copy of financial management

Upload: nilam9677

Post on 07-Apr-2018

221 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/4/2019 Copy of Financial Management

    1/23

    Course- GP CBM

    Course Title- Financial Manageme

    Packaging of Project

    Course No. - NCP 29

    Assignment no. - 14

    Financial Management &

    Packaging of Projects

  • 8/4/2019 Copy of Financial Management

    2/23

    Financial Management & Packaging of Project

    Page 2

    CONTENTS- Page No.

    1. INTRODUCTION 032. SCOPE OF WORKS 043. TECHNICAL STUDIES 054. COST OF CONSTRUCTION 065. THE WORK SCHEDULE 096. FINANCIAL AND ECONOMIC EVALUATION 167. PROPOSED PROJECT FINANCING 198. PROFIT MEASURES 209. REFERENCES 23

  • 8/4/2019 Copy of Financial Management

    3/23

    Financial Management & Packaging of Project

    Page 3

    INTRODUCTION-

    A Construction Contract is a contract specifically negotiated for the construction of an asset or a

    combination of Assets that are closely interrelated or interdependent in terms of their design,

    technology and function or their ultimate purpose or use (Construction Contract: IAS 11 1995)

    Managing the activities of Construction contract in a productive way produces the concept of

    Constructability. Constructability has been defined as the optimum use of construction

    knowledge and experience in planning, design, procurement, and field operations to achieve

    overall project objectives ("Constructability: A Primer" 1986). As a result of constructability, the

    quality of a constructed facility can be improved by better communication among major project

    participants such as design engineers and construction professionals. Communication among

    these participants reduces the chance of project failure and other related performance problems.

    Cost shifting is an accidental or deliberate misstatement in a contractors job cost system that

    can have a substantial impact on the contractors balance sheet and income statement. Both

    contractors and their auditors should be aware of the potential impact of shifts in job costs from

    one contract to another. The contractor should have a reliable job cost system in place to record

    contract costs accurately. The auditor should always test contract costs and look for unusual

    contract costing trends.

    Construction ContractsFinancial Management

    When a contract covers a number of assets, the construction of each asset shall be treated as a

    separate construction contract when:

    a. Separate proposals have been submitted for each asset.

  • 8/4/2019 Copy of Financial Management

    4/23

    Financial Management & Packaging of Project

    Page 4

    b. Each asset has been subject to separate negotiation and the contractor and customer have been

    able to accept or reject that part of the contract relating to each asset.

    c. The cost and revenue of each asset can be identified.

    A group of contracts whether with a single customer or with several customers, shall be treated

    as a single contract when:

    The group of projects are negotiated as a single package

    The contracts are so closely interrelated that they are, in effect, part of a single project with

    an overall profit margin

    The contracts are performed concurrently or in a continuous sequence.

    SCOPE OF WORK-

    An offer has been given by a Charitable Trust to develop and build a facility on a 10,000 sq.m of

    plot in a prime locality of Pune where 5,000 sq.m of area will be used by the trust for housing,

    health facilities for senior citizens. 5,000 sq.m. will be given free to the developers as a cost of

    development

    Cost of Land is Rs. 10,000/- sq.m

    Flooring specifications for flooring:

    - 10% Granite

    - 40% Kota stone

    - 50% Mosaic cement tiles

    Developers would like to have minimum 18% net profit on their investment. Developer can

    invest only Rs. 10 lakhs as his own funds and can raise not more than Rs. 50 lakhs as bank loan

  • 8/4/2019 Copy of Financial Management

    5/23

    Financial Management & Packaging of Project

    Page 5

    As in the given project the total area of the plot is 10000 Sq.m. In which we have to developed

    5000 sq.m. area for a trust for hosing & health facilities for senior citizens, which will be

    occupied by owner. For this development 5000 sq.m. area will be given to the developers (i.e.to

    us) as a cost of development.

    In this we have to construct a R.C.C. framed structure in which we have to provide aluminium

    sliding windows & for flooring we have to use granite, kota stone & cement tiles.

    TECHNICAL STUDIES-

    The technical study is to determine the needs for material and human means necessary to

    achieve the objectives. These take account of the market (availability of raw material, there is a

    demand, customer requirement), regulatory and standards-related product and also the financial

    (amount to invest and returns expected).

    The study focuses on two general areas: study of supply and the study of transformation. To carry

    out critical analysis of technical feasibility, there must be enough knowledge of technical,

    economic and regulatory environment.

    1. TECHNOLOGY-For the construction of above project we are going to use following technology-

    1.1. R.C.C. Framed Structure

    1.2. Granite- 10%

    1.3. Kota stone- 40%

    1.4. Mosaic cement Tiles- 50%

    1.5. Aluminium sliding Window

  • 8/4/2019 Copy of Financial Management

    6/23

    Financial Management & Packaging of Project

    Page 6

    1.6. P.C.C

    1.7. B.B.M

    1.8. Internal plaster

    1.9. External Plaster

    1.10. Waterproofing1.11. Carpentary1.12. Fittings1.13. Flooring1.14. Toilet floor & dado1.15. Flat skirting1.16. Plumbing1.17. Sanitary fixing1.18. PVC duct water line1.19. PVC duct drainage line1.20. Cleaning work

    COST OF CONSTRUCTION-

    The cost of construction includes both the initial capital cost and the subsequent operation and

    maintenance costs. Each of these major cost categories consists of a number of cost components.

    The capital cost for a construction project includes the expenses related to the initial

    establishment of the facility

    Land acquisition, including assembly, holding and improvement

  • 8/4/2019 Copy of Financial Management

    7/23

    Financial Management & Packaging of Project

    Page 7

    Planning and feasibility studies Architectural and engineering design Construction, including materials, equipment and labor Field supervision of construction Construction financing Insurance and taxes during construction Equipment and furnishings not included in construction Inspection and testing

    The operation and maintenance cost in subsequent years over the project life cycle includes the

    following expenses:

    Land rent, if applicable Operating staff Labor and material for maintenance and repairs Periodic renovations Insurance and taxes Financing costs Utilities

    The magnitude of each of these cost components depends on the nature, size and location of

    the project as well as the management organization, among many considerations. The owner is

    interested in achieving the lowest possible overall project cost that is consistent with its

    investment objectives.

  • 8/4/2019 Copy of Financial Management

    8/23

    Financial Management & Packaging of Project

    Page 8

    It is important for design professionals and construction managers to realize that while

    the construction cost may be the single largest component of the capital cost, othe r cost

    components are not insignificant. For example, land acquisition costs are a major expenditure

    for building construction in high-density urban areas, and construction financing costs

    can reach the same order of magnitude as the construction cost in large projects such as

    the construction of nuclear power plants.

    Particulars Rs./sq.ft Amount

    R.C.C. Framed Structure 4501,12,50,000/-

    Granite 952,37,500/-

    Kota stone 404,00,000/-

    Mosaic cement Tiles 15

    1,87,500/-

    Cost of Brick work, plaster etc 9022,50,000/-

    Cost of Electric work 6500/flat1,56,000/-

    Cost of Plumbing 6000/flat1,44,000/-

    Cost of Finishing 5413,50,000/-

    Labour Cost 3001,50,00,000/-

    Total3,09,75,000/-

  • 8/4/2019 Copy of Financial Management

    9/23

    Financial Management & Packaging of Project

    Page 9

    Total Cost of Construction- Rs. 3,09,75,000/-

    THE WORK SCHEDULE -

    Work Schedule represents the necessary framework to permit scheduling of construction

    activities, along with estimating the resources required by the individual work tasks, and

    any necessary precedences or required sequence among the tasks. The terms work "tasks"

    or "activities" are often used interchangeably in construction plans to refer to specific,

    defined items of work. The scheduling problem is to determine an appropriate set of activity start

    time, resource allocations and completion times that will result in completion of the

    project in a timely and efficient fashion. Construction planning is the necessary fore-

    runner to scheduling.

    In this planning, defining work tasks, technology and construction method is typically

    done either simultaneously or in a series of iterations.

    The definition of appropriate work scheduling can be a laborious and tedious process,

    yet it represents the necessary information for application of formal scheduling procedures.

    Since construction projects can involve thousands of individual work tasks, this definition

    phase can also be expensive and time consuming. Fortunately, many tasks may be repeated

    in different parts of the facility or past facility construction plans can be used as general

    models for new projects. For example, the tasks involved in the construction of a

    building floor may be repeated with only minor differences for each of the floors in the

    building.

  • 8/4/2019 Copy of Financial Management

    10/23

    Financial Management & Packaging of Project

    Page 10

    The work schedule on quarterly basis for the project is given below:

    IDOutline

    Number NameDuratio

    n Start Finish

    1 1 Contracts

    2 1.1 - Supply Lot Sale Agreement 0.00d 01/05/2011 01/05/2011

    3 1.2 - Supply Construction Agreement 0.00d 01/05/2011 01/05/2011

    4 1.3 - Supply Contract Plans 0.00d 01/05/2011 01/05/2011

    5 1.4 - Supply Contract Specifications 0.00d 01/05/2011 01/05/2011

    6 1.5 - Supply Contract Site Plan 0.00d 01/05/2011 01/05/2011

    7 1.6 - Secure Financing 0.00d 01/05/2011 01/05/2011

    8 1.7 - Construction Loan Settlement 0.00d 01/05/2011 01/05/20119 2 Document Review & Revision

    10 2.1 - Review & Finalize Plans 15.00d 02/05/2011 25/06/2011

    11 2.2 - Review & Finalize Specifications 20.00d 01/05/2011 25/06/2011

    12 2.3 - Review & Finalize Site Plan 1.00d

    Thu

    6/26/2011 26/06/2011

    13 2.4 - Print Construction Drawings 5.00d

    Thu

    7/3/2011 07/09/2011

    14 2.5 - Approve Revised Plans 0.00d

    Wed

    7/9/2011 07/09/2011

    15 2.6 - Approve Revised Specifications 0.00d

    Wed

    7/9/2011 07/09/2011

    16 2.7 - Approve Revised Site Plan 0.00d

    Wed

    7/9/2011 07/0920/11

    17 3 Site Work

    18 3.1 - Clear Lot 3.00d

    Mon

    7/28/2011 30/07/2011

    19 3.2 - Strip Topsoil & Stockpile 1.00d

    Thu

    7/31/2011 31/07/2011

    20 3.3 - Stake Lot for Excavation 1.00d

    Thu

    7/31/2011 31/07/2011

    21 3.4 - Rough grade lot 1.00d Fri 8/1/2011 08/01/2011

    22 3.5 - Excavate for foundation 2.00dMon8/4/2011

    Tue8/5/2011

    23 4 Foundation

    24 4.1 - Layout footings 1.00d

    Wed

    8/6/2011

    Wed

    8/6/2011

    25 4.2 - Dig Footings & Install Reinforcing 1.00d

    Thu

    8/7/2011

    Thu

    8/7/2011

    26 4.3 - Footing Inspection 0.00d Thu Thu

  • 8/4/2019 Copy of Financial Management

    11/23

    Financial Management & Packaging of Project

    Page 11

    8/7/2011 8/7/2011

    27 4.4 - Pour footings 1.00d Fri 8/8/2011 Fri 8/8/2011

    28 4.5 - Pin Footings 1.00d

    Mon

    8/11/2011

    Mon

    8/11/2011

    29 4.6 - Stock Block, Mortar, Sand 1.00d

    Tue

    8/12/2011

    Tue

    8/12/2011

    30 4.7 - Build Block Foundation 15.00d

    Wed

    8/13/2011

    Tue

    9/2/2011

    31 4.8 - Foundation Certification 0.00d

    Tue

    9/2/2011

    Tue

    9/2/2011

    32 4.9 - Draw #1 (Location Survey) 0.00d

    Tue

    9/2/2011

    Tue

    9/2/2011

    33 4.1 - Fill Block Cores w/ Concrete 1.00dWed9/3/2011

    Wed9/3/2011

    34 4.1 - Steel Delivery 1.00d

    Thu

    9/4/2011

    Thu

    9/4/2011

    35 4.1 - Set Lintels, Bolts, Cap Block 2.00d Fri 9/5/2011

    Mon

    9/8/2011

    36 4.1 - Waterproofing and Drain Tile 1.00d Fri 9/5/2011 Fri 9/5/2011

    37 5 Rough Carpentry 44.00d

    Tue

    9/9/2011

    Fri

    11/7/2011

    38 5.1 - Set Steel 1.00d

    Tue

    9/9/2011

    Tue

    9/9/2011

    39 5.2 - 1st Floor Deck Framing 4.00dWed9/10/2011

    Mon9/15/2011

    40 5.3 - 1st Floor Wall Framing 4.00d

    Tue

    9/16/2011

    Fri

    9/19/2011

    41 5.4 - Draw #2 (First Floor Deck) 0.00d

    Fri

    9/19/2011

    Fri

    9/19/2011

    42 5.5 - 2nd Floor Deck Framing 2.00d

    Mon

    9/22/2011

    Tue

    9/23/2011

    43 5.6 - Draw #3 (Second Floor Deck) 0.00d

    Tue

    9/23/2011

    Tue

    9/23/2011

    44 5.7 - 2nd Floor Wall Framing 3.00d

    Wed

    9/24/2011

    Fri

    9/26/2011

    45 5.8 - Set Roof Trusses 2.00d

    Mon

    9/29/2011

    Tue

    9/30/2011

    46 5.9 - Frame Roof 7.00d

    Wed

    10/1/2011

    Thu

    10/9/2011

    47 5.1 - Install Roof Plywood 5.00d

    Fri

    10/10/2011

    Thu

    10/16/2011

    48 5.1 - Install Windows & Doors 2.00d Wed Thu

  • 8/4/2019 Copy of Financial Management

    12/23

    Financial Management & Packaging of Project

    Page 12

    10/22/2011 10/23/2011

    49 5.1 - Frame Basement 3.00dFri10/10/2011

    Tue10/14/2011

    50 5.1 - Frame Basement Bulkheads 2.00d

    Thu

    11/6/2011

    Fri

    11/7/2011

    51 6 Concrete Slabs 8.00d

    Thu

    9/18/2011

    Mon

    9/29/2011

    52 6.1 - Basement Slab Preparation 2.00dThu

    9/18/2011Fri

    9/19/2011

    53 6.2 - Termite Treatment Basment Slab 1.00d

    Mon

    9/22/2011

    Mon

    9/22/2011

    54 6.3 - Slab Inspection 1.00d

    Tue

    9/23/2011

    Tue

    9/23/2011

    55 6.4 - Pour Basement Slab 1.00d

    Wed

    9/24/2011

    Wed

    9/24/2011

    56 6.5 - Prep Garage Slab 1.00d

    Thu

    9/25/2011

    Thu

    9/25/2011

    57 6.6 - Termite Treatment Garage Slab 1.00d

    Fri

    9/26/2011

    Fri

    9/26/2011

    58 6.7 - Pour Garage Slab 1.00d

    Mon

    9/29/2011

    Mon

    9/29/2011

    59 7 Plumbing Rough-in 37.00d

    Tue

    9/16/2011

    Wed

    11/5/2011

    60 7.1 - Plumbing Sub-slab 2.00d Tue9/16/2011 Wed9/17/2011

    61 7.2 - Plumbing Layout 1.00dWed

    10/29/2011Wed

    10/29/2011

    62 7.3 - Plumbing rough-in 5.00d

    Thu

    10/30/2011

    Wed

    11/5/2011

    63 8 Electric Rough-in 19.00d

    Fri

    10/24/2011

    Wed

    11/19/2011

    64 8.1 - Set Electric Boxes 2.00d

    Fri

    10/24/2011

    Mon

    10/27/2011

    65 8.2 - Install Electric Service Panel 2.00d

    Tue

    10/28/2011

    Wed

    10/29/2011

    66 8.3 - Electrical Walk-through 1.00d

    Thu

    10/30/2011

    Thu

    10/30/2011

    67 8.4 - Electrical Rough-wire 14.00d

    Fri

    10/31/2011

    Wed

    11/19/2011

    68 9 Specialty Rough-ins 5.00dThu

    11/20/2011Wed

    11/26/2011

    69 9.1 - Central Vacuum Rough-in 5.00d Thu Wed

  • 8/4/2019 Copy of Financial Management

    13/23

    Financial Management & Packaging of Project

    Page 13

    11/20/2011 11/26/2011

    70 9.2 - Alarm System Rough-in 5.00dThu11/20/2011

    Wed11/26/2011

    71 9.3 - Telephone System Rough-in 5.00d

    Thu

    11/20/2011

    Wed

    11/26/2011

    72 9.4 - Television System Rough-in 5.00d

    Thu

    11/20/2011

    Wed

    11/26/2011

    73 10 County Electrical inspection 0.00dWed

    11/26/2011Wed

    11/26/2011

    74 11 Draw #5 (Rough-ins complete) 0.00d

    Wed

    11/26/2011

    Wed

    11/26/2011

    75 12 County Framing Inspection 0.00d

    Thu

    11/27/2011

    Thu

    11/27/2011

    76 13 Roofing 68.00d

    Fri

    10/17/2011

    Tue

    1/20/2012

    77 13.1 - Roofing Paper Installed 3.00d

    Fri

    10/17/2011

    Tue

    10/21/2011

    78 13.2 - Draw #4 (Roof, windows, doors) 0.00d

    Thu

    10/23/2011

    Thu

    10/23/2011

    79 13.3 - Stock Roof Shingles 1.00d

    Fri

    10/24/2011

    Fri

    10/24/2011

    80 13.4 - Install Roof Shingles 7.00d

    Mon

    1/12/2012

    Tue

    1/20/2012

    81 14 Exterior Finishes 56.00d Fri10/24/2011 Fri 1/9/2012

    82 14.1 - Siding 3.00dFri

    10/24/2011Tue

    10/28/2011

    83 14.2 - Exterior Trim 7.00d

    Wed

    10/29/2011

    Thu

    11/6/2011

    84 14.3 - Brick Arch Forms 1.00d

    Fri

    11/7/2011

    Fri

    11/7/2011

    85 14.4 - Brick Veneer 45.00d

    Mon

    11/10/2011 Fri 1/9/2012

    86 15 Insulation 5.00d

    Fri

    11/28/2011

    Thu

    12/4/2011

    87 15.1 - Caulk & Air Seal 1.00d

    Fri

    11/28/2011

    Fri

    11/28/2011

    88 15.2 - Draft & Fire Stop 1.00d

    Mon

    12/1/2011

    Mon

    12/1/2011

    89 15.3 - Batt Insulation 3.00dTue

    12/2/2011Thu

    12/4/2011

    90 16 Floor Finishes 76.00d Tue Tue

  • 8/4/2019 Copy of Financial Management

    14/23

    Financial Management & Packaging of Project

    Page 14

    1/13/2012 4/28/2012

    91 16.1 - Ceramic Tile 15.00dTue1/13/2012

    Mon2/2/2012

    92 16.2 - Install Hardwood Floor 4.00d

    Fri

    3/27/2012

    Wed

    4/1/2012

    93 16.3 - Sand, Stain, Seal Hardwood 5.00d

    Thu

    4/16/2012

    Wed

    4/22/2012

    94 16.4 - Install Carpet 4.00dThu

    4/23/2012Tue

    4/28/2012

    95 16.5 - Final Coat Hardwood 2.00d

    Thu

    4/16/2012

    Fri

    4/17/2012

    96 17 Paint 59.00d

    Wed

    1/7/2012

    Mon

    3/30/2012

    97 17.1 - Prep Drywall for Prime Coat 2.00d

    Wed

    1/7/2012

    Thu

    1/8/2012

    98 17.2 - Prime Paint Drywall 2.00d Fri 1/9/2012

    Mon

    1/12/2012

    99 17.3 - Prep Trim for Prime Coat 2.00d

    Wed

    1/21/2012

    Thu

    1/22/2012

    100 17.4 - Prime Trim 2.00d

    Fri

    1/23/2012

    Mon

    1/26/2012

    101 17.5 - Finish Coat Trim 10.00d

    Mon

    2/23/2012 Fri 3/6/2012

    102 17.6 - Finish Coat Drywall 14.00d Mon3/9/2012 Thu3/26/2012

    103 17.7 - Caulk Exterior Windows & Doors 1.00dFri

    3/27/2012Fri

    3/27/2012

    104 17.8 - Finish Coat Exterior Trim & Siding 1.00d

    Mon

    3/30/2012

    Mon

    3/30/2012

    105 18 Interior Trim 29.00d

    Tue

    1/13/2012

    Fri

    2/20/2012

    106 18.1 - Interior Trim Delivery 1.00d

    Tue

    1/13/2012

    Tue

    1/13/2012

    107 18.2 - Install Interior Doors 5.00d

    Wed

    1/14/2012

    Tue

    1/20/2012

    108 18.3 - Install Interior Trim 15.00d

    Wed

    1/21/2012

    Tue

    2/10/2012

    109 18.4 - Install Cabinetry 5.00d

    Wed

    2/11/2012

    Tue

    2/17/2012

    110 18.5 - Install Appliances 1.00dWed

    2/18/2012Wed

    2/18/2012

    111 19 Exterior Landscaping 32.00d Mon Tue

  • 8/4/2019 Copy of Financial Management

    15/23

    Financial Management & Packaging of Project

    Page 15

    1/12/2012 2/24/2012

    112 19.1 - Rough Final Grade 1.00dMon1/12/2012

    Mon1/12/2012

    113 19.3 - Porches 5.00d

    Thu

    1/22/2012

    Wed

    1/28/2012

    114 19.4 - Sidewalks 7.00d

    Thu

    1/29/2012 Fri 2/6/2012

    115 19.5 - Decks 7.00dMon

    2/9/2012Tue

    2/17/2012

    116 19.6 - Driveways 2.00d

    Wed

    2/18/2012

    Thu

    2/19/2012

    117 19.7 - Final Grade and Seed 3.00d

    Fri

    2/20/2012

    Tue

    2/24/2012

    118 20 Electrical Final Trim 160.00d

    Thu

    6/5/2011

    Wed

    1/14/2012

    119 20.1 - Switch & Plug 2.00d

    Tue

    1/13/2012

    Wed

    1/14/2012

    120 20.2 - Install Fixtures 1.00d

    Thu

    6/5/2011

    Thu

    6/5/2011

    121 20.3 - Connect Appliances 1.00d

    Thu

    6/5/2011

    Thu

    6/5/2011

    122 21 Hardware 12.00d

    Fri

    3/27/2012

    Mon

    4/13/2012

    123 21.1 - Door Hardware 2.00d Fri3/27/2012 Mon3/30/2012

    124 21.2 - Bath Hardware 2.00dFri

    3/27/2012Mon

    3/30/2012

    125 21.3 - Mirrors 5.00d

    Tue

    3/31/2012

    Mon

    4/6/2012

    126 21.4 - Shower Doors 10.00d

    Tue

    3/31/2012

    Mon

    4/13/2012

    127 22 Cleaning 14.00d

    Fri

    3/27/2012

    Wed

    4/15/2012

    128 22.1 - Windows 3.00d

    Fri

    3/27/2012

    Tue

    3/31/2012

    129 22.2 - Rough Clean 3.00d

    Wed

    4/1/2012 Fri 4/3/2012

    130 22.3 - Final Clean 2.00d

    Tue

    4/14/2012

    Wed

    4/15/2012

    131 23 Final Walk-through 0.00dWed

    4/15/2012Wed

    4/15/2012

    132 24 Move-in 0.00d Thu Thu

  • 8/4/2019 Copy of Financial Management

    16/23

    Financial Management & Packaging of Project

    Page 16

    4/16/2012 4/16/2012

    FINANCIAL AND ECONOMIC EVALUATION-

    Capital

    - Business requires capital. The term capital is used differently in different contexts. It is

    used in the sense of means of production, usually the assets held by the firm. It is also used

    in the sense of finance obtained by a firm. In accounting, capital is used in the second

    sense. A part of the finance obtained by a firm is in the form of interest free credit,

    such as credit allowed by suppliers of materials or services and advance payment received by

    customers. The interest free credit is settled in the normal operating cycle of the business and is

    not included in the capital.

    Revenue

    Revenue is the income that arises from exchange transactions with customers in the

    course of ordinary activities of an enterprise. An entity s revenue earning activities

    include selling of goods, rende ring of services, and allowing others to use entity s

    resources yielding interest, royalties and dividends. Revenue increases the equity of the

    enterprise. As a general principle, an enterprise recognizes revenue when it receives cash,

    receivables or other consideration in its own account. For example, in an agency relationship,

    the agent recognizes the commission as revenue.

    Finance Resource mobilization

  • 8/4/2019 Copy of Financial Management

    17/23

    Financial Management & Packaging of Project

    Page 17

    Resource mobilization can facilitate the flow of resources from various sources and

    catalyze the flow of additional resources from official and private institutions. For projects

    and programs that are too large to be handled by one funding agency, mobilizing co financing

    from various funding sources can help meet these large resource requirements. Resources

    can be in any form such as finances, technology, manpower both skilled and labor,

    knowledge, information, etc

    Financial accounting

    - Financial accounting consists of recording, classifying and analyzing the business

    transactions so as to facilitate the preparation of Profit and loss account for a period and also

    the position statement (i.e. Balance Sheet) as on a particular day. Thus, the emphasis of

    financial accounting is on the ascertainment of profit and loss of the concern and not on the

    more important aspects of the business i.e. planning, control and decision-making.

    Cost accounting

    - Cost accounting analyses the transactions in an objective manner for the purposes of

    planning, control and decision making. Cost accountancy is the application of costing and

    Cost accounting principle, methods and techniques to the science, art and practice of cost

    control and the ascertainment of profitability. It includes the presentation of information

    derived there from for the purpose of managerial decision making. Cost accounting is also

    defined as the process of accounting for cost from the point at which expenditure is

    incurred or committed to the establishment of its ultimate relationship with cost centers

    and cost units.

  • 8/4/2019 Copy of Financial Management

    18/23

    Financial Management & Packaging of Project

    Page 18

    Management accounting

    - Management accounting is another aspect of accounting which has developed in recent

    years and is being employed in many concerns as an informative mechanism to aid the

    management in decision making by providing various information they need for the

    purpose. Both cost and management accounting working together can keep the management

    well informed about what is going on in the business and what changes, if any, is required to

    be given effect to.

    Capital budgeting or investment appraisal is the planning process used to determine whether a

    firm's long term investments such as new machinery, replacement machinery, new plants, new

    products, and research development projects are worth pursuing. It is budget for major capital,

    or investment, expenditures. Many formal methods are used in capital budgeting, including

    the techniques such as Accounting rate of return, Net present value, Profitability index,

    Internal rate of return, Modified internal rate of return, Equivalent annuity etc. These

    methods use the incremental cash flows from each potential investment, or project Techniques

    based on accounting earnings and accounting rules are sometimes used - though economists

    consider this to be improper - such as the accounting rate of return, and "return on

    investment." Simplified and hybrid methods are used as well, such as payback period and

    discounted payback period.

    Cash flow forecasting is in a corporate finance sense, the modeling of a company or

    assets future financial liquidity over a specific time frame. Cash usually refers to the

    company s total bank balances, but often what is forecast is treasury position which is

  • 8/4/2019 Copy of Financial Management

    19/23

    Financial Management & Packaging of Project

    Page 19

    cash plus short-term investments minus short-term debt. Cash flow is the change in cash or

    treasury position from one period to the next; in the context of the entrepreneur or manager,

    forecasting what cash will come into the business or business unit in order to e nsure that

    outgoing can be managed to as to avoid them exceeding cash flow coming in. If there is one

    thing entrepreneurs learn fast, it is to become very good at cash flow forecasting.

    PROPOSED PROJECT FINANCING-

    Capital structure refers to the way a corporation finances its assets through some combination

    of equity, debt, or hybrid securities. A firm's capital structure is then the composition or

    'structure' of its liabilities. The proposed capital structure for the project is as below:

    Capital Structure

    Asset 50,00,000.00

    Equity 1,00,000.00

    Debt 40,00,000.00

    The debt raised by the promoter is Rs 40 lacs. The total debt would not be taken all at

    once rather it would be disbursed in 4 equal quarterly installments. This debt will carry a

    fixed interest expense as follows:

    Month Amount Int. Payable Int. Payable Closing Loan bal.

    MonthAmount Int.Payble Int.Payble Closing Loan

    (Rs.) Monthly Quarterly Balance

    Apr-11 1100000 11000 1100000

    May-11 11000 1100000

    Jun-11 11000 30000 1100000

  • 8/4/2019 Copy of Financial Management

    20/23

    Financial Management & Packaging of Project

    Page 20

    Jul-11 1100000 20000 2000000

    Aug-11 20000 2000000

    Sep-11 20000 60000 2000000

    Oct-11 1100000 30000 3000000

    Nov-11 30000 3000000

    Dec-11 30000 90000 3000000

    Jan-12 1100000 40000 4000000

    Feb-12 40000 4000000

    Mar-12 40000 120000 4000000

    * Loan disbursed in 4 equal quarterly installments

    **Assuming interest @ 12% p.a.

    PROFIT MEASURES-

    A profit measure is defined as an indicator of the desirability of a project from the standpoint of

    a decision maker. A profit measure may or may not be used as the basis for project

    selection. Since various profit measures are used by decision makers for different

    purposes, the advantages and restrictions for using these profit measures should be fully

    understood..There are several profit measures that are commonly used by decision makers in

    both private corporations and public construction projects. Each of these measures is

    intended to be an indicator of profit or net benefit for a project under consideration.

    Some of these measures indicate the size of the profit at a specific point in time; others give the

    rate of return per period when the capital is in use or when reinvestments of the early profits are

    also include d. Some of the most frequently used profit measures are as follows:

    1. Net Future Value and Net Present Value

  • 8/4/2019 Copy of Financial Management

    21/23

    Financial Management & Packaging of Project

    Page 21

    When an organization makes an investment, the decision maker looks forward to the gain

    over a planning horizon, against what might be gained if the money were invested elsewhere. A

    minimum attractive rate of return (MARR) is adopted to reflect this opportunity cost of

    capital. The MARR is used for compounding the estimated cash flows to the end of the

    planning horizon, or for discounting the cash flow to the present.

    The profitability is measured by the net future value (NFV) which is the net return at the end of

    the planning horizon above what might have been gained by investing elsewhere at the MARR.

    The net present value (NPV) of the estimated cash flows over the planning horizon is

    the discounted value of the NFV to the present. A positive NPV for a project indicates the

    present value of the net gain corresponding to the project cash flows.

    2. Internal Rate of Return

    The internal rate of return (IRR) is defined as the discount rate which sets the net present value

    of a series of cash flows over the planning horizon equal to zero. It is used as a profit measure

    since it has been identified as the "marginal efficiency of capital" or the "rate of return

    over cost". The IRR gives the return of an investment when the capital is in use as if the

    investment consists of a single outlay at the beginning and generates a stream of net benefits

    afterwards. However, the IRR does not take into consideration the reinvestment

    opportunities related to the timing and intensity of the outlays and returns at the intermediate

    points over the planning horizon. For cash flows with two or more sign reversals of the

    cash flows in any period, there may exist multiple values of IRR; in such cases, the

    multiple values are subject to various interpretations.

  • 8/4/2019 Copy of Financial Management

    22/23

    Financial Management & Packaging of Project

    Page 22

    3.If the financing and reinvestment policies are incorporated into the evaluation of a project,

    an adjusted internal rate of return (AIRR) which reflects such policies may be a useful

    indicator of profitability under restricted circumstances. Because of the

    complexity of financing and reinvestment policies used by an organization over the life

    of a project, the AIRR seldom can reflect the reality of actual cash flows. However, it

    offers an approximate value of the yield on an investment for which two or more sign

    reversals in the cash flows would result in multiple values of IRR. The adjusted internal rate of

    return is usually calculated as the internal rate of return on the project cash flow modified so

    that all costs are discounted to the present and all benefits are compounded to the end of the

    planning horizon.

    4. Return on Investment

    When an accountant reports income in each year of a multi-year project, the stream of cash

    flows must be broken up into annual rates of return for those years.

    The return on investment (ROI) as used by accountants usually means the accountant's rate

    of return for each year of the project duration based on the ratio of the income (revenue

    less depreciation) for each year and the un-depreciated asset value (investment) for that same

    year. Hence, the ROI is different from year to year, with a very low value at the early years and a

    high value in the later years of the project.

    5. Payback Period

    The payback period (PBP) re fers to the length of time within which the benefits received

    from an investment can repay the costs incurred during the time in question while ignoring the

  • 8/4/2019 Copy of Financial Management

    23/23

    Financial Management & Packaging of Project

    Page 23

    remaining time periods in the planning horizon. Even the discounted payback period indicating

    the "capital recovery period" does not reflect the magnitude or direction of the cash flows

    in the remaining pe riods. However, if a project is found to be profitable by other measures, the

    payback period can be used as a secondary measure of the financing requirements for a

    project.

    REFERANCES-

    Text book of NICMAR on Financial management.