612.50 175.00

    21.20 Mazdoor I category 123.00 Each 2607.60 123.00 2607.60 123.00

    35.30 Mazdoor II category 111.00 Each 3918.30 111.00 3918.30 111.00

    10.00 Add for Vibration charges 24.20 m3

    242.00 24.20 242.00 24.20

    Rate for 10 m3

    34880.13 34960.46

    Rate per 1.00cum 3488.01 3496.05

    Rate Per Amount

    9.00 20mm ISS HBG metal 836.00 m3

    7524.00

    4.50 Cost of Sand 314.80 m3

    1416.60

    4.308 Cost of Cement 4364.00 MT 18800.11

    3.50 Mason II class 175.00 Each 612.50

    21.20 Mazdoor I category 123.00 Each 2607.60

    KM 4/0

    Km

    Cement concrete 1:1.5:3 using 20mm ISS HBG metal for all RCC item of works excluding cost

    of Rein forcement and fabricating charges, centering and shuttering but including curing

    and shall be finished smooth with cement mortar 1:3, 12mm thick. and with kraft paper

    without claiming extra as directed by the departmental officers complete complying with

    standard specifications.

    KM 1/0 Km 2/0

  • 8/13/2019 Copy of Surulipatty Road

    36/52

    35.30 Mazdoor II category 111.00 Each 3918.30

    10.00 Add for Vibration charges 24.20 m3

    242.00

    Rate for 10 m3

    35121.11

    Rate per 1.00cum 3512.11

    8

    Rate Per Amount Rate Amount Rate

    1.00 Cost of steel 37753.50 MT 37753.50 37757.00 37757.00 37760.50

    10.00 Cost of binding wire 34.50 Kg 345.00 34.50 345.00 34.50

    35 Fitter I Class for bendin 172.00 Each 6020.00 172.00 6020.00 172.00

    Rate for 1.00 MT 44118.50 44122.00

    Rate Per Amount

    1.00 Cost of steel 37764.00 MT 37764.00

    10.00 Cost of binding wire 34.50 Kg 345.00

    35 Fitter I Class for bendin 172.00 Each 6020.00

    Rate for 1.00 MT 44129.00

    9

    Rate Per Amount Rate Amount Rate

    0.22 Cement Mortar 1:4 1872.16 m3

    411.88 1876.72 412.88 1881.28

    KM 4/0

    KM 1/0 Km 2/0 K

    Plastering with CM 1:4, 20mm thick.over the cement concrete for floor finish including

    curing etc., complete complying with standard specifications and as directed by the

    departmental officers.

    KM 1/0 Km 2/0 K

    Supplying and Fabricating and placing in position MS steel or Ribbed Tor Steel for all

    Reinforced Cement Concrete works as per the design given including cost of steel and

    binding wire in all floors etc, Complete complying with stanard specification.(MS rod or

    RTS bar will be supplied departmentally at section stores and cost will be recoverd at

    issue rate). the binding wire shall supplied by the contactor.

  • 8/13/2019 Copy of Surulipatty Road

    37/52

    2.20 Mason I class 195.00 Each 429.00 195.00 429.00 1

    0.50 Mazdoor I category 123.00 Each 61.50 123.00 61.50 1

    3.20 Mazdoor II category 111.00 Each 355.20 111.00 355.20 1

    Rate per 10sqm 1257.58 1258.58

    Rate per 1.00sqm 125.76 125.86

    Rate Per Amount Rate Amount Ra

    0.22 Cement Mortar 1:4 1885.84 m3

    414.88 0.00 0.00

    2.20 Mason I class 195.00 Each 429.00 195.00 429.00 1

    0.50 Mazdoor I category 123.00 Each 61.50 123.00 61.50 1

    3.20 Mazdoor II category 111.00 Each 355.20 111.00 355.20 1

    Rate per 10sqm 1260.58 845.70

    Rate per 1.00sqm 126.06 84.57

    10

    Sub Data I

    Cost of MS sheets & angles for each set

    Weight of MS sheet B.G 10 Gauge size 90x60cm x 3.175 mm

    3.75 x 7850/1000 = 24.924 kg/m2

    24.924 Kg x 0.54 m2= 13.46 Kg.

    Weight of MS angle size 25 x 25 x 3 mm

    3.6 x 1.1 Kg/m = 4.00 Kg

    13.46 Cost of MS sheets 90 x 60 cm, 10 Gauge 34.50 Kg

    4.00 Cost of MS angle size 25 x 25 x 3 mm 34.50 Kg

    KM 4/0 Km 5/0

    Supplying & Erecting centering for sides & soffiots including necessary supports & strutting upto

    3.29m height for plane surfaces in all floors with all cross bracings using mild steel sheets of size

    90 x 60cm & 10 gauge stiffened, welded with steel angle of size 25 x 25 x 3mm for boarding laid over

    silver oak joists(Country wood) of size 10 x 6.5cm spaced @ about 90cm c/c and supported by casurina

    props of 10 - 13cm dia. spaced @ 75cm c/c etc., complete complying with standard specifications andas directed by the departmental officers. Rate for 10m

    2.for the following items.(RCC floor slab, roof

    slab, Rectangular/ square, Tee/ Ell beams, Lintels, staircase waist slabs, Landing slabs, Landing

    beam, Portico beam etc., ).

  • 8/13/2019 Copy of Surulipatty Road

    38/52

    LS Add for Cutting, Bending,welding charges etc., LS

    Total for each set (A)

    Sub Data II

    19.00 Cost of MS sheets & angles (A) 629.05 Set

    0.12 Cost of Silver Oak/ CW Joists 10 x 6.5 cm 97.00 m3

    98.50 Casurina props 10 - 13 cm dia. 0.00 Rm

    11.64

    MAIN DATA FOR CENTERING - 10 M2

    19.00 Cost of steel sheet & Angles ( D ) 298.80 1 use

    0.12 2.33 1 use

    98.50 Casurina props 10 - 13 cm dia. 0.00 1 use

    3.80 Carpenter I class 190.00 Each

    5.40 Mazdoor I category 123.00 Each

    1.00 Fitter II Class. 160.00 Each

    LS Add for wedges, coir, nails etc., LS

    LS Add for periodical cleaning & painting of MS sheets

    Total for 10 m2

    Rate for 1 m2 186.37

    Centering for Lintels & Beams per Sqm 186.37

    Centering for Small projections (Sunshades, Lofts) per Sqm 223.64

    Cost of silver Oak/ CW Joists 10 x 6.5 cm

    Cost of steel sheet & Angles for 1 use = B/40 11951.95

    Cost of MS sheet & Angles and silver Oaks, Joists & Casurina for 10 m2

    Adopting 40 uses for steel sheets & angles, 5 uses for silver oak/ CW joists

    and casurina props.

    Cost of silver Oak/ CW Joists 10 x 6.5 cm & Casurina props for

    1 use = C/ 5

  • 8/13/2019 Copy of Surulipatty Road

    39/52

    Centering for Roof Slabs per Sqm 186.37

    Centering below Ground level 186.367 / 2 93.18

    Centering sides 1863.67 - 2.328 / 10 186.13

    11

    3 420.00

    3.0 / 7.8 no mm dia PVC Sh 60 each 23.076923.0 / 7.8 no 110 mm dia PVC b 75 each 28.85

    3.0 / 7.8 9.31

    2.00 nos PVC clamp 10 each 20.00

    1.00 no Plumber I st class 169 No 169.00

    LS Sundries for cement LS 1.77

    Rate for 1m2 Rs 224.00 For 3m 672.00

    12

    Rate Per Amount Rate Amount Rate

    11.00 Rough stone dry packing f 267.20 m3 2939.20 272.80 3000.80 278.40

    3.50 Mason I class 195.00 Kg 682.50 195.00 682.50 195.00

    10.6 Maz I class 123.00 Each 1303.80 123.00 1303.80 123.00

    7 Maz II class 111.00 Each 777.00 111.00 777.00 111.00

    Rate for 10 m3 4925.50 4987.10

    Rate for 1 m3 492.55 498.71

    Rate for 1 m2 113.23 114.65

    Rate Per Amount

    11.00 Rough stone dry packing f 284.00 m3 3124.00

    3.50 Mason I class 195.00 Kg 682.50

    10.6 Maz I class 123.00 Each 1303.80

    Supplying and fixing in position best qulity PVC Rain water pipe having ISI

    mark and providing leak proof joints inculding fixing to the wall with special

    PVC / MS clamps etc

    KM 4/0

    Km

    Rough stone dry packing for revertments including cost,conveyance of all materials etc complete

    KM 1/0 Km 2/0

    no

    Rm

  • 8/13/2019 Copy of Surulipatty Road

    40/52

    7 Maz II class 111.00 Each 777.00

    Rate for 10 m3 5110.30

    Rate for 1 m3 511.03

    Rate for 1 m2 117.48

  • 8/13/2019 Copy of Surulipatty Road

    41/52

    Sl.No. Length Bredth Depth Contents

    Abutment 1 2 8.700 2.200 1.35 51.68

    Wings 2 2 1.500 1.900 1.35 15.39

    67.07

    cum

    Abutment 1 2 8.700 2.200 0.15 5.74

    Wings 2 2 1.500 1.900 0.15 1.71

    1 1 7.500 1.500 0.15 1.69

    9.14

    cum

    Below sill

    Abutment

    Footing 1 1 2 8.700 1.900 0.40 13.22

    Footing 2 1 2 8.300 1.600 0.40 10.62

    Footing 3 1 2 7.900 1.300 0.40 8.22

    Wings

    Footing 1 2 2 1.650 1.900 0.40 5.02

    Footing 2 2 2 1.800 1.600 0.40 4.61

    Footing 3 2 2 1.950 1.300 0.40 4.06

    Above Sill

    Abutment

    1 2 7.500 1.000 1.30 19.50

    (1.3+.7)/2

    Wings

    3. Providing and laying Cement Concrete of grade M10 Nominal Mix 1:3:6 using graded ISS size

    HBG metal including cost and conveyance of all materials to site including cost of cement at site

    including cost of formwork, soft water, labour charges for mixing, transporting, laying and curing

    concrete , working at depths , tools and plants and including all other incidental charges etc;

    complete as per relevant standard specifications clause 802,803,1202 &1203, for foundation

    DETAILED ESTIMATE

    Construction of slab culvert 2 m vent @ CH : 2400m

    Improvement of road from Cumbum To Surulipatty Road Km 0/8-3/6

    Description Nos

    1. Earthwork excavation in all classes of soil except soft rock not requiring blasting and hard rock

    requiring blasting and depositing on bank with all leads and lifts as per SS20B, including cost of all

    labour, equipments and all incidential charges such as baling our water, providing and maintaining

    necessary cofferdams, sheeting, shoring bracing and their subsequent removal, removal of all logs,

    stumps, grubs and other deleterious matter and obstructions, trimming bottom of excavation

    backfilling, and clearing the site and disposal of all surplus materials etc., complete as per relevant

    standard specification clause 1140 for foundation of abutments, wings

    2. Providing and laying Cement Concrete of grade M7.5Nominal Mix 1:4:8 using graded ISS sizeHBG metal including cost and conveyance of all materials to site including cost of cement at site

    including cost of formwork, soft water, labour charges for mixing, transporting, laying and curing

    concrete , working at depths , tools and plants and including all other incidental charges etc;

    complete as per relevant standard specifications clause 802,803,1202 &1203, for foundation

    Water way

  • 8/13/2019 Copy of Surulipatty Road

    42/52

    2 2 2.475 0.850 2.10 17.67

    Parapet 1 2 3.400 0.450 0.45 1.38

    84.30

    1 2 7.500 0.210 3.15

    sqm

    1 1 7.500 2.600 0.210 4.10

    1 2 7.500 0.700 0.200 2.10

    Dirt wall 1 2 7.500 0.400 0.210 1.26

    7.46

    Deck slab as per steel schedule 0.60

    Mt

    Wings 1 2 3.000 6.700 1.500 60.30

    4. Providing and fixing kraft paper full width of seating of deck slab and including cost and

    conveyance to wotksite, labour for fixing the same in corect position and all other incidental charges

    etc., complete as per standard specifications.

    Deck slab

    bed block

    6. Supplying, fitting and placing HYSD bar reinforcement in superstructure complete as per

    drawing and MORD technical specifications clause 1002,1010,&1202

    7. Back filling behind Abutments and Wings with granular materials including cost and conveyance

    to worksite, laying, handling charges and filling in layers, tamping under optimum moisture content

    to get the maximum density including watering, with all leads for water and all other incidental

    charges etc., complete as per specifications for filling behind the abutments and wings

    5. Vibrated Reinforced Cement Concrete of grade M 25 using ISS size HBG graded metal

    including cost and conveyance of all materials to site including cost ofcement at site including cost

    of formwork, soft water, labour charges for mixing, transporting, laying and curing concrete ,

    working at depths , tools and plants including all other incidental charges etc., complete as per

    relevant standard specifications,clause 800,1205.4, and 1205.5 for deck slab

  • 8/13/2019 Copy of Surulipatty Road

    43/52

    cum 60.30

    1 2 3.400 0.450 3.06

    sqm 3.06

    Above Sill

    Deck slab 1 1 7.500 1.500 11.25

    Deck slab 1 2 2.600 0.210 1.09

    Bed block 2 2 8.200 0.200 6.56

    Dirt wall 2 2 7.900 0.210 6.64

    Above Sill

    Abutment

    2 2 8.500 1.30 44.20Wings

    2 4 3.325 2.10 55.86

    Parapet 2 2 3.850 0.45 6.93

    132.53

    Below Sill

    Abutment

    Footing 2 2 10.600 0.40 16.96

    Footing 2 2 9.900 0.40 15.84

    Footing 2 2 9.200 0.40 14.72

    Wings

    Footing 1 2 4 1.650 0.40 5.28

    Footing 2 2 4 1.800 0.40 5.76

    Footing 3 2 4 1.950 0.40 6.24

    64.80

    9. Supplying, fixing and placing of centering for superstructure complete as per drawing and

    MORD technical specifications clause 1002,1010,&1202

    10. Supplying, fixing and placing of centering for superstructure complete as per drawing and

    MORD technical specifications clause 1002,1010,&1202

    8. Plastering with Cement mortar 1:4 15 mm thick including cost and conveyance of all materials to

    siteincluding all other incidental charges etc; complete as per relevant standard specifications

    Parapet top

  • 8/13/2019 Copy of Surulipatty Road

    44/52

    l. No. Unit Quantity Rate

    cum 67.07 63.20

    cum 9.14 1805.26

    cum 84.30 2040.72

    sqm 4.50 220.00

    cum 7.46 3504.08

    3. Providing and laying Cement Concrete of grade M10 Nominal Mix 1:3:6 using grade

    metal including cost and conveyance of all materials to site including cost of cement at sit

    of formwork, soft water, labour charges for mixing, transporting, laying and curing conc

    depths , tools and plants and including all other incidental charges etc; complete as per r

    specifications clause 802,803,1202 &1203, for foundation

    4. Providing and fixing kraft paper full width of seating of deck slab and including cost a

    wotksite, labour for fixing the same in corect position and all other incidental charges etc.,

    standard specifications.

    5. Vibrated Reinforced Cement Concrete of grade M 25 using ISS size HBG graded met

    and conveyance of all materials to site including cost ofcement at site including cost of

    water, labour charges for mixing, transporting, laying and curing concrete , working at d

    plants including all other incidental charges etc., complete as per relevant standard spe800,1205.4, and 1205.5 for deck slab

    1. Earthwork excavation in all classes of soil except soft rock not requiring blasting

    requiring blasting and depositing on bank with all leads and lifts as per SS20B, including c

    equipments and all incidential charges such as baling our water, providing and maint

    cofferdams, sheeting, shoring bracing and their subsequent removal, removal of all logs, st

    other deleterious matter and obstructions, trimming bottom of excavation backfilling, and

    and disposal of all surplus materials etc., complete as per relevant standard specification

    foundation of abutments, wings

    2. Providing and laying Cement Concrete of grade M7.5 Nominal Mix 1:4:8 using grad

    metal including cost and conveyance of all materials to site including cost of cement at sit

    of formwork, soft water, labour charges for mixing, transporting, laying and curing conc

    depths , tools and plants and including all other incidental charges etc; complete as per r

    specifications clause 802,803,1202 &1203, for foundation

    COST ESTIMATE

    Construction of slab culvert 2 m vent @ CH : 2400m

    Improvement of road from Cumbum To Surulipatty Road Km 0/8-3/6

    Description

  • 8/13/2019 Copy of Surulipatty Road

    45/52

    Mt 0.60 44125.50

    cum 60.30 147.63

    sqm 3.06 125.96

    sqm 128.72 223.64

    sqm 64.80 186.13

    9. Supplying, fixing and placing of centering for superstructure complete as per draw

    technical specifications clause 1002,1010,&1202

    10. Supplying, fixing and placing of centering for superstructure complete as per draw

    technical specifications clause 1002,1010,&1202

    Total

    6. Supplying, fitting and placing HYSD bar reinforcement in superstructure complete as

    MORD technical specifications clause 1002,1010,&1202

    7. Back filling behind Abutments and Wings with granular materials including cost an

    worksite, laying, handling charges and filling in layers, tamping under optimum moistu

    the maximum density including watering, with all leads for water and all other inciden

    complete as per specifications for filling behind the abutments and wings

    8. Plastering with Cement mortar 1:4 15 mm thick including cost and conveyance of

    siteincluding all other incidental charges etc; complete as per relevant standard specificati

  • 8/13/2019 Copy of Surulipatty Road

    46/52

    Amount

    4239

    16500

    172033

    990

    26140

    d ISS size HBG

    e including cost

    ete , working at

    levant standard

    d conveyance to

    complete as per

    al including cost

    formwork, soft

    epths , tools and

    ifications,clause

    and hard rock

    ost of all labour,

    ining necessary

    mps, grubs and

    clearing the site

    clause 1140 for

    d ISS size HBG

    e including cost

    ete , working at

    levant standard

  • 8/13/2019 Copy of Surulipatty Road

    47/52

    26475

    8902

    385

    28787

    12061

    296513

    ing and MORD

    ing and MORD

    er drawing and

    conveyance to

    e content to get

    tal charges etc.,

    all materials to

    ons

  • 8/13/2019 Copy of Surulipatty Road

    48/52

    Sl.No. Length Bredth Depth Contents

    Abutment 1 2 8.700 2.200 1.35 51.68

    Wings 2 2 1.500 1.900 1.35 15.39

    67.07

    cum

    Abutment 1 2 8.700 2.200 0.15 5.74

    Wings 2 2 1.500 1.900 0.15 1.71

    1 1 7.500 1.500 0.15 1.69

    9.14

    cum

    Below sill

    Abutment

    Footing 1 1 2 8.700 1.900 0.40 13.22

    Footing 2 1 2 8.300 1.600 0.40 10.62

    Footing 3 1 2 7.900 1.300 0.40 8.22

    Wings

    Footing 1 2 2 1.650 1.900 0.40 5.02

    Footing 2 2 2 1.800 1.600 0.40 4.61

    Footing 3 2 2 1.950 1.300 0.40 4.06

    Above Sill

    Abutment

    1 2 7.500 1.000 1.30 19.50

    (1.3+.7)/2

    Wings

    3. Providing and laying Cement Concrete of grade M10 Nominal Mix 1:3:6 using graded ISS size

    HBG metal including cost and conveyance of all materials to site including cost of cement at site

    including cost of formwork, soft water, labour charges for mixing, transporting, laying and curing

    concrete , working at depths , tools and plants and including all other incidental charges etc;

    complete as per relevant standard specifications clause 802,803,1202 &1203, for foundation

    DETAILED ESTIMATE

    Construction of slab culvert 2 m vent @ CH : 2950m

    Improvement of road from Cumbum To Surulipatty Road Km 0/8-3/6

    Description Nos

    1. Earthwork excavation in all classes of soil except soft rock not requiring blasting and hard rock

    requiring blasting and depositing on bank with all leads and lifts as per SS20B, including cost of all

    labour, equipments and all incidential charges such as baling our water, providing and maintaining

    necessary cofferdams, sheeting, shoring bracing and their subsequent removal, removal of all logs,

    stumps, grubs and other deleterious matter and obstructions, trimming bottom of excavation

    backfilling, and clearing the site and disposal of all surplus materials etc., complete as per relevant

    standard specification clause 1140 for foundation of abutments, wings

    2. Providing and laying Cement Concrete of grade M7.5Nominal Mix 1:4:8 using graded ISS sizeHBG metal including cost and conveyance of all materials to site including cost of cement at site

    including cost of formwork, soft water, labour charges for mixing, transporting, laying and curing

    concrete , working at depths , tools and plants and including all other incidental charges etc;

    complete as per relevant standard specifications clause 802,803,1202 &1203, for foundation

    Water way

  • 8/13/2019 Copy of Surulipatty Road

    49/52

    2 2 2.475 0.850 2.10 17.67

    Parapet 1 2 3.400 0.450 0.45 1.38

    84.30

    1 2 7.500 0.210 3.15

    sqm

    1 1 7.500 2.600 0.210 4.10

    1 2 7.500 0.700 0.200 2.10

    Dirt wall 1 2 7.500 0.400 0.210 1.26

    7.46

    Deck slab as per steel schedule 0.60

    Mt

    Wings 1 2 3.000 6.700 1.500 60.30

    cum 60.30

    1 2 3.400 0.450 3.06

    sqm 3.06

    4. Providing and fixing kraft paper full width of seating of deck slab and including cost and

    conveyance to wotksite, labour for fixing the same in corect position and all other incidental charges

    etc., complete as per standard specifications.

    9. Supplying, fixing and placing of centering for superstructure complete as per drawing and

    Deck slab

    bed block

    6. Supplying, fitting and placing HYSD bar reinforcement in superstructure complete as per

    drawing and MORD technical specifications clause 1002,1010,&1202

    7. Back filling behind Abutments and Wings with granular materials including cost and conveyance

    to worksite, laying, handling charges and filling in layers, tamping under optimum moisture content

    to get the maximum density including watering, with all leads for water and all other incidental

    charges etc., complete as per specifications for filling behind the abutments and wings

    8. Plastering with Cement mortar 1:4 15 mm thick including cost and conveyance of all materials to

    siteincluding all other incidental charges etc; complete as per relevant standard specifications

    Parapet top

    5. Vibrated Reinforced Cement Concrete of grade M 25 using ISS size HBG graded metal

    including cost and conveyance of all materials to site including cost ofcement at site including cost

    of formwork, soft water, labour charges for mixing, transporting, laying and curing concrete ,

    working at depths , tools and plants including all other incidental charges etc., complete as per

    relevant standard specifications,clause 800,1205.4, and 1205.5 for deck slab

  • 8/13/2019 Copy of Surulipatty Road

    50/52

    Above Sill

    Deck slab 1 1 7.500 1.500 11.25

    Deck slab 1 2 2.600 0.210 1.09

    Bed block 2 2 8.200 0.200 6.56

    Dirt wall 2 2 7.900 0.210 6.64

    Above Sill

    Abutment

    2 2 8.500 1.30 44.20

    Wings

    2 4 3.325 2.10 55.86

    Parapet 2 2 3.850 0.45 6.93

    132.53

    Below Sill

    Abutment

    Footing 2 2 10.600 0.40 16.96

    Footing 2 2 9.900 0.40 15.84

    Footing 2 2 9.200 0.40 14.72

    Wings

    Footing 1 2 4 1.650 0.40 5.28

    Footing 2 2 4 1.800 0.40 5.76

    Footing 3 2 4 1.950 0.40 6.24

    64.80

    MORD technical specifications clause 1002,1010,&1202

    10. Supplying, fixing and placing of centering for superstructure complete as per drawing and

    MORD technical specifications clause 1002,1010,&1202

  • 8/13/2019 Copy of Surulipatty Road

    51/52

    l. No. Unit Quantity Rate Amount

    cum 67.07 63.20 4239

    cum 9.14 1805.26 16500

    cum 84.30 2040.72 172033

    sqm 4.50 220.00 990

    cum 7.46 3504.08 26140

    3. Providing and laying Cement Concrete of grade M10 Nominal Mix 1:3:6 using graded ISS size

    HBG metal including cost and conveyance of all materials to site including cost of cement at site

    including cost of formwork, soft water, labour charges for mixing, transporting, laying and curing

    concrete , working at depths , tools and plants and including all other incidental charges etc; complete

    as per relevant standard specifications clause 802,803,1202 &1203, for foundation

    4. Providing and fixing kraft paper full width of seating of deck slab and including cost and

    conveyance to wotksite, labour for fixing the same in corect position and all other incidental charges

    etc., complete as per standard specifications.

    5. Vibrated Reinforced Cement Concrete of grade M 25 using ISS size HBG graded metal including

    cost and conveyance of all materials to site including cost ofcement at site including cost of

    formwork, soft water, labour charges for mixing, transporting, laying and curing concrete , working

    at depths , tools and plants including all other incidental charges etc., complete as per relevant

    standard specifications,clause 800,1205.4, and 1205.5 for deck slab

    1. Earthwork excavation in all classes of soil except soft rock not requiring blasting and hard rock

    requiring blasting and depositing on bank with all leads and lifts as per SS20B, including cost of all

    labour, equipments and all incidential charges such as baling our water, providing and maintaining

    necessary cofferdams, sheeting, shoring bracing and their subsequent removal, removal of all logs,stumps, grubs and other deleterious matter and obstructions, trimming bottom of excavation

    backfilling, and clearing the site and disposal of all surplus materials etc., complete as per relevant

    standard specification clause 1140 for foundation of abutments, wings

    2. Providing and laying Cement Concrete of grade M7.5 Nominal Mix 1:4:8 using graded ISS size

    HBG metal including cost and conveyance of all materials to site including cost of cement at site

    including cost of formwork, soft water, labour charges for mixing, transporting, laying and curing

    concrete , working at depths , tools and plants and including all other incidental charges etc; complete

    as per relevant standard specifications clause 802,803,1202 &1203, for foundation

    COST ESTIMATE

    Construction of slab culvert 2 m vent @ CH : 2950m

    Improvement of road from Cumbum To Surulipatty Road Km 0/8-3/6

    Description

  • 8/13/2019 Copy of Surulipatty Road

    52/52

    Mt 0.60 44125.50 26475

    cum 60.30 147.63 8902

    sqm 3.06 125.96 385

    sqm 128.72 223.64 28787

    sqm 64.80 186.13 12061

    296513

    9. Supplying, fixing and placing of centering for superstructure complete as per drawing and MORD

    technical specifications clause 1002,1010,&1202

    10. Supplying, fixing and placing of centering for superstructure complete as per drawing and MORD

    technical specifications clause 1002,1010,&1202

    Total

    6. Supplying, fitting and placing HYSD bar reinforcement in superstructure complete as per drawing

    and MORD technical specifications clause 1002,1010,&1202

    7. Back filling behind Abutments and Wings with granular materials including cost and conveyance

    to worksite, laying, handling charges and filling in layers, tamping under optimum moisture content

    to get the maximum density including watering, with all leads for water and all other incidental

    charges etc., complete as per specifications for filling behind the abutments and wings

    8. Plastering with Cement mortar 1:4 15 mm thick including cost and conveyance of all materials to

    siteincluding all other incidental charges etc; complete as per relevant standard specifications