construction of bridges

Upload: v-venkata-narayana

Post on 04-Jun-2018

220 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/13/2019 Construction of Bridges

    1/104

  • 8/13/2019 Construction of Bridges

    2/104

  • 8/13/2019 Construction of Bridges

    3/104

    A CULVERTis defined as a structure having a total length of 6.0 M or

    less between the inner faces of Dirt walls(Backing wall)

    A CAUSEWAYis a structure constructed across a stream which allows the

    normal flow of water through its vents and allows the Flood

    waters at MFL CONDITION above it. Normally Causeways aredesigned to take 30% of Flood water through vents and

    balance to overflow during MFL Condition

    A MINOR BRIDGEis a structure having a total length of 60.0m or less

    between the inner faces of Dirt walls (BACKING WALLS) i.e.

    more than 6.0M and less than 60.0M

    DEFINITIONS

  • 8/13/2019 Construction of Bridges

    4/104

    A Major Bridge

    is a structure having a total length of more than 60.0

    M Between the inner faces of Dirt walls (Backing

    walls)

    ROB Means a Road Over Bridge

    constructed across a Railway line over the Rails. This

    means the road traffic passes over the Railway line.

    RUB Means a Road Under BridgeConstructed across

    a Railway line under the Rails. This means the road

    traffic passes under the Railway line. This is lesscostlier, but causes stagnation of water in rainy

    season and may cause submersion during y rains.

  • 8/13/2019 Construction of Bridges

    5/104

  • 8/13/2019 Construction of Bridges

    6/104

  • 8/13/2019 Construction of Bridges

    7/104

    WATERThe properties of Water plays very important roll in

    achieving the required strength of concrete

    (1) The PH of Water should be more than 6

    (2) The Sulphate content should be less than

    400mg/Litre.

    (3) The Chloride content should be less than

    500mg/Litre for R.C.C and less than 2000 mg/Litre

    for P.C.C

  • 8/13/2019 Construction of Bridges

    8/104

    Curing of water is very important and must be

    continued for 28 days irrespective of grade of

    cement.

    Water used for mixing and curing should be of same

    source and of good quality. It is a wrong notion that

    Water used for Curing need not be of good quality

    In case of Structures near Sea coast Potable water may

    not be available. In such cases Extra water lead may be

    included in Estimate and insisted during Execution.

    Adequate number of COVER BLOCKS with Binding wire

    fixed may be casted and cured well in advance not less

    than 15 days and CURED under water before laying

    concrete and placed under Reinforcement.

  • 8/13/2019 Construction of Bridges

    9/104

  • 8/13/2019 Construction of Bridges

    10/104

  • 8/13/2019 Construction of Bridges

    11/104

  • 8/13/2019 Construction of Bridges

    12/104

    PIPE CULVERTS

    (1) The Depth of Foundation for Pipe culvert should

    be 0.90M Below sill level as per IRC SP-13, WITH Bed

    protection. It may be increased to 1.20M Below silllevel WITHOUT Bed protection.

    (2) The Sill level may be fixed at 0.15M Below

    existing Bed Level.

    (3) The Width of Body wall at bottom may be fixed

    as (0.40H+0.30) where H IS HEIGHT OF WALL in

    Meters

    (4) In case of multiple row Pipe Culvert the distance

    between the pipes should be not less than the

    Outer diameter of pipe subject to a minimum of

    450mm.

  • 8/13/2019 Construction of Bridges

    13/104

  • 8/13/2019 Construction of Bridges

    14/104

    SLAB CULVERTS

    (1) Slab Culverts are effective in discharging flood

    waters compared to Pipe culverts even though the

    construction takes little more time. The Pipe Culvertsare likely to get choked due to Debris, Jungle etc in

    vents during floods.

    (2) IRC SP-13 gives the sections of Abutments, Wing

    walls for different heights, sections of Deck slab and

    Reinforcement for Spans ranging from 1.0M to 6.0M

    (3) The Sections in IRC SP-13 are applicable for soilswith a S.B.C. of not less than 16.50 T/M2. For lower

    S.B.C. Values of foundation soils Raft foundation

    may be adopted.

  • 8/13/2019 Construction of Bridges

    15/104

  • 8/13/2019 Construction of Bridges

    16/104

  • 8/13/2019 Construction of Bridges

    17/104

  • 8/13/2019 Construction of Bridges

    18/104

  • 8/13/2019 Construction of Bridges

    19/104

  • 8/13/2019 Construction of Bridges

    20/104

  • 8/13/2019 Construction of Bridges

    21/104

  • 8/13/2019 Construction of Bridges

    22/104

    CAUSEWAY WITH GUIDE POSTS

  • 8/13/2019 Construction of Bridges

    23/104

  • 8/13/2019 Construction of Bridges

    24/104

  • 8/13/2019 Construction of Bridges

    25/104

  • 8/13/2019 Construction of Bridges

    26/104

    FOUNDATIONS

    SHALLOW FOUNDATION(< 4M) DEEP FOUNDATIONS(>4M)

    RAFT INDIVIDUAL

    FOOTINGS

    WELL

    FOUNDATION

    PILE

    FOUNDATION

  • 8/13/2019 Construction of Bridges

    27/104

    (1) Raft Foundation is adopted when the S.B.C. of

    Foundation soil is less than or equal to 10T/M2 like

    Black cotton soils, marshy soils with small spanarrangement.

    (2) Individual Footings are adopted when the S.B.C of

    the Foundation soil is more than 16.50T/M2.

    (3) This type of foundations are suitable when HARD

    soils are met at shallow depths and in case of ROB/

    RUB where there will not be any scour likely to

    occur as there will not be any flow.

    (4) Suitably designed Aprons are to be provided

    both on Upstream side and on Downstream side to

    Protect the Bridge structure.

    OPEN FOUNDATIONS

  • 8/13/2019 Construction of Bridges

    28/104

    EARTH WORK FOR OPEN FOUNDATION IN SANDY SOIL

  • 8/13/2019 Construction of Bridges

    29/104

    EARTH WORK FOR OPEN FOUNDATION IN SANDY SOIL

  • 8/13/2019 Construction of Bridges

    30/104

    Earth work excavation for open foundations in sandy soils. As it is difficult to excavateindividual foundation trenches, the excavation was done continuously like a canal. Asit is in the heart of town limits shoring and shuttering adopted to avoid sliding of sandand damage to adjoining railway quarters as they demanded total cost of structureson the plea that there quarts will be collapsed.

    OPEN FOUNDATION FOR INDIVIDUAL FOOTING IN SANDY SOIL

  • 8/13/2019 Construction of Bridges

    31/104

    LAYING OF CEMENT CONCRETE BED 100 MM THICK UNDER PIER

    FOOTING

  • 8/13/2019 Construction of Bridges

    32/104

    Reinforcement completed for pier footings. A beam connecting the three circularpiers can be seen above the footing reinforcement. The center to center distanceof piers should be verified carefully and main reinforcement of pier should beplaced at exact location before laying concrete for pier footing.

  • 8/13/2019 Construction of Bridges

    33/104

    A trapezoidal

    section was

    adopted for pier

    footing.

    Hence the topreinforcement

    was to be bent

    accordingly to

    suit the concrete

    section with a

    cover of 50 mm

  • 8/13/2019 Construction of Bridges

    34/104

    Laying of plain concrete for Abutment foundations in V.C.C. M15 using 40 mmgraded metal. Each layer should not exceed 200 mm for proper vibration of eachlayer. Shear keys in the form of holes may be provided by keeping concrete blocksin each layer of concrete and removing the same after one hour to leave holes andto act as key.

  • 8/13/2019 Construction of Bridges

    35/104

    Concrete completed for pier footing. A trapezium section with a beam connecting 3circular piers of 1.0 m dia. can be seen. The shutters should be thoroughly checked formaintaining three piers in one line and at exact distance to avoid variation in span.

  • 8/13/2019 Construction of Bridges

    36/104

    Circular piers of 1.0 m dia. completed by laying concrete in each stage of

    2.50 m inside face of sloped face of Abutment can be seen with weep holes.

  • 8/13/2019 Construction of Bridges

    37/104

  • 8/13/2019 Construction of Bridges

    38/104

  • 8/13/2019 Construction of Bridges

    39/104

  • 8/13/2019 Construction of Bridges

    40/104

  • 8/13/2019 Construction of Bridges

    41/104

    PHOTO SHOWING WELL CUTTING EDGE AND WELL CURB

  • 8/13/2019 Construction of Bridges

    42/104

  • 8/13/2019 Construction of Bridges

    43/104

  • 8/13/2019 Construction of Bridges

    44/104

  • 8/13/2019 Construction of Bridges

    45/104

  • 8/13/2019 Construction of Bridges

    46/104

  • 8/13/2019 Construction of Bridges

    47/104

  • 8/13/2019 Construction of Bridges

    48/104

    PHOTO SHOWING TREMIE PIPEFOR BOTTOM PLUGGING OF

    WELL.

  • 8/13/2019 Construction of Bridges

    49/104

  • 8/13/2019 Construction of Bridges

    50/104

  • 8/13/2019 Construction of Bridges

    51/104

  • 8/13/2019 Construction of Bridges

    52/104

  • 8/13/2019 Construction of Bridges

    53/104

  • 8/13/2019 Construction of Bridges

    54/104

  • 8/13/2019 Construction of Bridges

    55/104

  • 8/13/2019 Construction of Bridges

    56/104

  • 8/13/2019 Construction of Bridges

    57/104

  • 8/13/2019 Construction of Bridges

    58/104

    WEEP HOLES IN ABUTMENT

  • 8/13/2019 Construction of Bridges

    59/104

    Filter media using 50% of 150 mm HBG stone and 50% of 40 mm HBG metal were placed behindRetaining walls to allow seepage water to drain off easily in to weep holes. As the formation is to befilled with sandy soils, 0.60 m thick Gravel Backing adjoining the filter media is provided to avoidscooping out of sand with seepage water from pavement, other wise Gravel Backing adjoining filtermedia is not necessary

    REINFORCEMENT OF R C C DECK SLAB FOR 10 0 M SPAN

  • 8/13/2019 Construction of Bridges

    60/104

    REINFORCEMENT OF R.C.C. DECK SLAB FOR 10.0 M SPAN

  • 8/13/2019 Construction of Bridges

    61/104

  • 8/13/2019 Construction of Bridges

    62/104

  • 8/13/2019 Construction of Bridges

    63/104

  • 8/13/2019 Construction of Bridges

    64/104

  • 8/13/2019 Construction of Bridges

    65/104

  • 8/13/2019 Construction of Bridges

    66/104

  • 8/13/2019 Construction of Bridges

    67/104

  • 8/13/2019 Construction of Bridges

    68/104

  • 8/13/2019 Construction of Bridges

    69/104

  • 8/13/2019 Construction of Bridges

    70/104

    ELASTOMER UNITS 40MM THICK 0.75M OR 1.0M LENGTH

  • 8/13/2019 Construction of Bridges

    71/104

    SLAB SEAL TYPE

  • 8/13/2019 Construction of Bridges

    72/104

  • 8/13/2019 Construction of Bridges

    73/104

    STRIP SEAL EXPANSION JOINT FOR LARGER MOVEMENTS

    ELASTOMER SEAL

    I .S ANGLES

    ANCHOR

    RODS

    ANCHOR RODS

  • 8/13/2019 Construction of Bridges

    74/104

    CLOSER VIEW OF STRIP SEAL WITH ELASTOMERS

    CLOSER VIEW OF STRIP SEAL JOINT AT APPROACH SLAB

  • 8/13/2019 Construction of Bridges

    75/104

  • 8/13/2019 Construction of Bridges

    76/104

    Fixing of strip seal joint with main reinforcement of

    superstructure in the recess of concrete

    Close view of fixing of strip seal joint with main reinforcement

    of super structure

  • 8/13/2019 Construction of Bridges

    77/104

    of super structure

  • 8/13/2019 Construction of Bridges

    78/104

    Camber should be provided in joints itself at RCL and should

    extend in to kerb portion also duly welded to main reinforcement

  • 8/13/2019 Construction of Bridges

    79/104

    The top level of strip seal joint shall be kept equal to top level of

    wearing coat and care must be taken that no jerk is observed at

    joints.

  • 8/13/2019 Construction of Bridges

    80/104

    ELASTOMER STRIPS IN ROLLS AND FIXING IN JOINT

  • 8/13/2019 Construction of Bridges

    81/104

    CLOSER VIEW OF FIXING ELASTOMER IN ANGLE ATACHMENT

  • 8/13/2019 Construction of Bridges

    82/104

    T- BEAM GIRDERS SEEN FROM BOTTOM

  • 8/13/2019 Construction of Bridges

    83/104

    BRIDGE COMPLETED

  • 8/13/2019 Construction of Bridges

    84/104

    PIER

    WELL AFTER SCOUR

    DECK SLAB COLAPSED

  • 8/13/2019 Construction of Bridges

    85/104

    WELL AFTERSCOUR

    DECK SLABS COLLAPSED

    PIER

  • 8/13/2019 Construction of Bridges

    86/104

    REINFORCEMENT CORRODED DUE TO INADEQUATE COVER

  • 8/13/2019 Construction of Bridges

    87/104

    DECK SLAB REINFORCEMENT CORRODED AND EXPOSED

  • 8/13/2019 Construction of Bridges

    88/104

    MINOR BRIDGE COLAPSED DUE TO CORROSION OF STEEL

    LOAD TEST FOR BRIDGE 70R LOADING

  • 8/13/2019 Construction of Bridges

    89/104

    The load is to be accommodated in the span which gives maximum bending

    moment. For 10m clear span the critical load works out to 68.0 MT (4x17.0

    MT). For other spans this will be different. This critical load is to be increased

    by 25% as per is 456-2000

    LOADING FOR CLASS 70R LOAD AS PER APPENDIX I OF IRC 6-2000

    TRACKED VEHICLE :70.0M.T WHEELED VEHICLE :100.0 M.T

    LOAD TEST FOR BRIDGE 70R LOADING

    CONTACT AREA :610X410 MMTOTAL LENGTH OF VEHICLE

    :14.31OM

    THE LOADING SHALL BE DONE AT 30%,50%,70%, 80%,90%,100%

  • 8/13/2019 Construction of Bridges

    90/104

    THE LOADINGSHALL BE DONE AT 30%,50%,70%, 80%,90%,100%0F TOTAL LOAD.

    THE MAXIMUM DEFLECTION PERMISSIBLE IS 40L2

    /D (WHERE LIS THE EFFECTIVE SPAN),AS PER CLAUSE 17.6.3.1 OF IS 456-2000 WHICH WORKS OUT TO 5.33mm FOR 10.76M C/C SPAN.

    THE STRUCTURE SHOULD HAVE A RECOVERY OF NOT LESS

    THAN 75% OF MAXIMUM DEFLECTION DUE TO SUPERIMPOSEDLOAD ON REMOVAL, AS PER CLAUSE 17.6.3 OF IS 456-2000.

    THE SUPERIMPOSED LOAD SHALL BE KEPT FOR 24 HOURS ANDDEFLECTIONS RECORDED

  • 8/13/2019 Construction of Bridges

    91/104

    LOAD TEST ON R.O.B. MARKAPUR WITH STEEL PLATES OF610X410X25 MM EACH TAKING A LOAD OF 10.625 M.T

  • 8/13/2019 Construction of Bridges

    92/104

    LOADING WITH SAND BAGS EACHWEIGHING 35 KG

  • 8/13/2019 Construction of Bridges

    93/104

    LOAD TEST WITH PLATES 610X410MM FOR 70R LOADING

  • 8/13/2019 Construction of Bridges

    94/104

    CLOSE UP VIEW OF LOADED PLATES 610X410 MM, ISBEAMS, PLOTFORM

  • 8/13/2019 Construction of Bridges

    95/104

    CLOSE UP VIEW OF LOADED PLOTFORM, CHANNELS,IS ANGLES,PLATES

  • 8/13/2019 Construction of Bridges

    96/104

    SIDE VIEW OF PLOTFORM WITH SAND BAGS EACHWEIGHING 35 KG

  • 8/13/2019 Construction of Bridges

    97/104

    LOADED PLOTFORMS 2 NO. EACH WITH 4 SETS OF PLATES.LOAD ON EACH SET OF PLATES IS 10.625 M.T

  • 8/13/2019 Construction of Bridges

    98/104

    LOADED PLATFORMS 2 NO, EACH WITH 4 SETS OF PLATES.

    LOAD ON EACH PLATE IS 10.625 M.T .

    TOTAL LOAD IS 8X10.625 = 85.0 M.T

  • 8/13/2019 Construction of Bridges

    99/104

    LOADING PLOTFORMS EACH CARRYING 42.5 M.TTOTALLING TO 85.0 M.T FOR 10 M CLEAR SPAN`

  • 8/13/2019 Construction of Bridges

    100/104

    DIAL GUAGES UNDER SLAB FOR MEASURING DEFLECTIONS3 NO. ALONG SPAN+ 2 NO. TRANSVERSE DIRECTION

  • 8/13/2019 Construction of Bridges

    101/104

    CLOSE UP VIEW OF DIAL GUAGES FOR MEASURINGDEFLECTIONS, PLOTFORMS

    RESULTS OF LOAD TEST

  • 8/13/2019 Construction of Bridges

    102/104

    DEFLECTOMETERIDENTIFICATIONMEMBERLOCATION

    DEFLECTION AFTER24 HOURSLOADING(MM)

    DEFLECTIO

    N DUE TOTEMPERATUREDURINGLOADPERIOD(7 AM TO

    6PM)IN MM

    CORRECTEDDEFLECTION

    (MM)

    LIMITINGDEFLECTION

    (MM)

    MAX

    VALUEASPERANALYSIS

    (MM)

    %RECOVER

    YAFTER 24HOURSOFLOADING

    D1R/S

    END1.17

    0.92

    UPWARD2.09

    5.33

    mm

    6.9

    085.6%

    D2

    CENTR

    E OF

    DECK

    0.841.15

    UPWARD1.99 -do- -do 89.4%

    D3L/S

    END0.46

    0.77

    UPWARD1.23 -do- -do- 86.2%

    D4 SPAN 0.940.77UPW

    ARD1.71 -do- -do- 87.1%

    D5 SPAN 0.73 0.73UPWARD

    1.46 -do- -do- 80.1%

    LEAST COUNT =0.01mm MAX TRAVEL = 50mmDEFLECTIONS DUE TO LOADING

    CONCLUDING REMARKS

  • 8/13/2019 Construction of Bridges

    103/104

    1) From the results of load test ,the maximum deflectionrecorded is 2.09 mm ,against the limiting deflection of5.33mm,as per clause 17.6.3 of IS 456-2000.

    2) The deflection recovery of the Deck slab was found to bemore than Stipulated minimum of recovery of 75 afterremoval of test load.3) Hence it can be concluded that the deflection behavior ofthe Deck slab of the bridge is within the permissible limits.

  • 8/13/2019 Construction of Bridges

    104/104

    THANK YOU

    For further clarification and comments

    Sri P.SURESHDEPUTY EXECUTIVE ENGINEER(R&B) SUB DIVISION, UDAYAGIRI

    9440818349