controls global group tasks

32
A U.S. Department of Energy Office of Science Laboratory Operated by The University of Chicago Argonne National Laboratory Office of Science U.S. Department of Energy Controls Global Group Tasks John Carwardine Feb 8, 2006

Upload: gloria-mendoza

Post on 04-Jan-2016

18 views

Category:

Documents


1 download

DESCRIPTION

Controls Global Group Tasks. John Carwardine Feb 8, 2006. Focus on three areas…. Develop a reference design and costing for RDR The high priority activity of GDE in 2006. Continue to develop the baseline design Pursue key R&D activities - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Controls Global Group Tasks

A U.S. Department of EnergyOffice of Science LaboratoryOperated by The University of Chicago

Argonne National Laboratory

Office of ScienceU.S. Department of Energy

Controls Global Group Tasks

John CarwardineFeb 8, 2006

Page 2: Controls Global Group Tasks

2

Pioneering Science andTechnology

Office of Science U.S. Department

of Energy

Focus on three areas…

• Develop a reference design and costing for RDR- The high priority activity of GDE in 2006.

• Continue to develop the baseline design

• Pursue key R&D activities- LLRF development at various test stands (TTF, ILCTA, etc)- RF phase / timing distribution- High Availability

Page 3: Controls Global Group Tasks

3

Pioneering Science andTechnology

Office of Science U.S. Department

of Energy

Continue to develop the baseline design and BCD

Page 4: Controls Global Group Tasks

4

Pioneering Science andTechnology

Office of Science U.S. Department

of Energy

Instrumentation & Control outline in BCD

• 11.1 Controls Standard Architecture

• 11.2 Timing System

• 11.3 Diagnostic Interlock Layer

• 11.4 Global Network

• 11.5 Machine Protection

• 11.6 Low level RF

• 11.7 Feedback

• 11.8 Integration with Instrumentation

• 11.9 Machine Detector Interface

• 11.10 Instrumentation – Beam position monitors

• 11.11 Instrumentation – Beam profile monitors (transverse)

• 11.12 Instrumentation – Longitudinal

• 11.13 Instrumentation – other (intensity, loss, ring)

Page 5: Controls Global Group Tasks

5

Pioneering Science andTechnology

Office of Science U.S. Department

of Energy

Control system architecture in BCD…

Page 6: Controls Global Group Tasks

6

Pioneering Science andTechnology

Office of Science U.S. Department

of Energy

Issues arisen from BCD Comments

• Comments received from Toge, Lockyer, Himel

• Communicate to technical system and accelerator area leaders the implications of ATCA and Control System High Availability.

• Change baseline design from VME/VXI to ATCA.

• Address failure modes for the rf phase reference distribution system (phase jumps).

• We need more diagrams to communicate what the control system will look like (being done…)

Page 7: Controls Global Group Tasks

7

Pioneering Science andTechnology

Office of Science U.S. Department

of Energy

Main tasks still to do (BCD)

• To be addressed by BCD section authors…- Update other BCD sections in response to comments.- Expand LLRF and feedback sections.- Respond to comments from Himel, Toge, Lockyer (written)- New summary has been written.- Submit case for ATCA instead of VME/VXI.- Submit updated BCD to CCB before Bangalore.

• To be addressed by the Controls Topic Groups…- Understand requirements from accelerator areas.- Continue to develop control system design details.- Apportion the RF performance requirements across the

subsystems.

Page 8: Controls Global Group Tasks

8

Pioneering Science andTechnology

Office of Science U.S. Department

of Energy

Controls Topic Groups

• CONTROLS INTEGRATION (overall integration)- Carwardine (ANL), Simrock (DESY), Michizono (KEK), Mcbride (FNAL)

• CONTROL SYSTEM ARCHITECTURE- Saunders (ANL), Clausen (DESY), Rehlich (DESY), Votava (FNAL)

Rechenmacher, Pavlicek (FNAL), Furukawa (KEK)

• DATA ACQUISITION / CONTROL- Wendt (FNAL), Votava (FNAL)

• HIGH AVAILABILITY- Larsen (SLAC), Downing (SLAC), Lenkszus (ANL), Saunders (ANL).

• CONTROLS / INSTRUMENTATION INTEGRATION- Wendt (FNAL)

Page 9: Controls Global Group Tasks

9

Pioneering Science andTechnology

Office of Science U.S. Department

of Energy

Controls Topic Groups (2)

• LLRF- Nageitsev (FNAL), Cancelo (FNAL), Carcagno (FNAL), Chase (FNAL), Simrock

(DESY), Michizono (KEK), Lockyer (U.Penn)

• TIMING AND RF PHASE REFERENCE DISTRIBUTION- Lenkszus (ANL), Frisch (SLAC), Pavlicek (FNAL), Matsumoto (KEK)

• MACHINE PROTECTION SYSTEM- Ross (SLAC), Lenkszus (ANL)

• BEAM-BASED FEEDBACK- Burrows (U. Oxford), Carwardine (ANL), Lebrun (FNAL), White (U. Oxford)

Page 10: Controls Global Group Tasks

10

Pioneering Science andTechnology

Office of Science U.S. Department

of Energy

Instrumentation Topic Groups

• BEAM POSITION MONITORS:- Smith (SLAC), Wendt (FNAL), Baboi (DESY)

•BEAM PROFILE MONITORS - LASERWIRE:

- Blair (RHUL), Urakawa (KEK)

• BEAM INTENSITY MONITORS, BEAM LOSS MONITORS:- TBA

• BUNCH LENGTH MONITORS:- Ross (SLAC)

• SPECIAL INSTRUMENTATION:- Ross (SLAC), KEK physicist

Page 11: Controls Global Group Tasks

11

Pioneering Science andTechnology

Office of Science U.S. Department

of Energy

Pursue key R&D activities

Page 12: Controls Global Group Tasks

12

Pioneering Science andTechnology

Office of Science U.S. Department

of Energy

LLRF development

• FNAL, DESY, KEK already actively pursuing this with regard to test stands (ILCTA, TTF, ATF-2, etc)

• [Feb 9-10th workshop]

• Should determine how we can best integrate the test stands into other controls related development activities.

Page 13: Controls Global Group Tasks

13

Pioneering Science andTechnology

Office of Science U.S. Department

of Energy

Timing / RF phase reference distribution

Various issues discussed at Jan 19-20 meeting, including…

• Evaluate and demonstrate various options- Trench test of fiber system (vs coil in oven)- Sector test – the copper part (local distribution).- Two-channel receiver comparator scheme- Low-cost way of building a vcxo with sufficient performance?- “To chop or not to chop”

• Different schemes to meet the bunch compressor requirements.

• Failure modes and effects analysis.

• Pursue HOM phase detector scheme.

Page 14: Controls Global Group Tasks

14

Pioneering Science andTechnology

Office of Science U.S. Department

of Energy

Feedback development issues

Various issues discussed at Jan 19-20 meeting, including…

• How do the beam-based feedback systems deal with exceptions?- Startup, beam loss, MPS trip, etc- Detecting and handing bad sensors or actuators.

• Integrated simulation of LLRF and beam-based feedback.• Interplay between the various feedbacks and feed-forwards?

• How does beam-based feedback help the rf specs?

• How many intra-train feedbacks do we have, and how many pulses do they collectively take to converge?

• Should beam trajectory feedback be several individual loops or a single global system?

Page 15: Controls Global Group Tasks

15

Pioneering Science andTechnology

Office of Science U.S. Department

of Energy

High Availability control system demo

• R&D Roadmap (starting point)

- Claude’s proposal- ATCA + EPICS iocCore + shelf manager + ICE middleware- Claude to set up discussion with interested parties.- Develop an AMC module to plug in / integrate with Claude’s ATCA

crate.

- How do we utilize the test stands (ILCTA, ATF, TTF)? Feb 9/10 Fermilab mtg

Page 16: Controls Global Group Tasks

16

Pioneering Science andTechnology

Office of Science U.S. Department

of Energy

Develop a reference design and costing for RDR

Page 17: Controls Global Group Tasks

17

Pioneering Science andTechnology

Office of Science U.S. Department

of Energy

RDR Design Matrix

Page 18: Controls Global Group Tasks

18

Pioneering Science andTechnology

Office of Science U.S. Department

of Energy

“Charges for RDR Leaders” memo of 1/12/06

[see Ray Larsen’s table]

Page 19: Controls Global Group Tasks

19

Pioneering Science andTechnology

Office of Science U.S. Department

of Energy

Guidance for costing exercise

• High level guidance- Expected margin of error for control system costing is +/-30%.- Focus first on overall ILC cost drivers first.- DCB looking for resolution of a few x 0.1% (~$50M).- Priority should be on a top-down rather than bottom-up costing.- Use what has already been done for NLC, TTR, USLCTOS, etc- The RDR is not a detailed design document.- Need to include ‘everything’

• We need to know what to cost and how many…

Page 20: Controls Global Group Tasks

20

Pioneering Science andTechnology

Office of Science U.S. Department

of Energy

Baseline is a High Availability control system…

• Front-end hardware- Switch from VME to ATCA in baseline for RDR.- Need to know what needs hardware redundancy at front-end.

• Servers etc- Need to budget for HA relational databases, software, central

computing, data archivers, etc- Central computing + archiving + data backups, etc is part of

controls domain. MIS computing is not.

• Control system- We will provide infrastructure for implementing HA functionality.- We have to make the middleware reliable (especially).- Cost will be in implementing the recovery policies.- To what level do we go with HA software in the various layers?

Page 21: Controls Global Group Tasks

21

Pioneering Science andTechnology

Office of Science U.S. Department

of Energy

Main tasks to do (RDR and costing)

• Develop WBS structure for Controls and LLRF.

• Collect baseline info from accelerator areas.

• Develop Control System and LLRF block diagrams.

• Generate Excel spreadsheet of line items for costing exercise.

• Meet RDR deliverables, as listed in the “Charge to RDR Leaders” memo.

• Prepare for LLRF and Controls reviews in April/May.

• Issue: an apparent lack of availability of people to work on RDR.

Page 22: Controls Global Group Tasks

22

Pioneering Science andTechnology

Office of Science U.S. Department

of Energy

Immediate tasks

• Continue to develop the integrated control system diagram.

• Develop an RF/LLRF block diagram of each accelerator area (linac is the most important to do first)- How many I/O + DAQ channels.- How many relay racks.- Cable plant.

• Develop a controls block diagram for each accelerator area- How many I/O + DAQ channels.- How many relay racks.- Show interfaces to LLRF, Instrumentation, Timing, MPS, etc- Cable plant.

Page 23: Controls Global Group Tasks

23

Pioneering Science andTechnology

Office of Science U.S. Department

of Energy

Control System WBS outline

• Global Control System - <List of global systems>

- <Control system line items>

• <Accelerator Areas>- <Technical Systems>

- <Control System line items>- RF System

- <LLRF line items>- <Control System line items>

• We need information from the area and technical leaders to complete the Controls WBS for the accelerator areas.

Page 24: Controls Global Group Tasks

24

Pioneering Science andTechnology

Office of Science U.S. Department

of Energy

Control System WBS (Global level)

• Global level (starting point)- Central computing- Networking infrastructure- Timing system / RF phase reference.- Central MPS- Personnel Protection System- Control Room(s)- Data archiving- Control System Software development- Installation / commissioning

• Aim to develop a structure with nodes that can be costed and that can be cloned as needed.

Page 25: Controls Global Group Tasks

25

Pioneering Science andTechnology

Office of Science U.S. Department

of Energy

Requirements gathering exercise

• Plan:- Appoint two points of contact (POC) for each of the six

accelerator areas: one for LLRF; one for the Control System.- Appoint one POC for each of the five global groups.

• Goals:- Get a broad-brush understanding of the scope of the control

system requirements to be able to cost the control system.- Create building-blocks for the RDR costing exercise.- Help establish treaty points.

• Initial deliverables from each Point of Contact- Block diagram showing functions and basic geographic layout.- Estimate of number of I/O channels and data rates.

Page 26: Controls Global Group Tasks

26

Pioneering Science andTechnology

Office of Science U.S. Department

of Energy

Proposal for accelerator area POCs

E- source E+ source Damping Ring

RTML Linac BDS

LLRF

Controls

Page 27: Controls Global Group Tasks

27

Pioneering Science andTechnology

Office of Science U.S. Department

of Energy

Integrated control system block diagrams

• We should develop a hierarchy of block diagrams for the integrated control system- Integrated control system functional diagram (Ned’s diagram)- Block diagram of each global subsystem

- Timing, MPS, archiving, central control system, etc, etc- Block diagram of each accelerator area control system

- E-, E+, DR, RTML, Linac, BDS- Block diagram of each accelerator area LLRF system

- E-, E+, DR, RTML, Linac, BDS- Beam-based feedback.- Hardware/geographic and software centric views.

• Each block becomes a node on the WBS.

Page 28: Controls Global Group Tasks

28

Pioneering Science andTechnology

Office of Science U.S. Department

of Energy

ICS Functional Diagram“Ned’s Diagram” (2/1/06 revision)

Page 29: Controls Global Group Tasks

29

Pioneering Science andTechnology

Office of Science U.S. Department

of Energy

ICS Functional Diagram (detail)

Page 30: Controls Global Group Tasks

30

Pioneering Science andTechnology

Office of Science U.S. Department

of Energy

Cryo section block diagram

Page 31: Controls Global Group Tasks

31

Pioneering Science andTechnology

Office of Science U.S. Department

of Energy

Summary: RDR action items

• Identify Points of Contact for accelerators and global groups

• POCs develop LLRF and controls block diagrams for each accelerator area.

• Develop the controls story for Bangalore.

• Develop a costable WBS for Controls and LLRF.

• Define costing procedures.

• Prepare for first review in April/May timeframe.

Page 32: Controls Global Group Tasks

32

Pioneering Science andTechnology

Office of Science U.S. Department

of Energy

We need a pitch for Bangalore…

• Strategy for completing the RDR task- Management, technical, etc

• How we see things coming together.

• What we need from the area, technical, and global groups.

• R&D issues for controls and LLRF.