construction of mobile offshore drilling units… …and some

29
Charles Taylor Adjusting Limited 88 Leadenhall Street London EC3A 3BA Construction of Mobile Offshore Drilling Units… …and some claims arising. Mike McMahon CEng LMA 24 July 2014

Upload: others

Post on 31-Dec-2021

8 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Construction of Mobile Offshore Drilling Units… …and some

Charles Taylor Adjusting Limited 88 Leadenhall Street London EC3A 3BA

Construction of Mobile Offshore Drilling Units… …and some claims arising.

Mike McMahon CEng

LMA

24 July 2014

Page 2: Construction of Mobile Offshore Drilling Units… …and some

Content

• What’s a modern MODU? • MODU construction locations • Significance of South Korea • How a yard big works / stages of construction • Transfer of risk • Recent claims • Issues arising • Other considerations

1

Page 3: Construction of Mobile Offshore Drilling Units… …and some

Semi-Sub Drilling Unit - Overview

• 44 MW DP3 • 150 crew • 3,000m water depth • 9,000m drilling • Harsh environments • Development Drilling

2

Page 4: Construction of Mobile Offshore Drilling Units… …and some

Drill Ship Overview

• 42MW DP3 • 200 crew • 3,000m water depth • 12,000m drilling • Storage space • Exploration

3

Page 5: Construction of Mobile Offshore Drilling Units… …and some

MODUs currently under construction by country

4

Location Semisub Drillship Total South Korea 9 36 45 Brazil 6 23 29 China 10 4 14 Singapore 1 3 4 Azerbaijan 1 0 1 Total 27 66 93

Source www.rigzone.com

Page 6: Construction of Mobile Offshore Drilling Units… …and some

DSME in 2013

5

Page 7: Construction of Mobile Offshore Drilling Units… …and some

DSME – Sales Trends

6

Page 8: Construction of Mobile Offshore Drilling Units… …and some

DSME – Sales Trends

7

Page 9: Construction of Mobile Offshore Drilling Units… …and some

DSME – Sales Trends Units Numbers Built Average Unit Price (US$/m)

Commercial Ships 995 Gas Carrier 105 93 LNG Carrier 83 109 LPG Carrier 22 33 Oil Tanker 333 105

ULCC/VLCC 147 161 Suezmax TK 70 82 Aframax TK 37 58

Others 79 44 Full Containership 234 76

Above 10,000 TEU 54 137 5,000 TEU ~ 10,000 TEU 67 86

Below 5,000 TEU 113 41 Other Commercial Vessels Ro/Ro, Car Carrier 64 58 Bulk Carrier 193 62 Naval & Special Ship 56 1 Ferry 10 19

Wind Turbine Installation Vessel 2

OSV 2

Offshore Projects & Plant 72

Fixed Platform 25 FPSO 4

TLP 3 FPU 3

Semi-Submersible Rig 20 Drillship 13

Jack Up Rig 2 Drilling Barge 1 Modular Plant 1 8

Page 10: Construction of Mobile Offshore Drilling Units… …and some

DSME Shipyard – home to 47,000 workers

9

Page 11: Construction of Mobile Offshore Drilling Units… …and some

Construction

10

Page 12: Construction of Mobile Offshore Drilling Units… …and some

Recent S. Korea Shipyard Experiences

Claim Year Description Construction Stage

Shipyard specific?

Insured Value (US$)

Deductible (US$)

Approx. Cost (US$)

Semi-Sub

2013 Flooding Pre-commissioning Yes 700m 250,000 100m

Drillship

2013 Engine over-speed Sea-trials Yes 566m 500,000 8m

Drillship

2013 Engine Pre-commissioning Yes 566m 250,000 5m

Drillship

2013 Engine Pre-commissioning Yes 566m 250,000 0.3m

Semi-sub 2012 Collapsed mud tank Commissioning Yes 709m 250,000 0.5m

Semi-sub 2011 Dropped Module Assembly Yes 561m 250,000 10m

11

Page 13: Construction of Mobile Offshore Drilling Units… …and some

Transfer of risk – WELCAR Schedule 2

Stage Value US$ OFE Preliminary Cost 15,000,000 BFE (1) Derrick 27,480,000 BFE (2) Builder Furnished Equipment (2) 360,000,000 Hull Hull Construction 144,700,000 Topside Topside Construction 120,520,000

Integration Integration of Hull and Topside 667,700,000 Sea Trials Sea Trails 667,700,000 DEM Design, Engineering and Management 106,831,000 Total 774,531,000

12

Page 14: Construction of Mobile Offshore Drilling Units… …and some

Builder Furnished Equipment

• Main diesel generator sets (eg, 8 x 5mw) • Propulsion system, (DP3) • Mud handling (Dual system) • Drilling systems • Ballast water management • Power distribution System • Lifting gear • Mooring system • Etc.

13

Page 15: Construction of Mobile Offshore Drilling Units… …and some

Recent S. Korea Shipyard Experiences

Claim Year Description Construction Stage

Shipyard specific?

Insured Value (US$)

Deductible (US$)

Approx. Cost (US$)

Semi-Sub

2013 Flooding Pre-commissioning Yes 700m 250,000 100m

Drillship

2013 Engine over-speed Sea-trials Yes 566m 500,000 8m

Drillship

2013 Engine Pre-commissioning Yes 566m 250,000 5m

Drillship

2013 Engine Pre-commissioning Yes 566m 250,000 0.3m

Semi-sub 2012 Collapsed mud tank Commissioning Yes 709m 250,000 0.5m

Semi-sub 2011 Dropped Module Assembly Yes 561m 250,000 10m

14

Page 16: Construction of Mobile Offshore Drilling Units… …and some

Dropped Module

15

Page 17: Construction of Mobile Offshore Drilling Units… …and some

Dropped Module

16

Page 18: Construction of Mobile Offshore Drilling Units… …and some

Engine Damage

17

Page 19: Construction of Mobile Offshore Drilling Units… …and some

Engine Damage

18

Page 20: Construction of Mobile Offshore Drilling Units… …and some

Mud Tank Collapse

19

Page 21: Construction of Mobile Offshore Drilling Units… …and some

Overspeed of Generator Sets

20

Page 22: Construction of Mobile Offshore Drilling Units… …and some

Overspeed of Generator Sets (x2)

21

Page 23: Construction of Mobile Offshore Drilling Units… …and some

Flooding

22

Page 24: Construction of Mobile Offshore Drilling Units… …and some

Flooding

23

Page 25: Construction of Mobile Offshore Drilling Units… …and some

Common Themes/ Considerations

• Failure of working systems • Risks are constantly changing • Human error (1,000 personnel) • Production is extremely quick

(20 months) • Sea Trials in congested waters

24

Page 26: Construction of Mobile Offshore Drilling Units… …and some

Common Adjusting Issues Arising

• Restoration vs replacement • Cost effective repairs (Use of a repair yard?) • Cost presentation – labour / yard costs • Claims Control / Co-operation • WELCAR sub-limits

• Tests, Leak and/or Damage Search Costs • Expediting Costs

25

Page 27: Construction of Mobile Offshore Drilling Units… …and some

Working in Korea

• Shipbuilding Nation • Local survey expertise • Cultural sensitivities • Commercial considerations – the ‘Chaebol’ • Local Insurers’ Relationships • Local retentions

26

Page 28: Construction of Mobile Offshore Drilling Units… …and some

Summary

• There is demand for new MODU • S. Korea still main market • Construction is highly automated / controlled • Some claims arise (modest compared to value?) • S. Korea is unique

27

Page 29: Construction of Mobile Offshore Drilling Units… …and some

Questions?