COORDINATED AUDIT OF THE FUNDS
EARMARKED FOR THE FUNDING OF
PROJECTS IMPLEMENTED WITHIN THE
OPERATIONAL PROGRAMME CROSS-
BORDER COOPERATION THE CZECH
REPUBLIC – POLAND 2007–2013
Iwona Zyman, Director of the Regional Branch in Opole SUPREME AUDIT OFFICE OF POLAND
www.nik.gov.pl Vilnius, 9-11.09.2014
EUR 258 187 467 was allocated for the
implementation of the Operational
Programme.
This amount included the contribution of
EU funds (ERDF funds) in the total
amount of EUR 219 459 344 (85%)
which must be settled by the end of
2015.
The funding was granted on condition
that organisations from both sides of the
border, such as regional authorities,
universities and small and medium
enterprises, come together to implement
projects based on the needs of the
border region.
ilustracja
Iwona Zyman, Director of the Regional Branch in Opole SUPREME AUDIT OFFICE OF POLAND
www.nik.gov.pl Vilnius, 9-11.09.2014
Audit Objectives and Scope
The Agreement of Cooperation between the Czech Supreme Audit Office
(NKU) and the Supreme Audit Office of Poland (NIK).
Parallel audit.
Compliance audit with elements of performance audit.
Iwona Zyman, Director of the Regional Branch in Opole SUPREME AUDIT OFFICE OF POLAND
www.nik.gov.pl Vilnius, 9-11.09.2014
Audit Objectives and Scope
Implementation of Programme in accordance with legal regulations and
with obligatory programme documents or agreements.
Reliability of management and control system.
Achievement the objectives of the Operational Programme.
Implementation of selected projects in accordance with the obligatory
criteria set in the grant agreements or decisions.
Iwona Zyman, Director of the Regional Branch in Opole SUPREME AUDIT OFFICE OF POLAND
www.nik.gov.pl Vilnius, 9-11.09.2014
Audit Objectives and Scope
The selected joint audit sample included six projects.
The NKU conducted audits of 13 other projects.
The NIK conducted audits of two additional projects.
The financial means paid to beneficiaries from the ERDF that were audited
by NKU and NIK amounted to EUR 25 362 174 and EUR 8 450 784.
Iwona Zyman, Director of the Regional Branch in Opole SUPREME AUDIT OFFICE OF POLAND
www.nik.gov.pl Vilnius, 9-11.09.2014
The main audit conclusion
The level of identified irregularities did not exceed the materiality threshold.
The implementation of the OP CBC CZ-PL, including the management and
control system performance and the realization of selected projects, was
successful.
Effectiveness of the operations carried out within the Operational
Programme is a high level.
Iwona Zyman, Director of the Regional Branch in Opole SUPREME AUDIT OFFICE OF POLAND
www.nik.gov.pl Vilnius, 9-11.09.2014
Audit on Polish side
Beneficiaries audit was the basis for the assessment of the level of set
objectives achievement (output and effects), as well as regularity audit
of project activities.
The Polish partners spent PLN 45 821 001 for the project
implementation, out of which PLN 34 851 827 (76,1%) was subject to
funding.
The expenses that were audited by NIK amounted to PLN 44 798 821
(97,8%).
Iwona Zyman, Director of the Regional Branch in Opole SUPREME AUDIT OFFICE OF POLAND
www.nik.gov.pl Vilnius, 9-11.09.2014
Audit on Polish side
The legality and regularity of transactions underlying the accounts:
Eligibility of underlying transactions - eligibility criteria are met for the
various transactions.
Completeness and accuracy of accounting - all transactions are
accounted for, are not included more than once, and are recorded in
the correct accounting period and at correct value.
Iwona Zyman, Director of the Regional Branch in Opole SUPREME AUDIT OFFICE OF POLAND
www.nik.gov.pl Vilnius, 9-11.09.2014
Audit on Polish side
The materiality threshold set jointly with the Czech Supreme Audit Office
(2%).
Failure to confirm the irregularities by the Comptroller in the project
execution that were possible to be revealed (depending on audit type).
Prolixity in the entity’s activity connected to the OP CBC execution.
Inclusion of false information into the documents.
No compliance with Public Procurement Law that influenced the choice
of contractors.
Iwona Zyman, Director of the Regional Branch in Opole SUPREME AUDIT OFFICE OF POLAND
www.nik.gov.pl Vilnius, 9-11.09.2014
Audit on Polish side
Elements of a system of quality control.
Audit Programme.
Audit sampling.
Checklist/Questionnaire for public procurement .
Supervision and coordination.
Iwona Zyman, Director of the Regional Branch in Opole SUPREME AUDIT OFFICE OF POLAND
www.nik.gov.pl Vilnius, 9-11.09.2014
Analysis of project effects
The survey - 2 820 people
Eight discussion panels – 122 people
Iwona Zyman, Director of the Regional Branch in Opole SUPREME AUDIT OFFICE OF POLAND
www.nik.gov.pl Vilnius, 9-11.09.2014
The survey
ilustracja
Iwona Zyman, Director of the Regional Branch in Opole SUPREME AUDIT OFFICE OF POLAND
www.nik.gov.pl Vilnius, 9-11.09.2014
General assessment of audited activity
The NIK evaluated positively despite confirmed irregularities the
implementation of the Programme, including the functioning of
management and control system and the execution of selected
projects.
Iwona Zyman, Director of the Regional Branch in Opole SUPREME AUDIT OFFICE OF POLAND
www.nik.gov.pl Vilnius, 9-11.09.2014
wykres
Nazwisko autora/Departament SUPREME AUDIT OFFICE OF POLAND
www.nik.gov.pl Vilnius, 9-11.09.2014
For more information visit:
www.nik.gov.pl
www.nku.cz
www.cz-pl.eu/pl