construction of joka majherhat phase-i metro corridor considering the requirement of mrts in city...
DESCRIPTION
TRANSCRIPT
Construction of Joka- Majherhat Phase-I Metro corridor considering the
requirement of MRTS in city of Kolkata
By
Rajesh Prasad, IRSEChief Project Manager/RVNL
CONTENTS Kolkata : A few highlights
Various modes of Transport
Problems of high vehicular growth
Why to have more Metro in megacity like Kolkata?
Cost Analysis for Viaduct vis-à-vis Underground.
Role of RVNL for implementation of Metro Corridors in Kolkata
Planning and Execution of Joka – BBD Bag Part Section Drawing Management SystemLaunching of Segments.
KOLKATA : City of JoyAlso known as –
Cultural Capital of India Literary Capital of India City of Creative Energy City of ArchitectureCity of Brides of IndiaCity of Football in IndiaParis of East of India
City of Job Charnock (1690)(3 villages - Kalikata, Sutanuti & Gobindpur)
“City of Processions” Jawahar Lal Nehru
“A Dying City” Rajiv Gandhi
“ City of Joy” Dominique Lapierre
“Don’t worry Kolkata” Usha Uthup
KOLKATA : (Calcutta - Gateway to Eastern Region)
Kolkata was the capital of India till 1912.Kolkata was the capital of India till 1912.
The second train in India from Howrah to Hooghly in 1854 The second train in India from Howrah to Hooghly in 1854
The first Tramways Services The first Tramways Services in Indiain India (horse drawn) in (horse drawn) in Kolkata in 1873Kolkata in 1873
The first u/g Metro Railway in India started in Kolkata in The first u/g Metro Railway in India started in Kolkata in 19841984
The circular Railway in 1990.The circular Railway in 1990.
A city with all different modes of transportation.A city with all different modes of transportation.
84 KMs Metro network was sanctioned by Ministry of 84 KMs Metro network was sanctioned by Ministry of Railways in 2010 (66 KMs to RVNL)Railways in 2010 (66 KMs to RVNL)
KOLKATAbeing turned into CITY OF SORROW
Tram Service
Water Transport
Bus Service
Circular Railway
Metro Railway
Tram Service at a glance
In eighties 275 cars used to carry 0.75 million passengers.
As per RITES - 2004 trams carry 1.90 lakh passenger on an average week day.
68 KMs double track of standard gauge in operation of which only 25 kms are in reserved right-of-way.
Tram tracks have become major source of problem due to inadequate maintenance, non-investment of capital and mixed traffic operation.
6 KMs removed in July 2011 Joka - B.B.D. Bag Metro Section.
Tram Service at Kolkata
Water Transport System at and around Kolkata
In Kolkata and Howrah, water ferries are used through the extensive ghats like Fairlie Ghat, Howrah Ghat, Shibpur Ghat, Prinsep Ghat, Cossipore Ghat.
There were plans to start utilizing the canals running through the city as water-transport network.
BUS SYSTEM
Kolkata State Transport Corporation (KSTC)
Kolkata Tramway Company (KTC)
West Bengal Surface Transport Corporation (WBSTC)
North Bengal State Transport Corporation (NBSTC)
South Bengal State Transport Corporation (SBSTC)
Private Bus Syndicates
Other Hired/Charted Bus Operators.
The construction of Circular Railway from DDJ to Princep Ghat (13.42 km) was sanctioned in the year 1983 - 84 at a total cost of Rs. 35.49 Crore. The construction work was taken in hand in July '1983 and full of stretch of 13.42 km was opened for passenger traffic in June '1990.Section between Princep Ghat and Majerhat was opened in 2006.
Circular RailwayCircular Railway
Existing Metro net work
North-South Axis (Dum Dum to Tollygunge) 16.45 Kms was sanctioned on 1.6.1972.
1st Commercial run of the 1st Underground Metro Rly in India commenced on 24.10.1984 (between Esplanade and Bhowanipur (now Netaji Bhavan)
Section wise opening in stages :-Section Distance Opening Date
Esplanade - Netaji Bhavan 3.40 km 24.10.1984 Dum Dum - Belgachia 2.15 km 12.11.1984 Tollygunge -Netaji Bhavan 4.24 km 29.04.1986 Belgachia - Shyambazar 1.62 km 13.08.1994 Esplanade -Chandni Chowk 0.71 km 02.10.1994 Chandni Chowk - Central 0.60 km 19.02.1995 Shyambazar - Girish Park 1.93 km 19.02.1995 Dum Dum - Tollygunge 16.45 km 27.09.1995
POPULATION AND VEHICLE GROWTH
K M Area– Population( in Lakhs)
54.56
57.84
68.46
78.74
Kolkata – Population
As per INDIA 2011
Area (Sq. Km) Population
North 24 Parganas 4094 89.30 Lakhs
South 24 Parganas 9660 69.09 Lakhs
In 2000 Kolkata - 13.1 million
In 2015 Kolkata – 17.1 million
Kolkata – Population
The density of population is 33,000 per square kilometer.
Overcrowding has reached virtually intolerable proportions in many sections of the city.
Kolkata has experienced a high rate of population growth for more than a century.
Kolkata (KMA)– VehiclesTotal No. of vehicles as on 31 March 2010 – 18.75 Lakhs
More than 10000 new vehicles are being registered in Kolkata per month
COMPARISION OF THREE METRO CITIES
(AREA AND ROAD LENGTH)
Source –Transport Department
About Existing Roads of Kolkata
• Road space of Kolkata is about-6%. But effective Road space available for traffic movement is 5% only.
• Road space of
Delhi - 23%,
Mumbai - 18%
Chennai - 14%
Traffic Congestion is a normal phenomenon
Frequent traffic congestion at most traffic junctions along the Metro Corridor of Kolkata
Air PollutionSTANDARD RPM & NOX = 60,SPM = 140
Daily average micro gms / m3
Source -PCB
Present Average Noise level Present Average Noise level Peak Noise level recorded Peak Noise level recorded Permitted Noise levelPermitted Noise level
Noise Pollution
Contd..
70 dB70 dB 80 dB80 dB 60 dB60 dB
Noise Pollution
Location Noise Level (dB)
Howrah Bridge Approach 97
Moulali, Bara Bazar 95
Hazra, Jadavpur, New Market 80
Zone Day Night
Industrial 75 70
Commercial 65 55
Residential 55 45
Silence Zone 50 50
Noise Pollution Standards
Widening of Roads Widening of Roads
Limited Scope Limited Scope
due to lack of due to lack of
road spaceroad space
Remedies to the Traffic ProblemsRemedies to the Traffic Problems
Construction of Flyover-Construction of Flyover-
Limited scope due to financial Limited scope due to financial
and space involvementand space involvement
Remedies to the Traffic Problems in KolkataRemedies to the Traffic Problems in Kolkata
Remedies to the Traffic ProblemsRemedies to the Traffic Problems
Surface Metro SystemSurface Metro System
• Not Possible due to non availability Not Possible due to non availability of large open, continuous of large open, continuous strech of landstrech of land
• Frequent Crossing Frequent Crossing will pose problemwill pose problem
Grade Separated Mass Rapid Transit SystemGrade Separated Mass Rapid Transit System(Most appropriate solution)(Most appropriate solution)
Metro Rail - Advantages Requires 1/5th energy per passenger km
compared to road-based transport system. Causes less noise, no air pollution and eco
friendly transport system. Occupies no road space if underground and
only about 3.0 mtrs width of the road if elevated
More reliable, comfortableand safer than road based systems Reduces journey time.
KOLKATA METRO BEING EXECUTED BY RVNL
SALIENT FEATURES
SEORAPFULI
BARRACKPUR
TITAGARH
RISHRA
KHARDAH
SODEPUR
KONNAGAR
AGARPARA
DANKUNI
UTTARPARA
BELA NAGARBELGHARIA
BISARPARA
NEW BARRACKPUR
BIRATI
RAJCHANDRAPUR
BALLY
BALLY HALT
BELUR
LILUAH
TIKIAPARADASNAGAR
RAMRAJATALA
HOWRAH
PADMAPUKUR
BRACE BRIDGE
MAJHERHAT
NEW ALIPORE
TOLLYGUNGE
LAKE GARDENSDHAKURIA
JADABPUR
BAGHA JATIN
GARIA
NARENDRAPUR
SEALDAH
GURUDAS HALT
BIDHAN NAGAR RD.
DUM DUM
DUM DUM CANT.
DURGA NAGARBARANAGAR RD.
HIND MOTOR
SHRIRAMPUR
SOUTH 24PARGANAS
GOBRA
SANTRAGACHI
BALLYGUNGE
PARK CIRCUS
BALLY GHATDAKSHINESWAR
SHALIMAR
KOLKATA
SHOBHABAZAR
PARKSTREET
RABINDRASAROBAR
MAHANAYAKUTTAMKUMAR
NEWGARIA
SHAHIDKHUDIRAM
NETAJI
SHAHIDSURYASEN
GEETANJALI
KAVINAZRUL
RABINDRASADAN
MAIDAN
J.D PARK
NETAJIBHAVAN
KALIGHAT
ESPLANADE
CHANDNI CHOWK
M.G ROAD
CENTRAL
GIRISH PARK
SHYAM BAZAR
BELGACHIA
NOAPARA
BARANAGARBIMAN BANDAR
DAKSHINESWAR
B.B.D BAGH
JOKA
JOKAKM.-1.16
BEHALACHOWRASTAKM.4.87
MAJERHATKM.8.26
KHIDDIRPURKM.10.740
PARK ST.KM.13.42
HASTINGSKM.11.55
MOMINPURKM.9.456
THAKURPUKURBAZAR KM.1.45
SAKHER BAZARKM.2.97
BEHALABAZARKM.6.08
TARATALAKM.7.25
KM.0.00
KM.15.56
KM.15.86
ESPLANADE
PANIHATI
KHARDAH
TITAGARH
RAMKRISHNA PALLI
SHANTI NAGAR
JESSOR RDDUM DUM CANT 2.60KM
5.0KM
4.55KM
2.5KM
KAMARHATI2.5KM
4.5KM
6.0KM
8.0KM
10.0KM
12.5KM
AGARPARA
RUBY HOSPITAL
SCIENCE CITY
E.W CORRIDOR
SATYAJIT ROY
MUKUND PUR
KALIKA PUR
V I P BAZAR
CHINGRIGHATA
NICCO PARK
SECTOR V
RAJARHAT
NEW TOWN
HALDIRAM
CONVENTION CENTER
(2.0Km EX.BARANAGAR)
(0.0Km) (5.2Km EX.DUM DUM)
(0.0Km)(2.09Km EX.DMI)
(UP 6.15Km)(DN 6.4Km)
BIRATI(UP 7.75Km)(DN 8.00Km)
NEW BARRACKPUR(UP 10.75Km)(DN 11.00Km)
MADHYAMGRAM(UP 13.35Km)(DN 13.60Km)
HRIDAYPUR(UP 15.80Km)(DN 16.05Km)
BARASAT(UP 17.88Km)(DN 18.13Km)
Under operation -22.3 Km Dumdum-Kavi Nazrul
New Metro Rail Projects by RVNL
Joka-BBD Bag, 16.75 km
Noapara- Baranagar- Dakshineswar-Barackpur -14.50 km
Dumdum- Barasat via Airport -18.13 km by Metro Railway Kolkata
Recently commissioned-2.90 Km Kavi Nazrul – Kavi Subhash
Dumdum-Noapara by Metro Railway Kolkata
Howrah Maidan
Salt lake Sec-v
E-W CORRIDOR Under Construction by KMRCL
NEW TOWN
New Garia- Dumdum- via New Town 32.00 km
BARANAGAR
AIRPORT
BARANAGAR
NEW GARIA
NEW TOWN
AIRPORT
NEW GARIA
METRO RAIL IN KOLKATA
(1) Route alignment: Noapara(Ex.) to Baranagar (2.627Km) &
Baranagar to Dakshineswar (2Km).
Baranagar to Barrackpore (12.5 Km) Metro Corridor.
Joka to BBD Bag Via Majerhat (16.72Km) Metro Corridor.
DumDum Airport to New Garia (32Km) Metro Corridor.
Salient Feature of Joka-BBD Bagh Metro Corridor
• Total Length (Jaka -BBD Bag) - 16.75Km.
• Elevated – (Joka - Mominpur) - 9.0 Km.
• Underground – (Mominpur-BBD Bag) - 7.75Km.
• Total No of Stations – 13 nos
Elevated- 8 nos Underground- 5 nos
Passenger Interface at – Majerhat (Suburban and Circular Railway).Park Street and Esplanade Metro Railway Station.
Depot is to be setup Near Bakarahat Road adjacent to Chorialkhal.
Raw proposal at the stage of Sanction
RITES engaged as Consultant for DPR etc.
DDC contract engaged, IIT Delhi made proof consultant
Clearance taken from State Govt. (Police, PWD, KMC, Environment etc.)
Contract for Viaduct for Joka – Mominpur awarded in Dec’2010 and Stations in April 2012
Decision on removal of tramlines in May’ 2011.
Foundation Stone was laid by her Excellency, President of India, on
22.09.2010.
Work for Viaduct awarded to M/s Simplex infrastructures on
28.12.10 and stations in April 2012
CES is DDC for viaduct and Stations and IIT Delhi is the proof
consultant.
Construction of piles, pile caps, piers and Girder is in progress
between Joka & Majerhat (1185 nos. piles completed, 276 nos. pile
cap completed, 273 nos. pier completed and 233 nos. Girder
erected).
JOKA-BBD BAGH METRO ALIGNMENT
Details of the existing Diamond Harbour RoadDetails of the existing Diamond Harbour Road
DETAILS OF D. H. ROAD AT STATIONS FOR JOKA-MOMINPUR SECTION (Facing BBD Bag)
Chainage Location ROW LHS C.W. RHS C.W. Median Width Planned Width
JOKA 0
Start 38.18 6.61 6.94 7.88
2X7.5Center 38.88 6.24 6.45 9.92
End 36.69 5.41 6.74 11.90
MAJERHAT 7607 Center 15.45 40.06 Off the Road Flyover
MOMINPUR 8625
Start 25.99 13.32 5.83 1.06
2X7.5Center 26.33 12.53 5.89 1.07
End 25.87 13.36 8.56 1.06
Station Planning Joka Majerhat Corridor
Name of StationChainage
(in km)
Distance from previous
Station (in m)
Rail level (RL in m)
Height/ Depth from
Adjacent Ground
Platform Types and Nos
Alignment Description
1. Joka 00 -- 16.249 12.5 Side Platform - 2 Elevated, straight
1. Thakurpukar 1.455 1455 17.854 12.5 Side Platform - 2 Elevated, straight
1. Sakher Bazar 2.675 1220 17.896 12.5 Side Platform - 2 Elevated, straight
1. Behala Chowrasta
4.128 1453 18.961 12.5 Side Platform - 2 Elevated, straight
1. Behala Bazar 5.465 1337 19.916 12.5 Side Platform - 2 Elevated, straight
1. Taratala 6.450 0985 17.793 12.5 Side Platform - 2 Elevated, straight
1. Majerhat 7.607 1157 18.199 12.5 Side Platform - 2 Elevated, straight
1. Mominpur 8.625 1018 17.730 12.5 Side Platform - 2 Elevated, straight
Typical Station Layout
7500 7500
¢2
5500
MIN
3000
MIN
94015
0
50
1090
3000
1520 2100
D=STAIRCASE/ ESCALATOR
d=WORKING SPACE / FOOTPATH
OPTION-2 7.5m CW
BU
ILT U
P EDG
E
2500Dd
BU
ILT U
P EDG
E
2500 D d
23000
Joka MID Section
Thakkurrpukur
MID Section
ShakherBazar
MID Section
Behala Chowrasta
MID Section
Behala Bazar
MID Section
TaratalaMID Section
Majerhat MID Section
Mominpur
Chainage 0.00 0.65 1.46 1.81 2.68 2.99 4.13 4.45 5.46 6.1 6.45 6.72 7.607 8.13 8.625PF Length 180m 180m 180m 180m 180m 180m 180m 180m
High point
Low Point High point
Low Point High point
Low Point High point
Low Point
High point
Low Point
High point
Low Point High point
Low Point
High point
Rail Level 16.5 14.824 18.4 15.352 17.8 16.172 19.1 16.419 19.8 15.183 17.8 14.98 18.199 14.9 17.73
Ground Level 3.317 3.35 4.791 4.445 4.189 4.968 5.682 6.129 6.074 6.184 4.588 4.69 6.692 4.63 5.515
Gradient 388 227 115 355 190 389 119 299 139 134 96 276 159 175
Energy saving due to gradient
Lithological log indicates the presence of a clay bed at the top of the geological succession with thickness varying from 10-40 mts. There is a further alternate clay and sand bed. A group of granular aquifer is found between 250-650 mts. below ground level.
Geotechnical Details
Zone NumberApproximate Chainage
(km)
Location
Zone-I 0.000 to +1455 Joka Station to Thakurpukur Station
Zone-II +1455 to +2675 Thakurpukur Station to Sakher Bazar Station
Zone-III +2675 to +4128 Sakher Bazar Station to Behala Chowrasta Station
Zone-IV +4128 to +5465 Behala Chowrasta Station to Behala Bazar Station
Zone-V A +5465 to +6260
Behala Bazar Station to Taratala StationZone-V B +6260 to +6600
Zone-V C +6600 to +6900
Zone-VI +6900 to +7744 Taratala Station to Mazerhat Station
Zone-VII +7744 to +8755 Mazerhat Station to Mominpur Station
Zone-VIII 0.000 to -1250 Joka Station to Depot
TYPICAL SUBSOIL PROFILE IN JOKA-MAJERHAT SECTION
PILE CAPACITY1200mm diameter piles are being used in the construction.
For bored pile, load bearing capacity is calculated according to IS:2911 (Part-I/Sec-2)-1979.
A summary of pile capacities along with the shaft length proposed is presented below:
Pile diameter (mm)
Pile cut-off level below
EGL
Horizontal Pile
capacity (t)
Vertical Pile capacity (t)
Pile shaft length (m)
1200 2.3m 21.8t
Maximum = 606 Maximum = 40
Minimum =384 Minimum =25
Average= 484 Average= 31.5
Sequence :Sequence :
Road Widening
Barricading on the Central Verge
Checking of Utility
Removal / sifting of utilities
Execution of Metro Corridor (pile, Pile Cap, Pier)
Setting of Two Casting yards at Pailan
Quality Control Lab at PailanQuality Control Lab at Pailan
Batching Plant + Casting Yard at PailanBatching Plant + Casting Yard at Pailan
Casting of Segments
Auto launching in Progress at Joka Site
Erection of Launching girder
Behala Chowrasta: Launching of Segments
Auto launching in Progress at Joka Site
ROAD DIVERSION FOR THIRD LAUNCHING GIRDER
SKY LINE CHANGING…
Managing Drawing and Details Managing Drawing and Details in in
Joka – Majerhat Metro Site.Joka – Majerhat Metro Site.
Precast Post tensioned segmental single cell box girders of spans varying from 19m to 31m with increments of 3m for standard spans.
50m Cast-in-place post tensioned box girder.
Precast post tensioned I-girder made continuous for 4 spans at cross-over location.
2-span continuous post tensioned precast segmental box girder.
STR
UC
TUR
E TY
PES
STR
UC
TUR
E TY
PES
Elastomeric bearings for transferring normal loads.
Reaction block with/without cable restrainer for seismic loads.
POT-PTFE bearings for long spans.
STR
UC
TUR
E TY
PES
STR
UC
TUR
E TY
PES
Concentric piers of 1.95m circular section with heights varying from 11m to 18m (difference between Rail Top Level to Top of Pilecap).
Inverted L-piers up to 2.0m maximum eccentricity between centre line of track and pier section.
Portal piers at obligatory locations.STR
UC
TUR
E TY
PES
STR
UC
TUR
E TY
PES
1200mm dia bored cast-in-situ reinforced concrete pile.
Pile shaft length varying from 25m to 40m depending upon various types of soil strata.
STR
UC
TUR
E TY
PES
STR
UC
TUR
E TY
PES
10 types for standard simply supported
spans based on span length and radius of
curvature for 320 actual superstructure
configurations. Two extreme radii of
curvature are considered. One is the maximum radius, R → ∞ for straight
alignment and other is the minimum radius
of 202m.
5 types for non-standard spans.
DES
IGN
TYP
ESD
ESIG
N T
YPES
5 types of elastomeric bearings.
3 different sets of POT-PTFE
bearings.
DES
IGN
TYP
ESD
ESIG
N T
YPES
41 design types for concentric piersand common
piers for 275 actual pier configurations based on
height of substructure, span on both side and
curvature of alignment. This results in 15 types of
reinforcement arrangement with reinforcement %
varying from 1.50% to 5.40%.
11 design types for inverted L-piers for 30 actual
pier configurations based eccentricity between
track centerline and pier centerline in addition to
those mentioned above. This results in 3 types of
reinforcement arrangement with reinforcement %
varying from 1.50% to 2.10%.
(Contd…)
DES
IGN
TYP
ESD
ESIG
N T
YPES
2 design types for portal piers for 8 piers, one with
two legs and other with three legs.
DES
IGN
TYP
ESD
ESIG
N T
YPES
4- and 5-pile groups, in general.
M-35
M-35
M-40
M-40
M-50
Block Section wise details
• Joka – Thakurpukur (P/26 to P/72)
• Thakurpukur– Sakherbazar (P/73 to P/110)
• Sabherbazar– Behala Chowrasta (P/111 to P/157)
• Behala Chowrasta– Behala Bazar (P/158 to P/200)
• Behala Bazar—Taratala (P/201 to P/232)
Erection of Girder - Scheme
Erection of Launching girder
PRECAST SEGMENTS
Fabrication of reinforcement cage
PRECAST SEGMENTS
Lifting of reinforcement cage using lifting beam
Placement of reinforcement cage in shutter
PRECAST SEGMENTS
Fixing of HDPE sheathing pipe for HT Strands Fixing of rail for inner trolley
PRECAST SEGMENTS
Placement of inner trolley
PRECAST SEGMENTS
Segment ready for casting
PRECAST SEGMENTS
Segment casting
PRECAST SEGMENTS
De-shuttering
PRECAST SEGMENTS
Application of curing compound and curing with water
PRECAST SEGMENTS
Segment Lifting
SEG-1 Pedestal
Bearing
Tendon
SEG-2 SEG-3
1
2
3
4/5
LAUNCHING GIRDER BEING AUTO LAUNCHED
FIRST LAUNCHING GIRDER
SECOND LAUNCHING GIRDER
Launching Girder- I & II
Third Launching Girder
Launching Girder- III & IV
Fourth Launching Girder
Auto launching in Progress at Joka Site
Casting of Parapet
Erection of Parapet
Majerhat Station
GENERAL SUB-SOIL CHARACTERISTICS OF KOLKATA
Normal Calcutta DepositThe Upper zone covering the softer components of normally consolidated subsoil, which in this region extends approximately about 15 metres below ground level.
The second horizon comprises the stiffer or denser components occurring just beneath the first horizon and extends down to about 50 metres or more below the ground level.
River Channel Deposits Superimposed features over the typical subsoil deposits of this region and basically consist of silty sand to sandy silt of considerable thickness. At a few locations the upper portion of this deposit has exhibited clayey silt to silty clay, most probably, in lenticular form. The sand deposit has been generally found to be fine to medium coarse.
Lifting of Segments/Erection of girders started in March 2012 within 2 years of sanction.
JOKA MAINTENANCE DEPOT :JOKA MAINTENANCE DEPOT :
Joka Depot Layout PlanJoka Depot Layout Plan
Problem AreasProblem Areas
PROBLEM AREAS : Cross Road at Taratala
PROBLEM AREAS : Land of C-Comens / KOPT
Mint Boundary Wall
PROBLEM AREAS : Land of MINT / KOPT
Mint Post Office
PROBLEM AREAS : Land of MINT / KoPT
PROBLEM AREAS : Rehabilitation India plus Hutments / KOPT
Encroachments for Station