Consult Your Doctor Before It Hurts

+

The ABC’s of Delay Claims

Duncan W. Glaholt

Page 2: Consult Your Doctor Before It Hurts + The ABC’s of Delay Claims Duncan W. Glaholt

“Consult Your Doctor Before it Hurts”

Page 3: Consult Your Doctor Before It Hurts + The ABC’s of Delay Claims Duncan W. Glaholt

“Consult Your Doctor Before it Hurts”

Page 4: Consult Your Doctor Before It Hurts + The ABC’s of Delay Claims Duncan W. Glaholt

Premise :

All Conflict is Bad ConflictWRONG!

Page 5: Consult Your Doctor Before It Hurts + The ABC’s of Delay Claims Duncan W. Glaholt

Argument of this Section:

1. There will always be conflict; some good, some bad;

2. Conflict can be managed, not avoided;

3. Lawyers were advocates but are “conflict specialists”;

4. Conflict management is the key to good constructing

Page 6: Consult Your Doctor Before It Hurts + The ABC’s of Delay Claims Duncan W. Glaholt

Argument 1: There Will Always be Conflict; Some Good, Some Bad

In Life:

Page 7: Consult Your Doctor Before It Hurts + The ABC’s of Delay Claims Duncan W. Glaholt

If it Can Go Wrong, it Will!

Page 8: Consult Your Doctor Before It Hurts + The ABC’s of Delay Claims Duncan W. Glaholt
Page 9: Consult Your Doctor Before It Hurts + The ABC’s of Delay Claims Duncan W. Glaholt

Argument 2: Conflict is to be Managed, Not Avoided

This is not a new idea:

Bernard S. Mayer,

Beyond Neutrality: Confronting Crisis in Conflict Resolution

(Jossey-Bass, 2004)

Page 10: Consult Your Doctor Before It Hurts + The ABC’s of Delay Claims Duncan W. Glaholt

Mayer #1:

“By automatically thinking in terms of resolution,

Page 11: Consult Your Doctor Before It Hurts + The ABC’s of Delay Claims Duncan W. Glaholt

Mayer #1:

“By automatically thinking in terms of resolution, we inevitably drift toward a shallower and more behavioral definition of the issues,

Page 12: Consult Your Doctor Before It Hurts + The ABC’s of Delay Claims Duncan W. Glaholt

Mayer #1:

“By automatically thinking in terms of resolution, we inevitably drift toward a shallower and more behavioral definition of the issues, because those are usually the most easily available to resolution process”

Page 13: Consult Your Doctor Before It Hurts + The ABC’s of Delay Claims Duncan W. Glaholt

Mayer #2:

“Engaging in conflict means accepting the challenges of a conflict, whatever its type or stage of development may be,

Page 14: Consult Your Doctor Before It Hurts + The ABC’s of Delay Claims Duncan W. Glaholt

Mayer #2:

“Engaging in conflict means accepting the challenges of a conflict, whatever its type or stage of development may be, […] without automatically assuming that resolution is an appropriate goal.”

Page 15: Consult Your Doctor Before It Hurts + The ABC’s of Delay Claims Duncan W. Glaholt

Mayer #3:

“Effective engagement requires finding the right level of depth at which to engage”

Page 16: Consult Your Doctor Before It Hurts + The ABC’s of Delay Claims Duncan W. Glaholt

Q: How Do You :

Engage decision makers?Define dispute?Confine dispute?While leaving the door open to settlement,

without “loss of face”?

Page 17: Consult Your Doctor Before It Hurts + The ABC’s of Delay Claims Duncan W. Glaholt

A: Mayer #4:

Employ an advocate as “Conflict Specialist”

Mission statement required of an advocate:

“Our goal as advocates is to help people engage effectively and powerfully in conflict”

Page 18: Consult Your Doctor Before It Hurts + The ABC’s of Delay Claims Duncan W. Glaholt

Mayer #5:Good advocates are skilled in conflict engagement:

raising conflict (i.e. defining/confining conflict)negotiating conflict (i.e. earning and

maintaining credibility)resolving conflict (i.e. subordinating ego to

outcome)

Page 19: Consult Your Doctor Before It Hurts + The ABC’s of Delay Claims Duncan W. Glaholt

Roles

Your role as client: Change your assumptions about conflict

(Some conflict is good, some bad) Use conflict to test & mature your organization Change your approach to contracts to allow you

to engage effectively and powerfully in conflict (more about this later)

Use “process” rather than “position” Make conflict work for you, not against you

Page 20: Consult Your Doctor Before It Hurts + The ABC’s of Delay Claims Duncan W. Glaholt

Roles

Your lawyer’s role: Be a conflict ally:

Advocate

Page 21: Consult Your Doctor Before It Hurts + The ABC’s of Delay Claims Duncan W. Glaholt

Barrister’s Oath:

“You are called to the Degree of Barrister-at-law to protect and defend the rights and interest of such citizens as may employ you. You shall conduct all cases faithfully and to the best of your ability. You shall neglect no one's interest nor seek to destroy any one's property. You shall not be guilty of champerty or maintenance. You shall not refuse causes of complaint reasonably founded, nor shall you promote suits upon frivolous pretences. You shall not pervert the law to favour or prejudice any one, but in all things shall conduct yourself truly and with integrity. In fine, the Queen's interest and the interest of citizens you shall uphold and maintain according to the constitution and law of this Province. All this you do swear to observe and perform to the best of your knowledge and ability. So help you God.”

Page 22: Consult Your Doctor Before It Hurts + The ABC’s of Delay Claims Duncan W. Glaholt

Roles

Your lawyer’s role: Be a conflict ally:

AdvocateOrganizerStrategistCoach

Page 23: Consult Your Doctor Before It Hurts + The ABC’s of Delay Claims Duncan W. Glaholt

What Processes Best Define, Confine & Control “Good”

Conflict?

• Dispute Review Boards

• Adjudication

• Arbitration

• Litigation

Expert, non-binding, “project-driven”Summary, non-binding,

“commerce-driven”Due process, binding,

“outcome-driven”Due process, binding,

“society-driven”

Page 24: Consult Your Doctor Before It Hurts + The ABC’s of Delay Claims Duncan W. Glaholt

1. The more one-sided your contract, the less likely it is to be enforced

2. Concentrate on: Notice as a pre-condition (it works) Evidentiary burdens (they work) Liquidating claims (they work) Process solutions (DRB, DAB, Adjudication,

Expert Determination, Arbitration (they work))

What Contractual Terms Best Manage Conflict?

Page 25: Consult Your Doctor Before It Hurts + The ABC’s of Delay Claims Duncan W. Glaholt

Making Your Contract a Crystal Ball

+Predictability

Page 26: Consult Your Doctor Before It Hurts + The ABC’s of Delay Claims Duncan W. Glaholt

ASCE

“Ten Commandments for Better Contracting -

A practical guide to adding value to an enterprise through more effective SMART contracting”

Francis T. Hartman, ASCE Press, 2003, as paraphrased by D. Glaholt

Page 27: Consult Your Doctor Before It Hurts + The ABC’s of Delay Claims Duncan W. Glaholt

1. Stop, Look and Listen(be aware of your legal and working environment)

Page 28: Consult Your Doctor Before It Hurts + The ABC’s of Delay Claims Duncan W. Glaholt

2. Do Not Mix Packages do not mix contract types (cost plus + mix

rate + lump sum, for example) do not mix scope (supply only + EPC, for

example)

Page 29: Consult Your Doctor Before It Hurts + The ABC’s of Delay Claims Duncan W. Glaholt

3. Understand and Manage Expectationspuffery going in = misery going outsurprises = claimsnotice provisions are your friend,

not your enemy

Page 30: Consult Your Doctor Before It Hurts + The ABC’s of Delay Claims Duncan W. Glaholt

4. Don’t Go CheapDelay & disruption claims are

easy to raise and devilishly hard to prove

Risk management at the front end is always cheaper than at the back end

Page 31: Consult Your Doctor Before It Hurts + The ABC’s of Delay Claims Duncan W. Glaholt

5. Say what you mean, mean what you say

Do not make assumptionsConsistency is a virtueIf it can happen, it will! Provide for

it!

Page 32: Consult Your Doctor Before It Hurts + The ABC’s of Delay Claims Duncan W. Glaholt

6. Share risks according to ability to deal with them

i.e. subsurface, permits, means and methods

Think “risk management”, not “risk avoidance”

Page 33: Consult Your Doctor Before It Hurts + The ABC’s of Delay Claims Duncan W. Glaholt

7. Watch what the other side does, not what they say

Do they agree to take risks, but take no steps to manage them? There is a claim coming.

Do they promise schedule performance, but ignore it? There is a claim coming.

Do they object to minutes? There is a claim coming.

Page 34: Consult Your Doctor Before It Hurts + The ABC’s of Delay Claims Duncan W. Glaholt

8. Amend the contract sparingly, and in writing

Waiving notice? Say so, and amend contract.

Waiving dispute resolution provision? Say so, and amend contract.

Page 35: Consult Your Doctor Before It Hurts + The ABC’s of Delay Claims Duncan W. Glaholt

9. On changes and extras, remember: Your first loss is your best loss

Extras and changes cost $1 or more to resolve every $ in issue

Use the rule insurers and sureties do every day.

Page 36: Consult Your Doctor Before It Hurts + The ABC’s of Delay Claims Duncan W. Glaholt

10. Make conflict work for you, not against you.

Page 37: Consult Your Doctor Before It Hurts + The ABC’s of Delay Claims Duncan W. Glaholt

Summary

1. Stop, look and listen

2. Do not mix packages

3. Understand your customer’s expectations

4. Don’t go cheap

5. Say what you mean, mean what you say

6. Share risks according to ability to deal with them

7. Watch what they do, not that they say

8. Amend sparingly, and in writing

9. Neither a piker nor a fool be, on changes and extras

10. Embrace conflict, make it work for you

Page 38: Consult Your Doctor Before It Hurts + The ABC’s of Delay Claims Duncan W. Glaholt

A,B,C’s of Delay and Disruption

Page 39: Consult Your Doctor Before It Hurts + The ABC’s of Delay Claims Duncan W. Glaholt

A: Allocation of all risks which could cause delay and/or

disruption

Page 40: Consult Your Doctor Before It Hurts + The ABC’s of Delay Claims Duncan W. Glaholt

Q: What Risks?

1. Legal Risk2. Design risk3. Buildability risk4. Procurement risk5. Construction risk6. Financial risk7. Political risk8. Insurable risk

Page 41: Consult Your Doctor Before It Hurts + The ABC’s of Delay Claims Duncan W. Glaholt

Q: Legal Risk?

Who will interpret my contract? How will they interpret my contract with

nominated subcontractors? How does this jurisdiction deal with

waivers and exclusion clauses? Will this court award liquidated

damages? How does this jurisdiction deal with

contractual notice provisions?

Page 42: Consult Your Doctor Before It Hurts + The ABC’s of Delay Claims Duncan W. Glaholt

Q: Design Risk?

Over 60% of delay and disruption claims have their basis in defective, deficient or misinterpreted drawings and specifications

(1993, Kellogg Corporation) The standard E&O limitation is the greater of

$250,000 or insurance covered. Are the design professionals really taking my

side?

Page 43: Consult Your Doctor Before It Hurts + The ABC’s of Delay Claims Duncan W. Glaholt

Q: Buildability Risk?

Keep it simple! The greater the complexity, the greater

the potential for delay & disruption Complexity claims have their own

complexities

Page 44: Consult Your Doctor Before It Hurts + The ABC’s of Delay Claims Duncan W. Glaholt

Q: Procurement Risk?

What procurement strategy: Design-Build or Build Only?

Lines of responsibility and communication are different in each case

Are you prepared to fulfill your role under the procurement model chosen?

Page 45: Consult Your Doctor Before It Hurts + The ABC’s of Delay Claims Duncan W. Glaholt

Q: Construction Risk?

What does the project need v. what was expected?

“Foreseeability” Changes and extras

Page 46: Consult Your Doctor Before It Hurts + The ABC’s of Delay Claims Duncan W. Glaholt

Q: Financial Risk?

Cost of money issues; inflation; cost of materials issues:

They change the stakes of the game as the game is being played

Who is benefited by delay or disruption?

Page 47: Consult Your Doctor Before It Hurts + The ABC’s of Delay Claims Duncan W. Glaholt

Q: Political Risk?

Unions Out of province labour Permits, licenses, approvals How are these risks best allocated?

Page 48: Consult Your Doctor Before It Hurts + The ABC’s of Delay Claims Duncan W. Glaholt

Q: Insurable Risk?

Is Builder’s Risk insurance enough to accommodate risk?

“Delayed opening and start-up insurance” – what is it and who pays?

Page 49: Consult Your Doctor Before It Hurts + The ABC’s of Delay Claims Duncan W. Glaholt

B: Be Prepared!

Page 50: Consult Your Doctor Before It Hurts + The ABC’s of Delay Claims Duncan W. Glaholt

Get your contract administrators to do their job: an ounce of prevention…!

Learn to use scheduling delay analysis software; Monitor all data points, forecast all delays Your first loss is your best loss! Buy your way out

of a claim at your very first opportunity Document all delay events, whether claimed or

not (this will help you with “concurrency”) Liquidate all claims including all economic loss,

loss of profit, loss of productivity claims

Page 51: Consult Your Doctor Before It Hurts + The ABC’s of Delay Claims Duncan W. Glaholt

C: Causation

The Achilles Heel of All Claims

Page 52: Consult Your Doctor Before It Hurts + The ABC’s of Delay Claims Duncan W. Glaholt

The Elements of Causation:

1. Your contract

2. As-Planned programme v. As-Built programme

3. Float

4. Concurrency

5. Mitigation

6. Law of damages

Can you claim that an event is a “cause” if you failed to give notice of it under the contract?

Something happened, but did it have an effect?

Who owns it, who gets to use it?Excusable or compensable

events mixed up in the causeand effect cycle?

Did the delay or disruption cause your loss, or did you?

Direct cost incurred, or only economic loss?

Page 53: Consult Your Doctor Before It Hurts + The ABC’s of Delay Claims Duncan W. Glaholt

Listen Closely to Master Sandler!

Page 54: Consult Your Doctor Before It Hurts + The ABC’s of Delay Claims Duncan W. Glaholt

The End !