controls system installation status
DESCRIPTION
Controls System Installation Status. Ernest Williams for Controls Department. Outline. LCLS Control System Installation Project Staff and Assignments Schedule & the Process Cable Plant, racks and other infrastructure I&C Systems status and schedule Software Status Issues & Concerns - PowerPoint PPT PresentationTRANSCRIPT
Ernest Williams
FAC November 2008
Control Systems Software Section1
Controls SystemInstallation Status
Ernest Williams
for
Controls Department
Ernest Williams
FAC November 2008
Control Systems Software Section2
Outline
LCLS Control System Installation Project Staff and Assignments
Schedule & the Process
Cable Plant, racks and other infrastructure
I&C Systems status and schedule
Software Status
Issues & Concerns
Summary
Ernest Williams
FAC November 2008
Control Systems Software Section3
Project StaffDedicated LCLS Control System Deputy (E. Carrone) to help drive the project. E. Williams: Installation Manager.M. De Salvo: Coordination Manager.Each subsystem “owned” by a System Lead, responsible for schedule, resources and costs.Additional support provided by services from PCD.
Cable Shops and Fab Shops.
Controls Coordination Forum: every Thursday at 9.00 am.
Ernest Williams
FAC November 2008
Control Systems Software Section4
Plans & Process for LCLS Controls System Installation
Controls installation takes place in several steps:Design, documentation, procurement and Installation of the cable plant including long haul DC and I&C cablesCables termination and connection to beam line components (Mechanical Systems)Procurement & preparation of electronics racksInstallation of electronics chassis and modules including crates, IOCs, networks & timing modules in the racksRack installation in the field, AC & cable plant connection
Cable Plant Design & Installation Process
From the list of devices to be installed…
Develop racks layout & cable tray designGenerate rack profiles for electronics modulesIdentify DC & I&C cabling requirements & document in CAPTAR
Produce installation bid package from CAPTAR and tray designsGenerate installation bid package & award contractProcure trays, cables, connectors, etc.Install cable plant and terminate to beam line components
The readiness status of each Controls Subsystem is tracked weekly
SYSTEM System EngineerRack
ProfileEI
DiagramCable
CodingProcure-
ments
MAGNET Bellomo, De Lira 100% 99% 99% 85%
FEE SYSTEMS Bill Abraham 99% 40% 45% ?%
VACUUM Boyes 100% 75% 98% 90%
BEAM LOSS MON. Krejcik 100% 100% 100% 0%
OTR, YAG, TDUND Peng 100% 70% 100% 100%
COLL, WIRE SCAN Alarcon 100% 40% 99% 90%
BPM Johnson 90% 90% 99% 90%
TOROID Peng 100% 90% 100% 100%
TIMING Krejcik, Dusatko 80% 10% 95% 100%
NETWORKS Lahey 100% 40% 100% 65%
ADS Peters, Gassner 80% 50% 100%
MPS Norum, Tilgman 100% 100% 100% 60%
BCS Bennett 100% 60% 100% 90%
LION Tilghman/ Bennett 100% 0% 100% 100%
PPS P. Bong 100% 100% 100% 75%
TCs, TRP Tilghman 100% 100% 100% 95%
Flow SWITCHES (general)
ALL 50% 50% 50%
TRUNKS Di Salvo 100% 100%
I&C CABLE PLANT DiSalvo 100%
ConnectorsDC CABLES, TRAYS Rodriguez/RogersRACKS Di Salvo 100%
CRATES Di Salvo 100%
IOCS Alarcon 100%
MAJOR PROCUREMENTS
LCLSControls System Installation
The readiness status of all controls racks are reviewed weekly (sheet on SharePoint)
Rack Profiles on SharePoint
For each I&C rack we track the equipment to be installed in each “row”
Green – Installed
Yellow – Not installed, but there are no issues
Red – Cause for concern
Controls Installation Schedule Overview
LTU/Undulator/e-DumpControls Installation
Overview
Ernest Williams
FAC November 2008
Control Systems Software Section10
Control System Cable Plant & Racks
Nearly 100% of cable plant is installed and terminated.All Instrumentation Racks are installed and operational
Ernest Williams
FAC November 2008
Control Systems Software Section11
Control System Crates & IOCs, Modules
VME Crates are all installed and operational
All IOCs are installed and operational
We are in the end-to-end checkout phase
There are currently no anticipated major delays in completing most of the pre-beam checkout.
Ernest Williams
FAC November 2008
Control Systems Software Section
IOCs
Large number of IOCs running reliably for LCLS Accelerator
136 Coldfire-based embedded IOCsMainly used for BPM and LLRF front-end processors
104 MVME6100 IOCs33 MVME3100 IOCs
Beamlines will also use some number RTEMS-based IOCs for Slow controls
Ernest Williams
FAC November 2008
Control Systems Software Section13
Magnet Power Supply Control
Magnet Control System ready to support end-to-end checkout
Alarm Handler, SCORE, ChannelWatcher and Archiver configs are ready
Ernest Williams
FAC November 2008
Control Systems Software Section14
Safety SystemsSeparate talks later today on Safety Systems
BCSMature designProject is on schedule
PPSThe Initial Acceptance Test of the Undulator Complex has been executed.New documentation control process in place
Ernest Williams
FAC November 2008
Control Systems Software Section
MPS Systems
MPSConcurrently developing new LCLS MPSResponse time of less than one pulse at 120 HzNew hardware extended 1.2 km past current MPS
Non-CAMACReady for photon section
Pre-beam checkout will begin mid November
Ernest Williams
FAC November 2008
Control Systems Software Section16
NetworksAccelerator Network Infrastructure supports I&C Ethernet and MPSThe project consists of:
Network architecture designCable Plant Davis Bacon Phase IV & Phase V ContractsFiber Termination Contract
e-Controls networks Integrate with other networks:Undulator Alignment Diagnostics System NetworkConventional FacilitiesPhoton SectionsSLAC Scientific Computing and Computing Services (SCCS) centralized networking groups are helping with all networksNew network tech hired on to support Terri Lahey
Ernest Williams
FAC November 2008
Control Systems Software Section17
Network Design
Accelerator Switches reside in service buildings 911, 912, 913 and 921, and FEE Undulator accelerator switches are in service buildings B913 & B921 to reduce heat-loadThe network consists of Cat6 long hauls between service building patch panels and cat6 boxes at racksTunnel walkup stations: one each COW and wireless accessOther IOCs are located in service buildings: MPS, BPM, etc.Fiber Trunks support Ethernet switches and MPS
Ernest Williams
FAC November 2008
Control Systems Software Section18
Davis Bacon & Fiber Contracts
Phase IV: install and test cat6 long hauls
Phase V: fiber pull
Fiber Termination Contractterminate and test fibers for e-beam, photon, & timing
SCCS/Lahey created contract using knowledge/process learned from BC2 fiber termination contract
Ernest Williams
FAC November 2008
Control Systems Software Section19
Networks Procurements
Fiber trunks purchased
The order for network switches is in purchasing
DIGI terminal servers have been ordered
Patch panels have been ordered
Remaining: fiber jumpers and FODU (Fiber Optic Distribution Units)
Ernest Williams
FAC November 2008
Control Systems Software Section20
Timing System
The scope is to deliver triggers and timestamp data to all subsystems requiring such. The system can be split into two parts
Long-haul distribution of triggers from the EVG to EVRs in LTU and beyondShort-haul back end consisting of the HW & SW to receive the EVG timing signal and generate triggers. This is the extension of the timing for BC2
We have a procurement for the "back end" of the timing system consisting of all the HW (fan-outs, EVRs, crates, cables) to deliver triggers to the end subsystem.
Ernest Williams
FAC November 2008
Control Systems Software Section21
Beam Diagnostics
Profile Monitors:OTR30 and OTR33 installed and checked out. Waiting on air from Central Facilities
OTRDMP controls are ready but device will be installed in the tunnel this week. End-to-End checkout follows.
YAGXRAY controls is in progress. Waiting on fiber pull this week.
TOROIDs (Controls are ready):IM31 (system checkout complete)
IM36 (system checkout complete)
IMUNDO (waiting on cable termination)
IMUNDI (waiting for device installation and cable termination this week.)
IMDMP (waiting on cable termination)
Ernest Williams
FAC November 2008
Control Systems Software Section
Beam Diagnostics (Cont’d)
BPMsAll new Stripline BPMs controls pre-beam checkout completeCavity BPM controls pre-beam checkout in progress.Cavity BPM Calibration software is now in development.
Ernest Williams
FAC November 2008
Control Systems Software Section
Beam Diagnostics (Cont’d)
Alignment Diagnostic System (ADS)Interface to EPICS in good shape undergoing checkout
Ernest Williams
FAC November 2008
Control Systems Software Section
Facilities
HVACEPICS Interface complete and undergoing checkout.
Chiller/BoilerEPICS Interface complete and undergoing checkout
LCWEPICS Interface complete and undergoing checkout
Ernest Williams
FAC November 2008
Control Systems Software Section25
Vacuum
Vacuum Pump ControllersVacuum Guage ControllersVacuum Valve ControllersPLCs for interlocks and controlCabling and ConnectorsDrawing and documentation in progress and in good shape.
Ernest Williams
FAC November 2008
Control Systems Software Section26
Controls Subsystem Risk Matrix
System Risk
Magnet Power Supply control In good shapeRacks, Crates, IOC CompleteVacuum Control In good shapePPS, BCS In good shapeMotion Control In good shapeOTR/YAG In good shapeNetworks CompleteCavity BPM ADC New designMPS New designBPM New designUndulator Control Handover ConcernsCable Plant Complete
Ernest Williams
FAC November 2008
Control Systems Software Section27
Test Plan and Risk Analysis
Ernest Williams
FAC November 2008
Control Systems Software Section28
Testing & Checkout Strategies
Rack loading & testingWill accomplish as much as possible in B024 prior to transporting racks to the field.
In-field loading (Davis-Bacon) and intra-rack cabling is less efficient.
Networks and Timing will be the first system to be made operational in field to allow booting of IOCs and testing
Ernest Williams
FAC November 2008
Control Systems Software Section29
Rack Assembly Area (B024 )
B913 & B921 PS racks
B911 & B912 PS racks
Ernest Williams
FAC November 2008
Control Systems Software Section30
Procedure for AC Power Release to Rack Systems
Purpose: To provide for safe AC power application to the individual rack distribution systems (plug molds, outlets, breaker panels, ect.) and equipment in the racks
Constraints: Ensure that with the application of AC power to each rack no electrical hazards are created via rack equipment, cable plant or conductors (either within or leaving the rack).
ProcedureIdentify/list all potential hazards, correct or neutralize any potential electrical hazard, request and receive approval from LCLS Controls Manager and the LCLS Installation Manager (R. M. Boyce) for the release/application of AC power to identified rack.Once approval is given appropriate breakers will be unlocked and control of breakers turned over to responsible system engineer.
Ernest Williams
FAC November 2008
Control Systems Software Section31
PP-7 After Contractor Turn-over & LCLS Safety Lockout
PP-6 After Contractor Turn-over & LCLS Safety Lockout
Ernest Williams
FAC November 2008
Control Systems Software Section32
Rear of Racks LKG-03 thru LKG-10 (12/05/06)
Ernest Williams
FAC November 2008
Control Systems Software Section33
Software Installation StatusAll IOCs have loaded their software from a central EPICS file server. The server is ready to support pre-beam checkout and commissioning.All controls software will be installed and checked out according to a “signed off” test plan.Alarm Handler, Archiver, autosave/channelWatcher, Channel Access Security, and SCORE ready to support pre-beam checkout and commissioningSoftware has been installed following the LCLS software RELEASE procedure.
Ernest Williams
FAC November 2008
Control Systems Software Section34
Issues & Concerns
Schedule & ResourcesControls is the systems “integrator” – delays in other systems directly impact our installation. This has been the case in the Injector and BC2 installation phases
Support of operations while completing final installation and pre-beam checkout of LTU/UND/EDMPSystem Functionality
The new MPS – pre-beam checkout will be tight
Ernest Williams
FAC November 2008
Control Systems Software Section35
Summary
Controls in general is in good shape for 2008 installation No major design or production issues dominate the planThere are concerns about the transfer of systems from ANL to SLAC.
We will use BLMs from PEP (Thanks to Alan Fischer)
We have received a draft “HandOver” and a draft “Detailed Software Design Document” plan from ANLA large number of sub-systems have been installed and pre-beam checkout is the major activity before Dec. 1, 2008