CONSTRUCTION SUMMIT

Alex LeonDeputy CommissionerFebruary 7, 2018

C D A D E S I G N A N D C O N S T R U C T I O N

2018

TERMINAL AREA PLAN

2

O’HARE CAPITAL PROGRAMS OVERVIEW

O’Hare is taking steps to reconfigure and modernize for long-term growth

Working in partnership with United, American and other domestic and international airlines on facility needs

Projects are funded with multiple sources

3

POTENTIAL CONFIGURATION FOR NEW CONCOURSES

Terminal Area Development - TAP

• Over 400 acres available for gate expansion• Taxiways comply with FAA guidance to eliminate irregular geometry

4

EXPANSION OF TERMINAL 5 TO SUPPORT INCREASED DEMAND

Terminal expansion includes 9 new wide-body gates

Provides for a second A380 capable gate at O’Hare

Addresses near-term demand and capacity of International Terminal gates and facilities

Provides additional capacity for domestic flights

Includes expanded security screening and Federal Inspection Services (FIS) facilities

5

CM at Risk contracts to deliver the Terminal 5 M Extension projects as well as additional O’Hare 21 Projects

O’Hare 21 Projects will include airside facility projects, landside facility projects, terminal projects and security packages

CM AT RISK FOR T5 EXTENSION AND ADDITIONAL O’HARE 21 PROJECTS (ANTICIPATED TO BE AT LEAST TWO CONTRACTS)

Anticipated Term: TBD

Advertisement Date: 2nd Quarter 2017

Anticipated Award Date: 2nd Quarter 2018

ORD TERMINAL 5 M EXTENSION SITE/CIVIL

Scope of Work:The civil component of the building extension will include four (4) new hardstand positions, including all site, apron, lighting, security, fueling & taxiway design. Also included are modifications to the pavement area near Gates M1 to M6 for two additional contact gates for future operations.

ANTICIPATED ADVERTISEMENT DATE: 2ND QUARTER 2018

ESTIMATED CONTRACT VALUE: $90- $100 MILLION

DBE/MBE/SBE/WBE GOALS: DBE 30%6

TRADES LOCATION: AIRSIDEELECTRICIANS TEAMSTERS OPERATORS IRON WORKERS

LABORERS SURVEYORS CEMENT MASONS

7

Contracts designated for competition limited to MBEs or WBEs

The Target Market Program reserves a percentage of the City’s non-construction contracts and limits participation to M/WBEs

Contracts are not eligible for the program unless there are at least three qualified MBEs or WBEs interested in participating in that type of contract

The prime contractor on a Target Market Contract must perform at least 50 percent of the dollar value

TARGET MARKET CONTRACTS

8

Multiple target market Construction Manager contracts will be awarded to oversee various segments of O’Hare 21 Terminal Area Plan, the Capital Improvement program and the TAP enabling projects

Projects will include airside projects, landside projects, terminal projects, site preparation and security packages

Anticipated Term: 5 Years

Anticipated Advertisement Date: 1st Quarter 2018

Anticipated Award Date: 3rd Quarter 2018

TARGET MARKET CONSTRUCTION MANAGEMENT SERVICES

9

Multiple target market design/task order for O’Hare 21 and CIP projects.

Projects will include airside work, landside projects, terminal projects, site preparation and security packages

Anticipated Term: 5 Years

Advertisement Date: 2nd Quarter 2017

Award Date: 4th Quarter 2018

TARGET MARKET DESIGNS/TASK ORDERS

10

Multiple target market design/task order for O’Hare 21 and CIP projects.

Projects will include airside work, landside projects, terminal projects, site preparation and security packages

Anticipated Term: 5 Years

Advertisement Date: 2nd Quarter 2017

Award Date: 2nd Quarter 2018

TARGET MARKET, FEDERAL, NON-FEDERALDESIGNS/TASK ORDERS

11

Tunnel system from the east end of Terminal 2, through the Satellite Concourses, to a point beyond the relocated Taxiways A & B for the purpose of conveying passengers (sterile and non-sterile), baggage, utilities and bag carts/GSE

The tunnel provides sufficient width to enable the future installation of an APM

Designer will be tasked to bring up to 15% Design

Anticipated Duration: To task completion

Advertisement Date: 2nd Quarter 2018

Award Date: 4th Quarter 2018

LEAD DESIGNER – TUNNEL FORAIRSIDE PEOPLE MOVER (APM)

12

GT will provide Gate Space for a Multiple Aircraft Ramp

System (MARS) configuration to allow flexible use of Gate Space between regional jets, narrow body and wide body aircraft (as deemed appropriate) to serve international and domestic operations, as well as a Customs & Border Protection (CBP) arrival hall

Satellite concourses will provide Gate Space for a Multiple Aircraft Ramp System (MARS) configuration to serve international, precleared international and domestic operations

Up to two designers can be selected

Anticipated Duration: To task completion

Advertisement Date: 2nd Quarter 2018

Award Date: 4th Quarter 2018

LEAD DESIGNERS –O’HARE GLOBAL TERMINAL (OGT) AND SATELLITE CONCOURSES

O’Hare Modernization Program

14

The Modernization of O’Hare has completed approximately $5.8B of improvements, including:

Two New Airport Traffic Control Towers

Extension of Runway 10L/28R

New Runway 9L/27R

New Runway 10C/28C

New Runway 10R/28L

Multiple Taxiway Improvements (K&L, LL, others)

Ongoing Runway 9C/27C

Ongoing Consolidated Rental Car/Parking Multimodal facility

Ongoing ATS Modernization and Extension

O’HARE - AIRFIELD

15

RUNWAY 9C/27C – CONSTRUCTION PACKAGES

LEGENDRunway 9C-27C East PackageRunway 9C-27C Package 1Runway 9C-27C Package 2Runway 9C-27C Package 3Airline Employee Parking Lot

16

RWY 9C/27C – PACKAGE 2

ADVERTISEMENT DATE: 1/19/2018

ESTIMATED CONTRACT VALUE: $120 - $160 MILLION

DBE/MBE/SBE/WBE GOALS: DBE 30%

TRADES LOCATION: AIRSIDEELECTRICIANS TEAMSTERS OPERATORS IRON WORKERS

LABORERS SURVEYORS CEMENT MASONS

Scope of Work:Construction of airfield pavements, PCC and AC, airfield lighting and signage, demolitions of existing structures and underground utilities and other improvements, site preparation, grading and drainage, site restoration, utilities and other appurtenances and incidental work. Project site is located in the Air Operations Area (AOA).

17

AIRLINE EMPLOYEE PARKING LOT PKG #2

ANTICIPATED ADVERTISEMENT DATE: 1st QUARTER 2018

ESTIMATED CONTRACT VALUE: $6-$8 MILLION

DBE/MBE/SBE/WBE GOALS: M/WBE 26/6%

TRADES LOCATION: AIRSIDEELECTRICIANS TEAMSTERS OPERATORS IRON WORKERS

LABORERS SURVEYORS CEMENT MASONS

Scope of Work:Roadway intersection improvements on Bessie Coleman Drive to access new Employee Parking Lot, the expansion of the entrance to the new lot with supporting five lane check point, and the construction of a new Guard Post.

18

RWY 9C/27C – PACKAGE 3

ANTICIPATED ADVERTISEMENT DATE: 3RD QUARTER 2018

ESTIMATED CONTRACT VALUE: $40 - $60 MILLION

DBE/MBE/SBE/WBE GOALS: DBE 30%

TRADES LOCATION: AIRSIDEELECTRICIANS TEAMSTERS OPERATORS IRON WORKERS

LABORERS SURVEYORS CEMENT MASONS

Scope of Work:Phased construction of airfield pavements, PCC and AC, airfield lighting and signage, site preparation, grading and drainage, site restoration, utilities and other appurtenances and incidental work. Project site is located in the Air Operations Area (AOA).

19

CDF CONTROL TOWER

ANTICIPATED ADVERTISEMENT DATE: 1st QUARTER 2018

ESTIMATED CONTRACT VALUE: $4-6 MILLION

DBE/MBE/SBE/WBE GOALS: M/WBE – 26/6%

TRADES LOCATION: AIRSIDEELECTRICIANS TEAMSTERS OPERATORS IRON WORKERS

LABORERS SURVEYORS CEMENT MASONS

Scope of Work:Construction of a building to serve as a operations control tower for airlines management of their winter deicing operations at the Centralized Deicing Facility.

20

CENTRAL BASIN RECONFIGURATION

ANTICIPATED ADVERTISEMENT DATE: 4th QUARTER 2018

ESTIMATED CONTRACT VALUE: $100-$120 MILLION

DBE/MBE/SBE/WBE GOALS: M/WBE – 26/6%

TRADES LOCATION: AIRSIDEELECTRICIANS TEAMSTERS OPERATORS IRON WORKERS

LABORERS SURVEYORS CEMENT MASONS

Scope of Work:Modifications to the Central and South Basins to accommodate the future terminal developments. Work may include earthwork, large diameter deep tunnel construction, modifications to mechanical equipment, including an existing pump station. Project may be delivered as design-build.

21

RELOCATION OF TAXIWAYS A&B

ANTICIPATED ADVERTISEMENT DATE: 2ND QUARTER 2019

ESTIMATED CONTRACT VALUE: $80 - $100 MILLION

DBE/MBE/SBE/WBE GOALS: MBE 26% / WBE 6%

TRADES LOCATION: AIRSIDEELECTRICIANS TEAMSTERS OPERATORS IRON WORKERS

LABORERS SURVEYORS CEMENT MASONS

Scope of Work:Phased construction of airfield pavements, PCC and AC, airfield lighting and signage, pavement removal, PCCP crushing, and underground utilities and other improvements, site preparation, grading and drainage, site restoration, utilities and other appurtenances and incidental work. Project site is located in the Air Operations Area (AOA).

22

ATS LOT E STATION DEMOLITION

ANTICIPATED ADVERTISEMENT DATE: 4TH QUARTER 2019

ESTIMATED CONTRACT VALUE: $10 - $20 MILLION

DBE/MBE/SBE/WBE GOALS: DBE 30%

TRADES LOCATION: LANDSIDEELECTRICIANS OPERATORS LABORERS IRON WORKERS

Scope of Work:Demolition of the structure and platform of this station, modification of wayside systems, power systems and track work as required and site restoration. Construction will require coordination with and limited interruption of services of the Airport’s Transit System Project site is in the current Public Parking Lot E.

O’Hare International AirportCapital Improvement Program

BESSIE COLEMAN WATERMAIN REPLACEMENT

Scope of Work:Replacement of approximately 5,000 lfof water main along Bessie Coleman, a connection to the existing 12” service line adjacent to the E Lot ATS Station, and abandoning the existing water main running underneath I-190. Other work items will include: lateral runs to fire hydrants, isolation valves, valve boxes, fire hydrants, cathodic protection and other pertinent items integral to the installation of a new water distribution and/or capping and connections to the existing water main.

ADVERTISEMENT DATE: 2/1/2018

ESTIMATED CONTRACT VALUE: $2 - $3 MILLION

DBE/MBE/SBE/WBE GOALS: MBE 26% / WBE 6%

TRADES LOCATION: LANDSIDEOPERATORS CARPENTERS LABORERS ELECTRICIANS

TEAMSTERS PLUMBERS

24

NORTH AIRFIELD SANITARY SEWER REPLACEMENT

Scope of Work:Construction of a sanitary sewer system that will serve the North Airfield buildings. Existing flow that travels NW to the MWRD Kirie Plant will be intercepted and sent to an existing forcemain sewer on airport property near Building 850. That existing pipe outfalls near Mannheim Road where it enters the MWRD Stickney system. A new lift station will be included as well as approximately 6400LF of gravity pipe and forcemain.

ANTICIPATED ADVERTISEMENT DATE: 1ST QUARTER 2018

ESTIMATED CONTRACT VALUE: $2.5 - $3.5 MILLION

DBE/MBE/SBE/WBE GOALS: MBE 26% / WBE 6%

TRADES LOCATION: LANDSIDEELECTRICIANS PLUMBERS OPERATORS CARPENTERS

LABORERS SURVEYORS LANDSCAPERS WELDERS

PIPE FITTERS TEAMSTERS

25

RUNWAY 9R-27L RWSL INSTALLATION

Scope of Work:Install approximately 10,000 linear feet of electrical ductbank, handholes, and airfield lighting cable to complete the installation of the FAA Runway Status Lights (RWSL) system for Runway 9R-27L. A FAA-RWSL shelter to be located adjacent to the existing Runway 27L ALSF shelter will also be installed. A new Com Ed service feed as well as fiber optic cable connectivity to the air traffic control tower will be required to make the RWSL shelter fully functional.

ANTICIPATED ADVERTISEMENT DATE: 1ST QUARTER 2018

ESTIMATED CONTRACT VALUE: $2.5 - $3 MILLION

DBE/MBE/SBE/WBE GOALS: DBE 30%

TRADES LOCATION: AIRSIDEOPERATORS ELECTRICIANS TEAMSTERS LABORERS

26

MIAMI BEACH LIFT STATION IMPROVEMENT

Scope of Work:Demolish existing Lift Station and specified equipment, erosion control and paving, site utility installation, including jacked sanitary sewer, excavation and construction of the new Lift Station Facility in the SW corner of LOT B, electrical and communications duct bank installation, SMS installation and tie-in, and C1 Electrical Vault Switchboard replacement and lighting upgrades.

ANTICIPATED ADVERTISEMENT DATE: 2ND QUARTER 2018

ESTIMATED CONTRACT VALUE: $5 - $6 MILLION

DBE/MBE/SBE/WBE GOALS: MBE 26% / WBE 6%

TRADES LOCATION: LANDSIDEOPERATORS CARPENTERS LABORERS ELECTRICIANS

TEAMSTERS PLUMBERS

27

BAGGAGE SERVICE ROAD RETAINING WALL REPAIR

Scope of Work:Repair the Baggage Service Road Retaining Wall from approximately Guard Post 7 to Guard Post 10 (excluding Terminal 2). Scope will include the drilling of piles to support the wall footing; concrete and crack repair; cap replacement; new underdrain system; select stem replacement; cleaning and repainting and replacement of conduit and circuitry to roadway and apron lighting.

ANTICIPATED ADVERTISEMENT DATE: 2ND QUARTER 2018

ESTIMATED CONTRACT VALUE: $1 - $2 MILLION

DBE/MBE/SBE/WBE GOALS: MBE 26% / WBE 6%

TRADES LOCATION: AIRSIDEOPERATORS PAINTERS ELECTRICIANS FINISHERS

TEAMSTERS LABORERS

28

RING AND UTILITY TUNNEL CONCRETE REPAIRS

Scope of Work:Phased approach to address the areas in need of structural concrete repair in two utility tunnel locations. Scope varies from spall repair, cathodic protection of reinforcement to entire beam replacement. This project will address the 2nd Phase in the program.

ANTICIPATED ADVERTISEMENT DATE: 2ND QUARTER 2018

ESTIMATED CONTRACT VALUE (PH 2): $8 - $10 MILLION

DBE/MBE/SBE/WBE GOALS: MBE 26% / WBE 6%

TRADES LOCATION: AIRSIDEELECTRICIANS PLUMBERS OPERATORS TEAMSTERS

LABORERS IRONWORKERS CONCRETE MASONS

29

PEDESTRIAN TUNNEL REPAIRS

Scope of Work:Remediation of water infiltration throughout the pedestrian tunnels below the concourses and roadways. Scope also includes interior remodeling and updating of pedestrian tunnels. New finishes will allow for a back-up drainage system as a second line of defense to any possible water migration through the tunnel structure. New energy efficient lighting and mechanical distribution is included. Project area extends into the area of the tunnels under the Hilton for finishes continuity.

ANTICIPATED ADVERTISEMENT DATE: 2ND QUARTER 2018

ESTIMATED CONTRACT VALUE : $25 - $30 MILLION

DBE/MBE/SBE/WBE GOALS: MBE 26% / WBE 6%

TRADES LOCATION: AIRSIDEELECTRICIANS PLUMBERS OPERATORS TEAMSTERS

LABORERS IRONWORKERS CONCRETE MASONS ELECTRICIANS

CARPENTERS PAINTERS

30

I-190 LIFT STATION REPLACEMENT

Scope of Work:This project consists of improvements to the existing Taxiway Lift Station. Work includes removal and replacement of existing ventilation, pumps, valve, motors, motor starters, wet well control panel, associated piping, and electrical infrastructure. The project also includes Supervisory Monitoring System (SMS) integration, upgrades to the facility's lighting control, replacement of an existing "ship's ladder", and installation of a wet well concrete liner and partial depth concrete repair.

ANTICIPATED ADVERTISEMENT DATE: 3RD QUARTER 2018

ESTIMATED CONTRACT VALUE: $3-4 MILLION

DBE/MBE/SBE/WBE GOALS: MBE 26% / WBE 6%

TRADES LOCATION: AIRSIDEELECTRICIANS PLUMBERS CARPENTERS PIPE FITTERS

LABORERS TEAMSTERS OPERATORS FINISHERS

31

REPLACEMENT OF ROTUNDA AIR HANDLING UNITS

Scope of Work:Replacement of 11 Rotunda Air Handling Units. Recondition of the existing ductwork. The new, efficient, code complying units will serve the environments that require different temperature controls, air movement, cooling capacities, heating capacities, with separate multi-zone controls to reconnect to existing ducting.

ANTICIPATED ADVERTISEMENT DATE: 3RD QUARTER 2018

ESTIMATED CONTRACT VALUE: $15 - $20 MILLION

DBE/MBE/SBE/WBE GOALS: MBE 26% / WBE 6%

TRADES LOCATION: AIRSIDESHEET METAL

WORKERS ELECTRICIANS PLUMBERS LABORERS

32

RECIRCULATION BRIDGE RECONSTRUCTION

Scope of Work:The project includes the replacement of the three-span entrance roadway recirculation bridge and associated ramp and approaches for the structure.

ANTICIPATED ADVERTISEMENT DATE: 4TH QUARTER 2018

ESTIMATED CONTRACT VALUE: $3 - $4 MILLION

DBE/MBE/SBE/WBE GOALS: MBE 26% / WBE 6%

TRADES LOCATION: AIRSIDE

OPERATORS CEMENT MASONS ELECTRICIANS FINISHERS

TEAMSTERS LABORERS IRON WORKERS CARPENTERS

33

TERMINAL AREA FIRE MAIN REPLACEMENT

Scope of Work:Relocation of the terminal area fire main loop including approximately 7000 lf of 12” fire main, 1500 lf of 8” hydrant fire main and 32 fire hydrants. New alignment will minimize impacts to traffic by locating portions of the loop within the commercial vehicle lanes. Medians and center lanes will be reconstructed within the terminal area to meet ADA and will include new sidewalks and utility replacements. Approximately 2,500 lf of ComEd ductbank will be included to replace an existing ductbank that is at risk of failure.

ANTICIPATED ADVERTISEMENT DATE: 1ST QUARTER 2019

ESTIMATED CONTRACT VALUE: $20 - $25 MILLION

DBE/MBE/SBE/WBE GOALS: MBE 26% / WBE 6%

TRADES LOCATION: AIRSIDELABORERES PIPEFITTERS OPERATORS PLUMBERS

TEAMSTERS FINISHERS IRON WORKERS CARPENTERS

ELECTRICIANS

34

Midway International Airport Capital Improvement Program

TRADES LOCATION: AIRSIDEELECTRICIANS OPERATORS TEAMSTERS LABORERS

36

ANTICIPATED ADVERTISEMENT DATE: 1ST QUARTER 2018

ESTIMATED CONTRACT VALUE: $8 - $10 MILLION

DBE/MBE/SBE/WBE GOALS: DBE 30%

Scope of Work:Installation of a new duct bank system that will provide a more efficient way to maintain airfield electrical system. This will include new duct bank runs to provide more direct routing of circuits, the installation of new manholes and hand holes that minimize the need to access Runway and Taxiway safety areas during maintenance, replacement of aging cabling, and additional capacity to handle future improvements. This project also includes new fiber optic duct bank in the SW corner of the airfield.

MDW AIRFIELD LIGHTING INFRASTRUCTURE IMPROVEMENTS

TRADES LOCATION: LANDSIDEELECTRICIANS OPERATORS LABORERS SURVEYORS

CARPENTERS PLUMBERS IRON WORKERS PAINTERS

CEMENT MASONS

37

MDW AIRPORT MAINTENANCE COMPLEX IMPROVEMENTS

ANTICIPATED ADVERTISEMENT DATE: 1ST QUARTER 2018

ESTIMATED CONTRACT VALUE: $11 - $12.5 MILLION

DBE/MBE/SBE/WBE GOALS: DBE 30%

Scope of Work:Replacing the HVAC for the garage with an energy efficient system, replacing the overhead doors and associated hardware, an upgrade to the emergency generator and switchgear, and the replacement of the boilers with more energy efficient boilers. Expanding and replacing the potassium acetate pumps and tanks to allow for a total of 90,000 gallons of onsite storage. The project also includes replacing the roof membrane, an upgrade of the windows, replacing the HVAC system in the office area, replacement of the emergency egress doors and hardware, and improvements for ADA accessibility.

Residential Sound Insulation Program (RSIP)

39

On-call architectural and engineering (“A/E”) design and consulting services for the RSIP for O’Hare and Midway.

Federally-funded. DBE participation of 30% required.

Services may include, but are not limited to: making at least two site visits per home, computer-aided design and drafting, developing window and door schedules, preparing specifications, and reviewing submittals and code requirements.

Anticipated Term: 5 Years

Advertisement Date: 1st Quarter 2018

Award Date: 2nd Quarter 2018

ON-CALL A/E SERVICES FOR THE RSIP

40

ANTICIPATED ADVERTISEMENT DATE: 2nd QUARTER 2018

ESTIMATED CONTRACT VALUE: $10 - $15 MILLION

DBE/MBE/SBE/WBE GOALS: DBE 22%

Scope of Work:Sound-insulate 133 historical dwelling units in single-family homes and multi-family buildings in the Chicago Norwood Park Historical District near Harlem Avenue and Higgins Avenue. Work to include installation of approximately 2,600 acoustical window treatments, 2,600 storm windows, 260 acoustical prime door treatments, 260 storm doors, 20 central air conditioning systems, upgrades to electrical service and other miscellaneous work.

TRADES LOCATION: LANDSIDEPAINTERS TAPERS LABORERS INSULATORS

ELECTRICIANS SHEET METAL WORKERS PIPE FITTERS ASBESTOS

WORKERS

CARPENTERS

O’HARE PHASE 17 HISTORICAL HOMES

VISIT WWW.FLYCHICAGO.COM